WALL RECYCLING
Wall Recycling, LLC
2310 Garner Road
Raleigh, NC 27610
December 14, 2023
Ms. Sarah Moutos
Environmental Program Specialist
Division of Waste Management — Solid Waste Section
217 West Jones Street
Raleigh, NC 27609
Subject: Updated Operation Plan
LCID Landfill and Treatment and Processing Facility
Wall Recycling, LLC
3000 Gresham Lake Road
Raleigh, NC 27615
Dear Ms. Moutos:
RECEIVED
DEC 14 2023
BY
Lo-w 5G
Gee,
This letter is to address the comments on the August 2022 Operation Plan submitted with the request
for renewal of the Wall Recycling. The facility operation plan was updated based on the comments
received March 2, 2023 and the current operations and site plan.
Wall Recycling requests an update on the status of the renewal process and the approval of the facility
operation plan.
Should you have any questions regarding the Wall — Rowland, please contact Jenny Sheppard of ELM
Site Solutions at 919.637.8154 or email at 'she and a;elmsitesolutions.com or me at 919.582.7777 or
email at dustinrcr wallrec� cling.com.
Sincerely,
Dustin Hill, Chief Operating Officer
Wall Recycling, LLC
c: Dan Jarboe, Wall Recycling, LLC, diarboe�dwallrecN clim,.com
Chris Gustin, Wall Recycling, LLC, c ug stin(2wallrecycling com
Rusty Norris, ELM Site Solution, rnorris;i elmsitesolution.com
Sherri Stanley, DWM, Solid Waste Section, sherri.stanlev(cede nq c.6ov
Tim Davis, DWM, Solid Waste Section, timothµ.davis[r. Aeq.nc.gov
FACILITY OPERATION PLAN
WALL RECYCLING, LLC
LCID Landfill and
Treatment and Processing Facility
3000 Gresham Lake Road, Raleigh, NC 27615
Permit No. 92M-LCID
Wall Recycling, LLC
LCID Landfill and Treatment and Processing (T&P) Facility
Operations Plan
Table of Contents
Page
1.0 GENERAL FACILITY OPERATIONS....................................................................................1
1.1
Contact Information........................................................................................................................1
1.2
Facility Operating Hours................................................................................................................. 2
1.3
Site Access...................................................................................................................................... 2
1.3.1 Physical Restraints............................................................................................................ 2
1.3.2 Security............................................................................................................................. 3
1.4
Signage............................................................................................................................................3
1.5
Communications..............................................................................................................................3
1.6
Fire Control..................................................................................................................................... 3
1.6.1 Open Burning.................................................................................................................... 3
1.6.2 Equipment.........................................................................................................................4
1.6.3 General Fire Management Strategies................................................................................ 4
1.6.4 Surface Emissions.............................................................................................................4
1.6.5 Fires Within Disposal Areas ............................................................................................. 5
1.6.6 Notification....................................................................................................................... 5
1.7
Severe Weather Conditions............................................................................................................. 6
1.7.1 Ice Storms......................................................................................................................... 6
1.7.2 Heavy Rains......................................................................................................................6
1.7.3 Electrical Storms...............................................................................................................6
1.7.4 Windy Conditions............................................................................................................. 6
1.7.5 Violent Storms.................................................................................................................. 6
1.8
Equipment Requirements................................................................................................................ 7
1.9
Personnel Requirements.................................................................................................................. 7
1.10
Health and Safety............................................................................................................................ 7
1.10.1 Personal Protective Equipment........................................................................................ 8
1.10.2 Mechanical Equipment Hazard Prevention...................................................................... 8
1.10.3 Employee Health and Safety............................................................................................ 8
1.10.4 Physical Exposure........................................................................................................8
1.10.5 Safety Data Sheets.................................................................................................... 9
1.11 Record Keeping Program................................................................._......................................... 9
2.0 DEBRIS HANDLING OPERATIONS........................................................................................10
2.1
Acceptable Material..................................................................................................................10
2.2
Prohibited Wastes.....................................................................................................................10
2.3
Debris Screening.......................................................................................................................11
2.3.1 Receiving......................................................................................................................11
2.3.2 Hazardous Waste Contingency Plan............................................................................12
2.4
Disposal....................................................................................................................................13
2.4.1 Access.........................................................................................................................13
...............................................................
2.4.2 General Procedure ...................................... ..13
2.5
Cover.........................................................................................................................................14
2.5.1 Periodic Cover ................... ..........................................................................................14
2.5.2 Intermediate Cover.......................................................................................................14
2.6
Height Monitoring.....................................................................................................................14
3.0 TREATMENT AND PROCESSING OPERATIONS...............................................................15
3.1 Debris Grinding/Processing........................................................................................................15
3.2 Wood Processing.......................................................................................................................15
3.3 Leaves...................................................................................................................... ...15
...............
3.4 Topsoil.......................................................................................................................................15
3.5 Troubleshooting.........................................................................................................................15
4.0 ENVIRONMENTAL MANAGEMENT......................................................................................17
4.1 Surface Water Control...............................................................................................................17
4.1.1 Surface Water Run -On Control.....................................................................................17
4.1.2 Active Face Run -Off Control........................................................................................17
4.1.3 Erosion Control.............................................................................................................17
4.1.4 Sedimentation Control..................................................................................................18
4.2 Vector Control...........................................................................................................................18
4.3 Odor Control..............................................................................................................................18
4.4 Dust Control...............................................................................................................................18
5.0 QUALITY ASSURANCE AND REPORTING.......................................................................... 20
5.1 Overview........................................................................................... ....... 20
.................................
5.2 Documentation...........................................................................................................................20
TABLES
Table 1 Available Equipment................................................................................... 7
Table 2 Personnel Requirements.............................................................................. 7
Table 3 Troubleshooting........................................................................................ 16
FIGURES
APPENDICES
Figure 1 Existing Conditions
Appendix A Fire Occurrence Notification Form
Appendix B Waste Screening Form
1.0 GENERAL FACILPTY OPERATIONS
This Operations Plan is intended to guide the operations of the Wall Recycling, LLC LCID Landfill
and Treatment and Processing (T&P) Facility (Permit No.92M-LCID) located at 3000 Gresham Lake
Road in Raleigh, North Carolina. This facility is permitted to accept the following wastes generated
within Wake County, North Carolina:
• Land Clearing Waste
• Yard Trash
• Untreated and Unpainted Wood
• Uncontaminated Soil
• Inert Debris such as Rock, Brick and Concrete Block
• Asphalt
• Leaves
The continued use of the site will be conducted in accordance with the rules stated under 15A NCAC
13B .0500 and 15A NCAC 1313.0300. A site map of the facility has been added as Figure 1 and
illustrates the location of existing and proposed landfill units and other debris management activities.
1.1 Contact Information
All correspondence and questions concerning the Wall Recycling, LLC LCID Landfill and T&P
Facility should be directed to the appropriate personnel listed below. For fire or police
emergencies dial 911.
Chief Operations Officer
Dustin Hill
Wall Recycling, LLC 2310 Garner Road
Raleigh, NC 27610
Mobile (919) 896-1829
Office: (919) 582-7777
dustin+illwallrec. clina.com
Site Manager
Raleigh Nashwinter
Wall Recycling, LLC 3000 Gresham Lake Road Raleigh, NC 27615
Mobile: (919) 451-0807
Office: (919) 582-7777
Rnashwinte ct.wallrec� cling.com
Wall Recycling, LLC Facility
Operations Plan, Page 1 Revised November 2023
NCDEO Solid Waste
Diana Felix
217 West Jones Street 1646 Mail Service Center Raleigh, NC 27699-1646
Phone: (919) 707-8257
Di ana.Felixrivdeq.nc.6,ov
Eastern District Supervisor: Drew Hammonds
Environmental Specialist: Timothy Davis
Emergency Response
Raleigh Fire Department
Phone:911
1.2 Facility Ogeratina Hours
Normal operating hours of operations will be 12:00 A.M. to 11:59 P.M. Monday through Sunday.
We will normally be closed New Years, Memorial Day, Independence Day, Labor Day,
Thanksgiving and Christmas. In the event of disaster or other emergency situations, the site
manager will request approval from the NCDEQ regional office to allow additional temporary
operating hours during these events.
1.3 Site Access
The LCID and T&P will be primarily accessed by the East side entrance and the West side entrance
will be used once the Transfer Station is active.
• Unauthorized and illegal dumping of debris materials is prevented.
• Trespassing, and injury resulting therefrom, is discouraged.
• The risk of vandalism is greatly reduced.
Access to active areas of the landfill will be controlled by a combination of fences, natural barriers.
An attendant will be on duty at all times when the facility is open for public use.
1.3.1 Physical Restraints
The site will be primarily accessed by the existing entrance on Gresham Lake Road. The
primary entrance has a gate which will be securely locked during non -operating hours. A gate
house is provided at the main entrance for debris receiving and customer/visitor check in.
1.3.2 Securi
The facility is secured by fencing, security gates and natural buffers. Evidence of trespassing,
vandalism, or illegal operation will be reported to the owner to coordinate the repair or
replacement of the damaged property and to confirm the integrity of the facilities security.
Wall Recycling, LLC Facility
Operations Plan, Page 2 Revised November 2023
1.4 Siznaue
Signs containing the information required by the DWM will be placed at the facility entrance. The
signs will provide information on operating hours, permit number, contact phone number and
acceptable debris. Additional signage will be provided as necessary within the landfill complex to
distinguish the roadway to the active landfill unit(s). Service and maintenance roads for use by
operations personnel will be clearly marked. Site personnel will routinely inspect the conditions of the
posted signage to confirm that they are clearly visible and intact.
1.5 Communications
Communications will be maintained between the LCID landfill and the landfill gate house.
Radios/walk-talkies/cell phones will be used for communication between the gate attendant and the
working face supervisor. The gate house has a telephone in case of an emergency and to conduct
day-to-day business. Emergency telephone numbers are displayed in the gate house.
1.6 Fire Control
The possibility of fire within the landfill or a piece of equipment must be anticipated in the daily
facility operation. Potential fire hazards include both surface and subsurface conditions. Surface
conditions include equipment operations and newly placed debris. Subsurface conditions include
existing debris previously landfilled. Smoking is prohibited on the working face of the landfill.
1.6.1 Open Burning
Open burning is not allowed at the facility in accordance with 1 SA NCAC 13B.0566(12).
Controlled burning will occur only if permitted or approved by the DWM, the Division of Air
Quality (DAQ), and the local fire department, as appropriate.
1.6.2 Equipment
Portable fire extinguishers will be operational on all pieces of heavy equipment. Portable fire
extinguishers should be maintained in a state of readiness on each piece of moving equipment and
equipment should be cleaned periodically. Staff will be trained on the proper
utilization of the fire extinguishers. The fire extinguishers are checked on a regular basis to
ensure their utilization. The date of the units' inspections is documented on each tag.
Wall Recycling, LLC Facility
Operations Plan, Page 3 Revised November 2023
1.6.3 General Fire Management Strategies
Each fire situation is site/event specific; however, general strategies for active fire
management include the following (in no particular order):
• Accelerated high temperature combustion (displacing fuel).
• Covering burning material with soil (reduce oxygen).
• Covering burning material with foams (reduce oxygen).
• Flooding burning material with water (reduce heat).
• Injecting an inert gas such as CO2 (reduce oxygen).
• Excavating the burning material (displacing fuel) and then extinguishing it in small,
controlled areas; and
• Applying extinguishing agents that will interfere with and inhibit the combustion process
at the molecular level (break the chemical reaction).
In addition to the active fire management strategies mentioned above, periodic refresher
training on these strategies will be performed.
1.6.4 Surface Emissions
The presence of surface emissions in the form of steam or smoke may occur from time to
time. On -site personnel will watch sensitive areas across the cover for signs of these types of
emissions.
Steam
Steam is pure water vapor, produced by evaporated water within the debris mass. Ordinarily,
steam is completely colorless. As steam cools and condenses it becomes visible as water vapor and
can produce a white cloud which dissipates relatively quickly. It is odorless and tasteless.
Because the humidity is very high, the cloud may leave water droplets on solids that touch it.
Observed steam emissions on site will continue to be monitored; changes will be reported to
the site manager.
Smoke
Smoke consists of gases and soot. The gases typically include water vapor, but smoke differs
from steam in that there are other gases, such carbon dioxide and sulfur oxides, plus there are
small particles. The types of particles depend on the source of the smoke, but usually you can smell
or taste either the soot or some of the gases from smoke. Smoke may be white, but more
commonly it is colored by its particles and will linger across the cover as the particles in the
smoke are suspended. Observed smoke will be covered with soil or other action to prevent fire
creating conditions and continue to be monitored until smoke is no longer produced. The site
manager will be notified when smoke is observed on site.
1.6.5 Fires Within Disposal Areas
Fires within the landfill disposal areas will be limited using periodic cover as a fire break and
control of "hot" loads entering the landfill. See section 1.6.3 for potential methods of fire
control.
Wall Recycling, LLC Facility
Operations Plan, Page 4 Revised November 2023
1.6.6 Notification
DWM will be notified within 24 hours of discovery of a fire within the facility perimeter.
In addition, written documentation describing the fire, the actions carried out to extinguish the
fire, and a strategy for preventing future occurrences will be provided to the DWM within 15
days following any such occurrence using the DWM's Fire Occurrence Notification Form
(Appendix A).
1.7 Severe Weather Conditions
Inclement weather conditions can directly affect landfill facility operations. Some weather
conditions and recommended operational responses are as follows.
1.7.1 Ice Storms
An ice storm can make access to the facility and disposal locations dangerous, prevent
movement or placement of daily cover, and, thus, may require closure of the facility until the
ice is removed or has melted. The determination to discontinue activities due to inclement
weather conditions will be made by the Site Manager.
1.7.2 Heavy Rains
Rainy periods can create a muddy situation in areas of exposed soil. The control of drainage
and use of crushed stone on unpaved roads should provide all-weather access for the site and
promote drainage away from critical areas. In areas where the aggregate surface is washed
away or otherwise damaged, new aggregate should be used for repair.
Intense rains can affect newly constructed drainage structures such as swales, diversions,
cover soils, and vegetation. After such a rain event, inspection by facility personnel will be
initiated and corrective measures initiated to repair any damage found before the next rainfall. In
extreme cases the landfill will be closed for employee and customer safety and to prevent
excessive site damage.
1.7.3 Electrical Storms
Employees working on heavy equipment and open areas of the landfill and recovery areas
are susceptible to the hazards of an electrical storm. If necessary, disposal activities will be
temporarily suspended during such an event. To guarantee the safety of all field personnel
refuge will be sought, as necessary, in on -site buildings or in rubber -tired vehicles.
1.7.4 Windy Conditions
Operations during a particularly windy period may require the working face be temporarily
shifted to a more sheltered area. When this is done, the previously exposed face will be
immediately covered with soil.
Wall Recycling, LLC Facility
Operations Plan, Page 5 Revised November 2023
1.7.5 Violent Storms
In the event of hurricane, tornado, or severe winter storm warning issued by the National
Weather Service, operations may be temporarily suspended until the warning is lifted.
Cover will be placed on exposed debris and buildings and equipment will be
properly secured.
1.8 Equipment Requirements
Periodic equipment maintenance and minor and major repair work will be performed in designated
maintenance zones outside the facility.
The available equipment for daily operation and site maintenance are listed in the following
table. However, the operator may change as needed.
Table 1. Available Equipment
Description
Primary Function (Allocation)
1 Excavator
Soil excavation, LCID landfill mining and sorting
2 Dozer
Debris lacement and grading.
3) Front End Loader
Loading, mixing, and tumi .
4 Dump Truck
Hauling material around site.
5) Grinder
Grinding/shreddingGrinding/shredding of bulky debris, stumps, limbs, etc.
6) Screening
Equipment
Processing material to uniform consistency and sorting
of various gradations.
7) Water Truck
Dust suppression
1.9 Personnel Rea uirements
The anticipated personnel requirements for site operation and maintenance are listed in the
following table. However, personnel may be adjusted as needed.
Table 2. Personnel Requirements
Description
Primary Function (Allocation)
1) Site Manager —1
Overall management of the site, receiving
2) Gate attendant
and documentation of incoming loads.
Waste screening cameras stem
3) Operator - 1
Management of transfer station and the landfill
area.
4) Labor - 1
General labor and operational staff around site.
1.10Health and Safety
All aspects of landfill operations were developed with the health and safety of the operating
staff, customers, and neighbors in mind. Safety equipment provided includes equipment rollover
protective cabs, seat belts, audible reverse warning devices, hard hats, safety shoes and first
aid kits. A member of the operating staff is the designated site safety officer (Site Manager),
who works with the facilities management to ensure the site's safety and emergency
response program is consistent with the Occupational Safety and Health Administration
(OSHA) guidance. Other safety requirements designated by the owner may also be implemented.
Wall Recycling, LLC Facility
Operations Plan, Page 6 Revised November 2023
1.10.1 Personal Protective Equipment
Personal Protective Equipment (PPE) must be evaluated as to the level of protection
necessary for operating conditions and then made available to facility employees. The list
below includes the PPE typically used and/or required in a solid waste management facility
workplace.
• Safety shoes with steel toes.
• Noise reduction protection should be used in areas where extended exposure to
continuous high decibel levels is expected.
• Disposable rubber latex or chemical resistant gloves for handling and/or sampling
of debris materials.
• Dust filter masks (voluntary).
• Hard hats (in designated areas).
Following use, PPE should be disposed of or adequately cleaned, dried, or readied for
reuse.
1.10.2 Mechanical Equipment Hazard Prevention
Equipment should be operated with care and caution. All safety equipment such as horns,
backup alarms, and lights should be functional. A Lockout- Tagout program will be used
to identify equipment in need or under repair and ensure that operation is "off-limits" prior
to maintenance or repair.
1.10.3 Employee Health and Safety
Some general safety rules are:
• Consider safety first when planning and conducting activities.
• Review the equipment O&M manual(s) prior to attempting repairs/changes.
• Remember the buddy system for mechanical equipment repair.
• Post emergency contact phone numbers.
• Provide easy and visible access to the Right to Know materials.
• Provide easy and visible access to first aid kits and fire extinguishers.
1.10.4 Physical Exposure
Facility personnel may come in contact with the fluids, solids and airborne constituents
found at the facility. Safe work practices around these potential exposures as well as
appropriate equipment use, and proper disposal procedures will be followed. Routine training
should be conducted regarding individual and collective materials and their associated
hazards. Training concerning safe workplace practices around these potential exposures
should instruct employees on the proper usage of equipment and proper disposal procedures.
1.10.5 Safety Data Sheets
Safety Data Sheets (SDS) will be made available for all chemicals stored on site for use at
the facility.
Wall Recycling, LLC Facility
Operations Plan, Page 7 Revised November 2023
MIRecord Keeping Program
The owner will maintain the following records at the corporate office and with the engineer:
A. Current permit(s) (Permit to Construct, Permit to Operate, etc.).
B. Current operations manual/plan(s) and engineering plan for each landfill unit.
C. Inspection reports.
D. Audit and compliance records.
E. Annual reports (including survey and other documentation related to airspace usage in
landfill units).
F. Daily volume records.
G. Debris screening logs.
H. Employee training procedures and training records.
I. Unacceptable waste disposal tickets.
J. Grinding and chipping logs.
K. Finished product inventory.
L. Closure information, where applicable, including:
1. Notification of intent to close.
2. Testing.
3. Certification; and
4. Recording.
The operating record will be kept up to date by the owner or his designee; it will be presented, on
request, to the DWM for inspection.
Wall Recycling, LLC Facility
Operations Plan, Page 8 Revised November 2023
2.0 DEBRISHANDLING OPERATIONS
This section describes the required debris handling operations for the facility.
2.1 Acceptable Material
2.1.1 Only the following debris materials generated within the approved service area maybe
disposed of in the LCID landfill unit.
• Land Clearing and Inert Debris Landfill: as defined in 15A NCAC 13B.0101(30) means a
unit for the disposal of yard waste and inert debris waste (15A NCAC 13B .0563 through
.0567), uncontaminated soil, gravel and rock, and yard trash.
• Land Clearing Waste: as defined in 15A NCAC 13B.0101(31) means solid debris which
is generated solely from land -clearing activities, limited to stumps, trees, limbs, brush,
grass, and other naturally occurring vegetative material.
• Yard trash: as defined in G.S. 130A-290(a)(45) means solid waste consisting solely of
vegetative matter resulting from landscaping maintenance.
• Other Debris as Approved by the Solid Waste Section of the Division of Waste
Management.
2.1.2 The following debris may be accepted for use in the T&P facility:
• Naturally occurring tree debris: stumps, trees, limbs, brush, etc.
• Clean wood debris: from construction only. No demolition materials no painted or treated
wood, no engineered or laminated wood products. This may include pallets or skids if
the wood naturally occurring and is not engineered, treated, or manufactured.
• Concrete/brick debris
• Asphalt debris
• Leaves
Only materials listed above will be disposed. All other identified debris will be removed and
disposed in accordance with Section 2.3.
2.2 Prohibited Wastes (reference other permits)
No municipal solid waste (MSW), construction and demolition debris waste (C&D), hazardous
waste (as defined by 15,4 NCACI3A including hazardous waste from conditionally exempt
small quantity generators), or liquid waste will be accepted at this facility. In addition, no
polychlorinated biphenyl (PCB) waste will be accepted. The facility follows a screening
program as described in Section 2.3, to ensure no prohibited waste is accepted.
23 Debris Screening
Screening programs have been implemented to prevent prohibited wastes from entering the facility.
If any non -acceptable types of waste are identified, these wastes will be placed into a stockpile or
container and removed from the site for disposal at a solid waste facility permitted to accept the
particular waste. All records and receipts for this disposal will be kept in the operating record
for the site. It is anticipated that unacceptable wastes will be minor amounts and either generally
classified as MSW or C&D. The operators will be trained on identifying non-conforming/non-
acceptable wastes. The frequency for screening includes every load described as follows.
Wall Recycling, LLC Facility
Operations Plan, Page 9 Revised November 2023
2.3.1 Receiving
All vehicles must stop at the guard house located near the facility entrance and visitors are
required to sign -in. All debris transportation vehicles are checked and have their load content
assessed. The attendant(s) requests from the driver of the vehicle a description of the debris it
is carrying to ensure that unacceptable waste is not allowed into the landfill. The attendant(s)
then visually checks the vehicle. Signs informing users of the acceptable and unacceptable
types of debris are posted at the guard house. Once passing the attendant, the vehicles
containing LCID debris (See Section 2.1.1) are routed to the landfill. Vehicles carrying clean
wood debris (or debris listed in See Section 2.1.2) are directed to the raw material stockpiles
in the T&P area. Directional signs are used to guide traffic to the correct unloading area.
Each incoming load will be unloaded at its designated area (either the LCID disposal area or
the T&P raw material stockpile, depending on the material type). The attendant will alert the
yard operators with information on the incoming load, e.g., material type, truck description, etc.
The yard operator will be present when each vehicle is unloaded to ensure the material is
acceptable. This inspection will preferably take place prior to unloading, but at a minimum
soon after unloading and prior to the vehicle leaving the premises. If the load is deemed
suitable for the designated unloading area, the vehicle will be cleared to exit with the
attendant. If unacceptable, non -hazardous materials are found, the driver/owner of the truck
will be notified, and the materials will be removed from the site by the hauler. Any hazardous
waste discovered will follow the Hazardous Waste Contingency Plan as outlined in Section
2.4.2.
Vehicles are selected for random screening based on 1 % by volume of incoming site acceptance,
or a minimum of once per month. Selected vehicles are directed to an area of intermediate
cover adjacent to the working face where the vehicle will be unloaded. Debris is carefully spread
using suitable equipment, and the load is inspected by an attendant trained to identify unacceptable
wastes. All random debris inspections will be documented by facility staff using the waste
screening form provided in Appendix B.
Wall Recycling, LLC Facility
Operations Plan, Page 10 Revised November 2023
2.3.2 Hazardous Waste Contingency Plan
If identifiable hazardous waste or waste of questionable character is detected at the landfill,
appropriate equipment, protective gear, personnel, and materials as necessary will be
employed to isolate the wastes. The DWM will be notified immediately that an attempt was
made to dispose of hazardous waste at the landfill. If the vehicle attempting disposal of such
waste is known, all attempts will be made to prevent that vehicle from leaving the site or, if the
vehicle has left the site, immediate notice will be served on the owner of the vehicle that
hazardous waste, for which they have responsibility, has been disposed of at the facility.
The facility will assist DWM as necessary and appropriate in the removal and disposition of
the hazardous waste and in the prosecution of responsible parties. If needed, the hazardous
waste will be covered with either on -site soils or other tarping material until such time when
an appropriate method can be implemented to properly handle the waste. The cost of the
removal and disposing of the hazardous waste will be charged to the owner of the vehicle
involved. Any vehicle owner or operator who knowingly dumps hazardous waste in the
landfill may be barred from using the facility.
Should an incident where hazardous waste is found at the facility occur, the event will be
documented by facility staff using the waste screening form provided in Appendix B.
Records gathered as part of the waste screening programs will be maintained at the facility
during its active life.
2.4 Disposal
2.4.1 Access
Traffic will be clearly directed to the appropriate active access road. Access road location
during debris placement will be determined by operations personnel to reflect the debris
placement strategy.
2.4.2 General Procedure
Debris transportation vehicles will arrive at the working face at random intervals. There may
be a number of vehicles unloading debris at the same time, while other vehicles are waiting. To
maintain control over the unloading of debris, a certain number of vehicles will be allowed on
the working face at a time. The actual number will be determined by the personnel. This
procedure will be used to minimize the potential of unloading unacceptable debris and to control
disposal activity. Operations at the working face will be conducted in a manner which will
encourage the efficient movement of transportation vehicles to and from the working face,
and to expedite the unloading of debris.
The approach to the working face will be maintained such that two or more vehicles may
safely unload side by side. A vehicle turn -around area large enough to enable vehicles to arrive
and turn around safely at a reasonable speed will be provided adjacent to the unloading area.
The vehicles will back to a vacant area near the working face to unload. Following
completion of the unloading operation, the transportation vehicles will immediately leave the
working face area. Personnel will direct traffic necessary to expedite safe movement of
vehicles.
Wall Recycling, LLC Facility
Operations Plan, Page 11 Revised November 2023
Debris unloading at the landfill will be controlled to prevent disposal in locations other than
those specified by site management. Such control will also be used to confine the working face
to a minimum width yet allow safe and efficient operations. The width and length of the
working face will be maintained as small as practical to maintain the appearance of the site,
control windblown debris, and minimize the amount of cover required each day. Normally,
only one working face will be active on any given day, with all deposited debris in other areas
covered by either periodic, intermediate, or final cover, as appropriate.
The procedures for placement and compaction of debris include unloading of vehicles,
spreading of debris into nominal two (2) foot lifts, and compaction on relatively flat slopes
(i.e., 5H:1 V max.), using a minimum of three full passes. A maximum slope ratio of 3H:1 V
will be observed at all times.
The use of portable signs with directional arrows and portable traffic barricades will facilitate
the unloading of debris to the designated disposal locations. These signs and barricades will
be placed along the access route to the working face of the landfill or other designated
disposal areas which may be established.
2.5 Cover
The below cover requirements apply to debris which is placed into the permanent LCID landfill.
For the treatment and processing operations, material should be confined as practical, and all
windblown material should be collected and returned to the appropriate pile at the conclusion of each
day of operation.
2.5.1 Periodic Cover
Waste will be covered with no less than 6 inches of soil monthly, or when the working face
reaches 1 acre in size, whichever occurs first. This periodic cover is intended to control
vectors, fire, odors, and blowing debris. This does not include stockpiled material marked for
reuse.
2.5.2 Intermediate Cover
Areas that will not have additional wastes placed on them for three months or more, but
where final termination of disposal operations has not occurred, shall be covered with no less
than one foot of soil cover sloped to direct the flow of surface water from the landfill, and
stabilized with vegetative ground cover or other stabilizing material.
2.6 Heieht Monitoring
Staff will periodically monitor landfill top and side slope elevations. When such elevations approach
design grades, the final top of debris grades will be staked to limit over -placement of debris.
Wall Recycling, LLC Facility
Operations Plan, Page 12 Revised November 2023
3.0 TREAT MANDPROCESSINGOPERATIONS
3.1 Debris Grinding Processing
Grinding and/or chipping will be conducted centrally on the site within the future landfill footprint. The
grinding/chipping operations will be conducted as needed to facilitate the landfill recovery and
incoming waste operations by contract equipment. It is anticipated that incoming materials for
processing will include asphalt, concrete, and brick or stone. The material will be directed to the
grinders as per the material size. It is anticipated that grinding and chipping will be conducted on a
periodic basis as materials are available. Grinders and chippers pose both maintenance and safety
hazards. Therefore, please refer to the manufacturer's safety and/or maintenance literature prior to
operating equipment on site.
3.2 Wood Processing
The facility accepts tree stumps, logs, limbs, landscape trimmings, etc. A portion of the wood
materials are processed for use in industrial markets. Much of the woody materials are processed using
the equipment inventory and made into mulch which is then colorized and sold from the facility. The color
materials are a non -toxic organic inert dye that arrives in a concentrated liquid form. The concentrated
dye is then mixed with water to create a diluted solution for application to the mulch. Mulch dye runoff
will be managed using untreated mulch to adsorb the dye and worked back into the stockpile utilizing best
practices.
33 Leaves/Natural Vegetative Material
During the late fall/early winter months, leaves/naturally occurring vegetative material are accepted
from local landscapers and vacuum trucks. The naturally occurring vegetative materials are ground
using best practice and used as an additive in topsoil products.
3.4 Topsoil
Soil is separated from the incoming wood debris that is processed onsite (Section 3.2). This is
accomplished using a vibrating screen, and topsoil is then mixed with processed leaves (Section
3.5) to produce topsoil.
3.5 Troubleshooting
The final products must be maintained and monitored to prevent fire potential and to maintain an
acceptable product. Typical problems and solutions have been provided in Table 3. This table may
be updated from time to time to include additional information about the specific processes at this
site.
Wall Recycling, LLC Facility
Operations Plan, Page 13 Revised November 2023
Table 3. Troubleshootine
Condition
Reason
Check
Remedy
Pile temperature too
Insufficient
Is pile moist?
Turn pile or aerate
high (>150 °F]
aeration
Pile is too large
Height > 15 feet?
Decrease pile height
Extremely high
Spontaneous
Low moisture?
Decrease pile size, add
temperature (>170
combustion
Burnt smell?
water to smoldering
OF]
section, and combine with
other piles
Odors in pile
Piles are too
Height > 15 feet or
Decrease pile size
large
width > 25 feet?
Non -uniform texture
Poor mixing
Original raw
Screen product and
materials
improve mixing
discernible?
Wall Recycling, LLC Facility
Operations Plan, Page 14 Revised November 2023
4.0 ENVIRONMENTAL MANAGEMENT
This section reviews the overall environmental management tasks required for the successful operation
of Wall Recycling, LLC LCID Landfill and T&P Facility.
4.1 Surface Water Control
As used herein, the definition of "surface water" is water which results from precipitation or
site run-on that has not contacted the debris.
Proper surface water control at the facility will accomplish the following goals:
• Minimize the potential for the discharge of pollutants to waters of the United States, including
wetlands (point or non -point sources).
• Prevent the run-on of surface water into the landfill unit(s) or the active face(s).
• Prevent the run-off of surface water that has come into contact with the debris (i.e., leachate).
• Limit the erosion caused by surface waters.
* Limit sediments carried off -site by surface waters.
Maximize the separation of surface water from leachate using best management practices.
The following is a brief discussion of some of these features and practices, focusing more on the
landfill units.
4.1.1 Surface Water Run -On Control
The perimeter berms and/or perimeter channels around the landfill unit(s) are designed to
prevent the run-on of surface water from adjacent land into the landfill. Additional structures
such as diversion berms, channels, down pipes, etc. carry surface water away from the
landfill.
4.1.2 Active Face Run -Off Control
Particular care is required to ensure that surface water coming from the active face, e.g., having
potential contact with the debris, is allowed to percolate into the underlying debris. Only run-
off from disposal surfaces that have received adequate cover is not considered leachate
and should be directed to the stormwater drainage system where practical.
4.1.3 Erosion Control
The serviceability of the landfill relies heavily on soil berms, barrier layers, and agricultural
layers that are readily eroded by flowing water. Erosion control provisions incorporated in
the landfill include the following:
• The slope of the working face should typically be no steeper than practical to limit
erosion of the periodic cover.
• Intermediate cover that has been exposed for more than 30 days must be seeded
immediately and repaired when erosion features are identified.
• Water collected by each drainage break is routed to stormwater drainage channels or
down pipes so that the run-off volume does not accumulate going down the slope.
• The vegetative soil layer placed over the final cover must be seeded immediately.
Wall Recycling, LLC Facility
Operations Plan, Page 15 Revised November 2023
Additional erosion control measures have been established within the drainage channels and at
points of stormwater discharge. Final cover should be inspected regularly for erosion damage
and promptly repaired. Revegetation should be performed in accordance with the
requirements of the applicable erosion and sedimentation control plan.
4.1.4 Sedimentation Control
Stormwater run-off from the landfill unit and T&P facility is conveyed to one of the sediment
basins and traps located outside of the landfill footprint. These basins should be inspected
regularly for sediment build-up or erosion damage. The basins and/or traps should be cleaned
out when sediment fills the lower half of the basin.
4.2 Vector Control
Due to the nature of the debris disposed in this landfill unit, vector control is not anticipated to be
of concern. Note that the use of periodic cover will discourage animals from nesting in the debris.
4.3 Odor Control
Due to the nature of the debris disposed in this landfill unit, odor control is not anticipated to be of
concern. However, if odor control becomes a problem, additional measures (such as additional
cover) will be implemented to ensure odor control.
4.4 Dust Control
Dust related to equipment operations and traffic on the access roads will be minimized by strict
enforcement of slow speeds across the site. During dry periods and as needed, a water truck will be
used to control dust.
Wall Recycling, LLC Facility
Operations Plan, Page 16 Revised November 2023
5.0 QUALITYASSURANCE AND REPORTING
5.1 Overview
This section reviews the overall quality assurance and reporting tasks required for the site
operations. The information contained herein was prepared to provide facility personnel with
methodology and reporting requirements to satisfy these requirements.
5.2 Documentation
An essential component of solid waste facilities is documentation from the time the materials enter
the site to the last cubic yard of material is disposed or delivered to the customer. The documentation
is used to improve efficiency in the process, modify process designs, and in troubleshooting of the
process. The establishment of a reliable continuing record for proof of performance, thus justifies
operational decisions, expenditures, and recommendations. Daily operational records also provide
information useful in process adjustments required due to climatic or seasonal changes or other
recurring problems of a specific nature. Accurate records also provide the basis for planning future
expansion, planning future modifications, establishing, and adjusting operating budgets, and
providing evidence of performance in compliance with regulatory agencies.
The NC DEQ Division of Waste Management requires record keeping on the inflow and outflow of
material. Personnel from the NC DEQ Division of Waste Management will make periodic visits to
the facility. During these inspections, a review of operational and other records may be requested.
The following are points in the process where monitoring documentation are anticipated:
(i) Debris Screening Logs
(ii) Daily Volume Records
(iii) Employee Training Procedures and Records of Training Completed
(iv) Un-Acceptable Wastes Disposal Tickets
(v) Grinding and Chipping Logs
(vi) Laboratory Testing identifying soil or mulch properties such as density and gradation (if
performed).
(vii) Screening Logs
(viii) Finished Product Inventory identifying the quantity and type of material produced by
classification.
(ix) All Closure Information where applicable including testing, certification and recording.
(x) Annual Report for the period of July 1 to June 30 will be submitted to the Division by
August 1 st of each year.
Wall Recycling, LLC Facility
Operations Plan, Page 17 Revised November 2023
Figure 1— Existing Conditions
YK
J
_
•�!.. -
....
T
FUTURE TRANSFER
FACILITY
STATION ENTRANCE
ENT)zANCE
a ad
--
+
APPROXIMATE LAND USE
—
'
DELINEATION LINE
(DASHED CYAN LINE)
r7 SALES AND
IP r r
FUTURE SCALE
T&P AREA
EXISTING GATE
HOUSE AND
r y C - 3.& ACRE
4 HOUSE AND OFFICES e
SCALES LOCATION
FUTUR
TRANSfER
-
X 9VATIONAREA
'- APPROXIMATE f
.. 2-3±ACRE
PROPERTY LINE ESTIMATED EXTENT OF
(RED LINE)
LANDFILL WASTE BASED ON
yi
TOPOGRAPHIC CONTOURS
INTERPRETATION.
(RED DASHED LINE)
•'i Yr.-�A
- - C�
r."'
• 5:i
J
ow s
`..
.
G A ;%105
- LCID LANDFILL
'-- AND T&P AREA
^' EXTENT OF
WASTE AREA .
17.4±ACRE
-
f
C S°l��fo Site Layout
Rowland LCID Landfill
PERMIT - 92M
Wall Recycling Raleigh o
NSF
aEVE3000 Gresham Lake Road Z
mD
ELM Site Solutions, Inc. Raleigh, North Carolina 27615
P.O. Box 97607 REFERENCES:
Raleigh, NC 27624 1) WAKE COUNTY GIS PROPERTY LINES &PARCELS. 01 300' 600' Figure 3
Phone: 919 792-3733 2) WAKE COUNTY GIS 2022 AERIAL PHOTO.
( ) 3WAKE COUNTY GiSTOPOGRAPHICCONTOURS. SCALE:13001
Appendix A — Fire Occurrence Notification Form
New Submission
Facility Fire Occurrence Notification
Division of Waste Management (DWM) - Solid Waste Section
iJOR1"ti C•0.q)I iNia
UeDartmen(otFmironmwtalgwliMl r
This form is used for solid waste management facilities to submit to the Division of Waste Management (DWM)
Solid Waste Section a written notification of a fire at a solid waste management facility. Verbal notification is
required within 24 hours of the fire. This form must be submitted to DWM within 15 days of the fire.
County: * (?) v Permit/Site ID: * v
Facility Name:
Date of Fire:
Time of AM v
Fire: *
Reporting Method: How was the fire initially reported to DWM?
Who reported the fire to Provide the name of the person who gave 24-hour notice to DWM:
DWM? *
Title/Affiliation: * Provide the title or site affiliation of the person who gave 24-hour notice to DWM:
DWM Staff Notified: Provide the name of the DWM staff person that was given 24-hour notice:
Location: * Where at the facility did the fire occur?
Type(s) of Waste: What type(s) of waste caught fire?
Amount of Waste: Estimate the amount of waste that was burning:
Size of Fire: * Estimate the size of the area that was burning:
Units:
O tons
0 cu yds
Units *
0 acres
O sq ft
https://edoGs.deq.ne.gov/Forms/swfirenotification 1/2
New Submission
Cause of Fire: What was the cause of the fire?
Actions Taken: * List the actions taken to put out the fire and minimize damage:
Could fire have been What could have been done to prevent this fire?
prevented?
Plan for Prevention: * Describe the plan of action to prevent future incidents.
Name: * Provide the name of the person submitting this form:
Title/Affiliation: * Provide the title or site affiliation of the person submitting this form:
Phone: * Email: *
Date: * Date will be captured on form submission
https://edoes.deq.nc.gov/Forms/swfiirenotification 2/2
Appendix E — Waste Screening Form
Day I Date:
Truck Owner:
Truck Type:
Weight:
Debris Generator/ Source:
Wall Recycling, LLC
3000 Gresham Lake Road, Raleigh, North Carolina
Permit No. 92M-LCID
DEBRIS SCREENING FORM
Time Weighed in:
Driver Name:
Vehicle ID/ Tag No:
Tare:
Reason Load Inspected: Random Inspection Staff Initials
Detained at Gate House Staff Initials
Detained by Operating Staff Staff Initials
Inspection Location:
Approved Debris Determination Form Present? Yes No N/A
Description of Load:
Load Accepted (signature) Date
Load Not Accepted (signature) Date
Reason Load Not Accepted (complete only if load not accepted)
Description of Suspicious Contents:
Color: Hazardous Waste Markings:
Texture:
Drums Present: Smell:
Est. Cubic Yards in Load:
Est. Tons in Load:
DMW Emergency Management Contacted? Yes
Company orAuthority Contacted?
Hazardous Materials Present:
No
Hauler Notified (if debris not accepted) Phone: Time Contacted:
other Observations:
Final Disposition
Signed: Date: _
Debris Screening Inspector or Solid Waste Manager
Attach related correspondence to this form. File completed form in Operating Record.