HomeMy WebLinkAboutNCD980602163_19910909_Warren County PCB Landfill_SERB C_PCB Landfill data-OCR(.
September 9, 1991
Re: PCB Landfill in Warren County
Pumping Rate is about 7 to 8 gal/min
It takes about 15 to 20 minutes to pump the system dry
About 120 gallons are pumped per cycle
It takes about 2 hours and 45 minutes to recharge
Assume about 3 hours to pump and recharge for one cycle
Assume a constant rate of pumping and recharge
8 cycles of 3 hours per day
8 cycles X 120 gal/cycle= 960 gal/day
1,400,000 gal. / 960 gal/day= 1458 days= 4 years
assuming constant rate, 24 hrs/day, 365 days/yr
"u '0 ~ ~ •-"'-_',~~
l ¼.( l.a .. \\
4 X 3 = 12 years, assuming constant rate, 8 hrs/day, 365 days/yr
12 / .68 = 17.6 years, assuming constant rate, 8 hrs/day, 250 days/yr
Assumes constant rate of recharge and pumping
As sumes no additional infiltration
Set up continuous pumping operation
1. slow rate of continuous pumping
2. cycled pumping at higher rate with float valve on/off switch
Someone needs to be on site to monitor pumping, sample leachate,
measure draw-down, etc.
Permit requires certified waste water treatment plant operator???
Operate by using existing staff or contract out the work
PCB LANDFILL
As agreed to in the 9/9/91 meeting, I have compiled a list of tasks
that need to be accomplished at the PCB landfill. These tasks were
identified as items that need to be addressed in order to assess
the current conditions at the landfill and any changes that may
occur upon removal of the water in the landfill. The tasks have
been listed in the milestone chart below. Also in the chart is my
estimate of the amount of time required for a contracted consultant
to complete each activity. These estimates are based upon my
observations of work completed by consultants at RCRA facilities
over the past 8 years.
If the schedule below was to be completed by State personnel then
an additional 4-6 months must be added into each item requiring a
purchase. Also, additional time would be required to contract with
other Divisions to complete various tasks that the Solid Waste
Management Division is unable to perform.
DATA for Milestone Chart
WEEK
1-2
3
4-5
EST.
COST
4-SK
Ground Water
1 N/A*
2 N/A*
TASKS
Well Installation
determine specifications for recovery well to
be installed in the landfill.
develop cost estimates for installation of the
well in the landfill. The well is to be
completed at the interface between the sand
liner and the clay liner.
well installation and disposal of contaminated
cuttings.
Surveying
survey the top of the inner casing on the
wells in order that the ground water surface
elevation could be determined.
obtain water levels and determine ground water
flow direction.
Settlement in the Top Liner
1 N/A* establish benchmarks on the landfill cap and
survey benchmarks.
1-3
3-5
5-10
1-3
4-6
7-10
6-7
10-22
Fence
develop specifications on the fence to be
installed around the on site pond.
develop cost figures for purchasing and
installation of the fence.
installation of fence.
Water Removal
develop specifications for water removal
system consisting of either a continuously
operated low volume pump or a pump operated by
a float valve. ~~ ~rl·
develop cost figures for purchasing as well as
operation and maintenance of the pump system.
purchase and install equipment to remove water
from the landfill.
Removal and Treatment of Water from the Landfill
establish schedule for testing of water
removed from the landfill; make arrangements
with lab to have testing done.
Operate water removal system including: remove
approximately one foot of water in the
landfill; treat water withdrawn from the
landfill; test water accumulated in tanks;
discharge water to on site pond or have water
transported off site for disposal.
N/A* The expertise is available within the Division. The costs
incurred performing these activities should be employees time
only.
9/18/91
wp40
i,,
10-22 N/A*
1-2 N/A*
10-22 N/A*
1-3
3-5
6-10
1-3
3-4
3-4
5-6
6-18
monitor elevation of the benchmarks throughout
the water level extraction program.
Water Level Monitoring
implement a baseline water level monitoring
program in the landfill, with an accuracy of
+/-0.05 feet, to determine the static water
level in the landfill.
periodically turn off water extraction system
and allow water level in the landfill to
stabilize thereby allowing a static water
level measurement to be taken.
Electrical Power to Landfill
determine the needs for electrical power and
what type of physical structure would be
required.
develop cost figures for installation of
electrical power at the landfill and a
permanent structure if required.
install electrical power to landfill. If an
additional structure is required then the time
frame to complete this task may double or
triple.
Upgrade of Water Treatment System
determine the
treatment tanks
filters, etc.
need for any additional
i.e. sand filters, charcoal
develop cost figures for purchasing and
installation of the treatment tanks.
determine the need for holding tanks to
receive water discharged from the treatment
system. The water in the tanks will be tested
for PCBs and based upon the results will be
discharged to the on site pond or hauled
offsite for disposal.
develop cost figures for purchasing and
installation of holding tanks to be used as
part of the wastewater treatment system.
install additional tanks as required
lasl<-llel lmlalatloo Detenline Specs. for llel Deuelop cost est. for Instill Instill NI SUrueylng Slruey for fm direction 11easure aater Leuels Establish benci--t<s on cap 11onitor Benci--l<s aater Leuel 11on11or1ng lapleaenl baselne -.torlng Periodic shutoff of rm Electrlclll p_. to landfll Deterlline .,._-& struc. needs Deuelop cost figures Instill struc. & ~I Upgrade aater lreataait Sgstea Deterlline needs for .-equip. Deuelop cost figures Install addition trealaall Fe,w;e Deuelop specs Deuelop cost figures Install fe,w;e aater 11e11ooa1 Deuelop specs for r_,,,. Deuelop cost figures for puap Purchase and Instill ~I llellooal and lreataent of 9ater Establish schedule for testing Operate Nier r_,,,. systea Duratn (a<s) 5 2 2 21 2 12 21 2 12 1 D 2. 5 2. 5 5 18 l l 12 12 3 3 6 1 D 3 l 4 16 2 12 Resources flclual PCB LandfiR Project 1991 Sep Oct Nou I JK 23 1:se I 1 IM 121 IH J • I• I• 125 F"'·:CC· ~·:•:•:•:•:•:·:.:-:':.:•:•:•:•:·:•:•:i . I~ ' ' n:: : ..... w: ' ' ' ' ' ~ :•:•:•:•:•:•:•:•:•:•:•:•:• t-:•:):.·•:•:•:•·•:•··· :•:•:•:•:•:•J [':> b::•:•···· ' ' 'i I I I:.:.·.·····'· . ....-.·.·.·.·.·'•:•:•···· •:~ F:::;:::;-;--.-. t1ilestone I _,,,, I I • • 1992 Dec Jan Feb 2 I , IK 123 1:se I ' 113 IH 121 , I• .....
~ 1T Q ~K "
' ~ . -----J: -~~t:___--=· •✓• I ' -=--~-"-]. ,~~
-------------------------·-···---------·--
__ J)_} ,Q,~r~-r~ t \1\'" ~ c. ~~Y\, ~-t.a:_: ~~~"l.__·.:w~;~ +. :-/~C_,. ____ _
_____ _________ . _ J11~·.( ·:. 5~~-~h~._W_Jcr~~ + J DV-0---=C-=-·----
· s "''"' ~ \ t, ·. Y \-'! ,_,._ \ht ; o & :r.31c.t' 10 'r\ ) i M11,. % '-i-l ~ 1 "-• \sv,,;, i hj n 9
-----l: /~ ---·-----------'v-_1/~ k r-------------------____ O --
-_____ LJ _________ . ________________ rv ~'J~bts __________ 33:_ _____ _
-. -·--------/_:_}~_/~------------. _')_O __ ~'r)_Q _y.t\l(T __________ -----_\_() ~-
____ )•.'"a-,_ ____ ----·-----------______ 'I ... ---------------··------------~~-------·--
__________ J_'l-a_'. _\ ___________________ rv 1)a __ h~ ________ . _______________ 0 _____________ _
_ __ _ _ _ __ J~/~1 ·. J __ _ ___ ___ ____ __ _ '~--_ _ __ ___ .. ______________ o._____ __
·----. -----------------------------
--------------. -----------------------------
---------------------------·---------. --------- -·--------·--
--·----------------------------------· ------------------. --------··---------
--·----.. ·------·-------· ---
--------··
-----------------
----------------------------·---------