HomeMy WebLinkAboutPRLF571_20230823_RA-13a; 18a-c; & 19a-d_RA Phase Work Plan 2701 Westport Road Charlotte, NC 28208 P (704) 509-1777 F (704) 509-1888 Terracon.com August 23, 2023 Sean Gallagher NCDEQ – Division of Waste Management Special Remediation Branch – Pre-Regulatory Landfill Unit 1646 Mail Service Center Raleigh, NC 27699-1646 Subject: Remedial Action Phase - Task Order 571RA-13a, 18a-c, and 19a-d Albemarle Dump Nanny Drive Albemarle, Stanly County ID # NONCD0000571 State Contract # N42621-A Terracon Proposal # P71237296 Dear Mr. Gallagher: Terracon Consultants, Inc. (Terracon), is pleased to submit this work plan and cost estimate for the remedial action phase activities for the above referenced site. As requested by the North Carolina Department of Environmental Quality (NCDEQ), Division of Waste Management (DWM) Special Remediation Branch Pre-Regulatory Landfill (PRLF) Unit project manager (Unit PM), the following sections describe the proposed scope of work in accordance with your requests for proposals (RFP) dated July 13, 2023. Based on the RFP, Terracon is submitting this work plan and cost estimate for the following Task Orders: ◼ Task Order 571RA-13a: Work Plan and Cost Estimate, ◼ Task Order 571RA-18a: Bid Package Preparation (Area C), ◼ Task Order 571RA-18b: Bid Solicitation and Selection (Area C), ◼ Task Order 571RA-18c: Pre-Construction Preparation (Area C), ◼ Task Order 571WS-19a: Point-of-Entry (POE) System Maintenance, ◼ Task Order 571WS-19b: POE and Potable Well Sampling, ◼ Task Order 571WS-19c: POE and Well Sampling Report, and ◼ Task Order 571WS-19d: POE and Well Data Review and Compilation. The cost estimates to complete these task orders are summarized on the attached costing tables. 2 Task Order 571RA-13a: (Work Plan and Cost Estimate) This task order includes time for preparing the requested work plan and cost estimate, preparing and soliciting bids from subcontractors, project management, communication and coordination with the property owner, and communication with the Unit PM prior to conducting the field work. Task Order 571RA-18a: Bid Package Preparation (Area C) Terracon will finalize drawings and prepare bid specifications setting forth the RAP in greater detail and prescribing work to be done, including materials; workmanship; special equipment; site work; landscaping; bidding information; subcontractor’s proposal requirements; contract and bond forms; general and supplementary general conditions for the contract; and other information required for receiving construction bids for implementation of the remedy. Task Order 571RA-18b: Bid Solicitation and Selection (Area C) This task will be split into three subtasks. The scope of the subtasks are described below. Subtask A) Subcontractor Bid Solicitation Once completed and approved by NCDEQ, bid documents will be issued by Terracon to at least three potential subcontractors. Bids will be solicited through the Stanly News & Press, a newspaper with general circulation in the project region, and by electronic means appearing at least five full days that includes one day of largest readership. Subtask B) Pre-Bid Subcontractor Meetings Terracon will schedule and conduct one pre-bid meeting at the site with prospective bidders to review the remedial action plan and clarify any questions or comments. Subtask C) Finalize Bid Package, Bid Opening, and Compile Bid Data Terracon will develop a matrix of received bids for comparison followed by meeting with the Unit PM for their review and selection of a subcontractor. Terracon understands that a performance bond between Terracon and the subcontractor is required for work over $300,000. Task Order 571RA-18c: Pre-Construction Preparation (Area C) Upon final subcontractor selection, Terracon will schedule and conduct one pre-construction meeting at the site with subcontractor to review the remedial action plan and clarify any questions or comments in greater detail than discussed during the pre-bid meeting. The pre- construction meeting will cover logistical execution and financial management of the project in addition to Terracon safety policies and the critical junctures for the RAP implementation. Task Order 571WS-19a: POE System Maintenance & Sampling This task will be split into three subtasks. The scope of the subtasks are described below. 3 Subtask A) Pre-Maintenance POE Sampling Terracon will conduct sampling of the five POE systems prior to the conducting of annual POE maintenance by a subcontractor (Subtask B). Sampling will be completed in accordance with the potable well sampling procedure as described in the April 2023 Guidelines. Samples will be collected from the influent, mid-point, and effluent of the following POE systems: Well ID POE # Address Well 01 POE-32311 32311 Nanny Drive Well 03 POE-32322 32322 Nanny Drive Well 12 POE-JYFBYC 29387 Pennington Road Well 13 POE-Hicks 31796 Old Herlocker Road Well 28 POE-Clayton 34512 Tiffany Lane The POE systems will be purged at a rate of approximately 1 to 2 gallons per minute for at least 15 minutes. When possible, samples will not be collected through hoses and/or filters. The water will be purged into a bucket, or through a hose, and spread in an area away from on-site structures. Samples will be collected directly from the spigot into laboratory-supplied containers. Field staff will document the number of minutes the well was purged, the total volume purged and any site-specific conditions that might impact the well. POE samples will be submitted for laboratory analysis of: ◼ Volatile-organic compounds (VOCs) by EPA Method 8260, QA/QC sampling will consist of a laboratory provided trip blank. In accordance with the Guidelines, a duplicate will not be collected as the event is neither a “multi-point soil nor monitoring well sampling event” Subtask B) POE System Maintenance and Oversight Terracon will oversee the annual maintenance of the five forementioned POE filter systems by Culligan of Charlotte (Culligan). Terracon proposes to continue using Culligan in lue of getting quotes from multiple subcontractors to utilize their site and system knowledge in an effort to maintain consistency and system optimization. This task includes costs for Culligan to provide maintenance services for the POE systems. Culligan will provide labor, equipment, and materials to install and maintain the POE systems in an attempt to provide contaminant removal efficiency to less than the current maximum contaminant level specified in applicable regulations. This proposal includes subcontract costs for one maintenance event at each of the five systems that will include: ◼ Replace and/or reposition GAC vessels. ◼ Ultraviolet light bulb and filter replacements. ◼ Provide additional filters for subsequent homeowner installation. ◼ Transportation and disposal of waste activated carbon. ◼ Mobilization and demobilization labor and mileage. 4 Previously identified maintenance needs that will also be included in the plan of action for Fall 2023 were provided by AECOM (previous POE consultant) and are summarized below: ◼ Well 1, Well 13, and Well 28 POE structures/housing need replacement or repair. o Well 1 sediment filter located under the house, difficult to reach. o Well 13 building damaged and piping inside is weathered. o Well 28 floor has water damage below the system, stability compromised. ◼ Well 1 and Well 3 have outdated PVC piping that will need to be replaced. Some of this was replaced with PEX plumbing in 2022 ◼ Well 3 has an iron softener and chlorinator that have not been serviced and will be reviewed to determine if we need to replace or remove. Totalizer readings and details of the system maintenance conducted for each system will be documented and provided in a letter report (Task Order 571WS-19c) in conjunction with the sampling results. Subtask C) Post-Maintenance POE Sampling Terracon will conduct sampling of the five POE systems following to the completion of annual POE maintenance by a subcontractor (Subtask B). Sampling will be completed in accordance with the potable well sampling procedure as described in the April 2023 Guidelines. Samples will be collected from the influent, mid-point, and effluent. The POE systems will be purged at a rate of approximately 1 to 2 gallons per minute for at least 15 minutes. When possible, samples will not be collected through hoses and/or filters. The water will be purged into a bucket, or through a hose, and spread in an area away from on-site structures. Samples will be collected directly from the spigot into laboratory-supplied containers. Field staff will document the number of minutes the well was purged, the total volume purged and any site-specific conditions that might impact the well. POE samples will be submitted for laboratory analysis of: ◼ Volatile-organic compounds (VOCs) by EPA Method 8260, QA/QC sampling will consist of a laboratory provided trip blank. In accordance with the Guidelines, a duplicate will not be collected as the event is neither a “multi-point soil nor monitoring well sampling event” Task Order 571WS-19b: Potable Well Sampling Terracon will also conduct annual sampling of the 33 water supply wells without POE systems that are within 1000ft of the site. An attempt will be made to gain access to each of the following 33 wells via a sample request form sent by the Unit PM. 5 Well ID Address Well 02 32118 Nanny Drive Well 04 32055 Nanny Drive Well 05 32337 Nanny Drive Well 06 33627 Old Herlocker Road Well 07 33673 Old Herlocker Road Well 08 33734 Old Herlocker Road Well 09 35071 Scott Drive Well 10 35119 Scott Drive or 35139 Scott Drive Well 11 29387 Pennington Road Well 14 31888 Old Herlocker Road Well 15 34508 Lisa Drive Well 16 34529 Tiffany Lane Well 17 29233 Pennington Road Well 18 31923 Old Herlocker Road Well 19 31965 Old Herlocker Road Well 20 32023 Nanny Drive Well 21 32033 Nanny Drive Well 22 32393 Nanny Drive Well 23 34429 Lisa Drive Well 24 34444 Lisa Drive Well 25 34453 Lisa Drive Well 26 34460 Tiffany Lane Well 27 34481 Tiffany Lane Well 29 29125 Pennington Road Well 30 29163 Pennington Road Well 31 34413 Tiffany Lane Well 32 34442 Tiffany Lane TBD-1 34466 Lisa Drive TBD-2 34499 Tiffany Lane TBD-3 34447 Tiffany Lane TBD-4 34477 Lisa Drive TBD-5 29181 Pennington Road TBD-6 29425 Pennington Road The sampling will be completed in accordance with the potable well sampling procedure as described in the April 2023 Guidelines. Each well will be purged at a rate of approximately 1 to 2 gallons per minute for at least 15 minutes. When possible, samples will not be collected through hoses and/or filters. The water will be purged into a bucket, or through a hose, and spread in an area away from on-site structures. Samples will be collected directly from the spigot into laboratory-supplied containers. Field 6 staff will document the number of minutes the well was purged, the total volume purged and any site-specific conditions that might impact the well. Samples will be submitted for laboratory analysis of: ◼ Volatile-organic compounds (VOCs) by EPA Method 8260, QA/QC sampling will consist of a laboratory provided trip blank. In accordance with the Guidelines, a duplicate will not be collected as the event is neither a “multi-point soil nor monitoring well sampling event” Task Order 571WS-19c: POE and Potable Well Sampling Report A letter report will be prepared summarizing sampling activities, POE maintenance activities and analytical results from the POE and Potable Well Task Orders. The letter report will include text, a maintenance summary table, analytical summary tables, figures, and a photo log detailing the procedures and results of the activities completed under Task Orders 571WS-19a & 571WS-19b. The report will be submitted to the Unit PM in draft form via email for review prior to finalization. Task Order 571WS-19d: POE and Well Data Review and Compilation This task order includes time for Terracon to review existing POE and potable well sampling reports for the site and surrounding properties. Terracon will develop a summary table of sample results that includes the prior reports available on Laserfiche and provided by the Unit PM. The summary table will include results collected as part of Task Order 571WS-19a and 571WS-19b. The table will be submitted to the Unit PM for review and future remedial investigative/planning purposes. Scheduling Throughout completion of the above tasks, at least two Terracon employees will be present on-site when a subcontractor is not present. Personnel from Terracon’s Charlotte office will perform the field activities. Mileage costs are based on travel to the site from our Charlotte, North Carolina office. An overall project schedule is presented below. 7 Overall Project Schedule Week# Remedy Preparation Tasks POE and Potable Well Tasks 1 571RA-18a Bid Package Preparation (Area C) 571WS-19d POE and Well Data Review and Compilation 571WS-19a & -19b POE System Maintenance & Sampling and Potable Well Sampling 2 3 4 5 6 7 571WS-19c POE and Potable Well Sampling Report 8 9 571RA-18b Bid Solicitation and Selection (Area C) 10 11 12 13 14 15 571RA-18c Pre-Construction Meetings and Preparation (Area C) 16 17 18 Authorization If this work plan and cost estimate is acceptable, Terracon understands that the Unit PM will issue a task order in accordance with our contract N42621-A dated December 16, 2021. Terracon’s services will be performed in a manner consistent with generally accepted practices of the professional undertaken in similar studies in the same geographic area during the same period. Terracon makes no warranties, expressed or implied, regarding its services, findings, conclusions, or recommendations. Please note that Terracon does not warrant the work of laboratories, regulatory agencies or other third parties supplying information used in the preparation of reports. These services will be performed in accordance with the scope of work agreed with you as set forth in this proposal and our contract. We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you have any questions, please contact Michael Dail at (984) 202-4055. 8 Sincerely, Terracon Consultants, Inc. Kyle F. Church Michael B. Dail, P.G Senior Project Manager Senior Geologist Attachments: Task Order Cost Proposal Task Order 571RA-13a Task Order Cost Proposal Task Order 571RA-18a Task Order Cost Proposal Task Order 571RA-18b Task Order Cost Proposal Task Order 571RA-18c Task Order Cost Proposal Task Order 571WS-19a Task Order Cost Proposal Task Order 571WS-19b Task Order Cost Proposal Task Order 571WS-19c Task Order Cost Proposal Task Order 571WS-19d