Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
5103_JohnstonLF_ConstrMtgMin_20230717
SMITH GARDNER ABBRESS TEL WEB 14 N. Boylan Avenue, Raleigh NC 27603 919.828.0577 www.smithgardnerinc.com MEMORANDUM Date: July 17, 2023 To: Distribution From: Pieter K. Scheer, P.E. DOCUSigned by: P 5B6B31996A674D7... �,� � Smith Gardner, Inc. RE: Johnston County Landfill - Phase 4A and Area 2 Closure Construction Meeting Summary — June 22, 2023 Attendees: See the attached attendee list. Meeting Summary: A construction meeting was held Thursday June 22nd to discuss the closure construction of the Phase 4A municipal solid waste (MSW) and Area 2 construction and demolition debris (C&D) landfill units at the Johnston County Landfill. The meeting began at 2:00 p.m. and concluded at approximately 2:30 p.m. During the meeting, the following items were discussed: Current Progress: Mr. Gonzalez and Mr. Barker provided an overview of current progress. Atlantic Lining Co. (ALCO) has installed the geomembrane and much of the drainage geocomposite on Area 2. Thane Construction Co. (Thane) has started placement of the vegetative soil layer (using soils from Borrow Area F1) on Area 2 and is also working on preparation of the south slope of Phase 4A including waste relocation. Carlson Environmental (Thalle subcontractor) is currently installing LFG wells in Phase 4A. Planned Activities: Thalle plans to continue preparation of the Phase 4A slopes and placement of protective cover on Area 2. Carlson Environmental will continue the installation of LFG wells in Phase 4A. ALCO will demobilize for 2 to 3 weeks and return thereafter to complete installation of geosynthetics on Area 2 and start installation on Phase 4A. Mr. Gonzalez provided an updated construction schedule (copy attached). Submittals: There are currently no outstanding submittals. Construction Meeting Summary - June 22, 2023 July 17, 2023 Page 2of2 Other Items: Safety/Coordination: There were no safety or coordination issues or concerns to report. Independence Day Schedule: No site work is planned Monday (7/3) and Tuesday (7/4). LFG Collection System Piping_ Subsequent to the regular meeting, Thalle and Archaea Energy discussed coordination of installation of LFG piping to connect with the newly installed LFG wells in Phase 4A. Next Meeting: The next meeting was scheduled for Thursday July 27th at 2:00 p.m. Attachments: Attendee List Updated Construction Schedule CC: Distribution: Brian Beasley, Johnston County Andrew Braswell, Johnston County Eddie Overby, Johnston County Reinaldo Gonzalez, Thalle Chris Haverstrom, Thalle Aaron Barker, Thalle Eric Kuehnel, Thalle Ryan Coward, Thalle Travis Ross, Thalle Bill Morris, Thalle Jonathan Warrington, Thalle Cooper Dalton, Geotechnics Donna Wilson, NCDEQ Amanda Thompson, NCDEQ CONSTRUCTION MEETING ATTENDEES NAME COMPANY/AGENCY PHONE EMAIL Pieter Scheer Smith Gardner, Inc. (919) 828-0577 x123 (Office) (919) 815-9377 (Cell) pieterfasmithaardnerinc.com Jesse is 5 rwi Cs►a d-Kcr 9�� �?.S- oS�-? x mo Sol - 3 3 S' - T S L g e_ �� C�t�.1Ao-D Tup.LLv (33 G) S- f Co - 277 t 2- rGowo l•� °�, 4ke'lle. Goy. Arc-vi O�ev1- 5 Ice elC'17 j7k2 may A I 1!;' (,� pG�ia �� 7� - 9 7--6 7Lq'2 �%I cY �ato`le JVCA Ir�l� Pf�S4Ci -)A A TL JG can gq& - 6 3 ! - o�e'v -.ef w, <�,'•"' , bm�s►tit/4g'7d41F7'7C- . coer �A�a�►. �a�kc.r ��al�� e�s�-����ati (v06-35"9- S yye Gh bar ker C4 Ale- . Conti, 33 6►,a_-4- �>cq��y �55 �FIALL� 111- Zoj- 3660 Johnston County Landfill - Phase 4A and Area 2 Closure ,2D23 Page 1 NAME COMPANY/AGENCY PHONE 7oy.77`i EMAIL :r',7bn eam i- r Johnston County Landfill - Phase 4A and Area 2 Closure ,2023 Page 2 Project => 22-384 U4 RL - Johnston County Landfill Phase 4A BASELINE - U4 6-21-2023 TASK filter: All Activities I Rot Date: 22-Jun-23 09:19 Data Date: 21-Jun-23 Duration General Conditions 387 20 Milestones 387 20 M1000 Notice to Proceed (13-MAR-23) 0 0 MVI1013 Substantial Completion (07-MAR-24) 0 0 M1035 Final Acceptance (27-MAR-24) 0 fl Total Start Finish Duration IySIC31 Float % % Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr ® � . � to+o - 02•F -5 13-Mar-23A 02-Apr-24 94.83% --- 024 -5 13-Mar-23 A 02 Apr-24 94.83% =W1024 13-Mar23A 100% 100% Notice to Proceed �13-MAR-23) -T 113-Mar24' 0% 0% ---•----- - --- ----•-- -••••---- -------- ....••-- -- --------- ut 7 —� 02-Apr-24' 0%0% ! 11-M4-23A, 5 bmittals S1000 51010 51fl15 S1035 Erosion Control Plan Geocomposites Manufacturers QC Plan Y� Geocomposite Installer Qualifications and Plan Geomembrane Manufacturer's Info/QC Plan 3 3 3 3 0 0 0 0 13-Mar-23 A 13-Mar-23 A 13-Mar-23 A 13-Mar-23A 15-Mar-23 i5-Mar,23 15•Mar23 15-Mar-23 100% 100% 100% 100%v 100% 100%° 100% 100% Erosion Cc Geobomp Ge000mp ntrol Pin Sites MVE site to nufactuaers QC Pion alter Qualifications an nufacturers Info/QC ! , } 1 i Plan - - _ - -- - ion: ; Georriem rane M' Gearirem S1040 Geomembrane Installers Qualifications/CQC Plan 3 0 13 Mar-23A 15 Mac,23 100% 100% ne Installers Qualifibationsl Plan 51085 HDPE Pipe Materials v� 3 • ` 0 13-Mar-23A 15-Mar-23 100% 100% HDP Pip Mateijils E S1050 Geotextile Manufacturer Info QC Plan _ I ^ 3 0 13-Mar--23A 15-Mar-23 100% 100% Geofextiie anufdcturer Info QC Plan ! 51080 LFG Extraction Materials 3 0 13 Nlar-23A 15-Mar•23 100°Io 100°Ie tFGxfra ion Materials :. - -- ___•_____ ---------•----------- - S1030 Geomembrane Manufacturer's QC Certs and Test 3 0 20-Apr-23A 24-Apr-23A 100% 100% omerrrbrane Manu cturers QC Certsand Test Data Data S1020 j Geocomposite Manufacturers QC Certs and Test Data, 3 0 S1025 Preconstruction Geocomposite Project Samples 3; 0 S1045 Preconstruction Liner Project Samples 3' 0 SA1000 Approval - Erosion Control Plan SA1010 Approval - Geocomposites Manufacturers QC Plan SA1015 Approval - Geocomposite Installer Qualifications and Plan �SA1035 Approval - Geomembrane Manufacturers Info/QC Plan SA1040 Approval - Geomembrane Installers Qualifications/CQC; Plan SA1065 Approval - HDPE Pipe Materials J _ SA1050 Approval - Geotextile Manufacturer Info QC Plan SA1060 Approval - LFG Extraction Materials T 5A1030 Approval - Geomembrane Manufacturers QC Certs and Test Data SA1020 Approval - Geocomposite Manufacturers QC Certs and Test Data SA1025 j Approval - Preconstruction Geocomposite Project Samples SA1045 Approval - Preconstruction Liner Project Samples Project Construction Mobilization & Borrow Area F1 MS100 Mobilization MS105 Initial Survey/LOD MS115 y Clearing and Grubbing MS230 General Progress Survey MS120 Install EC -Silt Fence MS170 Access Road F1 - EXCAVATION AND FILL I MS130 Install EC Skimmer Basin F1 I MS150 Install Culverts- E1, E2, F 10 0 10 0 10 0 10 0 10 0 10 0 10 0 10 0 10 0 08-May-23 A 11-May-23 A 100% 100% Geocofnposite A anufacturers QC Certs and TQst Data ; 08-May-23A 10-May-23 100°%. 100% PreconMruction Geocomposite Prbject Sampled ! 08•May23A 10-May-23 100% 100% PreconStruction Liner Project Samples ; 24-Apr-----23 -- ---- .... ..............---......-.L............---------.t•• .- - ?- --- - - 13-Mar-23 A 13-Mar-23 100% 100% Apprq I - E rosion Control Plan ' 13-Mar-23A 134Mar--23 100°% 100% Appro I - C eoconI.posites Mandfactur& QC Plan I 13-Mar-23A 13-Mar23A 100%. 100% Appr4 I - ocoropcede I nsta 116r QuarffH ations and Plan ; 13-Mar-23A 13-Mar--23A 100% 100% Apprc I ometnbrane Manufactures Infd/QC Plan I ; 13-Mar-23A 13-Mar-23A 100%[ 100% Apprq I - omel brave Installers Qualifcattans/CQC Plar ' 13-Mar-23A 13-Mar-23 100% 100% Appra l- •- OPE Pipe Materials - -•- • - - - -- ...............••-- -- -- - ---- ••--•--- - - - -- - - - I i otextjle Manufactuier Info CC 13-Mar23A 13-Mar-23 �100°% 100% ApprQ Phan I 1 13-Mar23A 13-Mar-23 100%. 10096 Apprd I- GE*action Materials 10-Apr-23A 24Apr-23A 100% 100% Approval-:Gwmembr, ne Manufacturers QC Certs aril Te It Data 10 0 21-Apr-23 A 24-Apr-23 A 100% 100% AppTo I-;Gebwmpo 'ite Manufacturers QC Certs and Tes Data 10 0 1 21-Apr-23A . 24-Apr-23A 100% 100% i 1�ppro I -IPR OrlStru ion Geocomposit� Project Sarrjples I 10 0 21-Apr-23A ' 24-Apr-23, 100% 100% APprovc, IPreconstruc ion Liner Project Samples ' MEMO i3 2W,3 191 11 13-Mar-23A 13-Mar-24 27.35% f 82 94 108 13-Mar-23 A 30-Oct-23 41.94% 30-Oct 23, Mobilization &Borrow Area ;F1 17 0 13-Mar-23A 31-Mar-23 100% 100% Mobiliza p I_______ - --..•.........;---•--• ---- -•- --• ---- -- --- - - - -____•-____ -- 10 0 13-Mar-23A 15-Mar-23 100% 100% ... .... ........ Initial urveylt .........r---------- 14 0 13-Mar-23A 03-Apr-23, 100% 100% Cleann and bng 1 132 150 13-Mar-23A 30-Oct-23 0%iT 0% General Progress Survey; l 4 0 17-Mar-23A 28-Mar-23 100%1 100% stall EC Silt Fen ! 12 0 20-Mar-23 A 17-Apr-23, 100%� 100% ss Ro d F1 EXCAII - tlON AND FILL t ----••-•--•--•---...-.---==--- - ......-.... 1 - •-------- --...-- - tall EC _ .. 3 0 28-Mar-23A 17-Apr-23, 100%1 100% ki mr Basin 1 3 0 29-Mar-23A 13-Apr-23, 100%' 100% toINKu[ve iE1„E2, F t TH/1 LLE T Page 1 of 3 CONSTRUCTION COMPANY A TULLY GROUP COMPANY Final A 24• Proj Project => 22-384 U4 RL - Johnston County Landfill Phase 4A BASELINE - U4 6.21.2023 Activity ID Activity Name unginai _lainrng Duration MS140 Diversion Channel 6 1 MS110 Install Construction Entrance 3 0 MS180 Access Road F1 - Diversion Channet 11,12,13 6 0 MS190 Access Road F1 - Stone placement 6 0, MS160 Excavate Basin F1 15 8 MS220 Excavate Remaining Borrow F1 90 90 MS210 Basin F1 EC Features 6 6 ? MS200 ECB and Revegetation 4 4 Area 2 — - 205 139 P250 Initial Survey 4 0 P300 Strip & Shape Correction Areas 6 0 P460 General Progress Survey 1 139 P310 LFG Vents (16EA) 6 0 P320 Strip Area 2 6 0 P305 Place Intermediate Cover 10 0 P315 �! Seepage Collection Trenches (As Needed) 4 0 P302 Waste Relocation 6 0 P325�^ Finegrade IC for Geosynthetics Install 8 0 P327 Install Geosynthetics 15 5 P312 Overexcavation & Backfill - Soil/Waste` 2 0 P330 Place Protective Cover 241 22 P335 Install Rain Gutters DP 61 452 31 31 P380 Exterior Toe Drain 14 14 P340 Install Rain Gutters DP 63 12 12 P360 DC 63 CD & DC 63 AB 7 7 P360 Install Rain Gutters DP 64 20 20 P370 DC 61 5 5 P410 Flex Growth Medium (FGM) & Revegetation - North 8 8 Side i P400 Aggregate Surfacing f 4 4 P390 Flex Growth Medium (FGM) & Revegetation - South 8 8 4 Side B605 Silt Fence 2 2 B610 Earthwork 10 10 B630 EC Features & Skimmer Outlet 6 6 B405 Silt Fence 2 2 B410 Earthwork 10 10 B420 EC Features & Skimmer Outlet 6 6 Area 4A — J 253 191 PQ50 Initial Survey 4 D P06Q General Progress Survey 1 191 Pi DO Strip Slope -Correction Areas 8 0 P115 LFG Wells - North (13EA) 10 a Pilo Intermediate Cover -Apprx 27K CY from F1 25 15 P105 Waste Relocation 20 8 P120 Strip North End 6 3 P195 Overexcavation & Backfll - Soil/Waste 1 1 TASK filter: All Activities Rpt Date: 22-Jun-23 09:19 Data Date: 21-Jun-23 -lysical 2023 2024 %Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 201 03-Apr-23A 21-Jun-23 83-33%' 0% ❑mrsion Channel t i -------- ------------ ---- --- -- - --- ---- iDApr-23A 12-Apr10o%j 100% Ins IEConst `onntran 17-Apr-23A 05-May-23 100°/0 100% Road F1 )r__stone tsion Channet 11.12,13 •_____• t ' .........._t.._. 19-Apr-23A 12-May-23 100% 100% - s� Road placennnt I 47 29•May 23A 30-Jun 23 46.67% 0% Excavate Basin F1 47 21-Jun23 24-Od-23 0%;L 0% I Gavots Remaining Borrow F1 184 03-Jul-23 10-tu323 0%� 0% Basin 1 EC Features 108 11Sep-23A 304M-23 0% 0°k I --- _t__ LCB and RE?vegetation - - --- , -- , --- -_---..___1___ _.__- l______ __ __J....... .__J_-_____._.-.d..._ ___..'__. __._ . . 53 21-Mar-23A 01-Jan-24 32.16..% 01 Jan-24,Area 2 21-Mar-23A 17-Apr-23. 100% 100% 11 Val Survey: I 17-Apr-23 A 28 Apr-23. 10G% 100% ;Strip Shape Came tan Areas 47 17-Apr-23A 01•Jart-24 0% 0% ; General Progress Survey ' 01 May23A 29May23 100% 106°ia LFG ts�16EA) •--- - - -•-• _--- - •--- �. -- - 02-May-23A 26-May-23 100% 100% StripAfe 2 } 03-May24-May-23 100% 100% lace Intermediate Cover 03-May-23 A 08-May-23 100% 100% ; S a e Collect on Trenches (As Needed) 03-May23A 05-May-23 100% 100% W t' Relocation 05-MayA 30-May-23 100% 100% Pneg -de IC for Geosynthelics lnstan - - - _ _._ ._... _. _.. .. __.L____ ..-. ... _. _... �._____.._._ �.. ____ _. __.. _... _. i._... ___ , 197 24 May 23 A 27 Jun-23 66.679° 0°k stall Geosy�ithetics 19-Jun•23A 20-1un-23 1.00% 100% Overexcavation,'& Backfill-SdiINV ste 47 2Wun•23A 24-Oct-23 8,33%a 0% ve Cover 47 19Sep-23 31-0ct-23 Oo�O 0% :Gutters DP 6j1 & 62 91 25-Oct23 13-Nov-23 0% 0% l ior Toe Drain _ i- i - ----- ...........} -L_. .—......... ----•--••- ---•--•' -----'------•---- - 7�%-- ai47 Q144ov23 16-Nov-23 0%j 0% ill Rain Gutteis DP 6391 14-NoV23 22-Nov-23 0% 0%C 63 CD & DC 63 AB 47 17-Nov-23 14•Dec 23 0% 0% Install Rain Gutters DP 64 56 17-Nov-23 23-Nov23 0% 0% � 1 63 17 fVgv 23 28 Nov23 0% 0%P x Growth Medium (FGM) & Revegetat n - iyor 47 15 Dec 23 20 Dec 23 0% Q°1a-- - - - - - -- Aggregate Surfacing 47 21-Dec-23 01,Jan-24 0% 0% - Flex Growth Medium {FG j & RI k. ;p'mmm1 19 Dec-23, Sediment Basin ;fib • �- 56 24-Nov-23 27-Nov23 0% 0% 1P 1. Silt Fence 56 28-Nov-23 11•Deo-23 0% 0% I rthwork------------ -' - - 56 12-Dec-23 19-Dec-23 0% 0% EC; Features & Skimmer Outlet T00!m0mI 14-Dec-23, Sediment Basin #4y 59 21-Nov-23 22-Nov-23 0% 0% Fence 59 23-Nov-23 06-Dec-23 0% 0%F!,�.ilt Earthwork t 23 14 De 23 0°/ 0% EC Features &Skimmer Outlet 59 07-Dec c- o 11 13-Mar-23A 13-Mar-24 24.48% ------ --- -- --- -- --__ -- �3 13-Mar-23A 17-Mar-23 100% 100% Initial Survey ' l0% -5 17-Mar-23A 13-Mar-24 0% 29-May-23 A 19-Jun-23 100% 100% Strip Slope - Correction Areas' ` 30-May-23 A 09-Jun-23 100% 100% L Wells - North 13EA ( ) - - -- - - - ___ __---- - _ .. -3 31-May-23A 11-Jul-23 40% 0% r - �.... -----•------------•- -- --•- - Intermediate Cover=Apprx 27K Cy from F1 t ` -5 01-Jun-23A 30-Jun-23 60%i 0% ste.Rela'cation T*North ` -5 05-Jun-23A 23-Jun-23 50%. 0% En; J 201 21-Jun-23 21-Jun-23 l 0%, 0% = cavalloTi&Backfll-SbillWaste P Page 2 of 3 CONSTRUCTION COMPANY ATULLY GROUP COMPANY 24, Arel I Progfe Project => 22-384 U4 RL - Johnston County Landfill Phase 4A BASELINE - U4 6.21.2023 TASK filter: All Activities Rpt Date: 22-Jun-23 09:19 Data Date: 21-Jun-23 Original I raining I Total Duration I I Float - ,,,�° Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr P225 LFG Well Borehole Abandonment 1 1 201 21Jun-23 21Jun-23 0% 0% �._...-------•--•-••----- I LE.Well Borehole Abandonment �. ---- -- •-- •--- -- - - -- --�- - - - -- - - -- - - -- - r_ P245 MiscAdditional Embankment - Phase 4A 1 1 201 21-Jun-23 21Jun-23 OW 0% I M"ss Additional Embankmenf -Phase 4A ~P125 LFG Tenches - North 10 10 -5 26-Jun-23 07Jul-Jul 0%1 0% LFG Tenches - North ; I P150 Interior Toe Drains - North 6 6 5 10-Jul17Ju1-Jul 0% 0% ' _. inter Toe Drain$ - North ' ' P135 ---.---------�__ _. LFG Wells - South (15EA) 12 7 T -3 13 Jul-23 A 20JUI-Jul 41.67%� 0% , LFG Wells -South (15EA) P155 Seepage Collection Trenches (As Needed) 4 4. -51 18-Jul-23 21Jul-23 _ I 0% 0% - : e' page Collect on Trenches (As Needed]: •------ S g -- --- ; I- -- - P160 Finegrade IC for Geosynthetics Install 20 20 3 20-Jul 23 16 Aug 23 — 0% 0% Inegrade IC for Ceosynthetics;instal P165 Install Geosynthetics 30 30 -5 24-Jul-23 01Sep-23 0%° 0% Install Gedsynthetics P145 LFG Tenches -South 10 10 -3 i 26-Jul-23 08-Aug-23 0% 0% LF Tenches -South ' P170 Place Protectove Cover 44 44 -5 31-Jul-23 L28Sep-Sep 0% 0% Place Prote�tove ver ; I P175 Install Rain Gutter DP 51 15 15 07,FWg 23 25 Aug-23 0% 0% I�sta i Gutt DP 51 - - - er : _ - --- - P152 Interior Toe Drains - South 6 6 I �ti5. 3 09 Au 23 16-Au 23 g- 9- 0% 0% nteRar Toe in,4 -South _ f I P215 of Vents Emergency Gas Relief Vents (2) ( 1 1 ' — 154 09 Aug-23 09-Aug-23 0% : 0% ; _ E rJ --- en-- Gas libf llent5 (2) _ ----•-- P140 — — Strip South End 4 -- 3; -_ - 3 14-Aug-23A 25Ju1-Jul 25% 0% I ' P205 DC 51 - 5 - 5 52 28-Aug-23 01Sep-23 0% 0% DC 51 P176 Install Rain Gutter DP 52 371 37 -5 28-Aug-23 17-0ct-23 0% 0% Instill - — Rat Guttef DP 52 -- -_ . - - -�-- `- - d Improveme is _ " P440 North End Improvements 12 12 52 -Sep 19Sep-23 0% 0% North P185 F�cteriorToe drain H 6 124 29 Sep-23 06�3ct 23 0°I° 0% k k riOrT� d n _______________________ P235 Revegetation - 36 AC 'i 7 107 29Sep-23 09-0t t•23 0°/° 0% ;: Revegetation 36 AC P177 Install Rain Gutter DP 41 24'� 24 -5 18-Oct-23 ' 20-Nvv23 0% 0% ;_ Install Rain Gutter DP 41 P210 1 DC 52 4 ; 4 : 321 18-Oct-23 __' T,23-0ct-23 _ — 0% 0% ._.._......;-----------s..........--^;------ - - - ' _ QC 52- •----•-----•-- � - - _ -- 2 . ---- - -- - Rain DI 65 i — P178 — _ Install Rain Gutter DP 65 15 15 -5 21-Nov 23 11-Dec-23 o 0 /° ° 0 /° tall Gutter ns u P430 -- T - Flex GrowthMedium (FGM) &Revegetation -North Si 6 6 81 21-Nov-23 28-Nov-23 0% 0% -- ------Growtedium (FGM) & Revegeti n - N S e , Install Rairj Gutter DP 66 P179 Install Rain Gutter DP 66 16 16 , -5 12-Dec-23 02Jan-Jan 0% 0%; P230 DC 66A 8 8 -3 12-Dec-23 ' 21-Dec-23 0% 0% ' 66A P240 DC 6 6 -3 22-Dec-23 29-Dec-23 0% 0°I° --- ,_•• - - -- - DC666 ------ - - P190 Flex GrowthMedium (FGM) & Revegetation -South 6 6 56 03-Jan-24 10Jan-24 0% 0°�° ------------------- -•-- _ - - --•-- - - -- ^- - ---J---- -; Flex Medl Growth 'unj ( M & ] tic geta ' Side P260 DC 67 5 : 5 -5 03-Jan-24 09Jan-24 0% 0% ;; DC 67 ; P270 DC 68A 5 5 -5 10-.Ian-24 16Jan-24 0% 0% DC 68A P280 DC 68B 5 5 -5 17Jan 24 23Jan-24 0% 0% DC 68B _ ..... P420 DC 5 - 5 5 24Jan24 30Jan24 0% — 17% ; ; :......_ •-•--__ .... ---_-•--- DC 69 _------__ _--•..--------------- P450 South End Improvements 12 12 -5 31Jan 24 15-Feb-24 0% - 0% ----------- a--_------ - - -- _.. ----•- --------- - South nd Imp o' menu P220 DC 65 �— I 5 5 -5 16-Feb 24 ' 22-Feb-24 0%: 0% 5 P290 DC 62 7' 7 ; -5 23-Feb-24 1 04-Mar-24 0%i 0% DC 62 P200 Aggregate Surfacing 7 7 -5 05-Mar-24 13-Mar-24 0% 0% ' ! Ag ate 5ui - Closeout, 4 as aProject � - - q2!}7 C100 — - Punchlist Corrections 10 10 -5' 14-Mar-24 27-Mar-24 0% 0% - -.. .. - -- - ---- -- - -- --- --• ---- - -- -- --- - -----_--- unchlk C105 Demobilize 10 10 -5 `. 20-Mar-24 02-Apr-24 0%, 0% Demo Page 3 of 3 ■ ArWAFrU i■iT.. ` CONSTRUCTION COMPANY This Page Intentionally Left Blank