Loading...
HomeMy WebLinkAboutNCD003188844_19940815_Carolina Transformer_FRBCERCLA RD_Draft Remedial Design-OCRI I I I I I I I I I I I I I I I ii :1 I DRAFT REMEDIAL DESIGN for the Carolina Transformer Site Fayetteville, North Carolina I I I I I I I I I I I I I I I I I I I DRAFT REMEDIAL DESIGN Carolina Transformer Fayetteville, North Carolina Prepared for U.S. ENVIRONMENTAL PROTECTION AGENCY Region IV EPA Work Assignment N2 18-4NC2 Prepared by BLACK & VEATCH WASTE SCIENCE, INC. Atlanta, Georgia August 15, 1994 ---------- ------- ---"""Schedule of Sciill:xcavation for""Carolina Transformer Weeks rm 5 ' 7 8 9 10 11 12 13 14 15 1B 17 18 19 20 Survev Const. Limits Survey Grid System of Front 1 /3 of Site Fence The Site Office Setuo Temc. Decon Station Const. Temc. Stockoile Lavout Drummed Water Removal Time Estimates Based on All Work Drummed Soil Relocation being carried out in Health and Clearing and Grubbing(Frant 1/3 of Site and Safety Level D. Permanent Stockpile Areal IcxcavatIon{Front 1f.3 of site and Permanent Stocki:ile Areal Survey Back 2/3 of Site II I ID /A\ I c: 11' ~ Test 1 f3 of Site and Permanent Stockpile Area i UC u,J u u Construct Permanent Oecon Pad Construct Permanent Stockoile 1 ransfer 01 ~oil From l emp. Stockp1 e to Permanent Stockpile Remove Contaminated Soil in Building Decon Buildina Demolition of Buildina Removal of Buildina Debris Test Buildina Foundation Oecon Foundation Clearing and Grubbing (Back 2/3 of Site) Establish Sill/ Sediment Control Creek Excavation/Temp. Road Const./CMP Removal and.Replacement ( Creek Berm Liner lnstallatio~::i Excavation Back 213 of Site Secure Stockpile Remove Debris Demobilize I Soil Excavation 00 ill Cost Estimate ffi ~ V Carolina Transformer I Descrigtion Quanitiy Unit Eguigment Material Labor Total Survey Construction Limits 4.50 Acre $0.00 $189.00 $1,777.50 $1,966.50 Survey Grid System of Site 120.00 EA $0.00 $600.00 $5,400.00 $6,000.00 Fence Installation 2030.00 LF $3,471.30 $11,165.00 $5,278.00 $19,914.30 I Gate Installation 3.00 EA $127.50 $190.50 $195.00 $513.00 Office Setup 1.00 EA $0.00 $990.00 $296.80 $1,286.80 Temporary Decon Station Const. 1200.00 SF $0.00 $192.00 $108.00 $300.00 I Water Disposal 10000.00 GAL $200.00 $270.00 $1,000.00 $1,470.00 Drummed Water Removal 3200.00 GAL $32.00 $0.00 $96.00 $128.00 Drummed Soil Relocation 2310.00 GAL $300.30 $0.00 $254.10 $554.40 I Clearing and Grubbing 4.50 ACRE $4,725.00 $0.00 $4,275.00 $9,000.00 Excavation of Site 10000.00 CY $33,600.00 $0.00 $14,100.00 $47,700.00 Onsite Analytical 200.00 EA $0.00 $11,516.00 $1,484.00 $13,000.00 I Ollsite Analytical 20.00 EA $50.00 $3,000.00 $240.00 $3,290.00 Permanant Decon Pad Const (Excavation) 237.00 CY $796.32 $0.00 $334.17 $1,130.49 Permanant Decon Pad Const.(Conc. Work) 50.00 CY $570.00 $5,650.00 $8,950.00 $15,170.00 I Permanant Stockpile Const. (Clearing) 189.00 CY $459.27 $0.00 $200.34 $659.61 Stockpile Liner Const.(Membrane 21600.00 SF $0.00 $13,824.00 $6,480.00 $20,304.00 Drainage Net, Geotextile) Berm Construction and Liner Fill Material 978.00 CY $3,286.08 $4,890.00 $1,378.98 $9,555.06 I Transfer of Soil from Temporary Stockpile-1200.00 CY $4,032.00 $0.00 $1,692.00 $5,724.00 to Permanant Stockpile Removal Contaminated Soil/Debris From Building 1.00 LS $0.00 $0.00 $0.00 $500.00 I Decon Building 8.00 HR $150.00 $0.00 $148.40 $298.40 Demolttion of Building 11956.00 CF $1,195.60 $0.00 $836.92 $2,032.52 Removal/Disposal of Building and Site Debris 887.00 CY $11,087.50 $0.00 $3,592.35 $14,679.85 I Disposal of PCB Contaminated Transformers 20000.00 LB $0.00 $25,000.00 $0.00 $25,000.00 Disposal of Non-PCB Contaminated Transformers 40.00 TON $0.00 $1,400.00 $0.00 $1,400.00 Silt/Sediment Control 908.00 SY $0.00 $989.72 $980.64 $1,970.36 Creek Excavation 460.00 CY $1,545.60 $0.00 $648.60 $2,194.20 I Temporary Road Construction 119.00 CY $399.84 $0.00 $167.79 $567.63 CMP Removal and Replacement 60.00 LF $33.00 $507.00 $177.00 $717.00 Stockpile Secure 1.00 LS $0.00 $0.00 $0.00 $500.00 I Final Debris Removal & Disposal 4.00 CY $50.00 $189.16 $2.60 $241.76 Health & Safety Cost 20.00 Week $40,000.00 $0.00 $0.00 $40,000.00 Mobilization/Demobilization 1.00 LS $0.00 $0.00 $0.00 $6,000.00 I Subtotal $106,111.31 $80,562.38 $60,094.19 $253,767.88 Health and Safety Training 15% $0.00 $0.00 $9,014.13 $9,014.13 I Equipment Decontamination 8% $8,488.90 $0.00 $0.00 $8,488.90 Escalation 5% $5,305.57 $4,028.12 $3,004.71 $12,338.39 I Subtotal $119,905.78 $84,590.50 $72,113.03 $283,609.31 I Sales Tax6% $7,194.35 $5,075.43 $0.00 $12,269.78 Overhead 8% $9,592.46 $6,767.2~ $5,769.04 $22,128.74 I Profit 10% $11,990.58 $8,459.05 $7,211.30 $27,660.93 Subtotal $148,683.17 $104,892.22 $85,093.37 $338,668.76 I Total $338,668.76 I I I I I I I I I I I I I I I I I I I I Proposal Form Attachment 1 LUMP SUM OR UNIT PRICE SUMMARY Item of the Work SITE PREPARATION 1) Fence Installation per drawings. 2) Onsite Clearing and Prep Work per Section 02202. 3) 4) Offsite Clearing and Prep Work per Section 02202. Silt/Sediment Control Fencing Installation per drawings and Section 02050. EXCAVATION AND STOCKPILING 1) Permanent Stockpile Construction per drawings and Section 02050. 2) Excavation and Stockpiling of PCB Contaminated Soil per drawings and Sections 02202. Lump Sum or Engineers Unit Cost estimated quantity Unit Cost ($/LF) Lump Sum Unit Cost ($/Acre) Unit Cost ($/SY) Unit Cost ($/SF) Unit Cost ($/CY) 2,300 1 2 908 30,600 10,000 DEMOLITION, REMOVAL, TRANSPORTATION, AND DISPOSAL 1) Demolition of Buildings per Lump Sum drawings and Section 02050. 2) 3) Removal, Transportation, and Disposal of Non- Hazardous Solid debris, including Non-PCB contaminated transformers per section 02050. Removal, Transportation, and Disposal of Hazardous/PCB Solid debris, excluding PCB transformers per Section 02050. Unit Cost ($/TON) Unit Cost ($/TON) 1 1,530 10 Proposed Proposed Unit Price Price I I I I I 4) 5) 6) Removal, Transportation, Carcass Destruction, Smelting, and Disposal of PCB transformers per Section 02050. Removal, Transportation, and Disposal of Non- Hazardous wastewaters per Section 02050. Removal, Transportation, and Disposal of PCB Contaminated Product per Section 02050. I DECONTAMINATION I I I I I I I I I I I I I 1) Construction, Maintenance, and Operation of Temporary and Permanent Decontamination Station per Section 02203. OTHER COST 1) 2) 3) PERFORMANCE AND PAYMENT BOND Provide Performance and Payment Bond in Accordance With the General Conditions. Contractor Shall Indicate Cost of Bond as a Percentage of the Contract Sum. Mobilization Demobilization Unit Cost ($/TON) Unit Cost ($/GAL) Unit Cost ($/GAL) Lump Sum Percentage of Contract Sum Lump Sum Lump Sum 10 4,000 3,000 1 N/A 1 1 Total Estimate Bid Cost I I I I I I I I I I I I I I I I I I I I Table of Contents Division 1 SECTION 01015 PROJECT REQUIREMENTS Page t\Q. 1. Pre-Bid Meeting and Site Visit ............................... 01015-1 2. General Description of Work ............................... 01015-1 3. Other Contracts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2 4. Contracts and Communications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2 5. Work By Public Utilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2 6. Responsibility for Onsite Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-2 7. Responsibility for Onsite Equipment .......................... 01015-2 8. Offsite Storage .......................................... 01015-2 9. Equivalent Materials and Equipment .......................... 01015-2 10. Preparation for Shipment .................................. 01015-3 11. Salvage of Materials and Equipment .......................... 01015-3 12. Land for Construction Purposes ............................. 01015-3 13. Operation of Existing Facilities .............................. 01015-3 14. Notices to Owners and Authorities ........................... 01015-3 15. Lines and Grades ........................................ 01015-3 16. Allowances ............................................. 01015-4 17. Connections to Existing Utilities ............................. 01015-4 18. Unfavorable Construction Conditions ......................... 01015-4 19. Cutting and Patching ..................................... 01015-4 20. Asbestos Removal ....................................... 01015-5 21. Cleaning Up ............................................ 01015-5 22. Applicable Codes ........................................ 01015-5 23. Reference Standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-5 24. Abbreviations, Symbols and Definitions ........................ 01015-6 25. Alternatives ............................................ 01015-6 26. Preconstruction Conference ................................ 01015-6 27. Progress Meetings ........................................ 01015-7 28. Site Administration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01015-8 29. Notification ............................................ 01015-8 30. Substantial Completion and Completion ....................... 01015-8 SECTION 01025 MEASUREMENT AND PAYMENT 1. Scope ................................................ . 2. General .............................................. . 3. Contract Sum and Estimated Quantities ...................... . 4. Excavation and Stockpiling ................................ . 5. Removal and Non-Hazardous Solid Disposal ................... . 6. Removal and Hazardous Solid/PCB Disposal ................... . 7. Permanent Stockpile Construction ........................... . 8. Sewers ............................................... . 9. Pipelines .............................................. . 10. Miscellaneous Concrete .................................. . 11. Decontamination Station Construction ......................... . 2 E . D . . ' 1 . qmpment econtammat1on ............................... . 13. Demolition ............................................ . 01025-1 01025-1 01025-1 01025-1 01025-2 01025-2 01025-2 01025-2 01025-2 01025-2 01025-2 01025-2 01025-2 TC-1 August 12, 1994 I I I I I I I I I I I I I I I I I I I Table of Contents (Continued) Division 1 (Continued) Page fl>. 14. Mobilization and Demobilization ............................. 01025-3 15. Removal and Disposal of Non PCB Liquid Product ............... 01025-3 16. Removal and Disposal of PCB Liquid Product .................. 01025-3 17. Site Clearing and Prep Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01025-3 18. Removal and Disposal of Non-Hazardous Liquids ................ 01025-3 19. Site Fencing ............................................ 01025-3 SECTION 01061 SITE SAFETY AND HEALTH PLAN REQUIREMENTS 1. General ............................................... 01061-1 1.1 Work Included ....................................... 01061-1 1.2 References ......................................... 01061-1 1.3 Purpose ............................................ 01061-1 2. Products ............................................... 01061-1 2.1 Site Safety and Health Plan (SSHP) ....................... 01061-1 3. Execution .............................................. 01061-2 3.1 SSHP Implementation ................................. 01061-2 SECTION 01300 SUBMITTALS 1. Job Plan ............................................... 01300-1 2. Construction Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2 3. Progress Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2 4. Schedule of Values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2 5. Schedule of Payments ..................................... 01300-2 6. Survey Data ............................................ 01300-2 7. Shop Drawings and Engineering Data . . . . . . . . . . . . . . . . . . . . . . . . . 01300-2 8. Operation and Maintenance Data and Manuals .................. 01300-3 9. Layout Data ............................................ 01300-3 10. Density Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01300-3 SECTION 01400 QUALITY CONTROL 1. Testing Laboratory Services ................................ 01400-1 1.01 Testing Laboratory Services Furnished by Contractor ......... 01400-1 1.02 Testing Laboratory Services Furnished by Engineer .......... 01400-1 1.03 Transmittal of Test Reports ............................ 01400-2 2. Offsite Inspection ........................................ 01400-2 3. Manufacturer's Field Services ............................... 01400-2 3.01 Services Furnished Under This Contract ................... 01400-2 3.02 Services Furnished by Others ........................... 01400-2 SECTION 01500 TEMPORARY FACILITIES 1. Office at Site of Work .................................... 01500-1 2. Engineer's Office at Site of Work ............................ 01500-1 3. Water ................................................. 01500-1 4. Power .............................................. ,. ... 01500-1 5. Telephone Service ....................................... 01500-1 6. Sanitary Facilities ........................................ 01500-2 TC-2 August 12, 1994 I I I I I I I I I I I I I I I I I I I Table of Contents (Continued) Division 1 (Continued) Page N-2. 7. Construction Aids ........................................ 01500-2 8. Maintenance of Traffic .................................... 01500-2 9. Barricades and Lights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-2 10. Fences ................................................ 01500-2 11. Protection of Public and Private Property ...................... 01500-3 12. Damage to Existing Property . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3 13. Flood Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3 14. Tree and Plant Protection .................................. 01500-3 15. Access Roads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3 16. Parking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3 17. Noise Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-3 18. Dust Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4 19. Temporary Drainage Provisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4 20. Erosion Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4 21. Pollution Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4 22. Pest Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4 23. Rodent Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 01500-4 Division 2 SECTION 02050 STORAGE, DISPOSAL, DEMOLITION AND DUST CONTROL 1. General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-1 1.1 Work Included ....................................... 02050-1 1.2 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-1 1.3 Submittals .......................................... 02050-1 1.4 Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-1 2. Products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2 2.1 Drainage Gravel ..................................... 02050-2 2.2 Geo Net . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2 2.3 Filter Fabric . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2 2.4 Membrane Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2 2.5 Membrane Liner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2 2.6 Select Fill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-2 2. 7 Silt Fence Fabric . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-3 2.8 Sump Cleanout Pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-3 2.9 General Membrane Requirements . . . . . . . . . . . . . . . . . . . . . . . . 02050-3 3. Execution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-4 3.1 General Work Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-4 3.2 Specific Work Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-4 3.3 Permanent Stockpile Construction . . . . . . . . . . . . . . . . . . . . . . . . 02050-5 3.4 Handling, Storage, Transportation, and Disposal . . . . . . . . . . . . . . 02050-7 3.5 Demolition ........................................ 02050-13 3.6 Dust Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02050-13 3.7 Temporary Stockpile .............................. :' .. 02050-14 3.8 Silt Fence ......................................... 02050-14 TC-3 August 12, 1994 I I I I I I I I I I I I I I I I I I I Table of Contents (Continued) Division 2 (Continued) SECTION 02202 EXCAVATION AND STOCKPILING PageN:2. 1. General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-1 1.1 Work Included ....................................... 02202-1 1.2 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-1 1.3 Submittals .......................................... 02202-1 2. Products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-1 3. Execution .............................................. 02202-1 3.1 General Work Requirements ............................ 02202-1 3.2 Removal of Debris and Rubble .......................... 02202-2 3.3 Excavation .......................................... 02202-2 3.4 Quality Assurance Sampling ............................. 02202-2 3.5 Stockpiling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-3 3.6 Removal and Abandonment of Temporary Monitoring Wells .... 02202-3 3. 7 Backfill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02202-4 SECTION 02203 DECONTAMINATION 1. General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1 1.1 Work Included ....................................... 02203-1 1.2 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1 1.3 Submittals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1 2. Execution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-1 2.1 Construction of Decontamination Station ................... 02203-1 2.2 Decontamination of Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-2 2.3 Management of Decontamination Water and Decontamination Solutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-3 2.4 Personnel Decontamination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 02203-3 I TC-4 August 12, 1994 I I I I I I I I I I I I I I I I I I I Section 01015 PROJECT REQUIREMENTS 1. PRE-BID MEETING AND SITE VISIT. A prebid meeting will be held at the site at the scheduled time and date indicated on the bid. documents. Contractor shall supply and wear tyveks and boot covers. PPE may be left onsite upon completion of meeting. A failure to attend by Contractor will result in Engineer disallowing the Contractor's Proposal. No additional compensation shall be made for the pre-bid meeting and site visit. 2. GENERAL DESCRIPTION OF WORK. The Work to be performed under these Contract Documents consists of: the clearing and grubbing of approximately 4.8 acres; the excavation and stockpiling of PCB contaminated soil; the demolition, removal, and off site disposal of non-PCB contaminated buildings; and the removal and disposal of six transformers, four underground storage tanks (USTs) and other various site debris at the Carolina Transformer NPL Site in Fayetteville, North Carolina. The excavation and stockpiling of soil contaminated with PCBs will be conducted by areas. Soils from the first areas excavated will be temporarily stockpiled in the designated Temporary Stockpile Area while a Permanent Stockpile Area is under construction. After Permanent Stockpile construction is completed, all future excavated soils and soils previously placed in the Temporary Stockpile Area will be placed in the Permanent Stockpile. After the initial excavation of an area, the Engineer will conduct verification sampling to deter~ine the presence or absence of PCBs. Samples will be analyzed immediately onsite by the Engineer. The Engineer will use the sample results to determine if additional excavation is necessary and if so, to what depth excavation will be conducted. The demolition, removal and disposal of existing buildings will proceed concurrently with soil excavation activities. One half-buried UST contains product with elevated concentrations of PCBs. The PCB contaminated product shall be removed and properly disposed in accordance with specifications in SECTION 02050. The empty tank will be removed, decontaminated if necessary, and properly disposed. Contractor shall prepare waste characterization and manifesting for all wastes to be disposed as required by local, State, or Federal regulations and the Contractor' selected and Engineer approved disposal facility. EPA or their authorized representatiye will sign all manifests as the waste Generator and Owner. · If necessary, the Work may also include the temporary onsite storage of PCB contaminated and non-contaminated materials. 1 01015-1 DRAFT August 11, 1994 I I I I I I I I I I I I I I I I I I I 3. OTHER CONTRACTS. Work at the site performed by others under separate contracts includes the following: Engineer will contract a surveyor to conduct a volume survey of the permanent soil stockpile to determine compensation for the Contractor. 4. CONTACTS AND COMMUNICATIONS. All submittals or communications with the Engineer shall be through the Engineering Project Manager or his appointed representative: Mr. Rob Vicevich, P.E., Engineering Project Manager BLACK & VEATCH Waste Science, Inc. 400 Northridge Road Suite 350 Atlanta, Georgia 30350 (404) 643-2346 All written correspondence between the Contractor and the Engineer shall be via overnight courier. Facsimile communications shall be confirmed by hardcopy via overnight courier. However, facsimile communications shall carry the same weight as an original instrument during the interim period prior to receipt of the hardcopy via overnight courier. 5. WORK BY PUBLIC UTILITIES. (Not Used). 6. RESPONSIBILITY FOR ONSITE EQUIPMENT. The Contractor shall be fully responsible for maintaining all existing permanent locked monitoring wells in working condition and shall take all reasonable precautions to prevent damage to permanent monitoring wells during excavation activities. Temporary unlocked PVC monitoring wells may be removed and abandoned in accordance with Subpart 3.5 of Section 02202 at the Contractors discretion. 7. RESPONSIBILITY FOR MATERIALS AND EQUIPMENT. (Not Used). 8. OFFSITE STORAGE. (Not used). 9. EQUIVALENT MATERIALS AND EQUIPMENT. Whenever a material or article is specified or described by using the name of a proprietary product or the name of a particular manufacturer or vendor, the specified item men- tioned shall be understood as establishing the type, function, and quality desired. Other manufacturers' products will be accepted provided sufficient information is submitted in advance to allow Engineer to determine that the products proposed are equivalent to those named. Such items shall be submitted for review by the procedure set forth in the submittals section. Requests for review of equivalency will not be accepted from anyone except Contractor, and such requests will not be considered until after the contract has been awarded. I 01015-2 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I 10. PREPARATION FOR SHIPMENT. (Not used). 11. SALVAGE OF MATERIALS AND EQUIPMENT. Existing materials removed as a part of the Work shall become Contractor's property, except those materials which are contaminated with PCBs. Any permanent items damaged during demolition, excavation, or handling through carelessness or improper procedures shall be replaced by Contractor in kind or with new items. Existing materials removed by Contractor shall not be reused in the Work. 12a. LAND FOR CONSTRUCTION PURPOSES. The Contractor will be permitted to use available land on or near the site of the Work for construction purposes including parking, office space, storage of materials and equipment, and to provide access to the area of special conditions if necessary. The location and extent of the areas so used will be as follows: The Contractor may use the portion of the paved parking lot adjacent to .the site (southwest of the site) and a portion of the adjacent property to the northeast of the site to provide access from State Rt. 1714 (River Rd.) to the area of special conditions as specified herein and in the enclosed construction drawings. 12b. EASEMENTS AND RIGHTS-OF-WAY. All required easements and rights- of-way will be obtained by the Engineer for the Contractor. 13. OPERATION· OF EXISTING FACILITIES. (Not Used). 14. NOTICES TO OWNERS AND AUTHORITIES. of adjacent property and utilities when affect them. Contractor shall notify owners prosecution of the Work may When it is necessary to temporarily deny access by owners or tenants to their property, or when any utility service connection must be inter- rupted, Contractor shall give notices sufficiently in advance to enable the affected persons to provide for their needs. Notices will conform to any applicable local ordinance and, whether delivered orally or in writing, will include appropriate information concerning the interruption and instructions on how to limit their inconvenience. Utilities and other concerned agencies shall be contacted at least 24 hours prior to cutting or closing streets or other traffic areas or excavating near underground utilities or pole lines. 15. LINES AND GRADES. All Work shall be done to the lines, grades, and/or elevations indicated on the drawings. Basic horizontal and vertical control points will be established by the Contractor. These points shall be used as datum for the Work. All additional survey, layout, and measurement Work shall be performed by Contractor as a part of the Work. 01015-3 DRAFT August 11, 1994 I I I I I I I I I I I I I I I I I I I Contractor shall provide an experienced instrument man, competent assistants, and such instruments, tools, stakes, and other materials required to complete the survey, layout, and measurement Work. In addition, Contractor shall furnish, without charge, competent men from his force and such tools, stakes, and other materials as Engineer may require in checking survey, layout, and measurement Work performed by Contractor. Contractor shall remove and/or reconstruct Work which is improperly located. 16. ALLOWANCES. (Not Used). 17. CONNECTIONS TO EXISTING UTILITIES. Unless otherwise specified or indicated, Contractor shall make all necessary connections to Utilities, including water, sewer, gas, telephone, and electric as appropriate. In each case, Contractor shall receive permission from the owning utility prior to undertaking connections. Contractor shall protect utilities against deleterious substances and damage. Connections to existing utilities which are in service shall be thoroughly planned in advance, and all required equipment, materials, and labor shall be on hand at the time of undertaking the connections. Work shall proceed continuously (around the clock) if necessary to complete connections in the minimum time. Operation of valves or other appurtenances on existing utilities, when required, shall be by or coordinated with the owning utility. 18. UNFAVORABLE CONSTRUCTION CONDITIONS. During unfavorable weather, wet ground, or other unsuitable construction conditions, the Contractor shall confine his operations to work which will not be affected adversely by such conditions. No portion of the Work shall be constructed under conditions which would affect adversely the quality or efficiency thereof, unless special means or precautions are taken by Contractor to perform the work in a proper and satisfactory manner. In the event of rain or other form of precipitation, the permanent stockpile shall be covered as indicated in the drawings to prevent production of leachate or contaminant runoff. In the event that excessive leachate or contaminated runoff accumulates in the stockpile area due to Contractor's failure to cover the stockpiles, the Contractor shall dispose of such accumulation at Contractors sole expense. 19. CUTTING AND PATCHING. Contractor shall perform all cutting and patching required for the Work. Except when the cutting or removal of existing construction is specified or indicated, Contractor shall not undertake any cutting or demolition which may affect the structural stability of the Work without Engineer's concurrence. 01015-4 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I Contractor shall provide all shoring, bracing, supports, and protective devices necessary to safeguard all Work during cutting operations. Materials shall be cut and removed to the ings or as required to complete the Work. removed from the site by Contractor. 20. ASBESTOS REMOVAL. (Not used). extent indicated on the draw- All materials shall be 21. CLEANING UP. Contractor shall keep the premises free at all times from accumulations of waste materials and rubbish. Contractor shall provide adequate trash receptacles about the site, and shall promptly empty the containers when filled. Construction materials such as concrete forms and scaffolding shall be neatly stacked by Contractor when not in use. Contractor shall promptly remove splattered concrete, asphalt, oil, paint, corrosive liquids, and cleaning solutions from surfaces to prevent marring or other damage. Volatile wastes shall be properly stored in covered metal containers and removed daily. Wastes shall not be buried or burned on the site or disposed of into storm drains, sanitary sewers, streams, or waterways. All wastes shall be removed from the site and disposed of in a manner complying with local, State and Federal ordinances and antipollution laws. Adequate cleanup will be a condition for recommendation of progress payment applications. 22. APPLICABLE CODES. Applicable codes are referenced in the appropriate technical sections of these Construction Documents. 23. REFERENCE STANDARDS. Reference to standards, specifications, manuals, or codes of any technical society, organization, or associa- tion, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard specification, manual, code, or Laws or Regulations in effect at the time of opening of Proposals (or on the date Engineer signs the Proposal Form if there were no Proposals), except as may be otherwise specifically stated. However, no provision of any referenced standard, specification, manual, or code (whether or not specifically incorporated by reference in the Contract Documents) shall be effective to change the duties and responsibilities of Engineer, Contractor, Engineer, or any of their Consultants, agents, or employees from those set forth in the Contract Documents, nor shall it be effective to assign to Engineer, or any of their Consultants, agents, or employees, any duty or authority to supervise or direct the furnishing or performance of the Work. I 01015-5 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I 24. ABBREVIATIONS.SYMBOLS AND DEFINITIONS. Abbreviations and symbols used in the Contract Documents are defined as follows: CFR Code of Federal Regulations !OW Investigation Derived Waste OPAi Off-Property Area 1 (also areas 2 and 3) PCB Polychlorinated Biphenyls ppm Parts Per Million SSHP Site Safety and Health Plan SPCC Spill Prevention, Control, and Countermeasures UST Underground Storage Tank Definitions used in the Contract Documents are defined as follows: Site. Site shall mean the area within the limits of construction asindicated on the drawings. Area of Special Condition. The area in the northern corner of the property which may or may not provide difficulty to the Contractor due to saturated soils and standing water. Area is indicated on the drawings as Off-Property Area 2 (OPA2). Non-PCB Liquid Product. Liquids, primarily organic in nature, which contain less than 50 ppm of PCBs and have substantial BTU values. Typical substances are fuels, oils, etc .. PCB Liquid Product. Liquids, primarily organic in nature, which contain greater than 50 ppm of PCBs and have substantial BTU values. Typical substances are oils,·etc .. Non-Hazardous Wastewaters. Wastewaters derived from previous investigation activities, or stockpile leachate as verified by characterization analysis. 25. ALTERNATIVES. (NOT USED) 26. PRECONSTRUCTION CONFERENCE. Prior to the commencement of Work at the site, a preconstruction conference will be held at a mutually agreed time and place. The conference shall be attended by: Contractor and his superintendent. Principal Subcontractors. Engineer and his Resident Project Representative. Representatives of EPA. Other governmental representatives as appropriate. Others as requested by Contractor or Engineer. 01015-6 DRAFT August 11, 1994 I I I I I I I I I I I I I I I I I I I Unless previously submitted to Engineer, Contractor shall bring to the conference a tentative schedule for each of the following: Progress. Values for progress payment purposes. Shop Drawings and other submittals. The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The agenda wi 11 include: Contractor's tentative schedules. Transmittal, review, and distribution of Contractor's submittals. Processing applications for payment. Maintaining record documents. Critical Work sequencing. Field decisions and Change Orders. Use of premises, office and storage areas, security, housekeeping, and EPA's needs. Major equipment deliveries and priorities. Contractor's assignments for safety and first aid. Administration of the Contractor's Site Safety and Health Plan. Engineer will preside at the conference and will arrange for keeping the minutes and distributing the minutes to all persons in attendance. 27. PROGRESS MEETINGS. Contractor shall schedule and hold regular progress meetings at least weekly and at other times as requested by Engineer or required by progress of the Work. Contractor, Engineer, and all Subcontractors active on the site shall be represented at each meeting. Contractor may at his discretion request attendance by repre- sentatives of his suppliers, manufacturers, and other Subcontractors. Engineer will preside at the meetings and will provide for keeping and distribution of the minutes. The purpose of the meetings will be to review the progress of the Work, maintain coordination bf efforts, discuss changes in scheduling, and resolve other problems which may develop. 01015-7 DRAFT I August 11, 1994 I I I I I I I I I I I I I I I I I I I 28. SITE ADMINISTRATION. Contractor shall be responsible for all areas of the site used by him and all Subcontractors in the performance of the Work. He will exert full control over the actions of all employees and other persons with respect to the use and preservation of property and existing facilities, except such controls as may be specifically reserved to Engineer or others. Contractor has the right to exclude from the site all persons who have no purpose related to the Work or its inspection, and may require all persons on the site (except Engineer's employees) to observe the same regulations as he requires of his employees. 29. NOTIFICATION. The Contractor shall notify the Engineer if any of the following occur: 1. 2. 3. 4. 5. If the Contractor or Subcontractor is served with notice of violation of any law, regulation, permit or license which relates to this Contract. Proceedings are commenced which could lead to revocation of related permits or licenses. Permits, licenses, or other government authorizations relating to this Contract are revoked. Litigation is commenced which would affect this Contract. If the Contractor or Subcontractor becomes aware that its equipment or facilities are not in compliance, or may fail to comply in the future, with applicable laws or regulations. 30. SUBSTANTIAL COMPLETION AND COMPLETION. The Contractor shall have all building demolition material and site debris removed from the site and disposed by 120 calendar days from the Notice to Proceed. The Contractor shall have all soils contaminated with PCBs stockpiled in the permanent stockpile area, the permanent stockpile area securely covered, the site policed of all Contractor's equipment and debris, and the Contractor's presence gone from the site by 150 calendar days from the Notice to Proceed. End of Section 01015-8 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I Section 01025 MEASUREMENT AND PAYMENT 1. SCOPE. This section covers methods of measurement and payment for items~ork under this contract. 2. GENERAL. The Contract Sum shall cover all Work required by the Contract Documents, as selected by the Engineer. All costs in connection with the proper and successful completion of the Work, including furnishing all materials, equipment, supplies, and appurte- nances; providing all equipment and tools; and performing all necessary labor and supervision to fully complete the Work, shall be included in the unit and lump sum prices bid. All Work not specifically set forth as a pay item in the Proposal Form shall be considered a subsidiary obligation of Contractor and all costs in connection therewith shall be included in the prices bid. No additional or separate payment shall be made for any labor, consumable materials, or other costs incurred by the Contractor to replace unsatisfactory materials or workmanship as determined by the Engineer. 3. CONTRACT SUM AND ESTIMATED QUANTITIES. All estimated quantities stipulated in the Proposal Form or other Contract Documents are approximate and are to be used (a) as a basis for estimating the probable cost of the Work, (b) for the purpose of comparing the bids submitted for the Work, (c) as a basis for the Contract Sum as defined at the time of Contract Award, and (d) as a basis for the final Contract Sum at the completion of the Work. The actual amounts of work done and materials furnished may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work done and materials furnished. The Contract Sum, as defined at the time of Contract Award, will be adjusted via Change Order to reflect actuals. Contractor agrees that he will make no claim for damages, anticipated profits, or otherwise on account of any difference between the amounts of work actually performed and materials actually furnished and the estimated amounts thereof. 4. EXCAVATION AND STOCKPILING. Except where otherwise specified, the unit price bid for each item of Work which involves excavation, onsite storage (if necessary), permanent stockpiling of PCB contaminated soil, and permanent placement of the stockpile membrane cover shall include all costs for such Work. The basis of payment will be the volume of soil stockpiled in the permanent stockpile area as determined by the Engineer's surveyor. All excavation shall be unclassified as to materials which may be encountered. No additional or separate payment shall be made for any labor, consumable materials, or other costs incurred by the Contractor to remediate PCB materials spilled by the Contractor. 01025-1 DRAFT 'August 11, 1994 I I I I I I I I I I I I I I I I I I I 5. REMOVAL AND NON-HAZARDOUS SOLID DISPOSAL. Except where otherwise specified, the unit price bid for each item of Work which involves removal, transportation, non-hazardous disposal, and (if necessary) onsite storage, shall include all costs for such Work. The basis of payment will be the weight of solid material actually disposed as determined by disposal certificates. The Contractor shall arrange for weighing of solid material to be disposed at a location approved by Engineer. 6. REMOVAL AND HAZARDOUS/PCB SOLID DISPOSAL. Except where otherwise specified, the unit price bid for each item of Work which involves removal, transportation, hazardous disposal, and (if necessary) onsite storage, shall include all costs for such Work. The basis of payment will be the weight of solid material actually disposed as determined by disposal certificates. The Contractor shall arrange for weighing of solid material to be disposed at a location approved by Engineer. 7. PERMANENT STOCKPILE CONSTRUCTION. Except where otherwise specified, the lump sum price bid for Work which involves construction of the permanent stockpile area shall include all costs for such Work. 8. SEWERS. (Not Used). 9. PIPELINES. (Not Used). 10. MISCELLANEOUS CONCRETE. {Not Used). 11. DECONTAMINATION STATION CONSTRUCTION. Except where otherwise specified, the lump sum price bid for construction, maintenance and operation of the decontamination station shall include all coits for such work. 12. EQUIPMENT DECONTAMINATION. Except where otherwise specified, the unit or lump sum price bid for each item of Work which involves decontamination and disposal shall include all costs for such work. No separate payment shall be made for decontamination of Contractor's equipment. No separate payment shall be made for treatment and/or disposal of decontamination water or decontamination solutions. No additional or separate payment shall be made for any labor, consumable materials, or other costs incurred by the Contractor to remediate PCB or decontamination materials spilled by the Contractor. 13. DEMOLITION. Except where otherwise specified, the lump sum price bid for each.item of work which involves demolition shall include all costs for such work. Engineer will classify all demolished materials as either non-PCB contaminated or as material contaminated with PCBs. 01025-2 DRAFT Augus1t 11, 1994 I I I I I I I I I I I I I I I I I I I 14. MOBILIZATION AND DEMOBILIZATION. Except where otherwise specified, the lump sum price bid for mobilization and demobilization shall include all costs for such work. 15. REMOVAL AND DISPOSAL OF NON PCB LIQUID PRODUCT. See paragraph 16 of this section. 16. REMOVAL AND DISPOSAL OF PCB LIQUID PRODUCT. Except where otherwise specified, the unit price bid for each item of Work which involves collection, removal, transportation, PCB liquid product or non PCB liquid product disposal, and (if necessary) onsite storage, shall include all costs for such Work. Contractor shall be compensated at the unit price bid for disposal (in accordance with 40 CFR 761.60) of PCB contaminated product. The basis of payment will be the volume of liquid material actually disposed as determined by disposal certificates. The Engineer shall inspect all containerized liquids prior to removal from the site for disposal. 17. SITE CLEARING AND PREP WORK. Except where otherwise specified, the lump sum price bid for Site Clearing and Prep Work shall include all costs for such work. 18. REMOVAL AND DISPOSAL OF NON HAZARDOUS WASTEWATERS. Except where otherwise specified, the unit price bid for each item of Work which involves collection, removal, transportation, non-Hazardous liquid disposal, and (if necessary) onsite storage, shall include all costs for such Work. The basis of payment will be the volume of liquid material actually disposed as determined by disposal certificates. The Engineer shall inspect all containerized liquids prior to removal from the site for disposal. 19. SITE FENCING. Except where otherwise specified, the unit price bid for Work which involves the installation of new eight foot high chainlink fencing shall include all costs for such Work. End of Section 01025-3 DRAFT Augusi 11, 1994 I I I I I I I I I I I I I I I I I I I SECTION 01061 SITE SAFETY AND HEALTH PLAN REQUIREMENTS PART 1 GENERAL 1.1 WORK INCLUDED The requirements of this section pertain to all site activities. 1. 2 REFERENCES CODE OF FEDERAL REGULATIONS (CFR) 29 CFR 1910 29 CFR 1926 Occupational Safety and Health Standards, General Industry, latest edition. Safety and Health Regulations, Construction Industry, latest edition. U.S. DEPARTMENT OF HEALTH AND HUMAN SERVICES Occupational Safety and Health Guidance for Hazardous Waste Site Activities, NIOSH, October 1985. AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENIST Threshold Limit Values and Biological Exposure Indices for 1993-94. 1. 3 PURPOSE The Site Safety and Health Plan (SSHP) shall establish procedures, safety and health requirements, and emergency response as required by 29 CFR 1910.120 for the protection of Contractor employees, visitors, and the EPA's and Engineer's resident project representatives from potential safety and health hazards during remediation activities at the Carolina Transformer Superfund Site in Fayetteville, NC. PART 2 PRODUCTS 2.1 SITE SAFETY AND HEALTH PLAN (SSHP) The Contractor shall develop a SSHP which shall at a minimum include, address, or document those specific topics or items required by 29 CFR 1910.120. The Contractor shall be responsible for addressing the health and safety issues related to the tasks outlined in the Scope of Work and the hazards associated with the site and site activities. Individual 01061-1 . August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I copies of the SSHP shall be submitted to the Engineer by overnight delivery for review 14 days prior to the start of remediation activities at the site. Review of the plan will not constitute approval or disapproval of the SSHP content. Data obtained during previous site activities are contained in The Remedial Investigation (RI) Report (included in the Contract Documents). PART 3 EXECUTION 3.1 SSHP IMPLEMENTATION The Contractor shall be responsible for implementation of the SSHP. 01061-2 DRAFT August 11, 1994 I I I I I I I I I I I I I I I I I I I Section 01300 SUBMITTALS 1. JOB PLAN. The Contractor shall submit two copies of the proposed Job Plan via overnight carrier to the Engineer for approval not less than 21 calendar days after award of contract. Engineer shall have one week to review and comment in writing concerning the Job Plan. Contractor shall have one week to address Engineer's comments and resubmit to Engineer. Failure of Contractor to thoroughly incorporate or address written comments by the specified deadline shall be considered a material breach of Contractor's and Engineer's agreement for services. Contractor shall maintain exclusive responsibility to request clarification of any comment which is made by Engineer. Requests and communications are required to be made by telephone and/or facsimile during this time critical period. Changes to Engineer's review comments shall only be accepted if made in writing and signed by Engineer via facsimile or letter. The Job Plan shall be bound in such a manner as to easily allow the removal and replacement of revised pages and/or figures for the duration of the work. The procedures for accomplishing all of the Work shall be submitted as part of the Job Plan. The Job Plan shall contain but shall not be limited to the following: A Demolition Plan; A Spill Prevention, Control, and Countermeasures Plan (SPCC Plan); A Dust Control Plan; and A UST Removal Plan. A Decontamination Station Plan la. Portion Submitted with Proposal. The Job Plan shall also contain the following items which shall also be included as a portion of the Contractors Proposal: • Name and address of the firm to be used for transportation, as well as the method (rail/truck etc.) to be used for the transportation. • Name and address of subcontractors to be used. • Name and address of offsite treatment and disposal facilities to be used. • Name and address of liner manufacturer(s) and material specification sheets. • Name and address of all manufacturers and/or distributers of materials and the trade name of all materials to be used for work specified in these documents and drawings. Substitutions proposed for materials to be used in the work, in place of materials listed in Contractor's Proposal, shall be allowed only if approved by the Engineer and shall be approved or disapproved at his sole discretion. 01300-1 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I 2. CONSTRUCTION SCHEDULE. As part of the Job Plan, Contractor shall submit to Engineer for review a schedule of the proposed construction operations. The construction schedule shall indicate the sequence of the Work and the time of starting and completion of each part. At least every 30 days the schedule shall be revised as necessary to refle~t changes in the progress of the Work. Engineer may require Contractor to add to his equipment, or construction forces, as well as increase the working hours, if operations fall behind schedule at any time during the construction period. 3. PROGRESS REPORTS. A progress report shall be furnished to Engineer with each application for progress payment. If the Work falls behind schedule, Contractor shall submit additional progress reports at such intervals as Engineer may request. Each progress report shall include sufficient narrative to describe current and anticipated delaying factors, their effect on the construc- tion schedule, and proposed corrective actions. Any Work reported complete, but which is not readily apparent to Engineer, must be sub- stantiated with satisfactory evidence. 4. SCHEDULE OF VALUES. (Not Used). 5. SCHEDULE OF PAYMENTS. Within 15 days after award of contract, Contractor shall furnish to Engineer a schedule of estimated monthly payments. The schedule shall be revised and resubmitted each time an application for payment varies more than 10 percent from the estimated payment schedule. 6. SURVEY DATA. Contractor shall provide surveyor's field notes to Engineer upon completion of Work. Survey data including coordinates and elevations shall be recorded and included on Contractors As Built drawings. 7. SHOP DRAWINGS AND ENGINEERING DATA. Contractor shall provide As- Built drawings to Engineer within thirty calendar days after contractors presence has been removed from the site. Contractor shall also submit to Engineer the surveyor's field notes with the as-built drawings. As- Built drawings shall indicate existing site conditions at completion of the Contractor's field work and shall include but not be limited to final ground elevations, elevation contours (ift intervals), existing concrete slabs, existing fence, drainage culverts, roads, soil stockpile location with differentiation of berm, soil portions and cover , and onsite storage areas for materials if applicable. Contractor shall provide 4 copies of the as-build drawings sealed by a North Carolina Registered Surveyor. As-built drawings shall also be provided to Engineer by Contractor in electronic format on 3~ inch floppy disk 01300-2 DRAFT August 1'1, 1994 I I I I I I I I I I I I I I I I I I I readable by an IBM compatible computer Personal Computer running DOS. Computer Files shall be developed and saved by AutoCAD (Version 11 or later) in AutoCAD DWG Format. 8. OPERATION AND MAINTENANCE DATA AND MANUALS. (Not Used). 9. LAYOUT DATA. (Not Used). 10. DENSITY TESTS. Contractor shall submit results of Standard Proctor Density Tests in accordance with ASTM Standard D698 to the Engineer prior to initiation of stockpiling soil in the Permanent Stockpile Area as specified in Section 02050. End of Section 01300-3 August li, 1994 DRAFT I I I I I I I I I I I I I I I I I I I Section 01400 QUALi TY CONTROL 1. TESTING LABORATORY SERVICES. All tests which require the services of a laboratory to determine compliance with the Contract Documents shall be performed by an independent commercial testing laboratory acceptable to Engineer. The laboratory shall be staffed with experienced technicians, properly equipped, and fully qualified to perform the tests in accordance with the specified standards. Testing services provided by Engineer are for the sole benefit of Engineer. However, test results shall be available to Contractor. Additional field or laboratory testing necessary to satisfy Contractor's internal quality control procedures shall be the sole responsibility of Contractor. 1.01. Testing Laboratory Services Furnished h Contractor. Unless otherwise specified, Contractor shall be responsible for all testing laboratory services in connection with the following: All analytical testing required for waste characterization for any waste designated for removal from site. This shall include but not be limited to all testing of waste material as specified in the contract documents and all testing required by Contractor's waste disposal facilities as a condition of those facilities accepting waste from Contractor. Particle Size (Sieve), Moisture-density (Proctor) and relative density tests on backfill materials. Particle Size (Sieve} analyses used in determination of Select Waste Soil. All quality control testing required to demonstrate proper installation of the stockpile liner system. All other tests and engineering data required for Engineer's review of materials (see Sections 02202 and 02203) and equipment proposed to be used in the Work. All sampling and onsite testing performed by Contractor or Contractor's sub- contractors shall, at Engineer's option, be observed by Engineer. Contractor sha 11 obtain Engineer's acceptance of the testing laboratory before having services performed, and shall pay all costs for services. 1. 02. Testing Laboratory Services Furnished h Engineer. Unless otherwise specified, Engineer wi 11 pay all charges of field analyses and testing laboratories for quality contra l tests made for the purpose of determining lateral and vertical extent of excavation of PCB contaminated soil. Field sampling and testing will be performed by Engineer or testing laboratory personnel, in the general manner indicated in the Specifications, with minimum I 01400-1 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I interference with construction operations. Engineer will determine the exact time and location of field sampling and testing, and may require such additional sampling and testing as necessary to determine that materials and equipment conform with data previously furnished by Contractor and with the Contract Documents. Arrangements for delivery of samples and test specimens, collected by Engineer, to the testing laboratory will be made by Engineer. The testing laboratory will perform all laboratory tests within a reasonable time consistent with the speci- fied standards and will furnish a written report of each test. Contractor shall furnish all sample materials and cooperate in the sampling and field testing activities, interrupting the Work when necessary. When sampling or testing activities are performed in the field by Engineer or testing laboratory personne 1, Contractor sha 11 furnish personnel and facilities to assist in the activities at no cost to Engineer. 1.03. Transmittal of Test Reports. Written reports of tests and engineering data furnished by Contractor for Engineer's review of materials and equipment proposed to be used in the Work shall be submitted as specified for Shop Drawings in the General Conditions. The Contractor shall submit individual copies of the test reports to the Owner and Engineer within 3 days of Contractor's receipt of test results. The testing laboratory retained by Engineer will furnish three copies of a written report of each test performed by laboratory personnel in the field or laboratory. Two copies of each test report will be transmitted to the Engineer and one copy to Contractor within 3 days after ·each test result is received. 2. OFFSITE INSPECTION. (Not Used). 3. MANUFACTURER'S FIELD SERVICES. 3.01. Services Furnished Under This Contract. An experienced, competent, and authorized representative of the manufacturer of each item of equipment for which field services are indicated in the Contractor's Job Plan shall visit the site of the Work and inspect, check, adjust if necessary, and approve the equipment operation. In each case, the manufacturer's representative sha 11 be present when the equipment is placed in operation. The manufacturer's representative shall revisit the jobsite as often as necessary until all trouble is corrected and the equipment operation is satisfactory in the opinion of Engineer. All costs for these services shall be included in the Contract Price. 3.02. Services Furnished !ly_ Others. (Not Used). End of Section 01400-2 DRAFT I August 12, 1994 I I I I I I I I I I I I I I I I I I I Section 01500 TEMPORARY FACILITIES 1. OFFICE AT SITE OF WORK. During the performance of this contract, Contractor shall maintain a suitable office at the site of the Work which shall be the headquarters of his representative authorized to receive drawings, instructions, or other communication or articles. Any communication given to the said representative or delivered at Contractor's office at the site of the Work in his absence shall be deemed to have been delivered to Contractor. Copies of the Drawings, Specifications, and other Contract Documents shall be kept at Contractor's office at the site of the Work and avail- able for use at all times. 2. ENGINEER'S OFFICE AT SITE OF WORK. The Contractor shall provide and maintain a suitable office for the Engineer at the site of the Work. The office shall consist of ninety square feet at minimum. The office shall be air conditioned and heated to maintain ambient pir temperatures between 69 and 78 degrees Fahrenheit. The contractor shall provide approximately twenty five total square feet of horizontal desk working space in two desk areas for the Engineer to perform analyses of samples and perform required paperwork. The Contractor shall also provide a refrigerator of 12 cubic feet in capacity at minimum, a five gallon plastic bucket with handle, adequate lighting of approximately 2,000 foot-candles directly over the Engineer's desk area, a chair, a small oscillating fan to ventilate the area if necessary, a separate telephone line and telephone, access to a fax machine, and electrical power of 110V and two outlets at minimum in addition to those required for the refrigerator and fan. 3. WATER. Contractor shall make all necessary arrangements and pay all installation/connection and usage charges for potable water for decontamination activities, drinking water, and operation of Contractor's equipment, or for any other use by Contractor. Contractor shall make all distribution arrangements. 4. POWER. Contractor shall make all necessary arrangements and pay all installation/connection and usage charges for electrical power for cooling, heating, lighting, operation of Contractor's equipment, or for any other use by Contractor. Contractor shall make all distribution arrangements. 5. TELEPHONE SERVICE. Contractor shall make all necessary arrangements and pay all installation and usage charges for telephone lines and service in its offices at the site and shall provide all telephone instruments. Engineer shall reimburse Contractor for long distance phone calls made by the Engineer. I 01500-1 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I 6. SANITARY FACILITIES. Contractor shall furnish temporary sanitary facilities at the site, as provided herein, for the needs of all construction workers,EPA's and Engineer's representatives, and others performing work or furnishing services on the Project. Sanitary facilities shall be of reasonable capacity, properly maintained throughout the construction period, and obscured from public view to the greatest practical extent. If toilets of the chemically treated type are used, at least one toilet will be furnished for each 20 men. Con- tractor shall enforce the use of such sanitary facilities by all person- nel at the site. 7. CONSTRUCTION AIDS. (Not Used). 8. MAINTENANCE OF TRAFFIC. (Not Used). 9. BARRICADES AND LIGHTS. All streets, roads, highways, and other public or private thoroughfares which are closed to traffic shall be protected by effective barricades on which shall be placed acceptable warning signs. Barricades shall be located at the nearest intersecting public highway or street on each side of the blocked section. All open trenches and other excavations shall have suitable barricades, signs, and lights to provide adequate protection to the public. Obstructions such as material piles and equipment shall be provided with similar warning signs and lights. All barricades and obstructions shall be illuminated with warning lights from sunset to sunrise. Material storage and conduct of the Work on or alongside public streets and highways shall cause the minimum obstruc- tion and inconvenience to the traveling public. All barricades, signs, lights, and other protective devices shall be installed and maintained in conformity with applicable statutory requirements and, where within railroad and highway rights-of-way, as required by the authority having jurisdiction thereover. 10. FENCES. All existing fences affected by the Work shall be main- tained by Contractor until completion of the Work. The Contractor shall install new fencing at the perimeter of the site and the perimeter of site access easements (if utilized) if fencing is not present upon notice to proceed. New fences installed by the Contractor shall be chainlink or equivalent as approved by the Engineer, six feet high at minimum and shall be maintained by the Contractor until completion of the work. Where new or existing fences must be maintained across roads or construction easements, adequate gates shall be installed by the Contractor. Gates shall be kept closed and locked at all times when not in use. The Contractor shall provide all locks for fencing. Locks shall be of solid brass construction and of the key-padlock type. The contractor shall provide Engineer with keys to all locks for remaining fencing upon completion of the work. All fencing shall remain,erect and 01500-2 DRAFT August 11, 1994 I I I I I I I I I I I I I I I I I I I in working condition when the Contractor completes the work and vacates the site. However, fencing across easement properties may be removed or relocated by the Contractor upon completion of the work at the discretion of the Engineer. 11. PROTECTION OF PUBLIC AND PRIVATE PROPERTY. Contractor shall pro- tect, shore, brace, support, and maintain all underground pipes, con- duits, drains, and other underground construction uncovered or otherwise affected by his construction operations. All pavement, surfacing, driveways, curbs, walks, buildings, utility poles, guy wires, fences, and other surface structures affected by construction operations shall be restored to their original condition, except those structures designated for removal, whether within or outside the easement. All replacements shall be made with new materials. All fire hydrants and water control valves shall be kept free from obstruction and available for use at all times. 12. DAMAGE TO EXISTING PROPERTY. Contractor shall protect all existing structures and property from damage and shall provide bracing, shoring, or other work necessary for such protection. Contractor shall be responsible for all damage to streets, roads, curbs, sidewalks, highways, shoulders, ditches, embankments, culverts, bridges, or other public or private property, which may be caused by transporting equipment, materials, or men to or from the Work. Contractor shall make satisfactory and acceptable arrangements with the agency having juris- diction over the damaged property concerning its repair or replacement. 13. FLOOD PROTECTION. The facilities to be constructed are located in the 100-year flood plain. 14. TREE AND PLANT PROTECTION. (Not Used). 15. ACCESS ROADS. If applicable, Contractor shall maintain access roads to various parts of the site as required to complete the Project. Such roads shall be available for the use of all others performing work or furnishing services in connection with the Project. 16. PARKING. Contractor shall provide and maintain suitable parking for all construction workers and others performing work or furnishing services in connection with the Project, as required to avoid any need for parking personal vehicles where they may interfere with public traffic, Engineer's operations, or construction activities. 17. NOISE CONTROL. Contractor shall take reasonable measures to avoid unnecessary noise. Such measures shall be appropriate for the normal ambient sound levels in the area during working hours. All construction machinery and vehicles shall be equipped with practical sound-muffling devices, and operated in a manner to cause the least noise consistent with efficient performance of the Work. 1 01500-3 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I .1 18. DUST CONTROL. Dust control measures are specified in Section 02050 of these Contract Documents. 19. TEMPORARY DRAINAGE PROVISIONS. Contractor shall provide for the drainage of storm water and such water as may be applied or discharged on the site in performance of the Work. Drainage facilities shall be adequate to prevent damage to the Work, the site, and adjacent property. Existing drainage channels and conduits shall be cleaned, enlarged, or supplemented as necessary to carry all increased runoff attributable to Contractor's operations. Dikes shall be constructed as necessary to divert increased runoff from entering adjacent property (except in natural channels), to protect the Work, and to direct water to drainage channels or conduits. 20. EROSION CONTROL. Contractor shall prevent erosion of soil on the site and adjacent property resulting from his construction activities. Effective. measures shall be initiated prior to the commencement of clearing, grubbing, grading, excavation, or other operation that will disturb the natural protection. 21. POLLUTION CONTROL. Contractor shall prevent the pollution of drains and watercourses by sanitary wastes, sediment, debris, and other substances resulting from construction activities. No sanitary wastes shall be permitted to enter any drain or watercourse other than sanitary sewers. No.sediment, debris, or other substance shall be permitted to enter any drain or watercourse. 21a. SILT CONTROL. Contractor shall provide and install silt fencing as indicated on the drawings and as directed by the Engineer. Silt control measures shall be inspected and approved by the Engineer. Contractor shall inspect and clean in-stream flow through silt fencing daily and after each rain event or at Engineer's request if more frequent. 22. PEST CONTROL. {Not Used). 23. RODENT CONTROL. (Not Used). End of Section I 01500-4 August 11, 1994 DRAFT I I I I I I I I I I I I I I I I I I I SECTION 02050 PART 1 STORAGE, DISPOSAL, DEMOLITION AND DUST CONTROL GENERAL 1.1 WORK INCLUDED The work includes the control of fugitive dust emissions, demolition and disposal of the Main Building and adjacent building ruins as indicated on drawings, , removal and disposal of site vegetation, debris, four USTs, six electrical transformers, and if necessary, the temporary onsite storage of non-contaminated and contaminated materials. The requirements of this section pertain to all site activities, as outlined in Section 01015 and as required to complete the excavation, stockpiling and removal activities. 1.2 REFERENCES. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. CODE OF FEDERAL REGULATIONS {CFR) 40 CFR 761 POLYCHLORINATED BIPHENYLS (PCBs) MANUFACTURING, PROCESSING, DISTRIBUTION IN COMMERCE, AND USE PROHIBITIONS. NORTH CAROLINA ADMINISTRATIVE CODE NORTH CAROLINA ADMINISTRATIVE CODE, TITLE 15A, Chapter13 SOLID WASTE MANAGEMENT. 1.3 SUBMITTAL$. See Section 1300, SUBMITTAL$. 1.4 DEFINITIONS. Drainage Gravel. Gravel placed above the membrane liner along the containment berm to facilitate drainage and removal of leachate and meets the requirements specified in Part 2 of this Section. Geo Net. A polymeric material manufactured as a three dimensional lattice to promote drainage within the plane of material placement. Geo net is placed between the filter fabric and membrane liner to allow space for leachate flow. Filter Fabric. A non-woven polypropylene fabric manufactured to allow passage of water while retaining soil particles without clogging. Filter fabric is placed above geo net and membrane liner to facilitate leachate drainage. Membrane Cover. Sheeting which is placed on top of the permanent soil stockpile to prevent rainwater infiltration and meets the requirements specified in Part 2 of this Section. 1 02050-1 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I Membrane Liner. Sheeting which is placed above select fill and beneath the permanent soil stockpile to prevent stockpile leachate from seeping into the surrounding soil and meets the requirements specified in Part 2 of this Section. Select Fill. Fill which is used to bring subgrade below the membrane liner up to required elevation and grade and meets the requirements specified in Part 2 of this Section. Select Waste Soil. Select waste soil shall be that portion of excavated contaminated soil which is able to pass a 3/4 inch U.S. standard sieve and is free of rocks, debris, roots, deleterious material and other sharp objects which may potentially damage the Membrane Liner. Silt Control Fence (Silt Fence). Slit-film woven polypropylene fabric manufactured for the purpose of silt control application and placed as a fence perpendicular to runoff flow in areas where soil erosion is to be minimized or prevented. Sump Cleanout Pipe. Slotted PVC pipe placed in the layer of Drainage Gravel and against the stockpile berm to provide access to remove drained liquids for disposal. PART 2 PRODUCTS 2.1 Drainage Gravel. quartzite gravel Engineer. Drainage gravel shall be uncontaminated obtained from a local source and approved by the 2.2 Geo Net. The new Geonet shall consist of Gundle Gundnet® XL-14 or equivalent as approved by the Engineer. 2.3 Filter Fabric. The new filter Fabric shall consist of Polyfelt TS600® or equivalent as approved by the Engineer. 2.4 Membrane Cover. The new membrane cover shall consist of PVC material of not less than 20 mills nominal thickness placed continuously and sealed over the stockpiled soil to prevent the infiltration of rainwater. The Cover Liner shall be Huls America Inc. PVC 0176® or equivalent as approved by the Engineer. 2.5 Membrane Liner. The new membrane liner shall consist of high density polyethylene (HDPE) material of not less than 30 mils nominal thickness placed above Select Fill and below the Drainage net for the purpose of providing a continuous impermeable barrier to liquids. The Drainage Liner shall be GUNDLE GUNDLINE® HD or equivalent as approved by the Engineer. 2.6 Select Fill. Select fill shall be uncontaminated soil obtained from a local source, classified as "SC" under the Unified,Soil Classification System and shall contain greater than 12% clay by 02050-2 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I weight. Other suitable material may be substituted as approved by the Engineer. The Select Fill material shall be free of rocks, debris, roots, organic, deleterious or frozen material which may potentially damage the membrane liner. 100% of the Select Fill material shall pass a #4 U.S. Standard Sieve. 2.7 Silt Fence Fabric. The new geotextile shall meet the minimum specifications as follows: 2.8 2.9 Fabric Properties Mini mum 90 test method ASTM D1682 ASTM D1682 ASTM D3786 ASTM D751 CW-02215 ASTM 9-26 grab tensile strength(LB) elongation at fail {%) Mullen burst strength (PSI) puncture strength (lb) equivalent opening size ultraviolet stability{%) 50 190 40 40 40 -80 Sump Cleanout Pipe. The Sump Access pipe shall be new schedule 40 PVC pipe. The portion of pipe to be installed at the bottom of the sump shall be slotted 0.050 inch openings. GENERAL MEMBRANE REQUIREMENTS. A. The new membrane liner shall consist of HDPE material as appropriate and manufactured of new, first-quality products designed and manufactured specifically for the purpose of liquid contaminant in hydraulic structures. B. The new membrane cover shall consist of PVC material as appropriate and manufactured of new, first-quality products designed and manufactured for use in liquid containment. C. D. E. F. G. The Contractor shall, at the time of bidding, .submit a certification from the manufacturer(s) of the sheeting, stating that the sheeting meets physical property requirements for the intended application. The liner or cover material shall be so produced as to be free of holes, blisters, undispersed raw materials, or any sign of contamination by foreign matter. Labels on the roll shall identify the thickness, length, and manufacturer's roll number. There shall be no factory seams. The liner material shall meet the specification values according to the specification sheet for HDPE or PVC respectively. All welding or adhesive material and equipment shall be of a type supplied by the respective membrane manufacturer. 02050-3 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I PART 3 EXECUTION 3.1 GENERAL WORK REQUIREMENTS. The Contractor shall handle, store, and dispose of materials contaminated with PCBs in accordance with all applicable governmental laws, regulations, and orders which include, but are not limited to, the requirements of the Code of Federal Regulations -Title 40 -Protection of the Environment, Part 761 (40 CFR 761) and all regulations promulgated thereunder; and any State or local laws or regulations of a similar nature which apply in addition to or in lieu of the Federal requirements, if more extensive or more stringent. The Contractor shall control fugitive dust emission in accordance with all applicable governmental laws, regulations, and orders which include, but are not limited to the requirements of any Federal or local laws or regulations which apply in addition to or in lieu of the State requirements, if more extensive or more stringent. 3.2 SPECIFIC WORK REQUIREMENTS. The work described in this Contract shall include, but not be limited to, the following: A. B. C. The Contractor shall provide for permanent onsite stockpiling of soil contaminated with PCBs, which shall include, but is not limited to, providing all spill control, personnel protection, containment, and infiltration control. This portion of the work shall also include providing materials and labor to construct a permanent soil stockpile area in accordance with the contract documents and drawings. The Contractor shall demolish, remove, and dispose of the main building and adjacent building ruins as indicated on the drawings, which shall include, but is not limited to, personnel protection, transportation, permits, manifests, and certificates of disposal. This portion of the work shall also include removal and disposal of main building contents including but not limited to drums of !OW as specified in (C) below, and the collection, removal and stockpiling of PCB contaminated soil from the floor of the building. The Contractor shall remove and dispose of 100 drums of !OW contained within the main building which shall include providing temporary segregated onsite storage (if necessary) and permanent offsite disposal of liquid contents of investigation derived wastewater and the temporary segregation and onsite permanent stockpiling of soil contents of investigation derived solid waste. However, the Contractor shall dispose of investigation derived PPE waste as solid waste with site debris. The composition of the drums is as follows: • 24 drums containing drilling mud with composition of approximately 80% water and 20% soil which has settled, • 32 drums containing soil cuttings, 02050-4 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I 3.3 • • 39 drums containing decontamination and/or well purge water, and 5 drums containing PPE . D. The Contractor shall remove and dispose of all site vegetation and debris including, but not limited to six electrical transformers and contents if applicable, and four USTs and contents if applicable. This portion of the work shall include, but is not limited to, personnel protection, transportation, permits, manifests, and certificates of disposal. This portion of the work shall also include permanent offsite treatment and/or disposal of the product contents of the four USTs. Furthermore, the Contractor shall be required to remove, dispose, and replace with like materials existing drainage culverts located within the limits of construction as indicated on the construction drawings. E. The Contractor shall field verify all weights, quantities and dimensions shown on the drawings and listed in the specifications. Dimensions, quantities, and weights on the drawings and in the specifications are approximate. PERMANENT STOCKPILE CONSTRUCTION. The Contractor shall provide all labor, materials and equipment required to construct the Stockpile in accordance with these specifications and the construction drawings. The dimensions and slopes specified on the construction drawings shall not be altered. After excavation and removal of contaminated soil in the area of the permanent stockpile is completed as determined by the Engineer the Contractor shall begin permanent stockpile construction. Contractor shall fill to grade and slope indicated on drawings. Contractor shall then place Membrane Liner, Geo net and Filter Fabric as specified in the drawings. A 24 inch layer of Select Waste Soil shall then be applied over the entire stockpile area before general stockpiling may proceed. As the height of the stockpile is attained as specified in the drawings, the stockpile shall be covered with the Cover Liner. Pieces of the Cover Liner shall be welded together as each new piece of Cover Liner is laid in place. New pieces shall be laid in place as the specified height and capacity for each section is attained. A section is defined as the width of the Cover Liner segments as received from the manufacturer times the cross sectional area of the soil stockpile. A. STOCKPILE SUBGRADE CONSTRUCTION. The Contractor shall provide all labor, materials and equipment required to construct the Stockpile Subgrade. Contractor shall construct Subgrade to the dimensions and slopes specified in the construction drawings. The Subgrade shall be .constructed with Select Fill compacted to 90% Standard Proctor Density at minimum as determined by ASTM Standard D698. 02050-5 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I B. MEMBRANE LINER INSTALLATION. The Contractor shall provide all labor, materials and equipment required to install the Membrane Liner for the Stockpile Area. Contractor shall install the Membrane Liner to the dimensions and specifications shown in the construction drawings. 1. 2. 3. 4. 5. Area Subgrade Preparation. Subsurfaces to be lined shall be smooth and free of all rocks, sharp objects, or debris of any kind. The surface should provide a firm, unyielding foundation for the membrane with no sudden, sharp or abrupt changes or break in grade. No standing water or excessive moisture shall be allowed. The installation contractor shall certify in writing that the surface on which the membrane is to be installed is acceptable before commencing work. Field Seams. Individual panels of liner material shall be laid out and overlapped by a maximum of four inches (101 millimeters) for extrusion weld prior to welding or five inches (127 millimeters) for hot wedge weld prior to welding. Extreme care shall be taken by the installer in the preparations of the areas to be welded. The area to be welded shall be cleaned and prepared according to the procedures laid down by the material manufacturer. All sheeting shall be welded together by means of integration of the extrudite bead with the lining material, or all sheeting shall be welded together using a hot wedge welding system. The welding equipment used shall be capable of continuously monitoring and controlling the temperature in the zone of contact where the machine is actually fusing the lining material so as to ensure that changes in environmental conditions will not affect the integrity of the weld. No "open gaps'' shall be allowed within the seam area. Where ''open gaps" occur, the material shall be cut, overlapped, and an overlap extrusion weld shall be applied. Anchor Trenches. Membrane Liner anchor trenches will be excavated in accordance with the lines and widths as shown on the construction drawings prior to membrane placement. The corners of the anchor trench shall be rounded to avoid sharp bends in the liner. The anchor trench shall be adequately drained to prevent ponding or softening of adjacent soils while the trench is open. 02050-6 DRAFT I August 12, 1994 I I I I I I I I I I I I I I I I I I I 3.4 C. STOCKPILE BERM CONSTRUCTION. The Contractor shall provide all labor, materials and equipment required to construct the berm surrounding the permanent soil stockpile. The berm shall be constructed to the dimensions, grades, and slopes specified on the construction drawings. Berm side slopes shall not exceed 1:1 (one foot of vertical rise to one foot of horizontal run). The stockpile berm shall be constructed with Select Fill compacted to 90% Standard Proctor Density at minimum as determined by ASTM Standard D698. D. DRAINAGE SYSTEM. The Contractor shall provide all labor, materials and equipment required to construct the Drainage System for the stockpile. The Drainage System Area shall be -·constructed to the dimensions and specifications shown on the construction drawings. Drainage Net, Filter Fabric, Drainage Gravel, and Sump Cleanout Pipe shall be as specified in the Products Subsection of this Section. Filter Fabric and Geonet will be handled in such a manner as to ensure that they are not damaged in any way. Care will be taken to assure that any underlying membrane layers are not damaged during placement of Filter Fabric or Geonet. Care shall be exercised to assure that stones, mud, and dirt are not entrapped beneath the Filter Fabric and/or Goenet during placement and seaming operations. Cutting and trimming of product placed on top of the Membrane Liner shall be performed with a hooked blade knife. E. MEMBRANE COVER INSTALLATION. The Contractor shall provide all labor, materials and equipment required to install the Membrane Cover for the Stockpile Area. Contractor shall install the Membrane Liner to the dimensions and specifications shown in the construction drawings. HANDLING, STORAGE, TRANSPORTATION, AND DISPOSAL. The Contractor shall formulate a site-specific SPCC Plan for the project. The plan shall include an outline of the procedures and contingency plans for the removal, temporary storage, packing, transporting,. or otherwise handling of the PCB material. This SPCC Plan shall include measures designed to prevent spills or other risks to the environment and equipment. The SPCC Plan shall list the personnel required to implement the plan. Reference should be made to local, State and Federal requirements satisfied by this plan and its procedures. The SPCC Plan shall contain details and specific procedures for the following: a. Site Preparation/Spill Prevention at the Carolina Transformer site b. Spill Prevention During Transport c. Spill Response Procedure Instructions to Employees 1 Internal Reporting Procedures 02050-7 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I A. B. d. e. Guidelines for Notifying EPA and/or U.S. Coast Guard of Spills in accordance with 40 CFR 761 Written Reports Spill Cleanup Procedures Containment Containing and Remediating (in accordance with 40 CFR 761): PCB in Water PCB in Soils PCB on Impervious and Nonimpervious Surfaces Equipment to be Provided Containers Tools Absorbent Materials Solvents Personnel Protection Signs The Contractor shall be responsible for the containment and cleanup of any PCBs spilled during Work activities, including all consumable materials required. The Contractor shall store materials contaminated with PCBs in accordance with all applicable regulations which include, but are not limited to, 40 CFR 761 and as indicated on the drawings. Removal and Disposal of PCB Contaminated Materials. 1. The Contractor shall provide all labor, materials and equipment required to remove, pack, transport, and dispose of materials contaminated with PCBs. These materials shall include, but not be limited to, the existing contaminated PCB oil contained in the middle UST east of the main building as indicated on the drawings, and other materials which are contaminated as determined by the Engineer. 2. The Contractor shall remove, pack, transport, and dispose of solids contaminated with PCBs which may be generated by him during Contract activities. DISPOSAL OF DECONTAMINATION AND !OW WASTEWATERS. The Contractor shall determine at which facility waste will be disposed. 1. The Contractor shall provide all labor, materials and equipment required to collect, remove, transport, and dispose of decontamination and rancid wastewaters from the decontamination station and drummed !OW wastewater from previous investigations. Contractor may dAspose wastewater at the City of Fayetteville's Public Works 02050-8 DRAFT August 12, 1994 I I I I I I I I I I I I I I -I I I I I Commission sewage treatment plant. Contractor shall adequately characterize wastewater as determined by the City of Fayetteville Public Works Commission if applicable. C. REMOVAL AND DISPOSAL OF SITE VEGETATION AND DEBRIS. The Contractor shall determine at which facility waste will be disposed. 1. 2. 3. The Contractor shall clear, remove and dispose of all trees, shrubs and roots. This material may be disposed in the non-hazardous landfill specified by the Contractor in the Job Plan as determined by the Contractor. Contractor is responsible for properly characterizing waste prior to disposal. The Contractor shall remove and properly dispose of all debris located on the site. This material will be disposed in the non-hazardous landfill specified by the Contractor in the Job Plan if appropriate. Contractor is responsible for properly characterizing all waste prior to disposal. The Contractor shall remove and dispose of all electrical transformers located on the site. Some of these transformers have been sampled and are classified as non-PCB transformers in accordance with 40 CFR 761.3. Analytical results are provided below. Additional information is enclosed as Appendix A. Transformer Serial Number Liquid Waste PCB Results GE, OA-T class, #B686724 Below Detection Limit Pennsylvania, one phase, #2552-2 Below Detection Limit Pennsylvania, one phase, #2552-4 Contents not analyzed Pennsylvania, one phase, #2552-3 Below Detection Limit Unidentified Transformer Transformer empty, contents not analyzed GE, OA-T class, #B686723 Below Detection Limit Non-PCB transformers shall be disposed in the non- hazardous waste landfill specified by the Contractor in the Job Plan. Contractor shall sample all transformers prior to disposal to verify each transformer's status with respect to PCB concentration. Any transformer with oil containing greater than 50 ppm of PCBs or any transformer which cannot be sampled shall be classified as a PCB transformer. 02050-9 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I 4. Contractor shall drain all transformers and dispose of drained product as PCB oil or PCB contaminated oil, in accordance with 40 CFR 761.70 at the PCB disposal facility specified in Contractor's Job Plan. PCB transformers, PCB contaminated transformers, and unsampled transformers, and appurtenant piping shall be considered PCB transformers and shall be disposed of by the carcus destruction and smelting method in accordance with 40 CFR 761.70. The Contractor or qualified subcontractor shall have experience in handling, transporting, and disposal of a minimum of five transformers with gross weights in excess of ten tons and a minimum of 1000 gallons of PCB contaminated oil. In addition, the Contractor or qualified subcontractor shall have the following minimum limits of insurance coverages: • One million dollars in contractors pollution liability insurance, • five million dollars in an environmental restoration clause for contractors transportation insurance, and • ten million dollars in contractor's disposal facility's environmental restoration insurance. The Engineer shall be listed as an additional insured on the Contractor's or qualified subcontractors pollution liability insurance and automobile insurance. Contractor is responsible for properly characterizing all waste prior to disposal. The Contractor shall remove, crush, and properly dispose all USTs located on the site. All product-oil shall be removed prior to disposal. All product-oil shall be disposed as PCB oil or PCB contaminated oil in accordance with 40 CFR 761.70 at the PCB facility specified in the Contractors Job Plan. The middle UST located northeast of the main building contains PCBs in the product at concentrations of approximately 72 ppm. The Contractor may characterize and dispose of the middle UST as a PCB container (50 to 500 ppm) at the solid waste landfill specified in the Job Plan. However, the container shall be flushed once with solvent which has a PCB solubility of at least 10% prior to crushing and disposal. The solvent shall be drained and disposed with other product-oil. Hot cutting shall not be used on this UST. Contractor is responsible for properly characterizing all waste prior to disposal. 02050-10 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I D. Transport of Materials Contaminated with PCBs. The Contractor shall determine at which facility waste will be disposed as approved by the Engineer. 1. 2. 3. 4. 5. 6. 7. The Contractor shall transport materials contaminated with PCBs in .accordance with all applicable regulations which include, but are not limited to, the Code of Federal Regulations -Title 49 -Transportation. The Contractor shall instruct all personnel and Subcontractors as to the proper procedures to be used and the precautions to be followed in handling the material and transporting it. The Contractor shall require that all truck drivers and railroad personnel be fully trained, authorized, equipped and licensed to carry such material, in accordance with all prudent safety precautions and all applicable Federal, State, and local laws and regulations and the SPCC Plan for the Carolina Transformer Site. The Contractor shall provide all transportation personnel with a copy of the SPCC Plan. The Contractor shall submit to the Engineer and EPA copies of the hazardous waste transporter licenses, permits, or registrations for all states in which the shipment will travel. The Contractor shall require that all trucks and rail cars and other equipment used for the performance of this Contract shall be suitable for the particular services requested and shall be periodically inspected a·nd maintained. The Contractor shall utilize containers, as required for PCB storage, which meet the requirements of the Code of Federal Regulations -Title 49 -Transportation, Part 173. All Contractor personnel that will be involved with the loading of materials contaminated with PCBs shall be trained in the requirements of the SPCC Plan prior to the loading of any materials contaminated with PCBs. Proof of training for each person shall be submitted to the Engineer. The Contractor shall use engineering controls or shall use the intermediate decontamination procedures (listed in Section 02203) to minimize the contamination of the exterior of the transportation vehicles during loading. 02050-11 DRAFT I August 12, 1994 I I I I I I I I I I I I I I I I I I I E. F. Disposal of Materials Contaminated with PCBs. The Contractor shall determine at which facility waste will be disposed as approved by the Engineer. 1. 2. Landfill of solid materials contaminated with PCBs shall be performed at the designated EPA permitted chemical waste/PCB landfill specified in the Contractor's Job Plan. Disposal of liquid materials contaminated with PCBs shall be performed at the designated EPA permitted disposal facility specified in the Contractor's Job Plan. 3.The Contractor shall certify that the facility to which waste will be delivered is licensed and permitted in accordance with all applicable Federal, State and local laws, regulations and ordinances to receive such waste. The Contractor shall obtain the approval of the Engineer prior to the use of any treatment, storage or disposal facility by submitting a list of proposed facilities including detailed descriptive outlines of the proposed procedures and processes to be used. Waste shall not be diverted without the written consent of the Engineer. 4. 5. The Contractor shall comply with approval requirements for chemical waste landfills, disposal facilities and decontamination processes in 40 CFR 761. The Contractor shall submit to the Engineer copies of the permits for disposal facilities and landfills used. Permits and Documentation for Handling and Disposal of Materials Contaminated with PCBs. Permits and documentation for handling and disposal of materials contaminated with PCBs, as prepared and/or provided by the Contractor, shall include, but not be limited to, the following: 1. The Contractor shall initiate a manifest system for the EPA's signature as the PCB generator to record the transfer of materials contaminated with PCBs from the Carolina Transformer Site to each Subcontractor and through PCB destruction or disposal. This manifest system shall be in accordance with 40 CFR 761. The Contractor shall also initiate any manifest systems required by State or local laws. The Contractor shall provide completed copies of all manifests to the Engineer with the handwritten signature of the owner or operator of the designated disposal facility, within 35 02050-12 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I 3.5 3.6 2. days of the date the waste was accepted by the initial transporter. All PCB Containers, PCB Article Containers, PCB Articles, PCB Equipment, and PCB Transport Vehicles that contain material having 50 ppm or greater PCBs shall be labeled in accordance with 40 CFR 761. All labels (or marks) shall be placed on the exterior of PCB Items and transport vehicles so that they can be easily seen and read by anyone inspecting or servicing the vehicles. 3. The Contractor shall provide a certificate of disposal from the disposal facility indicating that all materials contaminated with PCBs listed on the manifest have been disposed in accordance with the applicable regulations noted herein and this Contract. The certificate of disposal shall itemize all materials contaminated with PCBs and shall include the Hazardous Waste Manifest document number and the date of disposal. 4. Submission of all documentation, including but not limited to manifests and certificates of disposal, will be a condition for progress payments. DEMOLITION. The Contractor shall generate and submit a Demolition Plan for the Main Building and adjacent building ruins . The plan shall list: what equipment and procedures the Contractor shall use to demolish the buildings, how the non-PCB contaminated and the PCB contaminated portions of the buildings will be kept segregated during demolition, removal and disposal methods for the debris, and (if necessary) onsite storage. Hot cutting shall not be used to demolish the building. The floor of the Main Building is covered with a thin layer of soil. Wipe tests of the Main Building floor indicate the presence of PCB contamination. The source of the contamination is assumed to be the overlying soils. Contractor shall remove and store these soils in the permanent stockpile. Engineer shall, at his discretion, collect samples from building. debris for determination of PCB contaminated material, and provide this information to the Contractor. DUST CONTROL. The amount of dust resulting from excavation activities shall be controlled to minimize health hazards, cross- contamination and prevent the creation of a general nuisance in the surrounding area. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding, and pollution. The Contractor shall generate and submit a Dust Control Plan. The plan shall list the procedures and equipment the Contractor will use to minimize dust during excavation, removal, and (if necessary) on-site storage. The plan shall also explain what procedures and equipment1shall be 02050-13 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I used by the Contractor to minimize contamination by dust contaminated with PCBs 3.7 TEMPORARY STOCKPILE. The Contractor shall place all material excavated prior to Permanent Stockpile completion in the Temporary Stockpile area designated on the construction drawings. Side slopes of the Temporary Stockpile shall be no steeper than 2:3 (two feet of vertical rise to three feet of horizontal run). No special containment structures shall be required for this temporary construction. Engineer estimates required Temporary· Stockpile dimensions to be approximately ten feet in height and 55 feet in length and width at the base of the pile. Contractor is responsible for constructing the temporary stockpile in compliance with all applicable Federal, State, and local safety regulations and ordinances. 3.8 SILT FENCE. This work shall consist of furnishing and placing a geotextile for erosion control and for controlling offsite migration of PCB contaminated silt. The geotextile shall be manufactured and installed to allow passage of water while retaining soil without clogging. The quantities of silt control fencing as shown on the drawings may be increased or decreased at the direction of the Engineer based on construction procedures and actual site conditions that occur during construction of the project. Such variations in quantity will not be considered as alterations in the details of construction or a change in the character of the work. END OF SECTION 02050 02050-14 DRAFT I August 12, 1994 I I I I I I I I I I I I I I I I I I I SECTION 02202 EXCAVATION AND STOCKPILING PART 1 GENERAL 1.1 WORK INCLUDED. The work includes the excavation and the permanent stockpiling of approximately 8,500 cubic yards of PCB contaminated soil. The term "soil" shall be defined as in 40 CFR 761.123 to be ''all vegetation, soils and other ground media, including but not limited to, sand, grass, gravel and oyster shells. It does not include concrete and asphalt." Additional excavation and stockpiling may be required as determined by the Engineer. 1.2 REFERENCES. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. CODE OF FEDERAL REGULATIONS (CFR) 40 CFR 761 POLYCHLORINATED BIPHENYLS (PCBs) MANUFACTURING, PROCESSING, DISTRIBUTION IN COMMERCE, AND USE PROHIBITIONS. 1.3 SUBMITTALS. The Contractor's proposed procedures for accomplishing the excavation and stockpiling shall be submitted as part of the Job Plan for review and approval by the Engineer. The procedures shall provide for safe conduct of the work and protection of property which is to remain undisturbed. The procedures shall include a detailed description of the methods and equipment to be used for each operation and the sequence of operations for the entire project. PART 2 PRODUCTS (NOT APPLICABLE) PART 3 EXECUTION 3.1 GENERAL WORK REQUIREMENTS. A. The Contractor shall handle and stockpile the materials contaminated with PCBs in accordance with all applicable governmental laws, regulations, and orders which include, but are not limited to, the requirements of the Code of Federal Regulations -Title 40 -Protection of the Environment, Part 761 (40 CFR 761), and all regulations promulgated thereunder; and any State or local laws or regulations of a similar nature which apply in addition to or in lieu of the Federal requirements, if more extensive or more stringent. B. The Contractor shall take note that soil samples preyiously collected show the presence of PCBs at a concentration 02202-1 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I requ1r1ng remediation (greater than 1 ppm PCB). The areas and depths required for excavation have been designated and are shown on the construction drawings. The estimated quantity of soils requiring excavation is stated in the Contractor's proposal form. However, if sampling and analyses indicate that additional soils are contaminated, the Engineer will direct the Contractor in excavating the remaining PCB contaminated soils. Contractor shall be compensated for additional excavation and stockpiling work as specified in Section 1025. 3.2 REMOVAL OF DEBRIS AND RUBBLE. Debris and rubble shall be removed until the original ground surface elevation has been reached. IN accordance with the SPCC Plan and the Dust Control Plan, the Contractor shall take the necessary steps to prevent any spills or the creation of dust during the removal of debris and rubble. 3.3 EXCAVATION. The Contractor shall provide all the labor, equipment, and materials required to excavate the materials contaminated with PCBs. These materials shall include, but are not limited to, the existing inplace soils, solid material contained in drums of investigation derived waste, and other construction materials which are contaminated with PCBs as determined by the Engineer. The depth of initial excavation shall be as indicated on the construction drawings. Once the initial excavation has been completed, the Engineer will conduct onsite confirmation sampling and analyses. If the analyses indicate that further excavation is necessary, additional material shall be removed as directed by Engineer. The Engineer will then resample and re-analyze. Excavation shall be complete when laboratory verification sample results indicate that all the contaminated soil and material has been removed as determined by the Engineer. In accordance with the SPCC Plan and the Dust Control Plan, the Contractor shall take the necessary steps to prevent any spills or the creation of dust during excavation. 3.4 Quality Assurance Sampling. Following excavation to grades indicated on the drawings, Engineer will perform Quality Assurance Sampling. Quality Assurance analyses will consist of a combination of field confirmation screening analyses and laboratory verification analyses. Field Confirmation Screening Analyses will be conducted by EPA Draft Method 4020 (immunoassay technique). Laboratory Verification Analysis will be conducted by SW 846 method 8080 for PCBs. Should additional excavation become necessary, sampling and analyses will be performed at Engineers discretion to insure that all contaminated soils have been removed. Sampling locations will be based upon the sampling grid established during the RI and indicated on the drawings as grid centers. Four discrete subsamples will be collected,from soils surrounding the grid center locations indicated on the 02202-2 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I drawings. The four subsamples will be composited and analyzed by the specified field screening technique. Laboratory verification analyses will be performed on samples selected by the Engineer at the rate of 1 verification sample per 10 confirmation screening analysis. Laboratory verification analyses will be conducted only on samples demonstrating low or nondetectable PCB concentrations by field confirmation screening analyses. In the event of discrepancy between field confirmation screening results and laboratory verification results, the laboratory verification results shall govern. 3.5 STOCKPILING. The Contractor shall provide all the labor, equipment, and materials required to permanently stockpile materials contaminated with PCBs. The Contractor shall continuously stockpile contaminated material as it is excavated. Excavated soil which is removed prior to and during construction of the Permanent Stockpile shall be placed in the temporary Stockpile Area designated on the construction drawings. Upon completion of the Permanent Stockpile, soil shall be removed from the Temporary Stockpile Area and Placed in the Permanent Stockpile. Thereafter, all rema1n1ng and additional excavated soil shall be placed in the Permanent Stockpile as it is excavated. 3.6 REMOVAL AND ABANDONMENT OF TEMPORARY MONITORING WELLS. The Contractor may, at his discretion and as approved by the Engineer, remove and abandon unlocked temporary PVC monitoring wells during excavation activities. However, monitoring wells which are removed shall be abandoned in accordance with the following procedures. No payment shall be made for any work on an abandoned monitoring well. An abandoned monitoring well shall be backfilled and sealed with cement-bentonite or high solids bentonite grout as follows: The cement-bentonite grout slurry shall weigh between 11 to 13 pounds per gallon and consist of 95 percent (by dry weight) cement with 5 percent high-swelling bentonite mixed. with no more water than is required for proper placement. Cement shall conform to ASTM C 150, Type I. The grout shall be thoroughly mixed and shall be used before any stiffening occurs. The Contractor shall supply a balance to measure the weight of the grout .. The high solids bentonite grout shall be Baroid Drilling Fluids, Inc. Aqua-Grout Catalyst/Benseal or an acceptable equivalent approved by the Engineer. If a substitute grout is proposed by the Contractor, the name of the product and manufacturer's brochures shall be included with Attachment C for review and approval by the Engineer. The.high solids bentonite grout shall be mixed according to the 1 manufacturer's specifications. 02202-3 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I Grout shall be placed by the tremie method. The tremie method shall consist of pumping the slurry down the boring through a pipe. The bottom of the pipe shall be placed near the bottom of the zone to be grouted and shall be raised as the grout is placed, always keeping the bottom of the tremie pipe below the top of the grout. Pumps, piping, and other materials for mixing and pumping grout shall be provided by the Contractor. 3.7 BACKFILL. After completion of contaminated soil excavation and verification that all contaminated material has been removed, the excavated areas beside Middle Road designated on the drawings as OPA3 shall be backfilled. Contractor shall place backfill material to the necessary elevations to match initial grade. The Contractor shall certify to Engineer that the backfill used is clean soil which does not contain detectable concentrations of PCBs, as required by 40 CFR 761.125(c)(4)(v). To accomplish this, the Contractor shall provide to Engineer one original laboratory certified test result via SW 846 method 8080 before any backfill is placed and shall retest after placement of each 500 cubic yards of backfill. The Contractor shall also certify to Engineer that the backfill used is clean soil free of contaminants including but not limited to metaJs and organic compounds. To accomplish this, prior to any backfill being placed, the Contractor shall provide to Engineer laboratory certified test results by EPA methods 6010, 8240/8260, and 8270 for every 500 cubic yards of the backfill soil. Backfill material shall meet the Engineer's approval prior to placement. Engineer may at his discretion resample inplace backfill for consistency with the previously submitted analytical results for the above chemical requirements. If inplace backfill analysis is not consistent with previous results submitted by the Contractor as determined by the Engineer, Contractor shall remove unsatisfactory material, return it to place of origin, and replace with satisfactory backfill without additional cost to the Engineer. Backfill shall be spread in lifts that will not exceed 8 inches in thickness after compaction to 90% of maximum density at · optimum moisture content (±2 percent) as determined by ASTM D698. END OF SECTION 02202-4 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I PART 1 GENERAL SECTION 02203 DECONTAMINATION 1.1 WORK INCLUDED. The work includes construction of a decontamination station and decontamination of the following: • All vehicles and construction equipment • Hand tools • 100 !OW drums after emptied of contents • Three USTs after emptied of contents • One UST containing PCB contaminated product after emptied of contents Decontamination work shall also include management of the associated decontamination water; and other appurtenant work. 1.2 REFERENCES. CODE OF FEDERAL REGULATIONS (CFR) 40 CFR 761 Protection of the Environment 1.3 SUBMITTALS. The Contractor shall develop a Decontamination Plan which shall at a minimum include methods to be used for: • Construction of a decontamination station. • Maintenance and operation of the decontamination station. • Decontamination and quality assurance for vehicles, equipment, tools, USTs and drums. • Storage and treatment/disposal of decontamination water. The above list is not all inclusive. A copy of the Decontamination Plan shall be submitted to the Engineer for review concurrently with the Job Plan; review of the plan will not constitute approval or disapproval of the Decontamination Plan content. The Contractor shall be responsible for implementation of the Decontamination Plan. PART 2 EXECUTION 2.1 CONSTRUCTION OF DECONTAMINATION STATION. Prior to decontamination of equipment, the Contractor shall construct a decontamination station. The location shall be as specified on the construction drawings. The decontamination station shall be designed and constructed by the Contractor to collect all runoff .from items being decontaminated. The decontamination station design shall be developed 02203-1 DRAFT August 12, 1994 I I I I I I I I I I I I I I I I I I I by the Contractor and included with the Decontamination Plan for approval by the Engineer. Liquid or solid residue collected at the decontamination station shall be managed in accordance with all applicable regulations and as specified in Subsection 3.3 of this Section. Demolition and reconstruction of the decontamination station may be required between work sessions, during rainstorms or as directed by the Engineer. Solid or liquid residue remaining in the decontamination station shall be managed as discussed in Section 02050 and/or Subsection 3.3 of this Section. Upon completion of the work, demolition of the decontamination station shall. Plastic~sheeting and any solid or liquid residue remaining in the decontamination station shall be managed as discussed in Section 02050 and/or Subsection 3.3 of this Section. 2.2 DECONTAMINATION OF EQUIPMENT. The Contractor shall be responsible for performing decontamination of those items listed in Subsection 1.1 of this Section. The Contractor shall also be responsible for performing decontamination of items in addition to those listed in Subsection 1.1 of this Section at the request of Engineer. All items shall be decontaminated to such a degree that surface wipe samples shall detect PCB concentrations at less than 10 ~g/lOOcm2 • In addition, equipment used to collect or prepare samples shall be decontaminated to such a degree that PCB concentrations are below sample detection limits. The Contractor shall protect decontaminated items from recontamination while stored onsite. In addition, the Contractor shall be responsible for performing all decontamination of personnel, equipment, and other material that becomes contaminated as a result of site activities. Decontamination of Contractor equipment shall be in accordance with the requirements of 40 CFR 761.125(c)(4) and will be divided into three phases: initial decontamination; intermediate decontamination; and final decontamination. The initial decontamination shall be performed before mobilizing the equipment to the site. The Contractor shall thoroughly clean all equipment that will be brought on site and shall provide the Engineer with certifications of decontamination. Intermediate decontamination shall be performed in the following situations: when equipment is moved from a ''contaminated'' area to a "clean'' area, on trucks transporting materials offsite, or as directed by the Engineer. Engineer reserves the right to sample vehicles transporting materials offsite. Following intermediate decontamination, decontaminated equipment that touches the ground in a contaminated area will be considered contaminated and shall require additional intermediate decontamination before being used in a different area. A final decontamination of all Contractor equipment shall be performed by the Contractor before leaving the site. 02203-2 DRAFT I August 12, 1994 I I I I I I I I I I I I I I I I I I I Decontaminated Contractor equipment may be sampled for PCBs by the Engineer at any time at the Engineer's discretion. If Engineer samples any piece of equipment, that equipment shall not leave the site until Engineer has determined that it has been sufficiently decontaminated. Equipment shall remain in the support zone until Engineer completes analysis. If equipment is not sufficiently decontaminated, it shall be returned to the decontamination station for further decontamination. All decontamination water shall be managed as specified in Subsection 3.3 of this Section. 2.3 MANAGEMENT OF DECONTAMINATION WATER AND DECONTAMINATION SOLUTIONS. The Contractor shall collect, transport and dispose of the decontamination water and decontamination solutions in accordance with all applicable laws, regulations, and orders. The Contractor shall provide all drums, hoses, pumps, tank trucks and other equipment necessary to collect, transport and dispose of the decontamination water and decontamination solutions. 2.4 PERSONNEL DECONTAMINATION. The Contractor shall provide the necessary equipment and supplies for personnel decontamination. The Contractor personnel shall follow the decontamination procedures specified in the Contractor's Site Safety and Health Plan. The Contractor shall properly dispose of all PPE wastes in accordance with all applicable laws, regulations and orders. End of Section 02203-3 DRAFT I August 12, 1994