HomeMy WebLinkAboutNCD980602163_19980409_Warren County PCB Landfill_SERB C_Detoxification Costs Using BCD Technological Process-OCRPCB LANDFILL DETOXIFICATION COSTS
USING BCD TECHNOLOGICAL PROCESS
April 9, 1998
Final design, including permit preparation
and plan submittal
Working Group, PCB office in Warren
County, CAB, Science Advisor(s)
Supplemental site investigation
Mobilization
Site preparation/set up
INITIAL PHASE, SUBTOTAL:
Demonstration test
Excavation
Soil/water treatment
Analytical (performance testing,
soil, water, air monitoring)
..
Estimated costs Phase Sub-totals
$539,000.00
$200,000.00
$100,000.00
$1,35,800.00
$2,614,400.00
$3,889,200.00
$487,300.00
$798,100.00
$13,457,600.00
$1 ,167,000.00
TREATMENT PHASE, SUBTOTAL $15,910,000.00
Backfill $930,000.00
Reclamation $74,000.00
Decon, dismantle, demob $1,092,800.00
RESTORATION/ DEMOB PHASE $2,096,800.00
SUBTOTAL
ESTIMATED COSTS $21,796,000.00
CONTINGENCY: $2,079,000.QO
TOT AL ESTIMATED COSTS $23,975,000.00
WARREN COUNTY PCB LANDFILL WARRENTON, NC. SECTION 6.3 PROPOSED PROJECT SCHEDULE PLAN SUBMLT / PERMIT PROCUREMENT (39 weeks) MOBILIZATION/ SITE PREP/ EQUIPMENT SET-UP (14 weeks) START-UP/ PERF DEMONSTRATION (4 weeks) PROCESSING (60 weeks) DECON/DISMANTLE/DEMOBE (8 weeks) 1998 I 1999 I 2000 M J JASON DJ FM AM J JASON DJ FM AM J JASON DIJ H r----i 64