HomeMy WebLinkAboutNCD980729602_19940101_Jadco-Hughes_FRBCERCLA RA_Remedial Action Work Plan-OCRI I g D 0 D I I • • I I I I I I I I I REMEDIAL ACTION WORK PLAN Jadco-Hughes Site Gaston Country, North Carolina JANUARY 1994 REF. NO. 3669 (18) This r~port is printed on recycled paper. RIECIE~VlED MAR 1 5 1994 SUPERFUND SECTION CONESTOGA-ROVERS & ASSOCIATES I I I • g ft I I I I I I I I I I I I I TABLE OF CONTENTS Page 1.0 INTRO DU CTI ON ...................................................................................................... 1 1.1 BACKGROUND INFORMATION AND PURPOSE OF REPORT ...... l 1.2 ORGANIZATION OF REPORT .................................................................. 7 1.3 PROPOSED REMEDIAL ACTION .............................................................. 9 1.4 PROJECT ORGANIZATION ....................................................................... 10 1.5 BASIS FOR REMEDIAL CONSTRUCTION ............................................. 10 2.0 EXISTING CONDITIONS ......................................................................................... 11 3.0 ACCESS AGREEMENTS AND PERMITTING REQUIREMENTS ................. 13 4.0 CONSTRUCTION HEALTH AND SAFETY PLAN ........................................... 15 5.0 SITE MANAGEMENT AND SEQUENCING ...................................................... 16 5.1 REMEDIAL ACTION CONTRACTOR SELECTION .............................. 17 5.2 SITE MANAGEMENT .................................................................................. 17 6.0 SPILLWAY, CULVERT AND DRAINAGE LINE ............................................... 19 6.1 ST A TEMENT OF WORK ............................................................................ 19 6.2 CONSTRUCTION SPECIFICATIONS AND DRAWINGS ................... 20 6.3 CONSTRUCTION QUALITY ASSURANCE PLAN .............................. 20 6.4 IMPLEMENTATION AND SEQUENCING ............................................. 20 6.4.1 Site Preparation .............................................................................................. 20 6.4.2 Construction of Spillway, Culvert Lining and Construction of Drainage Line .................................................................... 21 6.4.3 Construction Closeout .................................................................................. 21 6.5 SCHEDULE OF ACTIVITIES ....................................................................... 21 7.0 GROUNDWATER EXTRACTION SYSTEM ....................................................... 23 7.1 STATEMENT OF WORK ............................................................................. 23 7.2 CONSTRUCTION SPECIFICATIONS AND DRAWINGS ................... 24 7.3 CONSTRUCTION QUALITY ASSURANCE PLAN .............................. 24 7.4 IMPLEMENTATION AND SEQUENCING ............................................. 24 7.4.1 Site Preparation .............................................................................................. 24 7.4.2 Installation of Extraction Wells, Tile Drain and Pipeline ..................... 24 7.4.3 Construction Closeout .................................................................................. 25 7.5 SCHEDULE OF ACTIVITIES ....................................................................... 25 8.0 GROUNDWATER TREATMENT SYSTEM ....................................................... 26 8.1 STATEMENT OF WORK ............................................................................. 26 8.2 CONSTRUCTION SPECIFICATIONS AND DRAWINGS ................... 27 8.3 CONSTRUCTION QUALITY ASSURANCE PLAN .............................. 27 3669 08) CONESTOGA-ROVERS & ASSOOATES I I • I I I u D I I I I I I I I I I I TABLE OF CONTENTS 8.4 IMPLEMENTATION AND SEQUENCING ............................................. 27 8.4.1 Site Preparation .............................................................................................. 27 8.4.2 Construction and Commissioning of the Groundwater Treatment System ................................................................ 27 8.4.3 Construction Closeout .................................................................................. 28 8.5 SCHEDULE OF ACTIVITIES ....................................................................... 28 9.0 SOIL VAPOR EXTRACTION SYSTEM ................................................................. 29 9.1 STATEMENT OF WORK ............................................................................. 29 9.2 CONSTRUCTION SPECIFICATIONS AND DRAWINGS ................... 29 9.3 CONSTRUCTION QUALITY ASSURANCE PLAN .............................. 30 9.4 IMPLEMENTATION AND SEQUENCING ............................................. 30 9.4.1 Site Preparation .............................................................................................. 30 9.4.2 SVE Trenches and Pipeline ......................................................................... 30 9.4.3 Construction and Commissioning of the SVE Treatment System ................................................................................. 30 9.4.4 Construction Closeout .................................................................................. 30 9.5 SCHEDULE OF ACTIVITIES ....................................................................... 31 10.0 SOIL FLUSHING SYSTEM ....................................................................................... 32 10.1 STATEMENT OF WORK ............................................................................. 32 10.2 CONSTRUCTION SPECIFICATIONS AND DRAWINGS ................... 32 10.3 CONSTRUCTION QUALITY ASSURANCE PLAN .............................. 33 10.4 IMPLEMENTATION AND SEQUENCING ............................................. 33 10.4.1 Site Preparation .............................................................................................. 33 10.4.2 Soil Flushing Extraction Trench, Pipeline and Infiltration Galleries ........................... : .......................................................... 33 10.4.3 Commissioning of the Soil Flushing System .......................................... 33 10.4.4 Construction Closeout .................................................................................. 34 10.4.5 Schedule of Activities ................................................................................... 34 11.0 OPERATION AND MAINTENANCE PLAN ..................................................... 35 12.0 PROJECT DOCUMENTATION AND REPORTING .......................................... 36 13.0 PROJECT CLOSEOUT ................................................................................................ 37 14.0 COMMUNITY RELATIONS SUPPORT ............................................................... 39 15.0 REMEDIAL ACTION SCHEDULE OF ACTIVITIES .......................................... .40 16.0 CONSTRUCTION MANAGEMENT PLAN ........................................................ 41 3669 08) C0NESfOGA-R0VERS & AsS0OATES I I I I I ' u u D E I I I I I I I I I FIGURE 1.1 FIGURE 1.2 FIGURE 2.1 FIGURE 2.2 FIGURE 2.3 FIGURE 2.4 FIGURE 15.1 FIGURE 16.1 3669 (18) LIST OF FIGURES Following Page SITE LOCATION 1 MONITORING WELL AND PIEZOMETER LOCATIONS 4 SITE DRAINAGE PATTERN 12 GEOLOGIC CROSS-SECTION A-A' 12 SHALLOW GROUNDWATER FLOW PATTERNS 12 DEEP GROUNDWATER FLOW PATTERNS 12 RA SCHEDULE 40 PROJECT ORGANIZATION 41 CONESTOGA-ROVERS & ASSOOATES I I I ,. I I I I I g u u n fl 11 I I I I APPENDIX A APPENDIX B APPENDIXC APPENDIXD 3669 (18) LIST OF APPENDICES ACCESS AGREEMENTS CONSTRUCTION HEALTH AND SAFETY PLAN CONSTRUCTION QUALITY ASSURANCE PLAN CURRICULA VITAE CONESfOCA-ROVERS & ASSOCIATES I I B II ' I I I I I I I I ' ·1 I I l I. 1.0 3669 {18) INTRODUCTION This report presents the Remedial Action (RA) Work Plan for the Jadco-Hughes Site (Site). BACKGROUND INFORMATION AND PURPOSE OF REPORT The Site is located in Gaston County, North Carolina, approximately 15 miles west of Charlotte (Figure 1.1). The 6-acre Site is a former solvent reclamation and waste storage facility which had two operators: C.A. Hughes, Inc. (1971 to 1975); and Jadco, Inc. (1975). The Site was closed in 1975 and a North Carolina (State) ordered cleanup was completed by 1983. After closure of the Site, several reconnaissance evaluations were conducted by the United States Environmental Protection Agency (USEP A) and the State which identified residual contamination. The Site was subsequently placed on the National Priorities List (NPL) in May 1986. Later in 1986, an Administrative Order on Consent was entered into between USEPA and a group of companies identified as potentially responsible parties (PRPs) who formed the Jadco-Hughes Steering Committee (Steering Committee). Conestoga-Rovers & Associates (CRA) was retained by the Steering Committee to conduct a Remedial Investigation and Feasibility Study (RI and FS) and Superfund Risk Assessment (SRA). Based on the analytical results for the soil, groundwater, surface water and sediment samples which were collected during the RI, the delineated Site contamination included: • approximately 435 cubic yards (c.y.) of polychlorinated biphenyl (PCB) contaminated surface soil; 1 CONESTOGA-ROVERS & ASSOC!A TES I I I I I I ti I I u u n 8 8 G I D 0 o' 1000' ,-' - /"' ------c'.s -· -. -' .:_ ... ,--·--. -~· --. - \ ,,o___,,! . __./ . ' . .-d-•'• . ) <E::::::::.,....--=_j .\'\~~,,,~~ ,, ~D.\~1,l\ . ~--1re· :,~ -----=-~:-r-·· 1 ~--~9:"---": :!,RIJ!!!TA ,.-_;;.- ,. 1/ _u- r~vc: \. . ' J . ag '!. osal :..- -~-. ' ubsta~;· ~ , -' . 1/ •,:,' ._., I .-:~ fl. _.-_, -.. · :,'. . ,,' _..., ... - . / .... ;, , / ,• ,' ! , , , : : ! ' . ···--;~,; ' . . '! ~ ,' ,--.. ::,,,-,,, . ~ ;::i"V'-~-~ -!-'-. i ((2.Y:_J! r· _...,__.,,, 9l ,,..-, ,,re,, -_ _, ' -:,·}' ~ • ~"""!J.:C?.o ,,. ~---...=: /'-' I \ ,,--.:::::: -, ~ ,_.. =,----/'-: ! r •.......-7-'l ~ . 'o/~"-· r~,;:_,r,,,-...._ I ;.; \ / ( ( : • 1 •• UJ: .... ,,...:,'<.:~'4.. ·3,,_./ :;,/ 1 \ ,,-··,.,\ ( -_ / ,r-,~ "c:,t_ :z:~~§;;~~~~ ----------·, ,_/ 0 .~-.J'/ ',____ \ \,/i I .., ·••••A, I .----:::=too //. : ,' ·• rr .. • i\, J --r1 _ ,,.. 11 • • :Ebtne:r.er Ch ~(/ \ . "\./ .----" ,' I ) • .:I,•-., ,' ', •~::. ~ _ I .,.,,--:.,,,-•f-.'---/_pJP 7" ,; b -=--~: _-;-·----_:~_::::...,_----~. -~~ _,,. ·\\ -.---1; ----~ , _ l]1/{,::: I <,-(/}~~~j SOURCE: uses QUADRANGLE MAP, MOUNT HOLLY, N.C. CAA 3669 (18) JAN 10/94 (W) REV.O ont A ._ ;_ /'-/(! "') I r, __ ' -.~._; \\_; . 'I r-. . ,. ,,_. ,'V--I: ' -~,____....----,1 _-_; ,.~0/1 &l \ -~~ I. LAr,r£' I I figure 1.1 SITE LOCATION JADCO-HUGHES SITE Gaston County, NC I I I I I ' I I I I I I I I I a B I I 3669 (18) • approximately 6,000 c.y. of subsurface soil containing volatile organic compounds (VOes) and base/neutral and acid extractable compounds (BN As) and to a lesser extent, metals; • Site groundwater containing voes and BNAs; and • surface water in Tributary B containing voes. The SRA concluded that the groundwater and surface water pathways at the Site presented an unacceptable current and future risks to human health and to the environment. During the RI and FS, an Interim Remedial Measure (IRM) was completed between September and December 1990 which resulted in the excavation and disposal of PCB contaminated soils in the southeast swale area. Approximately 900 c.y. of soils were excavated and disposed of off-Site by landfilling at the Chemical Waste Management Inc. landfill in Emelle, Alabama. Upon completion of the RI and FS, USEPA issued a Record of Decision (ROD) on September 27, 1990. The final remedy selected by USEPA in the ROD and further described in the Scope of Work (SOW) requires the following actions: 1) Provision of deed and access restrictions; 2) Performance of soil and groundwater remedy treatability studies; 3) Further delineation of groundwater contamination by installing five additional groundwater monitoring wells and six piezometers; 4) Treatment of soils in the former landfill and approximately 500 c.y. of soil from the Former Operations Area which are to be consolidated into the former landfill. The soils shall be treated by a combination of soil vapor extraction (SVE) and soil flushing. The SVE system will be constructed and operated until data indicate that no further VOCs can 2 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I 9 D 0 I I I ' I I I I I 3669 (18) practicably be removed. The soil flushing system will be operated as an integral component of the groundwater collection and treatment system; 5) Construction of a groundwater extraction system within the Site boundaries including four extraction wells, in areas of elevated contaminant levels, a subsurface drainage tile trench to collect contaminated groundwater and a groundwater collection sump in the annulus of the slip-lined culvert to collect groundwater that is discharging to the culvert; 6) Construction of an on-Site treatment system. The system would consist of an equalization and aeration tank. The air vented from the aeration tank would be treated by carbon adsorption. The effluent from the treatment system would be pumped to a City of Mt. Holly sanitary sewer system manhole for subsequent treatment at the Mt. Holly publicly owned treatment works (POTW); 7) Excavation and repair of the damaged sections of the Site culvert followed by slip-lining of the culvert with butt-welded polyethylene pipe; 8) Construction of a gravity drainage line to carry uncontaminated groundwater from the spring discharge to the Tributary B north of the Former Operations Area; 9) Construction of a surface water diversion consisting of a Site spillway; 10) Provision of long-term operation and maintenance including monitoring of system controls; 11) Implementation of a monitoring program to assess the performance of groundwater extraction, aeration and discharge system components. Periodic monitoring of the groundwater will be performed to assure that the remedy is working; and 3 CONESTOCA-ROVERS & ASSOCIATES E m I u a I I I I , I I • u 'ft n D a I a I I 1 I I I u I I I I I I I I I I I I 3669 (18) 12) Tracking of analytical results to measure the efficiency /effectiveness of the remedy. Following issuance of the ROD by USEPA, the Steering Committee was issued with an administrative order under Section 106 of the Comprehensive Environmental Response, Compensation and Liability Act (Order) on June 19, 1991. Accompanying the Order was USEPA's Scope of Work (SOW) for the Remedial Design/Remedial Action (RD/RA) for the final remedy. The RD/RA schedule was revised according to USEPA's schedule which was provided in a March 20, 1992 RD letter. CRA has been retained to prepare the RD/RA Work Plans and perform associated design activities. In accordance with the SOW, pre-RD investigative activities were completed by CRA between April and June 1993 and included the following activities: • a geophysical survey in the northern portion of the Site to supplement the subsurface investigations that were completed during the Remedial Investigation (RI) in this Area and the RI's geophysical survey completed in the southern portion of the Site; • analyses of one round of groundwater samples from existing monitoring wells as part of the initiation of the groundwater monitoring program to verify RI data for the RD and to assess the impact of silts and sediments on metals concentrations in groundwater analyses; • the installation of five additional monitoring wells and six piezometers (Figure 1.2) to characterize groundwater chemistry and aquifer hydraulics and to establish the Site sentry groundwater monitoring system required by the USEPA's remedy for the Site (see Figure 1.2); • analyses of one round of groundwater samples from the new monitoring wells to characterize groundwater chemistry and aquifer hydraulics and to confirm the vertical extent of groundwater contamination; and 4 CONESTOGA-ROVERS & ASSOCIATES --- LOCATED ON CAROUNA CUSTOM CABINETS PROPERTY CAA - -- ellWGS el'Z•S PROPERTY LINE SHALLOW MONITORING 'M:Ll DEEP MONITORING Wfll LOCATION SHALLOW P1£ZOU[l[R DEEP Pl[ZOMETER PUMPING WELL - I I I I I I I I ) \ ;,' I I J669 (18) JAN 2B/94(W) R[V.O (P-55) I!!!!!! ,!!!!9 == TEXTILE SALES AND REPAIR PROPERTY MW1J(l WW1J5 • aa 0 50 IOO!l H I MONITORING WELL AND iiiii \ STARNES PROPERTY figure 1.2 PIEZOMETER LOCATIONS JADCO-HUGHES SITE Gaston County, NC - I D D I I I I I I I I I I ' I I I I I 31i69 (18} • performance of a groundwater treatability study and a soil vapor extraction (SVE) pilot study. RD is defined as those activities required to prepare the final plans and specifications, general provisions and specific requirements necessary to translate the ROD and SOW into the remedy to be constructed under the RA phase. RA is the implementation phase of site remediation or the actual construction of the remedy, including necessary operation and maintenance and performance monitoring. The RA is based on the RD to achieve the remediation goals specified in the ROD. The first task associated with the RD /RA for the Site was the completion of a Site visit and scoping session. This scoping session was held on August 29, 1991 and documented by CRA in the August 1991 progress report to USEPA dated September 5, 1991. No substantive modifications to the RD/RA resulted from this scoping session. The second task associated with the RD/RA for the Site was the preparation and submittal of a RD Work Plan. The RD Work Plan, consisting of the RD Work Plan, the Sampling and Analyses Plan, the Treatability Study Work Plan and the Health and Safety Plan was submitted to USEPA on September 30, 1991. The RD Work Plan was formally approved in its entirety by USEPA on April 7, 1993. The third task associated with the RD/RA for the Site was the preparation and submittal of a Preliminary Design Report reflecting the design effort at 30 percent completion. The Preliminary Design Report was based on pre-design activities which were conducted at the Site between April and June 1993, as described above. The Preliminary Design Report, documenting the results of the pre-design activities, treatability studies, and the RD at the 30 percent design phase was submitted to USEPA on August 5, 1993. USEPA commented on the Preliminary Design Report in a letter dated October 15, 1993 which was received by CRA on October 28, 1993. The Steering Committee responded to USEPA's comments in a letter dated November 29, 1993. USEPA has not submitted its responses to the Steering Committee's November 29, 1993 letter. 5 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I a u D u 3669 (18) The RA Work Plan, as presented herein, is submitted to USEPA as the fourth task associated with the RD/RA for the Site. The RA Work Plan presents the implementation, management and sequencing of the remedial construction activities required to implement the RD for the Site as presented in the Prefinal Design Report. The scheduled submission date for the RA Work Plan is January 31, 1994. The fifth task associated with the RD /RA for the Site is the preparation and submittal of a Remediation Goal Verification Plan. The Remediation Goal Verification Plan is a separate document which will be submitted under separate cover to USEPA concurrent with this report as required by the SOW. The scheduled submission date for the Remediation Goal Verification Plan is January 31, 1994. The sixth task associated with the RD/RA for the Site will be the preparation and submittal of a Prefinal Design Report reflecting the design effort at 90 percent completion. The scheduled submission date for the Prefinal Design Report is February 28, 1994. The seventh task associated with the RD/RA for the Site will be the preparation and submittal of an Operation and Maintenance Plan (O&M Plan). The O&M Plan will be submitted concurrently with the Prefinal Design Report. The eighth task associated with the RD/RA for the Site will be the preparation and submittal of a Final Design Report reflecting the design effort at 100 percent completion. The Final Design Report is scheduled to be submitted to USEPA on April 29, 1994. The above due dates are based upon a schedule proposed in the November 29, 1993 letter to USEPA. This schedule will be dependent upon USEP A approval of the schedule .and time-frames for USEP A approval of the submittals. 6 CONESTOGA-ROVERS & ASSOCIATES I I I I I g D u I I I I I I I I I I I 3669 (18) The remaining tasks associated with the RD/RA for the Site include: the construction of the remedy; the inspection of the completed construction by USEPA; the preparation and submission of the Remedial Action Report; and the Operation and Maintenance Manual; and the long-term operation, maintenance and monitoring of the remedy. 1.2 ORGANIZATION OF REPORT This includes each of the required elements as outlined in the SOW. The SOW states that this RA Work Plan must include the following elements: a. A detailed description of the tasks to be performed and a description of the work products to be submitted to EPA. This includes the deliverances set forth in the remainder of Task Ill. b. A schedule for completion of each required activity and submission of each deliverable required by this Consent Decree, including those in this SOW. c. A project management plan, including monthly reports to EPA and meetings and presentations to EPA at the conclusion of each major phase of the RA. d. A description of the community relations support activities to be conducted during the RA. At EPA 's request, it is expected that the Settling Defendants will assist EPA in preparing and disseminating information to the public regarding the RA work to be performed. e. A description of Settling Defendants' (sic) strategy for delivering the project. This description shall focus on the management approach to carry out the design and implement the Remedial Action. Items to be addressed include procurement method and contracting strategy, phasing alternatives, and contractor and equipment availability concerns. If the construction of the selected remedy is to be 7 C0NESTOCA-R0VERS & AsS0OATES I I I I I g u I I E I I I I I I I I I Jl,l,908) accomplished by Settling Defendants' "in-house" resources, these resources shall be identified. These require men ts are addressed by the major sections and Appendices of this RA Work Plan as follows: • Section 1.0 -a general introduction to the Site project; • Section 2.0 -a description of the existing conditions at the Site; • Section 3.0 the access agreements for the Site; • Section 4.0 -the Heath and Safety Plan; • Section 5.0 -the Site management and sequencing; • Section 6.0 -the Work Plan for the spillway construction, culvert lining and drainage line construction; • Section 7.0 -the Work Plan for the construction and implementation of the Groundwater Extraction System component of the RA; • Section 8.0 -the Work Plan for the construction and implementation of the Groundwater Treatment System construction; • Section 9.0 -the Work Plan for the construction and implementation of the SVE system; • Section 10.0 -the Work Plan for the construction and future implementation of the soil flushing system; • Section 11. 0 the Long-Term Operation, Maintenance and Monitoring Plan; • Section 12.0 -reports and documentation to be submitted; • Section 13.0 -the project closeout methodology; • Section 14.0 -activities to be undertaken to provide community relations support; • Section 15.0 -the RA schedule of activities; • Section 16.0 -the Construction Management Plan; • Appendix A -the access agreements related to the Site; • Appendix B -the Construction Health and Safety Plan for the Site; • Appendix C -the Construction Quality Assurance Plan for the Site; and • Appendix D -the Curricula Vitae for the assigned project personnel. 8 CONESTOCA·ROVERS & ASSOCIATES I I I I I 0 I I I I I I I I I I I I I 3669 (18) 1.3 PROPOSED REMEDIAL ACTION The SOW delineates and describes in detail the RA to be implemented at the Site. The major components of the RA to be implemented at the Site consist of the following: 1) Excavation and repair of the damaged sections of the Site culvert followed by slip-lining of the culvert with butt-welded polyethylene pipe, construction of a gravity drainage line to carry uncontaminated groundwater from the spring discharge to the Tributary B north of the Former Operations Area and construction of a surface water diversion consisting of a Site spillway. 2) Construction of a groundwater extraction system within the Site boundaries including four extraction wells, in areas of elevated contaminant levels, a subsurface drainage tile trench to collect contaminated groundwater and a groundwater collection sump in the annulus of the slip-lined culvert to collect groundwater that is presently discharging to the culvert; 3) Construction of an on-Site treatment system. The system shall consist of an equalization and aeration tank. The air vented from the aeration tank will be treated by carbon adsorption. The effluent from the treatment system will be pumped to the City of Mt. Holly sanitary sewer system manhole for subsequent treatment at the publicly owned treatment works (POTW); 4) Treatment of soils in the former landfill and approximately 500 c.y. of soil from the Former Operations Area which are to be consolidated into the former landfill; and 5) Construction of a soil flushing system utilizing some of the components of the SVE system and installing a soil flushing collection trench for future operation. This SVE system construction includes the consolidation of surplus excavated soils from the groundwater 9 CONESTOGA-ROVERS & ASSOCIATES I I I I I m D B I I I I I I I I I I I 3669 (18) extraction system and treatment facility construction into a soil cap on the surface of the former landfill. 1.4 PROTECT ORGANIZATION CRA is the primary consultant to the Jadco-Hughes Steering Committee for the RD portion of the RD/RA and will be performing the construction management during the implementation of the RA. Additional subcontractors will be selected to perform specific tasks during the RA phase of the RD/RA. Project organization charts for the remedial construction activities are provided in the Quality Assurance Project Plans for construction activities, presented in Appendix C, for each phase of the remedial construction. 1.5 BASIS FOR REMEDIAL CONSTRUCTION The remedial construction for the RA selected for the Site is based on the provisions of the SOW and the design for the RA of the Site as presented in the Prefinal Design Report. 10 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I 2.0 3669 {18) EXISTING CONDITIONS The Jadco-Hughes Site is located between the Catawaba River and the South Fork at the Catawaba River in a region known as the Piedmont physiographic province in Gaston County. The region is primarily rolling uplands although the county's western area contains some northeast trending ridges. The Site itself is flat, sloping slightly from south to north. The southern elevation is approximately 666 feet above mean sea level (AMSL) and the northern is approximately 653 feet AMSL. The Site is located in an unincorporated area between the cities of Belmont and Mt. Holly. The aerial photographs indicate that the Site was farmland until the late 1960s and was subsequently used for a solvent reclamation and waste storage facility until 1975. The Site shows little evidence of past Site operation. The majority of the 6-acre Site is revegetated. The southern and eastern boundaries are treed. Remnants of the facility include: a fence (now replaced with an 8-foot high barbed wire perimeter fence), a truck unloading area, a concrete pad, culvert and building remnants. Land to the south and east of the Site is wooded and undisturbed. The eastern area adjacent to the Site is sloped steeply upwards (to the east). Land to the west of the Site is utilized for industrial purposes. There is a former wood products plant to the southwest of the Site and a textile machinery supply warehouse opposite the Site. The area to the north of the Site is utilized for private residences. A machine shop and automobile service center/wrecking yard are also located among the residences. 11 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I 0 0 D D u I I 3669 (18) Drainage from the Site flows to tributaries of Fites Creek and ultimately to the Catawaba River approximately 2.5 miles downstream. Figure 2.1 illustrates the drainage pattern of the Site and downstream watercourses. The Site is predominantly underlain by a unit of weathered granite known as saprolite to a depth of 95 feet below ground surface. Lenses of fluvial deposits of clay, silt and sand lie upon this unit near ground surface. Granite bedrock underlies the saprolite and is found at depths below 95 feet. Figure 2.2 illustrates the geology underlying the Site by means of Cross-section A-A' which transects the Site. The section location is shown on Figure 2.1. A water table is found at a depth of approximately 9 feet below ground surface. Groundwater within the saprolite migrates north at a rate of approximately 8 to 14 feet/year and is strongly influenced by groundwater discharge into the on-Site culvert and tributaries to Fites Creek. Figure 2.3 presents the groundwater flow patterns in the shallow saprolite (approximately 15 feet below ground surface). Figure 2.4 presents the groundwater flow patterns in the deep saprolite (approximately 45 fee~ below ground surface). These groundwater contours are based on data collected during the hydraulic monitoring round in May 1993 and are similar to the contours presented in the RI. The Site is fenced with an 8-foot high chain link and barbed wire fence. This fence was installed in 1990 as part of a soil removal program completed by the Steering Committee. Contamination profiles for on-Site groundwater and soil are presented in Section 3.1.2 of the Preliminary Design Report (CRA, August 1993) and in Appendix B, Section B.2.0. 12 CONESTOGA-ROVERS & ASSOCIATES I!!!!! CRA I!!!!!! 1!!119 ----- -PROP(RTY LINE GROUND CONTOUR (fl. Al.ISi..) SURF ACE WATER ORAi NAG[ A·1 r CROSS-SECTION LOCATION J669 (18) JAN 28/94(W) REV.O (P-56) == == == r,;;;a liiiiiiiil lillil 0 50 \0011 I U I 1, / l !!!!! l!l!!!!I l!l!!!!I l!!l!li!iS -= == A " > 660.0 (16.}Sll.f 670.0 (Sll)SANO 660.0 -·-·- ai > < g_ 650.0 z 0 =" ~ ~ 640.0 """'"' 630.0 620.0 == == == -----·----- SAPROUTE UNIT w z 3 (ML}SILf {JJl}SJt..1 l)J.111 -Ciiiiiil w . ~ ... ~ ~~ I-!;. :::.::i; mo ,,,,,,._ liliii -.. ~-· ~~~~ - I .... 610.ol..------.----------.-----,------,----- 1 -.------,,~,~,,~,-~, O JOO 600 900 1200 1500 HORIZONTAL OIST.WCE (FEET) (!>6.HO} illllill. CRA 3669 (18) JAN 10/94(W) R(V.O (X-08) GROUND SURF AC( STRATIGRAPHIC DESCRIPTION STATIC WATER l£"'1:L (9/18/89) UONITORlNG v.fil SCREEN LOCATION GEOLOGIC 1800 figure 2.2 CROSS-SECTION A-A' JADCO-HUGHES SITE Goston County, NC !!!!!I l!!!!!I !!!!!I !!l!!!!I l!!!!l!I !!!!!I •"'""s .Pl9S =;> ---650 {"6.91) f=) CAA PROPERTY LINE SHALLOW MONITORING WEU SHALLOW PIEZOI.IETER CROUNOWA T£R FLOW DIRECTION GROUNDWATER CONTOUR (FT. AMSl) CROUNOWA T(R ELEVATION (A.PR1l lO, WA T(R l[\l[L NOT l.l[ASURED I I J669 (18) JAN 28/9~{W) R[V.O {P-57) 1993) == == == == == 0 50 100H H I figure 2.3 SHALLOW GROUNDWATER FLOW PATTERNS JADCO-HUGHES SITE Gaston County. NC iiiiil liiil PROPERTY UN[ • "'""° O[(P IJONITOO!NG WELL e Pl9'i DEEP PIEZOl.l[T(R -'-Pwi PUMPING WELL c=:::;>-CROUNOWAT(R fLOW OIR[CTION ----650 GROUNDWATER CONTOUR (fT. AIJSL) {6!16.Xt) GROUNDWATER ELEVATION (APRIL JO, 1993) (NJ,/) WATER LEVEL NOT IJ[ASUREO I I I I I I I I liiiii J \ :j__ ___ _ ________ .,__·~-------------~ __ cr.s·o.v stNi (r.11.&I) -·~ ""' CRA I I .J669 (18) JAN 28/94(W) R[V.O {P-58) -liiiii liiii liiiiiia liiliiiia 0 50 H DEEP liiiia liiiia !OOH I \ figure 2.4 GROUNDWATER FLOW PATTERNS JADCO-HUGHES SITE Goston County, NC - I I I I I I I I I I I I 3.0 3669 (18) ACCESS AGREEMENTS AND PERMITTING REQUIREMENTS Implementation of the RA for the Site requires access onto adjacent properties and obtaining various State, Federal and County Permits. Access agreements have been obtained for implementation of the pre-design activities, and for implementation of the RA on the properties adjacent to the south, east, west and north borders of the Site. These access agreements have been submitted to USEPA under separate cover and are included in Appendix A. The Jadco-Hughes Site is a CERCLA Site and, thus, is not required to obtain permits for activities conducted at the Site. In preparation for the RA, the Steering Committee has developed a list of permit programs for which the substantive requirements are to be identified and met by the RA. These permit programs are listed below: 1. SVE An air discharge permit application is to be filed to the State of North Carolina for the SVE system discharge. The State has advised CRA that no permit is required for this remediation system since the pilot study provided a favorable evaluation of the SVE system and the best available control technology will be utilized. However, the State (Keith Overcash, Air Quality Section) requested in a letter to CRA dated May 13, 1993 that the SVE system be registered with the Division of Environmental Management, Mooresville Regional Office by sending the following information: • location of the Site; • type and quantity of compounds expected to be emitted to the ambient air; • brief description of the remediation system components; and 13 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I • I I I I 3669 (18) • duration of time that the remediation system is expected to be operated. 2. Groundwater Extraction 3. 4. Extraction well permit applications will be filed for the groundwater extraction system pursuant to State requirements. POTW Discharge A discharge permit will be obtained from the City of Mt. Holly in early 1994. This permit will have specific discharge limits for the Site. The Jadco-Hughes Steering Committee completed its negotiations with the City and an agreement which will lead to the issuance of a sewer discharge permit was executed in-December 1993. Sediment and Erosion Control The State requires that a permit be obtained when any construction occurs on an area which exceeds one acre. The substantive requirements outlined in the North Carolina Erosion Control Design Manual will be incorporated in a Sediment and Erosion Control Plan to be provided in the Final Design. This plan will document site features and control measures to be implemented during construction and in the long-term to prevent erosion of soil and associated sediment migration. 5. Miscellaneous Permit Requirements Miscellaneous permit requirements include building permits and electric utility permits. The Steering Committee will assign the responsibility of obtaining these miscellaneous permits to the selected RA Contractor(s). 14 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I 4.0 3669 (18) CONSTRUCTION HEAL TH AND SAFETY PLAN A Construction Health and Safety Plan (HASP) is required to ensure that all remedial construction activities are performed safely and in accordance with applicable regulatory requirements, and that all persons on Site, the general public and the environment are protected from exposure to Site-related contaminated material during implementation of the remedial construction activities at the Site. A HASP has been developed for the remedial construction activities associated with the RA for the Site and is presented in Appendix B. Each employer involved in remedial construction activities at the Site will be required to develop and implement their own Site-specific HASP for activities they will perform at the Site. The HASP included in Appendix B will form the basis and minimum requirements for each employer's Site-specific HASP. The remedial contractors will prepare and submit a HASP to CRA before commencing work at the Site which could potentially result in contact with contaminated materials. CRA will review the HASP with respect to its consistency with Appendix B and the Contract requirements and approve the HASP prior to its implementation. CRA will also receive and review requisite training and medical surveillance documentation for contractor employees. 15 CONESTOGA-ROVERS & ASSOCIATES D D I I 0 u I D I I I I I I I I I I 5.0 3669 (18) SITE MANAGEMENT AND SEQUENCING The five components of the remedial construction at the . Site are described in Section 1.0 and are generally described as follows: 1) culvert replacement/ spillway construction. 2) groundwater extraction system; 3) groundwater treatment system; 4) SVE system; and 5) soil flushing system. Management of the Site during implementation of the remedial construction will be required to ensure that the Site operates in an orderly, efficient and safe manner, and to ensure that the remedial construction is successfully implemented in accordance with the RD. The tasks to complete the five components of the remedial construction have been sequenced to meet the following major objectives: i) ii) iii) iv) tasks should be performed in an orderly and safe manner such that the movement and double handling of materials and the exposure of personnel and the public to Site-related contaminants is minimized; tasks should be scheduled such that movement of contaminated materials over clean areas is avoided or minimized, and sequencing of tasks should result in the exclusion zone diminishing in size as the RA is implemented; tasks should be performed to encourage stormwater percolation. This would serve the dual purpose of preventing potentially contaminated run-off from leaving the Site and promoting the flushing of residual contaminants from the soil to the groundwater collection system; and upon completion of grading and excavation activities, the contractor should perform the work under conditions not requiring air monitoring or decontamination activities such that 40-hour OSHA trained workers are not required for construction activities. 16 CONESTOGA·ROVERS & ASSOCIATES I I I I I I I I I I It I I I I I I I I 3669 (18) Sequencing of the remedial construction tasks is presented in Sections 6.0 to 11.0. 5.1 REMEDIAL ACTION CONTRACTOR SELECTION A remedial contractors will be selected by a competitive bidding process. Bids will be solicited from qualified remedial contractors for performance of the remedial construction and for the installation of extraction wells. A contract reflecting the requirements of the RA Work Plan, the Final Design Report, the SOW and standard contract administration requirements will be entered into by the Steering Committee and the successful remedial contractor(s). The first activity to be completed by the selected remedial contractor is the preparation and submission (to CRA) of a Site-specific HASP for the work to be completed at the Site. The discussion of the sequencing of activities in Sections 6:0 through 10.0, below, do not include this task as a separate activity, since it will be completed at the start of construction for all phases of the work. All contractors retained by the Steering Committee will be required to prepare and submit a HASP before commencing work involving the excavation or handling of soils at the Site. 5.2 SITE MANAGEMENT Site activities related to the remedial construction will be supervised by a qualified engineer. Daily logs will be maintained for all activities occurring at the Site during remedial construction activities. Besides daily monitoring of the remedial construction activities, weekly progress meetings will be conducted with the remedial contractor(s) and monthly progress meetings will be conducted during the pedod of active construction with the remedial contractor(s), the Steering Committee and 17 CONESTOGA-ROVERS & ASSOCIATES I I I I I • I I I I I I I I ,, I I I I 3669 (18) USEPA. Details of Site management during implementation of the remedial construction activities are presented in Appendix C. 18 CONESTOGA-ROVERS & ASSOCIATES I I I I I I 6.0 3669 (18) SPILLWAY. CULVERT AND DRAINAGE LINE 6.1 STATEMENT OF WORK The first component of the RA to be implemented at the Site is the construction of the spillway and drainage line, lining of the existing on-Site culvert, and associated activities. These items are expected to be completed within 135 days of USEPA approval of the RA Work Plan or Final Design Report, whichever is later. Installation of the spillway and drainage line and culvert lining consists of the following activities: i) mobilization of labor, materials and equipment to the Site; ii) clearing, grubbing and grading of soil to create clean, level areas for the location of temporary Site offices, support facilities and parking during the implementation of the RA; iii) placing of granular material on access roads and on temporary parking area; iv) installation of temporary support facilities (Site offices, support trailers, toilet facilities, etc.); v) construction of a vehicle decontamination facility and installation of a personnel hygiene facility; vi) excavation of clean on-Site soils or importation of clean fill and the construction of earthen berms along the southeastern perimeter of the Site and the eastern foot of the landfill slope; vii) excavation to expose the damaged portion of the culvert, cleaning of the culvert, reparation of the damaged section of the culvert, backfilling of the repaired section of the culvert, and installation of the slip lining; 19 CONESTOGA-ROVERS & ASSOCIATES I I I I I It I Ii ii I I ' I ' I, I I ,, I 3669 (18) viii) construction of a precast concrete chamber at the north end of the culvert, blockage of the concrete culvert on the downstream side of the chamber, and installation of a sump pump; and ix) excavation, placing and backfilling of the drainage line on the southeast portion of the property, including precast concrete manholes. The design drawings for the spillage, culvert and drainage line will be presented in the Final Design Report. 6.2 CONSTRUCTION SPECIFICATIONS AND ORA WINGS Construction specifications for the implementation of the spillway, culvert and drainage line component of the RA at the Site and associated drawings will be presented in the Final Design Report. 6.3 CONSTRUCTION QUALITY ASSURANCE PLAN The Construction Quality Assurance Plan (CQAP) for the spillway, culvert and drainage line component of the RA is provided in Appendix C. Where applicable, the requirements of the CQAP have been incorporated into the construction specifications, provided in the Final Design Report. 6.4 IMPLEMENTATION AND SEQUENCING 6.4.1 Site Preparation Prior to commencing remedial construction activities at the Site, the Site will be cleared, grubbed and graded as required in the areas of the Site offices, support facilities and parking. A 6-inch layer of granular 20 CONESTOGA-ROVERS & ASSOCIATES I I ,, I ' rt ' I ,, I I ' I' i I I ' I I 3669 08) material will be distributed over the parking area and a 12-inch layer of granular material will be placed on the access roads. Site offices and support facilities will then be installed, including power and telephone hookups. Temporary piping will be installed from a potable water tank (supplied by the RA Contractor) or a temporary connection to municipal water supply to the Site offices and personnel decontamination facility. Sanitary solid waste will be placed in a dumpster near the support facilities. The RA Contractor will arrange for periodic disposal of these wastes. 6.4.2 Construction of Spillway, Culvert Lining and Construction of Drainage Line The construction of the spillway, the culvert lining, and the construction of the drainage line will then commence as shown on the construction drawings which will be detailed in the Final Design Report. 6.4.3 Construction Closeout Upon completion of the activities associated with the construction of the spillway and drainage line and the lining of the culvert, associated construction equipment not required for subsequent construction activities, will be decontaminated and then removed from the Site. Support facilities, structures and temporary controls (i.e. temporary fencing, sediment controls) are expected to remain in place. 6.5 SCHEDULE OF ACTIVITIES The schedule of activities for the implementation of the spillway, culvert and drainage line component of the RA activities at the Site is presented in Section 15.0 (activity No. 5). 21 CONESTOCA-ROVERS & ASSOCIATES I I ,, ' I ,, I I I I I ' I /I I I I I ,,, 3669 (18) This schedule is approximate and is dependent upon contractor availability, equipment availability and delays due to the weather, This schedule is to be used for construction planning purposes only, 22 CONESTOGA-ROVERS & ASSOCIATES I I I I I ,, ,, I I I I I I I I I I I 1- 7.0 3669 08) GROUNDWATER EXTRACTION SYSTEM 7.1 STATEMENT OF WORK The second component of the RA to be implemented at the Site is the construction and commissioning of a groundwater extraction system at the Site, and associated activities. The groundwater extraction systems will also be completed concurrently with the construction of the Site spillway and culvert repairs and with the construction of portions of the groundwater treatment system. The groundwater extraction system is expected to be completed within 180 days of USEPA approval of the RA Work Plan or the Final Design Report, whichever is later. Installation of the groundwater extraction system consists of the following activities: i) mobilization of labor, materials, equipment and temporary support facilities to the Site; ii) iii) iv) v) vi) clearing, grubbing and regrading along the alignment of the proposed tile drain and pipeline areas to create a level work area; installation of sump manhole in the northwestern corner of the Site, including sump pump and pipeline connection to the treatment facility; excavation, placing and backfilling with granular material in the tile drain alignment, equipped with intermediate and terminal manholes at all changes of pipe line and grade and spaced no greater than 250 feet; excavation, placing and backfilling of yard piping and/or carrier pipes which will connect the extraction wells and extraction drain sump to the treatment facility, equipped with intermediate and terminal precast concrete chambers; installation of control and power conduits; 23 CONESTOGA-ROVERS & ASSOOATES I I I ' I I I I I I ' t I ·u D I I I I 3669 (18) vii) installation of the extraction wells and access manhole mechanical and electrical components; and viii) commissioning the entire groundwater extraction system. The design for the groundwater extraction system will be presented in the Final Design Report. 7.2 CONSTRUCTION SPECIFICATIONS AND DRAWINGS Construction specifications for the implementation of the groundwater extraction system component of the RA at the Site will be presented in the Final Design Report. 7.3 CONSTRUCTION QUALITY ASSURANCE PLAN The CQAP for the installation of the groundwater extraction system component of the RA, is provided in Appendix C. Where applicable, the requirements of the CQAP have been incorporated into the construction specifications provided in the Final Design Report. 7.4 IMPLEMENTATION AND SEQUENCING 7.4.1 Site Preparation The Site will be prepared as discussed in Section 6.4.1. 7.4.2 Installation of Extraction Wells, Tile Drain and Pipeline Construction of the.pipeline, tile drain, manholes, sump manhole, conduits, power and control wiring to the groundwater treatment 24 CONESTOCA·ROVERS & ASSOCIATES I I I u c- /8 I fi ' I ~- I I I I I I 8 B I I 3669 (15) buildings and access road for the groundwater extraction systems will be completed to final grade as shown on the construction drawings which will be provided in the Final Design Report. Extraction wells adjacent to the pipeline manholes, mechanical and electrical components for each extraction well, and the discharge pipeline from each extraction well to the nearest pipeline manhole will be installed as shown on the construction drawings in the Final Design Report. 7,4,3 Construction Closeout Upon completion of the construction activities associated with the installation of the groundwater extraction system, construction equipment and support facilities not necessary for subsequent construction activities will be removed from the Site, Support facilities, structures and temporary controls are expected to remain in place, 7.5 SCHEDULE OF ACTIVITIES The schedule of activities for the implementation of the groundwater extraction system component of the RA activities at the Site is presented in Section 15,0 (activity No. 6). The commissioning of groundwater extraction system will occur after completion of the groundwater treatment system construction. This schedule is approximate and is dependent upon contractor availability, equipment availability and delays due to the weather. This schedule is to be used for construction planning purposes only. 25 CONESTOGA-ROVERS & ASSOCIATES B I I I ' I I I - I I I I 8 B I I 8.0 GROUNDWATER TREATMENT SYSTEM 8.1 ST A TEMENT OF WORK The third component of the RA to be implemented at the Site is the construction and commissioning of a groundwater treatment system at the Site, and associated activities. The construction and commissioning of the groundwater treatment system is expected to be completed within 250 days of USEPA approval of the Final Design Report or the RA Work Plan, whichever is later. The construction of the groundwater treatment system component of the RA consists of the following activities: i) mobilization of labor, materials, equipment and temporary support facilities to the Site; ii) clearing, grubbing and regrading of work area; iii) excavation and installation of foundations for the groundwater treatment building; iv) construction of the groundwater treatment building; v) installation and commissioning of utilities to the groundwater treatment building; vi) installation of the groundwater treatment system equipment and controls; vii) construction of the groundwater treatment facility discharge pipe; and viii) commissioning the groundwater treatment system. The design for the groundwater treatment system will be presented in the Final Design Report. C0NESTOCA-R0VERS & ASS0OATES I I I ·., 11 ' I I I ' I ' I I I I I I .,. I I I Jl,69 08) 8.2 CONSTRUCTION SPECIFICATIONS AND ORA WINGS Construction specifications for the implementation of the groundwater treatment component of the RA at the Site will be presented in the Final Design Report. 8.3 CONSTRUCTION QUALITY ASSURANCE PLAN The CQAP for the installation of the groundwater treatment system component of the RA, is provided in Appendix C. Where applicable, the requirements of the CQAP have been incorporated into the construction specifications provided in the Final Design Report. 8.4 IMPLEMENTATION AND SEQUENCING 8.4.1 Site Preparation The Site will be prepared as discussed in Section 6.4.1. 8.4.2 Construction and Commissioning of the Groundwater Treatment System The construction of the groundwater treatment building and system will then commence, including the construction of the discharge pipeline, as shown on the construction drawings which will be provided in the Final Design Report. The groundwater treatment system will then be commissioned as detailed in the Draft Operation and Maintenance Plan referenced in Section 11.0. 27 CONESTOGA-ROVERS & AsSOOATES 0 I I I I •• I 1· I I t I ff m I I I I I I 3669 OS) 8.4.3 Construction Closeout Upon completion of the activities associated with the construction of groundwater treatment facility, construction equipment and support facilities not necessary for subsequent construction activities will be removed from the Site. Support facilities, structures and temporary controls are expected to remain in place . 8.5 SCHEDULE OF ACTIVITIES The schedule of activ_ities for the implementation of the groundwater treatment component of the RA activities at the Site is presented in Section 15.0 (activity No. 7). This schedule is approximate and is dependent upon contractor availability, equipment availability and delays due to the weather. This schedule is to be used for construction planning purposes only. 28 CONESTOGA-ROVERS & ASSOOATES I I I m R 0 I I ' I I I I 9.0 3669 (18) SOIL VAPOR EXTRACTION SYSTEM 9.1 STATEMENT OF WORK The fourth component of the RA to be implemented at the Site is the construction and commissioning of the SVE system at the Site, and associated activities. The SVE system construction and commissioning are expected to be completed within 250 days after USEP A approval of the RA Work Plan or the Final Design Report, whichever is later. Implementation of the SVE system component of the RA consists of the following activities: i) ii) iii) mobilization of labor, materials, equipment and temporary support facilities to the Site; set up of the SVE treatment system and associated work, including installation of the soil vapor extraction trenches and construction of the vapor phase treatment system; installation of a soil cap over the former landfill; and iv) SVE system commissioning. The final design for SVE is presented in the Final Design Report. 9.2 CONSTRUCTION SPECIFICATIONS AND DRAWINGS Construction specifications for the implementation of the SVE system component of the RA at the Site will be presented in the Final Design Report. 29 CONESTOGA-ROVERS & ASSOCIATES I u u a m I 11 I I I I :1 I I I I I I I Jl,69 08) 9.3 CONSTRUCTION QUALITY ASSURANCE PLAN The CQAP for the installation and construction of the SVE system component of the RA, is provided in Appendix C. 9.4 IMPLEMENTATION AND SEQUENCING 9.4.1 Site Preparation The Site will be prepared as discussed in Section 6.4.1. 9.4.2 SVE Trenches and Pipeline Construction of the pipeline, extraction trench, conduits, power and control wiring to the SVE treatment equipment will be completed as shown on the construction drawings in the Final Design Report. 9.4.3 Construction and Commissioning of the SVE Treatment System The construction of' the SVE treatment system will then commence as shown on the construction drawings in the Final Design Report. The SVE treatment system will be commissioned as referenced in the Draft Operation and Maintenance Plan presented in Section 11.0. 9.4.4 Construction Closeout Upon completion of the construction activities associated with the installation of the SVE collection system and construction of the SVE treatment facility, associated construction equipment not required for subsequent construction activities will be removed from the Site. Support facilities, structures and temporary controls are expected to remain in place. 30 CONESTOGA-ROVERS & Asso□ATES I R u n 8 0 u: 8 I u I I a a I • I I I 3669 08) 9.5 SCHEDULE OF ACTIVITIES The schedule of activities for the construction and implementation of the SVE system component of the RA activities at the Site is presented in Section 15.0 (activity No. 9). This schedule is approximate and is dependent upon contractor availability, equipment availability and delays due to the weather. This schedule is to be used for construction planning purposes only. 31 CONESTOGA-ROVERS & ASSOOATES a u I 1 I I I I I I I I I I I I I 10.0 SOIL FLUSHING SYSTEM 3669 (18) 10.1 STATEMENT OF WORK The fifth component of the RA to be implemented at the Site is the soil flushing system. The soil flushing system will be constructed during the RA but will not be commissioned until the SVE system operation is terminated. The components of the soil flushing system may require modification after the termination of the SVE system operation. These modifications may be necessary in order to address conditions which may have changed since the installation of the soil flushing system (i.e. settlement). The soil flushing system construction will be completed concurrently with the SVE system installation, which is expected to be completed within 225 days after USEPA approval of the RA Work Plan or the Final Design Report, whichever is later. Implementation of the soil flushing system component of the RA consists of the following activities: i) ii) mobilization of labor, materials, equipment and temporary support facilities to the Site; and installation of the soil flushing collection trench and associated piping and equipment to the groundwater treatment facility for future operation. The final design of the soil flushing system is presented in the Final Design Report, however, full operation will only be completed after operation of the SVE system is terminated. 10.2 CONSTRUCTION SPECIFICATIONS AND ORA WINGS Construction specifications for the implementation of the soil flushing component of the RA at the Site will be presented in the Final Design Report. 32 C0NESTOCA-R0VERS & AsS0OATES I I I I fl u I I D n D I I 8 ff u u 0 0 3669 (18) 10.3 CONSTRUCTION QUALITY ASSURANCE PLAN The CQAP for the soil flushing component of the RA, is provided in Appendix C. 10.4 IMPLEMENTATION AND SEQUENCING 10.4.1 Site Preparation The Site will be prepared as discussed in Section 6.4.1. 10.4.2 Soil Flushing Extraction Trench, Pipeline and Infiltration Galleries Installation of the soil flushing extraction trench, pipeline, conduits, power and control wiring to the groundwater treatment building will be completed as shown on the construction drawings in the Final Design Report. Modifications to the SVE system which will be used in the soil flushing system will be completed after shut-off of the SVE system, as shown in the Final Design Report. 10.4.3 Commissioning of the Soil Flushing System The operation of the soil flushing system will commence after operation of the SVE system is terminated as determined in accordance with the Remediation Goal Verification Plan. The soil flushing system will be described as referenced in the Draft Operations and Maintenance Plan presented in Section 11.0. 33 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I 1 I I I I I I I 3669 (18) 10.4.4 Construction Closeout Upon completion of the construction activities associated with the installation of the soil flushing system, all construction equipment and support facilities, including Site offices and temporary controls, will be removed from the Site. 10.4.5 Schedule of Activities The schedule of activities for the construction and implementation of the soil flushing system component of the RA activities at the Site is presented in Section 15.0 (activity No. 10). This schedule is approximate and is dependent upon contractor availability, equipment availability and delays due to the weather. This schedule is to be used for construc~ion planning purposes only. 34 CONESTOGA-ROVERS & ASSOCIATES I R u u I u I I E I I I I 'I I I I I 11.0 OPERATION AND MAINTENANCE PLAN 3669 08) As required by the SOW, an Operation and Maintenance Plan (O&M Plan) for the remedial components will be developed and will be submitted as outlined (activity No. 8) in the RA Schedule (Section 15.0). The O&M Plan will be consistent with the requirements of the SOW and will include the following: i) equipment startup and operator training; ii) description of normal operation and maintenance; iii) description of potential problems; iv) description of routine monitoring and laboratory testing of treatment systems; v) description of alternate O&M; vi) health and safety plan; vii) description of equipment; and viii) records of reporting. 35 CONESTOGA-ROVERS & ASSOCIATES I 0 u I • I I I I I I I I I ,, I I I I 12.0 PROJECT DOCUMENTATION AND REPORTING 3669 (18) As required by the SOW, monthly reports will be submitted to USEPA. Meetings with USEPA will be held at USEPA's request at the conclusion of each phase of the RA and in accordance with the Construction Quality Assurance Plan (CQAP-Appendix C) . 36 CONESTOGA-ROVERS & ASSOCIATES I R I I I I I I I I I I I I I I I I 13.0 PROTECT CLOSEOUT 3669 08) On completion of the remedial construction as detailed in Sections 6.0 to 10.0, all construction equipment, facilities, and temporary controls will be removed, and the Site will be left in a clean and orderly fashion. Long-term operation and maintenance of the remedial action then will commence according to the requirements of the draft O&M Plan referenced in Section 11.0. Prefinal Inspection Upon preliminary project completion the Steering Cammi ttee will notify USEP A for the purpose of conducting a Prefinal Inspection. Participants will include the Project Manager, Project Engineer, Supervising Contractor, Construction Contractor, and other Federal, State, and local agencies with a jurisdictional interest. The Prefinal Inspection will consist of a walk through inspection of the entire project site. The objective ' of the inspection is to determine whether the project is complete and consistent with the Order. Any outstanding construction items discovered during the inspection will be identified and noted on a punch list. Additionally, treatment equipment will be operationally tested by the Steering Committee. The Steering Committee will certify that the equipment has performed to effectively meet the purpose and intent of the specifications. Retesting will be completed where deficiencies are revealed. A Prefinal Inspection Report will be submitted which outlines the outstanding construction items, actions required to resolve the items, completion date for the items, and an anticipated date for the Final Inspection. Final Inspection Upon completion of all outstanding construction items, the Steering Committee will notify USEPA for the purposes Qf conducting a Final Inspection. The Final Inspection will consist of a walk-through inspection of the entire project Site. The Prefinal Inspection Report will be used as a check list with the Final Inspection focusing on the outs tan ding construction items identified in the Prefinal Inspection. All tests that were 37 CONESTOGA·ROVERS & AsSOCIATES 'ffl I I I I I I I I I I I I 'I I I I I I 3669 (18) originally unsatisfactory will be conducted again. Confirmation will be made during the Final Inspection that all outstanding items have been resolved. Any outstanding construction items discovered during the inspection still requiring correction will be identified and noted on a punch list. If any items are still unresolved, the inspection will be considered to be a Prefinal Inspection requiring another Prefinal Inspection Report and subsequent Final Inspection. 38 CONESTOGA-ROVERS & ASSOCIATES I I u I I I I I I I I I I I I 14.0 COMMUNITY RELATIONS SUPPORT 3669 {18) As described in the RD Work Plan, the Steering Committee is committed to supporting USEP A's community relations program for the RD/RA to be conducted at the Jadco-Hughes Site. As USEPA has assumed the lead position on all community relations activities, the Steering Committee will provide technical support to USEP A at all public meetings. The Steering Committee will provide assistance to USEPA through its Project Coordinator. Assistance will include the provision of information to be used in community relations efforts and technical representation at public meetings and information sessions by personnel familiar with the RD/RA activities to be conducted. USEPA will have overall authority for coordinating community relations activities and ensuring that the public is kept informed. As part of these community relations activities, USEPA has the opportunity to review information and comment during the progress of the RD/RA. The community relations activities to be conducted by USEPA will: 1) 2) 3) 4) 5) familiarize area residents with the RD/RA process; keep area residents and other interested parties informed of the RD /RA activities to be conducted, especially with regard the on-Site activities; provide a mechanism for input to the RD/RA; provide a channel of communication for responding to Site-specific contamination issues; and ensure that all regulatory requirements concerning community relations are met. 39 CONESTOGA-ROVERS & ASSOCIATES R u 15.0 REMEDIAL ACTION SCHEDULE OF ACTIVITIES I A preliminary RA schedule was developed and included in Section 7.0 of the Preliminary Design Report. The final RA schedule is B shown on Figure 15.1. I I I m I I I • I I I I I I I 3669 (18) 40 CONESTOGA-ROVERS & ASSOCIATES ~ == == ee 1!!!11!!9 1!!!119 em 1!!!19 ee DURATION DAYS ACTl\1TY 7 " I ,, •• I 60 I 77 I 91 I 165 I "' I 1J3 I 1~1 I '" I 17s I 169 I 20J I 2i1 I rn I 2◄s 259 I 273 I 2a1 I 001 I J1s I J29 I J-4J I Js1 I 071 i Jas I 1. USEPA APPR0VAl. OF RA WORK Pt.AN.· .. ' RD.IEDI'°' TION COAL \IERIF"ICA TIC>-4 Pt.AN, O k 1.1 PLAN. ANO fltU,l. DESICH ,. COl,tPCllTI\.'E BIOOINC · . ... J.. PRECONSlRUCTION CONf(RCNC£ .. '- ◄. CONTRACTOR UOOIUZATION • ·-'- 5. SPILLWAY, CIJL\l(Rf ANO ORAINACC UN( • 5.1 SP1llWAY CONSTRVCTIOH 5.2 Ct.llVERT REPAIRS ANO SUP-Umt-10 INSTALlA TION 5.J ORAlNAC( UN[ CONSlRUCTION 6. CROUNOWA T[R CXTRACTICI-I SYSTEM· . . . . . .. 6.1 EXlRACTION WELL INSTALLATION 6.2 TILE DRAIN CONSTRUCTION 6.J PIPELINE CCf,ISTRUCTION 6.◄ CROUNDWAl"ER cxnv,cncr,i SYSTEM COMl.nSSION!NC 7. GROJNDWATER TR[AT\IEHT S'rSTtU· . . . . .. .. 7.1 CROUND\YAt(R TR[An.tOH BULDINC 7.2 ~d:~1~~ lR[ATM£NT SYSTCM [OUIPU[NT ANO INSTRUMENTATION INSTAI..LATION 7.J GROUNDWATER TR[Al\.l[NT svsrru COMUJSSIOtllNG ,. 0 lo U Pl.All (RE',1SIONS) ... I I I I I ,. SOIL VAPOR EXTIUCTION SYSlCM • .. 9.1 SOil VAPOR EXTRACTION TRENCH INST Al..LA llON 9.2 SOIL VAPOR EXTRACTION SYSTEM CONSTRUCTION 9.J SOIL CAP INSTAUATION 9.4 SOIL VAPOR [XffiACTIOH SYSTE:M COUl,IISSU)N!NG "· SOIL rt.USHING SYSTE:M • . . . . .. . . . . . . . .. 10.1 SOil rUJSHING SYST[M ca..u:cnON lR[NCH INSTAUATION 10.2 SOIL rt.VSHING SYSTE:M [OJ!PI.IE:NT INSTAUATIC>N 11. CONSTRUCTION a.OSCOIJT mo .. .. I I I I I 1 O[MOOIUZA lKlN 12. PRrf\NAL INSPECTION REPOOt PRE:PARATION· I IJ. VSEPA PRlJ1NAL INsPE:CnoN • . . . . . . . . . .. . . .. 14. VSEPA flHAL INSPCCTI0-1 • . . ..... I 15. RA R[PORT PR[PARATlON· HI I 111 111 I "· VS£PA Rc-,,[W RA R[PORT • I I I I I I I 17. SYS T[M CP£RA TION • • • . . . . . . . .. I I I I I I I I I I I I 1 I I I I I 1 l£GEND NOTt:: TiaS scm:ou.c IS TE:NTATM: \lillH R[SP[Cl figure 15.1 TO TH[ INOMDVAL [LEMENTS IN Tit[ SOiEOUtL RA SCHEDULE CONTIHVOUS ACTI'.UY THC SCLECT(O R[MEDIAL CONTRACTOR MAY MOOIFY TH( LNT[R!M COMPLETION OATES. PROV.OED JADCO-HUGHES SITE THAT Tl-£ OAT[ FOR THE COl,IP\.[TION Of lHE • EvtNT 0EMOOU2ATIO,f (DAY :27J) ANO USEPA LNSP[CTIONS Coston County, NC CRA (OAYS 238 mo 266) AR( MET. J669 (18) JAN 28/94(W) REV.1 (S 05) I u B u I I E I I I I I I I I I I 16.0 CONSTRUCTION MANAGEMENT PLAN This section presents the Construction Management Plan as required by the SOW. As the Supervising Contractor, CRA has assembled the following project management team and technical resource personnel with the necessary experience and capabilities required for the project. CRA's project management team will consist of Rick Shepherd; Steve Quigley; Jeanne Chew, Wolfe Engler; Mark Guthrie; Ian McRae; Mike Mateyk; Steve Day and Mitchel Bergner. Brief descriptions of all personnel roles and qualifications are listed below, and curricula vitae are included in Appendix D. Figure 16.1 presents an organizational chart for the project team and assigned personnel. R. Shepherd -Principal-In-Charge -provides overall corporate project management -ensures professional services provided by CRA are cost effective and of highest quality -ensures all resources of CRA are available on an as-required basis -managerial and technical guidance to CRA's Project Coordinator -final review of CRA submittals prior to issue S. Quigley -Project Manager -designated Project Coordinator under Order -supervisor of engineering project team members during the development of Work Plans, Contract Documents and Specifications and reports to State and Federal Agencies -technical manager of RA field activities -administrator of project costs and schedule -coordination of CRA's technical group T. Chew -Project Engineer -assists Project Manager in engineering team supervision -provides Construction Quality Assurance assistance -assists in completion of RA field activities 3669 08) 41 CONESTOGA-ROVERS & ASSOCIATES I R I I I n I I I I I I I I RD/RA TECHNICAL ADv1SORS MARK GUTHRIE WOLF£ ENGLER MITCHELL BERGNER TECHNICAL STAFF CAA PRINCIPAL IN CHARGE RICK SHEPHERD PROJECT MANAGER STEVc QUIGLEY PROJECT ENGINEER JEANNE CHEW ANALYTICAL CHEMISTRY CONTRACT HYDROGEOLOGIST TECHNICAL ADv1SOR ADMINISTRATOR STEVE DAY PROJECT STAFF /AN McRAE MIKE MATEYK HYDROGEOLOGIC FIELD STAFF figure 16.1 PROJECT ORGANIZA TlON JADCO-HUGHES SITE Goston County, NC 3669 (18) JAN 28/94(W) REV.1 (C-O5) u I I I m I I I I I I I I I I I I I I 3669 {18) W. Engler -RA Technical Advisor -provides technical assistance to CRA's project coordinator during preparation for RA field activities M. Guthrie -RD Technical Advisor -provides technical review of project designs and specifications -supervises project design staff I. McRae -Contract Administrator -development of Bid Documents -provides assistance to project design staff in the preparation of project specifications -coordination of competitive bidding -administration of contracts (bonds, insurance, payment certificates, contract addenda, change orders) M. Mateyk -Hydrogeologic Technical Advisor -development of hydrogeologic components associated with preparation of RA documents -provides hydrogeologic expertise support function for reporting to State and Federal Agencies S. Day -Analytical Chemistry Technical Advisor -provides technical assistance to Quality Assurance/Quality Control (QA/QC) personnel during preparation of the RA documents -provides analytical expertise support function for reporting to State and Federal Agencies M. Bergner -Project Industrial Hygienist -provides technical assistance to CRA's Project Coordinator for development and implementation of the health and safety program components of the Plan -reviews Contractor(s') health and safety plans 42 CONESTOGA-ROVERS & ASSOCIATES I I m I I D I I I I I I I I » I I I I I 3669 (18) Subcontractors will be selected to perform specific tasks during remedial design phases. The Steering Committee has contracted ENSECO-Air Toxics and ENSECO-Rocky Mountain Analytical to perform analytical testing for the RD/RA. The RA portion of the work is to be undertaken by qualified contractors selected in a prequalified bidding process. The remedial action will be administered and monitored by the Supervising Contractor and overseen by USEP A. USEPA will be notified of the start date for construction. During the RA, should significant changes to the construction schedule or to the construction activities occur, USEPA will be notified of these changes. 43 CONESTOGA-ROVERS & ASSOCIATES m m m ffl D 0 D u APPENDIX A I ACCESS AGREEMENTS m I • I I I I I I I 3669 m I m I u u I I I I I I I I I I I I AUG O 2 19-91i July 17, 1991 Reference No. 3669 ACCESS AGREEMENT I grant permission to the Jadco-Hughes steering committee, including its Contractors and representatives, and the United States Environmental Protection Agency (EPA) and its representatives to enter my property in Belmont, NC to perform all activities related to soil and·groundwater treatment and associated cxca·:ating, grading, cor:struction, well installations, sample collection and data collection activities as required by the EPA Administrative Order Docket No. 91-31-C for the Remedial Design/Remedial Action at the Jadco-Hughes Superfund Site. ,i 7/WL . O~fg /~~ Name: Date: \ cc. Ms. Barbara Benoy, EPA, Region IV Mr. Reuben Bussey, EPA, Region IV Charles H. Tisdale, Esq., King & Spalding Mr. Richard Shepherd, CRA Mr. Steve Quigley, CRA July 17, 1991 Reference No. 3669 ACCESS AGREEMENT I grant permission to the Jadco-Hughes steering committee, including its Contractors and representatives, and the United States Environmental Protection Agency (EPA) and its representatives to enter my property in Belmont, NC to · perform all activities related to soil and groundwater treatment and associated excavating, grading, construction, well installations, sample collection and data collection activities as required by the EPA Administrative Order Docket No. 91-31-C for the Remedial Design/Remedial Action at the Jadco-Hughes Superfund Site. Name: Date: cc. Mr. John Plecnik, 11 Spruce Pine, Belmont, NC Ms. Barbara Benoy, EPA, Region. IV Mr. Reuben Bussey, EPA, Region IV Charles H. Tisdale, Esq., King & Spalding Mr. Richard Shepherd, CRA Mr. Steve Quigley, CRA 28012 I I I I I I I I I I I I I I I m I m 0 B fi I I I I I I I I I I I I I September 11, 1991 - 3 - CONESTOGA-ROVERS & ASSOCIATES LIMITED Consulting Engineers Reference No. 3669 ACCESS AGREEMENT I grant permission to the Jadco-Hughes Steering Committee, including its Contractors and representatives, and the USEPA and its representatives to enter my property to perform field investigations as required for the RD for the Jadco-Hughes Site. Name: Date: c.c.: Ms. Barbara Benoy, USEP A, Region IV Mr. Reuben Bussey, USEPA, Region IV Mr. Benton Leach, Uniroyal Mr. Charles H. Tisdale Mr. Richard Shepherd Mr. Mike Mateyk Mr. Ron Frehner Mr. Steve Quigley Conditional Note: As CEO of Textile Sales & Repair Inc., we will grant the above access agreerrent only if you repair the damage to our drain line caused by the drilling of one of your wells (MW-13S or MW-130). This repair work must be completed before any more wells are drilled on our property. If you have any questions, you may contact rre at 704-827-0115. Thank you, Robert J. Baucom CONESTOGA-ROVERS & ASSOCIATES LIMITED Consulting Engineers November 10, 1992 Reference No. 3669 -3- ACCESS AGREEMENT I grant permission to the Jadco-Hughes Steering Committee, including its Contractors and representatives, and the United States Environmental Protection Agency and its representatives to enter my property located at 700 Cason Street, Belmont, North Carolina to perform field investigations as required by the Unilateral Administrative Order for Remedial Design and Remedial Action, EPA Docket No. 91-31-C. Name: Date: c.c.: Ms. Barbara Benoy, USEP A, Region IV Mr. Jimmy Kirkland Mr. Richard Shepherd Mr. Steve Quigley g m I I I I I I I I I I I I I I I I I m I I I I m I I I I I I I I I I I I SEIIT tll :nVLIUAI 1.1,, .-.ir.rvo., • --· w · --···-· April 2.0, 1993 ·3- CONESTOGA-AOVER& & A880CIATl:!I UIIITI:D C-Hlnt ..,.._. Reference No. 3669 ACCfS.'i AGBEEMENJ' I grant pmnhsion to the Jadco-Hughes Steering Committee, Including iti; Contractors ind repl'eMJ\tative1, and the United Statel Bnvironment.!11 P:iotedion Agency and Its repruentatlvei to enter my property located at 778 Cason Street. Belmont, North Carolina to pl!l'form field lnveatigati.ona as ff<J.Ulred by the Unllateral Administrative Order for Remedial Design and Remedial Action, F.PA Docket No. 91·31-C. Name; Date: c;.c.: Ms. Barbara !xnoy, tJSEPA, Region IV Mr. Jimmy Kirkland Mr. Rlchard Shepherd Mr. Steve Quigley I I I I I I I I APPENDIX B, I CONSTRUCTION HEALTH AND SAFETY PLAN I I I I I I I I I I 3669 (18) I I I I I I I I I I I I I I I I I I I TABLE OF CONTENTS ~ B.1.0 GENERAL. .................................................................................................................. B-1 B.2.0 SITE CHARACTERJZATION ................................................................................. B-3 B.3.0 BASIS ........................................................................................................................... B-4 B.4.0 RESPONSIBILITIES AND ADMINISTRATION ............................................... B-6 B.5.0 MEDICAL SURVEILLANCE .................................................................................. B-8 B.6.0 TRAINING ................................................................................................................. B-9 B.7.0 SITE WORK ZONES AND WORK ACTIVITIES .............................................. B-10 B.8.0 PERSONAL PROTECTIVE EQUIPMENT (PPE) ................................................. B-12 B.9.0 RESPIRATORY PROTECTION PROGRAM ....................................................... B-15 B.10.0 PERSONAL HYGIENE .......................................................................................... B-17 B.11.0 AIR MONITORJNG .............................................................................................. B-19 B.12.0 COMMUNICATIONS ........................................................................................... B-21 B.13.0 EMERGENCY AND FIRST AID EQUIPMENT ............................................... B-22 B.14.0 EMERGENCY RESPONSE PLAN ....................................................................... B-23 B.14.1 OFF-SITE CONTINGENCY PLAN ...................................................... B-23 B.14.2 ON-SITE CONTINGENCY PLAN ....................................................... B-23 B.15.0 EQUIPMENT AND PERSONNEL DECONTAMINATION ......................... B-25 B.16.0 CONTAMINATION MIGRATION CONTROL. ................. : ........................... B-26 3669 {18) CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I I I I TABLE OF CONTENTS B.17.0 CONFINED SPACE ENTRY PROCEDURE ...................................................... B-27 B.17.1 DEFINITIONS .......................................................................................... B-27 B.17.2 GENERAL PROVISIONS ...................................................................... B-28 B.17.3 PROCEDURE FOR CONFINED SPACE ENTRY .............................. B-30 B.17.4 CONFINED SPACE OBSERVER. ......................................................... B-31 B.18.0 HEAT STRESS ........................................................................................................ B-33 B.19.0 COLD STRESS ......................................................................................................... B-35 3669 (18) CONESTOGA-ROVERS & ASSOCIATES I I· I I I I I I I I I I I I I I I I I LIST OF FIGURES FIGURE B.2.1 FORMER LANDFILL AND OPERATIONS AREA FIGURE B.12.1 EMERGENCY HOSPITAL ROUTE LIST OF TABLES TABLE B.2.1 CONTAMINATION PROFILE -SUBSURFACE SOIL TABLE B.2.2 CONTAMINATION PROFILE -ON-SITE GROUNDWATER TABLE B.7.1 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVITIES -SPILLWAY, CULVERT AND DRAINAGE LINE TABLE B.7.2 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVITIES O GROUNDWATER EXTRACTION SYSTEM TABLE B.7.3 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVITIES -GROUNDWATER TREATMENT SYSTEM TABLE B.7.4 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVITIES -SOIL VAPOR EXTRACTION SYSTEM TABLE B.7.5 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVITIES -SOIL FLUSHING SYSTEM TABLE B.12.1 EMERGENCY TELEPHONE NUMBERS LIST OF ATTACHMENTS ATTACHMENT B-1 TRAINING ACKNOWLEDGMENT FORM ATTACHMENT B-2 CONFINED SPACE ENTRY PERMIT Following Page B-3 B-21 B-3 B-3 B-11 B-11 B-11 B-11 B-11 B-21 3669 08) CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I' I ' I I I I I I I I B.1.0 GENERAL 3669 (18) The Construction Health and Safety Plan (HASP) presented herein describes the health and safety procedures to be implemented during the Remedial Action (RA) at the Jadco-Hughes Site (Site) in Gaston County, North Carolina. Section 2.0 of the RA Work Plan presents a description of current Site conditions. The five remedial construction components to be implemented at the Site are as follows: • construction of the spillway, culvert and drainage line; • construction of the groundwater extraction system; • construction of the groundwater treatment system; • construction of the soil vapor extraction system; and • construction of the soil flushing system. During the remedial construction, personnel may come in contact with soils, groundwater, sludge and/ or sediments which potentially contain hazardous substances. To ensure _that direct contact with potentially contaminated material by Site personnel is minimized, this HASP will be adhered to by all on-Site personnel involved with the RA. This HASP has been developed to ensure the following: i) that Site· personnel are not adversely exposed to the compounds of concern; ii) that public welfare and the environment are not adversely impacted by off-Site migration of contaminated rpaterials due to work activities at the Site; iii) compliance with applicable governmental and non-governmental [American Conference of Governmental Industrial Hygienist (ACGIH)] regulations and guidelines. In particular, the amended rules of the Occupational Safety and Health Act for Subpart Hof Part 1910 (Title 29 Code of Federal Regulations (CFR) Part 1910.120) will be implemented for Site work; and B-1 CONESTOCA·ROVERS & ASSOCIATES 3669 (18) iv) initiation of proper emergency response procedures to minimize the potential for any adverse impact to Site workers, the general public or the environment. For the purpose of this HASP, the components of the RA activities performed on Site involving contact with potentially contaminated materials will be considered contaminated operations requiring personal protective equipment (PPE). A detailed description of the PPE required is presented in Section B.8.0. All RA activities at the Site will be conducted in accordance with the provisions of this Site-specific HASP. Cost and/or scheduling considerations will not be considered as justification for modifying this plan. A copy of this HASP and applicable Material Safety Data Sheets (MSDS) will be maintained on Site whenever Site activities associated with the RA activities are in progress. B-2 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I ' I ,, I I , , I I I I ,,, I I I I I I ' I I I I 1: I I I B.2.0 SITE CHARACTERIZATION 3669 (18) The Remedial Investigation (RI) identified the presence of volatile organic compounds (VOCs), base, neutral and acid extractable compounds (BNAs) and metals in the groundwater and in the soil. Polychlorinated biphenyls (PCBs) were detected in subsurface soils in the former landfill and in very low concentrations in groundwater samples from one monitoring well. Table B.2.1 identifies the contaminants in the subsurface soil of the former landfill area and the former operations area and their representative concentrations. The location of the former landfill area and the former operations area on Site are shown on Figure B.2.1. Table B.2.2 presents the contaminant profile of the on-Site groundwater. B-3 CONESTOGA-ROVERS & ASSOCIATES Page 1 of4 I TABLE B.2.1 I CONTAMINATION PROFILE-SUBSURFACE SOILS JADCO-HUGHES SITE, GASTON COUNTY, NC I RA WORK PLAN Part A -Fonner Land[ill ' Range of Detects Representative 95th Percentile Compo11nd Low High Concentration (1) Mean (2) voes Cmg(kg> I acetone 0.006 72 9.9 13 2-butanone 21 170 72 35 I 1, 1-dichloroethane 0.0027 0.0027 0.01 2.6 1,2-dichloroethane 1.6 9.3 5.7 3.4 ethylbenzene 8.4 65 36.4 19 methylene chloride 0.0019 11.0 3.1 2.9 I 4-methyl-2-pentanone 10.000 19.000 14.5 31 l, 1,2,2-tetrachl oroe thane 0.0095 0.0095 0.01 6.2 tetrachloroethene 0.0016 12 4.7 3.2 ,1 toluene 0.0018 620 303.6 182 1,1,1-trichloroethane 0.014 0.014 0.01 3.5 1, 1,2-trichloroethane 0.0028 0.0028 0.01 4.6 I trichloroethene 0.0075 3.5 1.8 1.8 total xylenes 0.0013 320 134.6 91 BNAs Cmg(kg) :I acenaphthene 0.17 0.98 0.58 1.3 anthracene 1 1 1.0 1.4 I benzo(a)pyrene 3.6 3.6 3.6 1.6 benzo(b )fluoranthene 2.7 2.7 2.7 1.7 benzo{g,h,i)perylene 1.4 1.4 1.4 1.6 I benzo(k)fluoranthene 2.2 2.2 2.2 1.4 benzoic acid 13 35 19.4 11 bis(2-chloroethyl )ether 1.2 1.7 1.5 1.7 bis (2-ethy lhexy 1 )p h tha late 0.09 260 53.8 67 I butyl bentzyl phthalate 2 8.2 5.0 2.8 2-chlorophenol 14 90 42.4 24 chrysene 0.27 3.4 1.8 1.6 I 1,2-dichlorobenzene 1.4 2.1 1.7 1.2 1,4-dichlorobenzene 0.57 0.98 0.78 1.5 d i-n-bu tyl ph thala te 2.4 8.4 3. 3.6 di-n-octyl phthala te 4.6 6.1 5.4 2.5 I fluoranthene 0.48 5.4 2.9 1.8 fluorene 0.19 0.69 0.44 1.3 indeno{l,2,3-cd)pyrene 2.0 2.0 2.0 1.6 I 2-methylnaphthalene 0.11 2.9 1.1 1.3 2-methylphenol 2.5 9.1 5.1 3.0 4-methylphenol 1 2.5 1.9 1.1 :1 naphthalene 1.8 6.3 3.6 2.0 phenanthrene 3.4 3.4 3.4 1.8 phenol 8.2 24.0 16.0 8.6 pyrene 0.48 5.6 3.0 1.8 t 1,2,4-trichlorobenzene 0.18 86.0 24.2 2.2 CRA 3669 (18) I I I I I I I ' I I I ' I .,.: I ' I I I I I I Page 2 of 4 TABLE B.2.1 CONTAMINATION PROFILE· SUBSURFACE SOILS JADCO-HUGHES SITE, GASTON COUNTY, NC RA WORK PLAN Range of Detects Representative 95th Percentile Compound Low High Concentration (1) Mean (2) Pesticides!PCBs Cmglkg/ PCB Aroclor 1248 11.0 36,0 20.3 NA Metals and Total Cyanide lmglkg/ Aluminum 1,570 27,600 13,856 19,551 Antimony 16.1 47.5 30.9 18 Arsenic 30,9 47.0 39.0 58 Barium 27.6 268 102 117 Beryllium 0.75 1.7 1.2 1.9 Cadmium 1.0 4,0 2.5 2.4 Calcium 1,177 16,400 4,031 7,014 Chromium 5,8 190 66 87 Cobalt 10 30.6 20 78 Copper 35.4 1,010 219 353 Iron 17,000 63,690 36,354 45,308 Lead 5.1 596 301 623 Magnesium 1,426 8,900 4,087 7,457 Manganese 110 990 487 696 Mercury 0.06 0.18 0.11 0.08 Nickel 5.6 60 21 53 Potassium 130.4 885 358 378 Sodium 227.3 757 530 476 Thallium 0.08 0.11 0.09 0,27 Vanadium 37 290 122 155 Zinc 23.6 175 71 95.4 Total Cyanide 4.0 8,9 6,8 4.7 Notes: • Based on RI soil data for the former landfill. • VCX:s = volatile organic compounds. • BNAs = base/neutral and acid extractable compounds. • The above profile is based on samples collected from the following locations: BH(MW-3), BH-7, BH-8, BH-9, BH-10, BH-11, TP-2 ,TP-3. (1) Representative concentration is a conservative estimate of the concentration of each contaminant in soil and was calculated by an arithmetic average of detections, (2) 95th percentile mean includes all duplicates and sample depths. NA Data not sufficient to calculate 95th percentile mean. CRA 3669 (18) TABLE B.2.1 CONTAMINATION PROFILE-SUBSURFACE SOILS JADCO-HUGHES SITE, GASTON COUNTY, NC RA WORK PLAN Part B -Fonner 012erations Area Range of Detects Compound Low High voes Cmglkg! acetone 0.0031 1.8 2-butanone 0.10 0.68 1,2-dichloroethane 0.0075 30 1,2-dichloroethene (total) 0.003 0.16 methylene chloride 0.0024 0.44 4-methyl-2-pentanone 0.018 0.18 toluene 0.0014 0.2 trichloroethene 0.0071 . 19 vinyl chloride 0.0055 0.0055 BNAs Cmglkg/ bis(2-chloroethyl )ether 0.23 0.23 bis(2-ethylhexy 1 )ph tha late 0.11 0.21 di-n-b utylph thala te 0.12 0.29 phenol 0.12 0.12 1,2,4-trichlorobenzene 0.15 0.15 PCBs !mg/kg! PCB Aroclor-1248 1.2 1.2 Notes: • voes = volatile organic compounds • BNAs • PCBs = base/neutral and acid extractable compounds = polychlorinated biphenyls Re pre sen ta tive Concentration (1) 0.39 0.39 6.06 0.08 0.11 0.06 0.06 4.76 0.01 0.23 0.15 0.19 0.12 0.15 1.2 The above profile is based on samples collected from the following locations: BH (MW-6), BH-17, BH-18, BH-19, BH-20, BH-21, TP-7. Page3 of 4 95th Percentile Mean (2) 0.41 0.53 6.8 0.04 0.10 0.90 0.05 4.0 0.10 0.35 0.68 0.32 0.27 0.27 NA (1) Representative concentration is a conservative estimate of the concentration of each contaminant in soil and was calculated by an arithmetic average of detections. These results are rounded to 2 decimal places. (2) 95th percentile mean includes all duplicates and sample depths. NA Data not sufficient to calculate 95th percentile mean. CRA 3669 (18) I I I ,, ' I I ., I I I I 11 I ' • I I I 'I I I I I I I 'I ' I ,. I ·1 I I ., ' I I I I I ··, I I Compound Metals lmglkg> Aluminum Arsenic, graphite AA Barium Berillium Cadmium Calcium Chromium Cobalt Copper Iron Lead, graphite AA Magnesium Manganese Nickel Potassium Silver Sodium Thallium Vanadium Zinc Notes: TABLE B.2.1 CONTAMINATION PROFILE-SUBSURFACE SOILS JADCO-HUGHES SITE, GASTON COUNTY, NC RA WORK PLAN Range of Detects Low High 8,800 2I,OO0 13 30 32.3 140 0.4 0.4 0.9 2.1 2,400 6,700 2.6 139 7 22 34 95 15,000 38,000 0.81 15 1,500 6,970 , 210 1,100 6 45.7 440 860 0.8 0.8 642 642 0.08 0.08 37 89 37 39 Representative Concentration (1) 14,560 23 82 0.4 1.9 4,228 34 15 63 25,400 4.6 4,394 521 16 590 0.8 642 0.08 68 38 Page 4 of 4 95th Percentile Mean (2) 22,461 33 138 0.47 2.8 7,050 13 24 117 40,677 16 4,894 1,256 12 1,002 0.67 466 0.08 115 41 The above profile for Metals is based on samples collected from the following locations: BH(MW-6), BH-21, TP-7. (1) Representative concentration is a conservative estimate of the concentration of each contaminant in soil and was calculated by an arithmetic average of detections. (2) 95th percentile mean includes all duplicates and sample depths. NA Data not sufficient to calculate 95th percentile mean. CRA 3669 (18) -.. CAA -.. -(-- ------PROPERTY LINE -•---;-FENCC UN( ~ fORM[R L.A.NOflll AREA FORMER OP[RA TlONS AREA I I ', / l[XllLE SAl.[S ANO 0 !)() \0011 e-L.J I \ / / H[l'AIR PHOPEffff ~ J \ ,<--~----,~--~~~~-/ / --~--,--' . " ""' , "" _., . ,. ····•·\: ....... , I I\ I .' :;c;,..Hl<l.'S J•l/01'1.Kl ( I I I · ~,.. • ✓ ~~~c•o""''' "'' ....... _ .. _. __ ._Li_·_:~; \-"' :_ .••. _:: .. ~.;. ;-•-. C (~~;,::~-·• \ i ~. \~ 11 ' r -1ibv,• '•\ .-I l '. : 1\ ~ •• -~.. ,. '~ •-.~. I/! a, ,. ' /-'dl~.·~ "-= ~-==----=~·:-· •·:· ~=-'J:.:_"·'_':_:;.;-~ PLWIIK l'ROl'[U IY I I ·-.,.,-rr,•r' "'()'(, FORMER LANDFILL figure B.2.1 AND OPERATIONS AREAS JADCO-HUGHES SITE Gaston County, NC J669 (18) JAN 28/94(W) REV.O (P-60) .. I I I I' I I I I I I ,, I I I ,, I I I I TABLE B.2.2 CONTAMINATION PROFILE-ON-SITE GROUNDWATER JADCO-HUGHES SITE, GASTON COUNTY, NC Compound voes CugtL> acetone benzene 2-butanone carbon disulfide carbon tetrachloride chlorobenzene chloroethane chloroform 1,1-dichloroethane 1,2-dichloroethane 1,1-dichloroethene 1,2-dichloroethene (total) 1,2-d ichloropropane ethylbenzene 2-hexanone methylene chloride 4-methy 1-2-pen ta none 1,1,2,2-tetrachloroethane tetrachloroethane toluene 1,1,1-trichloroethane 1,1,2-trichloroethane trichloroethene vinyl chloride total xylenes BNAs !ug!L) benzoic acid bis (2-chloroethyl) ether bis (2-chloroisopropyl) ether bis (2-ethylhexyl) phthalate 1,2-dichlorobenzene 1,3-dichlorobenzene 1,4-dichlorobenzene di-n-bu typhthalate di-n-octylphthalate 2-methylphenol 4-methylphenol naphthalene phenol 1,2,4-trichlorobenzene CR.A 3660 (18) RD WORK PLAN RI DATA Representative Concentration 30524 277 57124 1.8 7153 96 7.7 17083 22 986 141 2561 0.32 749 900 1750 6688 0.26 6.2 17359 168 1.6 69 11451 1376 2675 4623 11 41 56 19 121 196 1.9 26 74 8.1 1109 606 95th Percent Mean 8166 312 4700 131 1541 409 369 7061 210 483 337 1071 419 496 2445 679 3115 485 297 5940 271 352 145 3687 458 639 3089 161 37 41 33 113 85 39 175 177 25 255 326 PRE-RD DATA (1) Representative Concentration 27133 263.22 ND ND 7703 253 ND 18608 ND 770 ND 2934 ND 536 ND 1631 ND ND 5.8 15474 ND ND 59 11097 1278 ND ND 4286 ND 54 35 156 ND ND 25 63 10 ND 541 Page 1 of 2 Compound PCBs Cug!L) (2) Arochlor 1248 Arochlor 1232 Metals Cmg!L > aluminum antimony arsenic barium beryllium cadmium calcium chromium cobalt copper iron lead magnesium manganese nickel potassium silver sodium thallium vanadium zinc Notes: TABLEB.2.2 CONTAMINATION PROFILE-ON-SITE GROUNDWATER JADCO-HUGHES SITE, GASTON COUNTY, NC RD WORK PLAN RI DATA Representative Concentration ND ND 35 0.22 0.04 0.2 0.001 0.0067 136 0.14 0.068 0.17 55 0.0095 63 8.9 0.15 7.7 O.Dl 18 0.001 0.14 0.18 95th Pere en t Mean NA NA 38 0.12 0.02 0.2 0.01 0.03 131 0.15 0.05 0.14 57 0.1 58 10 0.15 3.6 0.1 18 0.18 0.13 0.95 PRE-RD DATA (1) Rep re sen tative Concentration 1.3 1.9 27 ND ND 0.2 ND ND 110 0.15 0.06 0.15 40 ND 50 6.8 0.13 6.4 ND 16 ND 0.12 0.16 Page 2 of 2 (1) Pre-RD data representative concentration is calculated based on all detections during the RI and pre-RD. If compound was not detected during pre-RD then representative concentration was non-detect. (2) Each PCB isomer only detected once in MW8S during pre-RD. These compounds were never detected in any other samples. CRA 3660 (18) I I I I I I I I .1 ' I {• I I I I I I I I I I I I I I I I I I I I I I B.3.0 BASIS 3669 (18) The Occupational Safety and Health Administration (OSHA) Standards and Regulations contained in Title 29, CFR, Parts 1910 and 1926 (29 CFR 1910 and 1926), including the amended sections in 29 CFR 1910.120 and current Threshold Limit Values (TL Vs) as provided by the ACGIH, provide the basis for this HASP. Some of the specifications within this section are in addition to OSHA regulations and reflect the positions of USEP A, the National Institute for Occupational Safety and Health (NIOSH) and the United States Coast Guard (USCG) regarding procedures required to ensure safe operations at potential hazardous waste sites. In addition, the following references have been used as guidance in developing the HASP: i) CERCLA Sections 104(£) and lll(c) (6); ii) EPA Order 1440.2 -Health and Safety Requirements for Employees Engaged in Field Activities; iii) EPA Order 1440.1 -Respiratory Protection; iv) EPA Occupational Health & Safety Manual v) EPA Interim Standard Operating Safety Guide (September 1982); vi) OSHA Standards for General Industry; vii) NIOSH, Manual of Analytical Methods, Volumes I-VII; viii) Threshold Limit Values (TLV) for Chemical Substances and Physical Agents in the Work Environment with Intended Changes Adopted by ACGIH; ix) x) xi) ANSI Z 88.2-1980, American Natiol).al Standard, Practices for Respiratory Protection; Air Sampling Instruments for Evaluation of Atmospheric Contaminants, 6th edition, 1983, American Conference of Governmental Industrial Hygienists; and Superfund Public Health Evaluation Manual, U.S. EPA (October 1986). The safety and health of the public and on-Site personnel and the protection of the environment will take precedence over cost and schedule considerations for all remedial construction work. The RA Contractor will designate an on-Site individual as Health and Safety Officer (HSO) during on-Site remedial constructio_n activities. Contractors working B-4 CONESTOGA-ROVERS & ASSOCIATES 3669 (18) on the Site will be responsible for the health and safety of their workers. This will include ensuring that all workers are thoroughly trained with the Standard Operating Procedures (SOPs) of any equipment (for example, excavators) they will be operating, or hazardous procedures (for example, confined space entry) they will participate in. The HSO will be responsible for decisions regarding when work will be stopped or started for health or safety considerations. The RA Contractor will develop a Site-specific HASP related to its specific activities at the Site. Each Site-specific HASP will be reviewed by Conestoga-Rovers & Associates (CRA) for completeness and compliance with the minimum standards set forth in this HASP, prior to commencing work activities involving contact with potentially contaminated materials at the Site. B-5 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I ,, I I I I I I I I I I I I I I I I I I I I I I I I I I ,, I I B.4.0 RESPONSIBILITIES AND ADMINISTRATION 3669 (18) The HSO will supervise the implementation of the HASP and will be responsible for all decisions regarding operations and work stoppages due to health and safety considerations. i) ii) iii) iv) v) vi) vii) The responsibilities of the HSO will be as follows: be responsible for implementation of the HASP at the initiation of Site work; conduct the initial briefing sessions for all on-Site personnel with regard to the HASP and other safety requirements to be observed during remedial construction, including: potential hazards, including heat/ cold stress, personal hygiene principles, PPE, respiratory protection equipment usage, and a) b) c) d) e) emergency procedures dealing with fire and medical situations; review and modify the HASP as more information becomes available concerning the hazardous materials involved, and review all monitoring reports; supervision and enforcement of safety equipment usage; supervision and inspection of equipment cleaning; personnel training in safety equipment usage and emergency procedures; monitoring of the health and safety program under the direction of an industrial hygienist; B-6 CONESTOGA-ROVERS & ASSOCIATES 3669 (18) viii) suspend work activity if unsafe working conditions develop, including unsafe working conditions generated by adverse wind, rain and lightning; ix) x) xi) xii) inform workers of the nature of chemical exposure risk as required by the "Right-to-Know" Law; recommend medical examination when worker appears to require it; coordination of emergency procedures; and maintain a sign in/ out log for personnel and visitors. I I I I I I I I I I --I I I I I I I I I B-7 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I I I I B.5.0 MEDICAL SURVEILLANCE 3669 (18) In accordance with requirements detailed in 29 CFR 1910.120 and 29 CFR 1910.134, all Site personnel who will come in contact with potentially contaminated materials will have received, within one year prior to starting field activities, medical surveillance by a licensed physician or physician's group. Medical records for all Site personnel who will come in contact with potentially contaminated materials will be maintained by their respective employers. The medical records will detail the tests that were taken and will include a copy of the consulting physician's statement regarding the tests and the employee's suHability for work. These medical records must be available to the employee or his designated representative upon written request, as outlined in 29 CFR 1910.120, Section (f). Each employer will en.sure and certify to the HSO that its personnel involved in activities associated with potentially contaminated materials will have had all necessary medical examinations prior to commencing work within contaminated areas. Personnel not obtaining medical certification and who do not have their records up-to-date will not perform work within contaminated areas. Interim medical surveillance will be completed if an individual exhibits poor health or high stress responses due to on-Site activity or when accidental exposure to elevated concentrations of contaminants occurs. B-8 CONESTOGA-ROVERS & ASSOCIATES B.6.0 TRAINING 3669 (18) The HSO will require that all Site personnel who will come in contact with potentially contaminated materials complete training sessions in accordance with 29 CFR 1910.120 prior to entering the Site. This training shall consist of a minimum of 40 hours of instruction off Site and three days of actual field experience under direct supervision. Each employer will maintain documentation stating that its on-Site personnel have complied with this regulation. Prior to commencing Site activities, all personnel will be required to attend a Site-specific initiation session. These sessions, conducted by the HSO, will be used to instruct the Site personnel as to what the Site activities and potential Site hazards are, level of PPE required, Site-specific requirements, work zones established at the Site, personal and equipment decontamination procedures; emergency response plan and procedures, and the basis of the HASP . At this session it will be confirmed by CRA that all on-Site personnel have the 40 hours of training required in accordance with 29 CFR 1910.120. All personnel who attend this session will sign a Training Acknowledgment Form, an example of which is presented as Attachment B-1. During the course of Site activities, additional safety meetings will be conducted by the HSO with on-Site personnel to provide updates on Site conditions and health and safety concerns. B-9 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I I I I I I a I D D I D u I I I I I I I I I B.7.0 SITE WORK ZONES AND WORK ACTIVITIES 3669 (18) Site work zones will be clearly laid out and identified in . the field prior to initiation of Site work activities. The establishment of all the Sites work zone boundaries may be modified by the HSO and/or Supervising Contractor (CRA). The purpose of establishing these work zones is to limit access to potentially contaminated areas or areas which may cause physical injury to individuals and to prevent the migration of potentially contaminated materials into adjacent non-contaminated areas. These designated work zones are described as follows: i) Exclusion Zone (EZ) -this zone will include areas where potentially contaminated soils, sediments, waters or waste material are located, excavated, removed, transferred, stored, or disposed of and all areas where contaminated equipment or personnel travel including the decontamination area. Sufficient area will be provided for efficient and safe movement of personnel and equipment as well as contaminant control. The EZ will be delinJ,ated in the field with fencing, flagging or warning barriers. Access to the EZ will be restricted to personnel who are wearing the proper PPE, have received and passed the required medical examination and have undergone the required health and safety training. A log of entry to and exit from the EZ will be maintained for the purpose of stress monitoring and determining exposure times; ii) iii) Contamination Reduction Zone (CRZ) -this zone lies immediately adjacent to the EZ and occurs at the interface of the EZ and Support Zone (SZ) and will provide for the transfer of construction materials, personnel and equipment, a place for donning and disposing of PPE, the storing of emergency first aid equipment and supplemental safety supplies. Access to the CRZ will be restricted to personnel who have received and passed the required medical examination and have undergone the required health and safety training; and Support Zone (SZ) -this area is comprised of the remainder of the designated work area at the Site and is defined as being an area outside B-10 CONESTOGA·ROVERS & ASSOCIATES 3669 (18) the zone of significant air, soil or surface water contamination. The SZ will be clearly delineated and procedures will be implemented to prevent active or passive contamination from the other work zones. The function of the SZ includes: a) b) c) d) an entry area for personnel, material and equipment to the CRZ, an exit for decontaminated personnel, materials and equipment from the CRZ, a storage area for clean safety and work equipment; and an area for ea ting, drinking and smoking. The work activities to be conducted for each component of the RA at the Site are detailed in Sections 6.0 to 10.0 of the RA Work Plan for the Site. Tables B.7.1 through B.7.5 present CRA's assessment of the hazard/risk analysis for the Site work activities for each component of the remedial construction and identify the level of personal protective equipment (PPE) required for each RA activity. B-11 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I u I I I I I I I I I I I I TABLE B.7.1 HAZARD/RISK ANALYSIS FOR REMEDIAL ACTION ACTIVITIES SPILLWAY, CUL VERT AND DRAINAGE LINE CONSTRUCTION JADCO-HUGHES SITE, GASTON COUNTY, NC Work Activity Site Preparation Activities (i.e. Install Offices) Installation of the Construction, Equipment and Personnel Decontamination Facilities Construction of the Spillway, Culvert Replacement and Drainage Line Note: RA WORK PLAN Anticipated Hazards/Risks • slip/trip/fall hazards • potential back injuries from lifting and moving • slip/trip/fall hazards • potential contact with contaminated soil, sediment and water • potential dust and/or vapor emissions • physical hazards presented by the use of heavy equipment • potential back injuries from lifting and moving • slip/trip/fall hazards : • direct contact with contaminated soil, sediment and water • potential dust and/or vapor emissions • physical hazards presented by the use of heavy equipment • confined space entries (1) Level of PPE Required • Level D (2) • Level D • Level C for ground invasive activities • Level D for surface grading work • Level C for subsurface work • Level C for decontamination activities • Level C or Level B if air monitoring results indicate the need I (1) Specific requirement for confined space entry are specified in Section B.17. (4) Levels of PPE discussed in Section B.8.0. I I CRA 3669 (18) TABLE B.7.2 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVITIES GROUNDWATER EXTRACTION SYSTEM . JADCO-HUGHES SITE, GASTON COUNTY, NC RA WORK PLAN Work Activity Backfilling with Clean Material Installation of Extraction Wells, Extraction Trenches, Manholes, Decontamination Activites and Sampling Activities Note: Anticipated Hazards/Risks • slip/trip/fall hazards • potential back injuries from lifting and moving • hazards presented by the use of heavy equipment • potential dust emissions • slip/trip/fall hazards • direct contact with contaminated soil, sediment and water • potential dust and/or vapor emissions • potential contact with unknown hazardous substances • hazards presented by the use of heavy equipment • confined space entries (1) • hazards presented by the use of specialized decontamination equipment (i.e. steam cleaning unit) • potential contact with decontamination fluids Level of PPE Required • Level D, or Level C if air monitoring results indicate the need • Modified Level C (2) for extraction well installation activities • Modified Level C for remaining acti vites or Level C or Level B if air monitoring results indicate the need (1) Specific requirements for confined space entry arc specified in Section B.17.0. (2) Modified Level C -Level C PPE, without respirator. CRA 3669 (l8) I I I I I I I I I I I I I I I I I I I 8 H u D I I m I I I I I I I I I I I TABLE B.7.3 HAZARD/RISK ANALYSIS FOR REMOVAL ACTION ACTIVITIES GROUNDWATER TREATMENT SYSTEM JADCO-HUGHES SITE, GASTON COUNTY, NC Work Activity Site Preparation Activities (i.e. Install Offices) Installation of the Construction, Equipment and Personnel Decontamination Facilities Construction of the Treatment Facility Note: RA WORK PLAN Anticipated Hazards/Risks • slip/trip/fall hazards • potential back injuries from lifting and moving • slip/trip/fall hazards • potential contact with contaminated soil, sediment and water • potential dust and/or vapor emissions • physical hazards presented by the use of heavy equipment • potential back injurics•from lifting and moving • slip/trip/fall hazards • direct contact with contaminated ' soil, sediment and water • potential dust and/or vapor emissions • hazards presented by the use of heavy equipment • confined space entries (1) (1) Specific requirement for confined space entry arc specified in Section B.17. (2) Modified Level C-Level C PPE, without respirator. CRA3669(l8) Lroe/ of PPE Required • Level D • Level D • Level C for ground invasive activities • Level D for surface grading work • Modified Level C (2) or Level C for subsurface work • Modified Level C or Level C for decontamination activities • Modified Level C or Level C or Level B if air monitoring results indicate the need TABLE B.7.4 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVffiES SOIL VAPOR EXTRACTION SYSTEM JADCO-HUGHES SITE. GASTON COUNTY, NC Work Activity Regrading of the Former Landfill Area and Installation of a Soil Cover Installation of SVE Trenches and SVE Treatment System Decontamination Activites and Sampling Activities Note: RA WORK PLAN Anticipated Hazards/Risks • slip/trip/fall hazards • physical hazards presented by the use of heavy equipment • potential dust and/or fugitive emissions • direct contact with contaminated soils • potential contact with unknown waste materials • decontamination activities • potential contact with decontamination fluids • slip/trip/fall hazards • potential dust and/or vapor fugitive emissions • physical hazards presented by the use of heavy equipment • direct contact with contaminated soils • potential contact with unknown waste materials • decontamination activities • potential contact with decontamination fluids Level of PPE Required • Level D, upgrade to Level C or B if air monitoring results indicate the need • Level D, upgrade to Level C or B depending on air monitoring results. To be specified in Contractor's Site-specific HASP (1) Specific requirements for confined space entry are specified in Section B.17.0. CRAJ{,69(18) I I I I I I I I I I I I I I I I I I I 8 B I I I I I I I I I I I I I I I I TABLEB.7.5 HAZARD/RISK ANALYSIS FOR REMEDIAL CONSTRUCTION ACTIVITIES SOIL FLUSHING SYSTEM Work Activity Site Preparation Activities (i.e. Install Offices) Installation of Soil Flushing Extraction Trenches Note: JADCO-HUGHES SITE, GASTON COUNTY, NC RA WORK PLAN Anticipated Hazards/Risks • slip/trip/fall hazards· • potential back injuries from lifting and moving • slip/trip/fall hazards • direct contact with contaminated soil, sediment and water • potential dust and/or vapor emissions • potential contact with decontamination fluids • physical hazards presented by the use of heavy equipment • hazards presented by the use of specialized decontamination equipment (i.e. steam cleaning unit) Level of PPE Required • Level D • Modified Level C (2), Level C or Level B if air monitoring results indicate the need (1) Specific requirements for confined space entry are specified in Section B.17.0. (2) Modified Level C -Level C PPE, without respirator. CRA 3669 (18) B.8.0 PERSONAL PROTECTIVE EQUIPMENT (PPE) 3669 {18) The HSO will require that all personnel are equipped with PPE appropriate for the work area and the nature of work being completed. The HSO will require that all safety equipment and protective clothing are kept clean, well-maintained and that their integrity is intact. Safety equipment and apparel as required for general work on Site will be Level D and/or Level C, or Level B protective equipment if air monitoring results indicate the need as discussed in Section 9.0. The levels of personal protection required for each phase of the remedial construction activities are presented in Tables B.7.1 to B.7.5. Level B Level B PPE which will be used on-Site consists of the following: i) · supplied-air respirator (MSHA/NIOSH approved). Respirators may be positive pressure-demand, self-contained breathing apparatus (SCBA) or positive pressure-demand, airline respirator (with escape bottle for Immediate Danger to Life and Health (IDLH) or potential for IDLH atmosphere); ii) chemical-resistant clothing (overalls and long-sleeved jacket; hooded one or two-piece chemical-splash suit; disposable chemical-resistant; one-piece suits); iii) long cotton underwear or long-sleeved shirt and pants; iv) gloves (outer), chemical-resistant; v) gloves (inner), chemical-resistant; vi) boots (outer), chemical-resistant, steel toe and shank; B-12 CONESTOGA ·ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I 3669 08) vii) boot covers (outer), chemical-resistant (disposable); and viii) hard hat (face shield). LevelC Level C PPE which will be used on Site consists of the following: i) ii) iii) air-purifying respirator, full-face (MSHA/NIOSH approved), equipped with organic vapor (OV / AG) cartridge with a high efficiency particulate air (HEPA) filter; chemical-resistant clothing (coveralls; hooded one-piece or two-piece chemical splash suit; chemical-resistant hood and apron; disposable chemical-resistant coveralls); long cotton underwear or long-sleeved shirt and pants; iv) gloves (outer), chemical-resistant; v) gloves (inner), chemical-resistant; vi) boots (outer), chemical-resistant, steel toe and shank; vii) boot covers (outer), chemical-resistant (disposable); and viii) hard hat (face shield). Level D following: i) ii) coveralls; gloves; Level D PPE which will be used on Site consists of the B-13 CONESTOGA-ROVERS & ASSOCIATES 3669 (18) iii) iv) v) boots/ shoes (leather or chemical-resistant) with steel toe and shank; safety glasses; and hard hat. Additional protective equipment usage guidelines to be implemented include: i) ii) iii) iv) v) vi) vii) vii) prescription eyeglasses in use on the Site will be safety glasses; contact lenses will not be permitted in the EZ; all disposable or reusable nitrile, latex and/ or cotton gloves worn on the Site will be changed, decontaminated or discarded at the end of each day; during periods of respirator usage, respirator cartridges and filters will be changed daily, or upon breakthrough, whichever occurs first; on-Site personnel who have not passed a respirator fit test will not be permitted to enter or work in the EZ. Personnel will not be permitted to have beards, or long sideburns or mustaches that interfere with a proper fit of the respirator; all PPE worn on Site will be decontaminated or discarded at the end of each work day; duct tape will be used to ensure that disposable coveralls and gloves are · · tightly secured when personnel are working within the EZ; and no watches, rings or other accessories will be permitted during drilling and sampling activities. I I I I I I I I I I ,_ I I I I I I I I B-14 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I I I I I B.9.0 RESPIRATORY PROTECTION PROGRAM 3669 (18) Prior to arriving at the Site, all on-Site personnel will have received training in the use of, and have been fit tested for full-facepiece respirators. All on-Site personnel will be required to comply with their employer's specific written respiratory protection program developed in accordance with OSHA 29 CFR 1910.134. Respiratory protectio1;1 will be required during all subsurface ground activities, subject to the results of air monitoring. This is to ensure worker protection from potentially contaminated particulates. During work at the Site a Photoionization Detector (PIO) will be used to determine if organic vapors are present. A background reading will be established prior to commencing work activities at each active work area. Action levels to determine the level of respiratory protection necessary during nonground invasive activities are based on the concentration of unknown organic vapors measured within the breathing zone. The action levels and appropriate respiratory protection for these Site activities are as follows: Sustained Organic Vapor Reading Above Background within Breathing Zone 0 -5 ppm or background 5-50 ppm >50 ppm >500 ppm B-15 Action Taken full-facepiece air purifying respirator available wear full-face air purifying respirator wear supplied air respirator shut down activities, implement additional engineering controls CONESTOGA-ROVERS & ASSOCIATES 3669 (18) However, if the ambient concentrations of organic vapors are due to identifiable substances, the level of respiratory protection may be altered by the HSO. Periodic air monitoring data may be obtained which will form the basis of making modifications to the levels of respiratory protection presented above. B-16 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I, I I I I I I I I m I I I I I I I I I I I I I I I I I I B.10.0 3669 (18) PERSONAL HYGIENE The HSO will require that all personnel performing or supervising work within the EZ observe and adhere to the personal hygiene-related provisions of this section. On-Site personnel found to be disregarding the personal hygiene-related provisions of this HASP will, at the discretion of the HSO, be barred from the Site. Each employer will ensure that the following equipment/ facilities are available for the personal hygiene of its on-Site personnel: i) ii) iii) iv) suitable disposable outerwear, gloves, respiratory protection and footwear on a daily basis for the use of its on-Site personnel; disposal containers for used disposable outerwear; emergency eye wash and emergency shower facilities; and potable water and a suitable sanitation facility. The RA Contractor will be responsible for the disposal of used PPE, sanitary wastes, and sanitary solid wastes. The HSO also will enforce the following regulations for personnel actively participating in the remedial construction activities: i) on-Site personnel will wear appropriate PPE when in the EZ; ii) used disposable outerwear will not be reused and when removed, will be placed inside disposal containers provided for that purpose; B-17 CONESTOGA-ROVERS & ASSOCIATES iii) iv) 3669 (18) smoking, eating and drinking will be prohibited within the EZ and the CRZ. These activities will be permitted only within a designated area of the SZ; and on-Site personnel will thoroughly cleanse their hands, face, neck area and other exposed areas before smoking, eating, drinking or using toilets and before leaving the Site. B-18 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I B.11.0 3669 (18) AIR MONITORING During the progress of remedial construction activities, periodic monitoring of total particulate levels and organic vapors will be taken by the HSO or his designee. The following air monitoring instrumentation will be used for this purpose: i) a PIO; and ii) a real time digital particulate monitor. All monitoring equipment will be calibrated on a daily basis in accordance with the manufacturer's guidelines, and such calibrations will be recorded in the Site daily log book. Results of daily air monitoring also will be recorded in the Site daily log book. Air monitoring will be conducted in the breathing zone of workers in the EZ and at the downwind perimeter of the Site on an hourly basis or as deemed necessary by the HSO based on Site-specific conditions. Background measurements immediately:upwind of the EZ will be taken before activities commence. Work activities generating sustained particulate levels in excess of 150 µg/m3 or sustained organic vapor levels greater than 10 ppm above background at the downwind Site perimeter, will temporarily be halted until alternate work methods or engineering controls are in place to maintain particulate levels below 150 µg/m3 and organic vapor levels below 10 ppm above background at the downwind Site perimeter. These action levels may be modified based upon chemical-specific data. Respiratory action levels for organic vapors are discussed in Section 9.0. Immediately upon identifying sustained elevated levels of organic vapors (greater than 500 parts per million) within the work zone, the air monitoring results will be reported to the HSO, and work activities will be shut down. The HSO or his designee will determine the cause of the B-19 CONESTOGA-ROVERS & ASSOC!A TES 3669 (18) sustained elevated levels of organic vapors, and alternate work methods or engineering controls will be implemented to rectify the release of elevated concentrations of organic vapors, or the level of PPE will be upgraded as required. B-20 CONESTOGA-ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I I I I I I D I I I I I I I I I I I I I I I B.12.0 3669 (18) COMMUNICATIONS Emergency numbers including police, fire, ambulance and hospital are presented in Table B.12.1 and will be prominently posted near the Site telephone(s). A route map to the nearest emergency medical facility is presented on Figure B.12.1 and will be posted in each vehicle. Prior to initiating Site activities, the emergency medical facility will be notified of Site activities to ensure preparedness to respond to any Site-related injuries. The nearest emergency medical facility is the Gaston Memorial Hospital. Directions to the hospital are provided in Section B.14.0. B-21 CONESTOGA-ROVER5 & ASSOCIATES TABLE B.12.1 EMERGENCY TELEPHONE NUMBERS JADCO-HUGHES SITE, GASTON COUNTY, NC RA WORK PLAN Gaston Memorial Hospital Gaston County Emergency Management Belmont Fire Department Ambulance Police Conestoga-Rovers & Associates (after 6 p.m.) Stephen Quigley or Jeanne Chew USEP A Region IV Michael Townsend Duke Power (24-hour) CRA 3669 (18) (704) 886-2000 (704) 886-3300 911 911 911 (519) 725-3313 (519) 746-7338 (519) 886-9618 (404) 347-7791 (704) 864-7711 I I I m 0 D E E I I I I I m D D I • I --------------- a I & RANLO • • I I EGEND EMERGENCY HOSPITAL ROUTE CAA 3669 (18) JAN 10/94 (W) REV.O ~, ~ .... ~ .. , " ,,,_. ,,. 0 3600ft figure 8.12.1 EMERGENCY HOSPITAL ROUTE JADCO-HUGHES SITE Gaston County, NC ·g I I I I I I I I I I I I I I I I I I B.13.0 3669 (18) EMERGENCY AND FIRST AID EQUIPMENT Emergency safety equipment will be available for use by Site personnel and will be located and maintained on Site. The safety equipment will include, but is not limited to, the following: i) portable emergency eye wash and shower; ii) two 20-pound ABC type dry chemical fire extinguishers; iii) appropriate first-aid kit for a minimum of 10 persons; iv) fire blanket; v) two SCBA units; vi) portable air horn; and vii) a flashlight. CONESTOGA-ROVERS & ASSOCIATES B.14.0 EMERGENCY RESPONSE PLAN 3(,69 (18) B.14.1 OFF-SITE CONTINGENCY PLAN Prior to commencing work involving the excavation and/or handling of potentially contaminated material, the HSO will coordinate the development of an off-Site emergency contingency plan. This plan is intended to provide immediate response to a serious Site occurrence such as explosion, fire or migration of significant quantities of toxic or hazardous material from the Site into adjacent public areas. A coordination meeting will be held with appropriate local authorities to identify the remedial action activities to be performed on Site and to discuss the protocols to be taken in the event of an incident. The contingency plan will be developed to incorporate the following: 1) notification of incident; 2) evacuation of adjacent areas; 3) transport of injured personnel to medical facilities; and 4) priority transportation routes. B.14.2 ON-SITE CONTINGENCY PLAN In the event of injury to on-Site personnel or contact with hazardous materials, the following protocols will be followed: 1) in the event of injury, notify the HSO, and the Resident Engineer; 2) 3) contact hospital and describe the injury ( Gaston Memorial Hospital, as shown on Figure B.12.1); decontaminate personnel and administer appropriate emergency first aid; and B-23 CONESTOGA-ROVERS & ASS<XIA TES g 0 D D 0 0 u I I I I I g • • I I I I I I I I I I I I I I I I 3669 (18) 4) transport personnel to the hospital along the following predefined route. The predefined route is as follows: turn left on Cason Street upon exiting the Site; follow Cason Street to the end, turn left on Woodlawn Street; follow Woodlawn to the end (set of traffic lights), turn right on Old Route 273; follow signs to Interstate Highway 85 west (on right side); follow Highway 85 for approximately four miles, exit New Hope Road; turn right on New Hope Road; turn right on Court Road; follow Court Road for approximately one mile; Gaston Memorial Hospital is on the right side. Fire extinguishers will be maintained in strategic locations within the Site to combat small localized fires. In the event of significant release of potentially toxic or hazardous vapors from any container or excavation, equipment operators will immediately don self contained breathing apparatus and the source of such vapors will be backfilled or covered with fill. Alternate plans of contaminant removal will be developed and submitted to the HSO prior to recommencing work in the area. The Resident Engineer will assume the responsibility of notifying USEP A of such an incident. Emergency telephone numbers for the Site are listed in Table B.12.1. Figure B.12.1 and Table B.12.1 will be posted in a prominent place in the CZ. B-24 CONESTOGA-ROVERS & ASSOCIATES B.15.0 EQUIPMENT AND PERSONNEL DECONTAMINATION 3669 (18) During the initiation of the RA activities, procedures will be implemented to reduce the amount of contact of both personnel and equipment with the waste constituents. These procedures include the following: i) proper work practices that would lead to minimal direct contact with potentially contaminated material (e.g. avoid contact in areas of obvious contamination, remote sampling and handling procedures, etc.); ii) use of disposable equipment and clothing as much as practicable; and iii) encase source of contaminants (e.g. with plastic sheeting or foam). All vehicles and equipment leaving the EZ which came in contact with potentially contaminated material will be decontaminated on the vehicle/equipment decontamination pad, and as a minimum will include high pressure water wash of the affected areas of the vehicle/equipment. Personnel decontamination will take place at the exit from the EZ and will, as a minimum, consist of a glove and boot wash with detergent and removal of gloves, boots, disposable suit and hard hat. All personnel will remove their protective clothing and wash their hands, face, neck area and other exposed areas before entering the on-Site lunch and break areas to eat, drink, smoke or use the toilet facilities, and before leaving the Site. B-25 CONESTOGA-ROVERS & ASSOC!A TES I g D D D D I I I I I I I I g I I I I I I I I I I I I I I I I I I B.16.0 CONTAMINATION MIGRATION CONTROL 3669 (18) All vehicles and equipment used within the EZ will be decontaminated on Site at the vehicle/equipment decontamination pad prior to leaving the Site. Decontamination, when required, will consist of the thorough cleaning, using a high pressure cleaner, of those parts of the equipment which come in contact with potentially contaminated material. The HSO will certify that each piece of.equipment is clean or has been decontaminated prior to removal from Site. Personnel engaged in vehicle decontamination will wear Level C personal protective equipment including respiratory protection and face shields. All decontamination wash waters, decontamination solvents, purge water, well development water and water generated from dewatering excavations will be collected and treated in the on-Site groundwater treatment system. B-26 CONESTOGA-ROVERS & ASSOCIATES B.17.0 3669 ~8) CONFINED SPACE ENTRY PROCEDURE A confined space provides the potential for unusually high concentrations of contaminants, explosive atmospheres, oxygen deficient atmospheres, limited visibility and restricted movement. This Section establishes requirements for safe entry into, continued work in, and safe exit from confined spaces. Additional information regarding confined space entry can be found in 29 CFR 1926.21, 29 CFR 1910 and NIOSH 80-106. At this Site, confined spaces may be encountered during excavation activities or if any tank or vessel needs to be entered for cleaning purposes. B.17.1 DEFINITIONS Confined Space: A space or work area not designed or intended for normal human occupancy, having limited means of egress and poor natural ventilation; and/ or any structure, including buildings or rooms, which have limited means of egress. Confined Space Entry Permit (CSEP): A document to be initiated by the supervisor of personnel who are to enter into or work in a confined space. The CSEP will be completed by the personnel involved in the entry and approved by the HSO before personnel will be permitted to enter the confined space. The CSEP shall be valid only for the performance of the work identified on the permit and for the location and time specified on the permit. The beginning of a new shift with change of personnel will require the issuance of a new CSEP. A copy of a CSEP is provided in Attachment B-2. Confined Space Observer: An individual assigned to monitor the activities of personnel working within a confined space. The confined space observer monitors and provides external assistance to those inside the confined space. The confined space observer summons rescue personnel in the event of emergency and assists the rescue team. B-27 CONESTOGA-ROVERS & ASSOCIATES D 0 0 0 D I I I I I I I I D H I I I I I I I I I I I I I I 3669 {18) B.17.2 GENERAL PROVISIONS The following general provisions will apply to confined space entry: i) confined spaces should be identified with a posted sign which reads: Caution -Confined Space; ii) iii) iv) v) vi) only personnel trained and knowledgeable of the requirements of these confined space entry procedures will be authorized to enter a confined space or be a confined space observer; a CSEP must be issued prior to the performance of any work within a confined space. The CSEP will become a part of the permanent and official health and safety record for the response action at the Site; natural ventilation shall be provided for the confined space prior to initial entry and for the duration of the CSEP. Positive/forced mechanical ventilation may be required. However, care should be taken to not spread contamination outside of the enclosed area; if flammable liquids are anticipated to be within the confined space, explosion proof equipment will be used. All equipment shall be positively grounded; the contents of any confined space shall, where necessary and where possible, be removed prior to entry. All sources of ignition must be disconnected and/or removed prior to entry; vii) hand tools used in confined spaces shall be in good repair, explosion proof and spark proof, and selected according to intended use. Where possible, pneumatic power tools, are to be used; viii) hand-held lights and other illumination utilized in confined spaces shall be equipped with guards to prevent contact with the bulb and must be explosion proof; B-28 CONESTOGA-ROVERS & ASSOCIATES 3669 (18) · ix) compressed gas cylinders, except cylinders used for self-contained breathing apparatus, shall not be taken into confined spaces. Gas hoses shall be removed from the space and the supply turned off at the cylinder valve when personnel exit from the confined space; x) if a confined space requires respiratory equipment or where rescue may be difficult, safety belts, body harnesses, extraction equipment and lifelines will be used. The outside observer shall be provided with the same equipment as those working within the confined space; xi) a ladder or extraction device is required in all confined spaces deeper than the employee's shoulders. The ladder shall be secured and not removed until all employees have existed the confined space; xii) only SCBA or NIOSH approved airline respirators equipped with a 5-minute emergency air supply (egress bottle) shall be used in untested confined spaces or in any confined space with conditions determined immediately dangerous to life and health; -·' xiii) where air-moving equipment is used to provide ventilation, chemicals .·: shall be removed from the vicinity to prevent their introduction into the confined space; xiv) vehicles shall not be left running near confined space work or near air-moving equipment being used for confined space ventilation; xv) smoking in confined spaces will be prohibited at all times; and xvi) any deviation from these confined space entry procedures requires the prior permission of the HSO. B-29 CONESTOGA-ROVERS & ASSOCIATES I m m m g g 0 D 0 0: D 0 0 D 0 I E I I I I I • I I I I I I I I I I I I I I 3669 (18) B.17.3 PROCEDURE FOR CONFINED SP ACE ENTRY The HSO and confined space entry personnel shall adhere to the following confined space entry procedures: i) evaluate the job to be done and identify the potential hazards before a job in a confined space is scheduled; ii) ensure that all process piping, mechanical and electrical equipment, etc., have been disconnected, purged, blanked-off or locked and tagged as necessary; iii) if possible, ensure removal of any standing fluids that may produce toxic or air displacing gases, vapors or dust; iv) initiate a CSEP in concurrence with the Engineer or designated alternative; v) ensure that any hot work (welding, burning, open flames or spark producing operation) that is to be performed in the confined space has been approved by the Engineer and is indicated on the CSEP; vi) ensure that the confined space is ventilated before starting work in the confined space and for the duration of the time that the work is to be performed in the confined space; vii) ensure that the personnel who enter the confined space and the confined space observer helper are familiar with the contents and requirements of this instruction and the CSEP; viii) ensure remote atmospheric testing of the confined space prior to and during employee entry and before validation/revalidation of a CSEP to ensure the following requirements: a) oxygen content between 19.5 percent -23.0 percent, B-30 CONESTOCA·ROVERS & ASSOCIATES 3669 (18) ix) b) c) d) no concentration of combustible gas in the space. Sampling will be done throughout the confined space and specifically at the lowest point in the space, the absence of other atmospheric contaminants if the space has previously contained toxic, corrosive or irritant material, and if remote testing is not possible, Level B PPE is required for confined space entry; designate whether hot or cold work will be allowed. If all tests are satisfactory, complete the CSEP listing any safety precautions, protective equipment or other requirements; and x) ensure that a copy of the CSEP is posted at the work Site, a copy is filed with the work supervisor and a copy is furnished to the Engineer. The CSEP shall be considered void if work in the confined space does not start within one hour after the tests in Item viii) above are performed or if significant changes within the confined space atmosphere or job scope occurs. The CSEP posted at the work Site shall be removed at the completion of the job or the end of the shift, whichever is first. B.17.4 CONFINED SPACE OBSERVER The duties of the confined space observer are as follows: i) while personnel are inside the confined space, a confined space observer will monitor the activities and provide external assistance to those in the confined space. The observer will not have other duties which may take his attention away from the work or require him to leave the vicinity of the confined space at any time while personnel are in the confined space; CONESTOGA-ROVERS & ASSOCIATES g 0 0 D D -11 --·II· I I I I I I I I I • I I I I I I I I I I I I I I I I I I 3669 (18) ii) the confined space observer sha\l maintain at least voice contact with all personnel in the confined space. Visual contact is preferred, if possible; iii) the confined space observer shall be instructed by his supervisor or the HSO in the method for contacting rescue personnel in the event of an emergency; iv) if irregularities within the confined space are detected by the observer, personnel within the confined space will be ordered to exit; v) in the event of an emergency, the confined space observer must not enter the confined space prior to contacting and receiving assistance from a helper. Prior to this time, he should attempt to remove personnel with the lifeline and to perform all other rescue functions from outside the space; and vi) a helper shall be designated to provide assistance to the confined space observer in case the observer must enter the confined space to retrieve personnel. B-32 CONESTOGA-ROVERS & ASSOCIATES B.18.0 (1) 3669 {18) HEAT STRESS The combination of warm ambient temperature and protective clothing increases the potential for heat stress. In particular, heat stress can be evident as: i) heat rash; ii) heat cramps; iii) heat exhaustion; and/ or iv) heat stroke. These hazards will be discussed during daily safety meetings before commencement of work activities, when relevant. Personnel must increase consumption of water and electrolyte-containing beverages, such as Gatorade, during warm and hot weather conditions. At a minimum, workers will break approximately every two hours for 10-to 15-minute rest periods. In addition, workers will be encouraged to take rests whenever they feel any adverse effects that may be heat related. The frequency of breaks may need to be increased upon worker recommendation to the HSO. A work/rest schedule will be calculated based on heat stress monitoring results. Monitoring will consist of taking the radial pulse of a worker for 30 seconds immediately after exiting the work area. The frequency of monitoring the radial pulse will be as follows: Ambient Temp. Modified Level D PPE(l) Level C PPE/Level B 90°F or above After 45 min. of work After 15 min. of work 87.5°F -90°F After 60 min. of work After 30 min. of work 82.5°F -87.5°F After 90 min. of work After 60 min. of work 77.5°F -82.5°F After 120 min. of work After 90 min. of work 72.5°F -77.5°F After 150 min. of work After 120 min. of work Tyveks on top of Level D PPE. · B-33 CONESTOGA-ROVERS & ASSOCIATES m D 0 0 D m I I I I I I I I I g I 0 I D D a u 0 D ff I D I D D a D D D u 3669 (18) If the heart rate exceeds 110 beats per minute at the beginning of the rest period, the next work cycle will be shortened by 1/2 and the rest period will be kept the same. If the heart rate still exceeds 110 beats per minute at the next rest period, the following rest period will be increased by 1/3. The initial rest period will be at least five minutes. Monitoring for heat stress will begin when the ambient temperature reaches or exceeds 70°F when wearing Level C or Level B PPE, or 80°F when wearing Level D PPE and humidity levels are above 50 percent. B-34 CONESTOGA-ROVERS & ASSOCIATES B.19.0 COLD STRESS 3669 (18) With outdoor work in the winter months, the potential exists for hypothermia and frostbite. Protective clothing greatly reduces the possibility of hypothermia in workers. However, personnel will be instructed to wear warm clothing and to stop work to obtain more clothing if they become too cold. Employees must also change into dry clothes if their clothing becomes wet from perspiration or from exposure to precipitation. In cold weather, the potential for frostbite exists, especially in body extremities. Personnel must pay particular attention to hands, feet and any exposed skin when dressing. Personnel will be advised to obtain more clothing if they begin to experience loss of sensation due to cold exposure. Employees will be encouraged to seek heated shelter at regular intervals, depending upon the severity of ambient temperatures. Symptoms of cold stress, including heavy shivering, excessive fatigue, • ii drowsiness, irritability or euphoria will necessitate immediate return to the I heated shelter. B-35 CONESTOGA-ROVERS & ASSOCIATES I I I I I I 0 u I B D 0 I ATTACHMENT B-1 D TRAINING ACKNOWLEDGMENT FORM I 9 a D ' a - I I I 3669 (18) I I I I ,, I I ' ' ' I e t t D ft ·B fl I TRAINING ACKNOWLEDGMENT FORM Please Print NAME: ADDRESS: SOCIAL SECURITY NUMBER: EMPLOYER: JOB SITE: TADCO-HUGHES SITE. GASTON COUNTY. NORTH CAROLINA I have attended and understood the mandatory site-specific initiation session for the above referenced job site. This program referenced the following topics: i) known potential hazards on site; ii) level of personal protection equipment required; iii) emergency procedures for the site; and iv) the basics of the Site-specific Health and Safety Plan. I further confirm that I have the required 40 hours of training to comply with 29 CFR 1910.120, have a respirator for which I have been fit tested and have been thoroughly trained on the standard operating procedures of equipment I will be operating or procedures (i.e. confined space) which I will be participating in. Date Signature 3669 (18) CONESTOGA-ROVERS & ASSOCIATES I I I I ,, I ' ' ATTACHMENT B-2 ' CONFINED SP ACE ENTRY PERMIT t t ' t ' a tt I ' '---· D 3669 (18) I I CONFINED SPACE ENTRY PERMIT I SITE NAME/LOCATION/REF. NO.: !adco-Hughcs Site I Gaston Count)c, North Carolina I WORK ACTIVITY: Duration: Issue Date: Ttm:,: Filled Out by: I I POTENTIAL HAZARDS: (System Generated) ' ,, 0 t ' (Work Generated) I :t ' I AIR MONITORING: PRE-ENTRY PERIODIC CONTINUOUS I I 3669 08) B-2-1 CONESTOGA-ROVERS & ASSOCIATES I CONFINED SPACE ENTRY PERMIT DATE/TIME ISOLATION: BY (]NIT) ppm co Purging Required: YES NO Safety Tags Required: YES VENTILATION REQUIRED: YES CONTINUOUS NO NO OTHER EMERGENCY RESCUE EQUIPMENT REQUIRED: ________ Communications Device ________ .First Aid Kit ________ S.tretcher /Backboard ________ Fire Extinguisher ________ SCBA % LEL OTHER TEST TYPE RESULT PURGING CONFIRMED: ________ Winch/Hoist ________ Harness with Lifeline (type) ________ PPE (type) ________ Lighting (type) ________ Otrcr _______________________ _ I ' I I I I I I ,,. ,,-. ,, ,. g -u tl ., ' I 3669 (18) B-2-2 CONESTOGA-ROVERS & ASSOCIATES I I I u 8 D I I I f I ,, I} ,, I I ,, ~I I' ' ' ,, I I CONFINED SPACE ENTRY PERMIT PERSONAL PROTECTIVE EQUIPMENT REQUIRED: ________ Hardhat ________ ,Safety Glasses ________ Face Shield ________ Ear Plugs/Muff ________ Emergency Escape Pack ________ Lanyards ________ Respiratory Protection (type) ________ Coveralls Chemical Suits ________ Rain Suits ________ Li,fclines ________ Qovcs(typc) _____________________ _ ________ Hamcs.<c;(typc) ____________________ _ ________ Olrr _______________________ _ ADDITIONAL WORK INSTRUCTIONS: EMERGENCY CONTACT PHONE NO., ___________ _ PERSONS ENTERING CONFINED SPACE (PRINT NAME) ST AND BY PERSON REQUIRED: YES:~ ___ NO~ ___ ,(PRINT NAMES) 3669 {18) B-2 - 3 CONESTOCA-ROVERS & ASSOCIATES CONFINED SPACE ENTRY PERMIT I have reviewed and met the requirements of this permit and expect that this work shall be done safely. Entrants have been instructed on the proper confined space entry procedures, requirements and conditions. ENTRY AUTI-IORIZED BY:. ____________ _ DATE:~--------- All work under this permit has been completed and all materials and entrants have been withdrawn from the confined space. Attendant or Entrant Date 3669 08) B-2-4 CONESTOGA-ROVERS & AssOOATES I j ' I ' I, ,. I ,, \.• I ,.· I t 'I ,I ,, I I I I :I I I I .a APPENDIXC " I CONSTRUCTION QUALITY ASSURANCE PLAN I I .I I I ') I - I ' I 3669 (18} ' I I j I ,I I I , .... · I t I I ,. I I I ' 1. I I '-: I TABLE OF CONTENTS C.1.0 INTRODUCTION ........................................................... : ....................................... C-1 C.2.0 PROJECT DESCRIPTION ....................................................................................... C-2 C.3.0 PROJECT ORGANIZATION AND RESPONSIBILffiES ................................ C-3 C.3.1 PROJECT MANAGER. ............................................................................... C-3 C.3.2 PROJECT ENGINEER. ................................................................................ C-3 C.3.3 RESIDENT ENGINEER ............................................................................. C-4 C.3.4 CQA SUPPORT PERSONNEL. ................................................................. C-4 C.3.5 QA/QC TEST LABORATORIES .............................................................. C-5 C.3.6 CONTRACTOR ........................................................................................... C-5 C.4.0 PERSONNEL QUALIFICATIONS ....................................................................... C-6 C.4.1 RESIDENT ENGINEER ............................................................................. C-6 C.4.2 CQA SUPPORT PERSONNEL. ................................................................. C-6 C.4.3 CONTRACTOR ........................................................................................... C-6 C.5.0 PROJECT MEETINGS ............................................................................................. C-8 C.5.1 PRECONSTRUCTION MEETING ........................................................... C-8 C.5.2 DAILY PROGRESS MEETINGS ............................................................... C-9 C.5.3 PERIODIC PROGRESS MEETINGS ......................................................... C-9 C.5.4 PROBLEM OR WORK DEFICIENCY MEETINGS ............................... C-10 C.6.0 INSPECTION AND TESTING ACTIVITIES ..................................................... C-11 C.6.1 SCOPE ............................................................................................................ C-11 C.6.2 INSPECTIONS ............................................................................................. C-12 C.6.3 TESTING ....................................................................................................... C-14 C.7.0 CQA DOCUMENTATION .................................................................................... C-15 C.7.1 GENERAL. .................................................................................................... C-15 C.7.2 CONTRACTORS DAILY LOG BOOK ..................................................... C-15 C.7.3 CQA INSTRUMENT CALIBRATION ................................................... C-16 C.7.4 INSPECTION LOG BOOK ......................................................................... C-16 C.7.5 PROBLEM/CORRECTIVE ACTION REPORTS ................................... C-17 C.7.6 WORK TASK REPORTS ........................................................................... C-18 C.7.7 REMEDIAL ACTION (RA) REPORT ...................................................... C-18 C.7.8 STORAGE OF RECORDS .......................................................................... C-19 3669 (18) CONESTOGA·ROVERS & ASSOCIATES I I ./ I I I ,I I' 1, I Ii I I I I t I I -. I '."/ I LIST OF FIGURES FIGURE C.3.1 PROJECT ORGANIZATION LIST OF TABLES TABLE C.6.1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE 1NSPECTIONS TABLE C.6.2 SUMMARY OF CONSTRUCTION Following Page C-3 C-13 QUALITY ASSURANCE TESTING REQUIREMENTS C-14 LIST OF ATTACHMENTS ATTACHMENT C-1 TYPICAL CONTRACTORS DAILY LOG BOOK 3669 (18) CONESTOGA-ROVERS & ASSOOATES I I I I I I ff ff fl fl C.1.0 INTRODUCTION 3669 08) This Construction Quality Assurance Plan (CQAP) presents the quality assurance program to be implemented during the Remedial Action (RA) as detailed in the RA Work Plan, to ensure that the components of the RA are constructed to meet or exceed all design criteria, plans and specifications. This report is organized as follows: i) ii) iii) iv) v) Section C.1.0 presents the background information, purpose and organization of the report; Section C.2.0 provides a description of the project; Section C.3.0 outlines the project organization and responsibilities; Section C.4.0 presents the personnel qualifications requirements; Section C.5.0 presents the project meeting requirements; vi) Section C.6.0 describes the inspection and testing activities required to ensure that construction and materials comply with all design specifications and plans; and vii) Section C.7.0 describes documentation requirements of construction quality assurance (CQA) activities. Construction specifications for the Remedial Action components are provided in the Appenclices to the Final Design Report, and also in the Construction Drawings provided in the Final Design Report. C-1 CONESTOCA·ROVERS & ASSOCIATES C.2.0 PROJECT DESCRIPTION 3669 (18) The major components of the RA to be implemented at the Site consist of the following: 1) 2) Excavation and repair of the damaged sections of the Site culvert followed by slip-lining of the culvert with butt-welded polyethylene pipe, construction of a gravity drainage line to carry uncontaminated groundwater from the spring discharge to the Tributary B north of the Former Operations Area and construction of a surface water diversion consisting of a Site spillway. Construction of a groundwater extraction system within the Site boundaries including four extraction wells, in areas of elevated contaminant levels, a subsurface drainage tile trench to collect contaminated groundwater and a groundwater collection sump in the annulus of the slip-lined culvert to collect groundwater that is presently discharging to the culvert; 3) Construction of an on-Site treatment system. The system shall consist of aeration and equalization tanks. The air vented from the aeration tank shall be treated by carbon adsorption. The effluent from the treatment system shall be pumped to the City of Mount Holly sanitary sewer system manhole for subsequent treatment at the publicly owned ' 4) 5) treatment works (POTW); Treatment of soils in the former landfill and approximately 500 c.y. of soil from the Former Operations Area which are to be consolidated into the former landfill; and Construction of a soil flushing system utilizing some of the components of the SVE system and installing a soil flushing collection trench for future operation. This SVE system construction includes the consolidation of surplus excavated soils from the groundwater extraction system and treatment facility construction into a soil cap on the surface of the former landfill. C-2 CONESTOGA-ROVERS & ASSOCIATES D I I I I I I I I I I t I I I I I I· C.3.0 PROTECT ORGANIZATION AND RESPONSIBILITIES 3669 (18) The remedial construction activities will be supervised by Conestoga-Rovers & Associates (CRA). The project organization chart is presented on Figure C.3.1. A brief description of the duties of the key personnel are presented below. C.3.1 PROTECT MANAGER i) ii) iii) iv) v) The duties of the Project Manager are as follows: provides overall project management; ensures professional services by' CRA are cost effective and of highest quality; ensures all resources of CRA are available on an as-required basis; participates in key technical negotiations with USEP A; and provides managerial and technical guidance to CRA's Project Engineer. C.3.2 PROTECT ENGINEER i) ii) iii) iv) v) The duties of the Project Engineer are as follows: provides day-to-day project management; provides managerial guidance to CRA's technical group; provides technical representation at meetings as appropriate; retains testing firms to perform' quality control field/laboratory tests; and prepares and reviews reports. C-3 CONESTOGA-ROVERS & ASSOCIATES I I I I " m I m u B' • u 8 I' ' I I I II USEPA-REGION IV NORTH CAROLINA DEPARTMENT OF HEALTH MICHAEL TOWNSEND AND NATURAL RESOURCES JADCO-HUGHES TECHNICAL COMMITTEE PROJECT MANAGER STEPHEN OU!GLEY PROJECT ENGINEER J£ANN£ CHEW RESIDENT ENGINEER FIELD ACTIVITIES QA/QC TEST LABORATORIES CQA SUPPORT PERSONNEL eg. -SURVEYING CRA 3669 (18) JAN 28/94(W) REV.1 (C-04) -GEOTECHNICAL -ANALYTICAL SELECTED REMEDIAL CONTRACTOR figure C.3.1 PROJECT ORGANIZATION REMEDIAL CONSTRUCTION ACTIVITIES JADCO-HUGHES SITE Gaston County, NC I I I I I I I I I I I I I I I I I I RICHARD G. SHEPHERD. B.A.Sc .• P. Eng. EDUCATION: B.A.Sc. University of Waterloo 1975 Numerous continuing education courses and seminars in hydrogeology, waste management, construction management and health & safety: 1980 to present. EMPLOYMENT: 1983- Present 1981- 1983 1979-81 1976-79 1975-76 1974-75 1974-75 1973 1971-72 1968-71 Principal Conestoga-Rovers & Associates Associate Conestoga-Rovers & Associates Senior Engineer Conestoga-Rovers & Associates Engineering Services Manager Malawi/Canada Railway Project Project Engineer, Steed and Evans Co. Ltd., Kitchener Project Supervisor, Steed and Evans Co. Ltd., Kitchener University of Waterloo, Department of Civil Engineering Construction Layout Supervisor, Steed and Evans Co. Ltd., Kitchener Design Technician, City of Brantford Engineering Department Survey party chief, J. D. Lee Engineering Limited, Kingston and Brantford PROFESSIONAL AFFILIATIONS: Association of Professional Engineers of Ontario Canadian Society of Civil Engineers D Richard G. Shepherd D PROFILE OF PROFESSIONAL ACTIVITIES: • Corporate responsibility for all administration and project management of remedial construction related to remedial action implementation. • Corporate responsibility for Health and Safety. • Corporate responsibility for Analytical Services. • Senior Engineering Supervisor /Project Manager for in excess of 600 environmental remedial projects. Areas of experience with selected example projects are: Remedial Investigation /Feasibility Studies -Hardeman County Site, Hardeman County, Tennessee (NPL Site) -Yellow Water Road Site, Baldwin Florida (NPL Site) -Love Springs Site, Cherokee County, South Carolina (State Listed Site) -Carolawn Site, Chester County, South Carolina (NPL Site) -Mallory Capacitor Site, Waynesboro, Tennessee (NPL Site) -North Hollywood Dump, Memphis Tennessee (NPL Site) -C. L. Hale Site, Ohio (NPL Site) -Jadco-Hughes Site, North Carolina (NPL Site) -FMC South Site, Fridley, Minnesota (NPL Site) -Universal Manufacturing, Bridgeport, Connecticut (State Listed Site) -FMC Plant Site, Middleport, N.Y. (State·Listed Site) -Mallory Site, Glasgow, Kentucky -Tonawanda Coke, Tonawanda, N.Y. (State Listed Site) -Cedartown Landfill, Cedartown, Georgia (NPL Site) -Packaging Corporation of America Site, Manistee, .Michigan (NPL Site) -Vulcan Cincinnati Site, Northport, Michigan (State Listed Site) -Heavy manufacturing complex, Peoria, Illinois (State Listed Site) -J. I. Case Site, Terre Haute, Indiana (State Listed Site) -Ellis Road Site, Jacksonville, Florida (NPL) Site Design and Project Management of Remedial Construction -Decommissioning of PCB contaminated waste oil recycling facility, Dearborn, Michigan (CERCLA 106 Order) -Chem-Dyne Site, Hamilton, Ohio (NPL Site) -Yellow Water Road Site, Baldwin, Florida (NPL Site) 2 D 0 D D 0 D 0 D 0 D D 0 0 I 0 D 0 I I I I I I I I I u D D D D I I I u Richard G. Shepherd Ellis Road Site, Jacksonville, Florida (NPL Site) -North Hollywood Dump, Memphis, Tennessee (NPL Site) -Hardeman County Landfill, Tennessee (NPL Site) -LaBounty Landfill Site, Charles City, Iowa (NPL Site) -PAS Site, Oswego, New York (NPL Site) Bluff Road Site, Columbia, South Carolina (NPL Site) -Decontamination of four capacitor plapts, Kentucky, Tennessee and Indiana -Universal Manufacturing Sites, Totowa; New Jersey and Bridgeport, Connecticut (State Listed Sites) -Love Canal, Niagara Falls, New York (NPL Site) -Plant demolition and cleanup, Racine; Wisconsin (private action) -Waukegan Asbestos Landfill, Waukegan, Illinois (NPL Site) -Cleanup and demolition of manufacturing plant, Manville, New Jersey (State Site) -Velsicol Chemical Corporation Site, Marshall, Illinois (NPL Site) -Pentachlorophenol Site Remediation, Fort Lauderdale, Florida (State) -Michigan Chemical Site, St. Louis, Michigan (NPL Site) Acquisition/Sale of Industrial/Commercial Facilities -Facility assessment, recommendation of remedial measures, design of remedial measures for 21 operating companies in seven States in Illinois bankruptcy case -Site assessment, design of remedial measures, management of remedial construction for 300 surplus properties (heavy equipment dealerships, parts distribution centers and manufacturing plants across U.S.A. and Canada) -Assessment and investigation of a 76 retail gasoline facility chain, recommendation of remedial actions, preparation of remedial cost estimates (Florida, Georgia) Assessment and investigation of nine 'bottling facilities in Louisiana, Arkansas and Texas, recommendation of remedial actions, preparation of remedial cost es ti mates -Assessment and investigation of retail/wholesale gasoline chain, recommendation of remedial actions, preparation of remedial cost estimates (North Carolina, South Carolina) -Assessment and remediation of 12 bottling and distribution facilities with respect to underground storage tanks (Georgia, North Carolina, South Carolina) -Assessment and investigation of 8,000-acre manufacturing and mining complex, development of remedial alternatives, preparation of remedial cost estimates, technical assistance in negotiation of Agreement and Covenant Not to Sue with USEPA (Tennessee) -Environmental Assessments of 14 manufacturing companies, preparation of 3 Richard G. Shepherd remedial plans to bring facilities into compliance, preparation of cost estimates as part of Chapter 7 proceedings for bankrupt holding company (Illinois, Indiana, Michigan, Sou th Carolina) -Environmental assessments of two cement companies and nine terminals, preparation of remedial work plans, preparation of remedial cost estimates (Iowa, Mississippi) Environmental Assessments of nine manufacturing facilities, preparation of remedial recommendations and cost estimates (Brazil) Environmental Assessments of manufacturing and bottling facilities, preparation of remedial recommendations and cost estimates (Belgium, France, Swaziland) -Environmental Assessment, design of remedial measures, management of remedial construction for heavy manufacturing facility (Germany) Environmental Assessment, hydrogeologic investigation, design of remedial measures, management of remedial construction at metal plating facility (Indiana) Environmental Assessments of seven bottling/ distribution facilities, preparation of remedial cost estimates and compliance recommendations (North Carolina and Virginia) -Environmental Assessments of three bottling/ distribution facilities, preparation of remedial cost estimates and compliance recommendations (Sou th Carolina) Technical Negotiator for Consent Order/ Agreements or Selected Remedy Settlements -Michigan Chemical Site, St. Louis Michigan (USEP A, MDNR) -FMC Fridley Site, Fridley, Minnesota (USEPA, MPCA) -North Hollywood Dump, Memphis, Tennessee (USEPA, TDHE) -Two manufacturing sites (IBM), New York (NYDEC) -Decommissioning of Waste Oil Recycling Facility, Dearborn, Michigan (USEPA) Yellow Water Road Site, Baldwin, Florida (USEPA, FDER) -Several Remedial Actions, Middleport, New York (NYDEC) Mallory Site, Crawfordsville, Indiana (USEP A, IDEM) -Chem-Dyne Site, Hamilton, Ohio (USEP A, OEPA) -Summit National Site, Deerfield County, Ohio (USEPA, OEPA) -Miami County Incinerator Site, Troy, Ohio (USEPA, OEPA) -Mallory Site, Waynesboro, Tennessee (USEPA, TDHE) -Sun Bank Site, Fort Lauderdale, Florida (FDER) -CIW Site, Romulus, Michigan (USEPA, MDNR) -Vulcan Site, Northport, Michigan (USEPA, MDNR) -Ventron Site, Woodbridge, New Jersey (NJDEP) 4 D 0 u I I I I I I I I I I I I I I I I I I I I I I I I I I I Richard G. Shepherd -J. I. Case Site, Terre Haute, Indiana (IDNR) -Love Springs Site, South Carolina (SCDHEC) ' Peer Review of RI/FS, ROD, RD/RA or Administrative Record -American Chemical Services Site, Griffith, Indiana (NPL Site) -Wayne Recycling Site, Columbia City, Indiana (NPL Site) -Arlington Blending/Galloway Pits, Tennessee (NPL Site) -Picketville Landfill, Jacksonville, Florida (NPL Site) -Mabray Engineering Site, Alabama (NPL Site) -United Scrap Lead Site, Troy, Ohio (NPL Site) -Three RI/FS's at manufacturing facilities in three States (confidential) -Newport Dump, Newport, Kentucky (NPL Site) -Fultz Landfill, Cambridge Ohio (NPL Site) Expert Testimony -Litigation involving PCB and volatile organic contamination of building, soil and groundwater in Waynesboro, Tennessee. Testimony focussed on appropriate level of cleanup, construction methods to be used for cleanup, cost of cleanup. -Litigation involving excavation and disposal of drummed wastes and contaminated soils, Picillio Site, Rhode Island. Testimony focussed on appropriateness of remedial construction techniques employed by State, appropriateness of costs incurred by State. -Litigation involving contamination of soils and groundwater at former gasoline station in Charlotte, North Carolina. Testimony focussed on contaminant source identification, contaminant transport, remediation costs. -Litigation involving soil and groundwater contamination in Royal Oak, Michigan. Testimony focussed on contaminant source identification, contaminant transport, remediation techniques and costs. -Litigation involving soil contamination in St. Louis, Michigan. Testimony focussed on contaminant source identification and contaminant transport. -Five cases pending (North Carolina, South Carolina, Iowa, Indiana, Michigan) involving VOC contaminated groundwater (toxic tort), release from and remediation of USTs and contents; appropriateness of methods used and costs incurred for facility PCB decontamination work; divisibility of former and current releases from furniture refinishing manufacturer. 5 Richard G. Shepherd -Environmental Assessments of three bottling/ distribution facilities, preparation of remedial cost estimates and compliance recommendation (North Carolina). Environmental Assessments of 17 bottling/ distribution facilities, preparation of remedial cost estimates and compliance recommendation (Brazil) Special Court Master -Appointed Special Court Master to the Federal District Court, Northern District, Illinois. Responsible for the administration, design and management of remedial activities including the decommissioning, asset recovery, demolition and surficial cleanup of a 270-acre oil refinery in East Chicago, Indiana. Cost Allocation Provided technical assistance in development of cost allocation strategies for potentially responsible parties (PRPs) including database preparation and remedial component analysis -Newport Dump Site, Newport, Kentucky (NPL Site) -Miami County Incinerator Site, Troy, Ohio (NPL Site) -Hunts Disposal Landfill, Wisconsin (NPL Site) -Hardage Site, Criner, Oklahoma (NPL Site). 6 0 0 D D fl B • m - I I I I I I I I I I I I I I I I I I I I I· I I I I I STEPHEN M. QUIGLEY. B. Tech .. P. Eng. EDUCATION: 1979-84 B. Tech. (Chemical Engineering), Ryerson Polytechnical Institute EMPLOYMENT: 1991 - present 1989 -90 1988-89 1987-88 1984-87 1984 Project Manager, Conestoga-Rovers & Associates Project Engineer, Conestoga-Rovers & Associates Project Engineer, Canada Packers Specialty Chemical Group Production Foreman, Canada Packers Specialty Chemicals Group Health, Safety and Environmental Supervisor, Canada Packers Chemicals Division Quality Control Technician, Canada Packers Chemicals Division AFFILIATIONS: Member -Association of Professional Engineers of Ontario. PROFILE OF PROFESSIONAL ACTIVITIES: • Environmental Engineer responsible for one or more of the following: site investigation, site characterization, feasibility studies, litigation/hearings support, remedial design; contract document and specification preparation, and construction supervision for the following projects/ clients: -Remediation engineering project manager for groundwater, buried waste, environmental audit and Environmental Appeal Board hearings -Uniroyal Chemical Ltd., Elmira, Ontario, 1989 -ongoing. Stephen M. Quigley -Project Manager for Remedial Investigation (RI), Feasibility Study (FS), Remedial Design (RD) and Remedial Action (RA) including coordination of field work, database management, laboratory service coordination, preparation of Treatability Study Work Plans, completion of RI and FS reports, supervision of PCB-contaminated soil excavation and off-Site disposal, preparation of RD and Work Plans and development of RD documents, for a former solvent recycling/ disposal facility, Jadco-Hughes NPL Site, Belmont, North Carolina (Generator Group), 1989 -ongoing. -Project Manager for drum removal action, including development of Work Plan, Contract Documents and Specifications and provision of Construction Supervision, Northline Drums Site, Wayne County, Michigan. -Remedial Investigation, including development of Work Plans, Contract Documents and Specifications, waste excavation including buried drums and contaminated soil, Cherokee County, South Carolina, 1991 -ongoing. -Technical manager, provision of technical advice and expert witness testimony, preparation and implementation RI/FS Work Plan, West Central Phoenix/West Osborn Site, Maricopa County, Arizona, 1991 -ongoing. -Technical manager, completion of site investigation, provision of technical advice in negotiations with state agency and USEPA regarding issuance of a RCRA HSWA permit, Florida, 1991 -ongoing. -Remedial Action, design of remedial measures for a drummed inventory of · wood treating solution recovered from underground storage tanks, including the development of woi-k plans and contract documents and construction supervision, and implementation and completion of a Contamination Assessment Report, Ft. Lauderdale, Florida, 1989 -ongoing. -Project Manager for Feasibility Study, RD/RA development and evaluation of remedial alternatives for a former hazardous waste landfill including the preparation and oversight of a TO-1/T0-2 air monitoring program, critique of the EPA Risk Assessment, preparation and implementation of RD/RA Work Plans, Consent Decree negotiations, design and implementation of remedy, (Cap, groundwater extraction/trenching, reinjection system, soil vapor extraction system), Hassayarnpa Landfill NPL Site, Maricopa County, Arizona, (PRP Group), 1989 -ongoing. -Technical overview of groundwater remedial action plan and technical review of 30% Remedial Design for a VOC contaminated aquifer, Indian Bend 2 m m u D fl 0 0 0 0 0 0 u u ·I u I a m m I I I I I I I I I I I I I I I I Stephen M. Quigley Wash NPL Site Operable Unit Feasibility Study and Record of Decision, Scottsdale, Arizona NPL Site (PRP Grciup), 1989-1991. -Litigation support including preparation of a critique of a contractor's Rl/FS, a conceptual closure design and reports •on state-of-the-art of landfill practise, 19th Avenue Landfill NPL Site, Maricopa County, Arizona, 1990-ongoing. -Litigation support for suit related to the potential contamination of a food product including plant assessment, collection of environmental samples and data assessment (location confidential) 1990 -ongoing. -Project Manager and Auditor, site assessments for four automotive plastic injection molding plants, Ontario, Canada and Michigan, 1992. -Auditor, site assessments for soft drink bottling plants, North Carolina, 1992. -Critique of plaintiff's release estimates, air dispersion modeling and litigation support related to U.S. Department of Energy Facility (PRP), 1989-1991. -Technical coordination of intervenor group -cogeneration and hydrogen production, environmental assessment hearings related to 25-year Demand/Supply Plan, Ontario Hydro, 1991 -ongoing. -Remedial action -oil recovery system, including work plan development, permitting, negotiation of Contract Documents and Specifications, Rock Island, Illinois, 1990-1991. -Site assessment and evaluation of remedial alternatives, former solvent bulking and storage facility, Hartford, Connecticut 1989 -ongoing. -Plant Assessment for discharges to municipal treatment plant including a critique of municipal consultants sewage treatment plant design, data assessment, plant operations assessment, design and construction of pretreatment facilities, dairy plant, O1:}tario, 1990 -1992. -Assessment of a conventional spray irrigation effluent treatment system for a dairy plant, Ontario, 1991 -1992. • Technical Specialist/Project Engineer for the following project areas: -development and implementation of environmental waste treatment and general engineering projects; 3 Stephen M. Quigley -supervision and operation of a continuous batch process specialty chemical plant; -development and implementation of an Environmental Protection Plan and spill response plan for Canadian chemical manufacturer; -preparation of hazardous effluent _discharge permits; -project management of source monitoring for small scale S02 emission generator; -development and implementation of national training program for dangerous goods transportation and health, safety and environmental protection; -participation in environmental risk assessments; -co-development of corporate health and safety rating system for a Canadian food company; · -development and implementation of industrial. hygiene surveys and analyses; and -supervision of the development on asbestos removal training program. PUBLICATIONS AND SEMINARS Laboratory Decommissioning, OH&S Canada, November/December 1992. Integration of Environmental Management and Occupational Health and Safety, Occupational Safety and Health '91 Conference .. Evolution of Environmental Regulations in Ontario, Canadian Society of Safety Engineers Meeting, February 1991. 4 I I I I I I I I I I I) I I I I I I I I JEANNE CHEW. B.A.Sc EDUCATION: B.A.Sc. Chemical Engineering University of Waterloo, 1991 OTHER COURSES: 40-Hour OSHA Health and Safety Training 29 CFR 1910.120, February, 1992 EMPLOYMENT: 1991 - Present 1990 1989 1988 1987 Environmental Engineer Conestoga-Rovers & Associates· Junior Environmental Engineer Huskey Oil Operations Limited Junior Environmental Engineer Maclaren Engineers Incorporated Junior Process Engineer Abitibi-Price Research Assistant Petro-Canada PROFILE OF PROFESSIONAL ACTIVITIES: • Preparation of various reports including; ,Proposals for Professional Services, Rl/FS Reports, RD/RA Work Plans, Sampling and Analysis Plans, Health and Safety Plans, and Treatability Study Plans, • Air and Wastewater sampling activities. • Computer modelling of air dispersion, process control and gas generation in landfills. · • Preparation and expedition of contract documents. 0 Jeanne Chew n • Cost estimation. D~ • Conducting lab scale treatability studies. 0 • Compliance evaluations with Regulatory Criteria. • Production operation using statistical process control. 0 • Gasoline Research in catalytic cracking. u • Data management and analysis. ·D u 0 U: ,fl D n D D I D 2 0 D I I I I I m m I ' u D u I B u D I B D WOLFGANG (WOLFE) K. F. ENGLER, C.E.T. EDUCATION: Diploma Course Certification Course Civil Technician, 1970, Cambrian College, Sudbury Campus Practical Environmental Law, 1985 Civil Technologist, 1986, Ontario Association of Certified Engineering Technicians and: Technologists Environmental Compliance Audits and Site Assessments, 1989 EXPERIENCE: . 1980- Present 1981- Present 1976-81 1975-76 1975 1971-75 TRAINING: Associate Conestoga-Rovers & Associates Resident Engineer Conestoga-Rovers & Associates Manager, Kincardine Branch Conestoga-Rovers & Associates Manager -Kincardine Branch Conestoga Engineering Limited · Proctor and Redfern Consulting Engineers Dennis Consultants Limited -Compliance with OSHA 1910.120 and 1910.134 requirements Asbestos Abatement Supervisor -State of Minnesota AFFILIATIONS: Engineering Technologist -1986, Ontario Association of Certified Engineering Technicians & Technologists Technical Affiliate -The Engineering Institute of Canada Wolfgang (Wolfe) K.F. Engler Technical Affiliate -The Canadian Society for Civil Engineering Member -American Society of Certified Engineering Technicians (ASCET) COMMUNITY AFFILIATIONS: Past-President -Kincardine Rotary Club PROFILE OF PROFESSIONAL ACTIVITIES: -Resident Engineer and assistant Project Manager, asbestos abatement, lead abatement and PCB sampling, cleanunp and removal -Old Mack Stamping Plant, Chrysler Corporation, Detroit, Michigan -Resident Engineer Supervisor, lab pack removal, and tank and process pipe cleaning, White Chemical Site, Newark, New Jersey -Resident Engineer Supervisor, PCB contaminated soil and concrete removal, Totowa, New Jersey -Resident Engineer and assistant Project Manager, Asbestos Abatement, UST removal, PCB cleanup, installation of 20-acre cap, installation of a discharge basin and lagoon closures, former Johns Manville Site, Manville, New Jersey -Fourteen years experience in field investigations, design, contract administration and field supervision of numerous environmentally oriented projects -Site Monitoring Supervisor, drum and contaminated soil characterization, cleanup and removal -Love Springs Site, Cherokee County, South Carolina -Resident Supervisor in charge of site survey, drummed waste cleanup, hazardous waste inventory and removal, including lab packs, unknown cylinders, air and water reactives and shock sensitive materials -Former Recycling Site, Bluff Road, Columbia, South Carolina -Resident Engineer for drum sampling, waste characterization, staging, site securement and disposal -Gibbs Plating Site, Charlotte, North Carolina -Resident Supervisor and assistant project manager, securement of hazardous waste landfill, Velsicol Chemical Co., Hardeman County, Tennessee 2 g g u m g 11 I I I I ·1 I I ' I I I a B 0 I I I I I I I I I I I I I Wolfgang (Wolfe) K.F. Engler -Resident Engineer, waste characterization, cleanup and disposal of surficial drummed and tanked hazardous wastes -PAS Reclamation Site, Oswego, New York -Resident Engineer, drum and contaminated soil characterization, cleanup and removal, site test trenches and installation of monitoring wells -Ardenwood Estates, Staten Island, New York -Site Monitoring Engineer representing PRP group to oversee the Emergency Response cleanup action by the State of New York for drum and contaminated soil characterization, cleanup and removal -Novak Farm Site, Chenango County, New York -Site Monitoring Supervisor, drum and contaminated soil characterization, cleanup and removal -Lincklaen, Cortland County, New York -Resident Engineer and Safety Officer, Cleanup and disposal of contaminated soils -IBM Corporation, Poughkeepsie, New York -Resident Supervisor and Safety Officer for borehole sampling of contaminated soils, and installation of monitoring wells -Chem-Dyne Site, Hamilton, Ohio ' -Field Supervisor and technician for borehole sampling of contaminated soils - IBM Corporation, Poughkeepsie, New York -Resident Supervisor for test pit and borehole sampling of contaminated soils, and construction of decontamination facilities -FMC Manufacturing Facility, Minneapolis, Minnesota -Site Monitoring Supervisor, drum and contaminated soil removal, test trenches and sampling and waste characterization program -Nepera, Harriman and Hamptonburg, Orange County, New York -Project Manager, planning and design of a major recycling facility -IBM Corporation, Poughkeepsie, New York -Resident Engineer, storm water retention ~asin -ManviHe Sales Site, Manville, Somerset County, New Jersey -Resident Engineer, Asbestos Abatement and Demolition -Manville Sales Site, Manville, Somerset County, New Jersey 3 Wolfgang (Wolfe) K.F. Engler · -Project Manager, planning and design for a construction debris landfill -IBM Corporation, Poughkeepsie, New York -Project Manager, emergency response and closure of waste fuel and oil underground storage facility -Brinks Armored Service, Buffalo, New York -Project Manager, planning, design and supervision of a 45,000-gallon aboveground Jet A fuel storage, containment and dispensing facility, flight operations -IBM Corporation, Dutchess County, New York -Quality Assurance Supervisor, industrial waste treatment plant expansion -IBM Corporation, Poughkeepsie, New York -Field Supervisor for the disposal of oil refinery products -ECI, East Chicago, Indiana -Resident Engineer on numerous environmentally related projects -IBM Corporation, Poughkeepsie, New York -Resident Engineer, numerous tank closures -IBM Corporation, Poughkeepsie, New York -Resident Engineer, numerous tank closures -Johnson and Johnson, New Brunswick, New Jersey -Resident Engineer, fuel tank replacements with double wall tanks -IBM Corporation, Poughkeepsie, New York -Resident Engineer, lagoon closure -IBM Corporation, Poughkeepsie, New York -Resident Engineer and Safety Officer, Disposal of underground tank -Nassau, Long Island, New York -Field technician responsible for securement and disposal of radioactive soils and equipment -Velsicol Chemical Plant Site, St. Louis, Michigan -Field technician involved in preliminary and final design, securement of hazardous waste -Velsicol Chemical Plant Site, St. Louis, Michigan -Field technician involved in preliminary and final design of several toxic and hazardous waste projects for Occidental Chemical Co. in the Niagara Falls, New York area 4 D g I I I I I I I I I I I I I I I I D 0 I I I I I I I I I I I I I I Wolfgang (Wolfe) K.F. Engler -Seven years experience in design and field supervision of municipal engineering projects -Experience in cost analysis for determining project feasibility Extensive exposure to the planning and approval process of varied forms of development projects -Preparation of recreation feasibility studies for municipalities in the Bruce County area -Resident inspector for the Bruce Agripark Joint Venture in the construction of a combined one acre prototype greenhouse and hydroponic house utilizing waste heat -Project Manager on several municipal and residential developments in the Bruce County area. These projects have included the necessary planning and engineering approval procedures -Project Manager of a 750 lot subdivision in the Town of Kincardine -Preliminary field pick-up and design of a 270 lot subdivision in the City of Sudbury -Inspector for a Ministry of Transportation and Communications urban road reconstruction project in the City of Sudbury (urban renewal) -Design, supervision and inspection of numerous park projects and school sites in the Sudbury and surrounding areas -Project coordination, supervision and inspection for a ski hill in Sudbury employing lighting and snow making apparatus -Site inspector for numerous subdivisions in the Sudbury and surrounding area -Twenty-two years experience in field surveying, drafting, minor design for municipal engineering projects 5 a u u I I I I I I I I I I I I I I I I MARK C. GUTHRIE, P, Eng. EDUCATION: B.A.Sc. University of British Columbia Civil Engineering, 1987 Short Course Sewer Inventory Maintenance (SIMS) Implementors Seminar, sponsored by the MOE and the Tri-Committee EMPLOYMENT: 1987- Present Project Engineer Conestoga-Rovers & Associates 1986 1985 1984 Acres International Limited (summer term) Acres International Limited (summer term) SB Geological Associates (summer term) AFFILIATIONS: Member -Association of Professional Engineers of Ontario PROFILE OF PROFESSIONAL ACTIVITIES: -Conceptual and detailed design of water treatment and storage facility employing aeration and activated carbon adsorption units. -Detailed design of watermain river crossing using horizontal directional drilling or conventional open cut construction methodology. -Design and material specification for a package water treatment facility employing floculation and filtration. -Conceptual design and preparation of Class Environmental Assessments for water and sewage projects in Kincardine, Belleville, Brownsville, and Embro. I -Design of 3,000 Litre/minute groundwater pumping facility incorporating wet well storage and high lift turbine pumps for the Village of Dorchester. Project involved extensive environmental impact assessment under the Class EA Process for projects of this nature. Mark C. Guthrie Distribution system analysis, including extended period simulation, of Dorchester's water system using KYPIPE. -Design and implementation of a Supervisory Control And Data Acquisition (SCADA) System for the Village of Dorchester. -Conceptual and detailed design of communal well pumping stations in lnnerkip and Point Clark, including pipe layout, pressure tank sizing, and material specifications. Final Design and Contract Administration for a multi-stage road reconstruction including the replacement of sanitary, storm and watermain in downtown Cambridge (Preston). -Conceptual design for the replacement and realignment of trunk sewers and watermain through downtown Cambridge (Hespeler). Final design and layout of process piping using AutoCAD for the City of Sarnia sanitary landfill leachate treatment facility. Evaluation and undertaking of a flow monitoring program to isolate and quantify the degree of inflow and infiltration upon the sanitary sewer system in Wellesley. -Design of urban stormwater management facilities for a 60 hectare subdivision in Waterloo, and smaller commercial sites using the computer software MIDUSS and HYMO. -Supervision of sewer and watermain construction for a 54 lot subdivision in Stratford. -Development of an AutoCAD interface to the Total Station surveying equipment to automate the inclusion of detail information on base drawings. Engineering surveying using a Geodimeter 420 Total Station for construction layout, topographic mapping, and detail pick up of existing features. Structural analysis and design of 25 tonne capacity crane griders and columns under numerous loading conditions with the aid of mainframe computer simulation and spreadsheet analysis. -Stability investigation of a hydro-electric facility in New Brunswick, including applied soil mechanics, and earthquake simulation. -Geological mapping of subterranean formations for the purpose of petroleum exploration. 2 I I I I I I I I I I I I I I I I I I I a I R I I I I I I I I I I I I I I I I IANV. MCRAE EDUCATION: 1985 Certificate of Completion, Corrosion Prevention and Control, Carboline Company, St. Louis, Missouri. 1980 1977 1975 Certificate of Completion, Construction Specification Writing, ATB Courses Inc., Toronto, Ontario. Certificate of Completion, Maintenance and Marine Coatings Technology, Mobil Chemical, Toronto, Ontario. Certificate of Completion, Architectural Hardware Institute, University of Chicago ' 1971 Civil Engineering, 3rd Year, University of New Brunswick EMPLOYMENT: 1991- Present 1986-91 1985-86 1984-85 1979-84 1974-79 1974 1972-74 Contracts Manager Conestoga-Rovers & Associates Senior Contract/Specification Engineer Conestoga-Rovers & Associates Specifications Specialist Husky Oil Operations Ltd., Calgary, Alberta Contract Formation Specialist TransAlta Utilities Corporation, Calgary, Alberta Contract Administrator Monenco Consultants Limited, Calgary, Alberta Senior Specification Writer . New Brunswick Electric Power Commission, Fredericton, New Brunswick Civil Technician Neil and Gunter Ltd., Fredericton, New Brunswick Surveyor /Estimator Desourdy Construction Ltd., Montreal, Quebec m Ian V. McRae I 1971-72 Technical Assistant Lalonde, Valois, Lamarre, Valois and Associates, Montreal, Quebec AFFILIATIONS: Member of American Society for Testing and Materials Member of Steel Structures Painting Council Member of American Water Works Association PROFILE OF PROFESSIONAL ACTIVITIES: • Corporate responsibility for conducting all procurement-related activities for construction projects. • Corporate responsibility for managing and directing the preparation of all project specifications and procurement documents. • Corporate responsibility for ensuring compliance with contract administration and specification writing procedures. Areas of experience with reference to particular projects: -Negotiated contracts with contractors and owners -Developed model specifications, engineering practices, specification writing practice, st~ndards for use in engineering, procurement and construction -Evaluated corrosion protection options for structural steel in a petro-chemical environment -Conducted pre-id conferences and site visits -Reviewed and monitored activities of engineering contractors for conformity with established standards and policies -Formulated contract strategy and developed contractual-legal and contractual-technical language for construction projects including hazardous waste remediation projects, power generating stations, waste treatment and processing facilities, mining 2 I I I I I I I I I I I I I I I I I I I 0 I m I I I I I I I I I I I I I I Ian V. McRae Executed requests for proposals and consulting agreements for environmental and engineering studies including coordination of input from environmental, engineering, legal and government agencies Developed and maintained contractor qualification files Supervised preparation of bid and contract construction documents including specifications for nuclear, thermal and hydro generating plants, mining and airport facilities and equipment and hazardous waste remediation projects Performed contract and purchase order• administration including bidding, bid analysis and evaluation and contract award for public and private sector clients Supervised on-site construction contracts for construction of thermal generating stations Developed company-wide specification 'system including policies and standards and instructed engineering departments on methods of specification writing · Designed tank farm protective coating system and supervised application Performed site surveying, estimating and inspection for highway and bridge construction and municipal work 3 I a 0 u I I I I I I I I I I I I I I I MICHAEL G. MATEYK. P.Geol. EDUCATION: 1973 B.Sc., Geological Sciences, Brock University 1977-78 Graduate Courses in Hydrogeology University of Alberta June 1982 Short Course -Contaminant Hydrogeology University of Waterloo Nov. 1990 Short Course -Dense Immiscible Phase Liquid Contaminants in Porous and Fractured Media Waterloo Centre for Groundwater Research EMPLOYMENT: 1991- Present 1985-91 1983-85 1977-83 1976-77 1974-76 1973-74 Associate and Manager of Hydrogeology Conestoga-Rovers & Associates Senior Hydrogeologist Conestoga-Rovers & Associates President and Senior Hydrogeologist MLM Ground-Water Services Ltd. Project Hydrogeologist and Principal MLM Ground-Water Engineering Project Hydrogeologist EBA Engineering Consultants Ltd. Hydrogeologist James F. Maclaren Ltd. H ydrogeologis t Water Quantity Division Ministry of the Environment, Ontario AFFILIATIONS: Association of Ground-Water Scientists and Engineers Registered Professional Geologist Michael G. Mateyk Association of Engineers, Geologists and Geophysicists of Alberta Member, Board of Directors Waterloo Centre for Groundwater Research PROFILE OF PROFESSIONAL ACTIVITIES: Mr. Mateyk has 20 years of practical experience covering a broad range of hydrogeological issues and investigations throughout Canada and the United States. This experience includes project management, contaminant transport evaluation, Superfund investigations; solid waste site evaluations and groundwater resource development. The following presents some of Mr. Mateyk's experience: • Corporate responsibility for the quality assurance of hydrogeologic work performed by the company. • Project Management Mr. Mateyk is the project manger for several projects. Duties include direction of the Project Team, client and regulatory liaison and cost control. Representative projects which Mr. Mateyk manages are listed below: -Carolawn Site, Fort Lawn South Carolina (NPL Site) -Cedartown Municipal Landfill Site, Cedartown, Georgia (NPL Site) -Dartco Manufacturing Site, Neshanic Station, New Jersey (ECRA Site) -former Dart Industries Site, North Smithfield, Rhode Island (State Listed Site). • Remedial Investigations/Feasibility Studies Mr. Mateyk has been responsible for the hydrogeologic component of several RI/FS and RFI/CMS under Superfund and RCRA programs. In addition, Mr. Mateyk has conducted investigations on State lists including ECRA. The duties included the scoping of the activities, design of hydrogeologic 2 w I I I I I I I I I I I I I I I I I I I u D D I I I I I I I I I I I I Michael G. Mateyk investigations, interpretation of hydrogeologic and chemistry data, determination of fate and transport, the d_esign and evaluation of remedial alternatives and agency negotiations. Representative projects are listed below: -North Hollywood Dump Site, Memphis, Tennessee (NPL Site) -Hardeman County Landfill Site, Hardemen County, Tennessee (NPL Site) -Mallory Capacitor Site, Waynesboro, Tennessee (NPL Site) -Yellow Water Road Site, Baldwin, Florida (NPL Site) -Jadco-Hughes Site, Gastonia, North Carolina (NPL Site) -FMC Plant Site, Middleport, New York (State Site) -Vac Air Site, Frewsburg, New York (State Site) -Cedartown Municipal Landfill Site, Cedartown, Georgia (NPL Site) -Kent Dump Site, Kent, Ohio (removal action) • Remedial Design/ Remedial Actions Mr. Mateyk works with other professionals at CRA to design and implement groundwater remedial actions at Superfund, industrial sites and abandoned waste disposal sites. The duties involve the design of pre-design investigations required to determine the hydrogeological conditions, evaluation of aquifer testing data, evaluation of numerical models, preparation of design and specifications for extraction wells, and the development of long-term monitoring plans. Some representative projects of this type are listed below: -Uniroyal Chemical Plant Site, Elmira, Ontario -Lees Avenue Transitway, Ottawa, Ontario -Algoma Steel, Sault Ste. Marie, Ontario -Spiegelburg Site, Livingstone County, Michigan (NPL Site) -Summit National Landfill Site, Portage County, Ohio (NPL Site) -Miami County Incinerator Site, Miami County, Ohio (NPL Site) 3 Michael G. Mateyk • Solid Waste Management Sites Mr. Mateyk has extensive experience in the hydrogeologic aspects of solid waste management sites. This work has included preparation of constraint maps for initial screening of candidate sites, the design of detailed hydrogeological investigations, the preparation of boundary impact assessments, the development of contingency plans and long-term monitoring. These activities have been conducted for closed landfills and in support of interim and long-term expansion of existing landfills. Selected project experience in this area is: -Waterloo Landfill Site, Waterloo, Ontario (Long-Term Expansion) -Sarnia Landfill Site, Sarnia, Ontario (Interim Expansion and Long-Term Monitoring) -Keele Valley Landfill Site, Vaughan, Ontario (Interim Expansion) -Green Lane Landfill Site, St. Thomas, Ontario (Interim Expansion) -Aurora Landfill Site, Aurora, Ontario (Long-term Monitoring and Closure Plan) • Groundwater Resource Development Mr. Mateyk has been involved in numerous groundwater resource development projects for municipalities, industries and subdivisions throughout Canada. This work has included regional water resource evaluations based on limited data. The duties included: aquifer and flow system delineation, water quality evaluation, design of test drilling programs, aquifer testing and production well design and rehabilitation. Some representative groundwater resource development projects are listed: -Beaver River-Cold Lake Water Resources Study, Alberta -Gregg River Resources, Hinton, Alberta (4000 m3 / day supply) -Village of Earlton, Ontario -Nitnat River Fish Hatchery, Kemano, British Columbia 4 D D I I I I I I I I I I I I n I B I I I I I I I I I I I I I I Michael G. Mateyk • Environmental Impact Assessments Mr. Mateyk has been actively involved in the determination of potential environmental impacts of resource developments on the groundwater regime. The tasks performed are baseline investigations, identification of potential impacts, establishment of severity criteria and recommendations of mitigative measures. Typical projects are listed below: -Kemano Completion Hydroelectric Project, British Columbia -Gravel extraction below the water table, Villeneuve Gravel Extraction Area, Villeneuve, Alberta -assessment of open pit mining on the water balance of Mary Gregg Lake, Hinton, Alberta • Dewatering and Drainage Mr. Mateyk has extensive experience in dewatering at construction sites and open pit mines. This work included field testing, data evaluation, design and installation of dewatering systems. Some projects are listed below: -Assessment of dewatering requirements, proposed underground portion of Coal Valley Mine, Coal Valley, Alberta · -Dewatering requirements of three active open pits at Cardinal River Coal Mine, Hinton, Alberta. • Expert Witness Mr. Mateyk has experience in providing expert testimony for the purposes of litigation and environmental assessment hearings pertaining to solid waste management sites. Some projects are listed. below: -Mountain Road Landfill Site, Niagara Falls, Ontario. (Testified before the Environmental Assessment Board). -Sarnia Landfill Site, Sarnia, Ontario (Testified before the Environmental Assessment Board). -Greenlane Landfill Site, St. Thomas, Ontario (expert witness for hydrogeology). 5 Michael G. Mateyk -Regional Municipality of Ottawa-Carlton vs. Consumers Gas (expert witness for hydrogeology). PUBLICATIONS: • Mateyk, M. G. and C. J. MacGillivray (1977): "Investigating Groundwater Pollution from a Brine Pond" preprinted for the Third National Groundwater Quality Symposium • Hall, P. L. and M. G. Mateyk (1977): "Controlling Sea Water Intrusion by Pumping Salt Water" Water and Sewage Works, June 1977 • McBean, E. A., K. Schmidtke, M. Mateyk and F. Rovers (1990): "Determining Aquifer Characteristics from Tidal Fluctuation Data" paper presented at International Conference on Groundwater Resources Management, Bangkok, Thailand, November 1990 6 D 9 I I I I I I I I I I I I I I I I I I I n I D I I I I I I I I I I I I I I STEVEN DAY EDUCATION: 1980 BA Chemistry and Microbiology Miami University, Oxford, Ohio EMPLOYMENT: 1990 - Present Environmental Chemist Conestoga-Rovers & Associates 1989-90 Chemistry Laboratory Manager: National Sanitation Foundation 1985-1989 Laboratory Manager , Environmental Testing and Certification Corporation 1984-1985 Environmental Chemist Chemical Waste Management, Inc. 1983-1984 Manager Field Technical Services O.H. Materials Corporation 1982-1983 Project Chemist O.H. Materials Corporation 1981-1982 Chernis t O.H. Materials Corporation PROFESSIONAL AFFILIATIONS: American Chemical Society Association of Official Analytical Chemists PROFILE OF PROFESSIONAL ACTIVITIES: • Manager of Field Technical Services responsible for the analysis, handling and consolidation of containerized hazardous waste at the Chern-Dyne Site in Steven Day Hamilton, Ohio. In addition, was approved by the U.S. Army Corps. of Engineers to perform the segregation, classification/identification, repacking and manifesting of the lab-pack chemicals at Chem-Dyne • Project Chemist responsible for field sampling and consolidation monitoring of containerized hazardous waste at the Piccillo Pig Farm in Coventry, Rhode Island • Project Chemist responsible for the segregation, classification/identification, repacking and manifesting of lab-pack chemicals at the Piccillo Pig Farm in Coventry, Rhode Island • Field Chemist responsible for field sampling and analysis of containerized hazardous waste at the Dryfuss Street Uncontrolled Waste Site in Columbia, South Carolina • Field Chemist responsible for the segregation, classification/identification, repacking of lab-pack chemicals at the Dryfuss Street Uncontrolled Waste Site in Columbia, South Carolina • Manager of Field Technical Services responsible for numerous drum handling, sampling, analysis, consolidation and disposal projects. Supervised and trained field chemists in all aspects of drum handling procedures, field testing and monitoring of containerized waste, compatibility testing, laboratory test bulking, field consolidation monitoring, labelling and manifesting and lab-pack chemical handling procedures • Participated in numerous small unknown drum removal projects in both analyst and field chemist capacities. In addition, performed field identification, segregation and handling of explosive and shock-sensitive chemicals at numerous sites and laboratories • Analytical data assessment and liaison with project laboratories in support of various remedial projects • Development of laboratory quality assurance project plans (QAPP) • Responsibility for the management of an independent testing laboratory performing analyses in support of public health concerns • Responsibility for the management of an environmental testing laboratory performing analyses in support of groundwater assessments, tank 2 I DI D I a I I I I I I I I I I I I I I I I I g 0 D m I I I I I I I I I I I I I Steven Day closures/removals, soil assessments, excavations and containerized waste removal/ disposal • Performance of applied research into the use of pozzolonic materials in the stabilization of liquid hazardous wastes • Evaluation of the applications of new and existing technologies in hazardous waste treatment • Responsibility for the management of field technical activities including sampling, analyses, monitoring well installations and water treatment system operation • Responsibility for the supervision of a high-hazard laboratory performing sample preparation of dioxin samples from Times Beach, Missouri • Development of sampling and analysis plans for numerous Superfund and private-sector projects • On-site chemist for numerous Superfund and private-sector projects performing sampling and analyses, overseeing cleanup/treatment of spilled hazardous materials and operating water treatment systems • Laboratory chemist performing organic and inorganic analyses with a variety of analytical instrumentation and classical wet-chemical techniques on environmental samples 3 I I I I D 0 D I I I I I I I I I MITCHELL S. BERGNER. MS. CIH, ROH EDUCATION: BA Jersey City State College, Biology-Chemistry, 1973 MS Rutgers University, Environmental Health, 1975 EMPLOYMENT: 1990- Present 1988-90 1983-88 1981-83 1977-81 1975-77 Industrial Hygiene Manager Conestoga-Rovers & Associates Manager of Human Resources:Jnformation Systems Honeywell Defense System Group, Minnesota Manager of Occupational Health Services Honeywell Defense System Group, Minnesota Principal Industrial Hygienist Honeywell Defense System Group, Minnesota Senior Staff Industrial Hygienist US Department of labor -OSHA, Wisconsin, Pennsylvania Environmental Manager Piscataway Township, New Jersey AFFILIATIONS: American Industrial Hygiene Association Computer Application Committee Respiratory Protection Committee Hazardous Waste Committee American Academy of Industrial Hygiene American Conference of Governmental Industrial Hygienists American Society of Safety Engineers Canadian Board of Occupational Hygienists Mitchell Bergner CERTIFICATIONS: American Board of Industrial Hygiene, Certified Industrial Hygienist Canadian Board of Occupational Hygienists, Registered Occupational Hygienist Asbestos Abatement, Supervisor License PROFILE OF PROFESSIONAL ACTIVITIES • Implemented and directed the work activity of ·occupational health nurses, industrial hygienists and consulting physicians to provide full service occupational health programs to 6000 employees. • Designed computer systems for industrial hygiene and safety operations in the areas of Worker Right to Know, chemical labeling, training and hazardous waste management. • Designed policies and procedures for Industrial Hygiene and Radiological Health programs. • Developed and managed medical monitoring programs for persons exposed to radiological hazards. Interfaced with the Nuclear Regulatory Commission. • Designed and managed lead abatement programs for industry. • Implemented toxicological and medical evaluations for a variety of workplace communities. • Conducted over 300 on-site investigations and consultations for multi-national and small businesses regarding a wide variety of safety and health problems and concerns. • Prepared technical reports and participated in litigation by providing expert testimony in court proceedings. · • Designed response protocol for hazardous materials spiils and waterway contamination emergencies. Conducted air pollution investigations. • Conducted public health investigations of food service, housing and health care facilities. 2 0 I I I I I I I I I I I I I I I I I I I I I I D D I I I Mitchell Bergner • Conducted fatality investigations. • Managed Industrial Hygiene aspects of Hazardous Waste Site Remediation on superfund sites interfacing with EPA and OSHA. • Managed Health and Safety issues regarding removal and disposal of asbestos contaminated buildings and structures over a 150 acre Site. (Manville Corp.) 1990/1991. • Provided industrial hygiene and safety technical support for the excavation and removal of NPL sites. • Prepared and reviewed numerous Site Safety Plans for submission to EPA and for use on Sites during remediation activities. • Managed PCB and asbestos abatement activities in a 2.5 million square foot facility (1993). 3 I I I I I I I I APPENDIXD I CURRICULA VITAE I I I I I I I I I I 3(,69 (18) R I m I I I I I I I I I I I I I TYPICAL CONTRACTORS DAILY LOG BOOK Project Name: Rmmial Action Date: ]adco-HughcsSite Weather: Report No.~------ 1) 2) 3) 4) 5) 6) 3669 08) Personnel On Site a) CRA b) Contractor c) Subcontractor d) Other Phases of Construction in Progress (Give briefly only phase or phases of work in progress) Health and Safety a) Preparatory b) Initial c) Follow-up Material and/or Equipment on Site (Including equipment demobilization) Inspection Made (Include negative inspections, phase of in-progress construction work inspected and all deficiencies noted during inspections) Tests Performed and Results of Tests (including results of tests taken on previous dates). 7) 8) 9) Instructions Received (List any instructions given by Resident Engineer on construction deficiencies, retesting required etc., with action to be taken). Changed Conditions/Conflicts Encountered. Remarks S!GNA1URE~------------------ TIIlE _____________________ _ Contractor's Verification: The above report is complete and correct and all material and equipment used and work performed during this reporting period are in compliance with the construction plans and specifications except as noted above. Contractor's Approved Authorized Representative 3669 (18) I I I I I I I I I I I I I I I I I I 0 D I I I I I ATTACHMENT C-1 I TYPICAL CONTRACTORS I DAILY LOG BOOK I I I I I I I I I 3669 (18) I g I 0 0 u I I I I I I I I I I I I I I 3669 (18) Inspection Log Books, Problem/Corrective Action reports, deviations from design and material specifications (with justifying documentation), and as-built drawings. C.7.8 STORAGE OF RECORDS During remedial construction, the Resident Engineer will maintain a copy of the Construction Drawings and the Construction Specifications, CQAP and Problem/Corrective Action reports in the Site office. Once the construction is complete, all CQA documents (originals) will be retained by CRA. This information will be retained for the period specified in the Order. C-19 CONESTOGA-ROVERS & ASSOCIATES I I I 0 D I I I I I I I I I I I I I I 3669 (18) Items above may be formulated into checklists so that details are not overlooked. C.7.5 PROBLEM/CORRECTNE ACTION REPORTS A problem is define,d as material or workmanship that does not meet the construction specific~tions. Problem/Corrective Action Reports should be cross-referenced to specific inspection entries in the Inspection Log Book where the problem was identified. Problem/Corrective Action Reports will include the following information: i) unique identifying sheet number for cross-referencing and document control; ii) detailed description of the problem; iii) location of the problem; iv) probable cause; v) how and when the problem was located (reference to Inspection Log Book); ' vi) estimation of how long problem has existed; vii) suggested corrective action; viii) documentation of correction (reference to Inspection Log Book); ix) final results; x) suggested methods to prevent similar problems; and xi) signature of the appropriate CQA Support Personnel and concurrence by the Resident Engineer. In some cases, not all of the above information will be available or obtainable. However, when available, such efforts to document problems could help to avoid similar problems in the future. C-17 CONESTOGA-ROVERS & ASSOCIATES 3669 (18) C.7.6 WORK TASK REPORTS Within each work task, there may be several quality characteristics, or parameters, that are specified to be observed or tested, each by a different observation or test, with the observations and/ or tests recorded in different Inspection Log Books. At the completion of each task, these log books should be used to write a Work Task Report summarizing all of the construction activities related to that particular work task. Work Task Reports will be prepared by the Resident Engineer or the Project Coordinator and will include the following information: i) unique identifying sheet number for cross-referencing and document control; ii) description of work task (i.e. installation of underground pipeline); iii) quality characteristic being evaluated and references to construction specifications and plans; iv) v) vi) quality control test locations; inspections made (define procedure by name or other identifier); summary of inspection results, which will include all data outside acceptable limits, and documentation of corrective action and retest results; vii) define acceptance criteria (compare task inspection data with design specification requirements; indicate compliance or noncompliance; in the event of noncompliance, identify documentation that gives reasons for acceptance outside of the specified design); and viii) signature of the Resident Engineer, Project Engineer or Project Coordinator. C.7.7 REMEDIAL ACTION {RA) REPORT At the completion of the remedial construction and after completion of construction inspection, CRA will submit an RA Report to USEPA. This report will include copies of all of the Daily Log Books, C-18 CONESTOGA ·ROVERS & ASSOCIATES I I I I I I I I I I I I I I I I 0 0 0 fl D u I I I I I I I I I I C7.0 COA DOCUMENTATION 3669 (18) C.7.1 GENERAL This section details the documentation requirements for the CQAP. The proper, thorough, and accurate documentation of all CQA activities is important in ensuring quality installation. CQA testing will be documented daily. C.7.2 CONTRACTORS DAILY LOG BOOK The selected contractor(s) will record daily quality control activities in a Daily Log Book to be kept on Site. The log book will state the name of the person preparing the log and include the following information: i) ii) iii) iv) v) vi) vii) viii) ix) x) xi) xii) xiii) xiv) xv) xvi) xvii) date, weather conditions; all activities completed; decisions made regarding approval of units of material or of work, and/ or corrective actions to be taken in cases of s.ubstandard quality; submittals made by suppliers verifying material quality; quality control test and inspection results; construction delays, and causes; areas affected by delays; construction problems and corrective actions; personnel on Site; present phase of construction; material and/or equipment delivered (including equipment demobilization); inspections made; health and safety considerations; quality control tests performed and results of tests taken on previous work day; instructions given by the Resident Engineer; changed conditions/ conflicts encountered; and remarks. C-15 CONESTOGA-ROVERS & ASSOCIATES 3669 (18) Each daily entry into the log will be signed by the contractor(s) as verification to its correctness, and a copy of the signed entry will be provided to the Resident Engineer on a daily basis for verification. An example of this report sheet is presented in Attachment C-l. The contractor(s) may use alternate forms providing the same information, subject to the approval of the Resident Engineer. C.7.3 COA INSTRUMENT CALIBRATION The CQA support personnel will record calibr_ations of test equipment in an Instrument Calibration Log Book, maintained on Site by the I Resident_ Engineer. Actions taken as a result of recalibration will be recorded in the Inspection Log Book, as described in the next section. C.7.4 INSPECTION LOG BOOK All observations and quality control field tests will be recorded by the CQA support personnel into Inspection Log Books. These books will be kept and maintained by the Resident Engineer. The inspection log book will include the following information: i) date, time, weather conditions; ii) description or title of the inspection activity; iii) location of the inspection activity or location from which the sample increment was obtained; iv) type of inspection activity and procedure used (reference to standard method when appropriate); v) recorded observation or test data, with all necessary calculations; vi) results of the inspection activity and comparison with specification requirements; vii) personnel involved in the inspection activity; and viii) signature of the appropriate CQA inspection personnel and concurrence by the Resident Engineer. C-16 CONESTOGA-ROVERS & ASSCX:IA TES I I I I I I I I I I I I A. Rw:ki' Pt,,IRHI Pipeline High Dau.ity Polyethylene Pipe (HOPE;) or or Polyvinyl Chloride (PYO Common B.,,cldill and Imported To~il B. M«irkn«n« llaln Pipe, Vdves, Fittings, ConnectioN, etc. • Precast Concnte Ch.amben c. &tr..ctian Ta:,Kb • Gn.nuln B.tcldill • Commcn Ba.cldill D. [rtmctian Well, • Cuing ;;a a.a ;;;;a ;;a liiia T-yro/Tnt • Hydromtic • F1uahing TABLEC.6...2 SUMMAJlY Of CONSlllUCTION QUAUTI ASSURANCE TESTING RA WORK PLAN JADCO HUGHES Sm:, GASTON COUNn', NORIB CAROLINA Ttt1"11g Stlnultrnl • NA • NA Frripnuy of Tut each test shill not uettd 1,500 fttt of piping urtleu otherwi.\e authorized by Resident Engineer each test ah.I.II not exceed 1,500 feet of piping unleas otherwise authorized by Resident Engineer • Maximum Dry Density • ASn.<0698 minimwn of I test for each change inm11hiri.l • Gr.1.di.tion Moisture Content Bulk Density • Leakage • Hydrostatic • Leak.age • D,yO..Uity • See Section A. Buried Pipeline • Leabge ASTM Dl22 or ASThf D1140 n approprilte A5IM 02216 ASTM 0698, ASTM D15.56, A5TM 02167 or ASIM 02922, whichevc-r i, appropri•te • NA • NA • NA ASTh< 0698 • NA minimum of I test per SJXX) C\I. yd. of m.1terill removed 1.t MJurc-e minimum of 1 test for any CNnge in matffUI used in fill minimum l test per 2,00J ni. yd. minimum l Int per 2,00J ni. yd. after installation and after repairs after installation and 1fter repair, after irutalbtion ind 1fter any repairs • minimum l test per 2,00J cu. yd. • for eu::h hole drilled 1.mount of m11U-up w1.ter 1.dded thou Id not eio:ce-ed 0.25 gallons per 100' of pipe 1.1 let pr-e,5ure of 100 psi • flwh until di foreign m11terial i, removed • N.A. >25, wt < 0.005 mm• P-"rtide ,iu; :65, wt pusing No. 200 sif'\o'e minimum fluctuation of 5 p,i at 140 psi 1pplied pre.sure, over 1 hour minimum fluctuation of 5 psi at 140 psi 1.pplled pressure, over 1 hour • leakage g).3, vol/hr minimum 90-95, Standard Proctor Density to bottom of uUting ditch • no le.1kage for five minutn iiiil TABLEC.6.2 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE TESTING RA WORK PLAN JAOCO HUGHES SITE. CASTON COUNTY, NORTif CAROLINA Work T•d: C""'poflfflt tolKTnW r. BHil4inr:CmtrcbniorU5oil, • Engineered Flll/Grnel Bue • Lo.amSoil r. Qwifdi"t • Coaart, ~York c. BYildint·MuonQI Wallt II. Qyi/Jinr·Mccb,iniod Tinks, Pipes, Valves, Fittings, Connections, etc. I. 8Hildinr·Occtrinl Notes: Typ1to/Tnt mu:imum dry dmsity bulk density • gradation See Engineered Fill/Gravel Base Permeability • compressive strength (")("') tot;al air content (0)(00) temperature of mncrete s.1mp!e (")("") • compressive strength leakage Hydrostatic calibration wiring mntinuity PLC programming/control circuit5 loop checks motors bumped to check operation and rotation ASTM D698 and ASlM 02216 ASTM D1556orA5TMD2167or ASTM D2922 whichever is appropriate A5TM Dl,22 or ASI'M D1140 whichever is appropriate ASTM D2434 • ASTM C39 • ASTMCI43 ASTM C173 or ASTM C2Jl ASTM CHJ6-1 • ASTMC90,Cl29,Cl45,C55 NA NA NA NA NA NA If more than one {I) batching pl.Int is being used, these frequencies shall apply lo each batching pl.ant separately Fr1ttpmu:yofT1td minimum I test for e.ich change in m.tteTi.al minimum of I test per S<XJcu. yd. minimum of I test per 5.000 cu. yd. of nuterial removed at source minimum of I test for any change in material used in fill minimum 1 test pcr 2,000 cu. yd. minimum 1 test for any m.tlerial change l compressive strength tel per concrete truck lo.id 2 speciml'ns for 7 .and 28 day~ (compressive strength) at beginning, middle, and end of .a p.lr1icuUr concrctl' truck lo.id whenever concrete consistency varil."!', one for every strength te.t I for every slump te..t one for every strength te,;t or .is required mini,.;,~m of I test p<"r truck Jo.id after inst.albtio~ ind dter any reP3irs .ifter instalbtion .ind .after any rep.iirs before installation after inst.ilbtion .after inst.albtion before iruitallation Type of test and its frequency 1h.all be coruiidered minimums and sha.U be .added to or increased as determined necessary by the Contractor l. A5lM • Americ;m Society for Testing and Materials 2. AO American Concrete Institute NA Not Applicable Cribri11 NA minimum 95% Standard Proctor Density >2S'J. wt <0.005 mm e particle size; >55% wt passing No. 200sieve • l,o;I0-4cm/5 • 3500 psi .it 28 d.iys unless s!Jted otherwis-e to be determined fromConcrcte Mi• specifk.itions to b._. determined fromCono-cte Mi• specifications 40"F <l',;,mper;ature <77"F • to be determined from design specifications minimum Ouctu;ation of 5 psi at 100 psi .ipplied pres.sure, over 2 hour.,; minimum Ouctu.ition of 5 psi at 140 psi applied pre.sure, over 1 hour as specified as specified JS specified ;IS specified iiii iiiii liiii iiiii liiiil iiiiiil --iiii iiii P;age 2 of 2 -- - Work TIWC Conspono,t to bt' 1-,,ectr.d - B. hut:htmial Co,,rpu,ients - Installation of Valves. Pumps, Pipe and Fittings. Aow meters,. flow Control Valves,etc. C. Eltttriail Compm,enb Pull Boxes PVC Electrical and Control Conduits D. Piping and Esp,dpment to Jn{iJtn,lian ~ (F11:n1~ Dpurticm) • Piping and F.quipment - ---!!!!!!!! 11!!!9 == TABLE<:.6..1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JAOCO HUGHES SITE, CASTON COUNTY, NC • do specifications of mechanical components meet design specifications • are mechanical components being assembled according to specifications • do pull bolles meet design specifications • do conduits meet specifications • do piping ,1nd equipment meet specification • check 5Upplier's specifications • visual • visual • check supplier's specifications • check manufacturer's specification FrrlfNDC0f of bupec:tfcm • upon delivery to Site • periodically during assembly • upon delivery to Site • upon delivery to Site • upon delivery to Site or upon assembly == Swl,.,.ltt,ds to RnilUftt Engf,ua • manufacturer's operating and mainlenance literature • shop drawings P•ge9of9 • confirmation in wriling !hat equipmenl was !1,.1,tisfactorily lesled • none • manufacturer'scertication manufacturer's certification llii 3669 (18) C.6.3 TESTING In addition to the daily inspections of the construction progress, material testing will be carried out as required. Material testing will be performed to ensure compliance with material specifications and design criteria as presented in the Construction Specifications. The testing requirements, methods of testing, testing frequency for each of these work task components and submittals (test reports, certificates, verifying material quality /workmanship, etc.) are summarized in Table C.6.2 and have been incorporated into the construction specifications for the groundwater treatment system. This table may be modified upon completion and approval of the Final Design. C-14 CONESTOGA-ROVERS & ASSOCIATES u u I I I I I I I I I I I I I I --- Painting Process Equipment • Piping ~d Equipment Electrical Electrical Requirements IV 5Yf Sy1km • Depth . Cemmt Aggregate Wat.er Admixtures Concrete Grout Well Screens D.sings Silica Sand Sampling I!!!!!!! I!!!!!! == == == TABLE C..C..1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSP'ECTJONS RA WORK PLAN JADCO HUCHES SITE, GASTON COUNTY, NC Ito,u to be Ch«k.«I Dwmgha~ specificalioM • does all work meet specifications • do all proce-,,s equipment meet specifications • do piping and equipment meet specification • does all electrical work meet specifications • does all work required meet specifications • does trench depth mttt design specifications • does cement meet specifications • does awegate meet specifications • does water meet specifications • does admixture meet specifications • does concrete meet design specifications • does concrete mixture meet design specifications • see Section B • do well screens meet specification • do casing, meet specifications • does gradation meet specifications • See Remediation Goal Verification Plan • check specifications • check manufacturer'ssp«ification • check manufa.cturer's sp«ificatiorui • check specifications • check specifications • visual logging ol excavated ,oils • depth measurement - • check supplier's specifications • check supplier's specifications • check supplier's specificatioru • check supplier's specificatioru • visual (tape measurement) • check supplier's specification • check manufacturer's sp«ificalions • check manufacturer's sp«ificatioru • check supplier's specifications manufacture's supervision • following the completion of work • upon delivery to Site or upon iMtallation • upon delivery to Site or upon assembly • upon installation • during work • periodic • periodic and on completion • upon delivery to Site • upon delivery to Site • upon delivery to Site • upon delivery to Site • during concrete placement • upon delivery to Site • upon delivery to Site • upon delivery to Site • upon delivery to Site SJWMltt11l1 to RrsilUftt £1tghtffr • none • shop drawings • manufacturer's certification • certific.i.tion • certific.i.tion • exc.i.vation log • excavation log • certification·- • certific.i.tion • certification • certification • final dimell5ions • mixture certification • certification • certification • certification lliii liiiii Page 7 of 9 - Work Tui Compo,eent to be Ins,,«ted Installation of Valves. Pumps, Pipe and Fittings. Aow meters, Aow Conbol Valves,etc. D. E~ctriail Componoil.s Installation of Panelboards, Electrical Cable, Control Wire, Suspended Electrodes, Liquid Level Switch, etc. Pull Bo:,,;es PVC Electrical and Control Conduits V. Satl flM&tng S;uatan A. Soil F/ldhing Extniction Tmteks • Depth - Cement Aggregate Water Admbtures Concrete Grout Well Screens Casings Silica Sand - -- TABLE <:.6..1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JADCO HUGHES SITE, CASTON COUNTY, NC It-• to be Chtcked IJuri,,g hu,,«Hon • do specifications of mechanical components meet design specifications • are mechanical components being assembled according to specifications • do specifications of electrical components meet design specifications • are electrical components being assembled according to specifications • do pull bo:,,;es meet design specifications • do conduits meet specifications • does e,;traction trench meet design specifications • does cement meet specifications • doesaggregatemeetspecifications • does water meet specifications • does admi:,,;ture meet specifications • does concrete meet design specifications • does concrete mixture meet design specifications • see Section B • do well screens meet specification • do casing:, meet specifications • does gradation meet specifications - --.. Type of lnspeetio,s • check supplier·s specifications • visual • check supplier's specifications • visual • visual • check supplier's specifications • visual logging of excavated soils • depth measurement • check supplier's specifications • check supplier's specifications • check supplier's specifications • check supplier's specifications • visual (tape measurement) • check supplier's specification • check manufacturer's specifications • check manufacturer's specifications • check supplier's specifications -liiil • upon delivery to Site • periodically during assembly • upon delivery to Site • periodically during assembly • upon delivery to Site • upon delivery to Site • periodic • periodic and on completion • upon delivery to Site • upondeliverytoSite • upon delivery to Site • upon delivery to Site • during concrete placemen! • upon delivery to Site • upon delivery to Site • upon delivery to Site • upon delivery to Site liiiiiii Sub,,sittAls to Re6ldent E11gi11ttr • manufacturer's operating and maintenance literature • shop drawings Page8of9 • confirmation in writing that equipment • was satisfactorily tested ii.i • manufacturer's Certification • shop drawings • test results upon successful completion of installation • none • manufacturer's certication • e:,,;cavating log • e:,,;cavating log • certification • certification • certification • certification • final dimension, • mixture certification • certification • certification • certification iiiii liiiiii -- - - -- ------- Work TW COtfl,-U,St to be ln.,,«tr:d Precast Concrete Chambers and Appum"nances Mainteno1nce Hole Frames Crout Concrete • Gravel Base Granular Backfill for Maintenance Hole Frames C. £:drvdion Wtlls • Depth Cement Aggregate Water Admixtures Concrete Grout Well Screens Casings Silica Sand Sampling TABLEC..6.1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JADCO HUGHES SITE, GASTON COUNTY, NC It-.• to ff Checked Otim.g ht1pection • do maintenance hole frames and appurtenances meet design specifications • are maintenance holes in,talled to grade and plumb • does grout meet specifications • does concrete meet design specifications • does concrete mixture meet design specifications • does gravel meet gradation specilica tions • does compacted gravel meet design thickness • does granular backfill meet gradation specification • does well depth meet design spe~_ifi~ations • does cement meet specifications • does aggregate meet specifications • does water meet specifications • does admixture meet specifications • does concrete meet design specifications • does concrete mixture meet design specifications • does grout meet specifications • do well screens meet specification • do casings meet specifications • does gradation meet specifications • See Remediation Goal Verification Plan • check supplier's specifications • survey • check suppliers specification • visual (tape measurement) • check supplier's specification • check supplier's gradation • visual (grade stakes) or survey • check gradation from supplier • visual logging of well cuttings • depth measurement • check supplier's specifications • check supplier's specifications • check supplier's specifications • check supplier's specifications • visual (tape measurement) • check supplier's specification • check suppliers specification • check manufacturer's specifications • check manufacturer's specifications • check supplier's specifications Frrtfwost:y of bupectiOfl • 14 days prior to delivery to Sile • upon installation • upon delivery to Site • during concrete placement • upon delivery to Site • prior to delivery to Site • upon completion • prior to delivery to Site • periodic • periodic and on completion • upon delivery to Site • upon delivery to Site • upon delivery to Site • upon delivery to Site • during concrete placement • upon delivery to Site • upon delivery to Site • upon delivery to Site • upon delivery to Site • upon delivery to Sile S11-bnsitt11l1 to Raidr,ct £ngbua • manufacturer's certifico1tion • final elevations • certification • final dimensions • mixture certification • grain size distribution curve • measurements • grain size distribution curve • well drilling log • well drilling log • certification • certifico1tion • certification • certification • final dimensions • mixture certification • certification • certification • certification • certification Page5of9 - Work T,uk Cc.m,po,,ent to be ln•,ectrd Items to be Checkrd Dwing ln•p«tic,,t TABLE C6.1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JADCO HUGHES SITE, GASTON COUNTY, NC D. ~Nlniail Componnsts c,f Wdls 11,uJ Jhin~na Hold Installation of Valves,. Pumps, Pipe and Fittings, Aow meters, Aow Control Valves,etc. Installation of Panelboards, Electrical Cable, Control Wire, Suspended Electrodes, Liquid Levrl Switch, etc. Pull Boxes PVC Electrical and Control Conduits III. Grnff!ldrv@ttt Trt@tni:At S,,,,tffll A. Geolminial/Soi& Foundation Excavation Engineered fill/gravel base B. Tmzbnenf Facility • Cast-in-place Concrete Unit Masonry Metal Fabrications 5"<1 Decking Aashing and Sheet Metal Metal Doors and Frames C11A ,.., 11•• Concrete Aoor Seal -- -- • do specifications of mechanical components meet design specifications • are mechanical components being assembled according to specifications • do specifications of electrical components meet design specifications • are electrical components being assembled according to specifications • do pull boxes meet design specifications • do conduits meet specifications • excavation specifications • gravel gradation specifications • gravel base specified • compaction specifications • does concrete meet design specifications • does concrete mixture meet design specifications . • do unit masonry meet specifications· • do all metal fabrications meet specifications • do steel decking meet specifications • do flashings and steel metal meet specifications • do the doors and frames meet the specifications • does the concrete floor seal meet manufacture's ---- • check supplier's specifications • visual • check supplier's specifications • visual • visual • check supplier's specifications • measurement of layout and depth • check supplier's gradation • visual (grade stakes or level) • compaction • visual (tape measurement) • check supplier's specification • check supplier's specifications • check manufacturer's specifications • check supplier's specifications • check manufacturer's specifications • check manufacturer's specifications • check manufacturer's specifications - -- • upon delivery to Site • periodically during assembly • upon delivery to Site • periodically during assembly • upon delivery to Site • upon delivery to Site • upon completion of excavation • prior to delivery on site • upon completion • during compaction • during concrete placement • upon delivery to Sile • periodic • upon delivery to site • upon delivery to site • upon delivery and after installation • periodically during assembly • during assembly with --- Swl,.,.ittal, to Rniru"flt Cnginttr • manufacturer's operating and maintenance literature • shop drawings Page6of9 • confirmation in writing that equipment was satisfactorily tested • manufacturer's Certification • test results upon successful completion of installation • none • manufacturer'scertification • none • grain size distribution curve • none • compaction results • final dimensions • mixture certification • none • certfication • certfication • shop drawings • shop drawings • none ---- Work Tuk Coml"'"fflt to be l'llSp«teli Crout Concrete • Gravel Base --.. - ---TABLE c...6.1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JADCO HUGHES SITE, CASTON COUNTY, NC ltewu to be Chttlc.eil °"""' ,,,_ does grout meet specifications see Section C Extraction Wells,. Monitoring Wells and Piezometen • does gravel meet gradation specifications • check supplier's specifications • check supplier's gradation • upon delivery to Site • prior to delivery to Site - • does compact gravel meet design thickness G. MLC}wmial Components of ~inlt:ruma: H~ • visual (grade stakes) or survey • upon completion Installation of Valves, Pwnps, Pipe and Fittings H. Elutriall Compnmts Installation of Panelboards, Electric.iJ Cible, Control Wire, Suspended Electrodes, Liquid Level Switch, etc. Pull boxes PVC Electrical and Control Conduits II Croundw,1tcr Eduction Sntsm A. Burr.ii Conduits 11"'1. PipdinLS Depth and Alignment of Ex.ca v.i tion High Density Polyethylene Pipe (HOPE) or Polyethylene Pipe (PE) Granular Bedding Material • do specific;i.tions of mechanical components meet design specifications • are mechanial components being assembled according to specifications • do spedfiotions of electrical components meet design specifications • are electrical components being assembled according to specifications • do pull boxes mttt design specifications • do conduits meet specifications . • has trench been excavated to design elevation and line • do pipe and fittings meet specifications • has pipe bttn laid to design depth • has pipe been damaged or filled with soil during inslallation • does beddinfS material meet gTadation specifications • does imported backfill meet specifications • check supplier's specifications • visual • check supplier's specifications • visual • visual • check supplier's specifications • survey • check supplier's specifications • survey • visual • check supplier's gTadation • check supplier's specifications • upon delivery to Site • periodically during assembly • upon delivery to Sile • periodically during assembly • upon delivery to Site • upon delivery to Site • intermittent during excavation • upon delivery to Site • periodicaliy during excavation • periodically during excavation and at end of installation • prior to delivery on Site • for each source of material prior to delivery to site -- s ... bnsitti:ils to lfrsi4"tt Crtgirtttr • certification • gTain size distribution curve • measurements • manufacturer's operating and maintenance literahue • shop drawings -Page 3 of 9 • confirmation in writing that equipment was satisfactorily tested • manufacturer's Certifications • test results upon successful compleltion of - installation • none • manufacturer'scertification • final elevations, gTade, and alignment • manufacturer's certification • elevations • none • gTain size distribution curves • certification and test results - Work Tul COfflfO'UJ't to be J,up«trd • Native Fill Storage and Handling of Backfill Excavation == == == TABLE c.6.1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JADCO HUGHES SITE, CASTON COUNTY, NC Items to br Ch«krd I>url,tg bl,p«titm • is stockpile being properly stored and handled • does ba.cldill meet gradation specification • does ba.cldill contain unsuitable materials: i) material containing loam, roots or organic matter; ii) clays which are classified as inorganic days of high plasticity; iii) softand/ororganicdaysand silts of low strength; iv) swelling days; v) rock and lumps of material with dimensions greater than six inches for ba.cldill of deep excavation ueas or 1/2 inch for backfill of the upper six inches of any excavation area, measured through any axis before compaction; vi) tree, stumps, or any other wood or lumber; vii) wire, steel, cast iron, cans. drums or any other foreign materials; and viii) materials containing hazardous or toxic constituents at hazardous or toxic concentrations. • does native fill contain unsuitable materials: i) rocks and lumps of material with dimensions greater than specified layer thid.:neiS before compaction; and ii) other delrierious or foreign matter detrimental lo the use intended. • are stockpiles free of foreign materials • are stockpiles far enough apart to prevent intermixing • does excavation meet design specifications em !!!!9 ee Typr of Msprcti°" • visual • if backfill is imported check supplier's gradation • if on-site backfill is used, conduct gradation test • visual and laboratory • visual • visual • visual • measure layout and depth e!! I!!!!!!! • periodic • prior to delivery to site • minimum of 1 test per S,CXXJ cu yd of material removed at source • minimum 1 test per 5,000 cu yd of material removed at source. • periodic • upon delivery to Site • upon delivery to Site • upon completion I!!!!!! S1.1bmlttlds to Resid.rnt Engt,,ur • none • grain size distribution curves • gr~in size distribution curves • certification and test results • none • none • none • elevations ll!!!!!!I ro1ge4of9 iiiii iiii Work Ta.d: Compo,se,,t to be I,upecttd SvlllwSY CHIPat ed Pr:sbtarc lln< A. SpiIIWlly ~tnu:iian B. Tr,p Soil -iiiij - -.. -TABLE C-6.1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JADCO HUGHES SITE, CASTON COUNTY, NC Jtn,u to H Checked !h,rl,,g ht,,,«fio,, • is spillway con5tructed to design elevations • does backfill contain unsuitable materials i) material containing excess loam, roots or organic matter ii) frozen material or material containing snow or ice iii) clays which are classified as inorganic clays of high plasticity in accordance with ASTM 0248'7 iv) softand/ororganicclaysand silts of low strength v) frost swiceptible silts or days vi) swelling clays vii) rock and lumps of material with dimensions greater th.an 6 inches for backfill of deep excavation areas or 1 1/2 inches for backfill of the upper 6 inches of any excavation area, measured throug~ any_ axis befo~ co'!lr.action viii) tree5, stumps, branches, or any ther wood or lumber ix) wire, steel, cast iron. cans, drums or any other foreign materials • does imported top soil meet the following specifications i) be friable and loamy, non-swelling compactible material ii) be free of debris,. objectionable weeds and stones iii) contain no to;,dc substances that may be harmful! to plant growth iv) have pH in range 6.0 to 7.0 v) have a minimum organic matter content of2.75 percent (organic matter content may by raised by additives as approved by Engineer) • size distribution specification • does fertilizer meet specification • does grass seed meet specification • does mulch meet specification • does water meet specification Ty~ of bup«tio,, • survey • visual • check supplier's specifications • check supplier's specification • check specification • check specification • check specification • visual f1YIJUDU:y of bsspo:tio,c • intermitten during spillway construction • intermittent during berm construction • for each source mateial prior to delivery to site • 14 days prior to delivery • prior to delivery • prior to delivery • pr!or to delivery • prior to delivery - -- s,dm,ittals to Resident £nri"err -Page 1 of 9 • elevations before and after spillway construction • none • certification and test results • grain size distribution curves • supplier's certification • supplier's certification • supplier's certification • none - Work Ta,k Component to be lnspected D. Temporary SlockpikJ E. Buritd Conduits 1md Pipeline,, Depth and Alignment of Excavation High Density Polyethylene Pipe (HDPE), Polyethylene Pipe (PE) or Concrete Pipe • Granular Bedding Material • NatiVe Backfill • Storage and Handling of Backfill TABLEC.6.1 SUMMARY OF CONSTRUCTION QUALITY ASSURANCE INSPECTIONS RA WORK PLAN JADCO HUGHES SITE,. GASTON COUNTY, NC Item, to be Chtcktd Th,rlng Inspection • mixture rale • grass height • height • slope • does stockpile block natural drainage • polyethylene underlay and covering, if required soil erosion and sediment control has trench been excavated to design elevation and line do pipe and fittings meet specifications has pipe been laid to design depth has pipe been damaged or filled with soil during installation does bedding material meet gradation specifications does native fill contain unsuitable materials: i) rocks and lumps of materials with dimensions greater than specified layer thickness before compaction; and ii) other deleteriol.15 or foreigh matter detrimental to the use intended are stockpiles free of foreign materials are stockpiles far enough apart to prevent intermixing Type of Inspection • check specification • visual • measure • measure • visual • visual • visual • survey • check supplier's specifications • survey • visual • check supplier's gradation • visual • visual • visual Frtqumcy of lnspt~tion • continuous • continuous • intermittent, as required • intermittent, as required • intermittent, as required • intermittent, as required • intermittent, as required • intermittent during excavation • upon delivery to site • periodically during excavation • periodically during excavation and at end of installation • prior to delivery on Site • periodic • uJX!n delivery to Site • UJX!n delivery to Site F. M.aintenana Hoks (Pr=I Concret~ Chamber) Excavation Pree.a.st Concrete Chambers and Appurtenances Maintenance Hole Frames ;;a == does excavation ffil'i!t design specifications do maintenance hole frames and appurtenances meet design specifications are maintenance holes installed to grade and plumb == == • measure layout and depth • UJX!n completion • check supplier's specifications • 14 days prior to delivery to Site • survey • UJX!n installation l!!!!9 l!!!!!!9' I!!!!!! Submittal! to Rrsidmt Engine" • contractor's certification • none • none • none • none • none • none Page 2 of9 • final elevations, grades and alignment • manufacturer's certification • elevations • none • grain sire distribution curves • none • none • none • elevations • manufacturer's certification • final elevations (!!!!!! I I I I I I I I I B B I I I I I I I I 3669 (18) • groundwater treatment system control center • power supply C.6.2 INSPECTIONS Throughout the period of remedial construction, the quality of work completed and material used for each of the work tasks will be maintained at its highest possible level through regular inspections of the work. Inspections will be completed throughout the construction by the Resident Engineer, CQA support personnel, and representatives of USEPA on a periodic basis, if required. In general, inspections to be conducted by the Resident Engineer and CQA support personnel include the following: i) daily inspections of the work progress; ii) inspections of material as it is delivered to the Site to check for damage during delivery; iii) comparison of the material deliv~red to the Site to the design specifications to ensure that the proper material has been delivered; iv) inspection of materials after they have been installed to ensure that it has not been damaged during installation; v) a pre-construction inspection, performed prior to beginning work on any work task, including the following: • a review of contract requirements to ensure that all materials and/or equipment have been delivered and tested according to applicable standards and specifications, • ensure that provisions have been made to provide required quality ' control testing, and • examination of the work area to ascertain that all applicable preliminary work tasks have been completed; C-12 CONESTOGA·ROVERS & ASSOCIATES 3669 (18) vi) general inspections, performed periodically as the amount of work completed warrants an inspection, including the following: • examination of the quality of workmanship, • testing of materials for compliance with Contract requirements, • any omissions, and • general progress of work performed; and vii) a final inspection, performed upon completion of each work task, to ensure compliance with the Construction Drawings and Construction Specifications and to ensure that deficiencies identified in the general inspections have been corrected. These inspections will be performed by the Resident Engineer and the results of the inspections will be provided in the RA Report as defined in the SOW. The results of all inspections will be recorded in the Daily Site Log Book as described in Section C.7.2. Copies of the pre-construction, general and final inspection reports will be provided to all parties involved in the inspection. The components of each work task to be inspected, the types of inspections required and the frequency of the inspections are summarized in Table C.6.1. This table may be modified upon completion and approval of the Final Design. C-13 CONESTOGA-ROVERS & ASSOCIATES u fl u u 0 I I I I I I I I I I I I u 0 u I I I I I I I I I I I 3669 (18) Participants: Project Coordinator or Project Engineer, Resident Engineer, Contractor's Representative and USEPA. Topics: • health and safety report; • review of the work activities completed; • comparison of actual progress to scheduled work activities, noting of schedule slippage and actions implemented to rectify schedule the slippage; • summarize upcoming work activities scheduled; and • review potential remedial cor\struction problems/ conflicts for the upcoming remedial construction activities and proposed solutions to the potential problems/ conflicts. C.5.4 PROBLEM OR WORK DEFICIENCY MEETINGS Purpose: If a problem or deficiency is present or likely to occur. Participants: Resident Engineer and CQA Support Personnel, Contractor Representative (optional if major problem directly related to his work) Topics: • define and discuss problem or deficiency; • review alternative solutions; and • develop and implement a plan to resolve the problem or deficiency. For all meetings held on Site during the remedial construction, with the exception of the daily progress meetings, minutes will be taken by the Resident Engineer. Copies of the minutes will be provided to the Jadco-Hughes Steering Committee arid all organizations participating in the meetings. C-10 CONESTOGA-ROVERS & ASSOCIATES C.6.0 INSPECTION AND TESTING ACTIVITIES 3669 (18) C.6.1 SCOPE Throughout the implementation of the construction program there will be numerous inspections and testing requirements for specific work tasks. The inspection and testing requirements will ensure compliance with the contract specifications, applicable building codes as well as ensure completion of the work tasks to the highest level of quality. Inspections and testing will provide a qualitative means of monitoring the quality and progress of work performed. The components of each work task which will require inspection or testing include: i) Excavation. Regrading. Backfilling Activities ii) iii) iv) v) • horizontal and vertical control • compaction • backfill material quality control Geotechnical /Soils • quality of native material • compaction of backfill Steel Work • installation of structural steel • connections/ tolerances Mechanical Components • groundwater treatment equipment testing including pumps, blowers, flow meters, valves and other appurtenances • pressure testing of tanks and piping Electrical Components • level and pressure sensors and transmitters C-11 CONESTOGA-ROVERS & ASSOCIATES 0 D I I I I I I I I I I I I I I I I I • I I I I I I I I I I I I I C.5.0 PROTECT MEETINGS 3669 (18) Project meetings as detailed herein will be held during the remedial construction period to ensure that all tasks are accomplished according to schedule and that they are completed in accordance with the remedial construction plans and specifications. These progress meetings may be attended by the Project Coordinator; Resident Engineer, Contractor Representative and USEPA representative, as detailed below . C.5.1 PRECONSTRUCTION MEETING Purpose: To resolve any uncertainties in the remedial construction plans and specifications, and to review levels of responsibility, reporting requirements, and health and safety requirements. Participants: Project Coordinator, Resident Engineer, CQA Support Personnel, Contractor Representative. Topics: • present CQAP, Contractors Project-specific Health and Safety Plan, and other relevant documents; • review the activities to be conducted during the remedial construction; ' • review roles of each organization relative to the design criteria, plans and specifications within the CQAP; • determine any need to modify the CQAP that may be necessary to ensure that the construction i's performed to meet or exceed the specified design criteria; • review lines of authority and communication; • discuss the established procedures or protocol for observations and tests including sampling strategies; • discuss the established procedures or protocols for handling construction deficiencies, repairs and retesting; • review methods for documenting and reporting inspection data; C-8 CONESTOCA-ROVERS & ASSOCIATES 3669 (18) • review methods for distributing and storing documents and reports; • review work area delineation, security and safety protocol; • discuss the location for storing construction equipment and materials, and the protection of these items during inclement weather; • discuss the protection of uncompleted construction work during off hours and during inclement weather; and • conduct a tour to review construction areas, safety areas, and equipment and stockpile storage locations. C.5.2 DAILY PROGRESS MEETINGS Purpose: To daily review work schedule progress. This meeting is intended to be an informal meeting held at the end of each work day or at the start of each work day. Participants: Resident Engineer, Contractor Representative Topics: • review previous day's activities and progress; • review work location and activities for upcoming day; • review health and safety deficiencies from the previous work day and review health and safety requirements and potential problems for the next day's activities; • review Contractor's personnel and equipment assignments for the . upcoming day; and • discuss any potential construction problems. C.5.3 PERIODIC PROGRESS MEETINGS Purpose: To provide a remedial construction progress update to USEPA. C-9 CONESTOGA-ROVERS & ASSOCIATES u D fl 0 B ff 0 I I I I I I I I I I I I I I I I I I I I C.4.0 PERSONNEL OUALIFICA TIONS 3669 (18) C.4.1 RESIDENT ENGINEER The Resident Engineer will have the following qualifications: i) graduate of a recognized college in a technically related field; ii) minimum two (2) years experiel'\ce in the oversight and implementation of hazardous waste remedial construction and CQA activities; and iii) good management and communication skills. C.4.2 COA SUPPORT PERSONNEL The CQA support personnel will have the following minimum qualifications: i) degree from a recognized college in engineering technology, or equivalent; or a minimum of two (2) years experience in hazardous waste remedial construction and CQA inspection procedures; and ii) working knowledge of all relevant codes and regulations concerning material and equipment installation, observation and testing procedures, equipment, documentation procedures, and safety. C.4.3 CONTRACTOR The selected contractor(s) will assign experienced personnel to supervise the implementation of each of the r_emedial construction activities specified in the RA Work Plan. In particular, the selected contractor will assign experienced personnel to the following remedial construction activities: C-6 CONESTOGA-ROVERS & ASSOCIATES 3669 {18) i) installation of extraction wells; ii) installation of structures; iii) installation of mechanical and electrical components; and iv) commissioning of mechanical and electrical components. Experienced personnel will have a thorough knowledge of testing procedures, equipment and documentation procedures required for implementation of the remedial construction activities. The selected contractor will designate an on-Site Project Manager empowered to act on behalf of the contractor in all matters pertaining to the remedial construction activities. C-7 CONESTOGA-ROVERS & ASSOCIATES u D u mi I I I I I I I I I I I I I I I I D I I I I I I I I I I I !I I I I I 3669 (18) C.3.3 RESIDENT ENGINEER i) ii) iii) iv) v) vi) The duties of the Resident Engineer are as follows: reports to the Project Coordinator; provides immediate supervision of all construction activities; provides field management of CQA activities; reviews design criteria, plans and specifications for clarity and completeness so that the CQAP can be implemented; informs CQA support personnel on CQA requirements and procedures; ensures that regular calibration of testing equipment is conducted and recorded; vii) ensures that all Site activities are recorded daily and maintained; viii) ensures that CQA test results are accurately recorded; ix) identifies work that should be accepted, rejected, or uncovered for observation, or that may require special testing, inspection, or ' approval; x) rejects defective work and verifies that corrective measures are implemented; and xi) interacts daily with the contractor to,provide assistance in modifying the materials and work to comply with the specified design. The individual designated to be the Resident Engineer will be specified prior to commencement of the construction activities. C.3.4 COA SUPPORT PERSONNEL The duties of the CQA Support Personnel are as follows: i) reports directly to the Resident Engine7r; ii) conducts CQA tests and inspections as indicated in this CQAP; iii) iv) v) accurately records test results and inspections; calibrates testing equipment as required; maintains testing equipment in good working order; and C-4 CONESTOGA-ROVERS & ASSOCIATES 3669 (18) vi) immediately notifies Resident Engineer whether or not test results comply with design specifications. The CQA Support Personnel may include the Project Coordinator, the Project Engineer, the Resident Engineer and/ or other personnel meeting the qualifications specified in Section C.4.2. C.3.5 OA/OC TEST LABORATORIES QA/QC test laboratories that will conduct CQA Quality Control tests will be identified prior to the commencement of the construction activities. The duties of the QA/QC test laboratories are to provide QA/QC testing of construction activities, as requested by the Resident Engineer, to confirm construction activities have been implemented according to the construction specifications and drawings. C.3.6 CONTRACTOR The duties of the Contractor, as they relate to QA/QC, are as follows: i) retains qualified testing firms (for example laboratory, geotechnical), for testing of materials and workmanship to ensure that materials meet specified requirements; ii) iii) iv) submits samples and/ or materials for testing to determine if samples/materials meet specified requirements, and submits results directly to the Resident Engineer; records daily. CQA activities in the Contractors Log Book and submits a "Daily Construction Quality Control Report" (see Section C.7.2) to the Resident Engineer; and carries out construction activities according to design specifications. C-5 CONESTOGA-ROVERS & ASSOCIATES D I I I I I I I I I I I I' 11 i