Status Source
Open Date 7/10/2014 Added Initial Permit to Operate
Survey Date 4/18/2023 Correct Annual Facility Report
Years Open 9 Added Calculated
Fiscal Year Tons Tons 667,644.0 Correct Annual Facility Report
Total Tons Disposed to Date Tons 1,602,288.0 Correct Annual Facility Report
Average Tons per Year Tons 178,032.0 Added Calculated
Volume Used Cubic yards 1,149,245.0 Correct Annual Facility Report
Volume Constructed Cubic yards 2,227,886.0 Corrected Duke Representative
Total Permitted Volume Cubic yards 12,010,584.0 Corrected July 31, 2019 Permit (Estimated gross capacity, page 10)
Compaction Density Tons/Cubic yards 1.4 (Total Tons) / (Volume Used)
Remaining Volume for Future Construction Cubic yards 1,078,641.0 (Volume Constructed) - (Volume Used)
Remaining Permitted Volume Cubic yards 10,861,339.0 (Volume Overall) - (Volume Used)
Approximate Constructed Remaining in Tons Tons 1,503,851.3 (Volume Constructed Remaining) x (Compaction Density)
Approximate Constructed Remaining in Years Years 8.4 (Volume Constructed Remaining in Tons) / (Average Tons)
Remaining Constructed in Fiscal Year Tons 2.25 (Volume Constructed Remaining in Tons) / (Fiscal Year Tons)
Approximate Total Permitted Volume Remaining in Tons 15,142,979.2 (Volume Overall Remaining) x (Compaction Density)
Approximate Total Permitted Volume Remaining in Years 85.1 (Volume Overall Remaining in Tons) / (Average Tons)
Approximate Total Tonnage Remaining in Fiscal Year Tons 22.7 (Volume Overall Remaining in Tons) / (Fiscal Year Tons)
________________________________
From: Martin, Melonie Y <Melonie.Martin@duke-energy.com>
Sent: Monday, September 25, 2023 12:57
To: Yitbarek, Diana <diana.yitbarek@deq.nc.gov>
Subject: RE: [EXTERNAL] Mayo _7305_Capacity Report
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message button located on your Outlook menu bar on the Home
tab.
Hi Deana!
The Mayo Monofill Phase 1 volume is 2,227,886 cubic yards (gross capacity). Please let me know if you need any additional information.
Respectfully,
Melonie Martin
Duke Energy | EHS | Groundwater & Waste Programs
From: Yitbarek, Diana <diana.yitbarek@deq.nc.gov>
Sent: Friday, September 22, 2023 5:09 PM
To: Martin, Melonie Y <Melonie.Martin@duke-energy.com>
Subject: [EXTERNAL] Mayo _7305_Capacity Report
*** CAUTION! EXTERNAL SENDER *** STOP. ASSESS. VERIFY!! Were you expecting this email? Are grammar and spelling correct? Does the content make sense? Can you verify the sender? If suspicious
report it, then do not click links, open attachments or enter your ID or password.
Hi Melonie, Hope you are well.
I need your support with the table below. Mainly with the volume constructed. Would you mind providing the Volume Constructed, cubic yards? I would appreciate it if you could get back
to me sometime next week. Thank you and have a good weekend!
Source
Open Date
7/10/2014
Initial Permit to Operate
Survey Date
4/18/2023
Annual Facility Report
Years Open
9
Calculated
Fiscal Year Tons
Tons
667,644.0
Annual Facility Report
Total Tons Disposed to Date
Tons
1,602,288.0
Annual Facility Report
Average Tons per Year
Tons
178,032.0
Calculated
Volume Used
Cubic yards
1,149,245.0
Annual Facility Report
Volume Constructed
Cubic yards
1,592,000.0
?
Total Permitted Volume
Cubic yards
12,010,584.0
July 31, 2019, Permit (Estimated gross capacity, page 10)
Compaction Density
Tons/Cubic yards
1.4
(Total Tons) / (Volume Used)
Remaining Volume for Future Construction
Cubic yards
442,755.0
(Volume Constructed) - (Volume Used)
Remaining Permitted Volume
Cubic yards
10,861,339.0
(Volume Overall) - (Volume Used)
Approximate Constructed Remaining in Tons
Tons
617,293.1
(Volume Constructed Remaining) x (Compaction Density)
Approximate Constructed Remaining in Years
Years
3.5
(Volume Constructed Remaining in Tons) / (Average Tons)
Remaining Constructed in Fiscal Year Tons
0.92
(Volume Constructed Remaining in Tons) / (Fiscal Year Tons)
Approximate Total Permitted Volume Remaining in Tons
15,142,979.2
(Volume Overall Remaining) x (Compaction Density)
Approximate Total Permitted Volume Remaining in Years
85.1
(Volume Overall Remaining in Tons) / (Average Tons)
Approximate Total Tonnage Remaining in Fiscal Year Tons
22.7
(Volume Overall Remaining in Tons) / (Fiscal Year Tons)
________________________________
Email correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties by an authorized state official.