February 1, 2024
submitted via electronic mail
Ms. Jaclynne Drummond
Hydrogeologist
Solid Waste Section
Division of Waste Management
North Carolina Department of Environmental Quality
217 West Jones Street
Raleigh, North Carolina 27603
RE: Phytocap Project
Phase 1 Closure Program
C&D Landfill, Inc.
Permit #: 7407-CDLF-2001/2009
Dear Ms. Drummond:
On behalf of C&D Landfill, Inc., ELM Site Solutions (ELMSS) herein submits requested information
for the above -referenced facility. Details contained in this correspondence are based on recent
discussions between the department and facility ownership. This information supports the
Corrective Plan Addendum (ELMSS, September 2023) prepared for Phase 1 closure which was
approved by the Solid Waste Section (SWS) on October 20, 2023.
Phytocap Implementation Schedule
The following schedule for construction of the phytocap is anticipated:
Preparation and Submittal of the Permit to Construct/Operate Application: 2/1/24 - 2/19/24
Soil Cover Placement and Stabilization: 2/5/24 - 2/23/24
Tree Purchase and Shipping: 2/19/24 - 2/23/24
Tree Installation: 2/26/24 - 3/8/24
Deer Deterrent Installation: 2/26/24 — 3/1/24
Phytocap Installation Certification Report: 3/30/24
Performance Monitoring Equipment Procurement and Installation: 2/5/24 — 3/29/24
Irrigation System Installation: 3/11/24 — 3/29/24
Ms. Jaclynne Drummond
Phase 1 Corrective Action
February 1, 2024
Financial Assurance Estimate
A financial assurance estimate will be provided under separate cover by February 29, 2024.
Per -and Polyfluoroalkyl substances (PFAS) Sampling
PFAS sampling occurred on September 12-13 and December 13-15, 2024. Results will be
provided in the December 2023 Semi -Annual Compliance Report with an anticipated delivery date
to the SWS in April 2024.
Please contact us if you have any questions or if additional information is required.
Sincerely,
ELM Site Solutions, Inc.
s
Rusty Norris, PE, PLS, RSM
Senior Engineer