HomeMy WebLinkAboutNCD980602163_20040209_Warren County PCB Landfill_SERB C_Change Orders 16 - 20-OCROC-?4 rev. 9-88 INSTITUTION: PROJECT: ST A TE CODE & ITEM : CONTRACT FOR: CONTRACTOR: i NCDENR STATE CONSTRUCTION OFFICE CHANGE ORDER NO. 20 Warren County PCB Landfill Detoxification ID#: 010440101A BCD Detoxification Shaw Environmental & Infrastructure, Inc. D OR Owner Request X CR Contractor Request D DR Designer Request D CC Concealed Condition D DE Design Error lB D DO Design Omis · 19 0 SC Schedule 1l 0 OT Other ~ J,1fl/ 200 Horizon Center Blvd, Trenton, NJ 08691-1904 :::= C. St, <Oa, , ... n. Under the terms of the Contract and without invalidating the original provisions thereof, the following ch ~ .· e i/~g; f} authorized for the change in contract amount herein set forth: (Description of change order attached) ocP 'Ff'fct 7Q,t Add new line item #26, "Additional work related to stockpiled clay cap material" to cover work directed by wn_r. A . summary of those costs and supporting documents are attached. 'P £, ::. _\ Reduce line item #12 to reflect final actual cost, reduce by cost remaining as of Application for Payment #33. The time of completion including previous orders is 973 calendar days and shall be unchanged by Q calendar days by this change order, for a revised contract date of completion of November 10, 2003. CONTRACT COST SUMMARY 1. Original Contract Amount 2. Amt. Of Previous Orders 3. Amt. Of This Order: ADD ADD $ 7,539,655.67 $ 6,133.72 Deduct Deduct $638,240.90 $ 0.00 TOTALS $6,658,000.00 4. Total additions lines 2 &3 $ 7,545,789.39 Minus Total Deducts: $638,240.90 $6,907,548.49 (Line 4 shall show the net amount to be added or (deducted) from the contract amount.) 5. Revised Contract Total Amount 6. The Owner certifies that the contingency fund balance after this change is $13,565,548.49 $ Fill in one copy only I certify that my Bonding Company will be notified forthwith that my contract has been increased by the amount of this change order, and that a copy of the approved change order will be iled upon receipt by me to my surety. ,,,.-0 ~ \~ "-kl ( ate) Shaw Environmental & Infrastructure, Inc. By: -------------~---(Contractor) 200 Horizon Center Blvd Trenton, NJ 08691-1904 Earth Tech Gary W. uke, P.E. Ptranager By: -----------------(Designer) J;tvni ?J,j&h f--PVAIK:.. _N_C_D_E_N_R ..... ,_D_iv_o_f W_a_st_e_M_an_a_.g.__e_m_e_n_t ___ By: ~~ /);. ~ (Owner) _S_t_a_te_C_o_n_s_tr_u_ct_io_n_O_ff_ic_e ________ B~-Z~?-~~--·_.1/ _________ _ (_ -----------------By: Other approving Agency (if needed) DISTRIBUTION: 1 original to State Construction 1 original to Owner 1 original to Board or Commission (if any) (Date) (Date) (Date) REQUEST FOR AUTHORIZATION TO CHANGE DATE:. December 4, 2003 STATE CODE: SCO#010440101A REQUEST NO.: 20 NCDENR Earth Tech PROJECT NAME: Warren County PCB Landfill OWNER: CONTRACTOR: Shaw Environmental & Infrastructure, Inc. DESIGNER: CONTRACT FOR: BCD Detoxification DESCRIPTION OF CHANGE: Add new line item #26, "Additional work related to stockpiled clay cap material" to cover work directed by Owner. Reduce line item #12 to reflect final actual cost, reduce by cost remaining as of Application for Payment #33. No change in schedule. REASON FOR CHANGE: Line 26 required to cover additional work requested by Owner due to fact that stockpile of clay cap material was found to be contaminated with PCBs. Line 12 reduction is possible since work is complete and final actual quantity was less than bid quantity. SUMMARY REVIEW OF CONTRACTOR'S ESTIMATE FOR TIME AND COST: (Attach Contractor's detailed cost breakdown of labor and materials). Add line 26 -Additional work related to stockpiled clay cap material Reduce line 12 -Liquid BCD Treatment with offsite recycle by 1,847.92 gallons@ $4.40/gal Total change order value: DESIGNER SUMMARY: 1. Schedule items affected by this change: None ADD DEDUCT ADD 2. Can Contractor mitigate the change without requiring a contract time extension? Yes 3. Will the change require a contract time extension for other contractors? No Which? n/a $14,264.56 ($ 8,130.84) $6,133.72 4. Are a'dditional costs indicated by reason of the time extension? No If so they must be included in 5 & 6 Below. CONTRACTOR'S ESTIMATE DESIGNER'S ESTIMATE 5. Estimated cost of change: ---'-$ _6,_, 1_33_._72 _______ _ 6. Estimated time extension field cost (if any) _N/_a _________ _ DESIGNER RECOMMENDATION AND CERTIFICATION: I certify that I have reviewed all aspects of this change order and have determined that it is in the best interest of the owner to have the work accomplished. I have also determined that the cost and time allotment are fair and equitable, and I recommend acceptance by the owner. Approved by: ~ ,,.-J ~ Title: Orroj ,:;;,h '1 t'. Date: _J_/_s~/6_4-~_ Warren County PCB Landfill Shaw E&I Project #827062 Dukefile: c:\mydocs\nclf\corres to E ~~) ~ ¼c~ w) J L \)~ b <.\.. ~ :P,µ' updated: 12/3/03 Costs for Change Order, additioi additional work requel us Task 1. Double handling of m, pending Task 2. Task 3. Task 4. thermal treatment, Ju! 484.29 Shaw labOI 79.12 Shaw labo: 563.41 Total Sha'.A 112.68 Shaw 20% 676.09 TASK 1 Ti 1t attached Keep rented backhoe idle from 8/6/03 order from NCDENR to stop work on placing material from Mt. Tilley in landfill pending resolution of their issues with USEPA until unit was decontaminated and taken off rent on 9/10/03. 6,747.68 Gregory Poole invoices CPRR00052947 and CPRR00053286, copies attached, cover total rental period of 8/4 to 9/10, 38 days. Unit was used by Shaw only on 8/4-5 before activity was placed on hold. Idle period was 36 of 38 days= 95%. Invoices total $7,121 .50, so idle time accounts for $6,747.68 of the cost. 6,747.68 Total Shaw direct cost 1,349.54 Shaw 20% markup on non-subcontracted costs 8,097.22 TASK 2 TOTAL CHARGE TO NCDENR Aiken & Yelle survey to estimate remaining volume of soil for thermal treatment, work requested by NCDENR as support for Change Order #13 912.50 See markup of Aiken & Yelle invoice 45616, dated 9/8/03, copy attached 912.50 Total Shaw direct cost 136.88 Shaw 15% markup on subcontracted costs 1,049.38 TASK 3 TOTAL CHARGE TO NCDENR Aiken & Yelle survey to estimate remaining volume of soil for thermal treatment, work requested by NCDENR as support for Change Order #18 1,012.50 See markup of Aiken & Yelle invoice 13168, dated 10/9/03, copy attached 1,012.50 Total Shaw direct cost 151.88 Shaw 15% markup on subcontracted costs 1,164.38 TASK 4 TOTAL CHARGE TO NCDENR Task Sa. Aiken & Yelle survey to mark max elevation at which to place material from Mt. Tilley in landfill to comply with USEPA 15 ft minimum cover requirement. I Task Sb Aiken & Yelle survey to confirm "as-built" locations of placement of material from Mt. Tilley in landfill to comply with USEPA 15 ft minimum cover requirement 1,050.00 See markup of Aiken & Yelle invoice 13241 , dated 11 /21 /03, copy attached 1,050.00 Total Shaw direct cost 157.50 Shaw 15% markup on subcontracted costs 1,207.50 TASK 5 TOTAL CHARGE TO NCDENR Task 6. Paradigm Laboratories analyze 4 soil samples for PCBs, same day TAT, work requested by NCDENR as support for Change Order #13 1,200.00 See Paradigm invoice 23091501 and lab reports, copies attached 1,200.00 Total Shaw direct cost 180.00 Shaw 15% markup on subcontracted costs 1,380.00 TASK 6 TOTAL CHARGE TO NCDENR Task 7. Paradigm Laboratories analyze 2 soil samples for PCBs, same day TAT, work requested by NCDENR as part of Mt Tilley post-excavation confirmation 600.00 See Paradigm invoice 23102404 and lab reports, copies attached 600.00 Total Shaw direct cost 90.00 Shaw 15% markup on subcontracted costs 690.00 TASK 7 TOTAL CHARGE TO NCDENR TOTAL CHARGE TO NCDENR FOR TASKS 1 to 7 14,264.561 MT. TILLEY EXCAVATION LABOR DETAIL 7/15/2003 WBS# 02900901 WBS# 16200100 Equipment Used Dave Ditcher 8 Albert Scott 3 9 Cat 320 excavator Delmar Kinq 3 3 L90 loader Dave's time charged today was actually combined effort of Dave and Rick to remark grids to prevent overexcavation 7/16/2003 !Albert Scott 4 !Cat 320 excavator I 7/17/2003 Albert Scott 12 Cat 320 excavator Delmar Kinq 4 L90Ioader 7/18/2003 !Albert Scott. 5 IL901oader 7/25/2003 Dave Ditcher 1 Albert Scott 1 9 Cat 320 excavator Thomas Wilson 1 9 Volvo A-30C truck 565005 Shaw Environ & Infrastructure Project Transaction Detail Report by Cost Code RPM0S0-06/107 Dept/Proj. Project: .827062 NC DEPT OF ENVIRONMENT AND 827062 NC DEPT OF ENVIRONMENT AND Duke, Gary W. Supervisor Client: 00956837 1277440 NC DEPT OF ENVIRONMENTAL -WAR Project Class: Host Dept: CFP Client -Fixed Price 5403020 South Construction Contract#: Cost Code Description Cost Type 02900901 E&S Changes -Field Cost Ditcher, David A. 9111 ST **** Llll General Superintendent Ref# 00956641 BCI# 80873937 Seq# 000-001-001 GL Date 07/18/03 Sub-total 5403161 02900901 E&S Changes -Field Cost 9111 King, Delmar ST L041 Environmental Technician III Ref# 01207869 BCI# 80873938 Seq# 000-001-001 GL Date 07/18/03 02900901 E&S Changes -Field Cost Scott, Albert J. 9111 ST **** ****** ******** L061 Equipment Operator III Ref# 00957859 BCI# 80873939 Seq# 000-001-001 GL Date 07/18/03 Sub-total 5513510 Sub-total 9111 Sub-total 02900901 Prov Dept/ Gov' t Pool Service Date Document/ Subledger 5403161 07/15/03 T2-59602-3007. 022 5513510 07/15/03 T2-59602-3007. 022 5513510 07/15/03 T2-59602-3007. 022 ********** Sub-total 827062 NC DEPT OF ENVIRONMENT AND Grand Total **** End of Report**** E C 4 4 4 Page Number 4 Date 7/30/03 From Date 06/01/03 Thru Date 07/25/03 *** Service Date*** Planned Start Date: Planned Completion Date: Actual Completion Date: Quantity UM 8.00 HR 8.00 HR 3.00 HR 3.00 HR Direct Cost$ 378.05 378.05 45 .11 61.13 03/01/01 03/01/02 Total Cost$ 484.43 484.43 58.79 79 .14 6.00 HR 106.24 137.93 14.00 HR 484.29 622.36 14.00 HR 484.29 622.36 14.00 HR 14. 00 HR 484.29 ----~ ~ 622.36 622.36 Revenue ~ t9 f --- 565005 Shaw Environ & Infrastructure Project Transaction Detail Report by Cost Code RPM080-06/107 Dept/Proj. Project: .827062 NC DEPT OF ENVIRONMENT AND Supervisor Client: 827062 NC DEPT OF ENVIRONMENT AND 00956837 Duke, Gary W. 1277440 NC DEPT OF ENVIRONMENTAL -WAR Project Class: Host Dept: CFP Client -Fixed Price 5403020 South Construction Contract#: Cost Code Description Cost Type 02900901 E&S Changes -Field Cost 9111 **** Ditcher, David A. ST Llll General Superintendent Ref# 00956641 BCI# 81066684 Seq# 000-001-001 GL Date 08/01/03 Sub-total 5403161 0290~1<£&S Changes -Field Cost 9111 **** Scott, Albert J. ST L061 Equipment Operator III Ref# 00957859 BCI# 81066686 Seq# 000-001-001 GL Date 08/01/03 Sub-total 5513510 02900901 E&S Changes -Field Cost 9111 **** ****** ******** Wilson Jr., Thomas W. ST L032 Environmental Technician II Ref# 01306634 BCI# 81066685 Seq# 000-001-001 GL Date 08/01/03 Sub-total 5513511 Sub-total 9111 Sub-total 02900901 Prov Dept/ Gov•t Pool Service Date Document/ Subledger 5403161 07/25/03 T2-59654-441.0 022 5513510 07/25/03 T2-59654-441.0 022 5513511 07/25/03 T2-59654-441.0 019 E C 4 4 4 Page Number 5 Date 8/06/03 From Date 07/26/03 Thru Date 08/05/03 ***** G/L Date***** Planned Start Date: 03/01/01 03/01/02 Planned Completion Date: Actual Completion Date: Quantity UM 1.00 HR 1.00 HR 1.00 HR 1.00 HR Direct Cost$ 47.25 47.25 20.38 20.38 Total Cost$ 60.54 60.54 26.38 26.38 1.00 HR 11.49 15.09 1.00 HR 11.49 15.09 3.00 HR 79.12 102.01 3.00 HR -----~ ---------------~ 102.01 Revenue ~1 x u'-f -- , J\s\L -i_ FROM.: SHAW_ENUIR. INC [ount~,NC FAX NO. 252 257 4218 De c. 03 2003 03:56PM P2 Bill TO INVOICE Please llerl1il To; PO Bo~ 60ll57, Chariot\e, NC 26260 Federal Taxpayer !CJ. 56-04873"1 l ·SHIP TO · SHAW ENVIRONMENTAL, INC . , ROUTE 4, ,BOX 426 '.WARRENTON I NC DIRECTIONS ARE ATTACHED 27589 0426 ~·Jlli;y.rt)ci:·4,,1iJfiiici~-·;,:;;;,:,,,:,.,f\c ::ttii:v.clJO§:,: A<tt.::':':=i:=:':' ,,,,,, ·, ·: · R:,;~:i';,:,,,:,:,,:-::::' ,,~·~:· ... · ' ,. ,· · Ir':-' · · ; CPRR0005294 09 -04-03 DAV E 1 ~'?§C ,~w:c ... Ng·:: · .. ·. ·':: ... ,, ... ,: .... ;Q.OC .. .::>A~'·: -~2S~-" ;:,::: ·:,:::-:::::::~: •. <n:•··~•::•:;••·•··::•sli(t?~'"'';jl(,;,·-: ... :.:-::.:'.: ··;,:-:;;:;::::.:;::·, =~=ii"'-" li;:;:}tt,...i'i1:. I R24 l30 07-02-03 10 ALAN/RALEIGH 2119800 756E,-l [·:/'l\lf:AKE\,,;E:,:::,:,:::,:: ,t:':t=;;_.M . · .1:t::::;:;:,:'?=:~::=:::,:,:::,;::(::: :t,t:0'::s:::,:,•\,;;e"=:SE~l~?NlJMBE:ff:::':ei':iH'.i::\':'.::':f::;\fi\:j ",/eQUIJ?.MElll: :::NUMSER::',:?f' lfM~!:l?lt,:R AD G:::::,:,:;\1'/f;:: ;:tfflM'ACA:;:EO;;N:o ;l ;{ff i AA.. 320C/HYD PABOOS30 53. 0 I · 00020 8 !!.0 0 t2@K"'.nr.Y ..... ,.'·.·'"'·"'~-=-'·t~~-·-··'·'·~~--.q:r!!;ruf :,:: ::: ·,-,'''-''. ;·,:c.··,:,: •. ;/,:,w1F,·.':,:,;:,.=·:,···, .. _/ ·;:, .-.-.··_·.-,· ·."-::'° · ·:.-,nE$nR1P.no.~ .. :: : ~,~,.,,::,, ·:r':: ·.:.-:.: · . ...:: ::: :+.:: :' · .•. vm:r:,emca~, ,~,~;,,=,~-,~{",' "·:"'; ·,:-:,eSlri:.liJSia:a:.,:., :_,.,, · ::.~~,_::..--:;: ]. . 0 CUSTOMER CONTACT: DAVE ********~***************** INVOICE DUE UPON RECEIPT *********************•·••* EQUIPMENT RENTAL CATERPILLAR, INC ID NO: 00020840 0 ENVIRONIVINTAL CHG FROM 08/04/03 THRU 08/31/03 MODEL 320C/HYD SERIAL NO: OPAB00530 PIN: "-CAT0320CVPAB00530;- NC -STATE SALES TAX COUNTY SALES TAX ----···•--··-·------=----.---- AMOUNT 5000.00 3.00 225 ,C1 C 125-0C 535~. '.)0 TERMS: Machine Sale an~ Rental hwo·ices are due upou rec1?ipt of invoice, all other invoice - terms arc nr.t JO days from date o~ invoit~. A-servir.e charge of 1,5%.per montl\.i18% 11er annum) Will be pusted clirer.tly to your rrio,ittily s.tatilment i(11aymer.t not received within terms, Pa.ts returned camwt be accepted without prior Authorization and thP-u $uhjsct to' handling charyes, Cl~im tor .errors or 1l,1111r1111is must.be milde within 10 days. No ,et.urns accepted without invoice PAY THIS r--_--. 1-----------,----------·--AMOUNT .. CREDIT n111111Jer. . . . We _can Emi,:il ,,niVor Fa.,: your Invoice~·!'. Please, ctill us ar (919)890-4223 to begin today. . ' f J • FROM : SHALl_ENUIR. INC [ount~,NC rnx No. 252 257 4218 Dec. 03 2003 03:56PM P3 -',e_g_ory Poole BILL TO -----------...,,------'------------- 1 NV O ICE Plr.;,c;,:, R,:,mit To: PO Box 60457, Ch;-,rl.,tte, NC 2S2GO F;:d;:r.,1 T:>xpaye, Id. 56-048731 l SHIP TO SHAW ENVIRONMENTAL, INC ROUTE 4, BOX 426 WARRENTON, NC DIRECTIONS ARE ATTACHED 27589 0426 CPRR00053286 09-ll-03 2119800 DAVE .-.. .-::\·ps:Q:• •.: : <w-:::::::;::;::;:::::::::::::;:::: :;::::;a ·:':' .• J\.'liEs:is::::,,,,::,~:: •::::;,::p,-c;;::c:':';' t::•;:1:llc~;;:•;;;•:· ;::;:;•;• '. R21l30 07-02-03 10 .ZUJ.AN/RALEIGH •··::,.,l\n:ARE,.:.:::.:.·.;.'.•.:,:.:.:·:::.:.: --····· .. :. ....... , ~ • . :27: •.. :.··•. ;.::.:.: ....... , , ..... ,.,.,.,,:,., ..... , ...... : ..... se1:1t'°'t. .• t11.UMB.e:a .• ,.:.i, ... ;.,:,.,.,, .. ,.1,, .•.•...•. , ....... ,.. ,., .... En · Ui'cM A.A 320C/HYD PAB00530 00020840 r-"'.:i:.-.:;/(1'°'{}.,;;: ,::, •.. ,::: •• In .. ·:.:•:'..:':·.:.:::::: :::·.:: •· ·:·:·.·. T:f.f(II:::::: :.::::.:::::.:.·:::.:::::::.!:.;:::::\N!IL::.:::'.'.;:.;:::.::::'.::·:;::::.:: ••• ::.:: ::;·.L:.::])ES.~lf.lT©N':t.;!.::.::::::.:: .. ·:x.: ·.·:;.,-,.:· ;) .,·. ill . '. .... Gf.%~:i.t~;;.:::-.: •• ~i.:~~::;::,;%;:•~-:-E~C:'f:ENSIOM~·"'l h,\?:~< 1.0 1.0 CUSTOMER CONTACT: DAVE ************************** INVOICE DUE UPON RECEIPT ************************** EQUIPMENT RENTAL CATERPILLAR, INC HYDRAULIC EXCAVATOR FROM 09/01/03 THRU 09/10/03 MODEL 320C/HYD ID NO: 000208400 SERIAL NO: P~..B00530 FINAL RENTAL BILL ENVIRONMNTAL CHG PIN: *CAT0320CVPAB00530* NC STATE SALES TAX COUNTY S.ALES TAX 1650 .. or; 3.0J 74.25 41. 25 --------------,-,-----~------------------.--------,------------ 1 ERMS: M<'lchine Salo and Rental Invoices are due upon .receipt of invoice, ·1111 otlier invoice · · terms c1r~ 11ec 30 days from date of. invoice ... A service charge of .1 :5% per month ll'!iOfo p·er a,mum) will be po~ted dire~tly to your monthly statement'if payment no.t received lll(ithin terms. Pam returned cannot be ·accepted without prior Authorization and then suhjec.t to hillldling charges. Claim for ·errors or damagss must be made within 10 days. No returns accepted without invoice PAY THIS AMOUNT AMOUNT .CR.EDIT 11u,nber. · · · · · · · · · · We .can E,,;_~iil andJ,j,: I•t1xyour11rvoic~s! Pfeaj,·e ca/[ usat (9]9)890-"1223 to begin today. Customer Copy · l768.S.0 . ./ Aiken & Yelle Associates, PA . 3755 Benson Drive Raleigh, NC 27609 Phone: (919) 877-9992 ■ILLTO ShawE&I 200 Horizon Center Blvd Trenton, NJ 08691-1904 ATTN: Bill Gallagher Dl!SCRIPTION \ ~~'¥-. ~ / Invoice DATI! INVOICI! # 9/8/2003 45616 DUI! DATI! 10/8/2003 Payments not received by due date are subject to a 1.5% per month finance charge .. PllOJl!CT PCB Warren County QUANTITY RATI! Locate Pin Location For Clean Soil Two Man Field Crew ~b.~ -t--:;. ~1)1<\h,,~4'5 I)~ vV>li'I ,_;,~'I) ~"\-. 85.00 382.50 Load Pin Location Fax Drawing To Job Site Survey Technician \'I~ '-'K..l> !S<::> -~ -s:.-.,~""--~ ~ Topo Of Landfill (9203 Of Existing Conditions) Two Man Field Crew Cale Volumes of Remaining Untreated Material, Fills to Existing And Proposed Elevations, Send Report to Site Professional Land Surveyor 1 60.00 60.00 5 85.00 '¥-"-U..'>-X~•<.~ ~ U'i.t:-\~ /"Ti;;. 'r!,Q._',)I, <'t°(.,',,\ .>~ (..\;q,lN1'~ () ~X~ ~ \~ ' ~" "'-\ °' \ l.... .. t_; 'Q . 6.5 75.00 487.50 Total $1,355.00 61, /4 -7~· ~L/ ~ '---P-ay_m_e_n_ts_,c_r_e-di_ts ____ $_o_o_o__, Balance Due $1,355.00 Aiken & Yelle Associates, PA 3755 Benson Drive Raleigh, NC 27609 Phone: (919) 877-9992 BILL TO ----•·"•·---------•····--- ShawE&l 200 Horizon Center Blvd Trenton_, NJ 08691-1904 ATTN: Bill Gallagher l)l'lSCRIPTION ---·······•-·- Locate Locations of Flags and Clean/Unclean Materials Survey Technician Two Man Field Crew Recalcuated Volume Studies -t)~,h l.'li.. 7\.'\V\~ Professional Engineer Professional Land Surveyor Survey Technician T • d BL.88-L.L.8 rBTBl 1 ln'voice Paymeuts not received by du1· date are subject to 11 1.5% per month fin,mce charge .. QUANTITY 1.5 3 1.5 \ C\ , AMOUNl" 60.00 ... D2000 90.00 \ ~ \ Cl 990.00 ~ 95.00 f 42.50 75.00 Sl . s 22s.oo 60.00 90.00 Total $1,567.50 Paymenw/Crediw $0.00 Balance Due $1.567.50 dsE :20 EO 80 -:i.oo Aiken & Yelle Associates, PA 3755 Benson Drive Raleigh, NC 27609 Phone: (919) 877-9992 ■ILLTO ShawE&I 200 Horizon Center Blvd Trenton, NJ 08691-1904 ATTN: Bill Gallagher Dl!SCRIPTION Locate Elags Within Landfill and North of Pit (2 Mobilizations) , ~~ ~ h-\...'if-,:>...r- Two Man Field Crew "- Data Adjustment And Forward Data To Site Survey Technician ' \~s~~ S~ LSb Invoice DATe INVOICI! # 11/21/2003 13241 DUI! DATI! 12/21/2003 Payments not received by due date are subject to a 1.5% per month finance charge .. PROJl!CT PCB Warren County QUANTITY RATI! AMOUNT M ~~ ~ ~ ~· Q. "'¥-. ~~")I.... 't ~~"' S>o.1 \ o . .., \ ,-1 10 90.00 900.00 2.5 60.00 150.00 \.....o t.fii\;:..,::, Total · $1,050.00 Payments/Credits $0.00 Balance Due $1,050.00 Duke, Gary From: Duke, Gary Sent: Friday, September 12, 2003 5:08 PM To: Pat Backus (E-mail); Pat Backus (E-mail 2); Jim Cloonan (E-mail); John Funk (E-mail) Cc: Ditcher, David; Bill Gallagher (E-mail); Dennis Jones (E-mail); Rob Holland (E-mail) Subject: Lab results Batch 218 was 130 ppb Untreated soil samples taken by EarthTech were Pole Barn, 310 ppm LF1, 740 ppm LF2, 220 ppm LF3, 180 ppm Page 1 of I I just spoke to Pat so she has this info, Paradigm also faxed results for ET samples to John Funk about half an hour ago. You may notice that there was no spike recovery on ET samples, that's because spike was 100 ppb and so was lost in the dilutions. Paradigm did not show units for the spike so I had to call to confirm that this was indeed the case. Good news all around, the sample that needed to be low was, the 4 that needed to be high were. (Jary (J)ukf Gary W. Duke, P.E. Shaw Environmental & Infrastructure, Inc. 200 Horizon Center Blvd. Trenton, NJ 08691-1904 phone (609) 588-6373 fax (609) 588-6300 work schedule 'A' 9/12/2003 f aradigm Analytical Labs, Inc. r. 500 Business Drive . Wilmfagton, NC 28405 · 910-350-1903 . i MAIL TO: !'sh~~ Envir~n~~~t~T~ NC ·. ! Route 4 Box 426 · . i Warrenton, NC 27589 Atten: .Dave Ditcher I I I '~~"-l Invoice l DATE I INVOICE NO. : 9/15/2003 23091501 '---'----~----'--'---'------·- f . ~~;EN·T·~~OJECT . -····-~·-~--····· ··_···_·· --·····-··--·· i Pi·oject ID: 827062 . I . Sample ID'.s: . .. . . · WCLF-PB-1 , WCLF-LF-I, WCL.F-LF-2 WCLF-LF-'3 ' I I .... _J . ' --, I i . ' P.O. NO. TERMS . DUE DATE. LAB PROJECT NO. I -----·--··' •·······-·~-----+------+--------.I See Above ,-·-.. ·---·-·-.. -DESCRIPT!ON i ...... · .... ··-· ·····••~····:·••······ •··-.. , ........ _,,_ ................ -----...... . : PCB's by 8082 ., Son.ication -Same Day Rush I . ! ' i i Thank you for your btisiness. .. '' ... cd Wd£p:10 £00c 91 ·das Net 30 10/15/2003 G515-521 . . ! QTY --7,'-,-·.--U-N-IT_P_R_IC_E_·..._~--A-M-;~·~~--I. ! ······-··· . ···1 4 300.00 1 ;200.00 ; · I . .\ I I I ...... ..... ......... . _ ... !. ···--· .. ····• ... ·-· ~~a~---$1,200.00 Sep:12·03 05:0Bpm . From,.PARADIGM LABS 9103501557 T-881 P.02/06 F-163 r~u1u1,.1. n1,.nJ..J1,&.1."'"'"' .. ,a..,, ..... '",...,.,,""""''·----.. ---, -- · ------.\ Client Sample ID: WCLF-PB·1 Client Project ID: 827062 Lab Sample ID: 80496 Lab Project ID: G515-521 Matrix: Soil Compound Aroctor-1016 Aroclor-1221 Aroclor-1232 Aroclor-1242 Aroclor-1248 Aroclor• 1254 Aroclor-1260 Surrogate Spike Recoveries TCMX Comments: BQL "' Below Quantitation Limit NA = Not applicable, surrogate diluted out. Results for PCBs by EPA 8082 %SOLIDS: 83.9 Quantitation Limit (ug/KG) 41000 41000 41000 41000 41000 41000 41000 Spike Added 100 ?\S~ Date Collected: 9/11/03 Date Received: 9112/03 Date Analyzed: 9/12/03 Analyzed By: CLP Dilution: 500 Spike Result NA Result (ug/KG) BQL BQL BQL BQL BQL BQL 310000 Percent Recovered NA Reviewed By: L N.C. Certification #481 S.C. Certification #99029 Sep-12-03 . 05:0Spm · From-PARADIGM LABS Client Sample ID: WCLF-LF-1 Client Project ID: 827062 Lab Sample 1D: 80497 Lab Project ID: G515-521 Matrix: Soil Compound Aroclor-1016 Aroclor-1221 Aroclor-1232 Aroclor-1242 Aroclor-1248 Aroclor-1254 Aroclor-1260 Surrogate Spike Recoveries TCMX Comments: BQL = Below Quantitation Limit NA ~ Not applicable, surrogate diluted out. 9103501557 Results for PCBs by EPA 8082 ¾SOLIDS: 87.7 Quantitation Limit (ug/KG) 47000 47000 47000 47000 47000 47000 47000 Spike Added 100 T-881 P.03/06 F-163 Date Collected: 9/11/03 Date Received: 9/12103 Date Analyzed: 9/12/03 Analyzed By CLP Dilution 500 Spike Result NA Result (ug/KG) BQL BQL BQL BQL BQL BQL 740000 Percent Recovered NA Reviewed By. L N .C. Certification #481 S.C. Certification #99029 .. Se.p-12-03 . 05: 08pm , From-PARADIGM LABS I Client Sample 10: WCLF-LF-2 Client Project ID: 827062 Lab Sample ID: 80498 Lab Project ID: <3515-521 Matrix: Soil Compound Aroclor-1016 Aroclor-1221 Aroclor-1232 Aroclor-1242 Aroclor-1248 Aroclor-1254 Aroclor-1260 Surrogate Spike Recoveries TCMX Comments: BOL = Below Quantitation Limit NA = Not applicable, surrogate diluted out. 9103501557 Results for PCBs by EPA 8082 %SOLIDS: 87 .2 Quantitation Limit (ug/KG) 8800 8800 8800 8800 8800 8800 8800 Spike Added 100 T-881 P.04/06 F-163 Date Collected: 9/11103 Date Received: 9/12/03 Date Analyzed: 9/12/03 Analyzed By: CLP Dilution: 100 Spike Result NA Result (ug/KG) BOL BQL BQL BQL BQL BQL 220000 Percent Recovered NA l:• . •; Reviewed By,~ N.C. Certification #481 S.C. Cenification #99029 Sep-!2-03 05:0Bpm From-PARADIGM LABS 9103501557 ..... "' .......... _ ... __ ._ ..... ··----------- Client Sample ID: WCLF-LF-3 Client Project ID: 827062 Lab Sample ID: 80499 Lab Project ID: G515-521 Matrix: Soil Compound Aroclor-1016 Aroclor-1221 Aroclor-1232 Aroclor-1242 Aroclor-1248 Aroclor-1254 Aroclor-1260 Surrogate Spike Recoveries TCMX Comments: BQL : Below Quantitation Limit NA = Not applicable, surrogate diluted out. Results for PCBs by EPA 8062 %SOLIDS: 87_6 Quantitation Limit (ug/KG) 8300 8300 8300 8300 8300 8300 8300 Spike Added 100 T-881 P 05/06 F-163 Date Collected; 9/11/03 Date Received: 9/12/03 Date Analyzed: 9/12/03 Analyzed By: CLP Dilution: 100 Result (ug/KG) BQL BOL BQL BQL BQL BQL 180000 Spike Percent Result Recovered NA NA .. Reviewed By· L . N.C. Certification #481 S.C. Certification #99029 PARADIGl\f ANALYTICAL LABORATORJES, INC. 5:',00 Business Drive. Wilminglon, NC 28405 Phone: (910)-350-1903 FAX: (910)-350-1557 Chain-of Cuslolly Rccon.J & AnalylicaJ Request Client: Er"'e,T /Jru,.,,~ Project ID: 8'-,. 7o I~ Date: JI T-r[1l-0J Address: RT 'I Bv.)( '/:J-6 Contact: ~>l Jl,-0 (,.J..J Turnaround: s11~e. P!iy TAT COC# __:; . i ( : I ,-.~ U> a, '<J . !. , ~ Page 1 of_}__~ Jvi~/d~ ~ Report To: Er-Ne iI ~ ~ -Af: f .fJ d )(. ~ ;-6 ~ Address:"-'",.,..e..7°"1,vc,, ,-JS-8'1 Phone/'lS-~1-S7 /8'/d JobNumber:_______ w,,,t<&-t'.1f.•C .1JS ~ Quote#: ________ Faxe,~:,;; 7 'I'>-1 S: P.O. Number: _______ invoice To: 5 /-1 {J W E + I ~ .-=----------r-----r---r----r------------------------------------=--------> I I I I I I Analyses I Comments: ~ Preservatives SampJe ID ~~a·· -PB -I wcJ.f-Lf· I w<-lf-/J -,. lwc.l}_ • L f -J Date I Time IMalrix \J v 1,, I I fcp1d) 1,r:10 lso) ,, / II S,1>To) IS"~JS' ft1,l / -·-,;-·-. ~ cl ~~ oo Q.. Ve ✓ . Please spedfy any special reportiDJ:l :=, · requirements ~ U> ~JI 5n,.._,J,T pre,, 7Y'C/'17c.,.... TJ..,....., S"(.I Pl',,.., P( D 5Pr.t lll'y T!Jf -'i t...<c. ✓ -I I I I I I I I I is:0"'; ficJ>h~ c,-J.,-,.,1;·.>f\J O,v/"t , !~J!To) l5:'/f' fql / ./ I II 1--w[":_fJ t1) lf:So ~(J,) ✓ ✓ I I r~,+ +o: ~ I ----------= U1 --------·l-----l----+---l-+--1--+---1-1 I I 1--~-1--+-----+-~-I ~ct),-1 ~i-...J\(.. __ _ E"c.r-\¼-\t:(.\.\ ~\~.\~ 1.-, U1 -.a --• --··--•---·----1-----+--~--+---l---t--I J~Tl,-.1.cFr..ci,..,k (B l"<.d·"''"'"~ I<'-. -, _____ I ------l----·l----l--+--+--+--l-_.,__-~_____.-----l--1----+---l----1---.1.---I n;., )( q J 'I S"J -4 (:, 'l.. ", -cf --t I CD CD -------1--·---+ I'--+--+---+--I I I I 1------1---1---11-----------a ✓-ic:--/e::-e: 2 / __.,, ~ ------11---1-----'-I I I I I I I I 1-~--.---+---+---1-I-_J,,2-.:/(7~ / --~-· ~ 1./'J 1' Re1inquishe~,. Date Time Receh·ed ll~• Dale Time Temp;rature State Certification Requcstetf -~ ·~ .-1'-:f.~.'.",; J)JJU, J(,?0 •. I '. r(,/1!J;•· ?../J. ~.3tJjY-I-c __ N(' ____ SC~--O!hcr -·--(;' ---· -·--· __ ,_. ·-____ i ___ -, ------+---------4--------l SEE REVEHSE FOR r1•..--:n" .• c, ., "'''' .,._., .... ,,. \. ,, .•. ,..,, ... ,_ FROM SHAW_ENVIR. INC [ount~,NC 1aradigrn Analytical Labs, Inc. · .5500Business bi:-ive Wilfoi11gton, NC 28405 S)JQ.:350-1903 Atten: Dave Ditcher FA>< NO. 252 257 4218 Dec. 03 2003 03:57PM P4 Invoice ,-~·--······· .I ...... ····-- ! DATE. . j INVOICE \10, i· .... i ....... . · f 10/24(20.03 [ · 231 02~04 ..... ' . • -~-.... -:t_ ... •--:.-· ·-····, . -· · ... -···-·····~· --,--,-'--....... ·. ·(. : :: ... · . ....,;'.-,-.. --,-.-~ .. --:,..,..,· .....,....~"--,~'--'----"--~ ____ P .O. NO. • . TERrvis_·. ·._ •. --'-. --+·-··-'-D'-UE_._P_AT_,.l::~•;c-..,..• ·•~-'·.-LA-.. ·.·.~~P~-~J-~~T~NO~ ·SeeAbove ·Net30 :: ·102ihoo3 ;°,i G5f5-57·8 I · • oEScR1P_1_1o_N_· ·-----·--~·.-. :_ ......... __ 0_1Y--,-•._· _ .....•• ·--~-__ :_~_~:_·· ·._ ..... _ ... -'--::-.... · __ · .. _ .... -!-.. _·-·_-···_•··_---,-_ I .PCB·;~ by 8082~ Sonication -Same Day Rush · 2 ·. ·. ··. 300:0i) •· · 600:00 I I ' I f--·-----..... . I Thank you for your business. I . . .· l ••.•... " ·········-·~--------·-··-·-··· .. ·•······ .. -········ .. i Total·. I · J/. (t/1-J>DlC>OI $600.00 i . __ __j r ! ! i I Oc t:-23·03 05 :30pm From-PARADIGM LABS M~ ... ~ -,\'---\...'Xj '- Client Sample ID~1-13 Client Project ID: 827062 Lab Sample ID: 82402 Lab Project ID: G515-578 Matrix: Soil Compound Aroclor-1016 Aroclor-1221 Aroclor-1232 Aroclor-1242 Aroclor-1248 Aroclor-1254 Aroclor-1260 Surrogate Spike Recoveries TCMX Comments: BQL = Below Quantitation Limit NA = Not applicable, surrogate diluted out. 9103501557 Results for PCBs by EPA 8082 %SOLIOS: 80.4 Quantltation Limit (uglKG) 38 38 38 38 38 38 38 Spike Added 100 T-148 P. 02/04 F-430 \ ~'":)\L_ Date Collected: 10/22/03 Date Received: 10/23/03 Date Analyzed: 10123/03 Analyzed By: CLP Dilution: 1 Spike Result 63 Result {uglKG) BQL BQL BQL BQL BQL BQL 1300 ·Percent Recovered 63 ,. l Reviewed By: k N.C. Cenification #481 S.C. Certification #99029 ·, Oct-23-03 05:3Opm From-PARADIGM LABS Client Sample ID: MT-2-13 Client Project ID: 827062 Lab Sample ID: 82403 Lab Project ID: G515-578 Matrix: Soil Compound Aroclor-1016 Aroclor-1221 Aroclor-1232 Aroclor-1242 Aroclor-1248 Aroclor-1254 Aroclor-1260 Surrogate Spike Recoveries TCMX Comments: BQL = Below Quantitation Limit NA == Not applicable, surrogate diluted out. 9103501557 Results for PCBs by EPA 8082 %SOLIDS: 77.1 Quantitation Limit (ug/KG) 40 40 40 40 40 40 40 Spike Added 100 T-148 P.03/04 F-430 \ ~')~ 11 ~:';' Date Collected: 10/22/03 Date Received: 10/23/03 Date Analyzed: 10/23/03 Analyzed By: CLP Dilution: 1 Result Spike Result 64 (ug/KG) SOL BQL BQL BQL BQL BQL 330 Percent Recovered 64 Reviewed By:~ N.C. Certification #481 S.C. Certification #99029 PARADIGM ANALYTJCAL LABORATORIES, INC. 5500 Business Drive, Wilmington, NC 28405 Phone: (910)-350-1901 FAX: (9I0)-35O-1557 -.. -··--·-------------------COC# 35759 Chain-of Custody Record & Analytical Request {·-...... Page__L • C, 0 ...... I -. " , ... .., or l :;l.o> . _____ ·-:-6 ,... :::lient: SJ,pj,,, 1:--"--f-=l,..__ __ _ Project ID: 8rJ 706J.. Date: .JJ {)c,7 '0 3 Report To:YA46ft ~~, ~ \ddress:Ri ~ &t t'Jt Contact: .Ei;.,u;sz&o«w Turnaround: J/lme my /& ~ &x -¼t/4 ~ \ddress: haBR&nat4 NB. J. ·75~q Phone:~ f.J .;l,.f7-Lill2 Job Nwnber: _______ J1/IIJ?Rtltllffl? J//1, ~753q ~ }uole #: _______ _ Fax: d£.J a<57~ irJLO P.O. Number: _______ Invoice To: ,5/24«1 E/z ~ Sample ID )')7-,-, ~ h,-..l-/3 I I I I Preservatives I ~yses I . Comments: . ~ . Please specify any special reporting ~ Date I Time I Matrix 1 NI I I ~oe1 I I I 1b) j/4/<o I So, I I v I I I ~~ Oe1 . 'O':? IJ1/'111s..,,·1 1 t.,, 1 I I Ii~ I ,,,. I ~ I requirements ~ <n ~MP_ d11v /IIT -/.JS/::' ,-------.-~n .. ,~ ..£. n.,, /t'Y,) f'-1/Ti)A,R;;b.) aulr r;-~ /f?-~7~ i ~-------c:::, UI UI --., ----1 ~~ ~~ f ~ "TI -------------+--'--'.....,..----,----,'----'--...____.._____,__4----1.---+--~--+--......__.___-+------------------l. Relinquished By Date Time Received By Date Time Temperature State Certification Requested ~ . g~ NC __ SC __ Olher __ . I Cy.,fuJ., ----------,--------I----. . . . I ,, -·~ .. n ····~ SEE REVERSE FDR TERMS AND CONDlTlONS REQUEST FOR EXCEPTION TO CONTRACT 1. Project Title: Warren County PCB Landfill Detoxification (SCO Contract 010440101A. CO#20) 2. Division : Waste Management 3. Source of Funds: Appropriations: Receipts : Federal: Match Required: 4. Budget Codes: GL Company: 1604 GL Account: 53-2199 GL Center: 4845 5. Is there a deadline for obligation of these funds? If so, date: _______ _ No ✓ 6. Type of contract requested : Contract for Services ____________ _ Award of DENR Grant Funds _________ _ Amendment to existing contract/grant ____ ✓ __ _ 7. Pro posed Vend or/Reci p ient: __ ---=S"""h-'-"a=...;w-'--=E'-'-n'--'-v-'-'-i r-"'o"'"'n-'-'-m-'--'e"""n"'""t=a,_I &=---'-l'--'-nf'-'-r=a=-st'-'-r=uc=t=u"--re=----------------- 8. Summary of work/activities to be performed under this contractual arrangement: For additional work related to movement of the contaminated clay stockpile and determination of contaminated volume and concentration of contaminated soil in the landfill that exceeded the original contract quantity of 72,000 tons. Attached change order form OC-24 contains supporting information. 9. Justification of Need for Contract: A) Was this vendor selected through a competitive process? ✓Yes ___ No ___ Will Be B) Explanation of why this work cannot be performed within the resources of the DENR Agency: DENR does not have the equipment, staff, or expertise to operate a soil remediation facility. C) Is there a State Agency/University that could perform this work? __ Yes ✓No D) If Yes, provide a list of those agencies : E) Contacts made to determine the ability of other state agencies/universities to perform this work (name of contact, agency, telephone number and response): None F) If not utilizing another state agency/university, state the reason: Same as 9 (B). G) Calculation of available funding for this contract. Include amount available and amount previously obligated/approved to be obligated: See attached summary sheet of funding, expenditures, commitments, and remaining balance. CO#20 adds $6,133.72 to the Shaw contract. Shaw revised contract amount is $13,565,548.49. SUBMITTED BY: ';}t?a,t;: ~ Phone: 733-4996 x308 Contact Person for questions regarding this contract: ____ P~a~t_B_a~c~k~u~s __ APPROVALS: Disapproved Disapproved ~ Disapproved Date Transmitted to Purchase and Services: ______________ _ Contract Exception Form -9/20/02 Date: 12/17/2003 Phone: 733-4996 x308 FORM 2800 AGREEMENT INFORMATION & CONTRACT BUDGET ENCUMBRANCE DENR DIVISION OF PURCHASE AND SERVICES 1. PARTIES TO THIS AGREEMENT A B . *DENR CONTRACT NO: SCO# 010440101A *PURCHASE ORDER NO: REVISION NO: C0#20 ..-----------------------------DENR Division of: Waste Management Division Section Division Address (MSC#, City, State, Zip) 1646 Mail Service Center Ralei h NC 27699-1646 Division Contract Administrator Patricia M. Backus, P.E. Division Director/Authorized Agent Telephone No. (919) 733-4996 X 308 Date Contractor (Name Contract Issued To:) Shaw Environmental & Infrastructure I.R.S. Number or Social Security Number 753044680 I Check if Applicable _ Private and/or Non-Profit Address (to which checks will be mailed) Wire Transfer U.S.Bank, (Wire Transfer) ABA# 081000210 Acct# -1523020107 48 (City, State, Zip) St. Louis, MO 63195-6786 Please check one of the following: African American owned Woman owned _Handicapped owned _ Hispanic owned _Other minority owned ✓ None of the above Contractor Contact Person/Key Personnel: GaryW. Duke, P.E. I Telephone Number (609) 588-6373 3. DIVISION CONTRACT COORDINATOR:_~B~re~n=d=a~R=iv~e~rs~--------PHONE NO: --~<=9~19~)~7~3=3-~4=9=96~x=2~0~4 __ _ 4. FISCAL YEAR: ___ -'-F~Y~0~3~-0~4~------ 5. START DATE: ____ M~a~rc~h~1~3~2~0=0~1 ________ (Contractor cannot begin work until contract is executed by DENR) 6. TERMINATION DATE: November 10 2003 (Limit to time required; contract cannot exceed 3 years) 7. CURRENT CONTRACT AMOUNT: __ ~$~1=3~,5=5=9~.4~1-'-4.~7-'--7 ______________________ _ 8. *AMENDMENT AMOUNT: __ ~$~6=·~1=3=3~.7~2 ___ (/ndicate Previously Assigned Contract No. & PO in appropriate block ABOVE) 9. REVISED CONTRACT TOTAL: $_1~3~5~6~5~5=4~8~-~49~ ________ (Original Amount+ Amendment Increase/Decrease) 10. UNENCUMBRANCE (Balance remaining in Contract that will not be paid to Contractor):$ __________ _ 11. ITEM DESCRIPTION 12. DENR CONTRACT AMOUNT Contract Purpose/Brief Narrative: (Estimate of Expenditures each FY if multiple year contract) Detoxification of the Warren County PCB Landfill. Change order 20 is for additional costs associated with moving the contaminated stock Add line item 25 -Additional work related to file and for confirming that the contaminated material found above the original contract stockpiled clay cap material amount of 72 .000 tons was contaminated and required treatment. = $14,264.56 Reduce line item 12 -Liquid BCD treatment with offsite recycle by 1.847.92 gallons@ 13. $4.40/gal CFDACODE: (Catalog of Federal Domestic Assistance Code, if applicable) =$8,130.84 14. Total change order value =$6,133.72 GL COMPANY: 1604 GL ACCT: 53-2199 GL CENTER 4845 15. Federal Funds State Funds Contractor Match Other Funds TOTAL PROJECT COST $ $ 13,565,548.49 $ $ $ 13.565.548.49 16. IA hz/o 3 Division Budget Officer (Mandatory Signature) Date I I Funding: Source and Amount HB 230 SB 1366 DOJ-Settlement HB 162 HB 166 SB 1115 SB 1115 OSBM Autorized Transfers Funds remaining from DWR completed projects Parks FEMA reimbursement Balance in Funds ExQenditures DEH FEMA reimbursement Pending transfers Sub total Total Funding Total Funds Remaining Planning/Design/Contractor Selection Detoxification Project Paid to Date Remaining Contract Obligations & Expenses Shaw Contract Advisor Contract Oversight Contract Petroleum Traders DENR & Other Expenses Subtotal of contract obligatations Retainage Change Order #20 -Proposedb Additional contract obligations Qverall Balance Remaining Funds-Outstanding Expenditures 24308-2103 49816-4845 49716-4332 49816-4845 49916-4725 49816-4845 49816-4845 49816-4845 49816-4845 49815-4845 49815-4845 Less Hurricane Floyd Recovery Fund 49716-4332 49816-4845• 49916-4725 (Majority of Work Prior to 2000) (Work after 2000) (Excluding Retainage) (Monitoring Well Removal) $ 1,000,000.00 $ 2,000,000.00 $ 570,274.00 $ 7,000,000.00 $ 1,000,000.00 $ 2,500,000.00 $ 500,000.00 $ 323,420.62 $ 1,740,155.14 $ 1,540,417.51 $ 350,000.00 $ 18,524,267.27 ~439,450.00 $ 17,084,817.27 $ 225,900.16 $ 728,085.89 $ 18,389.29 !;lti _97~,3}'5:34 $ 1,560,550.00 $ 14,539,813.28 $ 16,100,363.28 $ 478,693.52 $ $ 72,418.69 $ $ 2,809.25 !-· __ SS3":"921A6 $ 403,048.96 $ 6,133.72 9,27J.20 = Includes $350,000 to be transferred to 4845 f::: b For additional contaminated cap work. • "\ ~ ~ ~ ~ 1A../11/oa a--1-~ ~ ~ ~-~ I - 1 00-24 rev. 9-88 / / 1 INSTITUTION: PROJECT: I STA TE CODE & ITEM : CONTRACT FOR: CONTRACTOR: NCDENR STATE CONSTRUCTION OFFICE CHANGE ORDER NO. 16 Warren County PCB Landfill Detoxification ID#: 010440101A BCD Detoxification Shaw Environmental & Infrastructure, Inc. X OR Owner Request D CR Contractor Request D DR Designer Request D CC Concealed Condition D DE Design Error D DO Design Omissi \\ 12 13 0 SC Schedule C 1l □ OT Other ~ /1/o I 200 Horizon Center Blvd, Trenton, NJ 08691-1904 CO V~OOJ ~ Under the terms of the Contract and without invalidating the original provisions thereof, the following cha I..!"\ l~f;tf/ ~ authorized for the change in contract amount herein set forth : (Description of change order attached) ~ OFF/Ct 'TIO/( ~ Add new line item 24, 0ffsite Sediment Removal, as authorized by NCDENR letter dated September 29, 2 ~nd daily (;,,,~"V time and materials cost summary, copies of which are attached. /Jf 6282 L2Sl-, The time of completion including previous orders is 956 calendar days and shall be unchanged by Q calendar days by this change order, for a revised contract date of completion of October 24, 2003. CONTRACT COST SUMMARY 1. Original Contract Amount 2. Amt. of Previous Orders 3. Amt. of This Order: ADD ADD $ 7,211,801.25 $ 5,293.30 Deduct Deduct $385,375.28 $ 0.00 TOTALS $6,658,000.00 4. Total additions lines 2 &3 $ 7,217,094.55 Minus Total Deducts: $385,375.28 $6,831,719.27 (Line 4 shall show the net amount to be added or (deducted) from the contract amount.) 5. Revised Contract Total Amount 6. The Owner certifies that the contingency fund balance after this change is $13,489,719.27 $ Fill in one copy only I certify that my Bonding Company will be notified forthwith that my contract has been increased by the amount of this change order, and that a copy of the approved change order will be mailed upon receipt by me to my surety. _S_h_a_w_E_nv_ir_o_n_m_e_nt_a_l &_ln_f_ra_s_tr_uc_t_ur_e-'-, _ln_c_. __ By: ~ ~ .-/ ~ __ \~~'~'l_<\-}_b_~-- (Contractor) ~ (Date) 200 Horizon Center Blvd Gary W. Duke, P.E. Trenton, NJ 08691-1904 Project Manager Earth Tech By: ~ J ~ -------0. ' (Designer) _N_C_D_E_N_R ...... , _D_iv_o_f_W_a_s_te_M_a_na_,g..__e_m_e_n_t ___ By: (Owner) State Construction Office By: ~~,,,,,,-5 /~ -------C-<77 ----------------By : Other approving Agency (if needed) DISTRIBUTION: 1 original to State Construction 1 original to Owner 1 original to Board or Commission (if any) 1 original to Designer 1 original to Contractor 1 original to Surety (Date) (Date) /,:z?~ 7-v 3 (Date) (Date) 1 REQUEST FOR AUTHORIZATION TO CHANGE DATE: October 28, 2003 STATE CODE: SCO#010440101 A REQUEST NO.: 16 NCDENR Earth Tech PROJECT NAME: Warren County PCB Landfill OWNER: CONTRACTOR: Shaw Environmental & Infrastructure, Inc. DESIGNER: CONTRACT FOR: BCD Detoxification DESCRIPTION OF CHANGE: Add new line item 24, Offsite Sediment Removal, as authorized by NCDENR letter dated September 29, 2003 and daily time and materials cost summary, copies of which are attached. Schedule is unaffected by this change. REASON FOR CHANGE: Offsite sediments were found to contain PCBs, so Owner directed that they be removed and brought back within the site for appropriate disposition. SUMMARY REVIEW OF CONTRACTOR'S ESTIMATE FOR TIME AND COST: (Attach Contractor's detailed cost breakdown of labor and materials). Add new line 24 -Offsite Sediment Removal, 1 lump sum Total change order value: DESIGNER SUMMARY: 1. Schedule items affected by this change: None ADD 2. Can Contractor mitigate the change without requiring a contract time extension? Yes 3. Will the change require a contract time extension for other contractors? No Which? n/a $5,293.30 $5,293.30 4. Are additional costs indicated by reason of the time extension? No If so they must be included in 5 & 6 Below. CONTRACTOR'S ESTIMATE DESIGNER'S ESTIMATE 5. Estimated cost of change: _$_5~,2_9_3_.3_0 _______ _ 6. Estimated time extension field cost (if any) Covered by unit price for Shaw DESIGNER RECOMMENDATION AND CERTIFICATION: I certify that I have reviewed all aspects of this change order and have determined that it is in the best interest of the owner to have the work accomplished. I have also determined that the cost and time allotment are fair and equitable, and I recommend acceptance by the owner. Approved by: _-i,,[114'--"'-'-"--...,.d'--J.._:........c. ____ Date: Title: rfrr u= f½r 1 1 Date Work Done DAILY LABOR COST Cost Item Dave Ditcher Rick Bergener Delmar King Albert Scott DAILY EQUIPMENT COST Cost Item Case 580 Bobcat L90 Loader Bobcat mob & demob DAILY TOTAL COST Date Work Done Previous Cost Today's Cost Total Cost DAILY LABOR COST Cost Item Dave Ditcher Rick Bergener Delmar King Albert Scott Off-Site Sediment Removal Cost Summary Change Order 16 10/28/2003 Capture cost of mobilization and demobilization of Bobcated rented from Gregory Poole Co., was $300.00 each way, total $600.00 Shaw cost. Total Hours Hourly Hourly Worked Labor Travel/Lodg. $47.25 $11.08 $22.31 $11 .08 $15.04 $11.08 $20..38 $11.08 Total Labor Cost: Total Days Used Cost per day $ 72.25 $ t---------1 $ 90.00 $ 1----------1 $ 116.00 $ .__ _____ ~ $ 600.00 $ Cost 600.00 Hourly Per Diem $6.05 $6.05 $6.05 $6.05 Total Equipment Cost: Labor Equipment Subtotal 20% Mark Up Total Daily Cost Off-Site Sediment Removal Cost Summary Change Order 16 10/13/2003 Cost $0.00 $0.00 $0.00 $0.00 $0.00 $600.00 $0.00 $600.00 $600.00 $120.00 $720.00 Sediment traps in both areas removed. Silt fabric disposed of. Rock dams spread out. CO #16 work is completed. $4,095.62 $477.68 $4,573.30 (Not to exceed $5,655) Total Hours Hourly Hourly Worked Labor Travel/Lodg. 1 $47.25 $11 .08 2 $22.31 $11 .08 4 $15.04 $11 .08 $20.38 $1 1.08 Total Labor Cost: Hourly Per Diem Cost $6.05 $64.38 $6.05 $78.88 $6.05 $128.68 $6.05 $0.00 $271.94 ' DAILY EQUIPMENT COST Cost Item Case 580 Bobcat L90 Loader DAILY TOT AL COST Date Work Done Previous Cost Today's Cost Total Cost DAILY LABOR COST Cost Item Dave Ditcher Rick Bergener Delmar King Albert Scott DAILY EQUIPMENT COST Cost Item Case 580 Bobcat L90 Loader DAILY TOT AL COST Total Days Used Cost per day 72.25 $ 90.00 $ 116.00 $ Cost 36.13 90.00 Total Equipment Cost: Labor Equipment Subtotal 20% Mark Up Total Daily Cost Off-Site Sediment Removal Cost Summary Change Order 16 10/8/2003 thru 10/10/2003 $126.13 $271 .94 $126.13 $398.07 $79.61 $477.68 No labor expended. Rental of Bobcat skid-steer for 3 days. Removal of the off site sediment traps is last task remaining. $3,771 .62 $324.00 $4,095.62 (Not to exceed $5,655) Total Hours Worked Total Days Used ___ 3 __ -1 : Hourly Hourly Labor Travel/Lodg. $47.25 $11.08 $22.31 $11.08 $15.04 $11 .08 $20.38 $1 1.08 Total Labor Cost: Cost per day 72.25 $ 90.00 $ 116.00 $ Cost 270.00 Hourly Per Diem $6.05 $6.05 $6.05 $6.05 Total Equipment Cost: Labor Equipment Subtotal 20% Mark Up Total Daily Cost Cost $0.00 $0.00 $0.00 $0.00 $0.00 $270.00 $0.00 $270.00 $270.00 $54.00 $324.00 Date Work Done Previous Cost Today's Cost Total Cost DAILY LABOR COST Cost Item Dave Ditcher Rick Bergener Delmar King Albert Scott DAILY EQUIPMENT COST Cost Item Case 580 Bobcat L90 Loader DAILY TOT AL COST Date Work Done Previous Cost Today's Cost Total Cost DAILY LABOR COST Cost Item Dave Ditcher Rick Bergener Delmar King Albert Scott Off-Site Sediment Removal Cost Summary Change Order 16 10/7/2003 Continue remediation in West area. Assume completion. Will wait for a final inspection from Earth Tech. All spoils stockpiled on Pad 4 awaiting backfill. $3,047.02 $724.60 $3,771.62 (Not to exceed $5,655) Total Hours Worked 2 1 5 3 Total Days Used ---~---1 : Hourly Hourly Labor Travel/Lodg. $47.25 $11 .08 $22.31 $11.08 $15.04 $11 .08 $20.38 $11 .08 Total Labor Cost: Cost per day 72.25 $ 90.00 $ 116.00 $ Cost 72.25 90.00 Hourly Per Diem $6.05 $6.05 $6.05 $6.05 Total Equipment Cost: Labor Equipment Subtotal 20% Mark Up Total Daily Cost Off-Site Sediment Removal Cost Summary Change Order 16 10/6/2003 Cost $128.76 $39.44 $160.85 $112.53 $441.58 $162.25 $441 .58 $162.25 $603.83 $120.77 $724.60 Complete remediation on East area. Excavated material staged on Pad 4. $2,526.65 $520.37 $3,047,02 (Not to exceed $5,655) Total Hours Hourly Hourly Worked Labor Travel/Lodg. 1 $47.25 $11 .08 1 $22.31 $11 .08 4 $15.04 $11 .08 2 $20.38 $11 .08 Total Labor Cost: Hourly Per Diem Cost $6.05 $64.38 $6.05 $39.44 $6.05 $128.68 $6.05 $75.02 $307.52 \ DAILY EQUIPMENT COST Cost Item Case 580 Bobcat L90 Loader DAILY TOT AL COST Date Work Done Previous Cost Today's Cost Total Cost DAILY LABOR COST Cost Item Dave Ditcher Rick Bergener Delmar King Albert Scott DAILY EQUIPMENT COST Cost Item Case 580 Bobcat L90 Loader DAILY TOT AL COST Total Days Used Cost per day 72.25 $ 90.00 $ 116.00 $ Cost 36.13 90.00 Total Equipment Cost: Labor Equipment Subtotal 20% Mark Up Total Daily Cost Off-Site Sediment Removal Cost Summary Change Order 16 10/3/2003 $126.13 $307.52 $126.13 $433.65 $86.73 $520.37 Resume remediation on west side discrete areas. Haul excavated spoils to staging area on Pad 4. Now approx. 65% complete on this area. East area still at 75% complete. $1 ,871 .24 $655.41 $2,526.65 (Not to exceed $5,655) Total Hours Worked 1 1 4 5 Total Days Used Hourly Hourly Labor Travel/Lodg. $47.25 $11 .08 $22.31 $11.08 $15.04 $11.08 $20.38 $11 .08 Total Labor Cost: Cost per day 72.25 $ 90.00 $ 116.00 $ Cost 36.13 90.00 Hourly Per Diem $6.05 $6.05 $6.05 $6.05 Total Equipment Cost: Labor Equipment Subtotal 20% Mark Up Total Daily Cost Cost $64.38 $39.44 $128.68 $187.55 $420.05 $126.13 $420.05 $126.13 $546.18 $109.24 $655.41 Date Work Done Previous Cost Today's Cost Total Cost DAILY LABOR COST Cost Item Dave Ditcher Albert Scott Delmar King DAILY EQUIPMENT COST Cost Item Case 580 Bobcat L90 Loader DAILY TOT AL COST Off-Site Sediment Removal Cost Summary Change Order 16 9/29/2003 The east and west areas were walked and flagged with John Funk. The chain link and silt tenses by the north sed basin were opened to gain access to the West area. About 75% of the west area remediation was completed. $0.00 $588.70 $588.70 (Not to exceed $5,655) Total Hours Worked 3 7 Total Days Used 1: Hourly Labor $47.25 $20.38 $15.04 Cost per day 72.25 90.00 116.00 Hourly Hourly Travel/Lodg. Per Diem $11.08 $6.05 $11 .08 $6.05 $11 .08 $6 .05 Total Labor Cost: Cost $ 72.25 $ $ Total Equipment Cost: Labor Equipment Subtotal 20% Mark Up Total Daily Cost Cost $193.14 $0.00 $225.19 $418.33 $72.25 $418.33 $72.25 $490.58 $98.12 $588.70 North Carolina Deparbnent of Environment and Natural Resources Division of Waste Management Michael F. Easley, Governor William G. Ross Jr., Secretary Dexter R. Matthews, Director September 29, 2003 Mr. Gary Duke, P.E. Shaw Environmental & Infrastructure 200 Horizon Center Blvd. Trenton, NJ 08691-1904 Reference: Off-Site Sediment Removal Change Order No. 16 Warren County Landfill PCB Detoxification NCSCO ID #010440101A Dear Mr. Duke: The State of North Carolina, Department of Environment and Natural Resources (the State) herein authorizes Shaw Environment & Infrastructure, Inc. (Shaw) to remove accumulated sediments from two drainage features located north of the Warren County PCB Landfill. The two drainage features and extent of sediment removal is generally shown on an aerial photograph prepared by Earth Tech titled "Sediment Removal Areas." Prior to proceeding with sediment removal, Earth Tech and Shaw personnel will flag the areas where sediment will be removed. Shaw shall then mobilize suitable equipment to remove accumulated sediments up to a depth of 2 inches from the two drainage features and transport the sediments to the PCB landfill for disposal. The work shall be performed in accordance with Shaw's proposal dated September 24, 2003, and the work will be paid on a time and material basis not to exceed $5,655.00 without written authorization from the State. The work shall be completed within two weeks from the date of this authorization. Sincerely, 'y)~/4-~ Patricia M. Backus, P.E. PCB Landfill Project Manager cc: Mike Kelly, DENR -DEH Jim Cloonan, Earth Tech John Funk, Earth Tech 1646 Mail Service Center, Raleigh, North Carolina 27699-1646 Phone: 919-733-4996 \ FAX: 919-715-3605 \ Internet: www.enr.state.nc.us AN EQUAL OPPORTUNITY \ AFFIRMATIVE ACTION EMPLOYER -50% RECYCLED / 10% POST CONSUMER PAPER REQUEST FOR EXCEPTION TO CONTRACT RE# SlDjt ot ol/ If {)t o t ft 1. Project Title: Warren County PCB Landfill Detoxification (CO#16) 2. Division: Waste Management 3. Source of Funds: Appropriations: Receipts: Federal: Match Required: 4. Budget Codes: GL Company: 1604 GL Account: 53-2199 GL Center: 4845 5. Is there a deadline for obligation of these funds? If so, date: _______ _ No ✓ 6. Type of contract requested : Contract for Services ___________ _ Award of DENR Grant Funds _________ _ Amendment to existing contract/grant ____ ✓ __ _ 7. Proposed Vendor/Recipient: __ ~S_h_a_w_E_n_v_i_ro~n_m_e=n~t~a_l &~l~nf~ra=s=t~ru~c~t=ur~e'---------------- 8. Summary of work/activities to be performed under this contractual arrangement: During the detoxification of the PCB Landfill it was discovered that a portion of the clay cap was contaminated with PCBs. The cap had been stockpiled at the north end of the site and some of it had been washed offsite during rainfall events before the discovery. The limit on the concentration per the EPA Region 4 TSCA approval is 1.0 ppm PCBs. Material that was above that concentration was removed by Shaw under a written approval. Cost is based on time and materials. 9. Justification of Need for Contract: A) Was this vendor selected through a competitive process? ✓Yes ___ No ___ Will Be B) Explanation of why this work cannot be performed within the resources of the DENR Agency: DENR does not have the equipment, staff, or expertise to operate a soil remediation facility. C) Is there a State Agency/University that could perform this work? __ Yes ✓No D) If Yes, provide a list of those agencies: E) Contacts made to determine the ability of other state agencies/universities to perform this work (name of contact, agency, telephone number and response): None F) If not utilizing another state agency/university, state the reason: Same as 9 (B). G) Calculation of available funding for this contract. Include amount available and amount previously obligated/approved to be obligated: Funds to cover amendment will be from savings due to state purchase of fuel. SUBMITTED BY:\;?d ~ Phone: 733-4996 x308 Date: 11/05./03 ~;;t:~:::;on for questions regarding thisry: T,~Pat :~ ~ Disapproved ,,.,2d&~~ .... ~--'-"""/M-1--,..-1<''-ht._.~ .... ---~,---Division Directo~ -~:? . ·:;,; A,~;~~-,.-i:.~ r¥'·, Phone: 733-4996 x308 ------+--------BPA _/(#_,,,____,..,~ ..... ------lo'----------Chief Deputy Approved Disapproved ~ Disapproved NOV ti ~0uS Date Transmitted to Purchase and Services: _____________ _ FORM 2800 AGREEMENT INFORMATION & CONTRACT BUDGET ENCUMBRANCE DENR DIVISION OF PURCHASE AND SERVICES 1. PARTIES TO THIS AGREEMENT A B. ASSIGNED BY PURCHASE & SERVICE *DENR CONTRACT NO: SCO# 010440101A *PURCHASE ORDER NO: REVISION NO: C0#16 ~---------------------------DENR Division of: Waste Management Division Section Division Address (MSC#, City, State, Zip) 1646 Mail Service Center Ralei h NC 27699-1646 Division Contract Administrator Patricia M. Backus, P.E. Division Director/Authorized Agent Telephone No. (919) 733-4996 X 308 Date Contractor (Name Contract Issued To:) Shaw Environmental & Infrastructure I.R.S. Number or Social Security Number 753044680 I Check if Applicable _ Private and/or Non-Profit Address (to which checks will be mailed) Wire Transfer U.S.Bank, (Wire Transfer) ABA# 08100021 O Acct# -152302010748 (City, State, Zip) St Louis, MO 63195-6786 Please check one of the following: African American owned Woman owned _Handicapped owned _ Hispanic owned _Other minority owned ✓ None of the above Contractor Contact Person/Key Personnel: Gary W. Duke, P.E. I Telephone Number (609) 588-6373 3. DIVISION CONTRACT COORDINATOR: __ B-'re_n-=-d~a_R_iv-'e_rs~--------PHONE NO: --~(-'-91-'9C4)-'-7-=-3-'-3-...:4-=-99~6~x...:2~0...:4 __ _ 4. FISCAL YEAR: FY 03-04 -------------- 5. START DATE: ___ ...:M=a"-'rc""'h'-1""'3:.i..::2:.;:;0-=-0-=-1 ________ (Contractor cannot begin work until contract is executed by DENRJ 6. TERMINATION DATE: October 24 2003 (Limit to time required; contract cannot exceed 3 years) 7. CURRENT CONTRACT AMOUNT: __ __,$'""'"1"""3'-'4-=-8..:..4'-'.4=25~.-=-97'----------------------------- 8. *AMENDMENT AMOUNT: __ ~$_5~1=2~93~·-=-3-=-0 ___ (/ndicate Previously Assigned Contract No. & PO in appropriate block ABOVE) 9. REVISED CONTRACT TOTAL : $ ___ -'$-'1_3~A_8_9~J_1_9_.2_7 ________ ~(0riginal Amount+ Amendment Increase/Decrease) 10. UN ENCUMBRANCE (Balance remaining in Contract that will not be paid to Contractor): $ _________________ _ 11. ITEM DESCRIPTION 12. DENR CONTRACT AMOUNT Contract Purpose/Brief Narrative: (Estimate of Expenditures each FY if multiple . year contract) Detoxification of the Warren County PCB Landfill. Change Order #15 is a lump sum cost for the removal of material outside of the project Add Line item 24 = $5,293.30 boundary which had a concentration greater than allowed by EPA TSCA (Offsite sediment removal) 13. CFDA CODE: (Catalog of Federal Domestic Assistance Code, if applicable) 14. GL COMPANY: 1604 GL ACCT: 53-2199 GL CENTER 4845 15 Federal Funds State Funds Contractor Match Other Funds TOTAL PROJECT COST $ $ 13,489,719.27 $ $ $ 13,489,719.27 16. o(visionBudget Officer (Mandatory Signature) 11 / (:, /o3 Date I I North Carolina Department of Environment and Natural Resources Division of Waste Management Michael F. Easley, Governor William G. Ross Jr., Secretary Dexter R. Matthews, Director September 29, 2003 Mr. Gary Duke, P.E. Shaw Environmental & Infrastructure 200 Horizon Center Blvd. Trenton, NJ 08691-1904 Reference: Dear Mr. Duke: Off-Site Sediment Removal Change Order No. 16 Warren County Landfill PCB Detoxification NCSCO ID #010440101A E;l\. -·~ rm ,,;, , ____ _ NCDENR The State of North Carolina, Department of Environment and Natural Resources (the State) herein authorizes Shaw Environment & Infrastructure, Inc. (Shaw) to remove accumulated sediments from two drainage features located north of the Warren County PCB Landfill. The two drainage features and extent of sediment removal is generally shown on an aerial photograph prepared by Earth Tech titled "Sediment Removal Areas." Prior to proceeding with sediment removal, Earth Tech and Shaw personnel will flag the areas where sediment will be removed. Shaw shall then mobilize suitable equipment to remove accumulated sediments up to a depth of 2 inches from the two drainage features and transport the sediments to the PCB landfill for disposal. The work shall be performed in accordance with Shaw's proposal dated September 24, 2003, and the work will be paid on a time and material basis not to exceed $5,655.00 without written authorization from the State. The work shall be completed within two weeks from the date of this authorization. Sincerely, y)~~-~ Patricia M. Backus, P.E. PCB Landfill Project Manager cc: Mike Kelly, DENR -DEH Jim Cloonan, Earth Tech John Funk, Earth Tech 1646 Mail Service Center, Raleigh, North Carolina 27699-1646 Phone: 919-733-4996 \ FAX: 919-715-3605 \ Internet: www.enr.state.nc.us AN EQUAL OPPORTUNITY \ AFFIRMATIVE ACTION EMPLOYER-50% RECYCLED / 10% POST CONSUMER PAPER OC-24 rev. 9-88 INSTITUTION: ,; PROJECT: ST A TE CODE & ITEM : CONTRACT FOR: CONTRACTOR: NCDENR STATE CONSTRUCTION OFFICE CHANGE ORDER NO. 1.I Warren County PCB Landfill Detoxification ID#: 010440101A BCD Detoxification Shaw Environmental & Infrastructure, Inc. X OR Owner Request D CR Contractor Request D DR Designer Request D CC Concealed Condition D DE Design Error D DO Design Omission \il l3 14 □ SC Schedule Ch \ ..A I$ lo □ OTOther o-..~ ~ ~ "" N ✓.;, 200 Horizon Center Blvd, Trenton, NJ 08691-1904 "'-a,, er V 2003 .; Under the terms of the Contract and without invalidating the original provisions thereof, the following ch CO e i?:cJfJof<lAf[ ~ authorized for the change in contract amount herein set forth: (Description of change order attached) -d" NSfRUCTfon• .~ rt' OFFICE •~ " Increase line item #20 for fuel adjustment change order for fuel to be supplied directly by state per "Letter eement lor Supply of Fuel". Increase is to reflect final actual contract quantities. /t')" r,,, ... -' The time of completion including previous orders is 956 calendar days and shall be unchanged by Q calendar days ·by this change order, for a revised contract date of completion of October 24, 2003. CONTRACT COST SUMMARY 1. Original Contract Amount 2. Amt. Of Previous Orders 3. Amt. Of This Order: ADD ADD $ 7,217,094.55 Deduct $ 0.00 Deduct $385,375.28 $252,865.62 TOTALS $6,658,000.00 4. Total additions lines 2 &3 $7,217,094.55 Minus Total Deducts: $638,240.90 $6,578,853.65 (Line 4 shall show the net amount to be added or (deducted) from the contract amount.) 5. Revised Contract Total Amount 6. The Owner certifies that the contingency fund balance after this change is $13,236,853.65 $ Fill in one copy only I certify that my Bonding Company will be notified forthwith that my contract has been increased by the amount of this change order, and that a copy of the approved change order will be mailed upon receipt by me to my surety. _S_h_a_w_E_n_vi_ro_n_m_e_n_ta_l_&_l_n_fr_a_st_ru_c_tu_r_e~, l_n_c_. __ By: (Contractor) ~~~~ 200 Horizon Center Blvd Trenton, NJ 08691-1904 Earth Tech By: (Designer) _N_C_D_E_N_R~,_D_iv_of_W_a_st_e_M_a_n_a_g~e_m_e_n_t ___ By: (Owner) Gary W. Duke, P.E. Project Manager 'kl d,AJ _S_t_a_te_C_o_n_s_tr_u_ct_io_n_O_ffi_1c_e ________ ~;~ -----------------By: Other approving Agency (if needed) DISTRIBUTION: 1 original to State Construction 1 original to Owner 1 original to Board or Commission (if any) 1 original to Designer 1 original to Contractor 1 original to Surety (Date) (Date) I (Date) -QPrc!J (Date) (Date) REQUEST FOR AUTHORIZATION TO CHANGE DAT,E: October 28, 2003 STATE CODE: SCO#010440101A REQUEST NO.: 17 NCDENR Earth Tech PROJECT NAME: Warren County PCB Landfill OWNER: CONTRACTOR: Shaw Environmental & Infrastructure, Inc. DESIGNER: CONTRACT FOR: BCD Detoxification DESCRIPTION OF CHANGE: Increase line item #20 for fuel adjustment change order for fuel to be supplied directly by state per "Letter Agreement for Supply of Fuel". Increase is to reflect final actual contract quantities. No change in schedule. REASON FOR CHANGE: Increase contract quantity to cover actual quantity of fuel supplied by state. SUMMARY REVIEW OF CONTRACTOR'S ESTIMATE FOR TIME AND COST: (Attach Contractor's detailed cost breakdown of labor and materials). Increase line 20 -"Credit for fuel purchased by state" Total change order value: DESIGNER SUMMARY: 1. Schedule items affected by this change: None CREDIT CREDIT 2. Can Contractor mitigate the change without requiring a contract time extension? Yes -$252,865.62 -$252,865.62 3. Will the change require a contract lime extension for other contractors? No Which? n/a 4. Are additional costs indicated by reason of the time extension? No If so they must be included in 5 & 6 Below. CONTRACTOR'S ESTIMATE DESIGNER'S ESTIMATE 5. Estimated cost of change: _-..:..$2-'5;_2..:..,8;...c6...;;.5~.6..;;c2 ______ _ 6. Estimated time extension field cost (if any) _N_/a __________ _ DESIGNER RECOMMENDATION AND CERTIFICATION: I certify that I have reviewed all aspects of this change order and have determined that it is in the best interest of the owner to have the work accomplished. I have also determined that the cost and lime allotment are fair and equitable, and I recommend acceptance by the owner. Approved by: _.,..U~_· __ d_-~wJ~· _____ Date: 0 pr b) f-\-5.r-Title: STATE OF NC FUEL DELIVERY LOG TO MIDWEST SOIL REMEDIATION Cost for load at Running total backup DENR/Shaw of DENR/Shaw data line Date Order Date Delivery Quantity Date Quantity price of price -by # Placed Requested Ordered Delivered Delivered $1.008/gal month 2 05/29/03 05/30/03 7,500 05/30/03 7,501 $7,561.01 $7,561.01 3 05/29/03 05/31/03 7,500 05/31/03 7,504 $7,564.03 $15,125.04 CUTOFF FOR END OF MAY BILLING BY SHAW AND MSR 5 05/29/03 06/02/03 7,500 06/02/03 7,501 $7,561.01 $7,561.01 6 06/02/03 06/03/03 7,500 06/03/03 7,499 $7,558.99 $15,120.00 7 06/02/03 06/04/03 7,500 06/04/03 7,500 $7,560.00 $22,680.00 8 06/02/03 06/06/03 7,500 06/06/03 7,504 $7,564.03 $30,244.03 9 06/02/03 06/07/03 7,500 06/07/03 7,498 $7,557.98 $37,802.02 10 06/05/03 06/07/03 6,000 06/07/03 6,001 $6;049.01 $43,851,02 11 06/02/03 06/09/03 7,500 06/09/03 7,503 $7,563.02 $51,414.05 12 06/02/03 06/10/03 7,500 06/10/03 7,495 $7,554.96 $58,969.01 13 06/09/03 06/12/03 7,700 Cancelled 6/10 16:30 $0.00 $58,969.01 14 06/09/03 06/13/03 7,700 Cancelled 6/10 16:30 $0.00 $58,969.01 15 06/09/03 06/14/03 7,700 06/14/03 6,000 $6,048.00 $65,017.01 16 06/09/03 06/16/03 7,700 06/16/03 7,501 $7,561.01 $72,578.02 17 06/09/03 06/17/03 7,700 06/17/03 7,698 $7,759.58 $80,337.60 18 06/16/03 06/18/03 7,700 06/18/03 7,702 $7,763.62 $88,101.22 19 06/16/03 06/20/03 7,700 06/20/03 7,651 $7,712.21 $95,813.42 20 06/16/03 06/21/03 7,700 06/21/03 7,700 $7,761.60 $103,575.02 21 06/16/03 06/23/03 7,700 06/23/03 7,701 $7,762.61 $111,337.63 22 06/16/03 06/24/03 7,700 06/24/03 7,700 $7,761.60 $119,099.23 23 06/23/03 06/25/03 7,000 06/25/03 7,000 $7,056.00 $126,155.23 24 06/23/03 06/26/03 6,000 Cancelled 6/25 08:30 $0.00 $126,155.23 25 06/23/03 06/27/03 6,000 Cancelled 6/25 08:30 $0.00 $126,155.23 26 06/23/03 06/28/03 6,000 06/28/03 7,700 $7,761.60 $133,916.83 27 06/23/03 06/30/03 7,700 06/29/03 7,701 $7,762.61 $141,679.44 CUTOFF FOR END OF JUNE BILLING BY SHAW AND MSR 29 06/23/03 07/01/03 7,700 07/01/03 7,701 $7,762.61 $7,762.61 30 06/30/03 07/02/03 7,700 07/02/03 7,705 $7,766.64 $15,529.25 31 06/30/03 07/03/03 6,000 07/03/03 5,999 $6,046.99 $21,576.24 32 06/30/03 07/05/03 6,000 .Cancelled 7/4 08:00 $0.00 $21,576.24 33 06/30/03 07/05/03 6,000 .Cancelled 7/4 08:00 $0.00 $21,576.24 34 06/30/03 07/07/03 7,700 Cancelled 7/4 08:00 $0.00 $21,576.24 35 06/30/03 07/08/03 7,700 Cancelled 717 09:45 $0.00 $21,576.24 2107B-1118-2180-51600 Page 1 DENR / Shaw NOTES Shaw credit to DENR for May= $15,125.04 this was supplemental order placed 6/5 Cancelled by PB due to 6/10-11 shutdown Cancelled by PB due to 6/10-11 shutdown Quantity revised by PB 6/10 Cancelled by PB due to 6/25-27 shutdown Cancelled by PB due to 6/25-27 shutdown Increased order from 6,000 to 7,700 gal 6/27 6/30 order delivered 6/29 at vendor's request Shaw credit to DENR for June= $141,679.44 Cancelled by PB due to 7/2-7 shutdown Cancelled by PB due to 7/2-7 shutdown Cancelled by PB due to 7/2-7 shutdown Cancelled by PB due to 7/2-7 shutdown FuelLogState 101103 FINAL as sent DENR backup data line Date Order Date Delivery Quantity # Placed Requested Ordered 36 07/07/03 07/09/03 7,700 37 07/07/03 07/10/03 7,700 38 07/07/03 07/11/03 6,000 39 07/07/03 07/12/03 6,000 40 07/07/03 07/14/03 7,700 41 07/07/03 07/15/03 7,700 42 07/14/03 07/16/03 7,700 43 07/14/03 07/17/03 7,700 44 07/14/03 07/18/03 6,000 45 07/14/03 07/19/03 6,000 46 07/14/03 07/21/03 7,700 47 07/14/03 07/22/03 7,700 48 07/21/03 07/23/03 6,000 49 07/21/03 07/24/03 6,000 50 07/21/03 07/25/03 6;000 51 07/21/03 07/26/03 6,000 52 07/21/03 07/28/03 7,700 53 07/21/03 07/29/03 7,700 54 07/28/03 07/30/03 6,000 55 07/28/03 07/31/03 6,000 STATE OF NC FUEL DELIVERY LOG TO MIDWEST SOIL REMEDIATION Cost for load at Running total DENR/Shaw of DENR/Shaw Date Quantity price of price -by Delivered Delivered $1.008/gal month 07/09/03 7,700 $7,761.60 $29,337.84 07/10/03 7,703 $7,764.62 $37,102.46 07/11/03 6,005 $6,053.04 $43,155.50 07/12/03 6,001 $6,049.01 $49,204.51 07/14/03 7,698 $7,759.58 $56,964.10 Cancelled 7/14.09:45 $0.00 $56,964.10 07/16/03 7,690 $7,751.52 $64,715.62 07/17/03 7,698 $7,759.58 $72,475.20 07/18/03 5,999 $6,046.99 $78,522.19 07/19/03 6,005 $6,053.04 $84,575.23 07/21/03 7,700 $7,761.60 $92,336.83 Cancelled 7/22 09:45 $0.00 $92,336.83 cancelled 1122 09:30 $0.00 $92,336.83 07/24/03 6,005 $6,053.04 $98,389.87 07/25/03 7,706 $7,767.65 $106,157.52 07/26/03 6,006 $6,054.05 $112,211.57 07/28/03 7,698 $7,759.58 $119,971.15 Cancelled 7/28 10:20 $0.00 $119,971.15 07/30/03 5,999 $6,046.99 $126,018.14 07/31/03 5,999 $6,046.99 $132,065.14 CUTOFF FOR END OF JULY BILLING BY SHAW AND MSR 57 07/28/03 08/01/03 6,000 08/01/03 6,004 $6,052.03 $6,052.03 58 07/28/03 08/02/03 7,700 08/02/03 6,004 $6,052.03 $12,104.06 59 07/28/03 08/04/03 SEE LINE 84 $0.00 $12,104.06 60 07/28/03 08/05/03 7,700 Cancelled 8/415:00 $0.00 $12,104.06 61 08/04/03 08/06/03 6,000 08/06/03 6,000 $6,048.00 $18,152.06 62 08/04/03 08/07/03 6,000 08/07/03 6,000 $6,048.00 $24,200.06 63 08/04/03 08/08/03 6,000 08/08/03 5,999 $6,046.99 $30,247.06 64 08/04/03 08/09/03 6,000 08/09/03 6,005 $6,053.04 $36,300.10 65 08/04/03 08/11/03 7,700 08/11/03 7,699 $7,760.59 $44,060.69 66 08/04/03 08/12/03 7,700 08/12/03 7,701 $7,762.61 $51,823.30 67 08/11/03 08/13/03 6,000 Cancelled 8/12 08:00 $0.00 $51,823.30 68 08/11/03 08/14/03 6,000 08/14/03 6,028 $6,076.22 $57,899.52 69 08/11/03 08/15/03 6,000 08/15/03 6,000 $6,048.00 $63,947.52 2107B-1118-2180-51600 Page 2 DENR / Shaw NOTES Cancelled by PB due to 7 /14 shutdown Cancelled by PB due to 7/21-22 shutdown Cancelled by PB due to 7/21-22 shutdown Increased order from 6,000 to 7,700 gal 7/23 Increased to 7,700 gal 7/23, back to 6,000 7/25 Cancelled by PB due to 7 /27-28 shutdown Shaw credit to DENR for July= $132,065.14 Decreased order from 7,700 8/1 by Bill G Missed in Aug, bill in Sept, see line 84 Cancelled by Bill, MSR down at noon 8/4 Cancelled by Bill, MSR down Increased to 7,700 gal 8/13, back to 6,000 8/14 FuelLogState 101103 FINAL as sent DENR backup data line Date Order Date Delivery Quantity # Placed Requested Ordered 70 08/11/03 08/16/03 6,000 71 08/11/03 08/18/03 7,700 72 08/11/03 08/19/03 7,700 73 08/18/03 08/20/03 6,000 74 08/18/03 08/21/03 6,000 75 08/18/03 08/22/03 6,000 76 08/18/03 08/23/03 7,700 77 08/18/03 08/25/03 7,700 78 08/18/03 08/26/03 7,700 79 08/25/03 08/27/03 6,000 80 08/25/03 08/28/03 6,000 81 08/25/03 08/29/03 6,000 82 08/25/03 08/30/03 6,000 STATE OF NC FUEL DELIVERY LOG TO MIDWEST SOIL REMEDIATION Cost for load at Running total DENR/Shaw of DENR/Shaw Date Quantity price of price -by Delivered Delivered $1.008/gal month Cancelled 8/15 09:50 $0.00 $63,947.52 Gancelled 8(15 09:50 $0.00 $63,947.52 08/19/03 7,701 $7,762.61 $71,710.13 Cancelled•8/19 10:45 $0.00 $71,710.13 08/21/03 6,001 $6,049.01 $77,759.14 08/22/03 6,001 $6,049.01 $83,808.14 08/23/03 6,000 $6,048.00 $89,856.14 08/25/03 7,700 $7,761.60 $97,617.74 08/26/03 7,724 $7,785.79 $105,403.54 08/27/03 6,003 $6,051.02 $111,454.56 Cancelled 8/2715:45 $0.00 $111,454.56 08/29/03 7,728 $7,789.82 $119,244.38 08/30/03 7,700 $7,761.60 $127,005.98 CUTOFF FOR END OF AUGUST BILLING BY SHAW AND MSR 84 07/28/03 . 08/04/03 7,700 08/04/03 · 7,704 $7,765.63 ···• $7;765:63 85 08/25/03 09/01/03 7,700 09/01/03 7,699 $7,760.59 $15,526.22 86 08/25/03 09/02/03 6,000 09/02/03 7,632 $7,693.06 $23,219.28 87 09/02/03 09/04/03 6,000 09/04/03 6,008 $6,056.06 $29,275.34 88 09/02/03 09/05/03 7,700 09/05/03 7,701 $7,762.61 $37,037.95 89 09/02/03 09/06/03 7,700 09/06/03 6,004 $6,052.03 $43,089.98 90 09/02/03 09/08/03 6,000 09/08/03 6,004 $6,052.03 $49,142.02 91 09/02/03 09/09/03 6,000 09/09/03 5,999 $6,046.99 $55,189.01 92 09/08/03 09/10/03 6,000 09/10/03 6,002 $6,050.02 $61,239.02 93 09/08/03 09/11/03 6,000 09/11/03 6,004 $6,052.03 $67,291.06 94 09/08/03 09/12/03 6,000 09/12/03 6,007 $6,055.06 $73,346.11 95 09/08/03 09/13/03 7,700 09/13/03 6,000 $6,048.00 $79,394.11 96 09/08/03 09/15/03 6,000 09/15/03 6,000 $6,048.00 $85,442.11 97 09/08/03 09/16/03 6,000 09/16/03 6,002 $6,050.02 $91,492.13 98 09/15/03 09/17/03 6,000 09/17/03 6,005 $6,053.04 $97,545.17 99 09/15/03 09/18/03 6,000 09/18/03 6,009 $6,057.07 $103,602.24 100 09/15/03 09/19/03 6,000 Cancelled $0.00 $103,602.24 101 09/15/03 09/20/03 6,000 Cancelled $0.00 $103,602.24 102 09/15/03 09/22/03 6,000 09/22/03 6,004 $6,052.03 $109,654.27 103 09/15/03 09/23/03 6,000 09/23/03 6,006 $6,054.05 $115,708.32 2107B-1118-2180-51600 Page 3 DENR / Shaw NOTES Cancelled by Bill, MSR down Cancelled by Bill, MSR down Cancelled by Bill, MSR down Decreased order from 7,700 8/22 by Bill G Cancelled by Bill, MSR down Increased to 7,700 gal 8/27 Increased to 7,700 gal 8/27 Shaw credit to DENR for Aug= $127,005.98 Missecl'in"Aug; bill in Sept, see line:59 .... Decreased order from 7,700 9/5 by Bill G Decreased order from 7,700 9/12 by Bill G Cancelled by Dave Ditcher ale Isabel Cancelled by Dave Ditcher ale Isabel Fuel Log State 101103 FINAL as sent DENR STATE OF NC FUEL DELIVERY LOG TO MIDWEST SOIL REMEDIATION Cost for load at Running total backup DENR/Shaw of DENR/Shaw data line Date Order Date Delivery Quantity Date Quantity price of price -by # Placed Requested Ordered Delivered Delivered $1.008/gal month 104 09/23/03 09/24/03 6,000 09/24/03 6,000 $6,048.00 $121,756.32 105 09/23/03 09/25/03 6,000 09/25/03 5,998 $6,045.98 $127,802.30 106 09/23/03 09/26/03 6,000 09/26/03 6,004 $6,052.03 $133,854. 107 09/23/03 09/27/03 7,700 09/27/03 7,700 $7,761.60 $141,615.94 108 09/23/03 09/29/03 6,000 09/29/03 6,005 $6,053.04 $147,668.98 109 09/23/03 09/30/03 6,000 09/30/03 6,000 $6,048.00 CUTOFF FOR END OF SEPT BILLING BY SHAW AND MSR 111 09/29/03 10/01/03 6,000 10/01/1__ -, DENR / Shaw NOTES 112 09/29/03 10/02/03 6,000 Cancelled 10/1 8:0u 113 09/29/03 10/03/03 6,000 10/03/03 6, 0.00 ,w-.u41Cancelled by Bill G. MSR down $12,104.06 114 09/29/03 10/04/03 7,700 10/04/03 7,860, 115 09/29/03 10/06/03 6,000 10/06/03 6,015 116 09/29/03 10/07/03 6,000 10/07/03 6,004 117 10/06/03 10/08/03 6,000 10/08/03 6,001, 118 10/06/03 10/09/03 6,000 10/09/03 6,010 119 10/06/03 10/10/03 6,000 10/10/03 6,000 120 10/06/03 10/11 /03 7,700 10/11 /03 6,000 121 10/06/03 10/12/03 6,000 Cancell~d,10/10 122 10/06/03 10/13/03 6,000 Cancel.led 10/10 123 10/06/03 10/14/03 6,000 Cancelled 10/10 CUTOFF FOR END OF OCT BILLING BY SHAW AND MSR $7,922.88 $6,063.12 $6,052.03 $6,049.01 $6,058.08 $6,048.00 $6,048.00 $0.00 $0.00 $0.00 125 IGRAND TOTALS, BASED ON SITE TICKETS I 620,970 I $625,937.76 126 !CORRECTIONS TO FINAL TOTALS BASED ON FUEL VENDOR INVOICES $20,026.94 $26,090.06 $32,142.10 $38,191.10 $44,249.18 $50,297.18 $56,345.18 Decreased order from 7,700 10/10 by Bill G $56,345.18 Canceled 10/10 by Bill G, MSR to buy future $56,345.18 Canceled 10/10 by Bill G, MSR to buy future $56,345.18 Canceled 10/10 by Bill G, MSR to buy future Shaw credit to DENR for Oct= $56,345.18 127 DENR Fuel Purchase Log shows total of 620,969 gallons on tickets, but only 617,077 invoiced by DENR's fuel vendor after corrections made by 128 vendor after offloading undelivered fuel after trucks returned to terminal, make correction below to adjust Shaw total to match vendor invoices. 129 Adjust Shaw's 620,970 to vendor's 617,077 gal (3,893) -$3,924.14 130 GRAND TOTALS, BASED ON VENDOR INVOICES 617,077 $622,013.62 131 Credited by Shaw through Sept application #31 $573,592.58 132 October total adjusted Shaw credit to DENR 48,037 $48,421.04 133 Total previously authorized on CO #9 $369,148.00 134 Excess to be authorized on CO #17 $252,865.62 135 Dukefile: c:\mydocs\nclf\FuelLogState 101103 FINAL.xis 2107B-1118-2180-51600 Page 4 FuelLogState 101103 FINAL as sent DENR DENA Fuel Purchases 'S ~~<;.~"i)~\-"I¼,.~ ~ c;l,.c:,-,. \ ~ x.~ ~..., ~ l'f'i' ~ lj'.) '-""'-v ~ ~L~'li;..~ Q.. ~ 9-.,i:>""l. t:.J-""( M~~~~~ Orders Reauested Actual DENR Shaw Savlnqs Delivery Quantity Cancel or Delivery Delivery Invoice Order No. Order Date Date Ordered Modifv Oat• Date Ticket Ouantitv Price Fuel CharQe Sales Tax Pum<>Charae Invoice Total Price Coat 1 5/29/2003 5/30/2003 7500 5/30/2003 7501 7479 0.7934 $5 933.84 $415.37 $30.00 $6 379.21 $1.008 $7 538.63 $1 159.62 2 5/29/2003 5/3112003 7500 5/3112003 7504 7485 0.7934 $5 938.60 $415.70 $30.00 $6 384.30 $1.008 $7,544.88 $1 160.58 3 5/2912003 612/2003 7500 612/3003 7501 7475 0.6341 $6,234.90 $436.44 $30.00 $6 701.34 $1.008 $7 534.80 $633.46 4 612/2003 61312003 7,500 61312003 7499 7475 0.7697 $5 753.51 $402.75 $30.00 $6186.25 $1.008 $7 534.80 $1 348.55 5 612/2003 614/2003 7 500 614/2003 7500 7475 0.7697 $5 753.51 $402.75 $30.00 $6186.25 $1.008 $7 534.80 $1 348.55 6 612/2003 61612003 7,500 61612003 7504 7474 0.7697 $5 752.74 $402.69 $30.00 $6185.43 $1.008 $7 533.79 $1 348.36 7 612/200' 617/2003 7 500 617/2003 7498 7465 0.7697 $5 745.81 $402.21 $30.00 $6178.02 $1.008 $7 524.72 $1 346.70 8 612/2003 619/2003 7500 619/2003 7503 7473 0.7697 $5 751.97 $402.64 $30.00 $6184.61 $1.008 $7 532.78 $1 348.18 9 612/2003 6110/2003 7500 6110/2003 7495 7458 0.7947 $5 926.87 $414.88 $30.00 $6 371.75 $1.008 $7 517.66 $1145.91 10 615/2003 617/2003 6000 617/2003 6001 5972 0.7697 $4 596.65 $321.77 $30.00 $4 948.41 $1.008 $6 019.78 $1 071.36 11 61812003 6112/2003 6110/2003 12 619/2003 611312003 6110/2003 13 619/2003 6114/2003 6000 6110/2003 6114/2003 6000 5964 0.7947 $4 739.59 $331.77 $30.00 $5101.36 $1.008 $6011.71 $910.35 14 619/2003 611612003 7700 611612003 7501 7465 0.7947 $5 932.44 $415.27 $30.00 $6 377.71 $1.008 $7,524.72 $1147.01 15 619/2000 6117/2003 7700 6117/2003 7698 7657 0.6341 $6,386.70 $447.07 $30.00 $6 863.77 $1.008 $7 718.26 $854.48 16 611612003 611812003 7700 611812003 7702 7664 0.6341 $6 392.54 $447.48 $30.00 $6870.02 $1.008 $7 725.31 $855.29 17 611612003 6120/2003 7700 6120/2003 7651 7613 0.6341 $6 350.00 $444.50 $30.00 $6824.50 $1.008 $7 673.90 $849.40 18 611612003 612112003 7700 612112003 7699 7663 0.6341 $6 391.71 $447.42 $30.00 $6 869.13 $1.008 $7 724.30 $855.18 19 611612003 612312003 7700 612312003 7701 7668 0.6341 $6 395.88 $447.71 $30.00 $6873.59 $1.008 $7729.34 $855.75 20 61161200: 6124/2003 7700 6124/2003 7700 7646 0.7913 $6 050.28 $423.52 $30.00 $6 503.80 $1.008 $7 707.17 $1 203.37 21 612312003 6125/2003 7000 612512003 7000 6959 0.7913 $5 506.66 $385.47 $30.00 $5 922.12 $1.008 $7014.67 $1 092.55 22 612312003 612612003 6125/2003 23 612312003 6127/2003 6125/2003 24 612312003 612812003 6000 6/2712003 612812003 7700 7648 0.7913 $6 051.86 $423.63 $30.00 $6 505.49 $1.008 $7 709.18 $1 203.69 25 612312003 6130/2003 7700 6129/2003 7701 7636 0.7913 $6042.37 $422.97 $30.00 $6 495.33 $1.008 $7697.09 $1 201.76 26 612312003 7/112003 7700 7/112003 7701 7649 0.8265 $6 321.90 $442.53 $30.00 $6 794.43 $1.008 $7 710.19 $915.76 27 6130/2003 7/2/2003 7700 712/2003 7705 7645 0.8265 $6 318.59 $442.30 $30.00 $6 790.89 $1.008 $7 706.16 $915.27 28 6130/2003 7/312003 6,000 71312003 5999 5962 0.8265 $4 927.59 $344.93 $30.00 $5 302.52 $1.008 $6009.70 $707.17 29 6130/2003 7/5/2003 7/4/2003 30 6130/2003 7/5/2003 7/4/2003 31 6130/2003 7/7/2003 7/4/2003 32 6130/2003 7/812003 7/7/2003 33 71712003 7/9/2003 7700 7/912003 7700 7646 0.6313 $6 356.12 $444.93 $30.00 $6 631.05 $1.008 $7 707.17 $876.12 34 7/7/2003 7/10/2003 7700 7/10/2003 7703 7644 0.6313 $6 354.46 $444.81 $30.00 $6829.27 $1.008 $7 705.15 $875.88 35 7/7/2003 7/11/2003 6000 7/11/2003 6005 5957 0.6313 $4 952.05 $346.64 $30.00 $5 328.70 $1.008 $6 004.66 $675.96 36 7/7/2 m 7/12/2003 6000 7112/2003 6001 5948 0.6313 $4944.57 $346.12 $30.00 $5 320.69 $1.008 $5 995.58 $674.89 37 7/7/2 n, 7/14/2003 7700 7/14/2003 7698 7636 0.6313 $6 347.81 $444.35 $30.00 $6 822.15 $1.008 $7 697.09 $874.93 38 7/7/200: 7/15/2003 7/14/2003 39 7/14/2003 7/1612003 7700 7/1612003 7690 7637 0.8513 $6501.38 $455.10 $30.00 $6,986.47 $1.008 $7 698.10 $711.62 40 7/14/2003 7/17/2003 7,700 7/17/2003 7698 7646 0.8513 $6 509.04 $455.63 $30.00 $6994.67 $1.008 $7 707.17 $712.50 41 7/14/2003 7/1812003 6000 7/1812003 5999 5957 0.8513 $5 071.19 $354.98 $30.00 $5 456.18 $1.008 $6,004.66 $548.48 42 7/14/2003 7/19/2003 6000 7/19/2003 6005 5961 0.8513 $5 074.60 $355.22 $30.00 $5 459.82 $1.008 $6008.69 $548.87 43 7/14/2003 7/21/2003 7700 7/21/2003 7700 7646 0.8513 $6 509.04 $455.63 $30.00 $6 994.67 $1.008 $7707.17 $712.50 44 7/14/2003 7/22/2003 7/2112003 45 7/21/2003 7/23/2003 7/22/2003 46 7/21/2003 7/24/2003 6000 7/24/2003 6005 5962 0.6340 $4 972.31 $348.06 $30.00 $5 350.37 $1,008 $6009.70 $659.33 47 7/21/2 7/25/2003 7700 7/2312001 7/25/2003 7706 7648 0.6340 $6 378.43 $446.49 $30.00 $6 854.92 $1.008 $7709.18 $854.26 48 7/21/2003 7/2612003 7700 712312003 7/2612003 6006 5963 0.6340 $4 973.14 $348.12 $30.00 $5 351.26 $1.008 $6010.70 $659.44 49 7/21/200: 7/2812003 7700 7/28/2003 7698 7646 0.6340 $6 376.76 $446.37 $30.00 $6 853.14 $1.008 $7707.17 $854.03 50 7/21/2003 7/29/2003 7/2812003 51 7/2812rYJ: 7/30/2003 6000 7/30/2003 5999 5958 0.8136 $4 847.43 $339.32 $30.00 $5 216.75 $1.008 $6 005.66 $788.92 52 7/2812r>I. 7/31/2003 6000 7/31/2003 5999 5956 0.8136 $4845.80 $339.21 $30.00 $5 215.01 $1.008 $6 003.65 $788.64 53 7/28/200 8/1/2003 6000 811/2003 6004 5932 0.8136 $4826.28 $337.84 $30.00 $5 194.12 $1.008 $5 979.46 $785.34 54 7/281200: 812/2003 6000 8/1/2003 812/2003 6004 5951 0.8136 $4841.73 $338.92 $30.00 $5 210.65 $1.008 $5998.61 $787.95 55 7/281= 814/2003 7700 814/2003 7704 7644 0.8136 $6219.16 $435.34 $30.00 $6684.50 $1.008 $7705.15 $1 020.65 56 7/2812003 815/2003 814/2003 57 814/200." 81612003 6000 81612003 6000 5956 0.8465 $5 041.75 $352.92 $30.00 $5 424.67 $1.008 $6003.65 $578.98 58 814/2•• 817/2003 6000 817/2003 6000 5954 0.8465 $5 040.06 $352.80 $30.00 $5 422.86 $1.008 $6001.63 $578.77 59 814/2003 81812003 6000 8/812003 5999 5951 0.8465 $5 037.52 $352.63 $30.00 $5 420.15 $1.008 $5 998.61 $578.46 60 814/2•• 819/2003 6000 819/2003 6005 5959 0.8465 $5 044.29 $353.10 $30.00 $5 427.39 $1.008 $6006.67 $579.28 61 814/2003 8111/2003 7700 8111/2003 7699 7642 0.8465 $6468.95 $452.63 $30.00 $6 951.78 $1.008 $7 703.14 $751.36 62 814/2003 8112/2003 7700 8/12/2003 7701 7643 0.8797 $6,723.55 $470.65 $30.00 $7 224.20 $1.008 $7704.14 $479.95 63 8111/2"' 811312003 8112/2003 64 8111/200'. 8114/2003 6000 8114/2003 6028 5980 0.8797 $5 260.61 $368.24 $30.00 $5 658.85 $1.008 $6 027.84 $368.99 65 8111/2003 8115/2003 6,000 8114/2003 8115/2003 6000 5951 0.8797 $5 235.09 $366.46 $30.00 $5 631.55 $1.008 $5 998.61 $367.06 pmb 10/2112003 ~ DENA Fuel Purchases Orders Re uested Actual DENA Shaw Savin s Delivery Quantity Cancel or Delivery Delivery Invoice Order No. Order Date Date Ordered Modi Dal Date Ticket Quanti Price Fuel Char e Sales Tax Pum Char e Invoice Total Price Cost 66 8,/11/2003 8,/16,/2003 8,/15/2003 67 8,/11/2003 8,/18,/2003 8,/15/2003 68 8,/11/2003 8,/19/2003 7700 8,/19/2003 7701 7647 0.8501 $6,500.71 $455.05 $30.00 $6 985.76 $1.008 $7708.16 $722.41 69 8,/18,/2003 8,/20/2003 8,/19/2003 70 8,/21/2003 6000 8,/21/2003 6001 5952 0.8501 $5,059.60 $354.19 $30.00 $5 443.96 $1.008 $5 999.62 $555.64 71 8,/22/2003 6000 8,/22/2003 6001 5951 0.8501 $5 056.95 $354.13 $30.00 $5 443.07 $1.008 $5 996.61 $555.54 72 8,/23/2003 6000 8,/22/2003 8,/23/2003 6000 5951 0.8501 $5 056.95 $354.13 $30.00 $5 443.07 $1.008 $5 996.61 $555.54 73 8,/25/2003 7700 8,/25/2003 7700 7635 0.8501 $6,490.51 $454.34 $30.00 $6 974.85 $1.008 $7 696.08 $721.23 74 8,/26,/2003 7700 8,/26,/2003 7724 7667 0.6475 $6 497.79 $454.85 $30.00 $6 962.64 $1.008 $7 726.34 $745.70 75 8,/25/2 8,/27/2003 6000 8,/27/2003 6003 5950 0.6475 $5 042.63 $352.98 $30.00 $5 425.61 $1.008 $5 997.60 $571.99 76 8,/25/2 8,/28,/2003 8,/27/2003 77 8,/25/2 8,/29/2003 7700 8,/27/2003 8,/29/2003 7728 7658 0.6475 $6 490.16 $454.31 $30.00 $6 97♦.41' $1.008 $7 719.26 $744.60 78 8,/25/2 8,/30/2003 7700 8,/27/2003 8,/30/2003 7700 7635 0.6475 $6 470.66 $452.95 $30.00 $6 953.61 $1.008 $7 696.08 $742.47 79 8,/25/2 9/1/2003 7700 9/1/2003 7699 7637 0.6475 $6 472.36 $453.07 $30.00 $6 955.42 $1.008 $7 696.10 $742.67 60 8,/25/2 9/2/2003 6000 9/2/2003 7632 7632 0.8558 $6 531.47 $457.20 $30.00 $7016.67 $1.008 $7 693.06 $674.39 81 9/2/2 9/4/2003 6000 9/4/2003 6008 5960 0.8556 $5 100.57 $357.04 $30.00 $5 467.61 $1.008 $6007.68 $520.07 62 9/2/2 9/5/2003 7700 9/5/2003 7701 7642 0.8558 $6540.02 $457.60 $30.00 $7 027.63 $1.008 $7 703.14 $675.31 63 9/2/2 9/6,/2003 7700 9/6,/2003 6004 5971 0.8558 $5 109.96 $357.70 $30.00 $5 497.68 $1.008 $6016.77 $521.09 64 9/2/2 9/8,/2003 6000 9/8,/2003 6004 5963 0.8558 $5 103.14 $357.22 $30.00 $5 490.36 $1.008 $6010.70 $520.34 85 9/212 9/9/2003 6000 9/9/2003 5999 5953 0.6106 $4 625.50 $337.79 $30.00 $5193.29 $1.008 $6000.62 $607.34 86 9/8,/2 9/10/2003 6000 9/10/2003 6002 5963 0.6106 $4633.61 $338.35 $30.00 $5 201.96 $1.008 $6010.70 $606.74 87 9/8,/2 9/11/2003 6000 9/11/2003 6004 5971 0.6106 $4640.09 $338.81 $30.00 $5 208.90 $1.008 $6016.77 $609.67 86 9/8,/2 9/12/2003 6000 9/12/2003 6007 5971 0.6106 $4640.09 $338.81 $30.00 $5 208.90 $1.008 $6016.77 $609.67 89 9/8,/2003 9/13/2003 6000 9/12/2003 9/13/2003 6000 5962 0.6106 $4 632.60 $338.30 $30.00 $5 201.10 $1.008 $6009.70 $606.60 90 9/8,/2003 9/15/2003 6000 9/15/2003 6000 5962 0.8106 $4 632.80 $338.30 $30.00 $5 201.10 $1.008 $6009.70 $606.60 91 9/8,/2003 9/16,/2003 6000 9/16,/2003 6002 5955 0.8136 $4646.18 $339.23 $30.00 $5 215.41 $1.008 $6002.64 $787.23 92 9/15/2003 9/17/2003 6000 9/17/2003 6005 5972 0.6136 $4660.01 $340.20 $30.00 $5 230.21 $1.008 $6019.76 $789.56 93 9/15/2003 9/18,/2003 6,000 9/18,/2003 6009 5973 0.8136 $4 660.63 $340.26 $30.00 $5 231.09 $1.008 $6,020.76 $769.70 94 9/15/2003 9/19/2003 9/18,/2003 95 9/15/2003 9/20/2003 9/18,/2003 96 9/15/2003 9/22/2003 6000 9/22/2003 6004 5966 0.8136 $4 855.13 $339.86 $30.00 $5 224.99 $1.008 $6 013.73 $786.74 97 9/15/2003 9/23/2003 6000 9/23/2003 6006 5958 0.7566 $4 507.82 $315.55 $30.00 $4 853.37 $1.008 $6 005.66 $1152.29 98 9/22/2003 9/24/2003 6000 9/24/2003 6000 5962 0.7566 $4 510.85 $315.76 $30.00 $4856.61 $1.008 $6009.70 $1153.09 99 9/22/2003 9/25/2003 6000 9/25/2003 5998 5974 0.7566 $4 519.93 $316.40 $30.00 $4 866.33 $1.008 $6021.79 $1155.46 100 9/22/2003 9/26,/2003 6000 9/26,/2003 6004 5969 0.7566 $4 516.15 $316.13 $30.00 $4 862.26 $1.008 $6 016.75 $1154.46 101 9/22/2003 9/27/2003 7700 9/27/2003 7700 7662 0.7566 $5 797.07 $405.79 $30.00 $6 232.86 $1.008 $7723.30 $1 490.43 102 9/22/2003 9/29/2003 6000 9/29/2003 6005 5965 0.7566 $4513.12 $315.92 $30.00 $4 859.04 $1.008 $6012.72 $1153.68 103 9/22/2003 9/30/2003 6000 9/30/2003 6000 5969 0.7908 $4 720.29 $330.42 $30.00 $5060.71 $1.008 $6016.75 $936.05 104 9/29/2003 10/1/2003 6000 10/1/2003 6005 5979 0.7908 $4 728.19 $330.97 $30.00 $5 089.16 $1.008 $6026.63 $937.67 105 9/29/2 10/2/2003 10/1/2003 106 9/29/2003 10/3/2003 6000 10/3/2003 6003 5974 0.7908 $4 724.24 $330.70 $30.00 $5,064.94 $1.008 $6 021.79 $936.86 107 9/29/2003 10/4/2003 7700 10/4/2003 7660 7 0.7908 $6191.96 $433.44 $30.00 $6 655.40 $1.008 $7 892.64 $1 237.24 108 9/29/2003 10/6,/2003 6000 10/6,/2003 6015 5990 0.7908 $4 736.89 $331.58 $30.00 $5 098.47 $1.008 $6037.92 $939.45 109 9/29/2003 10/7/2003 6000 10/7/2003 6004 5977 0.6410 $5 026.66 $351.87 $30.00 $5 408.52 $1.008 $6 024.82 $616.29 110 10/6,/2003 10/8,/2003 6000 10/8,/2003 6001 5962 0.6410 $5 030.86 $352.16 $30.00 $5 413.02 $1.008 $6 029.86 $616.63 111 10/6,/2003 10/9/2003 6000 10/9/2003 6010 5964 0.6410 $5 032.54 $352.28 $30.00 $5 414.62 $1.008 $6 031.87 $617.05 112 10/6,/2003 10/10/2003 6000 10/10/2003 6000 5979 0.6410 $5 028.34 $351.98 $30.00 $5 410.32 $1.008 $6026.63 $616.51 113 10/6,/2003 10/11/2003 6000 10/10/2003 10/11/2003 6000 5980 0.6410 $5 029.18 $352.04 $30.00 $5411.22 $1.008 $6027.64 $616.62 114 10/6,/2003 10/13/2003 10/10/2 115 10/6,/2003 10/14/2003 10/10/200 TOTAL &20900 ~--:--:::-7 620 969 617077 ~ , .., f ~~ ,..,. , -.. ~ ---,--•c $544 734. 75 $l522 013.&2 $77 278.87 1 ~,, ~\~'->~lie pmb 10/2112003 REQUEST FOR EXCEPTION TO CONTRACT RE# SCott o ,eil../lf 0/0t?t-' 1. Project Title: 2. Division: 3. Source of Funds: 4. Budget Codes: Warren County PCB Landfill Detoxification (CO#19) Waste Management Appropriations:~--------Receipts: -"--------------- Match Required: -"-----------Federal: GL Company: 1604 GL Account: 53-2199 GL Center:_-----"4-"-84-'-5"'----- 5. Is there a deadline for obligation of these funds? If so, date: _______ _ No~ 6. Type of contract requested: Contract for Services ___________ _ Award of DENR Grant Funds _________ _ Amendment to existing contract/grant ____ ✓ __ _ 7. Proposed Vendor/Recipient: Shaw Environmental & Infrastructure 8. Summary of work/activities to be performed under this contractual arrangement: The contractor purchased fuel directly the last week of operations. The contractor requested this in order to avoid having fuel at the end of the job that couldn't be used . The contract treatment cost was tied to a base fuel price. The cost of fuel purchased exceeded that base. Per the contract, Shaw is entitled to additional compensation. 9. Justification of Need for Contract: A) Was this vendor selected through a competitive process? ✓Yes ___ No ___ Will Be B) Explanation of why this work cannot be performed within the resources of the DENR Agency: DENR does not have the equipment, staff, or expertise to operate a soil remediation facility. C) Is there a State Agency/University that could perform th is work? __ Yes ✓No D) If Yes, provide a list of those agencies: E) Contacts made to determine the ability of other state agencies/universities to perform this work (name of contact, agency, telephone number and response): None F) If not utilizing another state agency/university, state the reason : Same as 9 (B). G) Calculation of available funding for this contract. Include amount available and amount previously obligated/approved to be obligated : Funds to cover amendment will come from savings due to the state purchase of fuel. SUBMITTED BY: ~ X3~ Phone: 733-4996 x308 Date:_1"-'1"""/0"-5"'"'.'--'/0~3~-- Contact Person for questions regarding this contract: Pat Backus Phone: 733-4996 x308 Ae ::::::::::: Qt?) iL~:;:;on m,ecto, R~.' __ .c, : FD ~ Disapproved _1...,q.~~,,-;~,.,.~~----+.~,_/_, ________ Chief Deputy Date Transmitted to Purchase and Services: _____________ _ FORM 2800 AGREEMENT INFORMATION & CONTRACT BUDGET ENCUMBRANCE DENR DIVISION OF PURCHASE AND SERVICES 1. PARTIES TO THIS AGREEMENT ASSIGNED BYPURCHASE & SERVI "' *DENR CONTRACT NO: SCO# 010440101A *PURCHASE ORDER NO: REVISION NO: CO#19 A. B . DENR Division of: ..-----------------------------Contractor (Name Contract Issued To:) Waste Management Division Section Division Address (MSC#, City, State, Zip) 1646 Mail Service Center Ralei h NC 27699-1646 Division Contract Administrator Patricia M. Backus, P.E. Division Director/Authorized Agent Telephone No. (919) 733-4996 X 308 Date 3. DIVISION CONTRACT COORDINATOR: Brenda Rivers Shaw Environmental & Infrastructure I.R.S. Number or Social Security Number I Check if Applicable 753044680 _ Private and/or Non-Profit Address (to which checks will be mailed) Wire Transfer U.S.Bank, (Wire Transfer) ABA#081000210 Acct#-152302010748 (City, State, Zip) St. Louis, MO 63195-6786 Please check one of the following: African American owned Woman owned _Handicapped owned _ Hispanic owned _ Other minority owned ✓ None of the above Contractor Contact Person/Key Personnel: Gary W. Duke, P.E. I Telephone Number (609) 588-6373 ---------------PHONE NO: --~(9_1_9~) _73_3_-4_9_9_6_x_20_4 __ _ 4. FISCAL YEAR: __ ___;F_Y:......:;..03;:;..--=-0..;,.4 _____ _ 5. START DATE: ___ -'M=ar'""c""h_1'""3'-'--"2""0""0"""1 ________ (Contractor cannot begin work until contract is executed by DENR) 6. TERMINATION DATE: November 10 2003 (Limit to time required; contract cannot exceed 3 years) 7. CURRENT CONTRACT AMOUNT: __ ~$_1-'-3~2-'-3~6~8-'-53~.-'-65 _______________________ _ 8. *AMENDMENT AMOUNT: __ ~$_2~3_13_._5_6 ___ (/ndicate Previously Assigned Contract No. & PO in appropriate block ABOVE) 9. REVISED CONTRACT TOTAL: $ ___ ....,$'-"1..;:;3...,;,5:;..;:5""9"'-A..;..1;_4"".7;_7'--_______ ..... (Original Amount+ Amendment Increase/Decrease) 10. UNENCUMBRANCE (Balance remaining in Contract that will not be paid to Contractor): $ __________ _ 11. ITEM DESCRIPTION I 12. DENR CONTRACT AMOUNT Contract Purpose/Brief Narrative: (Estimate of Expenditures each FY if multiple year contract) Detoxification of the Warren County PCB Landfill. Change order 19 is a fuel adjustment change order for fuel purchased by the Add line item 25 -Fuel adjustment for fuel contractor during October, 2003, per provisions of the contract. purchased by contractor in October, 2003 = $2,313.56 13. CFDA CODE: (Catalog of Federal Domestic Assistance Code, if applicable) 14. GL COMPANY: 1604 GL ACCT: 53-2199 GL CENTER 4845 15 Federal Funds State Funds Contractor Match Other Funds TOTAL PROJECT COST $ $ 13,559,414.77 $ $ $ 13,559,414.77 16. Division Budget Officer (Mandatory Signature) Date 1 OC-24 rev. 9-88 INSTITUTION: PROJECT: STATE CODE & ITEM : CONTRACT FOR: CONTRACTOR: NCDENR STATE CONSTRUCTION OFFICE CHANGE ORDER NO. 1§. Warren County PCB Landfill Detoxification ID#: 010440101A BCD Detoxification Shaw Environmental & Infrastructure, Inc. 200 Horizon Center Blvd, Trenton, NJ 08691-1904 D OR Owner Request X CR Contractor Request D DR Designer Request D CC Concealed Condition D DE Design Error D DO Design Omission □ SC Schedule Change □ OTOther Under the terms of the-Contract and without invalidating the original provisions thereof, the following change in work is authorized for the change in contract amount herein set forth: (Description of change order attached) Increase line item 11, BCD soil treatment, by 3,622.71 tons (from 78,000 to 81,622.71 tons), per contract General Conditions Article 19. c. 1. The time of completion including previous orders is 956 calendar days and shall be increased by 17 calendar days by this change order, for a revised contract date of completion of November 10, 2003. CONTRACT COST SUMMARY 1. Original Contract Amount 2. Amt. Of Previous Orders 3. Amt. Of This Order: ADD ADD $ 7,217,094.55 $ 320,247.56 Deduct Deduct $638,240.90 $ 0.00 TOTALS $6,658,000.00 4. Total additions lines 2 &3 $ 7,537,342.11 Minus Total Deducts: $638,240.90 $6,899,101 .21 (Line 4 shall show the net amount to be added or (deducted) from the contract amount.) 5. Revised Contract Total Amount 6. The Owner certifies that the contingency fund balance after this change is $13,557,101.21 $ Fill in one copy only I certify that my Bonding Company will be notified forthwith that my contract has been increased by the amount of this change order, and that a copy of the approved change order will be mailed upon receipt by me to my surety. Shaw Environmental & Infrastructure, Inc. By: 4 ~ L?~ (Contractor) ~ 200 Horizon Center Blvd Gary W. Duke, P.E. Trenton, NJ 08691-1904 Project Manager _E_a_rt_h_T_e_ch ___________ By: A (J c) ,/-aJ (Designer) r . _N_C_D_E_N_R~,_D_iv_of_W_a_st_e_M_a_n_a~g~e_m_e_n_t ___ By: (Owner) State Construction Office By: Q ,.,,?-/~~ -----------------~ 7 -----------------By: Other approving Agency (if needed) DISTRIBUTION: 1 original to State Construction 1 original to Owner 1 original to Board or Commission (if any) 1 original to Designer 1 original to Contra 1 original to Suret}1<o '(Date) (Date) (Date) REQUEST FOR AUTHORIZATION TO CHANGE DATE: October 28, 2003 STATE CODE: SCO#010440101A REQUEST NO.: 18 NCDENR Earth Tech PROJECT NAME: Warren County PCB Landfill OWNER: CONTRACTOR: Shaw Environmental & Infrastructure, Inc. DESIGNER: CONTRACT FOR: BCD Detoxification DESCRIPTION OF CHANGE: Increase line item 11, BCD soil treatment, by 3,622.71 tons (from 78,000 to 81,622.71 tons), per contract General Conditions Article 19.c.1. Increase schedule by 17 days. REASON FOR CHANGE: Increase contract quantity to cover revised estimated amount of PCB contaminated soil on site requiring treatment. SUMMARY REVIEW OF CONTRACTOR'S ESTIMATE FOR TIME AND COST: (Attach Contractor's detailed cost breakdown of labor and materials). Increase line 11 -"BCD soil treatment" $320,247.56 Total change order value: $320,247.56 DESIGNER SUMMARY: 1. Schedule items affected by this change: Critical path item "BOC soil treatment increases by 17 days, see attached spreadsheet. 2. Can Contractor mitigate the change without requiring a contract time extension? No 3. Will the change require a contract time extension for other contractors? No Which? n/a 4. Are additional costs indicated by reason of the time extension? No If so they must be included in 5 & 6 Below. CONTRACTOR'S ESTIMATE DESIGNER'S ESTIMATE 5. Estimated cost of change: ___...$--'3_2..;_0,'-'2_47_ . ..;..56 _______ _ 6. Estimated lime extension field cost (if any) Covered by unit price for Shaw DESIGNER RECOMMENDATION AND CERTIFICATION: I certify that I have reviewed all aspects of this change order and have determined that it is in the best interest of the owner to have the work accomplished. I have also determined that the cost and time allotment are fair and equitable, and I recommend acceptance by the owner. Approved by: --:t"'u~--~~~) _ _f.L._~~----Date: Title: a;; t )~~ I J / 4. ( c3 Warren County PCB Landfill Detoxification Project NC SCO Project 1D#010440101A Shaw project #827062 Treated Soil Batch Weight and Treatment Certification Log A B C D E G H K M N 0 Batch# I Bin #I Date I Time I complete complete Date I Time I Belt scale I Belt scale I Belt I Residuals I Net Iona I Shaw I Name of~b Lab start start complete start scale recycled fnr batch sample # lab n,port # n,port {Ions) · {tons) not tons {tons) date SHAW INVOICE 131 FOR PERIOD THROUGH 9130103 COVERED THROUGH BATCH #235, TOTAL INVOICED TONS TO DATE• 77,144.22, NET FOR PERIOD• 8,894.36 2361 3 I 10/03/03 I 1:00 11oto2J031 0:10 I 88,180.00 I 87,838.oo I 342.oo I 3.80 I 338.20 13-236 IP1111dign1 I _ -81553110/06/03 2371 4 I 10/04/03 I 3:05 I 10/03/031 1:00 I 88,530.00 I 88,180.oo I 350.oo I 7.15 I 34ZJ!5 IH27 IParadigm~~_l_lQ/_0!!/93 2381 3 I 10/05/03 I 4:15 I 10!04to3l 3:o5J 88,880,00J __ 88,53o.oo I_ 35Q,QOl___6.20 J __ ~.80 J3-238 !ParadigmJ 81555110/06/03 2391 2 I 10/06/03 I 15:05 I 10/05/031 4:15 I 89,262.00 I 88,880.00 I 382.oo I 10.51 I 371.49 12-239 !Paradigm I 81657110/08/03 2401 1 I 1oto7to3 I 15:10 I 10/06/03115:051_ 89,602,!Q 1__89,262,oo l _ 340,10 I ___ n10 I 322.40 11-240 I Paradigm I 81658110/08/03 2411 4 I 10/08103 I 22:ao I 10/07/03121:201 89,952.00 I 89,602.10 I 349.90.I 8.02 I 341.88 14-241 !Paradigm I 81968110113/03 2421 3 I 10/09/03 I 22:00 110108/03/22:301 90,303.oo I -~9,952.00 I 351.oo I 5.15 I 345.85 13-242 !Paradigm I 81980110113/03 2431 2 I 10/11/03 I 1:00 I 10/09to3122:ool 90,655.oo I 90,303.oo I 352.oo I 6.81 I 345.1912-243 IParadigml 81981110/13/03 2441 3 I 10/12/03 I 7:ao 110111t031 1:00 I _ 91,005.oo I _90,655.oo I __ 350.oo I _ 1.a1 I _ 342,63 13-244 ___ Iearadig_m l _ _ 81982110/13/03 2451 1 I 10/13/03 I 3:00 I 10/12/031 7:30 I 91,267.oo I 91,005.oo I 262.00 I 5.19 I 258.81 11-245 !Paradigm I 81983110/13/03 2461 3 I 10114/03 I 11:30 110113/031 3:00 I 91,657.oo I 91,267.oo I 390.oo I 24.49 I 385.51 13-246 IP■radigm I 82078110/15/03 2471 4 110,15/03 I 9:26 I 10/14/03l 11:30I 91.882.00 I 91.657.00 I 225.00 I 1.11 I 217.89 !4-247 lpmgm I 82083110/16/03 248 2 10116/03 16:30 10115/03 9:26 92,233.00 91,882.00 351.00 _ 12.61 338.392-248Paradigm _ 8228710/20/03 2491 3 I 10/17/03 I 3:30 I 10116/03l 16:3ol 92,548.00 I 92,233.00 l 315.oo l 13.90 I 301.10 13-249 !Paradigm l 82268110/20/03 2501 4 I 10118103 I 18:30 110117to31 3:30 l 92,932.40 I_ 92,548.oo l_ 3_84.40 l 8.58 I __ 375.82 14-.250 _ !Paradigm! ___ 82269/ 10120/03 p Reaultaof PCB ■nalysia {mg/kg-ppm) or0.SofBQL mu■tbe<0.5 0.140 0._QI2 0.060 0.110 0.140 0.058 0.065 0.110 0.068 0.048 0.120 0.019 0.200 0.190 0.430 a R Approved, I Rojectad, can be rrNJlt be backfilled nttrnted s Total Iona approved 77,142.69 77,4!JQ.89 77,m.74 ''•']'.6i16'1',&U 78,539.03 78,861.43 79,203.31 79,549.16 ]_9,894.35 , •.. +:11~36lli8} 80,493.79 80,859.30 81,077.19 81,4_15.58 l·••·•Hll':C1'o1&.61L 8Jc~50 82,092.50 TOTALS 92,887,37 2.681,12 I_ 90.200.2_5. I ___ . . I _ --··· 1. . .. _ I ___ _ __ :_ I _ _ __ L I . _ .. -__ 1 ez,os2.50 9ili200.2$ •• : 90i200,25:::~+:VA4UESOIIII.THESEoIH£!E!;,,P;l!;S:t.A\1~'!':/il,\(1'C:a:rn::: ;°', ,, , ,,, , , , •.•,,,.,,:,y,::,;" ... 89.,11:?!,~2 .. GRAND TOTAL, NET TONS OF TREATED SOIL file ,,.,.._ for bfank form: batch~ loon 100802 SCALE ENTRIES CHECK belt scale net tons to date ADJUSTMENTS initial start tons gap between batches 4 & 5 batch e, see note Total adjustments Adjusted tons to date Most recent ~compete• tons 92,887.37 92.:932.40 30.61 7.65 6.77 ~ L--..AUiii :aidiiiii!iii!Jdr:i;lay6alc!!;1~••: :~ :,....:9Cl~po:,2:~::· Summary of Iona ■pprowd, by month Approved in : Sept 02 Oct02 Nov02 Dec02 Jan 03 Feb 03 March 03 April 03 May03 June 03 July03 August 03 Sept 03 1,918.79 7,992.40 4,338.55 1,721,61 6,938.03 6,468.57 4,325.91 6,819.12 5,399.&6 8,179.93 6,364.18 7,785.10 8,894.36 77,144.22 T Total Iona ntjected 7,735.02 7,735.02 7.7~M2 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 7,735.02 70735.02 7,735.02 7,735.02 u approwd_ batch tona•PCB •K"P"Q 0.0000 47.3480 24.6852 20.6280 40.8639 45.136'0 19.8290 22.4803 37.9709 23.296'8 12.3269 43.8612 4.0310 67.6780 57.2090 161.&026 0.0000 V Running Total of col u 10580.0846 10627.4328 10652.1178 10672.7458 10713.&097 10758.7457 10778.5747 10801.0550 10839.0259 10862.3247 10874.&516 10918.5128 10922.5437 10990.2217 11047.4307 11209.0333 11209.0333 Weighted avg PCB for Oct only r \ w Weighted Avg PCB cV/5 mustbe<0.2 0.137 0.137 0.137 0.137 0.136 0.136 0.136 0.136 0.136 0.135 0.135 0.135 0.135 0.135 0.135 0.137 0.137 0.127 . . DUKEFILE: CO #15 added days.xis Warren County PCB Landfill -thermal production 80,000 70,000 60,000 .c 50,000 B cu .0 -0 ~ schedule projection, "straight line" from 1/7 8/31/2003 68,248 .fl 40,000 IA -0 IA 117/2003 16,613 236 51,636 for 78,000 tons total cu IA ton/cal.dy 219 C 0 30,000 I-ton to go 9,752 days to go 44.57 for 81,622.71 tons total ton/cal.dy 219 20,000 ton to go 13,375 days to go 61.13 Additional days required for increase from 78,000 to 81,622.71 tons 10,000 add days 16.56 round up 17.00 N N N N N N N N N N O') O') O') O') O') O') O') O') O') O') O') O') O') O') O') O') O') ~ e a e ~ e ~ e e ~ e e 0 e ~ e ~ ~ 0 ~ a e e e ~ ~ 0 co ..,. ~ 0) M 0 ..,. ;:::: N ~ .,;i O') ... ~ ,;i ~ ~ li; a e ~ ~ N ~ ~ ~ ~ ~ e !2 ~ fa ~ ~ ~ ~ a, 0 ~ :: ,;i ;; ;; ,;i O') ~ "' in "' co ;:::: ... a, 0 0 0 ~ ~ ~ ~ ~ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Date batch started REQUEST FOR EXCEPTION TO CONTRACT RE# .sc Mo104L/v101 A 1. Project Title: Warren County PCB Landfill Detoxification (CO#18} 2. Division: Waste Management 3. Source of Funds: Appropriations: Receipts: Federal: Match Required: 4. Budget Codes: GL Company: 1604 GL Account: 53-2199 GL Center: 4845 5. Is there a deadline for obligation of these funds? If so, date: _______ _ 6. Type of contract requested: Contract for Services ___________ _ Award of DENR Grant Funds _________ _ Amendment to existing contract/grant ____ ✓ __ _ 7. Proposed Vendor/Recipient: __ ---=S'-'-h""a""w;....=.E'-'-nv"""i"'"'ro""'n..;.;.m.;..ce=n""t=a""'"I =&....:.l'-'-nf.:..c.r=as=t:.:....ru=c~t=u'--'re'----------------- 8. Summary of work/activities to be performed under this contractual arrangement: More contaminated soil was in the landfill than indicated by the original landfill construction information. Original contract quantity was 72 ,000 tons. Change order #13 increased the quantity to 78 ,000 tons. The final treated quantity was 81,622.71 tons. This change order is for treatment of the additional 3,622.71 tons. 9. Justification of Need for Contract: A) Was this vendor selected through a competitive process? ✓Yes ___ No ___ Will Be B) Explanation of why this work cannot be performed within the resources of the DENR Agency: DENR does not have the equipment, staff, or expertise to operate a soil remediation facility. C) Is there a State Agency/University that could perform this work? __ Yes ✓No D) If Yes , provide a list of those agencies: E) Contacts made to determine the ability of other state agencies/universities to perform this work (name of contact, agency, telephone number and response): None F) If not utilizing another state agency/university, state the reason: Same as 9 (B). G) Calculation of available funding for this contract. Include amount available and amount previously obligated/approved to be obligated: Funds to cover the change will be from a combination of a reduction of other itefnsin the contract and additional funds authorized by the General Assembly and DENR. SUBMITTED BY: \'t?u ~ Phone: 733-4996 x308 Date :_1'-'1.:....:/0::....::5=./-=-0=3 __ ~;;t:~:::;on for questions regarding thisn •~ ~:;-;/~.'£ Phone 733-4996 x308 ~ Disapproved -=M-"---' ...... ~ .... ~~--/L~~~~.,..___...,~---.. ...... --Division DirectorT! ·~ ,,..,._:',i,...,;-,~-;-• __ Approved Disapproved ------,..,......,;---------BPA _t\,,Pc. : .. , .. _ •_,· ~-,D ~ Disapproved ~ Chief Deputy Date Transmitted to Purchase and Services: _____________ _ FORM 2800 AGREEMENT INFORMATION & CONTRACT BUDGET ENCUMBRANCE DENR DIVISION OF PURCHASE AND SERVICES 1. A. PARTIES TO THIS AGREEMENT DENR Division of: Waste Management Division Section Division Address (MSC#, City, State, Zip) 1646 Mail Service Center Ralei h NC 27699-1646 Division Contract Administrator Patricia M. Backus, P.E. Telephone No. (919) 733-4996 X 308 ASSlGNEO BYPURCHAS~ {!, 'SERVfCii *DENR CONTRACT NO: SCO# 010440101A *PURCHASE ORDER NO: REVISION NO: C0#18 B. Contractor (Name Contract Issued To:) Shaw Environmental & Infrastructure I.R.S. Number or Social Security Number 753044680 I Check if Applicable _ Private and/or Non-Profit Address (to which checks will be mailed) Wire Transfer U.S.Bank, (Wire Transfer) ABA# 081000210 Acct# -152302010748 (City, State, Zip) St. Louis, MO 63195-6786 Please check one of the following: African American owned Woman owned _Handicapped owned _ Hispanic owned _ Other minority owned ✓ None of the above Contractor Contact Person/Key Personnel: Gary W. Duke, P.E. I Telephone Number (609) 588-6373 3. DIVISION CONTRACT COORDINATOR:_....:B=..:r-=-e'-'-nd::..:a'-Rc.:;ic.=..ve=..:r-=-s--------PHONE NO: __ _.(-=-91.:...:9:...l...:..7-=-33-=---'4-=-99::..;6'-x'-"2=-=0-'4 __ _ 4. FISCAL YEAR: ___ c...FY-'--"0"""3--'-0'-4'-------- 5. START DATE: ___ ....;.M~ar'"'c""'h_1'"'3'--'-"2"'0-"0-'-1 ________ (Contractor cannot begin work until contract is executed by DENR) 6. TERMINATION DATE: November 10 2003 (Limit to time required; contract cannot exceed 3 years) 7. CURRENT CONTRACT AMOUNT: __ ~$_1_3~2_3~6~8_53_._65 _______________________ _ 8. *AMENDMENT AMOUNT: __ ~$_3_2_0~2_4_7_._56 ___ (/ndicate Previously Assigned Contract No. & PO in appropriate block ABOVE) 9. REVISED CONTRACT TOTAL : $ ___ _,$'--'1"""3""',5'"'5'-'-7..,_11-'-'0'"'1c.c.2=-1-'-----------'(0riginal Amount+ Amendment Increase/Decrease) 10. UNENCUMBRANCE (Balance remaining in Contract that will not be paid to Contractor):$ __________ _ 11. ITEM DESCRIPTION 12. DENR CONTRACT AMOUNT Contract Purpose/Brief Narrative: (Estimate of Expenditures each FY if multiple year contract) Detoxification of the Warren County PCB Landfill. Change order 18 is an increase in the contract value due to the treatment of additional Increase line item 11 (BCD soil treatment) contaminated soil. = $320,247.56 13. CFDA CODE: (Catalog of Federal Domestic Assistance Code, if applicable) 14. GL COMPANY: 1604 GL ACCT: 53-2199 GL CENTER 4845 15 Federal Funds State Funds Contractor Match Other Funds TOTAL PROJECT COST $ $ 13,557,101 .21 $ $ $ 13,557,101 .21 16. 11/t-/03 Division Budget Officer (Mandatory Signature) Date I I OC-24 rev. 9-88 INSTITUTION: PROJECT: STA TE CODE & ITEM : CONTRACT FOR: CONTRACTOR: NCDENR STATE CONSTRUCTION OFFICE CHANGE ORDER NO. 1!t Warren County PCB Landfill Detoxification ID#: 010440101A BCD Detoxification Shaw Environmental & Infrastructure, Inc. 200 Horizon Center Blvd, Trenton, NJ 08691-1904 D OR Owner Request X CR Contractor Request D DR Designer Request D CC Concealed Condition D DE Design Error D DO Design Omission □ SC Schedule Change □ OTOther Under the terms of the Contract and without invalidating the original provisions thereof, the following change in work is authorized for the change in contract amount herein set forth: (Description of change order attached) Add new line item #25, for fuel adjustment change order for fuel purchased by contractor during October, 2003, per provisions of specification paragraphs 01270-1.03-C-4d and 6b. The time of completion including previous orders is 973 calendar days and shall be unchanged by Q calendar days by this change order, for a revised contract date of completion of November 10, 2003. CONTRACT COST SUMMARY 1. Original Contract Amount 2. Amt. Of Previous Orders 3. Amt. Of This Order: ADD ADD $ 7,537,342.11 $ 2,313.56 Deduct Deduct $638,240.90 $ 0.00 TOTALS $6,658,000.00 4. Total additions lines 2 &3 $ 7,539,655.67 Minus Total Deducts: $638,240.90 $6,901,414.77 (Line 4 shall show the net amount to be added or (deducted) from the contract amount.) 5. Revised Contract Total Amount 6. The Owner certifies that the contingency fund balance after this change is $13,559,414.77 $ Fill in one copy only I certify that my Bonding Company will be notified forthwith that my contract has been increased by the amount of this change order, and that a copy of the approved change order will be mailed upon receipt by me to my surety. Shaw Environmental & Infrastructure, Inc. By: ~ ~ £?__.L _______ (_C_o-nt-ra-c-to_r_)--~--- 200 Horizon Center Blvd Gary W. uke, P.E. Trenton, NJ 08691-1904 Project Manager J2 du-J By: -----------------Earth Tech (Designer) _N_C_D_E_N_R~, _D_iv_o_f_W_a_s_te_M_a_na~g-e_m_e_n_t ___ By: Cf}~~ )F, . ~ (Owner) State Construction Office -----------------By: Other approving Agency (if needed) DISTRIBUTION: 1 original to State Construction 1 original to Owner 1 original to Board or Commission (if any) 7(D e) (Date) (Date) ~ftcJ3 (Date) REQUEST FOR AUTHORIZATION TO CHANGE DATE: October 29, 2003 REQUEST NO.: OWNER: DESIGNER: 19 NCDENR Earth Tech DESCRIPTION OF CHANGE: STATE CODE: SCO#010440101 A PROJECT NAME: Warren County PCB Landfill CONTRACTOR: Shaw Environmental & Infrastructure, Inc. CONTRACT FOR: BCD Detoxification Add new line item #25, for fuel adjustment change order for fuel purchased by contractor during October, 2003, per provisions of specification paragraphs 01270-1.03-C-4d and 6b. No change in schedule. REASON FOR CHANGE: Reimburse contractor for unit price cost difference for fuel from base cost established by Owner in contract bid documents. SUMMARY REVIEW OF CONTRACTOR'S ESTIMATE FOR TIME AND COST: (Attach Contractor's detailed cost breakdown of labor and materials). Add line 25 -fuel adjustment for fuel puchased by Contractor in October, 2003 Total change order value: DESIGNER SUMMARY: 1. Schedule items affected by this change: None ADD ADD 2. Can Contractor mitigate the change without requiring a contract time extension? Yes $2,313.56 $2,313.56 3. Will the change require a contract time extension for other contractors? No Which? n/a 4. Are additional costs indicated by reason of the time extension? No If so they must be included in 5 & 6 Below. CONTRACTOR'S ESTIMATE DESIGNER'S ESTIMATE 5. Estimated cost of change: --'-$_2 .... ,3_1_3._56 _______ _ 6. Estimated time extension field cost (if any) _N_/a _________ _ DESIGNER RECOMMENDATION AND CERTIFICATION: I certify that I have reviewed all aspects of this change order and have determined that it is in the best interest of the owner to have the work accomplished. I have also determined that the cost and time allotment are fair and equitable, and I recommend acceptance by the owner. Approved by: ___,...,k~l __ ,~-_) ..... {nR~. ____ Date: Uct u1 ri qt: Title: .. Filename: CO #19 FUELLOG Oct 03 102903 backup data line # 2 3 4 DATE AMT PRE-TAX DELIVERED DELIVERED TOTAL SALES TAX 10/14/03 7478 $7 088.92 $496.22 10/16/03 7488 $7,049.73 $493.48 10/17/03 6090 $5,701.82 $399.13 TOTALS 21,056 $19,840.47 $1,388.83 Check on calculations Avg actual cost = total $ I total gal Avg actual cost less contract cost Avg cost difference x total gal TOTAL $7 585.14 $7,543.21 $6,100.95 $21,229.30 $1 .0082 $0.0916 Difference from Running total $0.916666 of difference contract base from $0.916666 cost for this contract base load Calculations of fuel price adjustment change order fom NCDENR to Shaw for this month Total fuel purchased, from above Deduct quantity of oil added to feed soil Total Gallons 21,056 0 2 3 4 5 Deduct value of line 2 at avg actual cost for month Net fuel used to thermally treat soil 21,056 6 7 Value of fuel quantity on line 4, at contract base rate of $1.10/gal divided by 1.2 overhead & profit factor Cost differential for all fuel used to thermally treat soil Tons of soil treated to specification this month 8 Tons of soil treated but not meeting specification this month 9 10 11 Tota·I tons of soil treated this month Percentage of total soil treated to specification this month Cost differential subject to change order = line 6 • line 1 o 12 IF line 11 is NEGATIVE, calculate CREDIT due to NCDENR as line 11 • 1.1 13 IF line 11 is POSITIVE, calculate ADJUSTMENT due to SHAW as line 11 • 1.2 14 Amount due from NCDENR to Shaw Total Cost $21,229.30 $0.00 $21 ,229.30 $19,301 .33 $1 ,927.97 4,948.26 4,948.26 100.00% $1,927.97 $2,313.56 $2,313.56 cost/gal with tax for load $1.01433 $1 .00737 $1 .00180 backup data line DATE AMT PRE-TAX # DELV'D DELV'D TOTAL 2 10/14/03 7478 $7,088.92 3 10/16/03 7488 $7,049.73 4 10/17/03 6090 $5,701.82 BOWERS BURROWS INC FUEL DELIVERY LOG TO MIDWEST SOIL REMEDIATION, IN Difference from $0.916666 contract base cost for this SALES TAX TOTAL load $496.22 $7,585.14 $730.31 $493.48 $7,543.21 $679.21 $399.13 $6,100.95 $518.45 These were last 3 loads aflter last state fuel delivery on 10/11 /03 GRAND TOTAL 21,056 $19,840.47 $1,388.83 $21,229.30 $1,927.97 Check on calculations Avg actual cost to date= total$/ total gal $1.0082 Avg actual cost to date less contract cost $0.0916 Running total of difference from $0.916666 contract base cost $730.31 $1,409.52 $1,927.97 $1,927.97 Avg cost difference x total gal to date $1,927.97 Value musfmatch running total Dukefile: c:\mydocs\nclf\Fuellog MSR 102903 FINAL.xis 2107B-1118-2180-51600 Page 1 cost/gal without cost/gal tax for with tax load for load $0.94797 $1.01433 $0.94147 $1.00737 $0.93626 $1.00180 FUELLOG MSR 102903 FINAL ■ .,.,_ .. & ■UIIIIOW8, INC. __ • Da....., Drift 15 · ttencleraon, NC 27131 , , 212..-2.0111 'IJL ~ 3123s ~~~ ro/L!41Jt"dfR Su V ADDRESS I BILLOFLADING#Z?}o/J~ ] PETROLEUM PI.ODUCT GALLONS UNIT PRICE TOT Al. PLUSGAct\lllR NO LEAD GASOLINE PUMRJM GASOUNE KE1'0SENE DIESEL FUEL -FUEL OIL #2 '.Jt/'l >? • '1¢-77') ?lJ8Y. C/:l. OTHER PACKAGES KIND UNIT PRICE TOTAL MISC. PETa.OLEUM -nn11rfl s OTHEIVMJSC. s I SAL£STAX sc,-; ~-~ ,~ --AUTifORIZED SIONA nJR.£ INVOICE TOT AL s"..,. -'J. r/ • awea & IIURIIOW8, INC. 11-~ IIO Dabney Drive Henderaon, NC 27131 212-tl2-4111 ~ 31236 ::10 A3~d SJii ADDRESS I BILL Of LADING • 6199 Jg o' PETROLBUM PROOUCT GALLONS UNIT PRICE TOT AL NO LEAD GAIOUNE PREMIUM GASOLJHE k!ROSENE DIESEL FUEL FUEL OJL#l OTHER KIND UNIT PRICE TOTAL MISC. PETllOLEUM ont.EIVMISC. SALES AUTHORIZED SIGNA TIJRE INVOIC • GWallS & ■UIUIOWS, INC. . -Dallney Drive 11.p Henderaon. NC 27131 , , 212-a2.0111 !q)'7il3 31237 ~~~TO =-~~d Zf = ADDllESS ------------------ PETl'OLEUM PRODUCT GALLONS UNIT PRICE TOTAL NO LEAD GASOLINE PllMIUM GASOLINE kEJlOSEN£ DIESEL FUEL FUEL OIL #2 OTHER MISC. PETROLEUM OTHEI/MISC. SALES TAX AUTHORIZED SIGNA nJR£ INV ICE TOTAL REQUEST FOR EXCEPTION TO CONTRACT 1. Project Title: 2. Division: 3. Source of Funds: 4. Budget Codes: Warren County PCB Landfill Detoxification (CO#17) Waste Management Appropriations:~--------Receipts:~------------- Match Required: ~----------Federal: GL Company: 1604 GL Account: 53-2199 GL Center: _ __,,4-=-84....:...5=------ 5. Is there a deadline for obligation of these funds? If so, date: _______ _ 6. Type of contract requested : Contract for Services ___________ _ Award of DENR Grant Funds ________ _ Amendment to existing contract/grant ____ ✓ __ _ 7. Proposed Vendor/Reci pient: __ ---=S;,.:..;h=ac.:..:wc...,;E=n:...:..v.:....:i.:....:ro::..:.n.:..:..m:...:..e=n-'-'t=a.:..,_I &=-..:.I:...:..nf:..:..ra=s=t::...;ru=c=-=-t=urc..::e;....._ _____________ _ 8. Summary of work/activities to be performed under this contractual arrangement: Change order #9 deducted $369,148 to cover the cost of fuel purchased by the state for the project. The deduction was based on an estimated fuel usage and an agreement signed by the state and Shaw. More fuel was required than estimated. This change order increases the deduction to reflect the final actual quantities purchased. 9. Justification of Need for Contract: A) Was this vendor selected through a competitive process? ✓Yes ___ No ___ Will Be B) Explanation of why this work cannot be performed within the resources of the DENR Agency: DENR does not have the equipment, staff, or expertise to operate a soil remediation facility. C) Is there a State Agency/University that could perform this work? __ Yes ✓No D) If Yes, provide a list of those agencies: E) Contacts made to determine the ability of other state agencies/universities to perform this work (name of contact, agency, telephone number and response): None F) If not utilizing another state agency/university, state the reason: Same as 9 (B). G) Calculation of available funding for this contract. Include amount available and amount previously obligated/approved to be obligated: See form OC-24 supporting information. SUBMITTED BY: ~ ~ Phone: 733-4996 x308 Contact Person for questions regarding th?')ntract: Pat Backus AP~LdS : rnsappmved ~ Approved Date: 11 /05./03 Phone: 733-4996 x308 Division Director BPA ~) Disapproved Disapproved ----------::----------..... //4~-· ,..~"'......_"-+· ________ Chief Deputy Date Transmitted to Purchase and Services: _____________ _ FORM 2800 AGREEMENT INFORMATION & CONTRACT BUDGET ENCUMBRANCE DENR DIVISION OF PURCHASE AND SERVICES 1. A. PARTIES TO THIS AGREEMENT DENR Division of: Waste Management Division Section Division Address (MSC#, City, State, Zip) 1646 Mail Service Center Ralei h NC 27699-1646 Division Contract Administrator Patricia M. Backus, P.E. Division Director/Authorized Agent Telephone No. (919) 733-4996 X 308 Date ASSIGNED BY PURCHASE & SERVICE *DENR CONTRACT NO: SCO# 010440101A *PURCHASE ORDER NO: REVISION NO: C0#17 B. Contractor (Name Contra.;t Issued To:) Shaw Environmental & Infrastructure I.R.S. Number or Social Security Number I Check if Applicable 753044680 _ Private and/or Non-Profit Address (to which checks will be mailed) Wire Transfer U.S.Bank, (Wire Transfer) ABA# 081000210 Acct# -152302010748 (City, State, Zip) St. Louis, MO 63195-6786 Please check one of the following: African American owned Woman owned _Handicapped owned _ Hispanic owned _ Other minority owned ✓ None of the above Contractor Contact Person/Key Personnel: Gary W. Duke, P.E. I Telephone Number (609) 588-6373 3. DIVISION CONTRACT COORDINATOR: __ B~r~e~nd=a~R_iv_er_s _______ _ PHONE NO: __ ..._{9::...1:..::9c,_) .:....73::..:3=--4.;..;9:..::9"°6-"x=-20=-4'---- 4. FISCAL YEAR: ___ .:....F..:..Y....:0:..::3....;-0=-4'-------- 5. START DATE: ___ ....;M..:.=.a'""rc"'h'-1'""3'-'-"2:..::0..:a0..:..1 ________ (Contractor cannot begin work until contract is executed by DENR) 6. TERMINATION DATE: October 24 2003 (Limit to time required; contract cannot exceed 3 years) 7. CURRENTCONTRACTAMOUNT: __ _,$~1~3~4~8~9~7-=-1~9-.:2.:....7 ______________________ _ 8. *AMENDMENT AMOUNT:. __ __,_(z.$-=2:.::5.:2.1..:,8:..::6:.::5"'"'.6:..:2,.,.) __ (lndicate Previously Assigned Contract No. & PO in appropriate block ABOVE) 9. REVISED CONTRACT TOTAL: $ ___ --'$'-"1'-"3'"",2::..:3::..:6c.,8-=-5::..:3c.c·..c.6-=-5----------'(Original Amount+ Amendment Increase/Decrease) 10. UN ENCUMBRANCE (Balance remaining in Contract that will not be paid to Contractor): $. ___ __:$,:.:2:..::5c.:::2"-'8"-'6::..::5:..:..6:::..:2=------------ 11. ITEM DESCRIPTION 12. DENR CONTRACT AMOUNT Contract Purpose/Brief Narrative: (Estimate of Expenditures each FY if multiple year contract) Detoxification of the Warren County PCB Landfill. Change order 17 is a reduction in the contract value due to the purchase of fuel by the Increase line item 20 (Credit for fuel state for the project. purchased by state) = ($252,865.62) 13. CFDA CODE: (Catalog of Federal Domestic Assistance Code, if applicable) 14. GL COMPANY: 1604 GL ACCT: 53-2199 GL CENTER 4845 15 Federal Funds State Funds Contractor Match Other Funds TOTAL PROJECT COST $ $ 13,236,853.65 $ $ $ 13,236,853.65 16. 11/to/03 Division Budget Officer (Mandatory Signature) Date I I