Loading...
HomeMy WebLinkAboutNCD980602163_20011005_Warren County PCB Landfill_SERB C_Detoxification NCSO ID# 01044010A Appendix H - Meeting Agendas and Minutes-OCRCopy l Warren County Landfill PCB Detoxification NCSCO ID #010440101A AppendixH Meeting Agendas and Minutes Prepared by Earth Tech 710 Corporate Center Dr. Suite 475 Raleigh, NC 27607 (1 of 1) AGENDA PROJECT INITIATION MEETING WARREN COUNTY PCB DETOXIFICATION DESIGN/BUILD PROJECT ID #6095220110 MARCH 13, 2001 8:30 AM Earth Tech 701 Corporate Center Drive, Suite 475 RALEIGH, NORTH CAROLINA 27607 1.0 INTRODUCTIONS 2.0 PROJECT REQUIREMENTS 2.1 Performance Basis 2.2 Design/Build Basis 2.3 Phase I/II Transition 2.4 Facility Construction 2.5 Performance Demonstration 2.6 EPA In-Kind Services 3.0 PROJECT IMPLEMENTATION 3 .1 Required Area 3.2 Air Monitoring Locations 3.3 Background Air Analyses 3 .4 Site Access 3 .5 Utilities 3 .6 Soil Quantity for Performance Demonstration 4.0 SUBMITTALS 4.1 Project Schedule 4.2 Schedule of Values 4.3 Spending Forecast 4.4 Permit List 4.5 Agency Contacts 4.6 Notice to Proceed 4. 7 Design Submittals/submittal Register 4.8 Performance Demonstration Plan 4.9 Other Plans 4.10 Heat & Material Balance 5.0 COMMUNITY EFFORTS 5.1 Outreach and Redevelopment 5 .2 Minority Business Participation 5.3 Retained Facilities 6.0 QUESTIONS 6.1 Outstanding Design Issues 6.2 Others 7.0 ACTION ITEMS Date: Minutes Project Initiation Meeting Warren County PCB Landfill Detoxification Design/Build Project Earth Tech Job No. 43116 March 13, 2001 Location: Earth Tech Offices Raleigh, North Carolina Present For: NCDENR Pat Backus Mike Kelly Ed Mussier The IT Group John Duffey Jim Garrett Bill Gallagher Gary Duke Carl Palmer Tony Fetherling Community Advisory Board Dollie Burwell Pat Barnes Earth Tech Kathleen McNelis John Funk Jim Cloonan Purpose: Confirm Project Requirements and Answer Contractor Questions Items of Discussion: 1) Agenda was distributed and sign-in sheet was circulated. 2) Notice to Proceed was given in the transmittal letter for the contract as March 12, 2001. Earth Tech will provide a separate, formal Notice to Proceed to IT. 3) Phase I of the contract has been funded and awarded. Phase II has not yet been funded. 4) Contract terms were explained. The basic requirements of this contract are performance based. IT has a Design-Build contract. Changes in design, such as upgrading foundations to support IT equipment, are IT's responsibility. 5) Pat Backus will set up a coordination meeting with EPA TSCA, Region IV, IT, DENR, and Earth Tech to occur next month. Page 1 of3 6) EPA in-kind services are still to be determined. Terry Lyons is point of contact for EPA and he will be invited to the coordination meeting. 7) IT estimates that design and preparation of the TSCA permit application will take two months. Receipt of the North Carolina air permit will require approximately 90 days. The state and TSCA permits will be on a parallel track. 8) IT doesn't need any additional county land, will use the footprint given in Drawing C-3 unless they notify Earth Tech otherwise. 9) IT will maintain access for the adjacent landowner. 10) IT handed out a preliminary schedule, showing construction to begin on June 4th. Earth Tech will conduct the baseline air monitoring prior to that date and will notify IT and DENR in advance of the sampling date. 11) IT estimates their thermal unit will produce approximately 35 MM BTU/hr. Their unit will satisfy the NC sulfur criteria for fuel oil. 12) IT estimates their unit can treat 19 to 30 tons/hour of soil. 13) IT is not planning to use a flameless thermal oxidizer for emissions control. This will be addressed as part of the TSCA permit application. 14) IT needs to estimate how many tons of soil will be treated during the Performance Demonstration. TSCA allows 720 hours of operation under shakedown. 15) IT would like leeway from EPA to treat soils with higher concentrations than those treated in the Performance Demonstration, may use historical data to get this. 16) IT will add required permits to their project schedule. 17) Pat Backus will see if the existing DENR permit for storm water discharge can be modified for use by IT. 18) Phase I is currently scheduled to be completed on February 26, 2002, which is past the 270 day contract time (completion date of December 7, 2001). 19) IT requires a minimum of 250 gallons of condensed oils for LBCD treatment. They will have a 2,000-gallon reactor. 20) A pre-construction meeting will be scheduled with the NC State Construction Office prior to mobilization (prior to June 4th). 21) IT handed out a preliminary schedule of values and submittal register. Once the schedule and schedule of values are fixed, IT will generate a spending forecast that will predict the values of future invoices. Earth Tech distributed a copy of the SCO Section 323 form to be used as an Application for Payment. 22) IT said they may need a storage permit for fuel oil and propane and may need a SARA Title 3 permit for nitrogen. 23)Pat Backus will provide IT with the necessary information for abandonment of the monitoring wells. 24) Earth Tech will forward the communication report from the meeting with Don Van Der Vaart of the NC Division of Air Quality to IT. 25) Earth Tech and DENR will prepare a list of existing agency contacts for IT. 26) IT would like to schedule HAZWOPER training for one week prior to mobilization. This date needs to be set and advertised in the community. 27) IT will prepare a table identifying the title, duties, requirements, and employment dates for the available job openings. 28) DENR needs to track MBE participation and project costs spent in the local community. IT will submit a sample form for review and approval. Page 2 of3 29) Facilities are to be constructed as needed to support the remediation. The contract requires some facilities to be left in place after the remediation. It is not necessary to build these facilities if they are not required to support the remediation. Improvements to remain on the property are listed in Section 01270, Part 1.03F. IT will not construct a building for the PCSAPT system. 30) IT will use a frac tank to store most of the storm water that accumulates in their process areas. Overflow during storm events will go to the lined pond. A 100-year storm would produce 8-inches of rain in 24 hours. IT can treat 100-gpm of stormwater through their activated carbon system. 31) IT asked if a double liner was required in the retention pond. Earth Tech will evaluate whether there is a regulatory requirement. If not, a double liner won't be required. 32) IT submitted a revised concrete plan that removes expansion joints and requires smaller pours. 33) Carl Palmer will do a pilot test of the system at a facility in Elgin, Illinois. He will need approximately 30 gallons of soil. Pat Backus will check on the available volume of soils already in pails at Ecoflo in Greensboro, NC. 34) IT and Earth Tech will have a conference call next week to discuss submittals and the project schedule. 35) Digital pictures with minimum 1 MB pixels are acceptable for progress photographs. The above represents the understanding of the writer as to the significant discussions and outcomes of the meeting. Please contact the undersigned at (864) 234-3056 with any corrections or additions. Jim Cloonan, PE March 20, 2001 Page 3 of3 Meeting: Topic: Present: Copy: 3/19/01 Laboratory Requirements for Perimeter Monitoring Kelly Wallace, Pace Analytical Services, Inc Jim Cloonan, Earth Tech Kathleen McNelis, Earth Tech Pat Backus, NCDENR John Funk, Earth Tech Jerry Winberry, Envirotech Solutions Ms. Wallace visited Earth Tech's Greenville South Carolina office to discuss the scope and schedule for upcoming perimeter air monitoring work. Ms. Wallace signed and delivered the subcontract to our office. Earth Tech will provide Ms. Wallace with a schedule, based on the construction schedule we will receive from IT. Pace will provide a contact name from the Minneapolis laboratory. Reports can be transmitted in spreadsheet form, or as PDFs of the laboratory report. Pace will provide us with some example copies and we can work with them to determine what format is preferred. We confirmed that the following work would be required: • Baseline -4 locations, 1 event. Each location will have PUF sample for PCB by TO- 4A and dioxin/furan by TO-9A; Summa canisters for VOCs by TO-14A; and TSP gravimetric per 40 CFR 51. We will be able to give notice to Pace once we have equipment delivery scheduled. This work will be completed before June 4, 2001. • Performance Demonstration -4 locations, once per stack test, 3 tests probably a 1 to 2 week period. Will be able to give advance notice, but exact day may differ from predictions. Each location will have PUF sample for PCB by TO-4A and dioxin/furan by TO-9A; Summa canisters for VOCs by TO-14A; and TSP gravimetric per 40 CFR 51. • After Performance Demonstration, we may be able to go directly into operations or there may be a delay. We will not know for sure until PD is conducted and EPA decides. • First Month of operation -daily samples from 4 locations. Each location will have PUF sample for PCB by TO-4A; TSP gravimetric per 40 CFR 51 . • Following first month -weekly samples from 4 locations. Each location will have PUF sample for PCB by TO-4A; TSP gravimetric per 40 CFR 51. AGENDA EPA TSCA PERMIT MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION PROJECT APRIL 24, 2001 1 :00 PM RALEIGH, NORTH CAROLINA 1.0 INTRODUCTIONS 2.0 PROJECT STATUS 3.0 IT/MSR TEATMENT PERMIT 4.0 PERMISSION FROM REGION IV TO PERFORM THE REMEDIATION 5.0 TSCA LANDFILL PERMIT 6.0 IN-KIND SERVICES 7.0 PROJECT SCHEDULE 8.0 COMMUNITY EFFORTS 9.0 SITE WALK 10.0 ACTION ITEMS Date: Minutes EPA Meeting Warren County PCB Landfill Detoxification Design/Build Project Earth Tech Job No. 43116 Location: April 24, 2001 NCDENR Offices Raleigh, North Carolina Present For: NCDENR Pat Backus Mike Kelly Ed Mussler The IT Group Gary Duke Carl Palmer (MSR) Carl Swanstrom (MSR) EPA Craig Brown Dody Dodohara Winston Lue Terry Lyons Earth Tech Kathleen McNelis Jim Cloonan Purpose: Discuss TSCA Permitting Requirements and EPA In-Kind Services Items of Discussion: 1) Agenda was distributed and sign-in sheet was circulated. 2) Midwest Soil Remediation (MSR) will hold the TSCA permit as owner/operator of the BCD treatment unit. MSR will provide an org chart to EPA. 3) Craig Brown of Region IV is in charge of the landfill remediation permitting and will provide 761(c) approval. 4) Terry Lyons of ORD in Cincinnati is in charge of the SITE demonstration, including sampling of the stack, soils and oil. 5) Dody Dodohara of HQ will evaluate the demonstration test results for compliance with the permit application. 6) Winston Lue of HQ will have the lead on the TSCA permit and be the main point of contact. 7) MSR will not install the equipment until the demonstration test plan is approved. Page 1 of3 8) Shakedown testing could include 20,000 tons of soil over one month during January and February of 2002. Shakedown testing will be part of the demonstration test plan. 9) MSR anticipates a soils feed rate of 19 to 30 tons/hour. 10) Confidential business information (CBI) is very difficult for EPA to handle, requiring a safe and a document control officer. Submitting documents as CBI will make the permitting process three times longer. Documents should not be stamped as "Confidential" or "Proprietary" unless absolutely necessary. 11) MSR stated that compounds in the process vent will be nitrogen and non-condensable hydrocarbons (e.g., ethane, methane). There will be no SVOCs and dioxins will be below ambient air standards. 12) MSR will submit their NC air permit application in June. They expect to receive their permit in 30 to 90 days, as there are no major issues. 13) MSR will demonstrate treated soils at 2 ppm of PCBs for the permit and 0.2 ppm for the contract. 14) The TSCA permit will be for thermal unit with liquid BCD treatment as an optional unit. This could be done as a two-part or conditional permit. EPA will resolve the best approach for handling the dual treatment systems. 15) Diatomaceous earth will be used as filter aid in the press. Filter cake will be returned to the soils unit for treatment. Recovered fines at the end of the project that could not be re-treated and final decon water would be sent off-site for disposal. Classification, manifesting, and treatment would be according to TSCA regulations. 16) The SITE program will do the sampling and analysis but MSR will do the reporting. EPA has to bid the sampling work to four pre-qualified firms, need process description and details to allow preparation of bids. SITE will prepare the sampling QAPP for the demonstration test, need one month to bid the work, 4 -6 weeks to prepare the document, and two weeks to review, total of three months once they have the process information. If ORD gets process description from MSR by May ih, they should have a contractor on board by June 8th and a QAPP by July 20th• 17) Results of the shakedown pre-test will be submitted to HQ as soon as available to allow approval for interim operation. 18) EPA HQ will provide approval or comments on the demonstration test plan in eight weeks. EPA-HQ stated that while their initial review normally is complete in eight weeks, it is likely that approval will require both a meeting to discuss key technical issues, and an additional period for review of additional information requested by EPA-HQ. 19) MSR will provide Region IV with Notification to Demonstrate 30 days prior to testing, although Region IV said this is not necessary. 20) MSR wants to demonstrate higher feed concentrations by running unit for three weeks during shakedown, recovering the oil, and augmenting the feed with recovered PCBs. Goal is to show performance at 10,000 ppm. EPA will need two out of three runs in the PDT at the highest feed concentration. MSR plans on three runs at 500 tons each. 21) MSR can do shakedown testing under the Demonstration Permit, will need to define quantity of soils required to generate sufficient oil to augment feed. May be able to recover oil from the first test and use in the later tests. Page 2 of 3 22) The unit will be permitted at a maximum concentration and maximum throughput based on what is demonstrated during the test. There will be a limit on throughput irrespective of concentration. 23) MSR expects to issue report one month after test results are received. 24) EPA can approve interim operations using raw data to show six 9's DRE. The data is generated from a pre-test during the shakedown period and will allow interim operations while awaiting results of the performance demonstration testing (PDT). The pre-test must provide PCB stack test results for one run. Process is to show DRE with pre-test data, then show DRE two weeks following the three-run PDT, and then provide D/F data. EPA-ORD was in agreement that they can support both the pre-test and PDT. Unit can keep operating so long as data shows compliance while waiting for the final TSCA permit. MSR is to provide the details of this testing sequence, along with a schedule for data submission, as part of the demonstration test plan. EPA-ORD stated that "results only" preliminary data will be made available directly to MSR as soon as possible after each test event (pre-test and PDT). EPA-HQ stated that this type of data is acceptable for approving interim operations. 25) Schedule is to set up unit in early January and conduct shakedown testing in late January 2002. 26) The 1998 amendments for PCB remediation waste allow a self-implementing approach with variances for closure of the landfill. As an example, closure should note use of the variances for confirmation sampling, as described in 76l(a)(3). 27) The NCDENR will submit a request to stop leachate collection and abandon the groundwater monitoring wells. The above represents the understanding of the writer as to the significant discussions and outcomes of the meeting. Please contact the undersigned at (864) 234-3056 with any corrections or additions. . ~ er Jim Cloonan, PE May 9, 2001 Page 3 of3 AGENDA AIR MONITORING MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION PROJECT MAY 16, 2002 1:00 PM WARREN COUNTY SITE 1.0 INTRODUCTIONS 2.0 AlR MONITORING PLAN 2.1 Revisions 2.2 Perimeter Sampling Frequency 2.3 Reserve Samples 2.4 Trip Blanks 2.5 Perimeter Sampling SOPs 2.6 Sample Preparation 2.7 Sample Validation 2.8 Data Records and Presentation 2.9 Evaluation of Duplicate Samples 2.10 Real-Time Monitoring -VOCs 2.11 Real-Time Monitoring -PM 2.12 Data Forms 3.0 MONITORING AND MET STATIONS 3.1 Met Station Status 3.2 Modem and Software 3 .3 Revised Monitoring Station Locations 3.4 Monitoring Stands 3 .5 Status of Sampling Equipment 4.0 ADMINISTRATIVE ISSUES 4.1 Project Personnel 4.2 Schedule 4.3 Target Shakedown Sampling Date 4.4 Coordination with Pace Labs 4.5 Application of Ambient Air Guidelines 4.6 Dust Control 4.7 Site Walk 5.0 ACTION ITEMS AGENDA PROJECT STATUS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION PROJECT MAY 22, 2001 RALEIGH, NORTH CAROLINA 1.0 OBJECTNES 2.0 PROJECT STATUS 2.1 Subcontracts 2.2 Mobilization Date 2.3 Work for First Two Weeks 2.4 Clean Vehicles 2.5 Electrical Disconnection/Connection 2.6 Site Office Trailers 2.7 Signage 2.8 Backup on Applications for Payment 2.9 Application for Payment No. 2 2.10 Pending Action Items 3.0 DESIGN 3.1 Basis of Review 3 .2 Lead Items 3 .3 Submittals to Date 3.4 Review Comments 3.5 Submittal Register 3.6 MSR Submittals/Heat & Material Balance 3.7 Schedule and Review Time 4.0 AIR MONITORING 4.1 Baseline Monitoring 4.2 Air Monitoring Locations 4.3 Coordination of Air Monitoring 4.4 Dust Control 5.0 PROJECT SCHEDULE 5.2 Modifications 5.2 Permit Submittals 6.0 COMMUNITY EFFORTS 6.1 Ground Breaking Event 6.2 Toll-Free Number 6.3 Newsletter 6.4 Proposed Re-Development Efforts 7.0 ACTION ITEMS PRE-CONSTRUCTION CONFERENCE WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101 A MAY 22, 2001 -TIME 1:30 PM LOCATION: Earth Tech 701 Corporate Center Drive, Suite 475 Raleigh, North Carolina 27607 ATTENDEES: Pat Backus Bill Sessoms Ed Mussler Mike Kelly Jim Cloonan John Funk NCDENR NCDENR NCDENR NCDENR Earth Tech Earth Tech Dennis Jones Earth Tech Gary Duke Bill Gallagher Mark Sapyta Rudy Lopez IT Corp. IT Corp. IT Corp. State Construction Office NOTE: Meeting was started at 9:30 AM as scheduled and repeated at 1 :30 PM due to schedule conflicts. Not all attendees were present for both meetings. MEETING MINUTES 1. Work performed in the last 30 days. IT Corporation (IT) has completed subcontract agreements with all major subcontractors and suppliers. Seeding subcontractor will be selected later in the project. Names of subcontractors and minority businesses will be provided to Jim Cloonan to forward to State Construction Office. IT is preparing grading plan and structural plans. Completion of the concrete drawings awaits details from building supplier. IT is also coordinating with CP&L for terminating existing power (planned June 4, 2001), and installing new power supply and poles. 2. Work to be performed in the next 30 days Initial site survey will be completed, and IT Corp. plans to mobilize to the site week of June 4, 2001. Ground breaking ceremony is schedule for 11 :00 am on June 11, 2001 at the site. Power will be provided to the trailers and telephone lines installed. IT will notify Pat Backus of site telephone number, who will relay the number to State Construction Office. Erosion and sediment control permit will be obtained, and draft TSCA permit will be completed for Earth Tech and DENR review June 8, 2001. Midwest Soil Remediation (MSR) will continue with their efforts to prepare the BCD unit for mobilization to the site. Earth Tech will perform the baseline air monitoring. 3. Review of change orders ( outstanding/anticipating) No change orders are outstanding or anticipated at this time. 4. Review status of permits applications, project drawings and submittals Draft TSCA permit will be submitted for Earth Tech and DENR review June 8, 2001. NC air permit will follow. IT was reminded of minimum 90-day Air Quality review period. IT was also reminded of the 180-day review time required by Water Quality for NPDES permits, which may be required for the site storm water treatment system. 5. Review construction schedule compliance Project schedule unchanged. IT Corp. will hold to 270-day Phase I completion schedule excluding EPA review times for the TSCA permit. Using the given EPA review time, estimated completion date for Phase I is March 1, 2002. State Construction Office reminded IT to include time for State Construction Office final inspections in the project schedule. State Construction Office also explained the procedure for calculating contractor schedule extension based on weather delays. 6. Percentage complete to be reported by Contractor (actual work in place) Project is 13.84% based upon contractor invoices. No work was in place at the site, but work plans, drawings, permit applications, and BCD equipment preparation are in various stages of completion. IT has provided a surety certificate from their bonding company affirming the progress payment to MSR. 7. Discuss construction/coordination issues Earth Tech plans to conduct base-line air sampling prior to IT mobilization and disruption of power. Sampling will be completed week of May 29, 2001. 8. Comments from Owner, SCO, Contractor, and Designer State Construction Office stated that no firearms are permitted on the site, reviewed change order procedures, and requested that Earth Tech complete the SCO weekly and monthly inspection reports. State Construction Office also reminded IT that DENR is exempt from North Carolina state sales tax and such taxes should be documented on invoices. Earth Tech commented that vehicles are to be clean when brought on-site, IT should place signs at site entrance and on roads leading to the site to facilitate deliveries of supplies and equipment, monitoring wells are to be abandoned in accordance with State Regulations, and copies of the well abandonment forms are to be provided to DENR and Earth Tech. The official SCO ID number for the project is 010440101A. DENR reminded IT that the replacement benchmark should have horizontal and vertical controls. 9. Schedule project monthly progress meeting date, time, and place The next monthly progress meeting is scheduled for June 7, 2001 at the Warren County PCB Landfill at 1 :00 PM. Future monthly progress meetings will be coordinated with the Community Advisory Board meetings such that both will occur on the same date. 2 MONTHLY PROGRESS MEETING -JUNE 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A June 7, 2001 -TIME 1 :00 PM LOCATION: Coley Springs Baptist Church Warrenton, North Carolina MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders ( outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals 5. Review construction schedule compliance 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues 8. Comments from Owner, SCO, Contractor, and Designer 9. Schedule project monthly progress meeting date, time, and place MEETING MINUTES MONTHLY PROGRESS MEETING -JUNE 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A June 7, 2001 -TIME 1 :00 PM LOCATION: Coley Springs Baptist Church Warrenton, North Carolina MEETING ATTENDEES John Funk, Earth Tech Dennis Jones, Earth Tech Gary Duke, IT Corp. Bill Gallagher, IT Corp. Rudy Lopez, State Construction Office Pat Backus, DENR Bill Sessions, DENR Mike Kelly, DENR MEETING MINUTES 1. Work performed in the last 30 days. Erosion and Sediment Control permit submitted to State June 4, 2001 , Comments received June 6, 2001. Site grading plan will change to lessen slopes on fill areas. Change may effect erosion and sediment control plan such as relocation of sediment trap, but no significant changes expected. Site survey started during the week ending June 8, 2001 to define perimeter limits. Limited clearing also started week ending June 8, 2001. Trailers will be on site June 8, 2001. 2. Work to be performed in the next 30 days Site Clearing and grubbing scheduled to start June 19, 2001 , and erosion and sediment control measures construction to start the same date. Monitoring well abandonment scheduled for June 12, 2001. Delayed due to weather, does not effect overall project schedule. Mtg-junO I-minutes.doc Warren County Landfill -43116 It is expected that CP&L and telephone will bring power to the site and provide telephone service, respectively, during the next 30 days. 3. Review of change orders ( outstanding/anticipating) No change orders are outstanding or anticipated. 4. Review status of permits applications, project drawings and submittals Draft TSCA permit will be submitted to Earth Tech and DENR June 12, 2001. Submittal date slipped from June 8, 2001. No schedule impacted anticipated. Draft Demonstration test plan will be submitted to Earth Tech and DENR June 26, 2001. IT Corp. was reminded of the need to maintain overall project schedule. DENR requested preliminary concrete drawing (less pole barn supports). IT Corp. will provide by June 22, 2001. DENR provided IT Corp. with a copy of the current Non-Discharge Permit. IT Corp. will request a permit amendment or apply for a NPDES permit as appropriate. State Air Permit was added to the project schedule. 5. Review construction schedule compliance The importance of maintaining the project schedule was stressed during the meeting, and no changes to the schedule were proposed by IT Corp. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 15.5% 7. Discuss construction/coordination issues Based the results of analytical testing by DENR of site monitoring well purge water, the purge water currently stored in drums on-site can be emptied on the ground. The drums can be disposed of off-site. IT Corp. to submit the name of the disposal site (drum reclaimer) to Earth Tech and DENR for approval. 8. Comments from Owner, SCO, Contractor, and Designer IT Corp. handed out a photo log and CD of pictures taken at the site. MBE table was also handed out by IT Corp. According to IT Corp. interpretation of regulations, sales taxes are exempt only for those items incorporated into the work. DENR to check if sales tax on rental fees is also exempt. Mtg-junO I-minutes.doc 2 Warren County Landfill -43116 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for July 12, 2001 at 1:30 PM at the project site. Subsequent meeting will be held on the first Thursday of the month at 1:30 PM. Mtg-junO I-minutes.doc 3 Warren County Landfill -43116 • Status of ECS permit ISSUES FOR DISCUSSION MONTHLY PROGRESS MEETING -JULY 12, 2001 WARREN COUNTY PCB LANDFILL PROJECT • Revised schedule and substantial completion • Work for next four weeks • Air monitoring locations • Air monitoring connections and pads • Preliminary baseline monitoring results • IT Application for Payment No. 4 • MEETING MINUTES MONTHLY PROGRESS MEETING -JULY 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A July 12, 2001 -1:00 PM LOCATION: IT Construction Trailer MEETING ATTENDEES Gary Duke, IT Corp. Bill Gallagher, IT Corp. John Calp, IT Corp. Mark Sapyta, IT Corp. David Jaegar, IT Corp. Tom McSweeney, IT Corp. Patrick Barnes, BF A Env. Paul Kearney, Kearnco. Pat Backus, DENR Bill Sessoms, DENR Mike Kelly, DENR Jim Cloonan, Earth Tech Dennis Jones, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. Revised Erosion and Sediment Control plan submitted to State on June 29th by Aiken & Yelle. IT will construct two sedimentation basins on the west side of the landfill and they have requested additional land from the County for this construction. TSCA permit application was submitted to EPA for review. The Performance Demonstration Plan will be submitted separately. All monitoring wells that were to be abandoned have been abandoned. Well construction records were found for all but one of the abandoned wells (MW-3S). Completed clearing of trees and brush. Materials to be hauled to Kearney's yard for disposal. Trailers sited and connected to power. Still waiting for complete phone service, have partial service. Number ofIT's trailer is (252) 257-3603. mtg-jul12-minutes.doc Warr en County Landfill -4 3116 2. Work to be performed in the next 30 days No further site work can be conducted without the Erosion and Sedimentation Control Permit. Earliest anticipated date for permit is July 13th. Will then need pre- construction meeting with NCDENR before installing controls and inspection of installed controls prior to start of grading. Draft Performance Demonstration Plan is scheduled to be submitted to NCDENR and Earth Tech for comment on July 23rd . Survey site layout and grade lines. 3. Review of change orders ( outstanding/anticipating) IT will submit a request for change order for time and costs associated with delays in receipt of the Erosion and Sedimentation Control Permit. Under General Conditions, they have 20 days from date of delay to submit request. 4. Review status of permits applications, project drawings and submittals Draft TSCA permit application was submitted to EPA. Draft Performance Demonstration Plan scheduled to be submitted to Earth Tech and DENR on July 23rd (vs. target date of June 26th at last meeting). IT requested to send plan directly to Kathleen McNelis. IT Corp. stated that they cannot obtain an NPDES permit unless they have no other discharge options. IT needs to dispose of more contaminated stormwater from the excavation and process areas than can be used in their treatment process. They will obtain an indirect discharge permit using spray irrigation to discharge treated stormwater. Treatment standard will be 0.5 ug/1 of PCBs. IT will hire a soil scientist to evaluate the wooded area to the west of the landfill to receive the water. Discharge may require up to 20 acres of land. Testing the soils and obtaining the permit should not impact the schedule. DENR requested preliminary concrete drawing (less pole barn supports) at last meeting. IT Corp. was to provide by June 22, 2001. Drawings depend on revised grading plan and have not been submitted. At their monthly meeting on July 2nd, the County approved IT's request for access to their land to the west for construction of two sedimentation basins. IT will formally find out about their request for access to County land for discharge of treated water by spray irrigation on August 61\ when the County commissioners next meet. IT already has the NCDOT encroachment agreement for connection to the water main. IT will submit the draft NC air permit application to NCDENR and Earth Tech for review on July 23rd. IT requested to send Earth Tech copy directly to John Funk in Raleigh. mtg-jul 12-minutes.doc 2 Warren County Landfill -43116 5. Review construction schedule compliance IT submitted a revised schedule. This schedule shows site grading beginning on July 23 rd and requires 288 days, 18 days past the Contract Time of 270 days. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 20.5% through Application for Payment No. 4. 7. Discuss construction/coordination issues IT will send revised Erosion and Sedimentation Control Plan, including site-grading plans, to NCDENR and Earth Tech on Friday, July 13th• Earth Tech will use the grading plan to establish final locations of the perimeter air monitoring stations. 8. Comments from Owner, SCO, Contractor, and Designer IT Corp. handed out a CD of pictures taken at the site along with submittal of the Emergency Response Plan and the hot tap for the water line. Earth Tech discussed preliminary results of the baseline air monitoring. PCBs were non-detect at all four locations. Dioxins/furans TEQs were detected at all four locations but these compounds are detected across North America and Europe. Station No. 2 exceeded the site standard for TEQs and the State standard for methylene chloride. The data must still be validated and the air flow rates of the samplers confirmed. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for August 2, 2001 at 1:00 PM in IT's trailer at the project site. A CAB meeting will follow at 3:00 PM at the Coley Springs Baptist Church. mtg-ju! 12-minutes.doc 3 Warren County Landfill -43116 MONTHLY PROGRESS MEETING -AUGUST 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A August 2, 2001 - 1 :00 PM LOCATION: IT Construction Trailer Warrenton, North Carolina MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days • Water line status • ESC status • Performance Demonstration Plan submittal 3. Review of change orders ( outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals • NC Air Quality Permit to Construct • Non-discharge/discharge permit • Other pending permits and regulatory submittals • Technical submittals to NCDENR/Earth Tech 5. Review construction schedule compliance • Phase I target completion date 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues 8. Comments from Owner, SCO, Contractor, and Designer • Results of PCB soil analyses • Revised benchmark location • Approval of other submittals as noted • Air monitoring station locations • CAB Meeting at 4:00 PM 9. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING -SEPTEMBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A September 6, 2001 - 1 :00 PM LOCATION: IT Construction Trailer Warrenton, North Carolina MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days • Water line • Grading • Concrete 3. Review of change orders (outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals • Performance Demonstration Plan • Jersey barriers • Air monitoring locations • Revised water line submittals • Other pending permits and regulatory submittals • Technical submittals to NCDENR/Earth Tech 5. Review construction schedule compliance • Phase I target completion date 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues • Disposal of waste materials discovered during grading • Rain days • Grading progress 8. Comments from Owner, SCO, Contractor, and Designer • Sales tax credit • Input on TSCA landfill permit • Pilot study results • Baseline air monitoring results • CAB Meeting 9. Schedule project monthly progress meeting date, time, and place MEETING MINUTES MONTHLY PROGRESS MEETING -SEPTEMBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A September 6, 2001 - 1 :00 PM LOCATION: IT Construction Trailer MEETING ATTENDEES Gary Duke, IT Corp. Bill Gallagher, IT Corp. David Jaeger, IT Corp. Pat Backus, DENR Bill Sessoms, DENR Mike Kelly, DENR Rudy Lopez, SCO Pat Barnes, BF A Mark Ellington, Ellington & Sons Phil Ellington, Ellington & Sons Jim Cloonan, Earth Tech Dennis Jones, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. Continued grading efforts. There were seven rain days (defined as > 0.1 inch) in August, one more than the monthly average. Began excavation of stormwater retention pond. Installed main gate for the landfill fencing. 2. Work to be performed in the next 30 days Complete grading of the site. Complete installation of the permanent stormwater control features (e.g., the lined pond). Install the water main. Begin pouring concrete pad. Ellington & Sons were at the meeting to plan for this work. Sep06-minu tes. doc Warren County Landfill -43116 3. Review of change orders (outstanding/anticipating) IT submitted a change order at the meeting for 21 days to be added to the Contract Time due to circumstances associated with delays in approval of the Erosion and Sedimentation Control Plan. 4. Review status of permits applications, project drawings and submittals The Draft Performance Demonstration Plan was submitted to Earth Tech and DENR on August 15th for review and comment. A conference call was set for Friday, September ?1h to discuss comments from DENR and Earth Tech. IT submitted information on the origin and condition of Jersey barriers to be used to segregate treated soil piles. Use of the barriers was approved but soil residuals were observed on a number of the delivered barriers. IT agreed to remove and containerize the adhered soil. 5. Review construction schedule compliance IT submitted a revised schedule. This schedule shows completion of Phase I on April 11, 2002. Including EPA review time, IT's schedule is within the revised Contract Time of 291 days. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 32% through Application for Payment No. 6. Based on the revised Contract Time of 291 days, the project is 61 % complete. 7. Discuss construction/coordination issues Progress on the grading work needs to be accelerated to maintain the project schedule, based on the average daily quantity of approved lifts. IT will provide a form showing rain days for Earth Tech's oversight to approve as they occur. Drummed drill cuttings are to be stored on site and thermally treated. 8. Comments from Owner, SCO, Contractor, and Designer IT handed out a CD of pictures taken at the site. IT will provide Pat Backus with information (e.g., site plans) for revisions to the TSCA landfill Permit. The baseline air monitoring results have been validated and are final. Concentrations of dioxins and furans are consistent with national averages. The NCDENR will evaluate use of the promulgated State air standard for D/Fs rather than the site-specific air standard. Sep06-minutes.doc 2 Warren County Landfill -43116 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for October 4, 2001 at 1:00 PM in IT's trailer at the project site. A Community Advisory Board meeting will follow at 3:00 PM in the Cooley Springs Baptist Church. Sep06-minutes.doc 3 Warren County Landfill -43116 MONTHLY PROGRESS MEETING-OCTOBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A October 4, 2001 -1 :00 PM LOCATION: IT Construction Trailer Warrenton, North Carolina MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days • Water line • Grading • Concrete 3. Review of change orders ( outstanding/anticipating) • ESC plan delay • Rain delays 4. Review status of permits applications, project drawings and submittals • Submittal Nos. 27 -33 • Revised water line and concrete submittals • Performance Demonstration Plan • CBI Drawings • Non-Discharge Wastewater Permit • Upcoming technical submittals to NCDENR/Earth Tech 5. Review construction schedule compliance • Phase I target completion date • Status of thermal treatment unit 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues • Construction of water line 8. Comments from Owner, SCO, Contractor, and Designer • Distribution of submittals • Pilot study results • Baseline air monitoring results • CAB Meeting 9. Schedule project monthly progress meeting date, time, and place MEETING MINUTES MONTHLY PROGRESS MEETING -OCTOBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A October 4, 2001 -1 :00 PM LOCATION: IT Construction Trailer MEETING ATTENDEES Gary Duke, IT Corp. Bill Gallagher, IT Corp. Pat Backus, DENR Pat Barnes, BF A Jim Cloonan, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. Continued grading efforts, nearly complete. Began delivery of ABC stone for concrete installation. Light poles installed on west side oflandfill. 2. Work to be performed in the next 30 days Complete grading of the site, including access road and parking lot. Complete installation of fencing and the permanent stormwater control features (e.g., the lined pond). Install the water main. Form and pour concrete foundations in BCD process area. 3. Review of change orders (outstanding/anticipating) Earth Tech approved and forwarded to NCDENR Change Orders 1 -3, as follows: • CO 1: Request of 21 days time for delays associated with ESC plan • CO2: Request of 1 day of time for rain delays in August • CO 3: Request of $5 3 9 for off-site disposal of encountered construction debris 4. Review status of permits applications, project drawings and submittals IT submitted their non-discharge permit to NCDENR on September 26th and provided copies to Earth Tech and NCDENR at meeting. Pat Backus heard internally that application was incomplete. Also, NCDENR must be listed as Owner. IT will set up a conference call to determine deficiencies and re-submit. This should be last State permit application except E&S Plan for opening landfill. Oct04-minutes. doc Warren County Landfill -43116 IT/MSR will submit remainder ofTSCA Permit application to EPA by October 8u,_ 5. Review construction schedule compliance IT submitted a revised schedule. This schedule shows completion of Phase I on May 9, 2002. Pole barn should be installed by November 30, 2001 and then IT will demobe from site until TSCA demonstration test plan is approved. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 43% through Application for Payment No. 7. 7. Discuss construction/coordination issues IT will contact Macon Robertson of Warren County regarding sequence for water line disinfection. Pat Backus will check NCDENR requirements and Earth Tech will check State plumbing code as well. If EPA takes 8 weeks to review the TSCA Permit application, IT anticipates mobilization of the thermal treatment unit to the site around March l, 2002. This is based on three weeks to prepare for mobilization, one week to transport the equipment, and two weeks to set up the unit. 8. Comments from Owner, SCO, Contractor, and Designer IT will distribute future submittals for review and approval as follows: • Pat Backus - 2 copies, Jim Cloonan - 2 copies, John Funk - 1 copy The PCB Hotline is now in operation, number is (252) 257-3772. IT will add an answering machine. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for November 1, 2001 at 1 :00 PM in IT' s trailer at the project site. [NOTE: This was subsequently changed to 2:00 PM.] Oct04-minutes.doc 2 Warr en County Landfill -4 3 116 MONTHLY PROGRESS MEETING -NOVEMBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A November 1, 2001 - 2:00 PM LOCATION: IT Construction Trailer Warrenton, North Carolina MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days • Water line • Concrete • Pole Barn • Site Security 3. Review of change orders (outstanding/anticipating) • Rain delays 4. Review status of permits applications, project drawings and submittals • Pond liner • Concrete berms • TSCA Permit submittal/EPA review schedule • CBI Drawings • Non-Discharge Wastewater Permit • Upcoming technical submittals to NCDENR/Earth Tech 5. Review construction schedule compliance • Completion of site preparation • Phase I target completion date • Status of thermal treatment unit 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues • Construction of water line • Concrete breaks • Site security 8. Comments from Owner, SCO, Contractor, and Designer • Coordination of revisions • Status of PCB Hotline 9. Schedule project monthly progress meeting date, time, and place MEETING MINUTES MONTHLY PROGRESS MEETING -NOVEMBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A November 1, 2001 -2:00 PM LOCATION: IT Construction Trailer MEETING ATTENDEES Gary Duke, IT Corp. Mike Kelly, DENR Pat Backus, DENR Bill Sessoms, DENR Rudy Lopez, SCO Paul Kearney, Kearney Grading Pat Barnes, BF A Jim Cloonan, Earth Tech John Funk, Earth Tech Dennis Jones, Earth Tech Kathleen McNelis, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. Grading efforts for the pad and parking area are complete. Formed and poured all four sections of concrete and installed curbing. Installed column bolts for pole barn. Installed discharge line to old pond and hot tap into public water supply along Limer Town Road. Completed installation of fencing except for barbed wire on some portions. 2. Work to be performed in the next 30 days Cure concrete and add sealant. Repair cracks in pad curbs. Complete installation of power connections to air monitoring locations. Install culverts for pole barn gutters and complete access roads. Install liner in new pond. Deliver and install pole barn. Pressure test and disinfect water line. Connect water to trailers. Site work should be essentially complete by next progress meeting on December 6th• Site work will then be suspended until EPA approves TSCA permit applications. Novo I-minutes.doc Warr en County Landfill - 4 3116 3. Review of change orders (outstanding/anticipating) Earth Tech distributed signed copies of Change Orders 1 -3, as follows: • CO 1: Request of 21 days time for delays associated with ESC plan • CO 2: Request of 1 day of time for rain delay in August • CO 3: Request of $539 for off-site disposal of encountered construction debris There were no rain days above normal in September and October and no change orders are anticipated. 4. Review status of permits applications, project drawings and submittals EPA received the confidential business drawing and the Demonstration Test Plan on October 11th• IT anticipates comments from EPA by December 5th. Submittal of CBI drawing should not delay EPA review. [NOTE: EPA subsequently requested a meeting in DC to discuss general comments.] EPA in Cincinnati is revising the lab QAPP and will submit to EPA HQ, date uncertain. NCDENR submitted preliminary comments on the non-discharge permit application. IT will discuss with their subcontractor, Agriwaste Tech, on Monday. IT doesn't need the permit until site activities resume in March. Earth Tech requested design submittal on the dry stack wall to be used for loading of the feed prep area. IT provided copies of Submittal Nos. 39, 40, 42, and 43 at the end of the meeting. IT is waiting on final test results from Gundle on their liner materials. Earth Tech approved used of the 40-mil LLD PE instead of the previously approved 30-mil HDPE. 5. Review construction schedule compliance IT submitted a revised schedule. This schedule shows completion of Phase I on June 17, 2002. Site preparation should be complete by November 28th• The thermal treatment unit should be complete by the end of the year. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 52.5% through Application for Payment No. 8. 7. Discuss construction/coordination issues Water line should be completed by December 9th• 7-day concrete breaks for slabs 1, 2, and 3 look good, however the average of the breaks for slab 4 appears low compared to the 4,000-psi requirement. IT will provide 14-day breaks to estimate final strength. 8. Comments from Owner, SCO, Contractor, and Designer Pat Backus will notify the community that the PCB Hotline is in operation. NovOl -minutes.doc 2 Warren County Landfill -4 3116 The subgrade for the new pond contains numerous cleat marks from compaction. Earth Tech questioned whether the irregularities would allow competent installation of the liner. Earth Tech requested smooth grading, IT said they could not get a roller out of the excavation. IT will evaluate condition and provide a response. Nat White, the adjacent property owner, may need access through the fenced area. Pat Backus will look into this. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for December 6, 2001 at 1:00 PM in IT's trailer at the project site. This will be the last meeting until IT re-mobilizes to the site. The meeting will include an inspection of punch list items prepared by Earth Tech. A Community Advisory Board meeting will follow at 3:00 PM in the Coley Springs Baptist Church. NovO I-minutes.doc 3 Warr en County Landfill - 4 3116 ~ Ol (") ::,-1 C) ct CD >< 'ui Date: Minutes TSCA Permitting Meeting with EPA Warren County PCB Landfill Detoxification Design/Build Project Earth Tech Job No. 43116 Location: November 28, 2001 EPA Offices Washington DC Present For: NCDENR Pat Backus The IT Group Gary Duke Carl Palmer (MSR) EPA -Office of Pollution Prevention and Toxics Hiroshi Dodohara Winston Lue Earth Tech Kathleen McNelis Purpose: Discuss EPA Comments on TSCA Demonstration Test Plan Items of Discussion: 1. EPA indicated they are reviewing both the operating permit application and test plan, but are currently focusing most of their efforts on the test plan. They will provide comments on the operating permit application after the demonstration test. The scope of this meeting was limited to addressing requirements for performance testing. 2. EPA inquired about a date set for the demonstration testing. IT indicated that shakedown with PCB soils was scheduled to begin in April based on receiving approval of the demonstration plan by the end of January. A pre-test will be performed within the first five days that PCB-contaminated soils are fed to the desorber and would be followed by the performance tests. EPA stated they will require performance testing to document destruction and removal efficiency (DRE) for each 5,000 tons of PCB soils treated during shakedown, pre-testing and performance testing. The pre-test and initial performancetest will count for two of these. Two additional tests will be required to treat the proposed 20,000 tons prior to interim operations. IT agreed, butwants to use NIOSH method 5503 instead of Method 0010 to demonstrate DRE during the additional tests. EPA will consider approving the use of the NIOSH method if during the pre-test a correlation can be shown between the results of Method 0010 and NIOSH method 5305. Page 1 of2 3. EPA inquired about the sufficiency of oils for spiking. IT stated that oils collected from the shakedown will be used to spike soil for the performance testing. Based on laboratory practical quantitation limits (PQLs), as little as 2 ppm in soil will allow for demonstration of 99 .9999 % ("six nines") DRE. IT's concern is the ability to generate sufficient oil to spike soils to a minimum of 2,000 ppm in order to set a maximum concentration range for operation. IT estimates that it will take 15 to 20 days of desorption to collect sufficient quantity to spike soils to 2,000 ppm. EPA will review the concentration estimates. 4. EPA will target the end of January to have a permit complete for the demonstration. The demonstration permit will include approval for pre-testing, performance testing, and interim operations. EPA will provide a draft demonstration permit around the end of December. They will need a copy of the Quality Assurance Project Plan (QAPP) to review prior to this. EPA is concerned about collecting isokinetic samples from a small diameter duct. IT indicated that flow might be laminar in the 4-inch section. EPA will contact the contractor, EQM, who is preparing the QAPP to discuss stack testing protocols. IT provided EPA with a draft copy of the QAPP. IT provided the phone number of the test engineer at EQM, John Wentz, so that EPA may contact EQM directly with questions on the QAPP. 5. EPA requires more information on the Base Catalyzed Decomposition (BCD) process -a description of equipment and test protocols -that will be used to treat the recovered PCB-contaminated oils. IT will provide the additional information. EPA will combine the BCD and desorber into the same permit. IT requested that the permit include the provision for the oil to be sent off site for disposal at a TSCA permitted facility to allow flexibility. 6. EPA is concerned about the condensed water from the off-gas recovery system being put back onto treated soils without first being treated to regulatory levels ( either 0.5 or 3 ug/L depending on use). IT contends that this stream is internal to the process and should not be required to meet these regulations because analysis of treated soil occurs after the addition of the condensed water. IT will prepare a justification for remixing water and soil without treating the water and will it submit to EPA for review of regulatory compliance. 7. EPA reminded IT that a 30-day notification is required before PCB-contaminated materials can be fed to the desorber. EPA will provide information on the notification requirements to IT via email. The notification should include reference to all PCB treatment phases -i.e. demonstration, interim operations and operations. Page 2 of2 MONTID.,Y PROGRESS MEETING-DECEMBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A December 6, 2001 -10:00 AM LOCATION: IT Construction Trailer Warrenton, North Carolina MEETING AGENDA I. Work performed in the last 30 days. 2. Work to be performed in the next 30 days • Concrete • Pole Barn • Punch list items • Site Security 3. Review of change orders ( outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals • Pond liner letter • Concrete repairs • TSCA Permit submittal/EPA meeting results • Non-Discharge Wastewater Permit • Upcoming technical submittals to NCDENR/Earth Tech 5. Review construction schedule compliance • Phase I completion/punch list • Status of thermal treatment unit • Target re-mobe date • Target treatment kick-off meeting date 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues • Concrete breaks (letter/56-day breaks) • Site security 8. Comments from Owner, SCO, Contractor, and Designer • Outstanding items needing approval • Status of PCB Hotline • Interim visits prior to re-mobe 9. Schedule project monthly progress meeting date, time, and place MEETING MINUTES MONTHLY PROGRESS MEETING -DECEMBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A December 6, 2001 -10:00 AM LOCATION: IT Construction Trailer MEETING ATTENDEES Gary Duke, IT Corp. Bill Gallagher, IT Corp. David Jaeger, IT Corp. Carl Palmer, TD*X/MSR Mike Kelly, DENR Pat Backus, DENR Jim Cloonan, Earth Tech John Funk, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. Concrete continued to cure, Pads 1, 2 and 3 have met 4,000 psi strength, Pad 4 at 3,853 psi. Installed epoxy coating on Pad 3. Erected pole barn except for tensioning cables in second bay. Survey work is complete. Facility lighting installed on east side. Completed installation of fencing. Completed installation of power connections to air monitoring locations. Installed culverts for pole barn gutters and completed access roads. Installed liner in new pond. Water line passed disinfection and pressure testing requirements. 2. Work to be performed in the next 30 days Repair cracks in pad curbs and complete work on pole barn. Will collect 56-day breaks on Pad 4 cylinders to check concrete strength. Complete electrical connections to main system panel box except for tie-in from CP&L feed. All work should be completed by December ih. Site will then shut down until TSCA performance demonstration application is approved and thermal treatment system is mobilized. 3. Review of change orders (outstanding/anticipating) There were no rain days above normal in November and no change orders are anticipated. Dec06-minutes. doc Warren County Landfill -43116 4. Review status of permits applications, project drawings and submittals IT received the NC air permit for the thermal treatment unit (TIU) heating system without comment. The non-discharge permit application was resubmitted to NCDENR m early November. Pat Backus will check on the status. IT will submit a revised design for the stacked wall to be used for unloading contaminated soils onto Pad 1. IT provided copies of Submittal Nos. 41 and 48 -55 and updated progress photographs at the meeting. 5. Review construction schedule compliance IT submitted a revised schedule. This schedule shows completion of Phase I on June 10, 2002. The thermal treatment unit will be complete prior to mobilization but the timing is tight. Pending EPA approval of the TSCA submittals, IT would remobilize to the site around February 18th and the TIU would arrive around February 25 th• A project meeting would be held prior to remobilization in Earth Tech's Raleigh office to verify procedures and forms to be used during thermal treatment. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 58.1 % through Application for Payment No. 9. 7. Discuss construction/coordination issues Concrete breaks for slab 4 are 4% low compared to the 4,000-psi requirement. IT will provide 56-day breaks to estimate final strength. 8. Comments from Owner, SCO, Contractor, and Designer Earth Tech needs the as-built surveys when they are ready. Earth Tech will conduct periodic (at least monthly) visits to the site during the down time to check security and conditions of the improvements. Earth Tech will distribute minutes from the meeting with EPA in DC on November 29th via e-mail. IT will need minimum 4,000 tons of soil for the performance demonstration, maximum of 20,000 tons. Will need 15 days of treatment to be able to spike at 300 ppm. Will need three, 6-hour destruction and removal efficiency (DRE) tests, two at the maximum feed rate. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for January 3, 2002 at 1 :00 PM will be held via conference call. IT will set up the call. Dec06-minutes.doc 2 Warren County Landfill -43116 MONTHLY PROGRESS MEETING -JANUARY 2002 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A January 3, 2002 -1 :00 PM LOCATION: Via Conference Call MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders (outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals • Pond liner letter • Submittal Nos. 48 -56 • TSCA performance demonstration submittal/EPA response • EPA Laboratory QAPP • Non-Discharge Wastewater Permit • Upcoming technical submittals to NCDENR/Earth Tech 5. Review construction schedule compliance • Phase I completion/punch list • Status of thermal treatment unit • Target re-mobe date • Target treatment kick-off meeting date 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues • Concrete breaks (56-day) • Site security 8. Comments from Owner, SCO, Contractor, and Designer • Status of PCB Hotline • Interim visits prior to re-mobe 9. Schedule project monthly progress meeting date, time, and place • February ih via conference call MEETING MINUTES MONTHLY PROGRESS MEETING -JANUARY 2002 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #01044010 IA January 3, 2002 -10:00 AM LOCATION: Via Conference Call MEETING ATTENDEES Gary Duke, IT Corp. Bill Gallagher, IT Corp. David Jaeger, IT Corp. Carl Palmer, TD*X/MSR Carl Swanstrom, MSR Mike Kelly, DENR Pat Backus, DENR Jim Cloonan, Earth Tech John Funk, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. Concrete met 4,000 psi strength for Pad 4 based on 56-day breaks. Repaired cracks in pad curbs. Tensioned cables in second bay of pole barn to complete installation. Completed electrical connections to main system panel box except for tie-in from CP&L feed. All site work is essentially complete. MSR submitted a "white paper" to EPA regarding the treatment of aqueous condensate. 2. Work to be performed in the next 30 days Site is shut down until TSCA performance demonstration application is approved and thermal treatment system is mobilized. IT will submit the as-built drawings and revised plans for the stacked dump wall. MSR will submit the BCD "recipe" to EPA to address a comment on their draft submittal. EPA approval of the performance demonstration application may occur in January, although this is optimistic. Terry Lyons will submit the SITE Lab QAPP directly to EPA in DC. MSR will continue construction of the thermal treatment unit and should finish in mid-February. Jan03-minutes.doc Warren County Landfill -43116 During the week ending January 11 , 2002, MSR to follow up with EPA concerning treatment standard for condensate water from the BCD process. 3. Review of change orders ( outstanding/anticipating) There were no rain days above normal in December and no change orders are anticipated. 4. Review status of permits applications, project drawings and submittals IT submitted a letter showing that the pond liner passed the requirements of the QC plan. Earth Tech approved IT Submittal Nos. 48 -56. NCDENR review of the non-discharge permit continues. Akin & Yelle will prepare an addendum to the Erosion and Sedimentation Control Plan for the excavation work during Phase II. 5. Review construction schedule compliance IT submitted a revised schedule. This schedule shows completion of Phase I on June 26, 2002. Pending EPA approval of the TSCA submittals, IT would remobilize to the site around February 25th and the TIU would arrive around March 1gth_ 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 60.25% through Application for Payment No. 10. All site work is essentially complete and the thermal treatment unit will be ready for the target mobilization date. 7. Discuss construction/coordination issues Earth Tech will visit the site periodically to confirm conditions of trailers and security. 8. Comments from Owner, SCO, Contractor, and Designer IT will schedule a project meeting prior to remobilization in Earth Tech's Raleigh office to verify procedures and forms to be used during thermal treatment. IT will also schedule an open house at the site following mobilization of the thermal treatment unit. Condensate water issue should be resolved with EPA prior to next scheduled monthly meeting so as not to impact mobilization schedule. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for February 6, 2002 at 2:00 PM and will be held via conference call. IT will set up the call. Jan03-minutes.doc 2 Warr en County Landfill - 4 3116 MONTHLY PROGRESS MEETING -FEBRUARY 2002 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A February 6, 2002 -2:00 PM LOCATION: Via Conference Call MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders (outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals • TSCA performance demonstration submittal/EPA response • EPA Laboratory QAPP • Non-Discharge Wastewater Permit 5. Review construction schedule compliance • Erosion control features • Status of thermal treatment unit • Target re-mobe date • Target treatment kick-off meeting date 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues 8. Comments from Owner, SCO, Contractor, and Designer • Response to letter dated January 24, 2002 regarding effects of Chapter 11 on performance of the contract • Payments to pre-petition subcontractors 9. Schedule project monthly progress meeting date, time, and place • March ih via conference call? MEETING MINUTES MONTHLY PROGRESS MEETING -MARCH 2002 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A March 6, 2002 -2:00 PM LOCATION: Via Conference Call MEETING ATTENDEES Gary Duke, IT Corp. Bill Gallagher, IT Corp. David Jaeger, IT Corp. Carl Palmer, TD*X/MSR Carl Swanstrom, MSR Mike Kelly, DENR Pat Backus, DENR Pat Barnes, BF A Jim Cloonan, Earth Tech John Funk, Earth Tech Dennis Jones, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. The as-built drawings have been submitted to the NCDENR and Earth Tech. IT/MSR provided comments on EPA's draft TSCA permit, which were largely incorporated. All major issues have been resolved but need to adjust date of performance based on revised schedule and allow contingency in case liquid BCD treatment doesn't meet the concentration standard. Earth Tech repaired the erosion and sediment control features. 2. Work to be performed in the next 30 days IT is reconsidering the dry stack wall submittal concept. Kearnco to provide IT with justification for final payment amount. The surety has agreed to provide the last progress payment to MSR. MSR will resume fabrication of the thermal treatment unit once they receive the payment. NCDENR will submit landfill permit revision to Craig Brown, EPA Region IV. EPA HQ should provide final TSCA demonstration permit. M ar06-minutes. doc Warr en County Landfill - 4 3116 3. Review of change orders ( outstanding/anticipating) There was no significant site work in February and no change orders were submitted. IT cannot sign the deductive change order for the erosion repairs due to the surety claim. 4. Review status of permits applications, project drawings and submittals The final QAPP was submitted to EPA HQ in early January. EPA HQ added testing for dioxins during the pre-test. EQM will be sampling contractor and STL will be the analytical laboratory. Agriwaste will submit the draft of the revised non-discharge permit to the NCDENR no later than March ih. 5. Review construction schedule compliance A revised schedule was submitted by IT. MSR should receive the last progress payment next week and call back their workers from furlough. MSR has ordered the BCD treatment tank. Pending confirmation of the fabrication schedule, IT plans to remobe to the site on April 22nd and the BCD system would begin to arrive on May ih. Earliest possible date for shakedown would be May 29th. DRE test would then begin around June 6th with end of demonstration test around July 15th. Group should target early April for kick-off meeting, will confirm date at next progress meeting. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 60.53% through Application for Payment No. 12. All site work is essentially complete and fabrication of the thermal treatment system will resume. 7. Discuss construction/coordination issues Earth Tech will visit the site periodically to confirm conditions of trailers and security. 8. Comments from Owner, SCO, Contractor, and Designer The names of potential buyers for IT should be announced on March 20th. The NCDENR notified the performance bond surety that IT was considered in default of their contract according to the provisions of the General Conditions but stipulated they would approve of IT continuing the work. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for April 3, 2002 at 2:00 PM and will be held via conference call. IT will set up the call. If there is sufficient progress on the BCD system, this meeting may be changed to a kick-off meeting in Raleigh. Mar06-minutes.doc 2 Warren County Landfill -43116 MONTHLY PROGRESS MEETING -APRIL 2002 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A April 3, 2002 -2:00 PM LOCATION: Via Conference Call MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders (outstanding/anticipating) • Fencing along south side 4. Review status of permits applications, project drawings and submittals • TSCA demonstration permit • Non-Discharge Wastewater Permit 5. Review construction schedule compliance • Status of thermal treatment unit • Target re-mobilization date • Target treatment kick-off meeting date 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues 8. Comments from Owner, SCO, Contractor, and Designer • Status of bankruptcy proceedings • Spending forecast for Phase I 9. Schedule project monthly progress meeting date, time, and place • Kick-off meeting in Raleigh? MEETING MINUTES MONTHLY PROGRESS MEETING -APRIL 2002 WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101 A April 3, 2002 -2:00 PM LOCATION: Via Conference Call MEETING ATTENDEES Gary Duke, IT Corp. Carl Palmer, TD*X/MSR Carl Swanstrom, MSR Mike Kelly, DENR Pat Backus, DENR Pat Barnes, BF A Jim Cloonan, Earth Tech John Funk, Earth Tech Dennis Jones, Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. IT sent the final progress payment (No. 4) to MSR on March 11 th • EPA approved the Laboratory QAPP with modifications regarding dioxin sampling. There was no site work. 2. Work to be performed in the next 30 days NCDENR will submit the TSCA permit modification to Region IV for approval. EPA HQ should provide final TSCA demonstration permit. MSR will complete fabrication of the thermal treatment by the end of April. Equipment will start to arrive at the site beginning on April 15th• 3. Review of change orders (outstanding/anticipating) IT will be issued a change order to install an access gate to Mr. White's property. Earth Tech will be issued a change order for the erosion control repairs constructed in February. 4. Review status of permits applications, project drawings and submittals MSR will begin to mobilize equipment before receipt of the final performance demonstration permit. MSR can construct their unit but cannot handle TSCA waste Mar06-minutes. doc Warren County Landfill -4 3116 until the permit is issued. The spray irrigation permit is still pending. Construction of the water treatment system can't begin until the permit is issued. 5. Review construction schedule compliance A revised schedule was submitted by IT. The thermal treatment unit should be completed by the end of April and be at the site by mid-May. Mobilization will occur from April 15 th through May 131\ with the bulk of activity occurring in May. Dave Ditcher and Bill Gallagher ofIT will be at site on April 15th with the remainder of the crew arriving on April 22nd. The guard shack will be installed on April 22nd. IT will have two equipment operators, two laborers, one H&S officer, and one H&S technician. 6. Percentage complete to be reported by Contractor (actual work in place) Percent complete by invoice is 62.5 % through Application for Payment No. 13. All site work is essentially complete and fabrication of the thermal treatment system has resumed. 7. Discuss construction/coordination issues Earth Tech will visit the site periodically to confirm conditions of trailers and security until IT has returned. 8. Comments from Owner, SCO, Contractor, and Designer Bankruptcy bids for IT are due on April 16th, with the auction (if multiple bidders) on April 18th, results to be confirmed by the court on April 19th, and the last hearing is set for April 24th• At that point, the sale should be completed. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for May 1, 2002 at 10:00 AM at the site. Mar06-minutes.doc 2 Warren County Landfill -43116 MONTHLY PROGRESS MEETING -MAY 2002 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A May 1, 2002 -10:00 AM LOCATION: Warren County -IT Construction Trailer MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders (outstanding/anticipating) • New gate to White property 4. Review status of permits applications, project drawings and submittals • TSCA demonstration permit • Non-Discharge Wastewater Permit • 30-Day advance notification • Region IV approval 5. Review construction schedule compliance • Status of thermal treatment unit • Target dates for shakedown • Target dates for performance demonstration 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues • New site staff • Start of perimeter air monitoring • Perimeter monitoring locations • Inputs to heat & material balance 8. Comments from Owner, SCO, Contractor, and Designer • Status of sale to Shaw • Contract issues • Use oflocal resources • Status of PCB Hotline 9. Schedule project monthly progress meeting date, time, and place • June 61\ 1 :00 PM MEETING MINUTES MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A MAY 5, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill ATTENDEES: Pat Backus Jim Cloonan John Funk Dennis Jones Pat Barnes NCDENR Earth Tech (by phone) Earth Tech Earth Tech BFA MEETING MINUTES 1. Work performed in the last 3 0 days. Gary Duke Bill Gallagher Dave Ditcher Mike Kelly Shaw Shaw Shaw NCDENR EPA reviewed test plan permit. Shaw (MSR) has not received responses from Carl Palmer's comments on TSCA permit, but permit is expected by the end of May. Shaw has received comments from DWQ on NPDES permit, Shaw will submit responses by May 10, 2002. DWQ requested a closure plan for lined pond. Shaw started construction of the site haul road and the ramp from the road to pad #1. Shaw has mobilized some equipment to the landfill site and will continue to mobilize during May. 2. Work to be performed in the next 30 days Complete site haul road and ramp. Shaw handed out an equipment shipping schedule during the meeting. Schedule indicates that all equipment will be on site by the end of May and system setup will commence at the end of the month and setup will be compete by July 15 , 2002. Site security will also in instituted during May. 3. Review of change orders ( outstanding/anticipating) Change Order No. 4 (?) will be signed when contract is transferred to Shaw. 4. Review status of permits applications, project drawings and submittals Carl Palmer is to resolve EPA comments on TSCA permit. Responses to comments on NPDES permit due to DWQ May 10, 2002. After comments are received, there is a 30-day review period before a permit would be issued. 5. Review construction schedule compliance Gary Duke handed out a revised project schedule during the meeting. System set up complete by July 15 , 2002. DRE testing will be comprised of three runs starting July 23-24, 2002. Testing will require an estimated 500-900 tons of soil. 6. Percentage complete to be reported by Contractor (actual work in place) Project is 66.61 % complete based upon contractor invoices. 7. Discuss construction/coordination issues New Shaw personnel on site are Dave Ditcher -Site Supervisor, Joe Walker -Site Health and Safety, and Barry Howard -Site Accountant. Earth Tech plans to erect met tower and construct air monitoring platforms during May. Carl Palmer needs to provide Earth Tech with confirmation of the assumptions used in their heat and material balance on the BCD System. 8. Comments from Owner, SCO, Contractor, and Designer The sale ofIT to Shaw has been approved by the courts, and the Warren County PCB Landfill project is on Shaw's accepted list of projects. Local resources will be utilized for site security, on-site trucking, and BCD System fuel supply. PCB hot-line will be restored by May 14, 2002 9. Schedule project monthly progress meeting date, time, and place The next monthly progress meeting is scheduled for June 5, 2002 at the Warren County PCB Landfill at 10:00 am. AGENDA AIR MONITORING MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION PROJECT MAY 16, 2002 1:00 PM WARREN COUNTY SITE 1.0 INTRODUCTIONS 2.0 AIR MONITORING PLAN 2.1 Revisions 2.2 Perimeter Sampling Frequency 2.3 Reserve Samples 2.4 Trip Blanks 2.5 Perimeter Sampling SOPs 2.6 Sample Preparation 2. 7 Sample Validation 2.8 Data Records and Presentation 2.9 Evaluation of Duplicate Samples 2.10 Real-Time Monitoring-VOCs 2.11 Real-Time Monitoring -PM 2.12 Data Forms 3.0 MONITORING AND MET STATIONS 3 .1 Met Station Status 3 .2 Modem and Software 3.3 Revised Monitoring Station Locations 3.4 Monitoring Stands 3.5 Status of Sampling Equipment 4.0 ADMINISTRATIVE ISSUES 4.1 Project Personnel 4.2 Schedule 4.3 Target Shakedown Sampling Date 4.4 Coordination with Pace Labs 4.5 Application of Ambient Air Guidelines 4.6 Dust Control 4.7 Site Walk 5.0 ACTION ITEMS MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 June 6, 2002 -TIME 8:30 AM LOCATION: Warren County PCB Landfill MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders (outstanding/anticipating) Status of Change Order No. 4 Pending change order for thermal treatment 4. Review status of permits applications, project drawings and submittals Status ofTSCA permit. Wastewater discharge permit Implications of Liquid BCD being RCRA hazardous waste (corrosive) 5. Review construction schedule compliance Weekly work forecasts (major items) Start of shakedown using PCB soils 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues 8. Comments from Owner, SCO, Contractor, and Designer Status of Shaw bonding for Phase I and Phase II Dust control Trigger levels for site based on real-time monitoring MSR confirmation of HIM balance assumptions 9. Schedule project monthly progress meeting date, time, and place MEETING MINUTES MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A June 6, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill ATTENDEES: Pat Backus Jim Cloonan John Funk Mike Kelly NCDENR Earth Tech (by phone) Earth Tech NC-DENR MEETING MINUTES 1. Work performed in the last 30 days. Gary Duke Bill Gallagher Dennis Jones Pat Barnes Shaw Shaw Earth Tech BFA BCD mobilization is 95% complete. Trailers are on site, and plumbing and wiring will be completed in June. Haul road and ramp to Pad No. 1 are complete, and sprinkler system for haul road will be completed in June. Spray irrigation permit has been received. Expect TSCA permit in June. 2. Work to be performed in the next 30 days Complete mobilization and proceed with BCD system setup. Shakedown test to be started by July 10th or sooner. System pre-test scheduled for July 15th or following week. Opening up the landfill for collection of soils will require EPA Region IV approval -Shaw to pursue. Complete storm water collection and treatment system. Run BCD system with clean soil scheduled for the last week in June. 3. Review of change orders ( outstanding/anticipating) Change Order No. 5 for soil treatment will be prepared by Shaw. Shaw needs bonding for the additional work covered in Change Order No. 5. 4. Review status of permits applications, project drawings and submittals Carl Palmer will contact EPA regarding the TSCA permit. 5. Review construction schedule compliance Gary Duke handed out a revised project schedule during the meeting. System set up complete by July 15, 2002. DRE testing will be comprised of three runs starting July 23 -24, 2002. Testing will require an estimated 500-900 tons of soil. 6. Percentage complete to be reported by Contractor (actual work in place) Phase I is 70.66% complete based upon contractor invoices. 7. Discuss construction/coordination issues None 8. Comments from Owner, SCO, Contractor, and Designer DENR to schedule open house at the site before June 24th since public access to the site may be restricted after that date. Schedule half-day for open house. 9. Schedule project monthly progress meeting date, time, and place The next monthly progress meeting is scheduled for July 2, 2002 at the Warren County PCB Landfill at 10:00 am. MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 July 2, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders (outstanding/anticipating) Status of Change Order #5. 4. Review status of permits applications, project drawings and submittals TSCA demonstration permit implications Performance demonstration analysis Performance documentation and certification Soil weight documentation, weight certification, and scale certification 5. Review construction schedule compliance Schedule dates for clean soil test run Opening up of landfill Start of Performance Demonstration test 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues Real-time air monitoring 8. Comments from Owner, SCO, Contractor, and Designer Status of Shaw bonding for Phase I and Phase II Local hiring and financial involvement 9. Schedule project monthly progress meeting date, time, and place MEETING MINUTES MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #010440101A July2, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill ATTENDEES: Pat Backus Mike Kelly Jim Cloonan John Funk NCDENR NCDENR Earth Tech Earth Tech MEETING MINUTES 1. Work performed in the last 30 days. Carl Palmer Gary Duke Dave Ditcher Pat Barnes Midwest Shaw Shaw BFA BCD mobilization is complete. TSCA permit was received with start date of June 18, 2002. Storm water system is complete except of engineer's certification of system as required in spray irrigation permit. . 2. Work to be performed in the next 30 days Complete installation of BCD system. Conduct clean soil shakedown test runs of BCD system. Form Jersey Barrier soil bins on slabs #2 and 4. Open up landfill to expose soils for sampling, and to stage clean soils under pole barn for clean soil test runs and weigh belt calibration. Collect soil samples from unlined pond for analysis. 3. Review of change orders (outstanding/anticipating) Change Order No. 5 approved. Shaw needs to secure bonding for additional work covered in the change order. 4. Review status of permits applications, project drawings and submittals All permits received and letter from EPA Region IV received authorizing opening up of the landfill. 5. Review construction schedule compliance Gary Duke handed out a revised project schedule during the meeting. System set up complete by July 15, 2002. Shakedown runs (contaminated soil) July 24, 2002. DRE testing will be comprised of three runs starting July 31, 2002. Testing will require an estimated 1000 tons of soil. 6. Percentage complete to be reported by Contractor (actual work in place) Project is 80.35% complete based upon contractor invoices. Note that percent complete does not include contract adjustment resulting from Change Order #5. 7. Discuss construction/coordination issues Shaw contracted with Toxicon Corp to analyze soil samples. This lab will produce PCB analytical results in less than 48 hours. Shaw distributed the following transmittals: Final Verification/Confirmation Sampling Plan and Technetics Industries weigh belt system description and calibration procedures. Terry Lyons said that his subcontractor can't meet the I-week TAT for analyses specified in the permit. Shaw will contact EPA HQ to modify the permit. TSCA permit start date is June 10, 2002 with termination date of September 20, 2002. Shaw/Midwest to obtain revised termination date to conform to anticipated shakedown and DRE schedule. 8. Comments from Owner, SCO, Contractor, and Designer Earth Tech asked about the anticipated production rates and completion date. Shaw estimates that they can treat 15 tons/hour (nominally 12 TPH based on 80% uptime for 6 days/week). At this rate, soil treatment should be complete by April 2003. Unit will run 24 hours/day, 6 days/week. Shaw won't reach the bottom of the landfill in the first excavation face until around Labor Day, will have to remove approx. 10,000 tons of soil first. Earth Tech asked about the Performance Demonstration Analysis, report that certifies treated soils meet the performance standards. Shaw produced a draft document for approval based on the requirements of the TSCA permit. 9. Schedule project monthly progress meeting date, time, and place The next monthly progress meeting is scheduled for August 7, 2002 at the Warren County PCB Landfill at 10:00 am. 2 MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 August 7, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill MEETING AGENDA 1. Work performed in the last 30 days. 2. Work to be performed in the next 30 days 3. Review of change orders (outstanding/anticipating) Status of bonding for Change Order #5. 4. Review status of permits applications, project drawings and submittals Comments on Sampling Plan Status ofEQM QAAP. Performance demonstration -EP A/EQM schedule Soil weight documentation, weight certification, and scale certification 5. Review construction schedule compliance Schedule dates for shakedown and performance demonstration test. 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues Contingency plan for conducting analysis during PDT if EP A/EQM cannot support schedule. Contingency plan for soil stockpiling/retreivel/retreatment if results of dioxine TEQ tests are above limits. 8. Comments from Owner, SCO, Contractor, and Designer Status of Shaw bonding for Phase I and Phase II 9. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 August 7, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill ATTENDEES: Pat Backus -NC DENR Gary Duke -Shaw Pat Barnes -BF A Jim Cloonan -Earth Tech John Funk-Earth Tech Bill Gallagher -Shaw Dave Ditcher -Shaw MINUTES 1. Work performed in the last 30 days. • Set up BCD system. • Excavate landfill cover and remove soil from beneath liner to obtain soil for the thermal treatment test runs. 2. Work to be performed in the next 30 days • Collect soil samples on 8/6/02 for PCB analysis to support DRE test. • Earliest date to start treating contaminated soil is 8/19/02. • First DRE test scheduled for 8/26-27, the 4th day of running. • Perform preliminary DRE on first 5,000 tons of contaminated soil. Conduct NIOSH sampling in conjunction with Environmental Quality Management (EQM) stack testing to validate NIOSH methods for subsequent DRE testing. • Treat second and third 5,000 ton increments after Labor Day. MSR/Shaw will shut down project from 8/31 through 9/3/02. • 9/16 or 9/23/02 conduct performance demonstration test (PDT) with EPA on-site. Dates contingent upon having collected sufficient PCBs to spike the feed soil. • MSR and Shaw to coordinate with EPA and their subcontractor for attendance at the PDT. 3. Review of change orders ( outstanding/anticipating) • Earth Tech provided Shaw with signed copies of Change Orders #4 and #5. • Bonds for Change Order #5 due Friday 8/16/02. 4. Review status of permits applications, project drawings and submittals • Shaw to revise Sampling Plan with verification soil level in the clay liner of the landfill and bottom of unlined pond set at the EPA high-density residential criteria for PCBs of 1 mg/kg, per comment from EPA Region IV on the TSCA permit. • Shaw to revise Sampling Plan to include dioxin TEQ testing of soils prior to thermal treatment. Dioxin in treated soils will be addressed similarly to the PDT. Shaw will test dioxin in the feed and treated soils during each of the three PDT runs. If treated soil levels meet the performance standard, dioxin will then be analyzed once a month in the feed soils. • Shaw to provide copy ofEQM QAAP. • Shaw to perform soil weight documentation and weigh belt calibration. Weigh belt scale certification to be provided by the NC Dept of Agriculture. Shaw will provide Earth Tech a copy of the Dept of Agriculture certification. 5. Review construction schedule compliance • Shaw will provide schedule dates for shakedown and performance demonstration test in future schedules. 6. Percentage complete to be reported by Contractor (actual work in place) Phase I is 91.76% complete 7. Discuss construction/coordination issues • Shaw to coordinate PDT with EPA and EQM. • Shaw to coordinate weigh belt calibration. • The meteorological station has been repaired and is now operational. 8. Comments from Owner, SCO, Contractor, and Designer Shaw to secure bonding for Phase II prior to treatment of contaminated soils. Phase I bonding remains in place. 9. Schedule project monthly progress meeting date, time, and place Next meeting scheduled for 9/11/02 at 10:00 am at the PCB landfill. 2 1.0 2.0 3.0 ITEMS FOR DISCUSSION PROJECT REVIEW MEETING WARREN COUNTY LANDFILL PCB DETOXIFICATION SEPTEMBER 10, 2002 2:00 PM THERMAL TREATMENT 1.1 Status of A WFCOs 1.2 Burner Operation 1.3 Scale Operation 1.4 DRE Results 1.5 Treated Soil Sampling Protocols 1.6 Control of Fines/Carryover 1.7 Performance Demonstration Test 1.8 Projected Treatment Rates 1.9 Projected Completion Date 1.10 Presence of Key Personnel 1.11 Operating Schedule 1.12 Training Issues 1.13 Protective Equipment on Pad 4 1.14 Community Perception CONTRACTUAL ISSUES 2.1 Bond Status 2.2 Fuel Charges 2.3 AFP #18 2.4 Performance Demonstration Analysis form 2.5 Definition of Batches 2.6 Subtraction of Solid Residuals 2.7 Definition of Attainment of Treatment Standard 2.8 Contract Time 2.9 Liquidated Damages ACTION ITEMS MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 September 11 , 2002 -TIME 1 :00 PM LOCATION: Warren County PCB Landfill MEETING AGENDA 1. Work performed in the last 30 days • Results of DRE test • Scale certification 2. Work to be performed in the next 30 days 3. Review of change orders ( outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals • Revised Sampling Plan • Performance Demonstration Analysis form 5. Review construction schedule compliance • Met tower repairs • Schedule dates for performance demonstration test • Soil quantity treated to date 6. Percentage complete to be reported by Contractor (actual work in place) 7. Discuss construction/coordination issues • Resolution of operating conditions • Target feed rate and completion date • Dioxin analyses in feed soils • Definition of batches • Real-time air monitoring results • Perimeter monitoring results 8. Comments from Owner, SCO, Contractor, and Designer • Status of Shaw bonding for Phase I and Phase II 9. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 September 11 , 2002 -TIME 1:00 PM LOCATION: Warren County PCB Landfill ATTENDEES: Pat Backus, NC DENR Mike Kelly, NC DENR Gary Duke, Shaw Bill Gallagher, Shaw MEETING MINUTES Dave Ditcher, Shaw Jim Cloonan, Earth Tech John Funk, Earth Tech Pat Barnes, BFA (via phone) Final minutes from the August 12, 2002 progress meeting were approved without comment. Approval of the minutes will be added to the agenda for future meetings. 1. Work performed in the last 30 days Environmental Quality Management (EQM) performed the DRE test on August 26, 2002. Shaw indicated the system passed the test. Dioxin results from DRE test were 1/100th of concentration needed to pass the test. Results were sent to EPA in a letter from Carl Palmer. MSR sent a request to TSCA asking them to extend the demonstration approval through 10/31/2002. Weigh belt scale was certified by NC Department of Agriculture and certification was also received for the flat (platform) scale that measures residuals. Shaw will add a direct readout in the control room for the flat scale. 2. Work to be performed in the next 30 days Continue operation of the BCD unit. Performance demonstration test (PDT) is scheduled for week of October 21 , 2002. Shaw believes they will have collected enough oil by this time to spike the feed soils. Collection on the ductwork has prevented Shaw from calculating how much oil is generated per ton of soil processed. MSR will perform NIOSH method stack test during the next 5,000 -10,000 tons of soil to be treated. 3. Review of change orders ( outstanding/anticipating) None outstanding. Fuel adjustment change order will be prepared on a quarterly basis or longer period, if warranted. 4. Review status of permits applications, project drawings and submittals Shaw is to revise the Sampling Plan to indicate that treated soil samples will be collected on Pad 4 rather than from the conveyor after the product cooler on Pad 3, due to decon issues. Craig Brown of EPA gave verbal approval for this during a conference call with Shaw and DENR. DWQ is scheduled to inspect the storm water treatment system. Daily production form modified to track weights of residual material. 5. Review construction schedule compliance Met tower repairs are complete except for installation of new rain gauge. PDT is scheduled for week of October 21, 2002. Shaw has processed 1,248 tons of soil to date, although most of these have not met the treatment standard. 6. Percentage complete to be reported by Contractor (actual work in place) -65 .6% for combined Phase I/Phase II work. 7. Discuss construction/coordination issues Treated soil discharge is 965 degrees F, and feed rate is temperature dependent. Shaw believes they have resolved the burner difficulties. The Daily Production Form has been modified to better track batches and weights of treated and recycled materials. Perimeter air monitoring results will be available early next month. Earth Tech will provide a copy of the results to all. Pat Barnes said he believed that the stormwater measures in place are protective. Sampling of the feed soils for dioxins will occur during the PDT. 8. Comments from Owner, SCO, Contractor, and Designer Bonding in place for Phase II covered by Change Order #5. 9. Schedule project monthly progress meeting date, time, and place October 9, 2002 at 10:00 am in the Shaw trailer. 2 MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 October 9, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill MEETING AGENDA 1. Work performed in the last 30 days • Soils processed/passed • Nominal throughput 2. Work to be performed in the next 30 days 3. Review of change orders ( outstanding/anticipating) 4. Review status of permits applications, project drawings and submittals • Revised Sampling Plan • Running average evaluation • Modified Performance Demonstration Analysis form 5. Review construction schedule compliance • Soils processed/passed to date • EPA extension of demonstration approval to 11/30/02 • Readiness/schedule for PDT • Likely throughput and Phase II completion date 6. Percentage complete to be reported by Contractor (Phase I & II) 7. Discuss construction/coordination issues • Resolution of operating conditions • Uptime percentage • Laboratory Analyses • Oil recovery quantity/rates • Spiking of feed soils • Liquid BCD test • Wastewater treatment performance • Perimeter monitoring schedule • Real-time air monitoring results • Perimeter monitoring results 8. Comments from Owner, SCO, Contractor, and Designer • Daily production reports • Definition of operating day • Cash flow projections for 2002 9. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 October 9, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill ATTENDEES: Pat Backus -NC DENR Mike Kelly -NC DENR Pat Barnes -Community Advisor Gary Duke -Shaw Bill Gallagher -Shaw MEETING MINUTES Jim Cloonan -Earth Tech John Funk-Earth Tech Rob Holland -Earth Tech Dave Ditcher -Shaw Minutes of the September 11, 2002 monthly progress meeting were approved without comment. 1. Work performed in the last 30 days • Shaw received a letter from EPA headquarters approving the DRE test results -Shaw is now in interim operations. The letter also extended the permit date to November 30, 2002. • As of September 301\ Shaw has processed approximately 3,000 tons of soil with 1,918 tons passing the acceptance criterion (200 ug/kg weighted average). • Shaw is processing approximately 15 tons per hour @ 85% uptime or 306 tons per day. They plan to increase soil production in the coming month. 2. Work to be performed in the next 30 days • Process soil with rate increasing to 20+ tons per hour. • PDT postponed until at least November 18, 2002. The date is tentative, and is contingent upon having enough oil to spike the soil for the PDT test and on availability of EQM to conduct testing. • MSR will conduct stack testing (NIOSH method) at about the 7500 tons mark. MSR/Shaw to coordinate with Earth Tech so that perimeter air monitoring will coincide with the NIOSH test. 3. Review of change orders (outstanding/anticipating) • Shaw submitted Change Order #6 for treatment of remainder of the soil (up to 72,000 tons). Change Order value is approximately $4.4 million, and is pending approval by Earth Tech, DENR, and SCO. The contract time will increase with substantial completion by September 2003. 4. Review status of permits applications, project drawings and submittals • Shaw revised the Sampling Plan to collect samples for compositing hourly from the side of each pile on pad #4. EPA has approved the revised Plan. Shaw is to submit to Earth Tech a final version of the Sampling and Analysis Plan for review and comment by October 18, 2002. • Soil will be accepted as successfully treated based on a weighted average approach. The weighted average cannot exceed 200 ug/kg and the maximum concentration cannot exceed 500 ug/kg. Sample results that are non-detect or below quantitation limits will be calculated in the weighted average as half the quantitation limit for that sample. • Shaw is to modify the production approval form to include the weighted average. • Shaw to submit names of laboratories to conduct PCB testing. • Shaw is to provide Earth Tech daily production reports by noon of each day. The production day runs from 1830 hours to 1830 hours. 5. Review construction schedule compliance • 1,918 tons of soil were accepted as successfully treated by Earth Tech. • EPA extended the demonstration approval to 11/30/02. • PDT tentatively scheduled for November 18, 2002. • With the approval of Change Order #6, project completion will be September ls1h, 2003. 6. Percentage complete to be reported by Contractor (Phase I & II)-68.15% (through CO#5) 7. Discuss construction/coordination issues • Shaw is assuming an uptime percentage of 85%, but actual percentage has been closer to 60% due to MSR having to retreat soils. • Shaw hired an independent review of both Paradigm and Southern Engineering laboratories. Both were found to be acceptable. Shaw is to select laboratories for PCB analysis and submit those names to Earth Tech. There should be one analysis per composite sample for each batch. • To date, Shaw has recovered approximately 50 gallons of oil. They estimate that 500 gallons will be required to spike soils for the PDT. PCBs will not be brought to the site for spiking. • The bag filters added to the wastewater system are not removing any additional PCBs. The DWQ approved the permit modification for the filters. Shaw to evaluate options and advise NC DENR. An additional permit modification may be required. • Treated water has been sent to the unlined pond only during the large rain event in Sepmber and not since. There is no standing water in the unlined pond. • Perimeter monitoring will be conducted in conjunction with the NIOSH stack test. Anticipated schedule is first week of November 2002 at the 7,500 tons mark. 2 • Earth Tech presented results of the perimeter air monitoring during the DRE test. All results are within NC and NAAQS limits except methylene chloride, as was the case for the background sampling. PCBs were detected at all locations but within the NC limit. Earth Tech will issue a summary memo to the group. • It was agreed that future perimeter air monitoring will not include volatile organic compounds since the results of the monitoring conducted during the DRE did not vary significantly from the base line monitoring. • The eastern limits of the landfill extend past the surveyed limits as shown on the project drawings. Shaw will determine the eastern limits using a trackhoe. The other landfill boundaries are assumed as shown on the drawings. Excavation has not yet reached the bottom of the landfill. Shaw will advise DENR/Earth Tech of the potential increase in landfill volume once the width and depth are defined. 8. Comments from Owner, SCO, Contractor, and Designer • Daily production reports to be submitted to Earth Tech by noon of each day. • An operating day is 1830 hours to 1830 hours. 9. Schedule project monthly progress meeting date, time, and place • November 6, 2002 at the landfill site at 1000 hours. 3 MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 November 6, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill MEETING AGENDA 1. Work performed in the last 30 days • Soils processed/passed • Nominal throughput 2. Work to be performed in the next 30 days 3. Review of change orders ( outstanding/anticipating) • Status of Change Order #6. 4. Review status of permits applications, project drawings and submittals • Revised Sampling Plan • Running average evaluation • Extension ofTSCA performance demonstration test. 5. Review construction schedule compliance • Soils processed/passed to date • EPA extension of demonstration approval to 01/2003 6. Percentage complete to be reported by Contractor (Phase I & II) 7. Discuss construction/coordination issues • Uptime percentage • Oil recovery quantity/rates • Wastewater treatment performance • Storm water treatment system performance • Erosion and sedimentation controls • Perimeter monitoring schedule -10,000 to 15, 000 tons range. • Perimeter monitoring results 8. Comments from Owner, SCO, Contractor, and Designer • Repair/maintenance of erosion & sediment control measures • Cash flow projections for 2002 • Liens on project • Subcontractor payment terms 9. Schedule project monthly progress meeting date, time, and place • December 11 th at 10:00 AM MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION ID #6095220110 November 6, 2002 -TIME 10:00 AM LOCATION: Warren County PCB Landfill ATTENDEES: Pat Backus -NC DENR Mike Kelly -NC DENR Gary Duke -Shaw Pat Barnes -Community Technical Advisor MEETING MINUTES John Funk -Earth Tech Jim Cloonan -Earth Tech Rob Holland -Earth Tech Minutes from the October 9, 2002 Monthly Progress Meeting were approved by all attendees with the following clarification requested by Shaw: Item No. 4, third bullet delete "weighted average" and insert -disposition, "Acceptable, But Contractor Chooses to Reprocess." 1. Work performed in the last 30 days • In the last 30 days, 8,445 tons of soils were processed. 7,992 tons passed and 453 tons did not meet the acceptance criteria. • Nominal throughput is 310 tons per day (tpd) versus a target of306 tpd. Production target is 20 tons per hour. 2. Work to be performed in the next 30 days • Continue processing soil. MSR intends to work through Thanksgiving and only break for the Christmas holiday. • The second NIOSH stack test, during the 10,000 to 15,000 ton range of treated soils, is scheduled for week of November 18, 2002. Earth Tech requested that test be conducted during dry weather so that the perimeter air monitoring, conducted as a simultaneous event, is conducted during non-rainfall conditions. 3. Review of change orders (outstanding/anticipating) • Money for Change Order #6 has not been transferred as yet to DENR's account. Funds will likely be available in November. 4. Review status of permits applications, project drawings and submittals • Comments on Sampling Plan were provided to Shaw on November 5, 2002, and Shaw will revise and resubmit accordingly. • Running average of approved soils is 109 ug/kg of PCBs versus the legislated target of 200 ug/kg. • Shaw is to continue contacting EPA concerning extension ofTSCA performance demonstration test from November 30, 2002 to January 31 , 2003. 5. Review construction schedule compliance • 9,911 tons of soils were processed and passed to date. 7,992 tons were processed and passed in October. • Soil processing finish date June -July 2003. • The estimated Phase II completion date is September 18, 2003. 6. Percentage complete to be reported by Contractor (Phase I & II) • 76.27% complete Phase I & II, 32.9% complete Phase II only. 7. Discuss construction/coordination issues • Uptime 82%, 310 tpd versus target of 306 tpd. • Oil recovery is approximately 300 gallons, which is below Shaw's expectations. From the DRE, oil contains 7% PCBs. Quantity should be sufficient to conduct PDT the week of January s111• • PDT should involve one run on January 6th and two runs on January ih. The liquid BCD test will likely lag a week to allow recovery of the spiked oils. • MSR is working on filter for wastewater treatment system to improve performance. • Storm water system has treated over 1 million gallons. Scheduled sampling of treatment system influent, effluent, unlined pond water and sediment, and sedimentation basin sediment was conducted on November 1, 2002 by Earth Tech and DENR personnel. • Perimeter monitoring schedule, 10,000 to 15,000 tons range, scheduled for week of November 18, 2002. • Perimeter monitoring results from the August sampling event were shared with the attendees. All PCB and dioxin results were within the NC guidelines. • Shaw reported a release of diesel fuel due to broken fuel line on a dump truck on November 6, 2002. Shaw was instructed to undertake reporting and corrective actions in accordance with Division of Water Quality, Groundwater Section Guidelines. • Shaw expects to have their NC General Contractor's license by January, will keep DENR informed of progress. 8. Comments from Owner, SCO, Contractor, and Designer • Due to recent heavy rains, Shaw was reminded of the importance of maintaining site erosion & sediment control measures. Shaw has added silt fences around the treated soil stockpile and will reseed the northern boundary of the landfill. • Cash flow projections were provide to DENR by Shaw and Earth Tech. • Lien filed by Pride on MSR was been corrected with MSR and Pride agreeing to a payment plan. • The Community Technical Advisor stated that the community concerns were mainly on the issues of storm water and potential impact on sediments. He was advised of the storm water and sediment sampling conducted on November 1, 2002, and that the results would be shared upon receipt. 2 • The Community Technical Advisor stated that he was concerned that storm water on the treated soil pad could pass beneath the jersey barriers such that contaminants from one bin could pass to an adjacent bin. Shaw stated that they had observed storm water flowing around the barriers but only in very heavy rain events due to the slope of the pad. Shaw stated that they observed no sediment transport in the flow around the barriers. They also stated that flow beneath the barriers was unlikely due to the build up of soil against the base of the barrier and beneath the barrier. Earth Tech will watch for run-off between bins during storm events. • The Community Technical Advisor stated that he was concerned that the contractor could negate the intent of the legislated criterion of 200 ug/kg by the using the running average (109 ug/kg current average) to produce a series of batches above 200 ug/kg. Shaw stated that their system was not that precise to enable them to "tweak" treatment system. DENR also stated that they would chart the results to look for any such action. The net result to date for the community is positive, as the average PCB concentration in the landfill is approximately half the legislated target. • The eastern limits of the landfill are still not delineated. 9. Schedule project monthly progress meeting date, time, and place • January 8, 2003 at 1100 hrs at Shaw's trailer. 3 MONTHLY PROGRESS MEETING -NOVEMBER 2001 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A December 11 , 2002 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill MEETING AGENDA 1. Approval of November minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate • Results of DRE test 3. Work to be performed in the next 30 days • Holiday schedule 4. Review of change orders (outstanding/anticipating) • Change Order #6 • Shaw change order notification • Potential change order costs to date (erosion controls) 5. Review status of permits applications, project drawings and submittals • TSCA • Non-Discharge Wastewater Permit 6. Review construction schedule compliance • Phase I target completion date • Phase II target completion date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Sediment sampling results • Sampling of landfill cover materials • Soil volume excavation requirements • Air monitoring results • Erosion control • Extent of landfill • Target dates for Performance Demonstration Test 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • East extension of landfill 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A December 11 , 2002 -TIME 11 :00 AM ATTENDEES: Pat Backus -NC DENR Doug Edwards -SCO Par Barnes -Community Technical Advisor Gary Duke -Shaw MEETING MINUTES Bill Gallagher -Shaw Jim Cloonan -Earth Tech John Funk-Earth Tech Dennis Jones -Earth Tech 1. Minutes of the November 6, 2002 progress meeting were approval without comment. 2. Work performed in the last 30 days. • 14,247 total tons of soil were treated and accepted. 4338 tons were treated and accepted in November. The average concentration is 106 ug/kg versus a target concentration of 200 ug/kg. • The November processing rate was below schedule of 306 tons per day due to equipment downtime and soil moisture content that limited production to 12-13 tons per hour. • Shaw did not have available the results ofNIOSH stack test conducted in November (10,000-15 ,000 tons increment) 3. Work to be performed in the next 30 days • Due to ice storm, power was out at the site from December 4th through December 11th when power was restored at 1600 hours. MSR and Shaw will shutdown on December 22nd until December 29th for the Christmas Holiday. They anticipate working over New Years. 4. Review of change orders ( outstanding/anticipating) • Change Order #6: Money is available and will be transferred into DENR account when needed. • Shaw anticipates issuing a change order for additional erosion and sediment control measures at the soil stockpile area. Change order expected to be in the $4,000- $5 ,000 range. • Project completion date should be increased 7 days to account for the power outage due to the ice storm. 5. Review status of permits applications, project drawings and submittals • Performance Demonstration Test is planned to start on January 6, 2003. EQM will mobilize on-site on Sunday, January 5th• • Earth Tech will conduct perimeter air monitoring during that week in conjunction with the PDT. • Shaw received an extension of the TSCA startup period to January 31 , 2003. • Shaw added a floe system to the storm water treatment system. 6. Review construction schedule compliance • Phase I is essentially complete. • Phase II target completion date is July 2003 for soil treatment, but meeting that date will require increase in production rate and system availability over performance to date. 7. 80.5% percentage complete on money approved to date. 96% complete on Phase I. 8. Discuss construction/coordination issues • Sampling results from the sedimentation basins were discussed. Pat Barnes requested that additional samples be collected down stream of the basins and he and Dennis Jones were to mark those locations. • Sampling of landfill cover materials showed PCB concentrations in the soil cover above the flexible membrane liner and also in the clay cap above the waste material. Earth Tech to develop options for dealing with these soils. • Shaw has indicated that the landfill may be 16 feet wider than had been delineated on the site as-built drawing for the landfill. Earth Tech to revise soil tonnage estimates and present to DENR. • Air monitoring results from the November sampling event are under review and will be available at the next progress meeting scheduled for January 2003. • Erosion control measures requested by Earth Tech for the north side of the site have been implemented by Shaw. • Target date for Performance Demonstration Test is January 6, 2003. 9. Comments from Owner, SCO, Contractor, and Designer • The Community Technical Advisor requested additional samples be collected downstream of the sedimentation basins, DENR and Earth Tech concurred. 10. Schedule project monthly progress meeting date, time, and place: January 9, 2003 at 1100 hours at the Landfill Site. AGENDA WARREN COUNTY PCB LANDFILL DETOXIFICATION PROJECT NCDENR -EARTH TECH MEETING -RALEIGH, NORTH CAROLINA JANUARY 6, 2003 2:00 PM 1.0 INTRODUCTIONS 2.0 TREATED SOILS 2.1 Tons to Date 2.2 Targeted Completion Dates (Shaw/Earth Tech) 2.3 Shaw's Project Management 3.0 PROJECTED COSTS 3.1 Spent to Date/Percent Completion (Shaw and Earth Tech) 3.2 Authorized Amount/Remaining Funds (Shaw and Earth Tech) 3.3 Soil Volume Budgeted for Treatment 3.3.1 Original Volume (tonnage) 3.3.2 Revised Volume (tonnage) 3 .4 Other Soil Volumes 3.4.1. Non-Treatment Rationale 3.3 .3 Topsoil (above Liner) 3.3.4 Cap Material (under Liner) 3 .3 .5 Stockpile of Cleared Soil 3.5 . Other Cost Items 3 .5 .1 Fuel Savings 3.5 .2 Liquid BCD Savings 3.5 .3 Potential Change Orders 3.5.3.1 Re-Handling Stockpile 3.5.3.2 Additional Erosion Control Measures 3.5.3.3 Moisture of Feed Soils 3.5.3.4 Organic Fouling of TIU 4.0 ACTION ITEMS MONTHLY PROGRESS MEETING -JANUARY 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A January 9, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of December minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate • Results of PDT test 3. Work to be performed in the next 30 days • Production goals • Reprocessing of batches • Delineation of south landfill sides and bottom 4. Review of change orders (outstanding/anticipating) • Change Order #6 • Shaw change order notifications 5. Review status of permits applications, project drawings and submittals • TSCA • Erosion controls inspection • Non-discharge treatment system status/sampling results • Shaw NC GC License 6. Review construction schedule compliance • Phase I target completion date • Phase II target completion date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Additional sediment sampling • Sampling of landfill cover materials • Extent of landfill • Estimated soil excavation volume • DRE #3 air monitoring results • Erosion controls • Results of the Performance Demonstration Test 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • East extension of landfill • Handling of residuals on Pad 1 • Production target chart and rates • Liquidated damages • Proactive system control MONTHLY PROGRESS MEETING MINUTES JANUARY 9, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR Mike Kelly -NCDENR Pat Barnes -Community Technical advisor Terry Lyons -US EPA Gary Duke -Shaw Jim Cloonan -Earth Tech John Funk -Earth Tech Dennis Jones -Earth Tech Dave Ditcher -Shaw Bill Gallagher -Shaw 1.0 Minutes of the December 12, 2002 monthly progress meeting were accepted without comment. 2.0 PROJECT STATUS • 3535 tons of soil were processed in December with 1721 tons accepted .. • Target completion date is significantly behind due to poor production rate in November and December 2002 • Average PCB concentration of accepted soil is 0.111 ppm • Results ofNIOSH stack test, 15,000 -20,000 ton range, were non-detect. 3.0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Continue to operate BCD unit with target production goal of 12-13 tons per hour if soils are wet. • Two, two-day outages are planned for the month to perform system maintenance. • Target production rate is 6,000 tons for the month. • Earth Tech determined northern end of the landfill, and staked sample points for southern extent. • Shaw plans to excavate to the bottom liner in the southern end of the landfill this month. 4.0 REVIEW OF CHANGE ORDERS • DENR to approve Change Order No. 6 after the Performance Demonstration Test. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • Status ofTSCA permit is on schedule with performance demonstration test (PDT) being conducted this week. No problems reported by EQM with sampling. EPA will extend the January 31, 2003 permit deadline and grant additional extensions as data from the PDT is submitted to EPA. Shaw provided a schedule of TSCA permit process. • State inspected erosion and sediment controls measures and found no problems. • Results of gel-floe addition to the storm water treatment system indicated that PCB concentration in storm water discharge to the unlined pond and spray irrigation system is 10 ppb. Shaw to contact gel-floe vender to determine if performance could be improved. Shaw will also floe the lined pond to lower turbidity into the system once the pond level drops below 50,000 gallons. • Shaw to check status of their NC GC license, contractor license board scheduled to meet this month. 6.0 REVIEW OF SCHEDULE COMPLIANCE • Phase I target completion date is February 3, 2003. • Final contract completion date will be determined after approval of Change Order No. 6. Anticipate developing final schedule and completion date for February meeting. • Based on current product rate completion is projected for October 2003 which is behind planned date of July 2003. 7.0 PERCENT COMPLETE: 96% Phase I, 51.61 % of Change Order No. 5. 8.0 CONSTRUCTION/COORDINATION ISSUES • Earth Tech will collect soil samples from cap soil stock pile (Mt. Tilley) week of January 13, 2003. • Earth Tech, DENR, and community technical advisor plan to collect off-site sediment samples January 6, 2003. • Northern extent of landfill has been determined through construction of test pits -no change to original northeast comer point. Southeast comer point is estimated to be 20 feet east of as-built location. • Estimated total of soil to be treated is 72,000 tons. • Shaw to clear Pad 1 of oversized material and black cleaning residuals. • Preliminary results to of PDT due to Shaw week of January 22, 2003, dioxins two weeks later. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • The community technical advisor indicated that community concerns had been addressed and did not identify any additional concerns. • East extent of the landfill has been estimated and staked. • Shaw was advised that liquidated damages were included in contract provisions. • Earth Tech and DENR requested that Shaw develop more of a proactive approach to system maintenance, and develop a more comprehensive preventive maintenance program. 10.0 NEXT SCHEDULED MEETING: February 5, 2003 at 1100 hrs at the project site. 10. Schedule project monthly progress meeting date, time, and place 2 MONTHLY PROGRESS MEETING -FEBRUARY 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A February 5, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of January minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate (tph and tpd) • Completion of PDT • Cleaning of Pad 1 3. Work to be performed in the next 30 days • Production goals • Handling of Mt. Tilley • Delineation of south landfill sides and bottom • Backfilling of treated soils 4. Review of change orders (outstanding/anticipating) • Change Order #6 • Contract completion date 5. Review status of permits applications, project drawings and submittals • TSCA • Erosion controls inspection • Non-discharge treatment system status/sampling results • Shaw NC GC License 6. Review construction schedule compliance 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Additional sediment sampling • Sampling of landfill cover materials • Estimated soil excavation volume • Air monitoring results on an annual basis • TSCA operating extensions • Analytical results from the Performance Demonstration Test • Fuel addition to feed soils 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Jim Warren letter • Production target chart and rates • Cyclone efficiency 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES FEBRUARY 5, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR Mike Kelly -NCDENR Pat Barnes -Community Technical Advisor Dave Ditcher -Shaw Gary Duke -Shaw Jim Cloonan -Earth Tech John Funk -Earth Tech Dennis Jones -Earth Tech Bill Gallagher -Shaw 1.0 Minutes of the January 3, 2002 monthly progress meeting were accepted with the following comment: Terry Lyons, US EPA stated his opinion that the black residue on Pad 1 consisted primarily of clay material mixed with black residue that resembled carbon black. 2.0 PROJECT STATUS • 6,936 tons of soil were processed in January with all batches meeting the acceptance criteria. • Target completion date for soil treatment has improved due to increased production rate in January to August 6, 2003. Weather delays are likely to extend date for substantial completion to October 3rd. • Average PCB concentration of accepted soil is 0.127 ppm • An addition of a diaphragm pump on the product cooler has resulted in increased production rate. • The performance demonstration test (PDT) was conducted January 7 -9, 2003. Shaw will submit the laboratory data to EPA according to the schedule outlined in the demonstration permit. • Shaw will advise NCDENR regarding TSCA storage and labeling requirements for the drums on Pad 1. Twenty-seven drums are currently stored on the Pad with a total of 30 to 35 required to contain the entire black residue. • Earth Tech will request that Shaw provide a change order (CO #7) for a test to provide information on the treatment of clay soils from cap stockpile area (Mt. Tilley). 3.0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • February goal is 7,300 tons with net target production rate of 306 tons per hour. • Shaw plans to excavate to the bottom liner in the southern end of the landfill this month and conduct testing of clay liner. Shaw will scrape away the sand and approximately one inch of clay, decon the bucket, and then excavate the next five inches of clay. • Earth Tech will provide a specification for placing stockpile and cap material back into the landfill for soils that exhibit a PCB concentration of <1 ppm. • Backfilling of landfill may start by the end of the month. 4.0 REVIEW OF CHANGE ORDERS • Shaw to prepare Change Order #7 for a test of the thermal treatment of clay material. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • Status ofTSCA permit is on schedule with data submitted to EPA as outlined in demonstration permit. • Shaw rebuilt the sedimentation basin weirs with new #57 stone per recommendation of NC inspector. • The addition of gel-floe to the storm water treatment system appears to give good results for removal of suspended particulates and associated PCBs. • Shaw submitted application for NC GC contractor's license in January. The board asked Show to provide additional information on bonding. The board will review again in February. 6.0 REVIEW OF SCHEDULE COMPLIANCE • Thermal treatment completion originally set for July 2003 but weather delays will likely extend the project completion date into the first week of August. 7.0 PERCENT COMPLETE: 60 .33%. 8.0 CONSTRUCTION/COORDINATION ISSUES • Earth Tech will collect soil samples from cap below the FML at sample points LF-13, 14 and 15. • Earth Tech, DENR, and community technical advisor plan to collect additional off- site sediment samples. • Estimated total of soil to be treated is 72,000 tons. • Shaw to clear Pad 1 of oversized material and black cleaning residuals. • Addition of fuel oil to the product feed seems to minimize the formation of black residue in the system, although Shaw feels this may also be due to absence of "bad" feed materials. • Liquid PCB quantity is lower than expected even with the addition of the fuel oil. Shaw will present tracking of condensate production at next meeting. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • The community technical advisor indicated that community strongly discourages trucking landfill material off-site for disposal. • Soil samples taken at the site in 1997 and stored at EcoFlo in Greensboro were shipped back to the site for treatment. The shipment consisted of one 85-gallon over-pack drum. 10.0 NEXT SCHEDULED MEETING: March 5, 2003at11:00 at the project site. 2 MONTHLY PROGRESS MEETING -MARCH 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A March 5, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of February minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate (tph and tpd) • Cleaning of Pad 1 • Erosion control measures 3. Work to be performed in the next 30 days • Handling of Mt. Tilley and cover soils • Delineation of south landfill sides and bottom • Backfilling of treated soils 4. Review of change orders (outstanding/anticipating) • Change Order #7 • Contract completion date 5. Review status of permits applications, project drawings and submittals • TSCA • Erosion controls inspection • Non-discharge treatment system status/sampling results • Shaw NC GC License 6. Review construction schedule compliance 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Additional sediment sampling • Sampling of landfill cover materials and Mt. Tilley • Handling of Mt. Tilley soils • Estimated soil excavation volume • Updated air monitoring results • TSCA operating extensions • Dioxin removal efficiency • Fuel addition to feed soils • Adjustment for fuel prices 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Jim Warren letter • Request to suspend withholding of retainage 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES MARCH 5, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR Mike Kelly -NCDENR Pat Barnes -Community Technical Advisor Dave Ditcher -Shaw Gary Duke -Shaw Jim Cloonan -Earth Tech John Funk-Earth Tech Rob Holland -Earth Tech Bill Gallagher -Shaw 1.0 Minutes of the February 5, 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 6,468.57 tons of soil passed in February with average PCB concentration of 0.15 ppm. Four days were lost due to CP&L power outages. • Production rate is 12-13 tons per hour (232 tons per day) gross production versus Shaw's target of 306 tons per day. • Pad No. 1 was has been cleaned of black residue and the residue placed in approximately 30 drums. • Shaw to complete seeding of north side of the site area by next Wednesday (March li11). 3 .0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Shaw will conduct pilot test of the clay soils in the stockpile (Mt. Tilley) tomorrow (March 6th). Earth Tech will monitor the test. • Shaw has removed all waste material and first layer of clay from the southern end of the landfill, and have exposed the clean clay bottom liner. Test results indicate that the PCB concentration in the clay liner is below 1 ppm criteria. • A sand seam at the southern end of the landfill near the top of the fill was found to contain PCBs at a concentration of 19 ppm. Shaw will remove that material and conduct testing of sand found in other areas. • Backfill of the landfill will commence within the next week. 4.0 REVIEW OF CHANGE ORDERS • Change Order #7 for a test of the thermal treatment of clay material was signed and test will be conducted on March 6th• • Shaw to compile running total of lost days due to weather (December ice storm) and power outages and present the totals at future monthly meetings. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • Status ofTSCA permit is on schedule with data submitted to EPA as outlined in demonstration permit. • State has conducted no erosion and sediment control inspection for the month of February. • The addition of gel-floe to the storm water treatment system appears to give good results for removal of suspended particulates and associated PCBs. • Shaw submitted application for NC general contractor's license in January but bonding is still an issue -an original bond is required, not a faxed copy. Shaw to resolve GC license this month. 6.0 REVIEW OF SCHEDULE COMPLIANCE • Thermal treatment completion originally set for July 2003 but weather delays will likely extend the completion of thermal treatment into the first week of August. 7.0 PERCENT COMPLETE: 64.47%. 8.0 CONSTRUCTION/COORDINATION ISSUES • Earth Tech and community technical advisor collected off-site sediment samples yesterday (March 4th). Samples will be sent to the state laboratory for analysis. • Shaw to setup clean soil stockpile area in the vicinity of the east air monitoring station. County permission may be required. • Cover material currently on top of landfill in grids 9 -12 will be placed back into the landfill with the treated waste material. • Based on analysis of feed soils, dioxin removal exceeds 98%. • MSR is adding diesel fuel to the feed soils at a rate of 1 gallon/ton. Shaw/MSR to track fuel addition and resent totals at the monthly progress meetings. • Liquid PCB collected to date is only 480 gallons, although some may be accumulated in the oil/water separator . Shaw to review and advise on status of liquids in the system. • Shaw to call Terry Lyons of EPA concerning quantity of oil required to conduct bench-scale test on liquid BCD. • Shaw to make repairs to flat scale. • Easement may be blocked temporarily due to need for stockpiling treated soil. • M. Kelly to give list of fuel blenders in North Carolina to Shaw for potential handling of collected oil. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • The community technical advisor indicated that community is opposed to trucking landfill material off-site for disposal. • Shaw to prepare design of potential filter berms for the control of off-site sediment. • Earth Tech found a truck gas tank containing a small quantity of fuel next to the inert debris dumpster. Shaw will again inform their workers of proper waste disposal procedures at site. 10.0 NEXT SCHEDULED MEETING: April 9, 2003 at 11 :00 at the project site. 2 MONTHLY PROGRESS MEETING -APRIL 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A April 9, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of March minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate (tph and tpd) • Repairs and maintenance to ITU • Delineation of PCBs along south side of landfill • Backfilling of treated soils • Erosion control measures • Creation of soil stockpile near air monitoring station #2 3. Work to be performed in the next 30 days • Handling of Mt. Tilley and cover soils • Delineation oflandfill sides and bottom 4. Review of change orders ( outstanding/anticipating) • Change Order #8 (fuel allowance) • Fuel usage and cost for the previous month • Contract completion date 5. Review status of permits applications, project drawings and submittals • TSCA • Erosion controls inspection • Non-discharge treatment system status/sampling results 6. Review construction schedule compliance • Contract delays for the previous month and total to date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Additional sediment sampling • Handling of Mt. Tilley soils • Estimated soil excavation volume • Updated air monitoring results • TSCA operating extensions (EPA letter of March 30th) • Meeting with Craig Brown of EPA regarding TSCA issues • Fuel addition to feed soils monthly and totals to date • PCB oil collected to date • EPA payment for EQM analytical testing 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Concerns of the owner and requested action items for month 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES APRIL 9, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR Mike Kelly -NCDENR Pat Barnes -Community Technical Advisor Dave Ditcher -Shaw Gary Duke -Shaw Jim Cloonan -Earth Tech John Funk-Earth Tech Rob Holland -Earth Tech Bill Gallagher -Shaw 1.0 Minutes of the March 5, 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 4,325 tons of soil passed acceptance criteria in March with an average PCB concentration of 0.27 ppm. Average PCB concentration to date of the treated soil is 0.15 ppm with approximately 50% of the landfill processed. • Production rate is 13-14 tons per hour (220 tons per day) gross production versus Shaw's target of 306 tons per day. Shaw's monthly target is 7,800 tons. • System was down 10 to 11 days due to hot tube removal and other repairs. • Sand seam was removed from the south side of the landfill. Approximately 20 tons required thermal processing; the remainder of the sand was clean. • Results of the analysis of the clay landfill bottom liner were below verification criteria, and backfilling of the landfill with treated soil was begun. • A clean soil stockpile area was created in the vicinity of the east air monitoring station (#2) to stockpile clean soil for the final cover. 3.0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Earth Tech will complete seeding and applying jute netting to the north soil stockpile (Mt. Tilley). • Earth Tech will collect soil samples on the north end of the landfill cover and in the area designed as the clean soil stockpile area. 4.0 REVIEW OF CHANGE ORDERS • Change Order #8 for fuel adjustment through February was approved as a zero sum change order to the Contract. • Fuel usage in March was 73,000 gallons with the adjustment due to Shaw totaling approximately $33,000. • Shaw is to provide a copy of MSR's subcontract for fuel purchase to Earth Tech. • Estimated extension to the contract time due to December 2002 ice storm and power outages is 12.6 days. Substantial completion with extension is October 24, 2003 . 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITIALS • EPA letter of March 30, 2003 approved interim operations pending review of Final Report from MSR. • Shaw to provide storm water treatment system effluent sampling results to Earth Tech. Effluent sampled after every 1 million gallons discharged. 6.0 REVIEW OF SCHEDULE COMPLIANCE • With contract time extension of 12 .6 days, the completion of thermal treatment is scheduled for August 28 , 2003 . This schedule is dependent upon Shaw processing 7,800 tons per month for the remainder of the project. Shaw will update the schedule each month based on actual production. 7.0 PERCENT COMPLETE: 68.49%. 8.0 CONSTRUCTION/COORDINATION ISSUES • Earth Tech presented results of off-site sediment samples collected in March. • Construction of off-sediment filter berms was completed, and the community technical advisor stated that he was pleased with the berms and other erosion and sediment control measures enacted on-site. • Based on the amount of landfill area uncovered to date, there is no change in the estimated 72,000 tons of soil to be treated. • Perimeter air monitoring results for March and for project to date were below North Carolina toxic pollutant guidelines. • To date, 2,123 gallons of fuel have been added to the feed soils. Fuel addition stopped recently since soil is being removed from the upper portions of the landfill. The "black snot" problem apparently occurs with soil at the bottom portion of the landfill. • EP A's budget passed but funds are frozen due to war in Iraq. EPA to reimburse DENR directly for approximately $52,000 for performance demonstration test by EQM when funds are released. • Thermal treatment test of clay soil was completed. Soil was processed at a rate of 10 tons per hour. High moisture content in clay soil, fines carry-over, and greater potential for failed batches would increase the cost for treating clay soils to at least $234 per ton. • Dioxins and furans TEQ in feed soils at 200 ppt in March. System has demonstrated 98% removal of those compounds so treated soils would be well below the treatment criteria of 200 ppt TEQ. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • No comments from the community technical advisor, Owner or Designer 10.0 NEXT SCHEDULED MEETING: May 7, 2003 at 11 :00 at the project site. 2 MONTHLY PROGRESS MEETING -MAY 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A May 7, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of April minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate (tph and tpd) • System maintenance/repairs (hot tube, condensate system, etc.) • Erosion control measures 3. Work to be performed in the next 30 days • Excavation of soils to be treated • Backfilling of treated soils • Maintenance of TIU 4. Review of change orders (outstanding/anticipating) • Pending fuel change order 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results 6. Review construction schedule compliance • Revised completion date vs. contract date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Effect of modifications to TIU • Jute cover on Mt. Tilley • Estimated soil excavation volume • Updated air monitoring results • PCB oil collected to date • NC supply of fuel for TIU • Water treatment system performance • Landfill bottom confirmation sampling • Landfill cover sampling results • Meeting with EPA on April 15th • EPA payment of EQM sampling costs 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Technical issues for CAB meeting 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES May 7, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Jim Cloonan -Earth Tech Mike Kelly -NCDENR Pat Barnes -Community Technical Advisor Dave Ditcher -Shaw Gary Duke -Shaw John Funk-Earth Tech Rob Holland -Earth Tech Bill Gallagher -Shaw 1.0 Minutes of the April 9, 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 6,819 tons of soil passed acceptance criteria in April with an average PCB concentration of 0.137 ppm. Average PCB concentration to date of the treated soil is 0.15 ppm with approximately 52% of the landfill processed. • Production rate is 11-12 tons per hour (237 tons per day) gross production versus Shaw's target of 306 tons per day. Shaw's monthly target is 7,800 tons. • Three batches failed acceptance criteria, and will be reprocessed. • No adverse effects in system performance were observed from the hot tube removal performed in March. • Carbon in the condensate stream was changed twice during the month of March. • Erosion and sediment control issues were identified during the month consisting of adding silt fence of the south side of the site and cleaning out several silt fences and check dams. • Debris, liner material, and other miscellaneous materials not suitable for thermal processing have been placed into 40-yard dumpster containers for transportation and disposal at Waste Management facility in Alabama. 3 .0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Earth Tech will complete seeding and applying jute netting to the north soil stockpile (Mt. Tilley). • Earth Tech will collect soil samples on the north end of the landfill cover and in the area designed as the clean soil stockpile area. • Shaw will remove the remainder of the landfill cap in two stages over the next several months. 4.0 REVIEW OF CHANGE ORDERS • Shaw to prepare a change order for State purchase of fuel. • Use of high sulfur fuel is in compliance with system air permit. • Estimated extension to the contract time due to December 2002 ice storm and power outages is 12.6 days. Substantial completion with extension is October 24, 2003. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • Shaw to provide storm water treatment system effluent sampling results to Earth Tech. Effluent sampled after every 1 million gallons discharged. 6.0 REVIEW OF SCHEDULE COMPLIANCE • With contract time extension of 12.6 days, the completion of thermal treatment is scheduled for August 28, 2003. This schedule is dependent upon Shaw processing 7,800 tons per month for the remainder of the project. Shaw will update the schedule each month based on actual production. 7.0 PERCENT COMPLETE: 73 .02%. 8.0 CONSTRUCTION/COORDINATION ISSUES • Based on the amount of landfill area uncovered to date, there is no change in the estimated 72,000 tons of soil to be treated. • Perimeter air monitoring results for April were above North Carolina toxic pollutant guidelines in North and East monitoring stations. Average for the site was below the guidelines. • To date, 1,500 gallons of PCB liquids have been collected in the tanks. No fuel was added to the feed soils during March. • State will supply fuel for the project after approval of deductive change order prepared by Shaw. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • No comments from the community technical advisor, Owner or Designer 10.0 NEXT SCHEDULED MEETING: June 11, 2003at11:00 at the project site. 2 MONTHLY PROGRESS MEETING -JUNE 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A June 11, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of May minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate (tph and tpd) • System maintenance/repairs • Erosion control measures 3. Work to be performed in the next 30 days • Excavation of soils to be treated • Backfilling of treated soils • Stripping of landfill cap • Maintenance of TIU 4. Review of change orders (outstanding/anticipating) • Erosion & Sediment control change order 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results • Air permit evaluation Shaw/MSR action items 6. Review construction schedule compliance • Revised completion date vs. contract date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Estimated soil excavation volume • Updated air monitoring results • PCB oil collected to date • NC supply of fuel for TIU • Water treatment system performance • Landfill bottom confirmation sampling • EPA payment of EQM sampling costs 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Technical issues for CAB meeting 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES JUNE 11, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Jim Cloonan -Earth Tech Mike Kelly -NCDENR Pat Barnes -Community Technical Advisor Dave Ditcher -Shaw Gary Duke -Shaw Herman Gnuechtel -MSR John Funk -Earth Tech Rob Holland -Earth Tech Bill Gallagher -Shaw Pat Backus -NCDENR 1.0 Minutes of the May 7, 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 5,400 tons of soil passed the acceptance criteria in May with an average PCB concentration of 0.151 ppm. Average PCB concentration to date of the treated soil is 0.149 ppm with approximately 57% of the landfill processed. • Production rate is 11-12 tons per hour (237 tons per day) gross production. • 493 tons of soil failed acceptance criteria and will be reprocessed. • May production was down in May due to repairs to trunion bearing, oil/water separator, kiln seal, and other system components. • Erosion and sediment control issues were identified during the month consisting of cleaning out several silt fences and check dams. • Two loads of diesel fuel were delivered by State in May. Remainder of fuel for project to be delivered by State. • TCDD TEQ in untreated soil sample collected in May was 403 ppt. Based on removal percentages in performance demonstration test, treated soils will be well below target of 200 ppt. 3 .0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Earth Tech will complete seeding and applying jute netting to the north soil stockpile (Mt. Tilley). • Earth Tech will collect soil samples on the north end of the landfill cover below the liner. • Shaw will remove the remainder of the landfill cap in two stages starting the week of July 7th_ • Shaw intends to use the cleared bottom of landfill for soil drying so they do not anticipate clearing move bottom liner grids or backfilling additional treated soil in June. 4.0 REVIEW OF CHANGE ORDERS • Change Order No. 9 -State supply of fuel approved by SCO . • Change Order No. 10 -Fuel charges submitted by Shaw, approved except for signature by SCO • Estimated extension to the contract time due to December 2002 ice storm and power outages is 14 days. Substantial completion with extension is October 6, 2003. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITT ALS • 375,000 gallons of storm water were treated in May. Effluent will be sampled after every 1 million gallons discharged. 6.0 REVIEW OF SCHEDULE COMPLIANCE • The completion of thermal treatment is scheduled for September 22, 2003. Shaw will update the schedule each month based on actual production. 7.0 PERCENT COMPLETE: 78.69%. 8.0 CONSTRUCTION/COORDINATION ISSUES • Based on the amount of landfill area uncovered to date, there is no change in the estimated 72,000 tons of soil to be treated. • Perimeter air monitoring results for April were above North Carolina toxic pollutant guideline for PCBs at North and East monitoring stations. Average for the site remains below the guideline. • To date, 2,000 gallons of PCB liquids have been collected in the tanks. No fuel was added to the feed soils during May. • Perimeter air monitoring will be conducted bi-weekly to ensure there are enough samples remaining in the budget to allow sampling after completion of thermal treatment and covering of the treated soils. • Shaw has encountered kiln dust in the landfill. Material so far has not presented a processing problem. Shaw to monitor alkalinity of condensate water. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • No comments from the community technical advisor, Owner or Designer • EPA refund of approximately $52,000 for performance demonstration analytical testing has not been received. Shaw will follow up with Terry Lyons of EPA. 10.0 NEXT SCHEDULED MEETING: July 9, 2003 at 11 :00 at the project site. 2 MONTHLY PROGRESS MEETING -JULY 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A July 9, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of June minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Processing rate (tph and tpd) • System maintenance/repairs • Erosion control measures • Sampling of north end of cap 3. Work to be performed in the next 30 days • Excavation of soils to be treated • Backfilling of treated soils • Stripping of landfill cap • Maintenance of TIU • Excavation and treatment of clay soils 4. Review of change orders ( outstanding/anticipating) • Erosion & Sediment control change order • Change Order Nos. 10 (Fuel) and 11 (Clay Treatment) 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results 6. Review construction schedule compliance • Estimated completion date vs. contract date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Updated air monitoring results • Duplicate sample of Batch #159 • PCB oil collected to date • Handling of non-aqueous condensate • Water treatment system performance • Landfill bottom confirmation sampling • Additional sampling of Mt. Tilley • EPA payment of EQM sampling costs 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Technical issues for CAB meeting 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES JULY 9, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Jim Cloonan -Earth Tech Mike Kelly -NCDENR Pat Barnes -Community Technical Advisor Dave Ditcher -Shaw Gary Duke -Shaw John Funk -Earth Tech Rob Holland -Earth Tech Bill Gallagher -Shaw Pat Backus -NCDENR 1.0 Minutes of the June 11, 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 8,179 tons of soil passed the acceptance criteria in June with an average PCB concentration of 0.125 ppm. Average PCB concentration to date of the treated soil is 0.144 ppm with approximately 75% of the landfill processed. • Production rate is 11-12 tons per hour (272 tons per day) gross production. • Two batches, 989 tons, of soil failed acceptance criteria and will be reprocessed. • During June, unit was down for five days for repairs to the trunion bearings, centrifuge, pug mill, and condensate system. • Kimberly Summers was on-site June 27th to inspect erosion and sediment control measures with no new issues being identified. • Analysis of water samples from north and south sed basins showed 1 ppb and ND. 3 .0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Shaw will complete stripping the remaining cap, soils to be handled based on Earth Tech sampling results. • Shaw will resume backfilling the landfill within two weeks as bottom grids are cleared and sampled. • No major maintenance shut-downs are planned for the month. • Earth Tech to complete sampling of the Tilley stockpile beginning of the month, and Shaw intends to treat clay soils from Tilley stockpile at the end of the month. 4.0 REVIEW OF CHANGE ORDERS • Change Order Nos. 10 (Fuel), 11 (Closeout of Phase I), and 12 (Clay Treatment) are fully executed. • Shaw to provide backup information on erosion and sediment control change order. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • E&S measures inspected on June 2i\ no issues identified. • Quench water sampled, results were 43 ppb. 6.0 REVIEW OF SCHEDULE COMPLIANCE • The completion of thermal treatment is scheduled for September 23, 2003. Substantial completion is scheduled for November 18, 2003. Shaw will update the schedule each month based on actual production. Revised contract time is September 26, 2003. • Liquid PCBs will be disposed one week after completion of soil thermal treatment. 7.0 PERCENT COMPLETE: 83.6%. 8.0 CONSTRUCTION/COORDINATION ISSUES • Based on the amount of landfill area uncovered to date, there is no change in the estimated 72,000 tons of soil to be treated. • Perimeter air monitoring results for May were above North Carolina toxic pollutant guideline for PCBs at site monitoring stations. • To date, 2,800 gallons of PCB liquids have been collected in the tanks, anticipate 3,000 to 4,000 gallons by project end. No fuel was added to the feed soils during June. • Perimeter air monitoring in July will include staging two off-site samplers, the spare at the Kearney residence and the north station sampler at the Davis residence. • Shaw is still waiting for EPA's contribution for the EQM sampling, will credit DENR approximately $30,000 in subsequent application for payment following receipt. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • No comments from the community technical advisor, Owner or Designer 10.0 NEXT SCHEDULED MEETING: August 6, 2003 at 11 :00 at the project site. 2 MONTHLY PROGRESS MEETING -AUGUST 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A August 6, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of July minutes 2. Work performed in the last 30 days. • Soil treated and concentration • Soil processing rate ( tph and tpd) • Clay processing results • System maintenance/repairs • Erosion control measures • Handling of Mt. Tilley 3. Work to be performed in the next 30 days • Final excavation of soils to be treated • Backfilling of treated soils • Handling of Mt. Tilley • Handling of non-aqueous condensate • Confirmation sampling of landfill bottom 4. Review of change orders (outstanding/anticipating) • Erosion & Sediment Control change order 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results 6. Review construction schedule compliance • Estimated completion date vs. contract date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Updated air monitoring results • PCB oil collected to date • Handling of screened rocks • Confirmation sampling update • Mt. Tilley sampling results • EPA payment of EQM sampling costs • Site restoration (cover materials, grading, improvements) 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Technical issues for CAB meeting 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES August 6, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR Mike Kelly -NCDENR Pat Barnes -Community Technical Advisor Dave Ditcher -Shaw Gary Duke -Shaw Jim Cloonan -Earth Tech John Funk -Earth Tech Herman Gnuechtel -MSR Bill Gallagher -Shaw 1.0 Minutes of the July 9, 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 6,363 tons of soil passed the acceptance criteria in July with an average PCB concentration of 0.101 ppm. 372 tons of clay material from Mt. Tilley was treated with average PCB concentration of BQL (Below Method Quantitation Limit). Average PCB concentration to date of the treated soil is 0.140 ppm excluding the 372 tons of clay. • Average production rate is 13 tons per hour (225 tons per day), including clay. • During June/July, the unit was down for five days for repairs to the trunion bearings, centrifuge, pug mill, and condensate system -total down time 201 hrs. • Kimberly Summers was on-site during the week of July 4th to inspect erosion and sediment control measures with no new issues being identified. • Mt. Tilley was excavated a further 4-foot depth with 372 tons thermally treated and the remainder placed in the landfill. Approximately five feet of Mt. Tilley remain for disposition. 3.0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Shaw will excavate the remaining soils to the bottom of the landfill. • Shaw will backfill the landfill as bottom grids are cleared and sampled. • No major maintenance shut-downs are planned for the month. • Earth Tech to complete sampling of the Mt. Tilley stockpile. 4.0 REVIEW OF CHANGE ORDERS • Shaw to provide backup information on erosion and sediment control change order. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • E&S measures inspected on during the week of July 4th with no issues identified. 6.0 REVIEW OF SCHEDULE COMPLIANCE • The completion of thermal treatment is scheduled for September 22, 2003, including that of the dewatered sludge from the lined pond. Substantial completion is scheduled for November 18, 2003. Shaw will update the schedule each month based on actual production. Revised contract time is September 26, 2003. • Liquid PCBs will be disposed one week after completion of soil thermal treatment. 1 7.0 PERCENT COMPLETE: 87.66%. 8.0 CONSTRUCTION/COORDINATION ISSUES • Based on the amount of landfill area uncovered to date, there is no change in the estimated 72,000 tons of soil to be treated. • Perimeter air monitoring results for off-site location will be available in August. • To date, 2,800 gallons of PCB liquids have been collected in the tanks, anticipate 3,000 to 4,000 gallons by project end. No fuel was added to the feed soils during July. • Shaw to provide plan for disposal of incompatible material (rocks or debris) that cannot be thermally processed. • Shaw is still waiting for EPA's contribution for the EQM sampling, will credit DENR approximately $30,000 in subsequent application for payment following receipt. • Shaw to provide site restoration plan and final site sampling plan. • DENR to prepare generator form for off-site disposal of condensate. Shaw to solicit firm quotes based on analyses. • Earth Tech will verify the estimated quantity of imported fill necessary for final cover of the treated soils. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • The Community Advisor asked that the debris berms outside the fence line be investigated. • The November progress meeting will include an open house for the community, tentatively set for November 8th• 10.0 NEXT SCHEDULED MEETING: September 10, 2003 at 11:00 at the project site. 2 MONTHLY PROGRESS MEETING -SEPTEMBER 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A September 10, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of August minutes 2. Work performed in the last 30 days. • Soil treated, concentration and processing rate • System maintenance/repairs • Erosion control measures • EPA approval on handling of Mt. Tilley 3. Work to be performed in the next 30 days • Final excavation of soils to be treated • Backfilling of treated soils • Handling of Mt. Tilley • Handling of non-aqueous condensate • Confirmation sampling of landfill bottom • Placement of cover material • Initial decontamination 4. Review of change orders (outstanding/anticipating) • Erosion & Sediment Control change order • CO #14 (Imported Cover Material) 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results 6. Review construction schedule compliance • Estimated completion date vs. contract date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Updated air monitoring results • PCB oil collected to date • Handling of screened rocks • · Confirmation sampling update • Decontamination approach • Soil/sediment sampling outside of landfill • Site restoration (cover materials, grading, improvements) 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Technical issues for CAB meeting 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES September 10, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR John Funk -Earth Tech Pat Barnes -Community Technical Advisor Bill Gallagher -Shaw Jim Cloonan -Earth Tech Jerry Winberry-Earth Tech Doug Edwards -SCO Gary Duke -Shaw 1.0 Minutes of the August 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 7,783 tons of soil passed the acceptance criteria in August with an average PCB concentration of 96 ppb. 68 ,246 tons of material have been treated to date at an average daily rate of 251 tons per day. Average PCB concentration to date of the treated soil is 0.135 ppm excluding the 372 tons of clay treated in July. • Average production rate is 251 tons per day. • During August, the unit was down for 167 hours for repairs to the pug mill, kiln seal, recirculation fan, and conveyor belt. • No E&S inspection was performed by Kimberly Summers during August. Last inspection was during the week of July 4th• No new issues were identified during that inspection. • On August 29, 2003 written approval was received from EPA region IV to place material containing <10 ppm PCBs in the landfill at a depth of 15 feet below final grade. • Onyx completed sludge removal and dewatering from the lined pond (approximately 60 cy were removed). 3.0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Shaw will excavate the remaining soils to the bottom of the landfill. • Shaw will backfill the landfill as bottom grids are cleared and sampled. • At completion of landfill excavation, Shaw to excavate openings in the landfill bottom liner using a trackhoe. Openings to be filled with treated soil. • Shaw to move a four-foot lift from MT. Tilley into the landfill. • No major maintenance shutdowns are planned for the month. • Earth Tech to complete sampling of the Mt. Tilley stockpile after four-foot lift is removed. 4.0 REVIEW OF CHANGE ORDERS • Earth Tech received backup information on erosion and sediment control change order and will review within the next two weeks. • Total landfill material to be treated will exceed 72,000 tons, the State to prepare change orders based on bid price unit rate for additional soil to be treated (approximately 7,000 tons). • Shaw to provide moisture change order prior to next monthly progress meeting. 5 .0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • No E&S inspection in August. • Non-discharge system sampling results 6.3 ppb. 6.0 REVIEW OF SCHEDULE COMPLIANCE • The completion of thermal treatment is scheduled for October 24, 2003 based on additional soil in the landfill. Substantial completion is scheduled for December 18, 2003. Shaw will update the schedule each month based on actual production. • Liquid PCBs will be disposed one week after completion of soil thermal treatment. Shaw to record condensate oil volume prior to MSR decon. 7.0 PERCENT COMPLETE: 91.926% based on 72,000 tons. 8.0 CONSTRUCTION/COORDINATION ISSUES • Perimeter air monitoring results indicate levels decreasing as soil is removed from the landfill. • To date, 2,90 gallons of PCB liquids have been collected in the tanks; anticipate 3,000 to 4,000 gallons by project end. No fuel was added to the feed soils during August. • Rocks to be crushed prior to thermal treatment. • Shaw is still waiting for EPA' s contribution for the EQM sampling and will credit DENR approximately $30,000 in subsequent application for payment following receipt. • Shaw to provide site restoration plan and final site sampling plan, and sealed as-built drawings at project completion. • DENR to prepare generator form for off-site disposal of condensate. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • It was requested that the Community Advisor solicit comments from the community on contents of the final report. 10.0 NEXT SCHEDULED MEETING: October 8, 2003 at 11 :00 at the project site. 2 AGENDA WARREN COUNTY PROJECT UPDATE MEETING NCDENR TRAILER OCTOBER 7, 2003 1.0 THERMAL TREATMENT 1.1 Condensate Volume (Current/Projected) 1.2 Liquid Enhanced Oxidation Quotes 1.3 Documentation of BCD Treatment per Patent 1.4 Running Average Concentration 1.5 Repairs to Pug Mill/Product Cooler 2.0 SCHEDULE 2.1 Total Soil Volume Estimate 2.2 Soils Passed to Date 2.3 Thermal Treatment 2.4 Demobilization (12/03) 3.0 MT. TILLEY 3 .1 Scheduling of Cutting Mt. Tilley 3 .2 Placement in Landfill 3.3 Latest Sampling Results 4.0 SITE RESTORATION 4.1 Cover Material Depth/Volume 4.2 Schedule for Importing Fill 4.3 Final Site Grading/Conditions 4.4 Dec on of Pads and Pole Barn 4.5 Pad Wipe Testing 4.6 Sampling/Disposal of Unlined Pond Sediments 5 .0 GENERAL ISSUES 5 .1 Review of Progress Meeting Agenda 5.2 Updated Air Monitoring Results (through Week 36) 5.3 Preparation for CAB Meeting 5 .4 EPA Analytical Funding 5.5 Site Sampling Plan (Rev. 4) 5.6 Status of Change Orders 6.0 ACTION ITEMS MONTHLY PROGRESS MEETING -OCTOBER 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A October 8, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of September minutes 2. Work performed in the last 30 days. • Soil treated, concentration and processing rate • System maintenance/repairs • Sediment removal from drainage areas • EPA approval on handling of Mt. Tilley 3. Work to be performed in the next 30 days • Final excavation of soils to be treated • Backfilling of treated soils • Handling of Mt. Tilley • Handling of non-aqueous condensate • Confirmation sampling of landfill bottom • Placement of cover material • Initial equipment/pad decontamination 4. Review of change orders (outstanding/anticipated) • CO #13 (Treated Soils to 78,000 Tons) • CO #14 (Imported Cover Material) • CO #15 (Erosion & Sediment Controls) • CO #16 (Off-Site Sediment Removal) 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results 6. Review construction schedule compliance • Estimated completion date vs. contract date 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Updated air monitoring results • PCB oil collected to date • Confirmation sampling update • Sampling and Analysis Plan (Rev. 4) • Soil/sediment sampling outside of landfill 9. Comments from Owner, SCO, Contractor, and Designer • Concerns of technical community advisor • Technical issues for CAB meeting 10. Schedule project monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES October 8, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR Mike Kelly-NCDENR Bill Gallagher -Shaw Pat Barnes -CT A Jim Cloonan -Earth Tech John Funk -Earth Tech Gary Duke -Shaw 1.0 Minutes of the September 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • 8,894.36 tons of soil passed the acceptance criteria in September with an average PCB concentration of0.156 ppm. 77,144.22 tons of material have been treated to date with an average PCB concentration of 0.137 ppm excluding the 372 tons of clay treated in July. • Average production rate for September was 300 tons per day. • During September, the unit was down for 24 hours for repairs and 48 hours due to Hurricane Isabel. • No E&S inspection was performed by Kimberly Summers during September, but an inspection was made on October 8, 2003. No new issues were identified during that inspection. • Shaw has removed sediment from both on-site and off-site areas ( completed 10/7/03). Off-site material, approximately 40 tons, is staged on pad 4 for subsequent disposal back into the former landfill. • Written approval was received from EPA Region N to place material containing <10 ppm PCBs in the landfill at a depth of 15 feet below final grade. 3 .0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Shaw has completed excavation of all remaining landfill material, and confirmation sampling of the clay bottom met acceptance criteria. • Shaw will continue backfilling the landfill since all bottom grids have been cleared and samples meet criteria. • Shaw excavated an opening in the landfill bottom liner using a trackhoe. The opening measures approximately 10 feet long by 5 feet wide. Depth is approximately 8-10 feet below the top of the clay liner. The opening penetrated the lower liner. • Shaw to move a four-foot lift from Mt. Tilley into the landfill during the week of October 13th . • Earth Tech to complete sampling of the Mt. Tilley stockpile after four-foot lift is removed. • No major maintenance shutdowns are planned for the month of October. Thermal treatment is scheduled for completion by October 15-16, 2003. • Non-aqueous liquids collected to date approximately 3,300 gallons. • Placement of final cover scheduled for mid-November. • Equipment decontamination will commence once MSR has completed thermal treatment (week of October 13111). • Shaw to send Sampling and Analysis Plan (Rev. 4) to NCDENR and Earth Tech week of October 61\ and NCDENR to forward plan to EPA Region IV. 4.0 REVIEW OF CHANGE ORDERS • CO #13 -Treated Soil to 78,000 Tons approved. • CO #14 -Increase in amount for Off-Site Disposal of Debris (material not suitable for thermal treatment) pending approval. • CO #15 -Erosion and Sediment Control -Mt. Tilley stockpile. Earth Tech recommended approval in the amount of $18,618.00. • CO #16 -Off-Site Sediment Removal -Letter of Authorization prepared for Shaw to proceed on a time and material basis not to exceed $5 ,800. • CO #17 -Final Tonnage. Change order will be prepared by Shaw after thermal treatment is complete. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • E&S inspection in October -Shaw to seed north side of the site and maintain sedimentation basins until grass is established. Seed north side first, then seed former landfill area. • Non-discharge system handled a total of 4 million gallons total during the project duration. John Hunt of DWQ inspected the system in September after hurricane Isabel, and no issues were identified. Lined pond did not overtop during the hurricane. Maximum wind speed measured at the site meteorological station was 45 mph. • Untreated soil dioxin results were TEQ of 1 73 ppt, which is less than the treatment standard. • NC DENR to sample site monitoring well the last week of October and then abandon the wells in accordance with the requirement contained in 15A NCAC 2C after the results are received in early December. 6.0 REVIEW OF SCHEDULE COMPLIANCE • The completion of thermal treatment is scheduled for October 16, 2003 based on additional soil in the landfill. Substantial completion is scheduled for December 15 , 2003. Shaw will update the schedule each month based on actual production. • Liquid PCBs will be disposed one week after completion of soil thermal treatment. Shaw to record condensate oil volume prior to MSR decon. 7.0 PERCENT COMPLETE: 93.23% based on 78,000 tons. 8.0 CONSTRUCTION/COORDINATION ISSUES • Perimeter air monitoring results had shown levels decreasing as soil was removed from the landfill with the exception of week 36 where levels had increased. • To date, 3,300 gallons of PCB liquids have been collected in the tanks; anticipate 4,000 gallons by project end. No fuel was added to the feed soils during August. • Rocks to be crushed prior to thermal treatment. • EPA has indicated to Shaw that they cannot reimburse for the addition sampling performed by EQM during the performance demonstration test in January because it 2 was not part of their contract with EQM. The plan had been to reimburse under the liquid phase demonstration test. Since the liquid will be shipped offsite, that is no longer possible. EPA can only reimburse for the $30,000 by finding discrete work that is to be done and having a contract approved and in place before the work is done. • Shaw to provide site restoration plan and final site sampling plan, and sealed as-built drawings at project completion. • DENR to prepare generator form for off-site disposal of condensate. Onyx has approved acceptance of the oil for disposal. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • Community perception is very positive now that project is at completion. 10.0 NEXT SCHEDULED MEETING: November 12, 2003 at 11 :00 at the project site. 3 MONTHLY PROGRESS MEETING -NOVEMBER 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A November 19, 2003 -TIME 11:00 AM LOCATION: Warren County PCB Landfill 1. Approval of October minutes 2. Work performed in the last 30 days. • Completion of soil treatment, final average concentration and processing rate • System demobilization • Landfill backfilling and handling of Mt. Tilley Soils • Cleaning of pads. • Final site confirmation sampling 3. Work to be performed in the next 30 days • Final quantity and disposal of non-aqueous condensate • Complete equipment demobilization • Placement of cover material • Hyrdoseeding cover and impacted site areas • Final equipment/pad decontamination 4. Review of change orders ( outstanding/anticipated) 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results • Air permit reporting requirements/notification • TSCA permit reporting requirements/notification 6. Review construction schedule compliance • Estimated completion date vs. contract date • Shaw estimated demobilization date. 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Updated air monitoring results • Soil sampling within landfill site 9. Comments from Owner, SCO, Contractor, and Designer • Project close-out requirements • Tasks remaining after Shaw demobilization • Unlined pond and sedimentation basin testing • System/equipment remaining on-site after demobilization 10. Schedule of final monthly progress meeting date, time, and place MONTHLY PROGRESS MEETING MINUTES November 19, 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION ATTENDEES Pat Backus -NCDENR Mike Kelly-NCDENR Bill Gallagher -Shaw Rob Holland -Earth Tech John Funk -Earth Tech Gary Duke -Shaw 1.0 Minutes of the October 2003 monthly progress meeting were approved without comment. 2.0 PROJECT STATUS • Thermal processing of soils was completed October 18, 2003. • A total of 82,092.51 tons of soil were processed by thermal desorption and passed the acceptance criteria of 200 ppb. The net tonnage, not including haul road material, was 81,622.71 tons. The average PCB concentration of all soils processed was 137 ppb. • Shaw and their subcontractor MSR are demobilizing from the site with MSR demobilization nearly 90% complete. • Backfill of landfill and placement of soil cover is complete. • Shaw plans to hydroseed landfill and disturbed site areas during the week of November 24, 2003. • One section of Pad 1 had been cleaned. The wipe sample results after cleaning were below the EPA high occupancy wipe sample limit of ~ 0 ug/100 cm2 . • No E&S inspection was performed by Kimberly Summers during October. • Total organic liquid waste was 4273.Slgallons. Shaw will deduct the amount of oil used for flushing equipment and the amount added to soil during thermal treatment to determine a net quantity of organic liquid waste for payment. Organic liquid was shipped to Onyx in Port Arthur, TX for destruction on November 14th •• 3.0 WORK TO BE PERFORMED IN THE NEXT 30 DAYS • Final demob to be completed by December 22, 2003. • Trailers and power will be demobilized during week of December gth. • Pads will be decontaminated and tested by December 12, 2003. 4.0 REVIEW OF CHANGE ORDERS • CO #17 -Treated Soil to 81,622.71 Tons requires SCO approval. • CO # 18 -Credit for State supplied fuel requires SCO approval. • CO # 19 -Fuel price adjustment for fuel Shaw supplied in October requires SCO approval. • CO #20-Fence-Change order on hold. • Change orders required for Mt Tilley stockpile placement, organic liquid waste quantity, and on-site debris not requiring thermal processing. 5.0 STATUS OF PERMITS, PROJECT DRAWINGS AND SUBMITTALS • E&S permit -Kimberly Summer to provide final approval of site stabilization and removal of E&S measures. • TSCA -MSR to comply with notification requirements contained in their TSCA Permit • Air Permit -Shaw to complete all notification requirement contained in the system air permit. • Non-Discharge -Shaw to complete all notification requirement contained in the non-discharge permit. • Shaw to provide seeding mixtures. 6.0 REVIEW OF SCHEDULE COMPLIANCE • Completion date is scheduled for December 15, 2003. The contract completion date without approval of weather and power delays is November 10, 2003. 7.0 PERCENT COMPLETE: 96.46% 8.0 CONSTRUCTION/COORDINATION ISSUES • Perimeter air monitoring will be conducted the first and third weeks of December 2003. Off-site air monitoring is scheduled for the third week. Sampling schedule may be accelerated based upon Shaw's progress in site demobilization. • Work scheduled after December demobilization includes: closure of sedimentation basins, closure of unlined pond, final seeding, relocation of fence in the vicinity of the sedimentation basins and clean soil stockpile, repair of fence and gate, and removal of silt fences. 9.0 COMMENTS FROM OWNER, SCO, CONTRACTOR, DESIGNER, AND COMMUNITY • No comments. 10.0 NEXT SCHEDULED MEETING: December 10, 2003 at 11 :00 at the project site. 2 MONTHLY PROGRESS MEETING -December 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A December 10, 2003 -TIME 11 :00 AM LOCATION: Warren County PCB Landfill 1. Approval of November minutes 2. Work performed in the last 30 days. • System demobilization • Cleaning of pads. • Hyrdoseeding cover and impacted site areas 3. Work to be performed in the next 30 days 4. Review of change orders ( outstanding/anticipated) 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection • Non-discharge treatment system status/sampling results -Submittal of laboratory analytical reports. • Air permit reporting requirements/notification -submittal of notification to Earth Tech • TSCA permit reporting requirements/notification -Submittal of notification to Earth Tech. 6. Review construction schedule compliance • Estimated completion date vs. contract date • Earth Tech inspection date -partial occupancy punch list • Earth Tech re-inspection and Shaw partial occupancy date. • Shaw 2004 re-mobilization date. • Shaw substantial completion date. 7. Percentage complete to be reported by Contractor (actual work in place) 8. Discuss construction/coordination issues • Updated air monitoring results • Submittal of laboratory analytical reports from soils collect from within landfill site • Submittal oflaboratory analytical reports, figure and summary from samples collected from the clay liner. • Submittal of laboratory analytical reports, figure and summary from samples wipe samples collected on the pads. • Contractor furnished as-Built drawings and completion of final report. • Disposal of LCID material in the unlined pond. • Storm water management and provisions for controlled drainage off the concrete pads during partial occupancy period and after substantial completion. 9. Comments from Owner, SCO, Contractor, and Designer • Partial completion requirements • Preliminary 2004 punch list items. • Unlined pond -water disposal contingency plan MONTHLY PROGRESS MEETING -December 2003 WARREN COUNTY PCB LANDFILL DETOXIFICATION SCO ID #010440101A December 10, 2003 -TIME 11 :00 AM ATTENDEES Pat Backus -NCDENR Mike Kelly -NCDENR Dave Ditcher -Shaw Pat Barnes-CTA John Funk-Earth Tech Gary Duke -Shaw (by Phone) 1. Minutes of the November 2003 monthly progress meeting were approved without comment. 2. Work performed in the last 30 days. • System demobilization with expected completion by December 31 st• • Decontamination Pad 4 complete. Pad 2 several areas complete. Pads 1 and 3 waiting for cleaning solution. Decontamination of all pads to be completed by the last week in December. • Hyrdoseeding cover and impacted site areas except in the area of the former lined pond. Vegetation not apparent after 2 weeks of seeding completion. • Installed storm water discharge line in the sump on Pad 4. • Liner removed from the lined pond. Grading in the area incomplete. Results of confirmation due week of December 15th . • 3. Work to be performed in the next 30 days • Complete cleaning of the pads. Water from cleaning solution to be placed into a tanker truck for subsequent transportation for disposal. • Abandon site monitoring wells (by NC DENR). • Demobilize DENR and Earth Tech trailer. Shaw trailer to remain over the winter. • Complete storm water management controls on the pads. • Close site water line and drain to prevent freezing over the winter. 4. Review of change orders ( outstanding/anticipated) • Final erosion and sediment control change order and liquid PCB adjustment combined into Change Order 20. 5. Review status of permits applications, project drawings and submittals • Erosion controls inspection performed by K. Summers on December 5th• No comments were noted during the inspection. • Division of water quality will be on-site December 12th to inspection the storm water treatment system. Shaw does not plan to set up the spray irrigation system, if required, until the spring 2004. • Non-discharge treatment system status/sampling results -Shaw to submit laboratory analytical reports. • Air permit reporting requirements/notification -Shaw to submit copies of notification to Earth Tech • TSCA permit reporting requirements/notification -Shaw to submit copies of notification to DENR and Earth Tech. 6. Review construction schedule compliance • Partial utilization beneficial occupancy complete by December 30, 2003. • Shaw re-mobilization date April 12, 2004 • Substantial completion by May 10, 2004. 7. Percentage complete to be reported by Contractor (98.42%) 8. Discuss construction/coordination issues • Earth Tech presented and updated air monitoring results for November 13th • Site average concentration at the ambient standard. • Earth Tech will provide the results of the laboratory analytical results from soils collect from within landfill site by December 12th• • Shaw to submit laboratory analytical reports, figure and summary from samples collected from the clay liner. • Shaw to submit laboratory analytical reports, figure and summary from samples wipe samples collected on the pads. • Shaw to furnished as-Built drawings and final report prior to substantial completion. • Shaw to provide a cost estimate for disposal off-site of non-salvageable jersey barriers . • 9. Comments from Owner, SCO, Contractor, and Designer • Earth Tech to provide a preliminary punch list by December 19th• • The Community Technical Advisor (CTA) Pat Barnes voiced the concern of creating an LCID landfill with the disposal of the non-salvageable jersey barrier in the unlined pond, and though it would create a misconception among the community over disposal of ever inert material on the site after completion of the "clean up". ace Analytical™ www.pacelabs.com May 13 , 2002 Ms. Shelley Gibbons Earth Tech 10 Patewood Drive Bldg VI, Suite 500 Greenville , SC 29615 RE : Lab Project Number: 1056569 Client Project ID: Warren Co. Landfill PCB Dear Ms. Gibbons: Pace Analytical Services, Inc. 1700 Elm Street, Suite 200 Minneapolis, MN 55414 Phone: 612.607.1700 Fax: 612.607.6444 Enclosed are the analytical results for sample(s) received by the laboratory on April 22, 2002. Results reported herein conform to the most current NELAC standards , where applicable, unless otherwise narrated in the body of the report. If you have any questions concerning this report please feel free to contact me. Sincerely, Daryl Peterson Daryl.Peterson@pacelabs.com Project Manager State of Minnesota laboratory 027-053-137 Enclosures REPORT OF LABORATORY ANALYSIS This report shall not be reproduced, except in full, without the written consent of Pace Analytical Services, Inc.