HomeMy WebLinkAboutNCD980602163_19830701_Warren County PCB Landfill_SERB C_Final Report for PCB Waste Disposal-OCRfi \
NORTH CAROLINA DEPARTMENT OF
CRIME CONTROL AND PUBLIC SAFETY
FINAL REPORT
PCB WASTE DISPOSAL SITE
WARREN COUNTY, NC
ITEM 1111-1990 CODE 14900
JULY, 1983
Prepared by
Sverdrup & Parcel
2211 W. Meadowview Road
Suite 114
Greensboro, NC 27407
GENERAL DESCRIPTION
FINAL REPORT
PCB WASTE DISPOSAL SITE
WARREN COUNTY
The PCB Waste Disposal Site is a hazardous waste landfill
containing approximately 40,000 cubic yards of polychlorinated biphenyl
(PCB) contaminated soil located in Warren County, North Carolina.
PERTINENT DATA
Contractor's bids for the construction of the site were opened on
January 21, 1982, and the contract was awarded May 28, 1982 to Jim
Lineberger's Grading & Paving Inc. of Gastonia, NC. Construction work
began on June 21, 1982. Continuous heavy rains and vandalism of the
groundwater monitoring wells and the 3O-mil PVC liner curtailed job
progress throughout the month of August, and construction was not
completed to the stage necessary for PCB placement until September 14,
1982. NC DOT trucks began hauling PCB contaminated soil on September
15, 1982 and completed hauling on October 12, 1982, except for twelve
loads of additional contaminated material which were delivered to the
landfill by NC DOT on November 17, 1982. A private firm, Propst
Construction Company of Concord, NC, under contract with the Department
of the Army, began hauling PCB contaminated soil from Fort Bragg on
October 6, 1982, and finished on October 27, 1982. Construction work
was completed on July 14, 1983. The final inspection of the completed
project was conducted on July 15, 1983 and final acceptance was on that
date.
-1-
(
CONSTRUCTION SEQUENCE AND DESCRIPTION
Initially four groundwater monitoring wells were installed, located
north, south, east, and west of the landfill. As designed and
installed, these wells were determined to be unsatisfactory by the NC
Department of Natural Resources and Community Development. Four
replacement wells were installed immediately adjacent to the original
wells. These wells were vandalized during construction and were
repaired or redrilled. The wells utilized 4" PVC pipe and screens with
lockable steel caps. An earthen containment structure 476' long and
232' wide was built by excavating to bottom elevations sloping from
elevation 320' to 314' and filling to a berm elevation of 342'. Side
slopes are 3:1 on the north, west, and east sides, 5:1 on the south.
Topsoil, clay, and silt materials excavated were stockpiled separately
for later use. A 9" layer of permeable sand was placed on this subgrade
as a lower leachate collection system, draining to a collection sump and
611 PVC extraction pipe in the northeast corner of the landfill. A
30-mil PVC liner, manufactured by Staff Industries of Detroit, Michigan,
was installed over this sand layer. This liner was slashed in 23 places
by vandals and was repaired by patching with additional liner material.
A one foot thick layer ot compacted bridging fill was placed over the
30-mil PVC liner, using previously stockpiled clay and silt materials.
A five foot thick compacted clay liner was constructed over the bridging
till using select clay material previously stockpiled, or obtained from
clay borrow areas on the site. Extensive heavy rains during this
critical stage of construction delayed progress for approximately one
month.
-2-
An upper leachate collection system was placed above the clay
liner, using a 9" layer of permeable sand, draining to a collection sump
and 6" PVC extraction pipe in the northeast corner of the landfill.
As final preparation for the placement of PCB material, a carbon
filter system was installed. This system consisted of a sand filter,
carbon filter, and temporary holding pond, located just northeast of the
landfill. The intent of the system was to treat excess rain water
collected in the disposal area during PCB placement, but the system was
not used during construction because a N.R.C.D. Discharge Permit had not
been obtained prior to construction. The system was left in place to
facilitate the State in removing water accumulated in the upper leachate
collection system during construction, and an irrigation system was
designed and installed during the later phase of the project to spray
the filtered water back on top of the landfill.
Supac filter fabric material, manufactured by the Phillips
Petroleum Company, was placed over the upper leachate collection sand
layer to prevent migration of the contaminated soil into the sand layer.
The PCB contaminated soil was then hauled and dumped by trucks from NC
DOT and by trucks from Propst Construction Company on contract with the
Department of Defense. The contaminated soil was placed and compacted
by the construction contractor to a final top elevation shown on the
plans. The actual volume of PCB material placed was approximately
40,000 cubic yards.
A one foot thick layer of compacted bridging fill was placed over
the PCB soil, again utilizing previously stockpiled clay /silt
materials.
-3-
I \
A two foot thick compacted clay liner was constructed over the
bridging fill using select clay material obtained from a second clay
borrow area on the site.
A 10-mil PVC liner, also manufactured by Staff Industries of
Detroit, Michigan, was installed over this clay liner and sealed to the
lower liner.
Another one foot thick layer of compacted bridging fill was placed
over the 10-mil PVC liner.
A 4" PVC pipe gas vent was installed, located at the center point
of the landfill.
The entire top surface of the landfill and the 5:1 outslopes were
then covered with a one foot thick layer of topsoil, utilizing material
previously removed and stockpiled. This area and all adjacent disturbed
areas were limed, fertilized, seeded, and mulched.
A steel chain-link fence, with steel posts was installed around the
perimeter of the disposal area.
-4-
EXHIBIT "A" -AREA FIGURES
The PCB Waste Disposal Site is located on a 142.3 acre tract, off
SR 1604 near Afton community in Warren County. Within this tract, a
19. 32 acre area contains the landfill and will be retained in state
ownership. The remainder has been deeded to Warren County as a buffer
zone surrounding the landfill.
The inside dimensions of the earthen containment structure are
476'x 232', or 2.54 acres. The area within the chain-link fence is 300'
x 550', or 3.79 acres.
-5-
CONTRACT
General
EXHIBIT "B" -COST DATA
ORIGINAL COST
$362,619.00
CONSTRUCTION COST
CHANGE ORDER ADDITIONS
$58,828.09
COST
$421,447.09
CONSTRUCTION COST SUB-TOTAL $ 421,447.09 ...;.._-----'----
DESIGN & CONSTRUCTION INSPECTION FEES
Sverdrup & Parcel $ 78,118.51
Soil & Material Engineers $ 14,810.11
DESIGN & CONSTRUCTION INSPECTION FEES, SUB-TOTAL $ 92,928.62
TOTAL PROJECT COST $ 514,375.71 --'--------'----
-6-
GENERAL CONTRACT
c.c.o. NO
1
2
3
4
5
6
7
8
9
10
EXHIBIT "C" -CHANGE ORDERS
DESCRIPTION
New Monitoring Wells
Time Extension
Time Extension
Security Guards
Security Guards
Security Guards
Security Guards
Additional Fencing
Spray Irrigation System
Temporary Seeding & Additional
Erosion Control
TOTAL
-7-
AMOUNT
$ 6,987.50
-0-
-0-
4,214.00
3,923.75
11,558.40
5,493.25
3,323.32
7,456.00
15,871.87
$58,828.09
•
(
EXHIBIT "D"" -CONTRACTORS, SUBCONTRACTORS, & MATERIAL SUPPLIERS
GENERAL CONTRACT
Prime Contractor -Jim Lineberger's Grading & Paving, Inc.
Route 2 -Box 77A
Gastonia, North Carolina 28052
SUBCONTRACT CONTRACTOR
Groundwater Monitoring Wells Ezra Mier Associates, Inc.
401 Glenwood Avenue
Surveyors
PVC Liners
Seeding
Chain-Link Fence
P. 0. Box 12447
Raleigh, NC 27605
Southern Survey, Inc.
1006 Lamond Avenue
Durham, NC 27701
Arkay Corporation
1321 Romany Road
Charlotte, NC 28204
Lineberry, Inc.
Climax, NC
U.S. Steel, Cyclone Fence
Charlotte, NC
-8-