HomeMy WebLinkAbout4120T_GreensboroTS_CostApproval_FID1811106_20230712Moutos, Sarah
From:
Sent:
To:
Cc:
Subject:
Attachments:
Follow Up Flag:
Flag Status:
laserfiche.ncdenr.gov@mccicloud.io
Wednesday, July 12, 2023 11:05 AM
Richard.Lovett@greensboro-nc.gov; emily.tucker@hdrinc.com
Moutos, Sarah; Stanley, Sherri; Yitbarek, Diana
[External] APPROVAL -Transfer Station Financial Assurance Cost Estimate - 4120T-
TRANSFER- City of Greensboro Solid Waste Transfer Station
TS Closure Cost Estimate_2023_Financial Assurance.pdf
Follow up
Flagged
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
F 00�
7
4N(Q)A TF • _
. CAF.CLIhL4
;Q
Oepairgt"I 9f EnwIhGIM150a101 �Nainv
Mr. Richard P. Lovett, P.G., C.P.G., A.S.P.
Environmental Compliance Support Manager
City of Greensboro
RE: Approved Cost Estimate
Transfer Station - City of Greensboro Solid Waste Transfer Station
Guilford County
Dear Mr. Richard P. Lovett, P.G., C.P.G., A.S.P.,
A review of the Transfer Station Cost Estimate for 4120T-TRANSFER- City of Greensboro Solid Waste Transfer Station
submitted on 6/12/2023 has been completed. The estimate meets the site -specific operations and appears to be appropriate.
Initial Review Comments: 20230612 - The Section appreciates the electronic form submittal for the closure cost
estimate for the City of Greensboro's transfer station.
Permitting Engineer's Review Comments: 20230712 - No concerns. Cost estimates appear to be satisfactory and match
the estimate in the submitted closure plan.
The Division of Waste Management - Solid Waste Section has reviewed and approved the provided cost estimate
required for establishing financial assurance for a transfer station. The cost estimate is provided for your use.
Approved Cost Estimate = $
At this time, you may work with your Finance Department Director and have the approved cost estimate incorporated
into the December 2023 Local Government or Capital Reserve submittal to the Section. Financial Assurance mechanism
templates, NC Rules for financial assurance, and inflation multipliers are among the pertinent information you can find
at the Section's Financial Assurance website: http://deq.nc.gov/swsfa. Should you or your Finance Department require
any assistance, feel free to reach out to Sarah Moutos at 919-707-8287 or Sarah.Moutos@ncdenr.gov .
Sincerely,
Sarah Moutos
Environmental Program Consultant
Division of Waste Management - Solid Waste Section
CC: Sherri Stanley
Diana Yitbarek
Tucker, Emily
CITY OF GREENSBORO, SOLID WASTE TRANSFER STATION
2023 COST ESTIMATE FOR FUTURE CLOSURE
ITEM
QUANTITY UNIT
UNIT COST
TOTAL COST
Mobilization/Demobilization (Max. 5% of the Work)
1 LS
$ 11,925.00
$
11,925.00
Pressure Washing
1 LS
$ 20,000.00
$
20,000.00
Leachate Disposal (Not Applicable)
1 LS
$ -
$
-
Leachate Collection System Decommission
1 LS
$ 100,000.00
$
100,000.00
Decontamination of System Components, Structures and Equipment
Decommissioning OWS Tank
Capping Discharge Points or Open -Ended Piping
Signage
1 LS
$ 5,000.00
$
5,000.00
Waste Disposal - Cleanup, Hauling, Tipping Fee
900 TONS
$ 125.00
$
112,500.00
Post -Closure Care (Not Applicable)
1 LS
$ -
$
-
Administration(including PE Certification
1 LS
$ 1,000.00
$
1,000.00
TOTAL CLOSURE
COST:
$
250,425.00
Note:
1. Transfer Station is capable of transferring a maximum average of approximately 900 tons per day of MSW based on an
eight -hour operating day.
2. The estimate is based on the cost of hiring a third -party and does not incorporate any salvage value that
may
be realized
by the sale of wastes, facility structures, or equipment, land or other facility assets at the time of closure.
ENGINEER'S COST ESTIMATE
`0%11111// j//
10,'
A�l /1
=; Q� 41 %
q�'7�
SEAL.
_ 051544
��111 111�
O b
Emily L. Tucker, PE
TS Closure Cost Estimate 2023 Financial Assurance