HomeMy WebLinkAbout0403_AnsonLF_0NewCellActivation_20240528New Cell Activation Form ----Leachate Column and Stormwater Separation
Phase, Cell, and Sub -cell:
A - Leachate collection trench/column:
The geotextile on the top of the leachate column has been removed or folded back,
along the length of the subcell column, to allow direct contact of waste with the
gravel/coarse aggregate.
Check if completed
B - Leachate pipe connection between sub -cells:
The leachate pipe connection flow between the two sub -cells has been connected
or opened.
Check if completed
The geomembrane liner weld around the leachate pipe has been removed or
altered to open flow around the pipe
Check if completed
C - Geomembrane flap along the width of the cell:
Describe the removal and flattening of the geomembrane flap along the entire
width of the cell, to allow sheet flow between the sub -cells.
0 Check if completed
Description and comments:
Name (printed):
Signature:
Date:
example
example
This form is to be added to the onsite operating record, and a copy emailed to the DEQ Solid Waste Section
permitting engineer and the senior environmental specialist.
r