HomeMy WebLinkAbout8004T_WM_EastSpencer_2023FA_Cost_Approval_FID_20230519Moutos, Sarah
From: laserfiche.ncdenr.gov@mccicloud.io
Sent: Friday, May 19, 2023 4:45 PM
To: kmertens@wm.com
Cc: Moutos, Sarah; Stanley, Sherri; Yitbarek, Diana
Subject: [External] APPROVAL -Transfer Station Financial Assurance Cost Estimate - 8004T-
TRANSFER-1995 kmertens@wm.com
Attachments: East Spencer Facility Operational Plan -final 2022.pdf
CAUTION: External email. Do not click links or open attachments unless verified. Report suspicious emails with the Report Message
button located on your Outlook menu bar on the Home tab.
D k7
m.E Q
0CpArtm�n7 vFnvirpnmCn'.A1 Qvnhty
5/19/2023
Kyle Mertens
EP Manager
Waste Management of Carolinas, Inc; East Spencer Waste Transfer Facility
RE: Approved Cost Estimate
Transfer Station - kmertens@wm.com
Rowan County
Dear Kyle Mertens,
A review of the Transfer Station Cost Estimate for 8004T-TRANSFER-1995, kmertens@wm.com submitted on 5/16/2023
has been completed. The estimate meets the site -specific operations and appears to be appropriate. The Division of
Waste Management - Solid Waste Section has reviewed and approved the provided cost estimate required for
establishing financial assurance for a transfer station.
Initial Review Comments: 20230517 - The Section is in receipt of the electronic form for East Spencer TS.
Permitting Engineer Review Comments: The closure cost estimate provided for this transfer station is considered
acceptable
This approval letter is for your use in establishing an appropriate financial assurance mechanism. The below are the
provided legal entity, facility name via onsite signage, assigned permit number, and approved cost estimate in 2022-year
dollars.
Owner Name: Waste Management of Carolinas, Inc; East Spencer Waste Transfer Facility
Facility Name: kmertens@wm.com
Permit Number: 8004T-TRANSFER-1995
Approved Cost Estimate = $ 35914.50
At this time, you may work with your Corporate Finance Officer and establish the appropriate financial assurance
mechanism(s). Waste Management of Carolinas, Inc; East Spencer Waste Transfer Facility has 60 calendar days from the
date of this approval to establish required financial assurance mechanisms. Financial Assurance mechanism templates,
NC Rules for financial assurance, and inflation multipliers are among the pertinent information you can find at the
Section's Financial Assurance website: http://deq.nc.gov/swsfa. Should you or your Finance Department require any
assistance, feel free to reach out to Sarah Moutos at 919-707-8287 or Sarah.Moutos@ncdenr.gov .
Sincerely,
Sarah Moutos
Environmental Program Consultant
Division of Waste Management - Solid Waste Section
CC: Sherri Stanley
Diana Yitbarek
Kyle Mertens
Table 1. Financial Closure Cost Estimate of the Solid Waste Transfer Station, East Spencer Facility, North Carolina
General Conditions/Mobilization/Demobilization-Backhoe and
Bulldozer
Lump Sum
$6,700.00
1
$6,700.00
Cleaning and Disinfection of the Facility (Pressure wash)
a) Labor
Per Hour
$15.00
40
$600.00
b) Procurement of cleaning materials
Lump Sum
$500.00
1
$500.00
Abandon 1 Wastewater (Leachate) Collection System
a) Labor
Per Hour
$15.00
30
$450.00
b) Materials requirement (concrete, 4 cubic yards)
per yard
$45.00
4
$180.00
c) Equipment Rental
Lump Sum
$400.00
1
$400.00
Signage (Attachment of 2 Metals Signs fixed to fence)
Lump Sum
$300.00
1
$300.00
Waste Disposal (-200 tons)
a) Mobilization/Demobilization of front-end loader
Lump Sum
$400.00
1
$400.00
b) Loading: Front end loader w/operator
Per Hour
$120.00
30
$3,600.00
c) Hauling of waste
Per Load
$500.00
15
$7,500.00
d) Disposal of Waste
Per Ton
$45.00
200
$9,000.00
Leachate Disposal
a) Wastewater disposal
Per Hour
$15
40
$600.00
Regulatory closure of existing discharge permits
Lump Sum
$1,000.00
1
$1000.00
Total Cost $ 31,230.00
Contingency Cost (10%) $ 3,123.00
Administrative Cost (5%) $1,561.50
Total Closure Cost $35,914.50
Solid Waste Transfer Station -East Spencer, North Carolina Facility
Closure Plan (Permit #8004T-TRANSFER-1995)
DAA Project No. 497270