HomeMy WebLinkAboutNCD003188844_19940815_Carolina Transformer_FRBCERCLA RD_Draft Remedial Design-OCRI
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ii
:1
I
DRAFT REMEDIAL DESIGN
for the
Carolina Transformer Site
Fayetteville, North Carolina
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
DRAFT REMEDIAL DESIGN
Carolina Transformer
Fayetteville, North Carolina
Prepared for
U.S. ENVIRONMENTAL PROTECTION AGENCY
Region IV
EPA Work Assignment N2 18-4NC2
Prepared by
BLACK & VEATCH WASTE SCIENCE, INC.
Atlanta, Georgia
August 15, 1994
---------- ------- ---"""Schedule of Sciill:xcavation for""Carolina Transformer
Weeks
rm 5 ' 7 8 9 10 11 12 13 14 15 1B 17 18 19 20
Survev Const. Limits
Survey Grid System of Front 1 /3 of Site
Fence The Site
Office Setuo
Temc. Decon Station Const.
Temc. Stockoile Lavout
Drummed Water Removal Time Estimates Based on All Work
Drummed Soil Relocation
being carried out in Health and
Clearing and Grubbing(Frant 1/3 of Site and Safety Level D.
Permanent Stockpile Areal
IcxcavatIon{Front 1f.3 of site and Permanent
Stocki:ile Areal
Survey Back 2/3 of Site II I ID /A\ I c: 11'
~ Test 1 f3 of Site and Permanent Stockpile Area
i UC u,J u u
Construct Permanent Oecon Pad
Construct Permanent Stockoile
1 ransfer 01 ~oil From l emp. Stockp1 e to
Permanent Stockpile
Remove Contaminated Soil in Building
Decon Buildina
Demolition of Buildina
Removal of Buildina Debris
Test Buildina Foundation
Oecon Foundation
Clearing and Grubbing (Back 2/3 of Site)
Establish Sill/ Sediment Control
Creek Excavation/Temp. Road Const./CMP
Removal and.Replacement
( Creek Berm Liner lnstallatio~::i
Excavation Back 213 of Site
Secure Stockpile
Remove Debris
Demobilize
I Soil Excavation
00 ill Cost Estimate ffi ~ V Carolina Transformer
I Descrigtion Quanitiy Unit Eguigment Material Labor Total
Survey Construction Limits 4.50 Acre $0.00 $189.00 $1,777.50 $1,966.50
Survey Grid System of Site 120.00 EA $0.00 $600.00 $5,400.00 $6,000.00
Fence Installation 2030.00 LF $3,471.30 $11,165.00 $5,278.00 $19,914.30
I Gate Installation 3.00 EA $127.50 $190.50 $195.00 $513.00
Office Setup 1.00 EA $0.00 $990.00 $296.80 $1,286.80
Temporary Decon Station Const. 1200.00 SF $0.00 $192.00 $108.00 $300.00
I Water Disposal 10000.00 GAL $200.00 $270.00 $1,000.00 $1,470.00
Drummed Water Removal 3200.00 GAL $32.00 $0.00 $96.00 $128.00
Drummed Soil Relocation 2310.00 GAL $300.30 $0.00 $254.10 $554.40
I Clearing and Grubbing 4.50 ACRE $4,725.00 $0.00 $4,275.00 $9,000.00
Excavation of Site 10000.00 CY $33,600.00 $0.00 $14,100.00 $47,700.00
Onsite Analytical 200.00 EA $0.00 $11,516.00 $1,484.00 $13,000.00
I Ollsite Analytical 20.00 EA $50.00 $3,000.00 $240.00 $3,290.00
Permanant Decon Pad Const (Excavation) 237.00 CY $796.32 $0.00 $334.17 $1,130.49
Permanant Decon Pad Const.(Conc. Work) 50.00 CY $570.00 $5,650.00 $8,950.00 $15,170.00
I Permanant Stockpile Const. (Clearing) 189.00 CY $459.27 $0.00 $200.34 $659.61
Stockpile Liner Const.(Membrane 21600.00 SF $0.00 $13,824.00 $6,480.00 $20,304.00
Drainage Net, Geotextile)
Berm Construction and Liner Fill Material 978.00 CY $3,286.08 $4,890.00 $1,378.98 $9,555.06
I Transfer of Soil from Temporary Stockpile-1200.00 CY $4,032.00 $0.00 $1,692.00 $5,724.00
to Permanant Stockpile
Removal Contaminated Soil/Debris From Building 1.00 LS $0.00 $0.00 $0.00 $500.00
I Decon Building 8.00 HR $150.00 $0.00 $148.40 $298.40
Demolttion of Building 11956.00 CF $1,195.60 $0.00 $836.92 $2,032.52
Removal/Disposal of Building and Site Debris 887.00 CY $11,087.50 $0.00 $3,592.35 $14,679.85
I Disposal of PCB Contaminated Transformers 20000.00 LB $0.00 $25,000.00 $0.00 $25,000.00
Disposal of Non-PCB Contaminated Transformers 40.00 TON $0.00 $1,400.00 $0.00 $1,400.00
Silt/Sediment Control 908.00 SY $0.00 $989.72 $980.64 $1,970.36
Creek Excavation 460.00 CY $1,545.60 $0.00 $648.60 $2,194.20
I Temporary Road Construction 119.00 CY $399.84 $0.00 $167.79 $567.63
CMP Removal and Replacement 60.00 LF $33.00 $507.00 $177.00 $717.00
Stockpile Secure 1.00 LS $0.00 $0.00 $0.00 $500.00
I Final Debris Removal & Disposal 4.00 CY $50.00 $189.16 $2.60 $241.76
Health & Safety Cost 20.00 Week $40,000.00 $0.00 $0.00 $40,000.00
Mobilization/Demobilization 1.00 LS $0.00 $0.00 $0.00 $6,000.00
I Subtotal $106,111.31 $80,562.38 $60,094.19 $253,767.88
Health and Safety Training 15% $0.00 $0.00 $9,014.13 $9,014.13
I Equipment Decontamination 8% $8,488.90 $0.00 $0.00 $8,488.90
Escalation 5% $5,305.57 $4,028.12 $3,004.71 $12,338.39
I Subtotal $119,905.78 $84,590.50 $72,113.03 $283,609.31
I Sales Tax6% $7,194.35 $5,075.43 $0.00 $12,269.78
Overhead 8% $9,592.46 $6,767.2~ $5,769.04 $22,128.74
I Profit 10% $11,990.58 $8,459.05 $7,211.30 $27,660.93
Subtotal $148,683.17 $104,892.22 $85,093.37 $338,668.76
I Total $338,668.76
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Proposal Form
Attachment 1
LUMP SUM OR UNIT PRICE SUMMARY
Item of the Work
SITE PREPARATION
1) Fence Installation per
drawings.
2) Onsite Clearing and Prep
Work per Section 02202.
3)
4)
Offsite Clearing and Prep
Work per Section 02202.
Silt/Sediment Control
Fencing Installation per
drawings and Section 02050.
EXCAVATION AND STOCKPILING
1) Permanent Stockpile
Construction per drawings
and Section 02050.
2) Excavation and Stockpiling
of PCB Contaminated Soil
per drawings and Sections
02202.
Lump Sum or Engineers
Unit Cost estimated
quantity
Unit Cost
($/LF)
Lump Sum
Unit Cost
($/Acre)
Unit Cost
($/SY)
Unit Cost
($/SF)
Unit Cost
($/CY)
2,300
1
2
908
30,600
10,000
DEMOLITION, REMOVAL, TRANSPORTATION, AND DISPOSAL
1) Demolition of Buildings per Lump Sum
drawings and Section 02050.
2)
3)
Removal, Transportation,
and Disposal of Non-
Hazardous Solid debris,
including Non-PCB
contaminated transformers
per section 02050.
Removal, Transportation,
and Disposal of
Hazardous/PCB Solid debris,
excluding PCB transformers
per Section 02050.
Unit Cost
($/TON)
Unit Cost
($/TON)
1
1,530
10
Proposed Proposed
Unit Price Price
I
I
I
I
I
4)
5)
6)
Removal, Transportation,
Carcass Destruction,
Smelting, and Disposal of
PCB transformers per
Section 02050.
Removal, Transportation,
and Disposal of Non-
Hazardous wastewaters per
Section 02050.
Removal, Transportation,
and Disposal of PCB
Contaminated Product per
Section 02050. I DECONTAMINATION
I
I
I
I
I
I
I
I
I
I
I
I
I
1) Construction, Maintenance,
and Operation of Temporary
and Permanent
Decontamination Station per
Section 02203.
OTHER COST
1)
2)
3)
PERFORMANCE AND PAYMENT
BOND
Provide Performance and
Payment Bond in Accordance
With the General
Conditions. Contractor
Shall Indicate Cost of Bond
as a Percentage of the
Contract Sum.
Mobilization
Demobilization
Unit Cost
($/TON)
Unit Cost
($/GAL)
Unit Cost
($/GAL)
Lump Sum
Percentage
of Contract
Sum
Lump Sum
Lump Sum
10
4,000
3,000
1
N/A
1
1
Total Estimate Bid Cost
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Table of Contents
Division 1
SECTION 01015 PROJECT REQUIREMENTS
Page t\Q.
1. Pre-Bid Meeting and Site Visit ............................... 01015-1
2. General Description of Work ............................... 01015-1
3. Other Contracts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2
4. Contracts and Communications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2
5. Work By Public Utilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2
6. Responsibility for Onsite Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2
7. Responsibility for Onsite Equipment .......................... 01015-2
8. Offsite Storage .......................................... 01015-2
9. Equivalent Materials and Equipment .......................... 01015-2
10. Preparation for Shipment .................................. 01015-3
11. Salvage of Materials and Equipment .......................... 01015-3
12. Land for Construction Purposes ............................. 01015-3
13. Operation of Existing Facilities .............................. 01015-3
14. Notices to Owners and Authorities ........................... 01015-3
15. Lines and Grades ........................................ 01015-3
16. Allowances ............................................. 01015-4
17. Connections to Existing Utilities ............................. 01015-4
18. Unfavorable Construction Conditions ......................... 01015-4
19. Cutting and Patching ..................................... 01015-4
20. Asbestos Removal ....................................... 01015-5
21. Cleaning Up ............................................ 01015-5
22. Applicable Codes ........................................ 01015-5
23. Reference Standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-5
24. Abbreviations, Symbols and Definitions ........................ 01015-6
25. Alternatives ............................................ 01015-6
26. Preconstruction Conference ................................ 01015-6
27. Progress Meetings ........................................ 01015-7
28. Site Administration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-8
29. Notification ............................................ 01015-8
30. Substantial Completion and Completion ....................... 01015-8
SECTION 01025 MEASUREMENT AND PAYMENT
1. Scope ................................................ .
2. General .............................................. .
3. Contract Sum and Estimated Quantities ...................... .
4. Excavation and Stockpiling ................................ .
5. Removal and Non-Hazardous Solid Disposal ................... .
6. Removal and Hazardous Solid/PCB Disposal ................... .
7. Permanent Stockpile Construction ........................... .
8. Sewers ............................................... .
9. Pipelines .............................................. .
10. Miscellaneous Concrete .................................. .
11. Decontamination Station Construction ......................... .
2 E . D . . ' 1 . qmpment econtammat1on ............................... .
13. Demolition ............................................ .
01025-1
01025-1
01025-1
01025-1
01025-2
01025-2
01025-2
01025-2
01025-2
01025-2
01025-2
01025-2
01025-2
TC-1 August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Table of Contents (Continued)
Division 1 (Continued)
Page fl>.
14. Mobilization and Demobilization ............................. 01025-3
15. Removal and Disposal of Non PCB Liquid Product ............... 01025-3
16. Removal and Disposal of PCB Liquid Product .................. 01025-3
17. Site Clearing and Prep Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01025-3
18. Removal and Disposal of Non-Hazardous Liquids ................ 01025-3
19. Site Fencing ............................................ 01025-3
SECTION 01061 SITE SAFETY AND HEALTH PLAN REQUIREMENTS
1. General ............................................... 01061-1
1.1 Work Included ....................................... 01061-1
1.2 References ......................................... 01061-1
1.3 Purpose ............................................ 01061-1
2. Products ............................................... 01061-1
2.1 Site Safety and Health Plan (SSHP) ....................... 01061-1
3. Execution .............................................. 01061-2
3.1 SSHP Implementation ................................. 01061-2
SECTION 01300 SUBMITTALS
1. Job Plan ............................................... 01300-1
2. Construction Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2
3. Progress Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2
4. Schedule of Values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2
5. Schedule of Payments ..................................... 01300-2
6. Survey Data ............................................ 01300-2
7. Shop Drawings and Engineering Data . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2
8. Operation and Maintenance Data and Manuals .................. 01300-3
9. Layout Data ............................................ 01300-3
10. Density Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-3
SECTION 01400 QUALITY CONTROL
1. Testing Laboratory Services ................................ 01400-1
1.01 Testing Laboratory Services Furnished by Contractor ......... 01400-1
1.02 Testing Laboratory Services Furnished by Engineer .......... 01400-1
1.03 Transmittal of Test Reports ............................ 01400-2
2. Offsite Inspection ........................................ 01400-2
3. Manufacturer's Field Services ............................... 01400-2
3.01 Services Furnished Under This Contract ................... 01400-2
3.02 Services Furnished by Others ........................... 01400-2
SECTION 01500 TEMPORARY FACILITIES
1. Office at Site of Work .................................... 01500-1
2. Engineer's Office at Site of Work ............................ 01500-1
3. Water ................................................. 01500-1
4. Power .............................................. ,. ... 01500-1
5. Telephone Service ....................................... 01500-1
6. Sanitary Facilities ........................................ 01500-2
TC-2 August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Table of Contents (Continued)
Division 1 (Continued)
Page N-2.
7. Construction Aids ........................................ 01500-2
8. Maintenance of Traffic .................................... 01500-2
9. Barricades and Lights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-2
10. Fences ................................................ 01500-2
11. Protection of Public and Private Property ...................... 01500-3
12. Damage to Existing Property . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3
13. Flood Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3
14. Tree and Plant Protection .................................. 01500-3
15. Access Roads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3
16. Parking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3
17. Noise Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3
18. Dust Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4
19. Temporary Drainage Provisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4
20. Erosion Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4
21. Pollution Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4
22. Pest Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4
23. Rodent Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4
Division 2
SECTION 02050 STORAGE, DISPOSAL, DEMOLITION AND DUST CONTROL
1. General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-1
1.1 Work Included ....................................... 02050-1
1.2 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-1
1.3 Submittals .......................................... 02050-1
1.4 Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-1
2. Products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2
2.1 Drainage Gravel ..................................... 02050-2
2.2 Geo Net . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2
2.3 Filter Fabric . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2
2.4 Membrane Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2
2.5 Membrane Liner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2
2.6 Select Fill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2
2. 7 Silt Fence Fabric . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-3
2.8 Sump Cleanout Pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-3
2.9 General Membrane Requirements . . . . . . . . . . . . . . . . . . . . . . . . 02050-3
3. Execution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-4
3.1 General Work Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-4
3.2 Specific Work Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-4
3.3 Permanent Stockpile Construction . . . . . . . . . . . . . . . . . . . . . . . . 02050-5
3.4 Handling, Storage, Transportation, and Disposal . . . . . . . . . . . . . . 02050-7
3.5 Demolition ........................................ 02050-13
3.6 Dust Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-13
3.7 Temporary Stockpile .............................. :' .. 02050-14
3.8 Silt Fence ......................................... 02050-14
TC-3 August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Table of Contents (Continued)
Division 2 (Continued)
SECTION 02202 EXCAVATION AND STOCKPILING
PageN:2.
1. General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-1
1.1 Work Included ....................................... 02202-1
1.2 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-1
1.3 Submittals .......................................... 02202-1
2. Products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-1
3. Execution .............................................. 02202-1
3.1 General Work Requirements ............................ 02202-1
3.2 Removal of Debris and Rubble .......................... 02202-2
3.3 Excavation .......................................... 02202-2
3.4 Quality Assurance Sampling ............................. 02202-2
3.5 Stockpiling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-3
3.6 Removal and Abandonment of Temporary Monitoring Wells .... 02202-3
3. 7 Backfill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-4
SECTION 02203 DECONTAMINATION
1. General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1
1.1 Work Included ....................................... 02203-1
1.2 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1
1.3 Submittals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1
2. Execution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1
2.1 Construction of Decontamination Station ................... 02203-1
2.2 Decontamination of Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-2
2.3 Management of Decontamination Water and
Decontamination Solutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-3
2.4 Personnel Decontamination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-3
I
TC-4 August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section 01015
PROJECT REQUIREMENTS
1. PRE-BID MEETING AND SITE VISIT. A prebid meeting will be held at the
site at the scheduled time and date indicated on the bid. documents.
Contractor shall supply and wear tyveks and boot covers. PPE may be
left onsite upon completion of meeting. A failure to attend by
Contractor will result in Engineer disallowing the Contractor's
Proposal. No additional compensation shall be made for the pre-bid
meeting and site visit.
2. GENERAL DESCRIPTION OF WORK. The Work to be performed under these
Contract Documents consists of: the clearing and grubbing of
approximately 4.8 acres; the excavation and stockpiling of PCB
contaminated soil; the demolition, removal, and off site disposal of
non-PCB contaminated buildings; and the removal and disposal of six
transformers, four underground storage tanks (USTs) and other various
site debris at the Carolina Transformer NPL Site in Fayetteville, North
Carolina.
The excavation and stockpiling of soil contaminated with PCBs will be
conducted by areas. Soils from the first areas excavated will be
temporarily stockpiled in the designated Temporary Stockpile Area while
a Permanent Stockpile Area is under construction. After Permanent
Stockpile construction is completed, all future excavated soils and
soils previously placed in the Temporary Stockpile Area will be placed
in the Permanent Stockpile. After the initial excavation of an area,
the Engineer will conduct verification sampling to deter~ine the
presence or absence of PCBs. Samples will be analyzed immediately
onsite by the Engineer. The Engineer will use the sample results to
determine if additional excavation is necessary and if so, to what depth
excavation will be conducted.
The demolition, removal and disposal of existing buildings will proceed
concurrently with soil excavation activities.
One half-buried UST contains product with elevated concentrations of
PCBs. The PCB contaminated product shall be removed and properly
disposed in accordance with specifications in SECTION 02050. The empty
tank will be removed, decontaminated if necessary, and properly
disposed.
Contractor shall prepare waste characterization and manifesting for all
wastes to be disposed as required by local, State, or Federal
regulations and the Contractor' selected and Engineer approved disposal
facility. EPA or their authorized representatiye will sign all
manifests as the waste Generator and Owner. ·
If necessary, the Work may also include the temporary onsite storage of
PCB contaminated and non-contaminated materials. 1
01015-1
DRAFT
August 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. OTHER CONTRACTS. Work at the site performed by others under
separate contracts includes the following: Engineer will contract a
surveyor to conduct a volume survey of the permanent soil stockpile to
determine compensation for the Contractor.
4. CONTACTS AND COMMUNICATIONS. All submittals or communications with
the Engineer shall be through the Engineering Project Manager or his
appointed representative:
Mr. Rob Vicevich, P.E., Engineering Project Manager
BLACK & VEATCH Waste Science, Inc.
400 Northridge Road
Suite 350
Atlanta, Georgia 30350
(404) 643-2346
All written correspondence between the Contractor and the Engineer shall
be via overnight courier. Facsimile communications shall be confirmed
by hardcopy via overnight courier. However, facsimile communications
shall carry the same weight as an original instrument during the interim
period prior to receipt of the hardcopy via overnight courier.
5. WORK BY PUBLIC UTILITIES. (Not Used).
6. RESPONSIBILITY FOR ONSITE EQUIPMENT. The Contractor shall be fully
responsible for maintaining all existing permanent locked monitoring
wells in working condition and shall take all reasonable precautions to
prevent damage to permanent monitoring wells during excavation
activities. Temporary unlocked PVC monitoring wells may be removed and
abandoned in accordance with Subpart 3.5 of Section 02202 at the
Contractors discretion.
7. RESPONSIBILITY FOR MATERIALS AND EQUIPMENT. (Not Used).
8. OFFSITE STORAGE. (Not used).
9. EQUIVALENT MATERIALS AND EQUIPMENT. Whenever a material or article
is specified or described by using the name of a proprietary product or
the name of a particular manufacturer or vendor, the specified item men-
tioned shall be understood as establishing the type, function, and
quality desired. Other manufacturers' products will be accepted
provided sufficient information is submitted in advance to allow
Engineer to determine that the products proposed are equivalent to those
named. Such items shall be submitted for review by the procedure set
forth in the submittals section.
Requests for review of equivalency will not be accepted from anyone
except Contractor, and such requests will not be considered until after
the contract has been awarded.
I
01015-2 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
10. PREPARATION FOR SHIPMENT. (Not used).
11. SALVAGE OF MATERIALS AND EQUIPMENT. Existing materials removed as
a part of the Work shall become Contractor's property, except those
materials which are contaminated with PCBs.
Any permanent items damaged during demolition, excavation, or handling
through carelessness or improper procedures shall be replaced by
Contractor in kind or with new items. Existing materials removed by
Contractor shall not be reused in the Work.
12a. LAND FOR CONSTRUCTION PURPOSES. The Contractor will be permitted
to use available land on or near the site of the Work for construction
purposes including parking, office space, storage of materials and
equipment, and to provide access to the area of special conditions if
necessary. The location and extent of the areas so used will be as
follows: The Contractor may use the portion of the paved parking lot
adjacent to .the site (southwest of the site) and a portion of the
adjacent property to the northeast of the site to provide access from
State Rt. 1714 (River Rd.) to the area of special conditions as
specified herein and in the enclosed construction drawings.
12b. EASEMENTS AND RIGHTS-OF-WAY. All required easements and rights-
of-way will be obtained by the Engineer for the Contractor.
13. OPERATION· OF EXISTING FACILITIES. (Not Used).
14. NOTICES TO OWNERS AND AUTHORITIES.
of adjacent property and utilities when
affect them.
Contractor shall notify owners
prosecution of the Work may
When it is necessary to temporarily deny access by owners or tenants to
their property, or when any utility service connection must be inter-
rupted, Contractor shall give notices sufficiently in advance to enable
the affected persons to provide for their needs. Notices will conform
to any applicable local ordinance and, whether delivered orally or in
writing, will include appropriate information concerning the
interruption and instructions on how to limit their inconvenience.
Utilities and other concerned agencies shall be contacted at least
24 hours prior to cutting or closing streets or other traffic areas or
excavating near underground utilities or pole lines.
15. LINES AND GRADES. All Work shall be done to the lines, grades,
and/or elevations indicated on the drawings.
Basic horizontal and vertical control points will be established by the
Contractor. These points shall be used as datum for the Work. All
additional survey, layout, and measurement Work shall be performed by
Contractor as a part of the Work.
01015-3
DRAFT
August 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Contractor shall provide an experienced instrument man, competent
assistants, and such instruments, tools, stakes, and other materials
required to complete the survey, layout, and measurement Work. In
addition, Contractor shall furnish, without charge, competent men from
his force and such tools, stakes, and other materials as Engineer may
require in checking survey, layout, and measurement Work performed by
Contractor.
Contractor shall remove and/or reconstruct Work which is improperly
located.
16. ALLOWANCES. (Not Used).
17. CONNECTIONS TO EXISTING UTILITIES. Unless otherwise specified or
indicated, Contractor shall make all necessary connections to Utilities,
including water, sewer, gas, telephone, and electric as appropriate. In
each case, Contractor shall receive permission from the owning utility
prior to undertaking connections. Contractor shall protect utilities
against deleterious substances and damage.
Connections to existing utilities which are in service shall be
thoroughly planned in advance, and all required equipment, materials,
and labor shall be on hand at the time of undertaking the connections.
Work shall proceed continuously (around the clock) if necessary to
complete connections in the minimum time. Operation of valves or other
appurtenances on existing utilities, when required, shall be by or
coordinated with the owning utility.
18. UNFAVORABLE CONSTRUCTION CONDITIONS. During unfavorable weather,
wet ground, or other unsuitable construction conditions, the Contractor
shall confine his operations to work which will not be affected
adversely by such conditions. No portion of the Work shall be
constructed under conditions which would affect adversely the quality or
efficiency thereof, unless special means or precautions are taken by
Contractor to perform the work in a proper and satisfactory manner.
In the event of rain or other form of precipitation, the permanent
stockpile shall be covered as indicated in the drawings to prevent
production of leachate or contaminant runoff. In the event that
excessive leachate or contaminated runoff accumulates in the stockpile
area due to Contractor's failure to cover the stockpiles, the Contractor
shall dispose of such accumulation at Contractors sole expense.
19. CUTTING AND PATCHING. Contractor shall perform all cutting and
patching required for the Work.
Except when the cutting or removal of existing construction is specified
or indicated, Contractor shall not undertake any cutting or demolition
which may affect the structural stability of the Work without Engineer's
concurrence.
01015-4 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Contractor shall provide all shoring, bracing, supports, and protective
devices necessary to safeguard all Work during cutting operations.
Materials shall be cut and removed to the
ings or as required to complete the Work.
removed from the site by Contractor.
20. ASBESTOS REMOVAL. (Not used).
extent indicated on the draw-
All materials shall be
21. CLEANING UP. Contractor shall keep the premises free at all times
from accumulations of waste materials and rubbish. Contractor shall
provide adequate trash receptacles about the site, and shall promptly
empty the containers when filled.
Construction materials such as concrete forms and scaffolding shall be
neatly stacked by Contractor when not in use. Contractor shall promptly
remove splattered concrete, asphalt, oil, paint, corrosive liquids, and
cleaning solutions from surfaces to prevent marring or other damage.
Volatile wastes shall be properly stored in covered metal containers and
removed daily.
Wastes shall not be buried or burned on the site or disposed of into
storm drains, sanitary sewers, streams, or waterways. All wastes shall
be removed from the site and disposed of in a manner complying with
local, State and Federal ordinances and antipollution laws.
Adequate cleanup will be a condition for recommendation of progress
payment applications.
22. APPLICABLE CODES. Applicable codes are referenced in the
appropriate technical sections of these Construction Documents.
23. REFERENCE STANDARDS. Reference to standards, specifications,
manuals, or codes of any technical society, organization, or associa-
tion, or to the Laws or Regulations of any governmental authority,
whether such reference be specific or by implication, shall mean the
latest standard specification, manual, code, or Laws or Regulations in
effect at the time of opening of Proposals (or on the date Engineer
signs the Proposal Form if there were no Proposals), except as may be
otherwise specifically stated. However, no provision of any referenced
standard, specification, manual, or code (whether or not specifically
incorporated by reference in the Contract Documents) shall be effective
to change the duties and responsibilities of Engineer, Contractor,
Engineer, or any of their Consultants, agents, or employees from those
set forth in the Contract Documents, nor shall it be effective to assign
to Engineer, or any of their Consultants, agents, or employees, any duty
or authority to supervise or direct the furnishing or performance of the
Work.
I
01015-5 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
24. ABBREVIATIONS.SYMBOLS AND DEFINITIONS. Abbreviations and symbols
used in the Contract Documents are defined as follows:
CFR Code of Federal Regulations
!OW Investigation Derived Waste
OPAi Off-Property Area 1 (also areas 2 and 3)
PCB Polychlorinated Biphenyls
ppm Parts Per Million
SSHP Site Safety and Health Plan
SPCC Spill Prevention, Control, and Countermeasures
UST Underground Storage Tank
Definitions used in the Contract Documents are defined as follows:
Site. Site shall mean the area within the limits of construction
asindicated on the drawings.
Area of Special Condition. The area in the northern corner of the
property which may or may not provide difficulty to the Contractor
due to saturated soils and standing water. Area is indicated on the
drawings as Off-Property Area 2 (OPA2).
Non-PCB Liquid Product. Liquids, primarily organic in nature, which
contain less than 50 ppm of PCBs and have substantial BTU values.
Typical substances are fuels, oils, etc ..
PCB Liquid Product. Liquids, primarily organic in nature, which
contain greater than 50 ppm of PCBs and have substantial BTU values.
Typical substances are oils,·etc ..
Non-Hazardous Wastewaters. Wastewaters derived from previous
investigation activities, or stockpile leachate as verified by
characterization analysis.
25. ALTERNATIVES. (NOT USED)
26. PRECONSTRUCTION CONFERENCE. Prior to the commencement of Work at
the site, a preconstruction conference will be held at a mutually agreed
time and place. The conference shall be attended by:
Contractor and his superintendent.
Principal Subcontractors.
Engineer and his Resident Project Representative.
Representatives of EPA.
Other governmental representatives as appropriate.
Others as requested by Contractor or Engineer.
01015-6
DRAFT
August 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Unless previously submitted to Engineer, Contractor shall bring to the
conference a tentative schedule for each of the following:
Progress.
Values for progress payment purposes.
Shop Drawings and other submittals.
The purpose of the conference is to designate responsible personnel and
establish a working relationship. Matters requiring coordination will
be discussed and procedures for handling such matters established. The
agenda wi 11 include:
Contractor's tentative schedules.
Transmittal, review, and distribution of Contractor's submittals.
Processing applications for payment.
Maintaining record documents.
Critical Work sequencing.
Field decisions and Change Orders.
Use of premises, office and storage areas, security, housekeeping,
and EPA's needs.
Major equipment deliveries and priorities.
Contractor's assignments for safety and first aid.
Administration of the Contractor's Site Safety and Health Plan.
Engineer will preside at the conference and will arrange for keeping the
minutes and distributing the minutes to all persons in attendance.
27. PROGRESS MEETINGS. Contractor shall schedule and hold regular
progress meetings at least weekly and at other times as requested by
Engineer or required by progress of the Work. Contractor, Engineer, and
all Subcontractors active on the site shall be represented at each
meeting. Contractor may at his discretion request attendance by repre-
sentatives of his suppliers, manufacturers, and other Subcontractors.
Engineer will preside at the meetings and will provide for keeping and
distribution of the minutes. The purpose of the meetings will be to
review the progress of the Work, maintain coordination bf efforts,
discuss changes in scheduling, and resolve other problems which may
develop.
01015-7
DRAFT
I
August 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
28. SITE ADMINISTRATION. Contractor shall be responsible for all areas
of the site used by him and all Subcontractors in the performance of the
Work. He will exert full control over the actions of all employees and
other persons with respect to the use and preservation of property and
existing facilities, except such controls as may be specifically
reserved to Engineer or others. Contractor has the right to exclude
from the site all persons who have no purpose related to the Work or its
inspection, and may require all persons on the site (except Engineer's
employees) to observe the same regulations as he requires of his
employees.
29. NOTIFICATION. The Contractor shall notify the Engineer if any of
the following occur:
1.
2.
3.
4.
5.
If the Contractor or Subcontractor is served with notice of
violation of any law, regulation, permit or license which
relates to this Contract.
Proceedings are commenced which could lead to revocation of
related permits or licenses.
Permits, licenses, or other government authorizations relating
to this Contract are revoked.
Litigation is commenced which would affect this Contract.
If the Contractor or Subcontractor becomes aware that its
equipment or facilities are not in compliance, or may fail to
comply in the future, with applicable laws or regulations.
30. SUBSTANTIAL COMPLETION AND COMPLETION. The Contractor shall have
all building demolition material and site debris removed from the site
and disposed by 120 calendar days from the Notice to Proceed. The
Contractor shall have all soils contaminated with PCBs stockpiled in the
permanent stockpile area, the permanent stockpile area securely covered,
the site policed of all Contractor's equipment and debris, and the
Contractor's presence gone from the site by 150 calendar days from the
Notice to Proceed.
End of Section
01015-8 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section 01025
MEASUREMENT AND PAYMENT
1. SCOPE. This section covers methods of measurement and payment for
items~ork under this contract.
2. GENERAL. The Contract Sum shall cover all Work required by the
Contract Documents, as selected by the Engineer. All costs in
connection with the proper and successful completion of the Work,
including furnishing all materials, equipment, supplies, and appurte-
nances; providing all equipment and tools; and performing all necessary
labor and supervision to fully complete the Work, shall be included in
the unit and lump sum prices bid. All Work not specifically set forth
as a pay item in the Proposal Form shall be considered a subsidiary
obligation of Contractor and all costs in connection therewith shall be
included in the prices bid. No additional or separate payment shall be
made for any labor, consumable materials, or other costs incurred by the
Contractor to replace unsatisfactory materials or workmanship as
determined by the Engineer.
3. CONTRACT SUM AND ESTIMATED QUANTITIES. All estimated quantities
stipulated in the Proposal Form or other Contract Documents are
approximate and are to be used (a) as a basis for estimating the
probable cost of the Work, (b) for the purpose of comparing the bids
submitted for the Work, (c) as a basis for the Contract Sum as defined
at the time of Contract Award, and (d) as a basis for the final Contract
Sum at the completion of the Work. The actual amounts of work done and
materials furnished may differ from the estimated quantities. The basis
of payment for work and materials will be the actual amount of work done
and materials furnished. The Contract Sum, as defined at the time of
Contract Award, will be adjusted via Change Order to reflect actuals.
Contractor agrees that he will make no claim for damages, anticipated
profits, or otherwise on account of any difference between the amounts
of work actually performed and materials actually furnished and the
estimated amounts thereof.
4. EXCAVATION AND STOCKPILING. Except where otherwise specified, the
unit price bid for each item of Work which involves excavation, onsite
storage (if necessary), permanent stockpiling of PCB contaminated soil,
and permanent placement of the stockpile membrane cover shall include
all costs for such Work. The basis of payment will be the volume of
soil stockpiled in the permanent stockpile area as determined by the
Engineer's surveyor. All excavation shall be unclassified as to
materials which may be encountered. No additional or separate payment
shall be made for any labor, consumable materials, or other costs
incurred by the Contractor to remediate PCB materials spilled by the
Contractor.
01025-1
DRAFT
'August 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
5. REMOVAL AND NON-HAZARDOUS SOLID DISPOSAL. Except where otherwise
specified, the unit price bid for each item of Work which involves
removal, transportation, non-hazardous disposal, and (if necessary)
onsite storage, shall include all costs for such Work. The basis of
payment will be the weight of solid material actually disposed as
determined by disposal certificates. The Contractor shall arrange for
weighing of solid material to be disposed at a location approved by
Engineer.
6. REMOVAL AND HAZARDOUS/PCB SOLID DISPOSAL. Except where otherwise
specified, the unit price bid for each item of Work which involves
removal, transportation, hazardous disposal, and (if necessary) onsite
storage, shall include all costs for such Work. The basis of payment
will be the weight of solid material actually disposed as determined by
disposal certificates. The Contractor shall arrange for weighing of
solid material to be disposed at a location approved by Engineer.
7. PERMANENT STOCKPILE CONSTRUCTION. Except where otherwise
specified, the lump sum price bid for Work which involves construction
of the permanent stockpile area shall include all costs for such Work.
8. SEWERS. (Not Used).
9. PIPELINES. (Not Used).
10. MISCELLANEOUS CONCRETE. {Not Used).
11. DECONTAMINATION STATION CONSTRUCTION. Except where otherwise
specified, the lump sum price bid for construction, maintenance and
operation of the decontamination station shall include all coits for
such work.
12. EQUIPMENT DECONTAMINATION. Except where otherwise specified, the
unit or lump sum price bid for each item of Work which involves
decontamination and disposal shall include all costs for such work. No
separate payment shall be made for decontamination of Contractor's
equipment. No separate payment shall be made for treatment and/or
disposal of decontamination water or decontamination solutions. No
additional or separate payment shall be made for any labor, consumable
materials, or other costs incurred by the Contractor to remediate PCB or
decontamination materials spilled by the Contractor.
13. DEMOLITION. Except where otherwise specified, the lump sum price
bid for each.item of work which involves demolition shall include all
costs for such work. Engineer will classify all demolished materials as
either non-PCB contaminated or as material contaminated with PCBs.
01025-2
DRAFT
Augus1t 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
14. MOBILIZATION AND DEMOBILIZATION. Except where otherwise
specified, the lump sum price bid for mobilization and demobilization
shall include all costs for such work.
15. REMOVAL AND DISPOSAL OF NON PCB LIQUID PRODUCT. See paragraph 16
of this section.
16. REMOVAL AND DISPOSAL OF PCB LIQUID PRODUCT. Except where
otherwise specified, the unit price bid for each item of Work which
involves collection, removal, transportation, PCB liquid product or non
PCB liquid product disposal, and (if necessary) onsite storage, shall
include all costs for such Work. Contractor shall be compensated at the
unit price bid for disposal (in accordance with 40 CFR 761.60) of PCB
contaminated product. The basis of payment will be the volume of liquid
material actually disposed as determined by disposal certificates. The
Engineer shall inspect all containerized liquids prior to removal from
the site for disposal.
17. SITE CLEARING AND PREP WORK. Except where otherwise specified,
the lump sum price bid for Site Clearing and Prep Work shall include all
costs for such work.
18. REMOVAL AND DISPOSAL OF NON HAZARDOUS WASTEWATERS. Except where
otherwise specified, the unit price bid for each item of Work which
involves collection, removal, transportation, non-Hazardous liquid
disposal, and (if necessary) onsite storage, shall include all costs for
such Work. The basis of payment will be the volume of liquid material
actually disposed as determined by disposal certificates. The Engineer
shall inspect all containerized liquids prior to removal from the site
for disposal.
19. SITE FENCING. Except where otherwise specified, the unit price bid
for Work which involves the installation of new eight foot high
chainlink fencing shall include all costs for such Work.
End of Section
01025-3
DRAFT
Augusi 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION 01061
SITE SAFETY AND HEALTH PLAN REQUIREMENTS
PART 1 GENERAL
1.1 WORK INCLUDED
The requirements of this section pertain to all site activities.
1. 2 REFERENCES
CODE OF FEDERAL REGULATIONS (CFR)
29 CFR 1910
29 CFR 1926
Occupational Safety and Health Standards, General
Industry, latest edition.
Safety and Health Regulations, Construction
Industry, latest edition.
U.S. DEPARTMENT OF HEALTH AND HUMAN SERVICES
Occupational Safety and Health Guidance for Hazardous Waste Site
Activities, NIOSH, October 1985.
AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENIST
Threshold Limit Values and Biological Exposure Indices for 1993-94.
1. 3 PURPOSE
The Site Safety and Health Plan (SSHP) shall establish procedures,
safety and health requirements, and emergency response as required by
29 CFR 1910.120 for the protection of Contractor employees, visitors,
and the EPA's and Engineer's resident project representatives from
potential safety and health hazards during remediation activities at
the Carolina Transformer Superfund Site in Fayetteville, NC.
PART 2 PRODUCTS
2.1 SITE SAFETY AND HEALTH PLAN (SSHP)
The Contractor shall develop a SSHP which shall at a minimum include,
address, or document those specific topics or items required by 29 CFR
1910.120.
The Contractor shall be responsible for addressing the health and
safety issues related to the tasks outlined in the Scope of Work and
the hazards associated with the site and site activities. Individual
01061-1 . August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
copies of the SSHP shall be submitted to the Engineer by overnight
delivery for review 14 days prior to the start of remediation
activities at the site. Review of the plan will not constitute
approval or disapproval of the SSHP content. Data obtained during
previous site activities are contained in The Remedial Investigation
(RI) Report (included in the Contract Documents).
PART 3 EXECUTION
3.1 SSHP IMPLEMENTATION
The Contractor shall be responsible for implementation of the SSHP.
01061-2
DRAFT
August 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section 01300
SUBMITTALS
1. JOB PLAN. The Contractor shall submit two copies of the proposed
Job Plan via overnight carrier to the Engineer for approval not less
than 21 calendar days after award of contract. Engineer shall have one
week to review and comment in writing concerning the Job Plan.
Contractor shall have one week to address Engineer's comments and
resubmit to Engineer. Failure of Contractor to thoroughly incorporate
or address written comments by the specified deadline shall be
considered a material breach of Contractor's and Engineer's agreement
for services. Contractor shall maintain exclusive responsibility to
request clarification of any comment which is made by Engineer.
Requests and communications are required to be made by telephone and/or
facsimile during this time critical period. Changes to Engineer's
review comments shall only be accepted if made in writing and signed by
Engineer via facsimile or letter. The Job Plan shall be bound in such a
manner as to easily allow the removal and replacement of revised pages
and/or figures for the duration of the work.
The procedures for accomplishing all of the Work shall be submitted as
part of the Job Plan. The Job Plan shall contain but shall not be
limited to the following:
A Demolition Plan;
A Spill Prevention, Control, and Countermeasures Plan (SPCC Plan);
A Dust Control Plan; and
A UST Removal Plan.
A Decontamination Station Plan
la. Portion Submitted with Proposal. The Job Plan shall also contain
the following items which shall also be included as a portion of the
Contractors Proposal:
• Name and address of the firm to be used for transportation,
as well as the method (rail/truck etc.) to be used for the
transportation.
• Name and address of subcontractors to be used.
• Name and address of offsite treatment and disposal facilities
to be used.
• Name and address of liner manufacturer(s) and material
specification sheets.
• Name and address of all manufacturers and/or distributers of
materials and the trade name of all materials to be used for
work specified in these documents and drawings.
Substitutions proposed for materials to be used in the work, in place of
materials listed in Contractor's Proposal, shall be allowed only if
approved by the Engineer and shall be approved or disapproved at his
sole discretion.
01300-1 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2. CONSTRUCTION SCHEDULE. As part of the Job Plan, Contractor shall
submit to Engineer for review a schedule of the proposed construction
operations. The construction schedule shall indicate the sequence of
the Work and the time of starting and completion of each part.
At least every 30 days the schedule shall be revised as necessary to
refle~t changes in the progress of the Work.
Engineer may require Contractor to add to his equipment, or construction
forces, as well as increase the working hours, if operations fall behind
schedule at any time during the construction period.
3. PROGRESS REPORTS. A progress report shall be furnished to Engineer
with each application for progress payment. If the Work falls behind
schedule, Contractor shall submit additional progress reports at such
intervals as Engineer may request.
Each progress report shall include sufficient narrative to describe
current and anticipated delaying factors, their effect on the construc-
tion schedule, and proposed corrective actions. Any Work reported
complete, but which is not readily apparent to Engineer, must be sub-
stantiated with satisfactory evidence.
4. SCHEDULE OF VALUES. (Not Used).
5. SCHEDULE OF PAYMENTS. Within 15 days after award of contract,
Contractor shall furnish to Engineer a schedule of estimated monthly
payments. The schedule shall be revised and resubmitted each time an
application for payment varies more than 10 percent from the estimated
payment schedule.
6. SURVEY DATA. Contractor shall provide surveyor's field notes to
Engineer upon completion of Work. Survey data including coordinates and
elevations shall be recorded and included on Contractors As Built
drawings.
7. SHOP DRAWINGS AND ENGINEERING DATA. Contractor shall provide As-
Built drawings to Engineer within thirty calendar days after contractors
presence has been removed from the site. Contractor shall also submit
to Engineer the surveyor's field notes with the as-built drawings. As-
Built drawings shall indicate existing site conditions at completion of
the Contractor's field work and shall include but not be limited to
final ground elevations, elevation contours (ift intervals), existing
concrete slabs, existing fence, drainage culverts, roads, soil stockpile
location with differentiation of berm, soil portions and cover , and
onsite storage areas for materials if applicable. Contractor shall
provide 4 copies of the as-build drawings sealed by a North Carolina
Registered Surveyor. As-built drawings shall also be provided to
Engineer by Contractor in electronic format on 3~ inch floppy disk
01300-2
DRAFT
August 1'1, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
readable by an IBM compatible computer Personal Computer running DOS.
Computer Files shall be developed and saved by AutoCAD (Version 11 or
later) in AutoCAD DWG Format.
8. OPERATION AND MAINTENANCE DATA AND MANUALS. (Not Used).
9. LAYOUT DATA. (Not Used).
10. DENSITY TESTS. Contractor shall submit results of Standard Proctor
Density Tests in accordance with ASTM Standard D698 to the Engineer
prior to initiation of stockpiling soil in the Permanent Stockpile Area
as specified in Section 02050.
End of Section
01300-3 August li, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section 01400
QUALi TY CONTROL
1. TESTING LABORATORY SERVICES. All tests which require the services of a
laboratory to determine compliance with the Contract Documents shall be performed
by an independent commercial testing laboratory acceptable to Engineer. The
laboratory shall be staffed with experienced technicians, properly equipped, and
fully qualified to perform the tests in accordance with the specified standards.
Testing services provided by Engineer are for the sole benefit of Engineer.
However, test results shall be available to Contractor. Additional field or
laboratory testing necessary to satisfy Contractor's internal quality control
procedures shall be the sole responsibility of Contractor.
1.01. Testing Laboratory Services Furnished h Contractor. Unless otherwise
specified, Contractor shall be responsible for all testing laboratory services
in connection with the following:
All analytical testing required for waste characterization for any waste
designated for removal from site. This shall include but not be limited
to all testing of waste material as specified in the contract documents
and all testing required by Contractor's waste disposal facilities as a
condition of those facilities accepting waste from Contractor.
Particle Size (Sieve), Moisture-density (Proctor) and relative density
tests on backfill materials. Particle Size (Sieve} analyses used in
determination of Select Waste Soil.
All quality control testing required to demonstrate proper installation of
the stockpile liner system.
All other tests and engineering data required for Engineer's review of
materials (see Sections 02202 and 02203) and equipment proposed to be used
in the Work.
All sampling and onsite testing performed by Contractor or Contractor's sub-
contractors shall, at Engineer's option, be observed by Engineer. Contractor
sha 11 obtain Engineer's acceptance of the testing laboratory before having
services performed, and shall pay all costs for services.
1. 02. Testing Laboratory Services Furnished h Engineer. Unless otherwise
specified, Engineer wi 11 pay all charges of field analyses and testing
laboratories for quality contra l tests made for the purpose of determining
lateral and vertical extent of excavation of PCB contaminated soil.
Field sampling and testing will be performed by Engineer or testing laboratory
personnel, in the general manner indicated in the Specifications, with minimum
I
01400-1
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
interference with construction operations. Engineer will determine the exact
time and location of field sampling and testing, and may require such additional
sampling and testing as necessary to determine that materials and equipment
conform with data previously furnished by Contractor and with the Contract
Documents.
Arrangements for delivery of samples and test specimens, collected by Engineer,
to the testing laboratory will be made by Engineer. The testing laboratory will
perform all laboratory tests within a reasonable time consistent with the speci-
fied standards and will furnish a written report of each test.
Contractor shall furnish all sample materials and cooperate in the sampling and
field testing activities, interrupting the Work when necessary. When sampling
or testing activities are performed in the field by Engineer or testing
laboratory personne 1, Contractor sha 11 furnish personnel and facilities to assist
in the activities at no cost to Engineer.
1.03. Transmittal of Test Reports. Written reports of tests and engineering
data furnished by Contractor for Engineer's review of materials and equipment
proposed to be used in the Work shall be submitted as specified for Shop Drawings
in the General Conditions. The Contractor shall submit individual copies of the
test reports to the Owner and Engineer within 3 days of Contractor's receipt of
test results.
The testing laboratory retained by Engineer will furnish three copies of a
written report of each test performed by laboratory personnel in the field or
laboratory. Two copies of each test report will be transmitted to the Engineer
and one copy to Contractor within 3 days after ·each test result is received.
2. OFFSITE INSPECTION. (Not Used).
3. MANUFACTURER'S FIELD SERVICES.
3.01. Services Furnished Under This Contract. An experienced, competent, and
authorized representative of the manufacturer of each item of equipment for which
field services are indicated in the Contractor's Job Plan shall visit the site
of the Work and inspect, check, adjust if necessary, and approve the equipment
operation. In each case, the manufacturer's representative sha 11 be present when
the equipment is placed in operation. The manufacturer's representative shall
revisit the jobsite as often as necessary until all trouble is corrected and the
equipment operation is satisfactory in the opinion of Engineer.
All costs for these services shall be included in the Contract Price.
3.02. Services Furnished !ly_ Others. (Not Used).
End of Section
01400-2
DRAFT
I
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section 01500
TEMPORARY FACILITIES
1. OFFICE AT SITE OF WORK. During the performance of this contract,
Contractor shall maintain a suitable office at the site of the Work
which shall be the headquarters of his representative authorized to
receive drawings, instructions, or other communication or articles. Any
communication given to the said representative or delivered at
Contractor's office at the site of the Work in his absence shall be
deemed to have been delivered to Contractor.
Copies of the Drawings, Specifications, and other Contract Documents
shall be kept at Contractor's office at the site of the Work and avail-
able for use at all times.
2. ENGINEER'S OFFICE AT SITE OF WORK. The Contractor shall provide and
maintain a suitable office for the Engineer at the site of the Work.
The office shall consist of ninety square feet at minimum. The office
shall be air conditioned and heated to maintain ambient pir temperatures
between 69 and 78 degrees Fahrenheit. The contractor shall provide
approximately twenty five total square feet of horizontal desk working
space in two desk areas for the Engineer to perform analyses of samples
and perform required paperwork. The Contractor shall also provide a
refrigerator of 12 cubic feet in capacity at minimum, a five gallon
plastic bucket with handle, adequate lighting of approximately 2,000
foot-candles directly over the Engineer's desk area, a chair, a small
oscillating fan to ventilate the area if necessary, a separate telephone
line and telephone, access to a fax machine, and electrical power of
110V and two outlets at minimum in addition to those required for the
refrigerator and fan.
3. WATER. Contractor shall make all necessary arrangements and pay all
installation/connection and usage charges for potable water for
decontamination activities, drinking water, and operation of
Contractor's equipment, or for any other use by Contractor. Contractor
shall make all distribution arrangements.
4. POWER. Contractor shall make all necessary arrangements and pay all
installation/connection and usage charges for electrical power for
cooling, heating, lighting, operation of Contractor's equipment, or for
any other use by Contractor. Contractor shall make all distribution
arrangements.
5. TELEPHONE SERVICE. Contractor shall make all necessary arrangements
and pay all installation and usage charges for telephone lines and
service in its offices at the site and shall provide all telephone
instruments. Engineer shall reimburse Contractor for long distance
phone calls made by the Engineer.
I
01500-1 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
6. SANITARY FACILITIES. Contractor shall furnish temporary sanitary
facilities at the site, as provided herein, for the needs of all
construction workers,EPA's and Engineer's representatives, and others
performing work or furnishing services on the Project.
Sanitary facilities shall be of reasonable capacity, properly maintained
throughout the construction period, and obscured from public view to the
greatest practical extent. If toilets of the chemically treated type
are used, at least one toilet will be furnished for each 20 men. Con-
tractor shall enforce the use of such sanitary facilities by all person-
nel at the site.
7. CONSTRUCTION AIDS. (Not Used).
8. MAINTENANCE OF TRAFFIC. (Not Used).
9. BARRICADES AND LIGHTS. All streets, roads, highways, and other
public or private thoroughfares which are closed to traffic shall be
protected by effective barricades on which shall be placed acceptable
warning signs. Barricades shall be located at the nearest intersecting
public highway or street on each side of the blocked section.
All open trenches and other excavations shall have suitable barricades,
signs, and lights to provide adequate protection to the public.
Obstructions such as material piles and equipment shall be provided with
similar warning signs and lights.
All barricades and obstructions shall be illuminated with warning lights
from sunset to sunrise. Material storage and conduct of the Work on or
alongside public streets and highways shall cause the minimum obstruc-
tion and inconvenience to the traveling public.
All barricades, signs, lights, and other protective devices shall be
installed and maintained in conformity with applicable statutory
requirements and, where within railroad and highway rights-of-way, as
required by the authority having jurisdiction thereover.
10. FENCES. All existing fences affected by the Work shall be main-
tained by Contractor until completion of the Work. The Contractor shall
install new fencing at the perimeter of the site and the perimeter of
site access easements (if utilized) if fencing is not present upon
notice to proceed. New fences installed by the Contractor shall be
chainlink or equivalent as approved by the Engineer, six feet high at
minimum and shall be maintained by the Contractor until completion of
the work. Where new or existing fences must be maintained across roads
or construction easements, adequate gates shall be installed by the
Contractor. Gates shall be kept closed and locked at all times when not
in use. The Contractor shall provide all locks for fencing. Locks
shall be of solid brass construction and of the key-padlock type. The
contractor shall provide Engineer with keys to all locks for remaining
fencing upon completion of the work. All fencing shall remain,erect and
01500-2
DRAFT
August 11, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
in working condition when the Contractor completes the work and vacates
the site. However, fencing across easement properties may be removed or
relocated by the Contractor upon completion of the work at the
discretion of the Engineer.
11. PROTECTION OF PUBLIC AND PRIVATE PROPERTY. Contractor shall pro-
tect, shore, brace, support, and maintain all underground pipes, con-
duits, drains, and other underground construction uncovered or otherwise
affected by his construction operations. All pavement, surfacing,
driveways, curbs, walks, buildings, utility poles, guy wires, fences,
and other surface structures affected by construction operations shall
be restored to their original condition, except those structures
designated for removal, whether within or outside the easement. All
replacements shall be made with new materials.
All fire hydrants and water control valves shall be kept free from
obstruction and available for use at all times.
12. DAMAGE TO EXISTING PROPERTY. Contractor shall protect all existing
structures and property from damage and shall provide bracing, shoring,
or other work necessary for such protection.
Contractor shall be responsible for all damage to streets, roads, curbs,
sidewalks, highways, shoulders, ditches, embankments, culverts, bridges,
or other public or private property, which may be caused by transporting
equipment, materials, or men to or from the Work. Contractor shall make
satisfactory and acceptable arrangements with the agency having juris-
diction over the damaged property concerning its repair or replacement.
13. FLOOD PROTECTION. The facilities to be constructed are located in
the 100-year flood plain.
14. TREE AND PLANT PROTECTION. (Not Used).
15. ACCESS ROADS. If applicable, Contractor shall maintain access
roads to various parts of the site as required to complete the Project.
Such roads shall be available for the use of all others performing work
or furnishing services in connection with the Project.
16. PARKING. Contractor shall provide and maintain suitable parking
for all construction workers and others performing work or furnishing
services in connection with the Project, as required to avoid any need
for parking personal vehicles where they may interfere with public
traffic, Engineer's operations, or construction activities.
17. NOISE CONTROL. Contractor shall take reasonable measures to avoid
unnecessary noise. Such measures shall be appropriate for the normal
ambient sound levels in the area during working hours. All construction
machinery and vehicles shall be equipped with practical sound-muffling
devices, and operated in a manner to cause the least noise consistent
with efficient performance of the Work. 1
01500-3 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.1
18. DUST CONTROL. Dust control measures are specified in Section 02050
of these Contract Documents.
19. TEMPORARY DRAINAGE PROVISIONS. Contractor shall provide for the
drainage of storm water and such water as may be applied or discharged
on the site in performance of the Work. Drainage facilities shall be
adequate to prevent damage to the Work, the site, and adjacent property.
Existing drainage channels and conduits shall be cleaned, enlarged, or
supplemented as necessary to carry all increased runoff attributable to
Contractor's operations. Dikes shall be constructed as necessary to
divert increased runoff from entering adjacent property (except in
natural channels), to protect the Work, and to direct water to drainage
channels or conduits.
20. EROSION CONTROL. Contractor shall prevent erosion of soil on the
site and adjacent property resulting from his construction activities.
Effective. measures shall be initiated prior to the commencement of
clearing, grubbing, grading, excavation, or other operation that will
disturb the natural protection.
21. POLLUTION CONTROL. Contractor shall prevent the pollution of
drains and watercourses by sanitary wastes, sediment, debris, and other
substances resulting from construction activities. No sanitary wastes
shall be permitted to enter any drain or watercourse other than sanitary
sewers. No.sediment, debris, or other substance shall be permitted to
enter any drain or watercourse.
21a. SILT CONTROL. Contractor shall provide and install silt
fencing as indicated on the drawings and as directed by the
Engineer. Silt control measures shall be inspected and approved by
the Engineer. Contractor shall inspect and clean in-stream flow
through silt fencing daily and after each rain event or at
Engineer's request if more frequent.
22. PEST CONTROL. {Not Used).
23. RODENT CONTROL. (Not Used).
End of Section
I
01500-4 August 11, 1994
DRAFT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION 02050
PART 1
STORAGE, DISPOSAL, DEMOLITION AND DUST CONTROL
GENERAL
1.1 WORK INCLUDED The work includes the control of fugitive dust
emissions, demolition and disposal of the Main Building and adjacent
building ruins as indicated on drawings, , removal and disposal of site
vegetation, debris, four USTs, six electrical transformers, and if
necessary, the temporary onsite storage of non-contaminated and
contaminated materials. The requirements of this section pertain to all
site activities, as outlined in Section 01015 and as required to
complete the excavation, stockpiling and removal activities.
1.2 REFERENCES. The publications listed below form a part of this
specification to the extent referenced. The publications are referred
to in the text by basic designation only.
CODE OF FEDERAL REGULATIONS {CFR)
40 CFR 761 POLYCHLORINATED BIPHENYLS (PCBs) MANUFACTURING,
PROCESSING, DISTRIBUTION IN COMMERCE, AND USE
PROHIBITIONS.
NORTH CAROLINA ADMINISTRATIVE CODE
NORTH CAROLINA ADMINISTRATIVE CODE, TITLE 15A, Chapter13 SOLID
WASTE MANAGEMENT.
1.3 SUBMITTAL$. See Section 1300, SUBMITTAL$.
1.4 DEFINITIONS.
Drainage Gravel. Gravel placed above the membrane liner along the
containment berm to facilitate drainage and removal of leachate
and meets the requirements specified in Part 2 of this Section.
Geo Net. A polymeric material manufactured as a three dimensional
lattice to promote drainage within the plane of material
placement. Geo net is placed between the filter fabric and
membrane liner to allow space for leachate flow.
Filter Fabric. A non-woven polypropylene fabric manufactured to
allow passage of water while retaining soil particles without
clogging. Filter fabric is placed above geo net and membrane
liner to facilitate leachate drainage.
Membrane Cover. Sheeting which is placed on top of the permanent
soil stockpile to prevent rainwater infiltration and meets the
requirements specified in Part 2 of this Section. 1
02050-1
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Membrane Liner. Sheeting which is placed above select fill and
beneath the permanent soil stockpile to prevent stockpile leachate
from seeping into the surrounding soil and meets the requirements
specified in Part 2 of this Section.
Select Fill. Fill which is used to bring subgrade below the
membrane liner up to required elevation and grade and meets the
requirements specified in Part 2 of this Section.
Select Waste Soil. Select waste soil shall be that portion of
excavated contaminated soil which is able to pass a 3/4 inch U.S.
standard sieve and is free of rocks, debris, roots, deleterious
material and other sharp objects which may potentially damage the
Membrane Liner.
Silt Control Fence (Silt Fence). Slit-film woven polypropylene
fabric manufactured for the purpose of silt control application
and placed as a fence perpendicular to runoff flow in areas where
soil erosion is to be minimized or prevented.
Sump Cleanout Pipe. Slotted PVC pipe placed in the layer of
Drainage Gravel and against the stockpile berm to provide access
to remove drained liquids for disposal.
PART 2 PRODUCTS
2.1 Drainage Gravel.
quartzite gravel
Engineer.
Drainage gravel shall be uncontaminated
obtained from a local source and approved by the
2.2 Geo Net. The new Geonet shall consist of Gundle Gundnet® XL-14 or
equivalent as approved by the Engineer.
2.3 Filter Fabric. The new filter Fabric shall consist of Polyfelt
TS600® or equivalent as approved by the Engineer.
2.4 Membrane Cover. The new membrane cover shall consist of PVC
material of not less than 20 mills nominal thickness placed
continuously and sealed over the stockpiled soil to prevent the
infiltration of rainwater. The Cover Liner shall be Huls America
Inc. PVC 0176® or equivalent as approved by the Engineer.
2.5 Membrane Liner. The new membrane liner shall consist of high
density polyethylene (HDPE) material of not less than 30 mils
nominal thickness placed above Select Fill and below the Drainage
net for the purpose of providing a continuous impermeable barrier
to liquids. The Drainage Liner shall be GUNDLE GUNDLINE® HD or
equivalent as approved by the Engineer.
2.6 Select Fill. Select fill shall be uncontaminated soil obtained
from a local source, classified as "SC" under the Unified,Soil
Classification System and shall contain greater than 12% clay by
02050-2
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
weight. Other suitable material may be substituted as approved by
the Engineer. The Select Fill material shall be free of rocks,
debris, roots, organic, deleterious or frozen material which may
potentially damage the membrane liner. 100% of the Select Fill
material shall pass a #4 U.S. Standard Sieve.
2.7 Silt Fence Fabric. The new geotextile shall meet the minimum
specifications as follows:
2.8
2.9
Fabric Properties Mini mum
90
test method
ASTM D1682
ASTM D1682
ASTM D3786
ASTM D751
CW-02215
ASTM 9-26
grab tensile strength(LB)
elongation at fail {%)
Mullen burst strength (PSI)
puncture strength (lb)
equivalent opening size
ultraviolet stability{%)
50
190
40
40
40 -80
Sump Cleanout Pipe. The Sump Access pipe shall be new schedule 40
PVC pipe. The portion of pipe to be installed at the bottom of
the sump shall be slotted 0.050 inch openings.
GENERAL MEMBRANE REQUIREMENTS.
A. The new membrane liner shall consist of HDPE material as
appropriate and manufactured of new, first-quality products
designed and manufactured specifically for the purpose of
liquid contaminant in hydraulic structures.
B. The new membrane cover shall consist of PVC material as
appropriate and manufactured of new, first-quality products
designed and manufactured for use in liquid containment.
C.
D.
E.
F.
G.
The Contractor shall, at the time of bidding, .submit a
certification from the manufacturer(s) of the sheeting,
stating that the sheeting meets physical property
requirements for the intended application.
The liner or cover material shall be so produced as to be
free of holes, blisters, undispersed raw materials, or any
sign of contamination by foreign matter.
Labels on the roll shall identify the thickness, length, and
manufacturer's roll number. There shall be no factory seams.
The liner material shall meet the specification values
according to the specification sheet for HDPE or PVC
respectively.
All welding or adhesive material and equipment shall be of a
type supplied by the respective membrane manufacturer.
02050-3
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PART 3 EXECUTION
3.1 GENERAL WORK REQUIREMENTS. The Contractor shall handle, store, and
dispose of materials contaminated with PCBs in accordance with all
applicable governmental laws, regulations, and orders which include, but
are not limited to, the requirements of the Code of Federal Regulations
-Title 40 -Protection of the Environment, Part 761 (40 CFR 761) and
all regulations promulgated thereunder; and any State or local laws or
regulations of a similar nature which apply in addition to or in lieu of
the Federal requirements, if more extensive or more stringent.
The Contractor shall control fugitive dust emission in accordance with
all applicable governmental laws, regulations, and orders which include,
but are not limited to the requirements of any Federal or local laws or
regulations which apply in addition to or in lieu of the State
requirements, if more extensive or more stringent.
3.2 SPECIFIC WORK REQUIREMENTS. The work described in this Contract
shall include, but not be limited to, the following:
A.
B.
C.
The Contractor shall provide for permanent onsite stockpiling
of soil contaminated with PCBs, which shall include, but is
not limited to, providing all spill control, personnel
protection, containment, and infiltration control. This
portion of the work shall also include providing materials
and labor to construct a permanent soil stockpile area in
accordance with the contract documents and drawings.
The Contractor shall demolish, remove, and dispose of the
main building and adjacent building ruins as indicated on the
drawings, which shall include, but is not limited to,
personnel protection, transportation, permits, manifests, and
certificates of disposal. This portion of the work shall
also include removal and disposal of main building contents
including but not limited to drums of !OW as specified in (C)
below, and the collection, removal and stockpiling of PCB
contaminated soil from the floor of the building.
The Contractor shall remove and dispose of 100 drums of !OW
contained within the main building which shall include
providing temporary segregated onsite storage (if necessary)
and permanent offsite disposal of liquid contents of
investigation derived wastewater and the temporary
segregation and onsite permanent stockpiling of soil contents
of investigation derived solid waste. However, the
Contractor shall dispose of investigation derived PPE waste
as solid waste with site debris. The composition of the
drums is as follows:
• 24 drums containing drilling mud with composition
of approximately 80% water and 20% soil which has
settled,
• 32 drums containing soil cuttings,
02050-4
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3.3
•
•
39 drums containing decontamination and/or well
purge water, and
5 drums containing PPE .
D. The Contractor shall remove and dispose of all site
vegetation and debris including, but not limited to six
electrical transformers and contents if applicable, and four
USTs and contents if applicable. This portion of the work
shall include, but is not limited to, personnel protection,
transportation, permits, manifests, and certificates of
disposal. This portion of the work shall also include
permanent offsite treatment and/or disposal of the product
contents of the four USTs. Furthermore, the Contractor shall
be required to remove, dispose, and replace with like
materials existing drainage culverts located within the
limits of construction as indicated on the construction
drawings.
E. The Contractor shall field verify all weights, quantities and
dimensions shown on the drawings and listed in the
specifications. Dimensions, quantities, and weights on the
drawings and in the specifications are approximate.
PERMANENT STOCKPILE CONSTRUCTION. The Contractor shall provide
all labor, materials and equipment required to construct the
Stockpile in accordance with these specifications and the
construction drawings. The dimensions and slopes specified on the
construction drawings shall not be altered. After excavation and
removal of contaminated soil in the area of the permanent
stockpile is completed as determined by the Engineer the
Contractor shall begin permanent stockpile construction.
Contractor shall fill to grade and slope indicated on drawings.
Contractor shall then place Membrane Liner, Geo net and Filter
Fabric as specified in the drawings. A 24 inch layer of Select
Waste Soil shall then be applied over the entire stockpile area
before general stockpiling may proceed. As the height of the
stockpile is attained as specified in the drawings, the stockpile
shall be covered with the Cover Liner. Pieces of the Cover Liner
shall be welded together as each new piece of Cover Liner is laid
in place. New pieces shall be laid in place as the specified
height and capacity for each section is attained. A section is
defined as the width of the Cover Liner segments as received from
the manufacturer times the cross sectional area of the soil
stockpile.
A. STOCKPILE SUBGRADE CONSTRUCTION. The Contractor shall
provide all labor, materials and equipment required to
construct the Stockpile Subgrade. Contractor shall construct
Subgrade to the dimensions and slopes specified in the
construction drawings. The Subgrade shall be .constructed
with Select Fill compacted to 90% Standard Proctor Density at
minimum as determined by ASTM Standard D698.
02050-5
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
B. MEMBRANE LINER INSTALLATION. The Contractor shall provide
all labor, materials and equipment required to install the
Membrane Liner for the Stockpile Area. Contractor shall
install the Membrane Liner to the dimensions and
specifications shown in the construction drawings.
1.
2.
3.
4.
5.
Area Subgrade Preparation. Subsurfaces to be lined
shall be smooth and free of all rocks, sharp objects, or
debris of any kind. The surface should provide a firm,
unyielding foundation for the membrane with no sudden,
sharp or abrupt changes or break in grade. No standing
water or excessive moisture shall be allowed. The
installation contractor shall certify in writing that
the surface on which the membrane is to be installed is
acceptable before commencing work.
Field Seams. Individual panels of liner material shall
be laid out and overlapped by a maximum of four inches
(101 millimeters) for extrusion weld prior to welding or
five inches (127 millimeters) for hot wedge weld prior
to welding. Extreme care shall be taken by the
installer in the preparations of the areas to be welded.
The area to be welded shall be cleaned and prepared
according to the procedures laid down by the material
manufacturer. All sheeting shall be welded together by
means of integration of the extrudite bead with the
lining material, or all sheeting shall be welded
together using a hot wedge welding system.
The welding equipment used shall be capable of
continuously monitoring and controlling the temperature
in the zone of contact where the machine is actually
fusing the lining material so as to ensure that changes
in environmental conditions will not affect the
integrity of the weld.
No "open gaps'' shall be allowed within the seam area.
Where ''open gaps" occur, the material shall be cut,
overlapped, and an overlap extrusion weld shall be
applied.
Anchor Trenches. Membrane Liner anchor trenches will be
excavated in accordance with the lines and widths as
shown on the construction drawings prior to membrane
placement. The corners of the anchor trench shall be
rounded to avoid sharp bends in the liner. The anchor
trench shall be adequately drained to prevent ponding or
softening of adjacent soils while the trench is open.
02050-6
DRAFT
I
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3.4
C. STOCKPILE BERM CONSTRUCTION. The Contractor shall provide
all labor, materials and equipment required to construct the
berm surrounding the permanent soil stockpile. The berm
shall be constructed to the dimensions, grades, and slopes
specified on the construction drawings. Berm side slopes
shall not exceed 1:1 (one foot of vertical rise to one foot
of horizontal run). The stockpile berm shall be constructed
with Select Fill compacted to 90% Standard Proctor Density at
minimum as determined by ASTM Standard D698.
D. DRAINAGE SYSTEM. The Contractor shall provide all labor,
materials and equipment required to construct the Drainage
System for the stockpile. The Drainage System Area shall be
-·constructed to the dimensions and specifications shown on the
construction drawings. Drainage Net, Filter Fabric, Drainage
Gravel, and Sump Cleanout Pipe shall be as specified in the
Products Subsection of this Section.
Filter Fabric and Geonet will be handled in such a manner as
to ensure that they are not damaged in any way. Care will be
taken to assure that any underlying membrane layers are not
damaged during placement of Filter Fabric or Geonet. Care
shall be exercised to assure that stones, mud, and dirt are
not entrapped beneath the Filter Fabric and/or Goenet during
placement and seaming operations. Cutting and trimming of
product placed on top of the Membrane Liner shall be
performed with a hooked blade knife.
E. MEMBRANE COVER INSTALLATION. The Contractor shall provide
all labor, materials and equipment required to install the
Membrane Cover for the Stockpile Area. Contractor shall
install the Membrane Liner to the dimensions and
specifications shown in the construction drawings.
HANDLING, STORAGE, TRANSPORTATION, AND DISPOSAL. The Contractor
shall formulate a site-specific SPCC Plan for the project. The
plan shall include an outline of the procedures and contingency
plans for the removal, temporary storage, packing, transporting,.
or otherwise handling of the PCB material. This SPCC Plan shall
include measures designed to prevent spills or other risks to the
environment and equipment. The SPCC Plan shall list the personnel
required to implement the plan. Reference should be made to
local, State and Federal requirements satisfied by this plan and
its procedures. The SPCC Plan shall contain details and specific
procedures for the following:
a. Site Preparation/Spill Prevention at the Carolina
Transformer site
b. Spill Prevention During Transport
c. Spill Response Procedure
Instructions to Employees 1
Internal Reporting Procedures
02050-7
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
A.
B.
d.
e.
Guidelines for Notifying EPA and/or U.S. Coast
Guard of Spills in accordance with 40 CFR 761
Written Reports
Spill Cleanup Procedures
Containment
Containing and Remediating (in accordance with 40
CFR 761):
PCB in Water
PCB in Soils
PCB on Impervious and Nonimpervious Surfaces
Equipment to be Provided
Containers
Tools
Absorbent Materials
Solvents
Personnel Protection
Signs
The Contractor shall be responsible for the containment and
cleanup of any PCBs spilled during Work activities,
including all consumable materials required.
The Contractor shall store materials contaminated with PCBs
in accordance with all applicable regulations which include,
but are not limited to, 40 CFR 761 and as indicated on the
drawings.
Removal and Disposal of PCB Contaminated Materials.
1. The Contractor shall provide all labor, materials and
equipment required to remove, pack, transport, and
dispose of materials contaminated with PCBs. These
materials shall include, but not be limited to, the
existing contaminated PCB oil contained in the middle
UST east of the main building as indicated on the
drawings, and other materials which are contaminated as
determined by the Engineer.
2. The Contractor shall remove, pack, transport, and
dispose of solids contaminated with PCBs which may be
generated by him during Contract activities.
DISPOSAL OF DECONTAMINATION AND !OW WASTEWATERS. The
Contractor shall determine at which facility waste will be
disposed.
1. The Contractor shall provide all labor, materials and
equipment required to collect, remove, transport, and
dispose of decontamination and rancid wastewaters from
the decontamination station and drummed !OW wastewater
from previous investigations. Contractor may dAspose
wastewater at the City of Fayetteville's Public Works
02050-8
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-I
I
I
I
I
Commission sewage treatment plant. Contractor shall
adequately characterize wastewater as determined by the
City of Fayetteville Public Works Commission if
applicable.
C. REMOVAL AND DISPOSAL OF SITE VEGETATION AND DEBRIS. The
Contractor shall determine at which facility waste will be
disposed.
1.
2.
3.
The Contractor shall clear, remove and dispose of all
trees, shrubs and roots. This material may be disposed
in the non-hazardous landfill specified by the
Contractor in the Job Plan as determined by the
Contractor. Contractor is responsible for properly
characterizing waste prior to disposal.
The Contractor shall remove and properly dispose of all
debris located on the site. This material will be
disposed in the non-hazardous landfill specified by the
Contractor in the Job Plan if appropriate. Contractor
is responsible for properly characterizing all waste
prior to disposal.
The Contractor shall remove and dispose of all
electrical transformers located on the site. Some of
these transformers have been sampled and are classified
as non-PCB transformers in accordance with 40 CFR 761.3.
Analytical results are provided below. Additional
information is enclosed as Appendix A.
Transformer Serial Number Liquid Waste PCB Results
GE, OA-T class, #B686724 Below Detection Limit
Pennsylvania, one phase, #2552-2 Below Detection Limit
Pennsylvania, one phase, #2552-4 Contents not analyzed
Pennsylvania, one phase, #2552-3 Below Detection Limit
Unidentified Transformer Transformer empty, contents not
analyzed
GE, OA-T class, #B686723 Below Detection Limit
Non-PCB transformers shall be disposed in the non-
hazardous waste landfill specified by the Contractor in
the Job Plan. Contractor shall sample all transformers
prior to disposal to verify each transformer's status
with respect to PCB concentration. Any transformer with
oil containing greater than 50 ppm of PCBs or any
transformer which cannot be sampled shall be classified
as a PCB transformer.
02050-9
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4.
Contractor shall drain all transformers and dispose of
drained product as PCB oil or PCB contaminated oil, in
accordance with 40 CFR 761.70 at the PCB disposal
facility specified in Contractor's Job Plan.
PCB transformers, PCB contaminated transformers, and
unsampled transformers, and appurtenant piping shall be
considered PCB transformers and shall be disposed of by
the carcus destruction and smelting method in accordance
with 40 CFR 761.70. The Contractor or qualified
subcontractor shall have experience in handling,
transporting, and disposal of a minimum of five
transformers with gross weights in excess of ten tons
and a minimum of 1000 gallons of PCB contaminated oil.
In addition, the Contractor or qualified subcontractor
shall have the following minimum limits of insurance
coverages:
• One million dollars in contractors pollution
liability insurance,
• five million dollars in an environmental
restoration clause for contractors transportation
insurance, and
• ten million dollars in contractor's disposal
facility's environmental restoration insurance.
The Engineer shall be listed as an additional insured on
the Contractor's or qualified subcontractors pollution
liability insurance and automobile insurance.
Contractor is responsible for properly characterizing
all waste prior to disposal.
The Contractor shall remove, crush, and properly dispose
all USTs located on the site. All product-oil shall be
removed prior to disposal. All product-oil shall be
disposed as PCB oil or PCB contaminated oil in
accordance with 40 CFR 761.70 at the PCB facility
specified in the Contractors Job Plan.
The middle UST located northeast of the main building
contains PCBs in the product at concentrations of
approximately 72 ppm. The Contractor may characterize
and dispose of the middle UST as a PCB container (50 to
500 ppm) at the solid waste landfill specified in the
Job Plan. However, the container shall be flushed once
with solvent which has a PCB solubility of at least 10%
prior to crushing and disposal. The solvent shall be
drained and disposed with other product-oil. Hot
cutting shall not be used on this UST. Contractor is
responsible for properly characterizing all waste prior
to disposal.
02050-10
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
D. Transport of Materials Contaminated with PCBs. The
Contractor shall determine at which facility waste will be
disposed as approved by the Engineer.
1.
2.
3.
4.
5.
6.
7.
The Contractor shall transport materials contaminated
with PCBs in .accordance with all applicable regulations
which include, but are not limited to, the Code of
Federal Regulations -Title 49 -Transportation.
The Contractor shall instruct all personnel and
Subcontractors as to the proper procedures to be used
and the precautions to be followed in handling the
material and transporting it.
The Contractor shall require that all truck drivers and
railroad personnel be fully trained, authorized,
equipped and licensed to carry such material, in
accordance with all prudent safety precautions and all
applicable Federal, State, and local laws and
regulations and the SPCC Plan for the Carolina
Transformer Site. The Contractor shall provide all
transportation personnel with a copy of the SPCC Plan.
The Contractor shall submit to the Engineer and EPA
copies of the hazardous waste transporter licenses,
permits, or registrations for all states in which the
shipment will travel.
The Contractor shall require that all trucks and rail
cars and other equipment used for the performance of
this Contract shall be suitable for the particular
services requested and shall be periodically inspected
a·nd maintained.
The Contractor shall utilize containers, as required for
PCB storage, which meet the requirements of the Code of
Federal Regulations -Title 49 -Transportation, Part
173.
All Contractor personnel that will be involved with the
loading of materials contaminated with PCBs shall be
trained in the requirements of the SPCC Plan prior to
the loading of any materials contaminated with PCBs.
Proof of training for each person shall be submitted to
the Engineer.
The Contractor shall use engineering controls or shall
use the intermediate decontamination procedures (listed
in Section 02203) to minimize the contamination of the
exterior of the transportation vehicles during loading.
02050-11
DRAFT
I
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
E.
F.
Disposal of Materials Contaminated with PCBs. The Contractor
shall determine at which facility waste will be disposed as
approved by the Engineer.
1.
2.
Landfill of solid materials contaminated with PCBs shall
be performed at the designated EPA permitted chemical
waste/PCB landfill specified in the Contractor's Job
Plan.
Disposal of liquid materials contaminated with PCBs
shall be performed at the designated EPA permitted
disposal facility specified in the Contractor's Job
Plan.
3.The Contractor shall certify that the facility to which
waste will be delivered is licensed and permitted in
accordance with all applicable Federal, State and local laws,
regulations and ordinances to receive such waste. The
Contractor shall obtain the approval of the Engineer prior to
the use of any treatment, storage or disposal facility by
submitting a list of proposed facilities including detailed
descriptive outlines of the proposed procedures and processes
to be used. Waste shall not be diverted without the written
consent of the Engineer.
4.
5.
The Contractor shall comply with approval requirements
for chemical waste landfills, disposal facilities and
decontamination processes in 40 CFR 761.
The Contractor shall submit to the Engineer copies of
the permits for disposal facilities and landfills used.
Permits and Documentation for Handling and Disposal of
Materials Contaminated with PCBs.
Permits and documentation for handling and disposal of
materials contaminated with PCBs, as prepared and/or provided
by the Contractor, shall include, but not be limited to, the
following:
1. The Contractor shall initiate a manifest system for the
EPA's signature as the PCB generator to record the
transfer of materials contaminated with PCBs from the
Carolina Transformer Site to each Subcontractor and
through PCB destruction or disposal. This manifest
system shall be in accordance with 40 CFR 761. The
Contractor shall also initiate any manifest systems
required by State or local laws. The Contractor shall
provide completed copies of all manifests to the
Engineer with the handwritten signature of the owner or
operator of the designated disposal facility, within 35
02050-12
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3.5
3.6
2.
days of the date the waste was accepted by the initial
transporter.
All PCB Containers, PCB Article Containers, PCB
Articles, PCB Equipment, and PCB Transport Vehicles that
contain material having 50 ppm or greater PCBs shall be
labeled in accordance with 40 CFR 761. All labels (or
marks) shall be placed on the exterior of PCB Items and
transport vehicles so that they can be easily seen and
read by anyone inspecting or servicing the vehicles.
3. The Contractor shall provide a certificate of disposal
from the disposal facility indicating that all materials
contaminated with PCBs listed on the manifest have been
disposed in accordance with the applicable regulations
noted herein and this Contract. The certificate of
disposal shall itemize all materials contaminated with
PCBs and shall include the Hazardous Waste Manifest
document number and the date of disposal.
4. Submission of all documentation, including but not
limited to manifests and certificates of disposal, will
be a condition for progress payments.
DEMOLITION. The Contractor shall generate and submit a Demolition
Plan for the Main Building and adjacent building ruins . The plan
shall list: what equipment and procedures the Contractor shall
use to demolish the buildings, how the non-PCB contaminated and
the PCB contaminated portions of the buildings will be kept
segregated during demolition, removal and disposal methods for the
debris, and (if necessary) onsite storage. Hot cutting shall not
be used to demolish the building. The floor of the Main Building
is covered with a thin layer of soil. Wipe tests of the Main
Building floor indicate the presence of PCB contamination. The
source of the contamination is assumed to be the overlying soils.
Contractor shall remove and store these soils in the permanent
stockpile.
Engineer shall, at his discretion, collect samples from building.
debris for determination of PCB contaminated material, and provide
this information to the Contractor.
DUST CONTROL. The amount of dust resulting from excavation
activities shall be controlled to minimize health hazards, cross-
contamination and prevent the creation of a general nuisance in
the surrounding area. Use of water will not be permitted when it
will result in, or create, hazardous or objectionable conditions
such as ice, flooding, and pollution. The Contractor shall
generate and submit a Dust Control Plan. The plan shall list the
procedures and equipment the Contractor will use to minimize dust
during excavation, removal, and (if necessary) on-site storage.
The plan shall also explain what procedures and equipment1shall be
02050-13
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
used by the Contractor to minimize contamination by dust
contaminated with PCBs
3.7 TEMPORARY STOCKPILE. The Contractor shall place all material
excavated prior to Permanent Stockpile completion in the Temporary
Stockpile area designated on the construction drawings. Side
slopes of the Temporary Stockpile shall be no steeper than 2:3
(two feet of vertical rise to three feet of horizontal run). No
special containment structures shall be required for this
temporary construction. Engineer estimates required Temporary·
Stockpile dimensions to be approximately ten feet in height and 55
feet in length and width at the base of the pile. Contractor is
responsible for constructing the temporary stockpile in compliance
with all applicable Federal, State, and local safety regulations
and ordinances.
3.8 SILT FENCE. This work shall consist of furnishing and placing a
geotextile for erosion control and for controlling offsite
migration of PCB contaminated silt. The geotextile shall be
manufactured and installed to allow passage of water while
retaining soil without clogging. The quantities of silt control
fencing as shown on the drawings may be increased or decreased at
the direction of the Engineer based on construction procedures and
actual site conditions that occur during construction of the
project. Such variations in quantity will not be considered as
alterations in the details of construction or a change in the
character of the work.
END OF SECTION 02050
02050-14
DRAFT
I
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION 02202
EXCAVATION AND STOCKPILING
PART 1 GENERAL
1.1 WORK INCLUDED. The work includes the excavation and the
permanent stockpiling of approximately 8,500 cubic yards of PCB
contaminated soil. The term "soil" shall be defined as in 40 CFR
761.123 to be ''all vegetation, soils and other ground media, including
but not limited to, sand, grass, gravel and oyster shells. It does
not include concrete and asphalt." Additional excavation and
stockpiling may be required as determined by the Engineer.
1.2 REFERENCES. The publications listed below form a part of this
specification to the extent referenced. The publications are referred
to in the text by basic designation only.
CODE OF FEDERAL REGULATIONS (CFR)
40 CFR 761 POLYCHLORINATED BIPHENYLS (PCBs) MANUFACTURING,
PROCESSING, DISTRIBUTION IN COMMERCE, AND USE
PROHIBITIONS.
1.3 SUBMITTALS. The Contractor's proposed procedures for
accomplishing the excavation and stockpiling shall be submitted as
part of the Job Plan for review and approval by the Engineer. The
procedures shall provide for safe conduct of the work and protection
of property which is to remain undisturbed. The procedures shall
include a detailed description of the methods and equipment to be used
for each operation and the sequence of operations for the entire
project.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL WORK REQUIREMENTS.
A. The Contractor shall handle and stockpile the materials
contaminated with PCBs in accordance with all applicable
governmental laws, regulations, and orders which include,
but are not limited to, the requirements of the Code of
Federal Regulations -Title 40 -Protection of the
Environment, Part 761 (40 CFR 761), and all regulations
promulgated thereunder; and any State or local laws or
regulations of a similar nature which apply in addition to
or in lieu of the Federal requirements, if more extensive or
more stringent.
B. The Contractor shall take note that soil samples preyiously
collected show the presence of PCBs at a concentration
02202-1
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
requ1r1ng remediation (greater than 1 ppm PCB). The areas
and depths required for excavation have been designated and
are shown on the construction drawings. The estimated
quantity of soils requiring excavation is stated in the
Contractor's proposal form. However, if sampling and
analyses indicate that additional soils are contaminated,
the Engineer will direct the Contractor in excavating the
remaining PCB contaminated soils. Contractor shall be
compensated for additional excavation and stockpiling work
as specified in Section 1025.
3.2 REMOVAL OF DEBRIS AND RUBBLE. Debris and rubble shall be removed
until the original ground surface elevation has been reached. IN
accordance with the SPCC Plan and the Dust Control Plan, the
Contractor shall take the necessary steps to prevent any spills
or the creation of dust during the removal of debris and rubble.
3.3 EXCAVATION. The Contractor shall provide all the labor,
equipment, and materials required to excavate the materials
contaminated with PCBs. These materials shall include, but are
not limited to, the existing inplace soils, solid material
contained in drums of investigation derived waste, and other
construction materials which are contaminated with PCBs as
determined by the Engineer. The depth of initial excavation
shall be as indicated on the construction drawings. Once the
initial excavation has been completed, the Engineer will conduct
onsite confirmation sampling and analyses. If the analyses
indicate that further excavation is necessary, additional
material shall be removed as directed by Engineer. The Engineer
will then resample and re-analyze. Excavation shall be complete
when laboratory verification sample results indicate that all the
contaminated soil and material has been removed as determined by
the Engineer.
In accordance with the SPCC Plan and the Dust Control Plan, the
Contractor shall take the necessary steps to prevent any spills
or the creation of dust during excavation.
3.4 Quality Assurance Sampling. Following excavation to grades
indicated on the drawings, Engineer will perform Quality
Assurance Sampling. Quality Assurance analyses will consist of a
combination of field confirmation screening analyses and
laboratory verification analyses. Field Confirmation Screening
Analyses will be conducted by EPA Draft Method 4020 (immunoassay
technique). Laboratory Verification Analysis will be conducted
by SW 846 method 8080 for PCBs. Should additional excavation
become necessary, sampling and analyses will be performed at
Engineers discretion to insure that all contaminated soils have
been removed. Sampling locations will be based upon the sampling
grid established during the RI and indicated on the drawings as
grid centers. Four discrete subsamples will be collected,from
soils surrounding the grid center locations indicated on the
02202-2
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
drawings. The four subsamples will be composited and analyzed by
the specified field screening technique.
Laboratory verification analyses will be performed on samples
selected by the Engineer at the rate of 1 verification sample per
10 confirmation screening analysis. Laboratory verification
analyses will be conducted only on samples demonstrating low or
nondetectable PCB concentrations by field confirmation screening
analyses. In the event of discrepancy between field confirmation
screening results and laboratory verification results, the
laboratory verification results shall govern.
3.5 STOCKPILING. The Contractor shall provide all the labor,
equipment, and materials required to permanently stockpile
materials contaminated with PCBs. The Contractor shall
continuously stockpile contaminated material as it is excavated.
Excavated soil which is removed prior to and during construction
of the Permanent Stockpile shall be placed in the temporary
Stockpile Area designated on the construction drawings. Upon
completion of the Permanent Stockpile, soil shall be removed from
the Temporary Stockpile Area and Placed in the Permanent
Stockpile. Thereafter, all rema1n1ng and additional excavated
soil shall be placed in the Permanent Stockpile as it is
excavated.
3.6 REMOVAL AND ABANDONMENT OF TEMPORARY MONITORING WELLS. The
Contractor may, at his discretion and as approved by the
Engineer, remove and abandon unlocked temporary PVC monitoring
wells during excavation activities. However, monitoring wells
which are removed shall be abandoned in accordance with the
following procedures. No payment shall be made for any work on an
abandoned monitoring well. An abandoned monitoring well shall be
backfilled and sealed with cement-bentonite or high solids
bentonite grout as follows:
The cement-bentonite grout slurry shall weigh between 11 to
13 pounds per gallon and consist of 95 percent (by dry
weight) cement with 5 percent high-swelling bentonite mixed.
with no more water than is required for proper placement.
Cement shall conform to ASTM C 150, Type I. The grout shall
be thoroughly mixed and shall be used before any stiffening
occurs. The Contractor shall supply a balance to measure
the weight of the grout ..
The high solids bentonite grout shall be Baroid Drilling
Fluids, Inc. Aqua-Grout Catalyst/Benseal or an acceptable
equivalent approved by the Engineer. If a substitute grout
is proposed by the Contractor, the name of the product and
manufacturer's brochures shall be included with Attachment C
for review and approval by the Engineer. The.high solids
bentonite grout shall be mixed according to the 1
manufacturer's specifications.
02202-3
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Grout shall be placed by the tremie method. The tremie
method shall consist of pumping the slurry down the boring
through a pipe. The bottom of the pipe shall be placed near
the bottom of the zone to be grouted and shall be raised as
the grout is placed, always keeping the bottom of the tremie
pipe below the top of the grout. Pumps, piping, and other
materials for mixing and pumping grout shall be provided by
the Contractor.
3.7 BACKFILL. After completion of contaminated soil excavation and
verification that all contaminated material has been removed, the
excavated areas beside Middle Road designated on the drawings as
OPA3 shall be backfilled. Contractor shall place backfill
material to the necessary elevations to match initial grade.
The Contractor shall certify to Engineer that the backfill used
is clean soil which does not contain detectable concentrations of
PCBs, as required by 40 CFR 761.125(c)(4)(v). To accomplish
this, the Contractor shall provide to Engineer one original
laboratory certified test result via SW 846 method 8080 before
any backfill is placed and shall retest after placement of each
500 cubic yards of backfill. The Contractor shall also certify
to Engineer that the backfill used is clean soil free of
contaminants including but not limited to metaJs and organic
compounds. To accomplish this, prior to any backfill being
placed, the Contractor shall provide to Engineer laboratory
certified test results by EPA methods 6010, 8240/8260, and 8270
for every 500 cubic yards of the backfill soil.
Backfill material shall meet the Engineer's approval prior to
placement. Engineer may at his discretion resample inplace
backfill for consistency with the previously submitted analytical
results for the above chemical requirements. If inplace backfill
analysis is not consistent with previous results submitted by the
Contractor as determined by the Engineer, Contractor shall remove
unsatisfactory material, return it to place of origin, and
replace with satisfactory backfill without additional cost to the
Engineer.
Backfill shall be spread in lifts that will not exceed 8 inches
in thickness after compaction to 90% of maximum density at
· optimum moisture content (±2 percent) as determined by ASTM D698.
END OF SECTION
02202-4
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PART 1 GENERAL
SECTION 02203
DECONTAMINATION
1.1 WORK INCLUDED. The work includes construction of a
decontamination station and decontamination of the following:
• All vehicles and construction equipment
• Hand tools
• 100 !OW drums after emptied of contents
• Three USTs after emptied of contents
• One UST containing PCB contaminated product after emptied of
contents
Decontamination work shall also include management of the associated
decontamination water; and other appurtenant work.
1.2 REFERENCES.
CODE OF FEDERAL REGULATIONS (CFR)
40 CFR 761 Protection of the Environment
1.3 SUBMITTALS. The Contractor shall develop a Decontamination Plan
which shall at a minimum include methods to be used for:
• Construction of a decontamination station.
• Maintenance and operation of the decontamination station.
• Decontamination and quality assurance for vehicles, equipment,
tools, USTs and drums.
• Storage and treatment/disposal of decontamination water.
The above list is not all inclusive. A copy of the Decontamination Plan
shall be submitted to the Engineer for review concurrently with the Job
Plan; review of the plan will not constitute approval or disapproval of
the Decontamination Plan content.
The Contractor shall be responsible for implementation of the
Decontamination Plan.
PART 2 EXECUTION
2.1 CONSTRUCTION OF DECONTAMINATION STATION. Prior to
decontamination of equipment, the Contractor shall construct a
decontamination station. The location shall be as specified on the
construction drawings. The decontamination station shall be designed
and constructed by the Contractor to collect all runoff .from items being
decontaminated. The decontamination station design shall be developed
02203-1
DRAFT
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
by the Contractor and included with the Decontamination Plan for
approval by the Engineer. Liquid or solid residue collected at the
decontamination station shall be managed in accordance with all
applicable regulations and as specified in Subsection 3.3 of this
Section.
Demolition and reconstruction of the decontamination station may be
required between work sessions, during rainstorms or as directed by the
Engineer. Solid or liquid residue remaining in the decontamination
station shall be managed as discussed in Section 02050 and/or Subsection
3.3 of this Section.
Upon completion of the work, demolition of the decontamination station
shall. Plastic~sheeting and any solid or liquid residue remaining in
the decontamination station shall be managed as discussed in Section
02050 and/or Subsection 3.3 of this Section.
2.2 DECONTAMINATION OF EQUIPMENT. The Contractor shall be
responsible for performing decontamination of those items listed in
Subsection 1.1 of this Section. The Contractor shall also be
responsible for performing decontamination of items in addition to those
listed in Subsection 1.1 of this Section at the request of Engineer.
All items shall be decontaminated to such a degree that surface wipe
samples shall detect PCB concentrations at less than 10 ~g/lOOcm2
• In
addition, equipment used to collect or prepare samples shall be
decontaminated to such a degree that PCB concentrations are below sample
detection limits. The Contractor shall protect decontaminated items
from recontamination while stored onsite.
In addition, the Contractor shall be responsible for performing all
decontamination of personnel, equipment, and other material that becomes
contaminated as a result of site activities.
Decontamination of Contractor equipment shall be in accordance with the
requirements of 40 CFR 761.125(c)(4) and will be divided into three
phases: initial decontamination; intermediate decontamination; and
final decontamination. The initial decontamination shall be performed
before mobilizing the equipment to the site. The Contractor shall
thoroughly clean all equipment that will be brought on site and shall
provide the Engineer with certifications of decontamination.
Intermediate decontamination shall be performed in the following
situations: when equipment is moved from a ''contaminated'' area to a
"clean'' area, on trucks transporting materials offsite, or as directed
by the Engineer. Engineer reserves the right to sample vehicles
transporting materials offsite. Following intermediate decontamination,
decontaminated equipment that touches the ground in a contaminated area
will be considered contaminated and shall require additional
intermediate decontamination before being used in a different area. A
final decontamination of all Contractor equipment shall be performed by
the Contractor before leaving the site.
02203-2
DRAFT
I
August 12, 1994
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Decontaminated Contractor equipment may be sampled for PCBs by the
Engineer at any time at the Engineer's discretion. If Engineer samples
any piece of equipment, that equipment shall not leave the site until
Engineer has determined that it has been sufficiently decontaminated.
Equipment shall remain in the support zone until Engineer completes
analysis. If equipment is not sufficiently decontaminated, it shall be
returned to the decontamination station for further decontamination.
All decontamination water shall be managed as specified in Subsection
3.3 of this Section.
2.3 MANAGEMENT OF DECONTAMINATION WATER AND DECONTAMINATION
SOLUTIONS. The Contractor shall collect, transport and dispose of the
decontamination water and decontamination solutions in accordance with
all applicable laws, regulations, and orders. The Contractor shall
provide all drums, hoses, pumps, tank trucks and other equipment
necessary to collect, transport and dispose of the decontamination water
and decontamination solutions.
2.4 PERSONNEL DECONTAMINATION. The Contractor shall provide the
necessary equipment and supplies for personnel decontamination. The
Contractor personnel shall follow the decontamination procedures
specified in the Contractor's Site Safety and Health Plan. The
Contractor shall properly dispose of all PPE wastes in accordance with
all applicable laws, regulations and orders.
End of Section
02203-3
DRAFT
I
August 12, 1994