Loading...
HomeMy WebLinkAbout5901_INSP_20230131 (1)FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 1 of 5 UNIT TYPE: Lined MSWLF LCID YW Transfer Compost SLAS COUNTY: Martin Closed MSWLF HHW White goods Incin T&P FIRM PERMIT NO.: 5901-CDLF-1995 CDLF X Tire T&P / Collection Tire Monofill Industrial Landfill DEMO SDTF FILE TYPE: COMPLIANCE Date of Site Inspection: January 31, 2023 Date of Last Inspection: August 25, 2022 FACILITY NAME AND ADDRESS: Martin County C&DLF 1445 Landfill Rd. Williamston, North Carolina 27892 GPS COORDINATES: N: 35 °86476 E: - 77 °09524 FACILITY CONTACT NAME AND PHONE NUMBER: Name: Justin Harrison – Solid Waste Director Telephone: 252-792-1240, office & 252-799-6552, cell Email Address: jharrison@martincountyncgov.com FACILITY CONTACT ADDRESS: Justin Harrison P.O. Box 668 Williamston, North Carolina, 27892 PARTICIPANTS: Justin Harrison, Solid Waste Director Ben Hardison, Landfill Supervisor John College, NCDEQ-DWM-SWS-FOB STATUS OF PERMIT: Active, PTO/PTC,Life of Site Permit. Issued April 12, 2018. PURPOSE OF SITE VISIT: Pre-Operations Inspection for Fill Sequence 2. STATUS OF PAST NOTED VIOLATIONS: None OBSERVED VIOLATIONS: None The item(s) listed above were observed by Section staff and require action on behalf of the facility in order to come into or maintain compliance with the Statutes, Rules, and/or other regulatory requirements applicable to this facility. Be advised that pursuant to N.C.G.S. 130A-22, an administrative penalty of up to $15,000 per day may be assessed for each violation of the Solid Waste Laws, Regulations, Conditions of a Permit, or Order under Article 9 of Chapter 130A of the N.C. General Statutes. Further, the facility and/or all responsible parties may also be subject to enforcement actions including penalties, injunction from operation of a solid waste management facility or a solid waste collection service and any such further relief as may be necessary to achieve compliance with the North Carolina Solid Waste Management Act and Rules. FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 2 of 5 ADDITIONAL COMMENTS: 01 - This site visit was conducted as a Pre-Operation’s Inspection to ensure the Vertical Expansion of Fill Sequence 2 meets the requirements of the Permit To Construct (PTC) as is written in the current Permit To Operate (PTO) dated April 12, 2018. New PTO will be issued upon this inspection. 02 -This permit approves construction of the 0.5-acre expansion area at the southeast corner of the landfill unit (also referred to as fill sequence 2). 03 -The required groundwater (GW) well has been installed and was locked and tagged as required. Christine Ritter (NCDEQ-DWM-SWS-Environmental Engineer) has approved the use of this well for GW comparison sampling. FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 3 of 5 04 - The Permanent Edge of Waste Markers have been installed for this expansion. 05 - The Berm outside of the Edge of Waste was put to a test. Approximately, a 1.0 inch rain event occurred the day/night before this inspection. 06 - No major erosion was noted on the berm. The top right corner of the above picture shows water ponded. The berm is higher than the water level. 07 - All water MUST be removed before any waste is placed into this expansion area. 08 - There has been a tile put into the surface water drainage ditch with a crushed inert debris road going to the new expansion of this site. FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 4 of 5 09 - Small samplings need to be removed from side slope in the background of the picture above. 10 - Facility has ALL required signage. Please contact me if you have any questions or concerns regarding this inspection report. _______________________________________ Phone: 919-268-1524 _ Email: john.college@ncdenr.gov Environmental Senior Specialist Regional Representative Sent on: February 6, 2023 X Email Hand delivery US Mail Certified No. [ _] Copies; * Andrew Hammonds, DWM Eastern District Supervisor, Solid Waste Section * Claire Osborn, DWM Environmental Engineer, Permitting Branch, Solid Waste Section * Christine Ritter, DWM Hydrogeologist, Environmental Compliance Branch, Solid Waste Section FACILITY COMPLIANCE INSPECTION REPORT Division of Waste Management Solid Waste Section Page 5 of 5