HomeMy WebLinkAbout78_N1027_INSP_20230124FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
Page 1 of 2
UNIT TYPE:
Lined
MSWLF LCID X YW Transfer Compost SLAS COUNTY: Robeson
Closed
MSWLF HHW White
goods Incin T&P FIRM PERMIT NO.: N1027
CDLF Tire T&P / Collection Tire Monofill Industrial Landfill DEMO SDTF FILE TYPE: COMPLIANCE
Date of Site Inspection: January 24, 2023 Date of Last Inspection: July 12, 2022
FACILITY NAME AND ADDRESS:
Parker and Sons
2816 Barlow Rd.
Parkton, NC 28371
GPS COORDINATES (decimal degrees): Lat.: 34.926527 Long: -79.050635
FACILITY CONTACT NAME AND PHONE NUMBER:
Name: Chris Parker – Operator and Owners Son
Telephone: 910-850-3437 or Daniel Parker 910-988-6506
Email address: a1lotclearing@aol.com
FACILITY CONTACT ADDRESS:
Parker and Sons
2816 Barlow Rd.
Parkton, NC 28371
PARTICIPANTS:
Dwayne Parker, Parker and Sons
Chris Parker
Jason Watkins, SWS
STATUS OF PERMIT:
N1027 – Notification originally 2009
PURPOSE OF SITE VISIT:
Partial Inspection – Follow Up
STATUS OF PAST NOTED VIOLATIONS:
Previously noted violations of 15A NCAC 13B .0566 (2 &3) have been fully resolved
OBSERVED VIOLATIONS: N/A
The item(s) listed above were observed by Section staff and require action on behalf of the facility in order to come into or maintain compliance
with the Statutes, Rules, and/or other regulatory requirements applicable to this facility. Be advised that pursuant to N.C.G.S. 130A-22, an
administrative penalty of up to $15,000 per day may be assessed for each violation of the Solid Waste Laws, Regulations, Conditions of a Permit,
or Order under Article 9 of Chapter 130A of the N.C. General Statutes. Further, the facility and/or all responsible parties may also be subject to
enforcement actions including penalties, injunction from operation of a solid waste management facility or a solid waste collection service and any
such further relief as may be necessary to achieve compliance with the North Carolina Solid Waste Management Act and Rules.
FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
Page 2 of 2
ADDITIONAL COMMENTS
1. The purpose of this visit was to follow up on the completion of corrective actions noted from the July 12, 2022
inspection and the on-site meeting on September 27, 2022, between representatives of Parker & Sons and the
Solid Waste Section.
2. On November 15, the Section was provided with a recombination plat filed with the Robeson County Register of
Deeds (Map Book 60, Page 200) showing a property exchange to provide the minimum 100-ft buffer around the
landfill. Additionally, the recorded plat showed the landfill to be 1.95 acres in size.
3. A plan of action was also submitted for work to be completed by the end of December 2022 to address other on-
site corrective actions. These actions included removal of waste from an area to the northeast of the landfill and
disposal in the landfill footprint, re-establishment of the permanent edge of waste markers per the new plat, and
regrading of the landfill side slopes.
4. Based on observations during the inspection, all the items in #3 above and the previous inspection reports have
now been completed and are fully resolved.
5. As noted in item #2 above and the revised survey plat, there is a .05 acre sliver in the NE corner of the landfill
that remains available to fill as well as continued vertical expansion on top of the existing area. As discussed on
site, permanent groundcover in the form of a grass species that can be mowed and/or otherwise maintained should
be established on all remaining 3 sides of the landfill below the current fill line, and subsequently once the .05
acre area has been brought up to current landfill elevation.
6. As has been previously conveyed, the current notified LCID landfill must cease operating no later than January
1, 2026 or be covered by a solid waste permit due to changes in the applicable rules effective January 2021.
Closure of the landfill must be completed in accordance with 15A NCAC 13B .0567(1). Should the facility
choose to expand the horizontal footprint of the landfill as was discussed on-site, a full permit application should
be submitted to the Section no later than January 2025 to allow processing prior to the rule required closure date.
Please contact me if you have any questions or concerns regarding this inspection report.
________________________________________ Phone: 336-776-9674 _
Jason M. Watkins
Field Operations Branch Head
Sent on: 2/8/2023 X Email Hand delivery US Mail Certified No. [ _]
Copies: David Powell, Environmental Sr. Specialist – Solid Waste Section
Andrew Hammonds, Eastern District Supervisor - Solid Waste Section
Chris Hollinger, Compliance Officer – Solid Waste Section