Loading...
HomeMy WebLinkAbout25009_East Side Truck Svc_EMP_20220324NORTH CAROLINA BROWNFIELDS PROGRAM ENVIRONMENTAL MANAGEMENT PLAN This form is to be used to prepare an Environmental Management Plan (EMP) for projects in the North Carolina Brownfields Program at the direction of a Brownfields project manager. The EMP is a typical requirement of a Brownfields Agreement (BFA). Its purpose is to clarify actions to be taken during the demolition and construction at Brownfields properties in an effort to avoid delays in the event of the discovery of new contamination sources or other environmental conditions. The EMP provides a means to document redevelopment plans and environmental data for each applicable environmental medium to inform regulatory -compliant decision -making at the site. As much detail as possible should be included in the EMP, including contingency planning for unknowns. Consult your project manager if you have questions. Prospective Developers and/or their consultants must complete and submit this form and all pertinent attachments, see checklist below, to their Brownfields project manager prior to any earthmoving or other development -related activities that have the potential to disturb soil at the Brownfields Property, including demolition. For the resultant EMP to be valid for use, it must be completed, reviewed by the program, signed by all parties working on the project, and approved by the Brownfields project manager. Failure to comply with the requirements of the EMP could jeopardize project eligibility, or in the event of a completed agreement, be cause for a reopener So that the EMP provides value in protecting brownfields eligibility and public health, the preparer shall ensure that the following steps have been completed prior to submitting the EMP for review. Any EMP prepared without completing these steps is premature. ® Site sampling and assessment that meets Brownfields' objectives is complete and has been reviewed and approved by the Brownfields Project Manager. ® Specific redevelopment plans, even if conceptual, have been developed for the project, submitted and reviewed by the Brownfields Project Manager. EMP Version 2, June 2018 Please submit, along with the completed EMP form, the following attachments, as relevant and applicable to the proposed redevelopment: © A set of redevelopment plans, including architectural/engineering plans, if available; if not conceptual plans may suffice if updated when detailed plans are drafted. ® A figure overlaying redevelopment plans on a map of the extent of contamination for each media. ® Site grading plans that include a cut and fill analysis. ❑ A figure showing the proposed location and depth of impacted soil that would remain on site after construction grading. ❑ Any necessary permits for redevelopment (i.e. demolition, etc.). ® A detailed construction schedule that includes timing and phases of construction. ® Tabulated data summaries for each impacted media (i.e. soil, groundwater, soil gas, etc.) applicable to the proposed redevelopment. ® Figures with the sampling locations and contamination extents for each impacted media applicable to the proposed redevelopment. ® A full final grade sampling and analysis plan, if the redevelopment plan is final. ❑ If known, information about each proposed potential borrow soil source, such as aerial photos, historic site maps, historic Sanborn maps, a site history, necessary for brownfields approval. ❑ Information and, analytical data if required, for quarries, or other borrow sources, detailing the type of material proposed for importation to the Brownfields Property. ® A work plan for the sampling and analysis of soil to be brought onto the Brownfields Property. Refer to Issue Resolution 15 in Brownfields Program Guidelines. ❑ A map of the Brownfields Property showing the location of soils proposed for export and sampling data from those areas. ❑ If a Vapor Mitigation System is required by the Brownfields Program, the Vapor Intrusion Mitigation System (VIMS) plan will be signed and sealed by a NC Professional Engineer. The VIMS Plan may also be submitted under separate cover. EMP Version 2, June 2018 Date:2/14/2022 GENERAL INFORMATION Revision Date (if applicable): 3/18/2022 Brownfields Assigned Project Name: East Side Trucking Service Brownfields Project Number: 25009-21-026 Brownfields Property Address: 520 Judson Church Road, Fayetteville NC Brownfields Property Area (acres): 3.39 Is Brownfields Property Subject to RCRA Permit? ....................... ❑ Yes © No If yes enter Permit No.: Click or tap here to enter text. Is Brownfields Property Subject to a Solid Waste Permit ............ ❑ Yes © No If yes, enter Permit No.: Click or tap here to enter text. COMMUNICATIONS A copy of this EMP shall be distributed to all the parties below as well as any contractors or site workers that may be exposed to site vapors, soil, groundwater, and/or surface water. Additionally, a copy of the EMP shall be maintained at the Brownfields Property during redevelopment activities. NOTE, THE EMP DOES NOT TAKE THE PLACE OF A SITE -SPECIFIC HEALTH AND SAFETY PLAN. Prospective Developer (PD): Naman Judson LLC. Contact Person: Nick Patel Phone Numbers: Office: 843-669-0855 Mobile: 917-379-6770 Email: nick@namanhotels.com Contractor for PD: MB Kahn Construction Contact Person: Chester Grider Phone Numbers: Office: 803 227-5251 Mobile: 803 608-6667 Email: cgrider@mbkahn.com Environmental Consultant: Atlantic Shores Environmental Services, Ltd. Contact Person: Cheryl Moody Phone Numbers: Office: 910-371-5980 Email: cmoody@atlanticshoresenv.com Brownfields Program Project Manager: Stephanie Graham Phone Numbers: Office: 704-235-2195 Email: stephanie.graham@ncdenr.gov Mobile: 910-512-5321 Mobile: Click or tap here to enter text. Other DEQ Program Contacts (if applicable, i.e., UST Section, Inactive Hazardous Site Branch, EMP Version 2, June 2018 Hazardous Waste, Solid Waste): _ncK or iap nere io enter text. NOTIFICATIONS TO THE BROWNFIELDS PROGRAM Written advance Notification Times to Brownfields Project Manager: Check each box to accept minimum advance notice periods (in calendar days) for each type of onsitetask: On -site assessment or remedial activities: .................................................... 10 days Prior Construction or grading start: .......................................................................... 10 days Prior Discovery of stained soil, odors, USTs, buried drums or waste, landfill, or other signs of previously unknown contamination: ................................................................................ Within 48 hours Implementation of emergency actions (e.g. dewatering, flood or soil erosion control measures in area of contamination, ventilation of work zones): ................................... Within 48 hours Installation of mitigation systems: ................................................................ 10 days Prior Other notifications as required by local, state or federal agencies toimplement redevelopment activities:(asapplicable):................................................................................. Within 30 days REDEVELOPMENT PLANS 1) Type of Redevelopment (check all that apply): ❑Residential ❑Recreational ❑Institutional ©Commercial ❑Office ❑Retail ❑ Industrial © Other specify: Hotel 2) Check the following activities that will be conducted prior to commencing earth -moving activities at the site: © Review of historic maps (Sanborn Maps, facility maps) ❑ Conducting geophysical surveys to evaluate the location of suspect UST, fuel lines, utility lines, etc. ❑ Interviews with employees/former employees/facility managers/neighbors 3) Summary of Redevelopment Plans (MANDATORY: attach detailed plans or conceptual plans, if detailed plans are not available. EMP review without such information would be premature): Provide brief summary of redevelopment plans, including demolition, removal of building slabs/pavement, grading plans and planned construction of new structures: The site is being redeveloped into Springhill Suites Hotel. The hotel will encompass 64,733 square- EMP Version 2, June 2018 feet and stand approximately 65 feet tall. The hotel will consist of 119 rooms and 126 parking paved spaces. A storm water detention pond will be constructed to manage storm water from the site. There are currently no structures on the site with the exception of a slab foundation and a potable well. The slab will be removed and the well will be abandoned by a North Carolina certified well driller when the on -site monitoring wells are being abandoned. 4) Do plans include demolition of structures)?: ® Yes ❑ No ❑ Unknown ® If yes, please check here to confirm that demolition will be conducted in accordance with applicable legal requirements, including without limitation those related to lead and asbestos abatement that are administered by the Health Hazards Control Unit within the Division of Public Health of the North Carolina Department of Health and Human Services. If available, please provide a copy of your demolition permit. 5) Are sediment and erosion control measures required by federal, state, or local regulations? ® Yes ❑ No ❑ Unknown ® If yes, please check here to confirm that demolition will be conducted in accordance with applicable legal requirements. If soil disturbance is necessary to install sediment and erosion control measures, they may not begin until this EMP is approved. 6) Which category of risk -based screening level is used or is anticipated to be specified in the Brownfields Agreement? Note: If children frequent the property, residential screening levels shall be cited in the Brownfields Agreement for comparison purposes. ❑ Residential ® Non -Residential or Industrial/Commercial 7) Schedule for Redevelopment (attach construction schedule): a) Construction start date: 4/1/2022 b) Anticipated duration (specify activities during each phase): 18 months c) Additional phases planned? ❑ Yes ❑ No If yes, specify the start date and/or activities if known: Start Date: NA Planned Activity: • No phases are planned. Cannot electronically check "No" in the document See attached construction schedule Start Date: Click or tap to enter a date. Planned Activity: 5 EMP Version 2, June 2018 Click or tap here to enter text. Start Date: Click or tap to enter a date. Planned Activity: Click or tan harp 4 mot d) Provide the planned date of occupancy for new buildings: 4/1/2023 CONTAMINATED MEDIA 1) Contaminated Media on the Brownfields Property Part 1. Soil: .............................................................. © Yes ❑ No ❑ Suspected Part 2. Groundwater: ............................................ © Yes ❑ No ❑ Suspected Part 3. Surface Water: .......................................... ❑ Yes © No ❑ Suspected Part 4. Sediment: ................................................... ❑ Yes © No ❑ Suspected Part 5. Soil Vapor: .................................................. © Yes ❑ No ❑ Suspected Part 6. Sub -Slab Soil Vapor: .................................. ❑ Yes ❑ No ❑ Suspected Part 7. Indoor Air: ................................................... ❑ Yes ❑ No ❑ Suspected 2) For the Area of Proposed Redevelopment on the Brownfields Property, attach tabulated data summaries for each impacted media and figure(s) with sample locations. PART 1. Soil — Please fill out the information below, using detailed site plans, if available, or estimate using known areas of contaminated soil and a conceptual redevelopment plan. Provide a figure overlaying new construction onto figure showing contaminated soil and groundwater locations. 1) Known or suspected contaminants in soil (list general groups of contaminants): ASE data - VOCs and metals - Toluene, Total xylene, m&p xylene, chloromethane, arsenic and hexavalent chromium. WithersRavenel data - Chromium, Lead, PCE, C9-C22 Aromatics 2) Depth of known or suspected contaminants (feet): 1.5 — 4 feet below ground level 10 feet for Chloromethane 3) Area of soil disturbed by redevelopment (square feet): Entire site 4) Depths of soil to be excavated (feet): 6 EMP Version 2, June 2018 0-5.2 feet (storm water pond is deepest excavation) 5) Estimated volume of soil (cubic yards) to be excavated (attach grading plan): 2,461— to be reused on site under impervious areas. This soil will be used under the parking lot and not in the footprint of the building. 6) Estimated volume of excavated soil (cubic yards) anticipated to be impacted by contaminants: 2,461 7) Estimated volume of contaminated soil expected to be disposed of offsite, if applicable: No export is anticipated Part 1.A. MANAGING ONSITE SOIL If soil is anticipated to be excavated from the Brownfield Property, relocated on the Brownfields Property, or otherwise disturbed during site grading or other redevelopment activities, please provide a grading plan that clearly illustrates areas of cut and fill (approximate areas & volumes are acceptable, if only preliminarydata available). 1) HAZARDOUS WASTE DETERMINATION: a) Does the soil contain a LISTED WASTE as defined in the North Carolina Hazardous Waste Section under 40 CFR Part 261.31-261.35?....................................... HYes ❑ No H If yes, explain why below, including the level of knowledge regarding processes generating the waste (include pertinent analytical results as needed). Historic data indicates that a release occurred from or in the vicinity of a former on -site AST. Brake cleaner or other chlorinated cleaners were used on site. Tetrachloroethylene has been identified in both soil and groundwater at this location. Groundwater impacts have been identified at a distance from the source. According to a September 2020 WithersRavenel report approximately 18.5 tons of impacted soil was removed from the source area. Groundwater flow from this area is away from the proposed hotel and contaminated groundwater is located approximately 85 feet west of the proposed hotel. H If yes, do the soils exceed the "Contained -Out" levels in Attachment 1 of the North Carolina Contained -In Policy? ................................................. ❑ Yes H No b) NOTE: IF SOIL MEETS THE DEFINITION OF A LISTED HAZARDOUS WASTE AND EXCEEDS THE CONTAINED -OUT LEVELS IN ATTACHMENT 1 TO THE NORTH CAROLINA CONTAINED -IN POLICYTHE SOIL MAY NOT BE RE -USED ON SITE AND MUST BE DISPOSED OF IN ACCORDANCE WITH DEQ HAZARDOUS WASTE SECTION RULES AND REGULATIONS. c) Does the soil contain a CHARACTERISTIC WASTE? .................................... ❑ Yes H No ❑ If yes, mark reason(s) why below (and include pertinent analytical results). ❑ Ignitability Click or tap here to enter text. 7 EMP Version 2, June 2018 ❑ Corrosivity Click or tap here to enter text. ❑ Reactivity Click or tap here to enter text. ❑ Toxicity Click or tap here to enter text. ❑ TCLP results "lick or tap here to enter text. ❑ Rule of 20 results (20 times total analytical results for an individual hazardous constituent on TCLP list cannot, by test method, exceed regulatory TCLP standard) LAICK or tap nere to enter text. © If no, explain rationale: Levels identified on the site are relatively low and would not be classified as a hazardous waste. d) NOTE: IF SOIL MEETS THE DEFINITION OF A CHARACTERISTIC HAZARDOUS WASTE, THE SOIL MAYNOT BE RE -USED ON SITE AND MUST BE DISPOSED OF IN ACCORDANCE WITH DEQ HAZARDOUS WASTE SECTION RULES AND REGULATIONS. 2) Screening criteria by which soil disposition decisions will be made (e.g., left in place, capped in place with low permeability barrier, removed to onsite location and capped, removed offsite): ❑ Preliminary Health -Based Residential SRGs © Preliminary Health -Based Industrial/Commercial SRGs © Division of Waste Management Risk Calculator (For Brownfields Properties Only) ❑ Site -specific risk -based cleanup level. Please provide details of methods used for determination/explanation. '< or tap here to enter text. Additional comments: -.. �_._ I-_.._ _tor tout 3) If known impacted soil is proposed to be reused within the Brownfields Property Boundary, please check the measures that will be utilized to ensure safe placement and documentation of same. Please attach a proposed location diagram/site map. © Provide documentation of analytical report(s) to Brownfields Project Manager © Provide documentation of final location, thickness and depth of relocated soil on site map to Brownfields Project Manager once known ❑ Geotextile to mark depth of fill material. Provide description of material: uIcK or tap nere to enter teh ❑ Manage soil under impervious cap ❑ or clean fill ❑ 8 EMP Version 2, June 2018 ® Describe cap or fill: The site soils will be capped by buildings, hardscape or six inches of clean fill. ❑ Confer with NC BF Project Manager if Brownfield Plat must be revised (or re -recorded if actions are Post -Recordation). ❑ GPS the location and provide site map with final location. ❑ Other. Please provide a description of the measure: 4) Please describe the following action(s) to betaken during and following excavation and management of site soils: Management of fugitive dust from site ® Yes, describe the method will include: If visible emissions or dust are observed, spray water mist will be employed to reduce emissions ❑ No, explain rationale: Field Screening of site soil ® Yes, describe the field screening method, frequency of field screening, person conducting field screening: If visual or olfactory indications of impacts are identified during redevelopment activities, field screening for volatile organic compounds will be conducted continuously in the impact area during earth moving activities. ❑ No, explain rationale: Soil Sample Collection ® Yes, describe the sampling method (e.g., in -situ grab, composite, stockpile, etc.): If undocumented impacts are identified during the grading or other earth moving activities, the removed impacted material will be stockpiled on site until characterization of the material can occur. The pile will be constructed per the attached figure. At least one composite sample will be collected from the pile. The sample numbers will be based on the size of the pile and will be determined in coordination with the Brownfield Project Manager. Composite samples will be analyzed for SVOCs, RCRA 8 metals, and hexavalent chromium. A grab sample will be collected for VOC analysis. If the soils are not considered hazardous by the rule of 20, the soil may be reused on site under the parking lot pavement cap. The known impacted soil under the existing slab will be excavated, along with impacted EMP Version 2, June 2018 material that may be identified during grading activities. Confirmatory soil samples will be collected from the base and sidewalls of any impacted soil excavation at the site. ❑ No, explain rationale: If soil samples are collected for analysis, please check the applicable chemical analytes: © Volatile organic compounds (VOCs) by EPA Method 8260 ® Semi -volatile organic compounds (SVOCs) by EPA Method 8270 ® Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): Method 6020/7471 ❑ Pesticides: Specify Analytical Method Number(s): Click or tap here ❑ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text ® Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Specify Analytical Method Number(s): Cr VI by EPA Method 7199 © Check to confirm that stockpiling of known or suspected impacted soils will be conducted in accordance with Figure 1 of this EMP. Stockpile methodology should provide erosion control, prohibiting contact between surface water/precipitation and contaminated soil, and preventing contaminated runoff. Explain any variances or provide additional details as needed: -lick or tap here to enter text. © Final grade sampling of exposed native soil (i.e., soil that will not be under buildings or permanent hardscape). Select chemical analyses for final grade samples with check boxes below (Check all thatapply): © Volatile organic compounds (VOCs) by EPA Method 8260 ® Semi -volatile organic compounds (SVOCs) by EPA Method 8270 © Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): Method 6020/7471. ❑ Pesticides: Specify Analytical Method Number(s): 10 EMP Version 2, June 2018 Click or tap here to enter tee. ❑ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text © Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Cr VI by EPA Method 7199 Please provide a scope of work for final grade sampling, including a diagram of soil sampling locations, number of samples to be collected, and brief sampling methodology. Samples should be collected from 0-2 ft below ground surface, with the exception of VOCs which should be taken from 1-2 ft below ground surface. Alternatively, a work plan for final grade sampling may be submitted under separate cover. The final grade soil sampling locations have been illustrated on the attached figure. The discrete samples will be collected from 1-2 feet below grade prior to placement of amendments for topsoil or installation of sod. The samples will be collected using a decontaminated hand auger and placed in laboratory supplied containers. The samples will immediately be placed on ice. The samples will be analyzed for VOC, SVCS and RCRA 8 metals including hex chrome. ❑ If final grade sampling was NOT selected please explain rationale: Part 1.B. IMPORTED FILL SOIL NO SOIL MAY BE BROUGHT ONTO THE BROWNFIELDS PROPERTY WITHOUT PRIOR APPROVAL FROM THE BROWNFIELDS PROGRAM. According to the Brownfields IR 15, "Documenting imported soil (by sampling, analysis, and reporting in accordance with review and written approval in advance by the Brownfields Program), will safeguard the liability protections provided by the brownfields agreement and is in the best interest of the prospective developer/property owner." Requirements for importing fill: 1) Will fill soil be imported to the site? ................................................ © Yes ❑ No ❑ Unknown 2) If yes, what is the estimated volume of fill soil to be imported? 1,741 cubic yards 3) If yes, what is the anticipated depth that fill soil will be placed at the property? (If a range of depths, please list the range.) 0-5 feet 4) Provide the source of fill, including: location, site history, nearby environmental concerns, 11 EMP Version 2, June 2018 etc. Attach aerial photos, maps, historic Sanborn maps and a borrow source site history: The source of the fill is to be determined but will come from a North Carolina permitted quarry, from virgin material. If the quarry is not a Brownfield approved quarry, soil sampling of the material will be conducted and DEQ approval will be obtained prior to import. Amendments for the topsoil will come from a composting location that does not accept yard waste. Soil sampling of the material will be conducted and DEQ approval will be obtained prior to import. The material will come from a location that does not accept yard waste. 5) PRIOR TO ITS PLACEMENT AT THE BROWNFIELDS PROPERTY, provide a plan to analyze fill soil to demonstrate that it meets acceptable standards applicable to the site and can be approved for use atthe Brownfields property. Sample(s) will be collected from the borrow pit prior to import fill. Amendment sample(s) will be collected from the facility immediately prior to import of the material. If not virgin material from a pre -approved quarry, sampling shall be representative of the material to be imported to the BF property at a ratio within a range of 1:500 cy to 1:1000 cy 6) Please check the applicable chemical analytes for fill soil samples. (Check all that apply): © Volatile organic compounds (VOCs) by EPA Method 8260 ® Semi -volatile organic compounds (SVOCs) by EPA Method 8270 ® Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver): Specify Analytical Method Number(s): Method 6020/7471 ® Pesticides: Specify Analytical Method Number(s): Pesticides and herbicides (8141, 8082B and 8151) will be analyzed on the soil amendments only. ❑ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text © Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.): Hexavalent Chromium Method 7199 7) The scope of work for import fill sampling may be provided below or in a Work Plan submitted separately for DEQ review and approval. Attach specific location maps for in -situ borrow sites. If using a quarry, provide information on the type of material to be brought onto the Brownfields Property. The import location for this project are to be determined. However, at least one composite and one discrete soil sample will be collected from the import locations. The numbers of samples will follow the frequency identified in No.s 4 and 5 above. The composite samples will be analyzed for SVOCs and metals (Amendment will include herbicides and pesticides). The discrete sample will be analyzed for VOCs. 12 EMP Version 2, June 2018 Part I.C. EXPORTED SOIL NO SOIL MAY LEAVE THE BROWNFIELDS PROPERTY WITHOUT APPROVAL FROM THE BROWNFIELDS PROGRAM. FAILURE TO OBTAIN APPROVAL MAY VIOLATE A BROWNFIELDS AGREEMENT CAUSING A REOPENER OR JEOPARDIZING ELIGIBILITY IN THE PROGRAM, ENDANGERING LIABILITY PROTECTIONS AND MAKING SAID ACTION POSSIBLY SUBJECT TO ENFORCEMENT. JUSTIFICATIONS PROVIDED BELOW MUST BE APPROVED BY THE PROGRAM IN WRITING PRIOR TO COMPLETING TRANSPORT ACTIVITIES. Please refer to Brownfields IR 15 for additional details. 1) If export from a Brownfields Property is anticipated, please provide details regarding the proposed export actions. Volume of exported soil, depths, location from which soil will be excavated on site, related sampling results, etc. Provide a site map with locations of export and sampling results included. Export is not anticipated for this project. However, the following has been included in the event export is required. . 2) To what type of facility will the export Brownfields soil be sent? © Subtitle D/Municipal Solid Waste Landfill (analytical program to be determined by landfill) ❑ Permitted but Unlined Landfill (i.e. LCID, C&D, etc.) Analytical program to be determined by the accepting Landfill; ❑ Landfarm or other treatment facility ❑ Use as fill at another suitable Brownfields Property — determination that a site is suitable will require, at a minimum, that similar concentrations of the same or similar contaminants already exist at both sites, use of impacted soil will not increase the potential for risk to human health and the environment at the receiving Brownfields property, and thata record of the acceptance of such soil from the property owner of the receiving site is provided to Brownfields. Please provide additional details below. ❑ Use as Beneficial Fill off -site at a non-Brownfields Property - Please provide documentation of approval from the property owner for receipt of fill material. This will also require approval by the DEQ Solid Waste Section. Additional information is provided in IR 15. Please provide additional details below. 3) Additional Details: (if transfer of soil to another property is requested above, please provide details related to the proposed plans). Click or tap here to ent , I ­ Part 1.D. MANAGEMENT OF UTILITY TRENCHES ❑ Install liner between native impacted soils and base of utility trench before filling with clean fill 13 EMP Version 2, June 2018 (Preferred) © Last out, first in principle for impacted soils (if soil can safely be reused onsite and is not hazardous waste), i.e., impacted soils are placed back at approximately the depths they were removed from such that impacted soil is not placed at a greater depth than the original depth from which it was excavated. © Evaluate whether necessary to install barriers in conduits to prevent soil vapor transport, and/or degradation of conduit materials due to direct impact with contaminants? © If yes, provide specifications on barrier materials: A barrier will be installed in the stormwater conduits east of catch basin DI-(B3) to prevent vapor transport toward the structure. A preliminary drawing of the structure has been attached to the EMP. An engineered drawing is currently being designed and will be forwarded to Brownfield group once it is completed. The barrier will not be installed until DEQ has approved the engineering control. ❑ If no, include rationale here: DICK or tap nere to enter tex. Other comments regarding managing impacted soil in utility trenches: Click or tap here to enter teY` PART 2. GROUNDWATER — Please fill out the information below. 1) What is the depth to groundwater at the Brownfields Property? Estimated to be 9.85' —11.8' feet below grade 2) Is groundwater known to be contaminated by ®onsite ❑offsite El both or El unknown sources? Describe source(s): The past uses of the former East Side Trucking have resulted in tetrachloroethene plume that has been identified above 2L standards by WitherRavenel. Lab data collected under the DEQ approved work plan Phase II conducted by ASE shows no additional impacts of TCE. 3) What is the direction of groundwater flow at the Brownfields Property? Groundwater flow on the site is to the west, southwest . A groundwater potentiometric map has been completed by ASE and is included in the DWQ approved work plan Phase II ESA. 4) Will groundwater likely be encountered during planned redevelopment activities? ❑Yes ©No If yes, describe these activities: The deepest excavation at the site is planned to be 5.2 feet which is just under two feet above the observed water table at the site Regardless of the answer; in the event that contaminated groundwater is encountered 14 EMP Version 2, June 2018 during redevelopment activities (even if no is checked above), list activities for contingent management of groundwater (e.g., dewateringof groundwater from excavations or foundations, containerizing, offsite disposal, discharge to sanitary sewer, NPDES permit, or sampling procedures). If groundwater is encountered during site operations, it will be determined if dewatering activities are necessary. If dewatering is necessary, the groundwater will observe for visual or olfactory evidence of contamination. If impacts are identified and dewatering is required, the water will be containerized and disposed of offsite. 5) Are monitoring wells currently present on the Brownfields Property? ................. ❑X Yes ❑ No If yes, are any monitoring wells routinely monitored through DEQ or other agencies?.................................................................................................................. ❑Yes ©No 6) Please check methods to be utilized in the management of known and previously unidentified wells. © Abandonment of site monitoring wells in accordance with all applicable regulations. It is the Brownfields Program's intent to allow proper abandonment of well(s) as specified in the Brownfields Agreement, except if required for active monitoring through another section of DEQ or the EPA. ❑ Location of existing monitoring wells marked ❑ Existing monitoring wells protected from disturbance ❑ Newly identified monitoring wells will be marked and protected from further disturbance until notification to DEQ Brownfields can be made and approval for abandonment is given. 7) Please provide additional details as needed: Please note, disturbance of existing site monitoring wells without approval by DEQ is not permissible. If monitoring wells are damaged and/or destroyed, DEQ may require that the PD be responsible for replacement of the well. PART 3. SURFACE WATER -Please fill out the information below. 1) Is surface water present at the property? ❑ Yes © No 2) Attach a map showing the location of surface water at the Brownfields Property. 3) Is surface water at the property known to be contaminated? ❑ Yes © No 4) Will workers or the public be in contact with surface water during planned redevelopment activities? ❑ Yes © No 5) In the event that contaminated surface water is encountered during redevelopment activities, or clean surface water enters open excavations, list activities for management of 15 EMP Version 2, June 2018 such events (e.g. flooding, contaminated surface water run-off, stormwater impacts): Stormwater that enters open excavation will be allowed to infiltrate into the site. PART 4. SEDIMENT — Please fill out the information below. 1) Are sediment sources present on the property? ❑ Yes © No 2) If yes, is sediment at the property known to be contaminated: ❑ Yes ❑ No 3) Will workers or the public be in contact with sediment during planned redevelopment activities? ❑ Yes © No 4) Attach a map showing location of known contaminated sediment at the property. 5) In the event that contaminated sediment is encountered during redevelopment activities, list activities for management of such events (stream bed disturbance): NA PART 5. SOIL VAPOR — Please fill out the information below. 1) Do concentrations of volatile organic compounds at the Brownfields property exceed the following vapor intrusion screening levels (current version) in the following media: IHSB Residential Screening Levels: Soil Vapor:...........© Yes ❑ No ❑ Unknown Groundwater:.....© Yes ❑ No ❑ Unknown IHSB Industrial/Commercial Screening Levels: Soil Vapor: ........... ❑ Yes © No ❑ Unknown Groundwater: ..... ❑ Yes © No ❑ Unknown 2) Attach a map showing the locations of soil vapor contaminants that exceed site screening levels. 3) If applicable, at what depth(s) is soil vapor known to be contaminated? Groundwater samples collected from Monitoring well MW-5 has had PCE concentrations of 13.6ug/L and 19 ug/L on 9/3/20 and 9/30/20, respectively. PCE was identified in one soil gas sample (SG-5) near the western portion of the parcel at 170 ug/m3. SG-5 is located downgradient of the plume identified around MW-5. 4) Will workers encounter contaminated soil vapor during planned redevelopment activities? ❑ Yes © No ❑ Unknown 16 EMP Version 2, June 2018 5) In the event that contaminated soil vapor is encountered during redevelopment activities (trenches, manways, basements or other subsurface work,) list activities for management of such contact: It is unlikely that workers will encounter contaminated soil vapor during the development. However, if odors are identified during the redevelopment activities, all work with stop. ASE will be called to evaluate the area for impacts. DEQ will be notified within 24 hours if impacts are apparent. PART 6. SUB -SLAB SOIL VAPOR — Please fill out the information below if existing buildings or foundations will be retained in the redevelopment. 1) Are sub -slab soil vapor data available for the Brownfields Property? ❑ Yes © No ❑ Unknown 2) If data indicate that sub -slab soil vapor concentrations exceed screening levels, attach a map showing the location of these exceedances. 3) At what depth(s) is sub -slab soil vapor known to be contaminated? ❑0-6 inches El Other, please describe: Click or tap here to enter text. 4) Will workers encounter contaminated sub -slab soil vapor during planned redevelopment activities? ❑ Yes ❑ No ©Unknown 5) In the event that contaminated soil vapor is encountered during redevelopment activities, list activities for management of such contact If odors are identified during the redevelopment activities, all work with stop. ASE will be called to evaluate the area for impacts. DEQ will be notified within 24 hours if impacts are apparent PART 7. INDOOR AIR — Please fill out the information below. 1) Are indoor air data available for the Brownfields Property? ❑ Yes © No ❑ Unknown 2) Attach a map showing the location(s) where indoor air contaminants exceed site screening levels. 3) If the structures where indoor air has been documented to exceed risk -based screening levels will not be demolished as part of redevelopment activities, will workers encounter contaminated indoor air during planned redevelopment activities? ❑ Yes ❑ No © Unknown 4) In the event that contaminated indoor air is encountered during redevelopment activities, list activities for management of such contact: If contaminated air is encountered once the building is constructed, ASE will conduct air sampling activities to determine the compound and concentrations present. Additional measures may be implemented based on the results of the sampling. 17 EMP Version 2, June 2018 VAPOR INTRUSION MITIGATION SYSTEM — Please fill out the information below. Is a vapor intrusion mitigation system (VIMS) proposed for this Brownfields Property? ❑ Yes © No ❑ Unknown If yes, ❑ VIMS Plan Attached or ❑ VIMS Plan to be submitted separately If submitted separately provide date: VIMS Plan shall be signed and sealed by a NC Professional Engineer If no, please provide a brief rationale as to why no vapor mitigation plan is warranted: Soil vapor samples collected from within the proposed hotel building footprint have no identified elevated VOCs. The groundwater flow on the site is to the west southwest away from the proposed structure. Any potential future construction over and downgradient of the known location of the chlorinated solvent contamination on the site will need to undergo reassessment for a VIMS based on contaminant constituent concentrations determined at that time. CONTINGENCY PLAN —encountering unknown tanks, drums, or other waste materials In this section please provide actions that will be taken to identify or manage unknown potential new sources of contamination. During redevelopment activities, it is not uncommon that unknown tanks, drums, fuel lines, landfills, orother waste materials are encountered. Notification to DEQ Brownfields Project Manager, UST Section, Fire Department, and/orother officials, as necessary and appropriate, is required when new potential source(s) of contamination are discovered. These Notification Requirements were outlined on Page 1 of this EMP. Should potentially impacted materials be identified that are inconsistent with known site impacts, the DEQ Brownfields Project Manager will be notified and a sampling plan will be prepared based on the EMP requirements and site -specific factors. Samples will generally be collected to document the location of the potential impacts. Check the following chemical analysis that are to be conducted on newly identified releases: © Volatile organic compounds (VOCs) by EPA Method 8260 © Semi -volatile organic compounds (SVOCs) by EPA Method 8270 ® Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and silver) Method 6020/7471, and Cr VI by EPA Method 7199 ❑ Pesticides: Specify Analytical Method Number(s): 18 EMP Version 2, June 2018 ❑ PCBs: Specify Analytical Method Number(s): Click or tap here to enter text. ® Other Constituents & Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.) Please note, if field observations indicate the need for additional analyses, they should be conducted, even if not listed here. CR VI by EPA Method 7199 Please provide details on the proposed methods of managing the following commonly encountered issues during redevelopment of Brownfields Properties. Underground Storage Tanks: Underground storage tanks are not expected on the site. If an underground storage tank is encountered during the redevelopment of the brownfield, all redevelopment activities must stop until actions have been taken. ASE will be contacted to evaluate the area and ASE will contact the Brownfields Project Manager. Any remaining regulated or hazardous material must be removed from the interior of the tank prior to excavation. Once the storage tank is cleaned, the excavation of the tank may proceed and disposed of at a recycling facility. If visual or olfactory indications of impacts are identified during construction activities, all work will stop in the area of suspected impact. Confirmation samples taken from the tank basin, four side walls, and at ten -foot intervals along any product lines will be collected and analyzed for VOCs, SVOCs, and RCRA Metals. Sub -Grade Feature/Pit: Sub grade features/pits are not expected based on the historical research for this site. However, if subsurface features are discovered, all work will stop, and ASE will be called to evaluate the area for potential impacts. ASE will contact the Brownfields Project Manager. . Buried Waste Material: Buried material is not expected to be on the site. If buried waste material is encountered during the redevelopment of the brownfield, all redevelopment activities must stop until actions have been taken. First the environmental consultant should be contacted to assess the situation prior to removal of the waste material. ASE will notify the Brownfields Project Manager. Once the area has been evaluated, removal of the waste material should proceed and be disposed of at an approved facility. If roofing material or other building materials are present, testing for the presence of asbestos may be warranted. The existing septic tank will be crushed in place and the void will be filled with on -site soils. Re -Use of Impacted Soils On -Site: 19 EMP Version 2, June 2018 Impacted soils that do not qualify as hazardous based on the Rule of 20 will be reused on -site under the parking lot. If unknown, impacted soil is identified on -site, management on -site can be considered after the project team provides the necessary information, outlined in Part I.A. Item 11, for Brownfields Project Manager approval prior to final placement on -site. If other potential contingency plans are pertinent, please provide other details or scenarios as needed below: If municipal waste is discovered during excavation activities, the material will be hauled to a permitted subtitle D landfill. POST -REDEVELOPMENT REPORTING ® Check this box to acknowledge that a Redevelopment Summary Report will be required for the project. If the project duration is longer than one year, an annual update is required and will be due by January 31 of each year, or 30 days after each one-year anniversary of the effective date of this EMP (as agreed upon with the Project Manager). These reports will be required for as long as physical redevelopment of the Brownfields Property continues, except that the final Redevelopment Summary Report will be submitted within 90 days after completion of redevelopment. Based on the estimated construction schedule, the first Redevelopment Summary Report is anticipated to be submitted on 12/30/2023 The Redevelopment Summary Report shall include environment -related activities since the last report, with a summary and drawings, that describes: 1. actions taken on the Brownfields Property; 2. soil grading and cut and fill actions; 3. methodology(ies) employed for field screening, sampling and laboratory analysis of environmental media; 4. stockpiling, containerizing, decontaminating, treating, handling, laboratory analysis and ultimate disposition of any soil, groundwater or other materials suspected or confirmed to be contaminated with regulated substances; and S. removal of any contaminated soil, water or other contaminated materials (for example, concrete, demolition debris) from the Brownfields Property (copies of all legally required manifests shall be included). X❑ Check box to acknowledge consent to provide a NC licensed P.G. or P.E. sealed, Redevelopment Summary Report in compliance with the site's Brownfields Agreement. 20 EMP Version 2, June 2018 APPROVAL SIGNATURES Brownfields Project Number: 25009-21-026 Brownfields Project Name: East Side Trucking Service �� AGtLd Prospective Developer: Naman Judson LLC Printed Name/Title/Company: Nick Patel Cheryl Moody Date 3/18/2022 Digitally signed by Cheryl Moody DN: cn=Cheryl Moody, o=Altantic Shores Environmental Services, Ltd., ou, email=cmoody@atlanticshoresenv.com, c=US Date: 2022.03.18 15:05:57-04'00' Consultant: Cheryl Moody, PE Date 3/18/2022 Printed Name/Title/Company: President, Atlantic Shores Environmental Services, Ltd )o — Brownfields Project Manager:Stephanie Graham 21 EMP Version 2, June 2018 Date 3/24/2022 Figure 1 NCBP Diagram for Temporary Containment of Impacted or Potentially Impacted Soil [: rom-Section View Top Plastic Cover Sheeting: Underliner: 1 laver. minimum of 10 {1 Layer, minimum: 10 mil thick) mil thick plastic Berm [Straw bales, WQight comlx)Sled earth, etc.) Of plastic N, ` cover used) d Lan� Land c Contaminated Soils Sujfh 1 Straw Bale Berm MAP View ■ � � � tiycight �... -. _......... _.... ■�T Contaminated Soils oo❑Plastic _ Shccting Dote Adapted from NC DEQ UST Section "Guidelines For Ex Situ Petroleum Contaminatcd Soil Remediation" dated December, 1, 2013 22 EMP Version 2, June 2018 00 c � o N Z � � O y N CD o Z W� • I � N � rI 1 Ln •� 1 'b cc Q fYi N U - N U Z ~� z ; 1 , kn a F&O ..................... ........................... . . . . . . . . . . ............ . .................. -: .............. —.. - ..... ...... ...... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Fir . . . . . . . . . . . . . . . . . . . . BRUrE BORUAY CAMg ra "TEN. NC.;FEUCAF, . . . . . . . . -rN dLO4SS*&-0TM UMBERLWDC0.W7Y . . . . . . . . . d . . . . . . . . . . p— ........... nh,.N E43D M. h&"Estt . . ......................... .............................. X'XIX P JE) W .......... F G' ........... ........... ........... ........... ... i i i i an i i i i i ..................................................................... ...........r.r.... . ............. .......... ................ EW,'BAFt- KULY TRUST ENY EFILki PER GARHEkU PIN x U554� . . . . . . k . . . . yi . . . . . . . . . . . Ilan . . . . . . . . . . . . . . . . . . . . . . . .. . . J. . . . . . . . . . ... --- ---- ----------------------- . . GRAPHIC SCALE, i Ja FIGURE 3 — Final Grade Sample Locations Source: Site Plans East Side Truck Service 6C S1,rah 520 Judson Church Road Nyl Fayetteville, North Carolina ASE Project No. 1487 Brownfields Project No: 25009-21-026 Aar September 2021 (0 bMwiIiiiew,il Sellices, 11(l. ((LU q I yl SS —'-Ss SS — SS sS SS sS SS SS SS IIINL_L— _ _---------------- II OLo N II ��DZ I 0Zo I I I —Z I � I - I ss SS 4— II II co I� i I \ ,II NCD NI 0� — -, w \ r^ so SS ~ I LI I z I �� ° 1 JC° co `n I O LO O, 00 Z00 LO u I I \ O7�NJ UZww 1 I } \� Dry D LL LL J J Of LL DLL LL LL LL LL LL q q qeS q q q I q —-- — ———GZ'e'; /bV1 V�V / �nG✓/`J LOO Ii� N -- \ O N 17 Him � ( � k (`! _ 0 £ 7 t8 `— �|77/( � �)k U A / kN— 0 (\\ \ \; a \ } \ ci ! ! \ \ -o * /!) } � � \ �\\ \ \ \\\ a } y3J .32. 5 75. \ \\\ `I \jj)\\\o \\\ \ \ } }}} � ` ; ! -Iln"LO Oy XI co c ----------1--------1----------1 ------ 1------- I ----- Clr C �1 N (00 co U) Q ---------- �------------------� ------------- -----III U >>O :�I0 � --- -- - - - - -- ----- - - - - -O-- -- i30" O-> L otj 11 a 1� -- - - -- I - - - - - -- N-- a 71 cr, O i7�6 LL,----------L--------I----------L------J-------1�--' O- O otS J(.� ! - - ----------L--------I----------L------J-------1L - ---- ----------L--------1----------L------J------ 1 0 - L----- ---------- L------- -I - - - - - - - - - - L------J------ a`�cn 1C-Y Oo 0o L----- ----------L--------I----------L------J----- otS Imo" c --FL =( - --L----- ----------L--------1----------L-- --J _ - W m j U) 71 N ` O O - ----- -L - ---- ----------L--------I----------L-- — --J - � p 0 0 d W (n LL � a------L----- ----------L--------1----------L a).--J c--�-- �- Q�------- L - ---- ----------L--------1----------L-- cv--J E-- N � — � o-�pL-------L----- ----------L------- -I - - - - - - - - - -L - - -CL --J �--0 w - O 1--------L----- ----------L------- J------- - - -L-- C -_J 0-0- .0 O O LL' ---1-------L----- 0 O -1-------L----- ----------L------ 1----------L-- 3--J�- M U O LL 41----1-------L----- ----------L------ Y1----------L---�.__J �" (>0.in" O O a -----1-------L----- ----------L------->>01----------L-- +`. L-J(n">'p" O LL M�--J-------1-------L----- ----------L------- >I - - - - - - - - - - L - --•N O-J-O--O L-LL J-------1-------L----- -- ----L-- - - - -- C1----------L---O 3 J C O. O O ce) ---J-------1-------L----- - -----1 ----- 01---------L- O J O 0" C ----J-------1-------L----- V F-- O ?) .� N --------1 - - - - -- OI - - -- �-----L---•L 0 J fp L -O ------J-------1-------L----- - -----1 -- -01---- L-- _' •' 01— O C�-1------J-------1-------L----- I co 71---- cu- ----�-- N> NIA- O N -4----- - ---- OId-- (0-- 01-- - - I - W a)-1-0-------I-------+-------4------ - LL l - - -- 31 I-- W N mg ) 4--------1-------4--------4------ ---1-------4--------4------ - 10--- >l --O- OI 1--------------4--------4------ - --- co —C (n- `I� - - -O I�Z -rl------------------*-------4------ - a) --- lotm - -- E IyEU +--------------+-------4------ - -- --- E0I1ca � ` ~�-- 0li p1T------�--------------�-------4------ -- 0f-7=�~"0 -A-------*--------------*-------4------ - -- C.�---LL-I L >--V0- (0) /) 06>--~I C -4-------+--------------+------------ EO - Cfn 06 (D -------t-------I-------t-------i------ (n - QI -U) I au) 0 -1-------+-------I-------+-------------- f Of L U c LI>>O L _LL__ a L I M 0+______�_______+_______�_____ - -- C--- �f� +P-= U oI> -Y- N f� Cn -------t-------I-------t-------------- -- U--- p1� -0 N �I >- co ~-F^ -------t-------I-------+--------- ----- - -- C - dfQ C NI�_W -m-�--H---- - -------t-------I-------t--------- ----- Ot p O — -WI p-----f-- - - - - -- -------+-------I-------+--------- ----- --U'c- -cjc i----------I---------------+-------I-------+-------i------ - -- E a = .-I 'a - -I- - - - - - - - ---- - - - - -- -------+-------I-------t--------- ----- - -- N --LL Cut �----I----------f-- - - - - -- -------t-------I-------t--------- ----- - --OU � 01(D -----I----------r------y-------t-------I-------t-------r----- C - --m c Oc. 11-------I----------r------ -------t-------I-------t-------r----- - --a) -1----------r------I-------t-------1-------t-------r----- - aDL) o—--------I----------r------1-------t-------I-------t-------r----- - N-N E r--------I----------r------y-------t-------I-------t-------r----- - - r--------I---------- r - - - - -- -------t-------I-------t------- r----- �" p - 0 Fa---r--------I----------r------ -------t-------I-------t-------r----- uuu � � ■ ■ ■ ■ i i i i i i■■ ■�..' u■ uu _ T JMFMME r - - - --------------------- - - - - -- -- ------------------------------ _----------------- -------------------------------------- ------------------------------- -------'--------!-------!----------------'--------'------- ---------------------------------------- — — — '— — — — — — — — L — — — — — — — 1 — — — — — — -----------------------1---------------------------------------- -------------------------- --------------------------------- !------- ------------------------ — — — — — — — — — —'— — — — — — — —'— — — -- -- - -- -- - — — '— — — — — — — — L — — — — — — — 1 — — — — — — -----------------------1---------------------------------------- -------'--------!-------!----------------'--------'------- ------------------------------ ---'--------!-------!----------------'--------'--- ------------------------------ - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - — — — — — — — — — —'— — — — — — — —'— — — !- - - - - -- ---------------------------- - - - - -- ! ---------------------------------- - - - - - - - - - -- - - - - - - -�- - - - - - - - L - - - - - - - -- - -- -- - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - L - - - - - - - L - - - - - - - 1 - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L - - - - - - - - - - - - - - - - - - - - - - L- - - - - - - - - - - - - - - -�- - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 4- - - - - - - - - - - - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 4- - - - - - - - - - - - - - - - -- - - - - - - -- - -- - - - - L- - - - - - - i- - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L- - - - - - - - - - - - - - - - - - - - - - - - - - 4- - - - - - - - - - - - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 4- - - - - - - - - - - - - - - - -- - - - - - - -- - - - - L- - - - - - - - i- - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 4- - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - 4- - - - - - - - - - - - - - - - -- - - - - - - -- - -- - - - - - - - - - - - - L- - - - - - - - -L - - - - - - - - - - - - - - - -- - - - - - - -- - - - - - - - L- - - - - - - - - - - f- - - - - - - - H - - - - - - - + - - - - - - - - - - - - - - - -I- - - - - - - -I- - - - - - - - - - - - - - - - - - - - - - - - - * - - - - - - - F - - - - - - - + - - - - - - - - - - - - - - - -I- - - - - - - -1- - - - - - - - - - - - - - - - - - - - - - - - - F - - - - - - - H - - - - - - - + - - - - - - - - - - - - - - - -I- - - - - - - -I- - - - - - - - - - - - - - - - - - - - - - - - - f- - - - - - - - H - - - - - - - t - - - - - - - - - - - - - - - -I- - - - - - - -1- - - - - - - - - - - - - - - - - - - - - - - - - * - - - - - - - F - - - - - - - + - - - - - - - - - - - - - - - -I- - - - - - - -I- - - - - - - - - - - - - - - - - - - - - - - - - F - - - - - - - H - - - - - - - + - - - - - - - - - - - - - - - -I- - - - - - - -I- - - - - - - - - - - - - - - - - - - - - - - - - f- - - - - - - - H - - - - - - - t - - - - - - - - - - - - - - - -I- - - - - - - -I- - - - - - - - - - - - - - - - - - - - - - - - - * - - - - - - - F - - - - - - - + - - - - - - - - - - - - - - - -I- - - - - - - -I- - - - - - - - - - - - - - - - - - - - - - - - - F - - - - - - - H - - - - - - - + - - - - - - - - - - - - - - - -I- - - - - - - -I- - - - - - - - - - - - - - - - - - - - - - - - - f- - - - - - - - H - - - - - - - t - - - - - - - - - - - - - - - -I- - - - - - - -1- - - - - - - - - - - - - - - - - - -------r-------r-------t------ ----------i--------i--------r- - - - - -- -- -------r-------r-------t------ ----------i--------i--------r- - - - - -- -- -------r-------r-------t------ ----------i--------i-------- r- - - - - -- -- -------r-------r-------t------ ----------i--------i--------r- - - - - -- -- -------r-------r-------t------ ----------i--------i--------r- - - - - -- --- - - - - -- -------r-------r-------t------ ----------i--------i-------- r- - - - - -- --- - - - - -- -------r-------r-------t------ ----------i--------i--------r- - - - - -- --- - - - - -- -------r-------r-------t------ - — — — — — r — — — — — — — — — — — — — — — — — — — — ----------i--------i--------r- - - - - -- — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — --- - - - - -- - — — — — — — — - - — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — `7 M cy, M M M M CO Cl) M Ct M Cf M M CO M M cl, CO M M cr M M M m M M M M co M M co M M y N Y N N N CN N CN N N N C, N Cs N N N N N N N N N N N N N N N N N N N N N N } Z Z Z 2 Z 2 J J � } Z Z Z J J J J J J J 0� Z Z Z �Q Q 3--.) --.) --) --.) --.) 2 QQ 2 2--,) --) --) --) --) --) --3 --,) -") --) < Q ---j—, —) M (fl M N a 0) C N 0) CO C 'IT a M r` O LO N Lr fI- 't N M C fI- LIB N N O M O 00 T — LO) I- zl- N O N O S c — Cl 0 0 — 0 — O O M O B — N O C O CN N O= — r- r- N N N O O N M M M co co M M co co M M M M cr M M M M M M M M M M M M M M M CN N N N N N N N N N N N N N} N N N N N N N N N } N N 11 I I QQ � ) j � ?� 2 QQ 22 -) ?? -)� �� � - Q �--) -) 00 LO I- — LO LOB N N O LO c N It O Lr Cfl 00 N Lr c LO — M Cfl CO CO CO fI- CO Cfl 00 N c N N O — M O — N O N O O — r N O N N 0 0 O N — r 0 O - -------------------------------------------- - - - - -- ----------------- ----- --------------------------------------------- - - - - -- ----------------- ----- --------------------------------------------- - - - - -- ----------------- ----- --------------------------------------------- - - - - -- ----------------- ----- --------------------------------------------- - - - - -- ----------------- ----- ----'--------!---------------!-------!--------'-------------- ' ------ i --- --------------------------------------------------- ----------------- ----- --'--------I----------------'-------!--------'------ ------ ------- - - - - -- ---- ----'--------I---------------!-------!--------'-------- - - - - -- ' - - - - -- ! --- --------------------------------------------------- ----------------- ----- --'--------I----------------'-------!--------'------ --- ---------- - - - - -- ---- ----'--------I---------------!-------!--------'-------- - - - - -- ' - - - - -- ! - -- --------------------------------------------------- ----------------- ----- --'--------I----------------'-------!--------'------ ------ ------- - - - - -- ---- ----'--------I---------------!-------!--------'-------- - - - - -- ' - - - - -- ! --- -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - - -I- - - - - - - - - - - - - - -I- - - - - - - - L - - - - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - L - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - L - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - - - L - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - - - L - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - L - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - - -I- - - - - - - - - - - - - - -I- - - - - - - - L - - - - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - L - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - L - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L - - - - - - - - - - - - - - - -I- - - - - - - J - - - - - - -I- - - - - - L - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L- - - - - - - - - - - - - - - - -- - - - - - - -I - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - -4 - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - -4 - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L- - - - - - - - - - - - - - - - -- - - - - - - -I - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - I- - - - - - - - - - - - - - - - -- - - - - - - -4 - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - I -- - - - - - - - - - - - - - - - -- - - - - - - -4 - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L- - - - - - - - - - - - - - - - -- - - - - - - -I - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - I- - - - - - - - - - - - - - - - -- - - - - - - -4 - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - I -- - - - - - - - - - - - - - - - -- - - - - - - -4 - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -�- - - - - - - - L- - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - -I- - - - - - - - H - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - -I- - - - - - - - H - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - -I- - - - - - - - H - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - -I- - - - - - - - H - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - -I- - - - - - - - H - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - -I- - - - - - - - H - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - -q - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - -�- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - -I- - - - - - - - H - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - -I- - - - - - - - H - - - - - ---i--------r----------------i---------------- - - - - -- ---------i-------- r---- ----i--------r----------------i---------------- - - - - -- ---------i-------- r---- ----i--------r----------------i---------------- - - - - -- ---------i-------- r---- ----i--------r----------------i---------------- - - - - -- ---------i-------- r---- ----i--------r----------------i---------------- - - - - -- ---------i-------- r---- ----i--------r----------------i---------------- - - - - -- ---------i-------- r---- ----i--------r----------------i---------------- - - - - -- ---------i-------- r---- ----i--------r----------------i-- - - - - ----- - - - - -- ---------i-------- r---- ----------------------------- - - - - ---- - - - - ------------- - - - - -- ---- ----------------------------- -- - - -- - --- - - - - ---- -- - - ---- - - - - -- - - -- Or M CM M M M M co M M M M CM M M Cl) co co N M N N N N N nJ M M CO CO M M M N co N N N N N M M M M N N N N N N N N N N N N N N N N 04 N N Z J J(D J (D(D(D(D 0�} Z Z Z Z z z Z J J J (D } J J J J J O O') CO N M O LO 00 'It— LO II- It CO O 0) Cfl N CO C W M r M 0 w w N f-- r, 00 Ln 00 N COCN N O C'M O N O O O— N M N O C M O N 0 0— C Cr N 0 N O cr M CM M M co co M M c'M M CO M C`� M M M M M M M M CO CO M M M Cr) M M M Cr) N N N N N N N N N N N N N N N N N N N N N N N N N N N C, N N N N Z J J J J 0(D(D CD D� Q} Z Z Z Z J J J J� 0 ��}D a_ J J J J J J CO cr co O rl- CO "t LO Cfl CO 00 N Lr C CO CO O fl- ti Lo N CO M 00 CA a CO N C r N N N 0 0 N N — O O r N C — N N N O C N N O O O N M L17 ILO L()7,-) M M Lfl7co 7co Ln7L�2 7cq I O L(� L17 LO LO M fM co Ln N Lf) LI) M Lij M Cl) �l C 0 - - - - - - - - - �- - - - - - - I - _ _ _ _ _ _ _ _ _ I _ _ _ _ I I I I I - - - - - - - - - - - I - - - - - - I - I I - --------------—--—--— - - - - - - - - - - - -I - -——————————— — — — — —— I- - - - - - - - - - - - -I - - - - - - - - - - - - -I- - - - - - - I - --—————————— — — — — —— I- - - - - - - - - - - - -I - - - - - - - I - - - - - - - - - - - - -II - --—————————— — — — — —— I- - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - J - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - -4 - - - - - - - - - - - - -I- - - - - - - -4 - - - - - - - - - - - - -I- - - - - - - -I - - - - - - - - - - - - -I- - - - - - - -4 - - - - - - - - - - - - -I- - - - - - - -4 - - - - - - - - - - - - -I- - - - - - - -I - - - - - - - - - - - - -I- - - - - - - -4 - - - - - - - - - - - - -I- - - - - - - -4 - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - - - - - - - - - - - - -I- - - - - - - - - cM N � C,M N Q coM OD M N CY) N N — — M 'COD N �'`� COY) U Q N Z N J 6� M CO N O N O 0110111101 a) C C n Table 3- Soil Sample Analytical Results East Side Trucking - 520 Judson Church Road Fayetteville, NC Boring B-7 B-8 B-9 Tl-SS T2-SS T3-SS T3-SSD SW -SS PSRG (Res)* (-g/kg) PSRG (GW)* (mg/kg) Depth 10.0' 1.5' 1.5' 3.5' 3.5' 3.5' 3.5' 4.0' Date 1/12/22 1/12/22 1/12/22 1/13/22 1/13/22 1/13/22 1/13/22 1/12/22 VOCs mg/kg Acetone <0.0062 <0.0369 <0.0358 <0.0363 <0.0406 <0.0393 <0.0394 <0.0115 12,000 25 Benzene <0.00038 <0.0023 <0.0022 <0.0023 <0.0025 <0.0024 <0.0024 <0.00071 1.2 0.01 2-Butanone (MEK) <0.0046 <0.0276 <0.0268 <0.0272 <0.0303 <0.0294 <0.0294 <0.0086 5,500 17 1,2-Dichloroethane <0.00064 <0.0038 <0.0037 <0.0037 <0.0042 <0.0025 <0.0041 <0.00084 0.49 0.0023 Ethylbenzene <0.00045 <0.0027 <0.0026 <0.0026 <0.0029 <0.0029 <0.0029 <0.00094 6.1 13 Naphthalene <0.00051 <0.003 <0.117 1 <0.003 <0.0033 1 <0.0032 <0.0032 <0.00094 2.1 0.39 Toluene <0.00027 <0.0016 <0.0016 <0.0016 <0.0018 <0.0017 <0.0017 10.6 990 1 8.3 1,2,4-Trimediylbenzene <0.00026 <0.0016 <0.0015 <0.0016 <0.0017 <0.0017 <0.0017 1 LU 63 12 Xylene (Total) <0.00055 9.91 10.7J 12 <0.0036 11.8.1 15.3 4.OJ 120 9.9 m&p-Xylene <0.00066 9.91 10.7J 12 <0.0043 11.81 12.1J 3.OJ 120 9.8 o-Xylene 1 <0.00043 1 <0.0025 <0.0025 <0.0025 <0.0028 <0.0027 1 3.2J 1.1J 140 9.8 SVOCs mg/kg Acenaphthene <0.123 <0.125 <0.121 <0.624 <0.132 <0.13 <0.13 <0.127 720 16 Acenaphthylene <0.123 <0.125 <0.121 <0.624 <0,132 <0.13 <0.13 <0.127 NE NE Anthracene <0.114 <0.116 <0.113 <0.581 <0,122 <0.121 <0.121 <0.119 3,600 1,300 Benzo(a)anthracene <0.116 <0.118 <0.115 <0.592 <0.125 <0.123 <0.123 <0.121 1.1 0.35 Benzo(b)fluoranthene <0.116 <0.118 <0.115 <0.592 <0.125 <0.128 <0.123 <0.121 1.1 1.2 Benzo(k)fluoranthene <0.123 <0.118 <0.121 1 <0.624 <0.132 1 <0.13 <0.13 <0.127 1 11 12 Benzo(g,h,i)perylene <0.135 <0.138 <0.134 <0.689 <0.145 <0.143 <0.143 <0.141 NE NE Benzo(a)pyrene <0.121 <0.123 <0.119 <0.614 <0.129 <0.128 <0.127 <0.125 0.11 0.12 Chrysene <0.127 <0.129 <0.125 <0.646 <0.136 <0.134 <0.134 <0.132 110 36 Chloromethane 1.0.1 <0.0044 <0.0043 <0.00348 <0.0053 <0.0051 <0.0052 <0.0015 23 0.015 Dibenz(a,h)anthracene <0,134 1 <0.137 <0.133 <0.684 <0,144 <0.142 <0.142 <0.14 0.11 0.38 Fluoranthene <0.12 <0.121 <0.118 1 <0.608 <0.128 1 <0.126 <0.126 <0.127 1 480 670 Flumene <0.123 <0.125 <0.121 <0.624 <0.132 <0.13 <0.13 <0.157 480 110 Indeno(1,2,3-cd)pyrene <0.138 <0.14 <0.136 <0.7 <0.147 <0.146 <0.145 <0.143 1.1 1 3.9 2-Methylnaphthalene <0.14 <0.142 <0.138 <0.711 <0.15 <0.148 <0.147 <0.145 48 3.1 Naphthalene <0.118 <0.12 <0.117 <0.603 <0.127 <0.125 1 <0.125 <0.123 2.1 0.39 Phenanthrene <0,114 1 <0.116 <0.113 <0.581 1 <0,122 <0.121 <0.121 <0.119 NE NE Pyrene <0.142 1 <0.144 1 <0.14 1 <0.721 1 <0.152 1 <0.15 <0.15 t <0.147 360 440 Metals mg/kg Arsenic 0.28J 2.5 2 1.3 1.3 1.6 1.7 1.2 0.68 5.8 Barium 2.3 21.1 18.4 15.9 Res PSRG 19.5 14.4 30.3 3100 580 Cadmium <0,031 <0.033 <0.033 <0.031 <0,035 <0.031 <0.032 <0.032 14 3 Chromium <1.4 6.4 5 5.8 5.7 7.6 5.4 5.9 23,000 360,000 Hex Cr 0.21J 1.1J 0.59J 0.54J 0.9J 0.64J 0.65J 0.58J 0.31 3.8 Lead 0.59 8.5 6.8 4.2 4.5 4.2 3.8 1 7.9 ND 270 Mercury <0.0089 0.029 0.016J 0.017J 0.017J 0.028 0.014J 0.023 1 2.3 1 1 Selenium <0,084 0.181 0.13J 0.181 0.17J 0.22J 0.18J 0.2J 78 2.1 Silver <0.14 <0.15 <0.15 <0.14 <0.16 <0.15 <0.15 <0.15 78 3.4 - - June 2021 Bold - exceedance of Residential or Soil to Water Criteria (Inactive Hazardous Sites Branch Preliminary Soil Remediation Goals) NA = Not analyzed Results are in mg/kg Yellow highlight represent MDL above the GW PSRG J values represent estimated concentration above adjusted method detection limit and below the adjusted reporting limit. Table 4 - Groundwater Analytical Results East Side Trucking 520 Judson Church Road, Fa ettville NC Well MW-7 MW-8 MW-8D MW-9 2L* Depth 19 feet 19 feet 19 feet 19 feet Baseline Depth to Water 11.8 feet 10.42 feet 10.42 feet 10.55 feet Depth to water prior to purging 11.8 feet 10.41 feet 10.41 feet 10.55 feet Date 1/14/22 1/14/22 1/14/22 1/14/22 VOCs (8260) (u /L) Acetone 5.2J <5.1 <5.1 <5.1 6,000 Chloroform <0.43 0.68J 0.6J <0.43 70 SVOCs (8270) (u /L) Phenol 3.4J 3.5J 2.2J 2.OJ 30 Metals (ug/L) Arsenic 0.16J 0.26J 0.3J 0.27J 10 Barium 8.3 27.6 28.7 69.7 700 Cadmium <0.06 <0.06 <0.06 <0.06 2 Chromium 2.6 2.1 2.9 1.6 10 Hexevalant Chromium* <0.30 <0.30 <0.30 <0.30 NE Lead 0.42J 0.40J 0.045J 0.42J 15 Mercury <0.12 <0.12 <0.12 <0.12 1 Selenium <0.072 <0.072 <0.072 <0.072 20 Silver <0.07 <0.07 <0.07 <0.07 20 * resampling for Hex Cr was conducted on 1/27/22 15 NCAC 02L .0202 Groundwater Standards (Effective April 1, 2013) ND- Not Detected NE- Not Established NA- Not Applicable J values represent estimated concentration above adjusted method detection limit a � ® ) � k �Cq�\ / £ 2 � � ) / e A \ ` e / �777- $ kn— � 7 f2� A � § § 72 w / » ] f 2 / 00 � $ � 2 Q = / �� ° a f%/jQ 2 6 @ ca � § { § � \ � a � � \ % k»2- \ CA/ © § £ v v , / / M \ .§ ) \ � « �\\ § \0/7\®®f , , o e■� 7 0 A j \ / \ \ / Table 1 Groundwater Sampling Results 520 Judson Church Road Fayetteville, North Carolina ASE Project Number 1487 Sample ID B1-S1 132-S2 NCDEQ Groundwater Quality Standards NCDEQ Gross Contaminant Level Depth 32' 16' Date 12/2/2020 12/2/2020 8260 (ug/L) Acetone 32.5 <25.0 6,000 6,000,000 Tetrachloroethene < 1.0 1.4 0.7 700 Values are in ug/L Bold values exceed the NCAC 2L Groundwater Quality Standards set by the North Carolina Department of Environmental Quality � ( � k (`! _ 0 £ 7 t8 `— �|77/( � �)k U A / kN— 0 (\\ \ \; a \ } \ ci ! ! \ \ -o * /!) } � � \ �\\ \ \ \\\ a } y3J .32. 5 75. \ \\\ `I \jj)\\\o \\\ \ \ } }}} � ` ; ! x r�rs E IT .o n J J J J J J Sr } Ln � 4--� o` .-i i C-4 CO m m m m m N L Q J oy U u u 01 ai Z N .2 a E < C '� N J- � zzzzzz z z z o -0 u --a w ar o M > U° E NN QQ�n O a Z Z J Z 0 0 4Nv-1cZ Eo � . wQ C: 0 ZJ L ❑ 0) ❑1 ��0 Z V L L Q 0) ❑ O O OS Q 4-> o n N o Do n�o ardn L> N N ++ 4-1 � o v, a � 4- Q .�ff u 4 W (D c E no co N 41 L E C( r p -a !✓ a-0 i- 1� C14ra ❑ ~ i -' co � a5 oz +, u Z mi- U n i• w 4-0 v L d.Y L3 ra 0) o m Lnn U) c "' a Q L7 o = U U) 4w i 0) C[ [LQ O1 J 0) i O 0 -0 G7 -2 iv{d N U �? Cj � C "" U .7V ❑ i U f6 C N eu0 cu 3 as C i E -0U o V) Do�' a)V p o .2- '- o .E -a a)' � v CD 4-J [V (7 W M Z) N Ey Z7J L 4 QQ�-v/�� Q E o o�.-' -� N N Vl U N ❑ u a N W N V E co m e¢. � N L J L CY� N-0 ❑ OL �+ W 0 c Q- 0) 0] N O u u rs y C V u U +0 o 0 Q N E U x X X T L) 4❑< ¢ co IIJ �j ST Q. +Ln N Z U J kn C W ui W N II J Z L 41 Z; � � VI V} N N C1 C} Of Of Q� N O O O N 0 s t� th i c c LLI a_ c 0 0 o 0 (6 0 w �- -0 Q = U ss-'-ssss ss C U_ L C - L III"L_L— ��M� , �\— I \ II ���00= C)N� O N W i O II ,� Cornrn CO 00 U �zZ I / Z c� I \ Z Z 0 1 _ Z W LU I o I t E N tB s U U (u E c m c o .+� L0 0� 0 L o) W m U U L p C m O >+ += N= U U) cn U) Q E .0 � , (0 �= }, E � N 0 U 0= U) O 0 N� U N L O N 0_ E O ! F �-a O O O , 00 � U H (a cA U U (n 0 y--r `� O U _O Q --� N U0 . N co CO ti r 00 m q I � II \ / I I NCL NI Q moZl CL —� \ \j r� �� o / Q Q Y M N a Z I / a) O > CD r— I i/ J0 10(0L I w a) 0- coo N d Q JNINi ]Vd c CO o o 1l Z I a dHdS`d 0Uzww ry �rCJ- -,g83„09�LS I \ i --------------------- K I / cu I � c / > / c > 0 w Qo w c Y � CL ae / D o = / i 5 iz) a) U o � CoN J CD7 c W .q /UI to SS- SS- SS- SS SS SS SS SS SS- SS SS- SS SS+ SS- wI Ond „8 L--- _ -- ! — — — — — — — — — — — — — — — — — — — — — — — — - t O N \ co Z H 0Zo I o Z _r_) I dia I d �� (� z m Io I ui _ — — — — — Q —m_ LU — m- =J0 � I U c I z I O U I o a1�L 0 Y O o ��� I I LU � o X a) a) — co N I I aQ a .O o cn zli°O� Olt N J o H ozuiw I } E _ IJ la a o N c rv- ) �'1�''L� — — crr-- 61 L6 I . a Z = J2Nd N 1 9dSVO ; N O LnON N 101-r - O — —1 9, A9 L9 3 o89S 10 0 �9 3„8V,5 o89S > ;• ,5 ,OZ m W ^ N > > Q N `9. W _0 N Q-p` OZ Lo o J C � C: U L O /J z =3C N II m CL 8� >N --t co CO m^ t > 0 L O- 'IT 0 IOZ ,OZ L_Lo ...F r 0 7 >, O O U � O M - \ -- - in N Lf) N co , N M _O I � �In LU q / U m SS SS - SS SS SS �� SS SS SS SS SS It Ond „8 N /M O N U) O � Tf O>O �z> z / I I� I I I I I I I I I LU - \ i --- z I °o ° I J C° co 10 o�mCy� I �c�� z 'n o u � N 0z W W I I } \ >4VIA AWN IYA AWN AWN AWN AWN Rio oil oil KV Rio All All > > i i i i♦ i a ♦ a ♦ ♦ a ♦ ♦ ♦ a . a♦ a♦ a a a a♦ a a a a♦ a `• ` i i i i♦ i♦ i i i i♦ i♦ i a •` a i a ♦ a. a♦♦♦♦ a. a. s♦ a a a ♦ a ♦ a ♦ a a ♦ a ♦ a ♦ a a aaaaa a ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ a i i ♦ i a i♦♦ a♦ i♦ i♦♦ a♦ i i i a ♦ ♦ ♦ i ♦ i ♦ ♦ ♦ ♦ i ♦ i ♦ ♦ i a ♦ ♦ a ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ a ♦ a ♦ ♦ a i i ♦ i i i a ♦ a a a i ♦ ♦ a a as aaaaaaa ♦ ♦ a ♦ a ♦ ♦ a a aaaaaa ♦ a a i i a ♦ a i i ♦ ♦ a9J �,J�,((�j�)J ♦ a ♦ a i ♦ ia� i i ♦ ♦ ♦ ♦ aaaaaa♦aaa a a i a ♦ a s ♦ ♦� a i i i♦ a a ♦ a a ♦ a ♦ i aaaaaa a a a a a a a a a a ♦ a a a a a a a a a a ♦ ♦ ♦ ♦ ♦ ♦ � � ,} a ♦ a �_ __ _ a a s . i ♦ ♦ a a a O ) 0 ((W�] q I yl SS - �SS� SS - SS SS SS SS SS SS SS SS SS SS 4- I � nd „ N o " � I I cornet o > o I �� I I ~ZZ I co I � I - I oil mozl 1 — I I Z I 0- CD ° 1 I Ln I �� I o u-) I of—o0N Oro ZLO o u o7� N J UZwW 1 1 J J O p0 \ 0 Q tY tY I q= On O v D L=L. D LL LLL LLL / \LL ri o It _LL \ 0 102.60 102.60 0 ` / O \ � N ` �'V 0 68706 68706 6570L / \ \ u' o 69701 \ N 0 OLZOLro m to \ N O O N \ O t p'`i p \ 0220 N UN /� Q N / O n' U O o o\ O � � o v _ 0 0 o v, � o � / _00- I NN + p N 00 N U I M J a_ ! U N 0 0 U ! otS Q O o iL M o oo U M N . / o f00N N _ p N p p o U N o 0 06 � O o c p p J N N � O O p O 0 0) Cl) Ll: No !1 U) y�I ss —'-�s ss — ss — ss ss ss ss ss SS 4— -nd..8 III L—L — \ — — — — — — — — — — — — — — -I -------- II/U)\ V pO Do C6oN� II c J O>O ~ZZ Z� �C) j O� N� r \� I LLZL fM Lo I J O O C N \ 'I O Cl) Q I —I N CD z = a moil �— AO IErI \ I �I I II II �I �I _ / Y/�, J ` \ LOD � LOD � LOD — LOD OD zo I I O cn LI: C C .-y O u71 - CO c ------------ - CL - - CD 0 / c \ --EERM ---RM ■ (10 N ' o \ as „� aS „t, � as „£ ______— 0- ' .�.�. Q in C: \ Cl) o O p aS „t, as ..� c o UO N \ d o ' o a �cn06 C) \ \ o 00o co \ aS ..V aS ..tl O p - p-------Fo co \ (n > (IS I.£ ao \ a ca M . I co \ C 00 J � co v m cn \ 0 (IS „t, O { e as „t/6-6 co a 000 � (� _ Z6 ca o o O 000 � � U O X \ \ (u L \ 1 \Jcuo aS11-V m / 06 z \ aS ..£ 0 HL —�H Pk 1 \ d W .q /U I rn SS— SS— SS— SS SS SS SS SS SS SS SS >+ Ond ..8 N L- \ _ O N \co C6 CO Z ~ 0Zo I o Z _i _) d2► dl�l o I co _ I Z I N cNo Z CL o Q moil I ui _ ---- — —m— r-- — J So I I Z I °o J (R (O LO 0 LO I I W I OON CD �o CO aQ a LO _ z CO o u OOzwwcn II } J J d q O �.I LL LL LL LL LL >> F LL LL N \ n� -TJ—N— t� — C7— _-'In U) JNMWd 1ldHdS`d ►M, IN f V9,9ti — C (W] • b I yl SS -sS•� SS SS SS SS SS SS SS — SS SS SS SS �-- IIN \ ----_------------/�d.------------- I _ \ I o"� \ I II ' �o�� o > o I - I 0 I dd d X i cn o �9F z I NI N O i O d O C / 00 O Z O C H ` H - o z J OL O W \ I 0- U) U O ?, \ j� I L � � �_ \ U � o a) � N M I II W — H D I O 06 L >J J II I d a C U> � o co Q (� + c '� Lo + C + d Q Cl) + O CO 3 E O _ _ N N O LO O J I I } J p X 0-0 ii' C CO CO C C> � IY � c) H� oN Co O + + �+ � N 0 0 I p 2 4 L c � Q o O LC) o O � 0 76 4) U C N 0 II 4) II II O U O'er a� Q �v �� > asOo cn —Xr, O O �_> �- C: > x I M� cn cn I— — --- — -- c7v i o 811V— — _ W M.V. \ \ \ \ \ \\\ \\\ \ \\\\\\ \ \ )\\O C O O C O 3d_ _ m -`IZ N C () L c O c C O LL o .L U _ C U 00 O - ,F N C a r CFL OLL L N U O O rn O cn U C C O XO O O O O O Q O O cn 11: y C C ui �71 m W- M } \ r------, L • / M O U cl O L LL "t -0 O II C O O LL � (B U \ M W C —_ N J � N 0 N U) N L C - d E 0 CO / JNI�i2iVd 1lVHdSV II/ r3 Of W ® I1 W II o I I co of I I ICI I I I ` Io c00 o wX iuXol I a m <'o I o 0 0 N / J / � M / 0 / . ® &o/o co p � N N 0 / f00 CD Ifm_n I • _ �® I I 1 1 I _ — V I / I / I / I I o I / I yl SS �Ss SS SS SS SS SS — 1�1I of II"L — �----- —---------- � I/U)o�cli \ IIII // 0Z0 I Z I � � 1 I �ba dlb U) I I I Ic z 0 I I z 1 IIII I o II I W \--- I;I I �o 0 I a I I � I �, O L c I °' 0 I O I op O IIIII o� II of o� L� IIII _ com II o I °� �voi J X .0 � ON a) I \� o� �I\ co oLL a LL LL LL LL j 'z LL 01 c 0 U a) C C � 0 O .� a> ca U 7 L }� a) C (n O L U cM IO C Q O Co O� X 7 Q /O Q a) Q � /Q O N a) C: C Vj § .O ch cn -M+' J O (W` :EliYl) L6't6 £9't,6 = ( 4-SS) £L't6 96'86 = Z5 North Carolina Department of Environmental Quality Division of Waste Management Brownfields Program BROWNFIELDS PROPERTY RECEPTOR SURVEY This form was created to clarify and simplify preparing a receptor survey for a brownfield site. Please provide the information requested below. Distances are measured from the site property boundary unless otherwise indicated by the DEQ Brownfield's Project Manager (PM). Site: East Side Trucking Service Address: 520 Judson Church Road City: Fayetteville, NC County: Cumberland County Brownfields Project Number: Date 3/18/22 25009-21-026 Property and Building Characteristics Surface Conditions Current Usage Proposed Usage Size of Property (acres) 3.39 NA % of property that is wooded/brush 90% gravel 56.90% % of property that is grassed areas 0 N/A % of property that is agricultural crops 0 N/A % of property that is paved 0 29.70% % of property that is covered by buildings 10% slab 13.40% If an existing building is on -site, please respond to the following. Information can be provided on additional sheets as needed. If numerous buildings are on -site, consult with your PM as only information on specific buildings may be needed. a. Provide occupancy and use information. There is currently no structures on the site with the exception of the slab foundation of a former building. There are currently no occupants on the property. The site is vacant. b. Describe the construction of the builidng including materials (e.g. wood frame, block), type and size of openings (e.g. windows, bay doors), and height (number of stories). Not Applicable. c. Describe the foundation construction. Include details on type, floor construction, and depth below grade. A concrete slab on grade foundation is present on the site. The thickness of the concrete is estimated to be three inches. d. Describe the HVAC system in the building. Include available details on type, equipment location, source of air return, and design considerations (e.g. positive pressure?). Not Applicable. e. Are any subslab ventilation systems or moisture barriers in place? If so, please provide details. Not Applicable. Rev. 09/2015 Page 1 of 3 North Carolina Department of Environmental Quality Division of Waste Management Brownfields Program Surrounding Property Land Use Please provide information on the following land uses in the vicinity of the subject site, including a map of the surrounding areas. If specific receptors are present, please provide addresses of the facilities. Zoning/Land Use Current Use/Occupant Proposed Usage North Undeveloped and/or residential Unknown South Three hotels Unknown East Undeveloped land Unknown West Kingdom Hall of Jehovah's Witnesses Unknown Specific Land Uses of Interest Y/N * Dista sta Distance Direction Address Is a school or daycare center within 1,000 ft of the Property? N N/A N/A N/A Is there a residence within 1,000 ft of the Property? Y 200', 236', 370', NW 526, 530, 538, 540, and 548 500' Is there a basement within 1,000 ft of the Property Unknown N/A N/A N/A * If numerous facilities of interest are present, their locations can be placed on a map in lieu of providing specific addresses. Utilities For the subject property, please provide a map of known buried utilites. If available, include depth to top, construction material, and diameter of the utilities. In addition, please provide the following information on utilty providers. If additional assessment is required, the public utility locators should be contacted. This information can then be added to a site map. Is there a septic system on -site? (Y or N) Yes, but to be closed upon redevelopment and isn't currently active Please provide the utility providers for the subject property a. Natural Gas Piedmont b. Sewer Fayetteville PWC c. Electricity Duke Energy d.Other N/A For surrounding properties, please complete the following table with available information. Utility/PotetttialRcceptor /N * Y Distance Vt) Direction Is a storm water pipe within 100 ft of the Property boundary? Unknon", Is a sanitary sewer within 100 ft of the Property boundary? N 986 SE Is a septic system leach field within 500 ft of the Property boundary? Y Site Former bldg Is a water line main within 100 ft of Property boundary? N 482 SW Is a natural gas line main within 100 ft of the Property boundary? N N/A N/A Is a buried telephone/ cable main within 100 ft of the Property boundary? Unknown Is a buried electrical cable main within 100 ft of Property boundary? Unknown * If yes, please provide a map or detailed information (distance, direction, depth) of the utility in correlation with the subject property. Rev. 09/2015 Page 2 of 3 North Carolina Department of Environmental Quality Division of Waste Management Brownfields Program Water Supply The purpose of this section is to provide information on the water supply for the site and surrounding areas. What is the potable water supply for the property? Public X Private X If Private, please provide details of the water supply source (i.e. well location, well construction, etc). If public, please include the water providers name. Public water is available along Judges Church Road at 505 Judson Church Road which is 482 feet southwest of the site. The water line currently terminates at this property. Fayetteville PWC Please provide the following information regarding water supply wells in the vicinity of the Property. At a minimum, a windshield survey within 1,500 ft of the property boundaries should be completed to determine if water supply or irrigation wells may be present. Information from applicable databases can and should be utilized; however, should not be utilized in lieu of the windshield survey. If multiple wells are present within the requested radius, please provide a map of the well locations. If needed, please attach a separate table to list all wells. Please note, the PM may opt for a more extensive water supply well survey if needed. Water Supply Wells YIN Distance Direction Address Is a public water supply well within 1 mile of the Property boundary? Yes 482 SW 505 Churchh RRd m Chd Is a private water supply well within 1,500 ft of the Property boundary? Yes 175 Nye Jude h C Church Rd Is an irrigation well within 1,500 ft of the Property boundary? Unknown Surface Water & Wetlands The purpose of this section is to provide information on the presence of surface waters and/or wetlands on, or in the vicinity of the Property. Provide Information regarding Surface Water and Response/Comments Wetlands Are there surface water features on the property? (If yes, please complete a. to d.) No a. Is the water body naturally developed or man-made? N/A b. List the uses of the water body. N/A c. What is the source of the water for the water body? N/A d. What is the nature of the bottom of the water body (e.g., rocky or concrete bottom, drainage N/A ways or impoundments) If no on -site surface water features, what is the nearest surface water body? 1,121 feet northeast of the site. Are there any wetlands present on the property? If no wetlands on -site, are wetlands suspected on No and no. adjoining properties? Rev. 09/2015 Page 3 of 3 Figure 1: USGS Topographic Location Map Legend 0 Site Location d,1zIt1 C: SO, *0 I r' Service Layer Credits: USGS The National Map: National Boundaries Dataset, 3DEP Elevation Program, Geographic Names Information System, National Hydrography Dataset, National Land Cover Database, National Structures Dataset, and National Transportation Dataset; USGS Global Ecosystems; U.S. Census Bureau TIGER/Line data; USFS Road Data; Natural Earth Data; U.S. Department of State Humanitarian Information Unit; and NOAA National Centers for Environmental Information, U.S. Coastal Relief Model. Data refreshed October 2018. 520 Judson Church Road Fayetteville, North Carolina Project Number: 25009-21-026 E,mimmici tal sellices, Ltd. 0 0.3 0.6 1.2 Miles N E 0 3 c O ^CD W O C �U N L C co N L U C O E L O co C U O m O Q O N co O Q O L- O • m L U) U) 0) c .Q .Q E 0 a� a� U c O