To:Peterson, Kyle R
Subject:Fw: [External] RE: Chemours - Sampling Plan - dated 12-28-2018 CO 11(b)
Date:Friday, March 29, 2019 12:29:00 PM
Attachments:image001.png
Sheila Holman
Assistant Secretary for EnvironmentNCDEQ1601 Mail Service CenterRaleigh, NC 27699-1601Phone: (919) 707-8619Fax: (919) 707-8619deq.nc.gov
sheila.holman@ncdenr.gov
**************************************************************************
Email correspondence to and from this address is subject to the North Carolina Public Records Law andmay be disclosed to third parties unless the content is exempt by statue or other regulation.**************************************************************************
From: Geoff Gisler <ggisler@selcnc.org>
Sent: Friday, March 29, 2019 12:23 PM
To: 'Compton, Christel E'; Grzyb, Julie
Cc: Lane, Bill F; Benzoni, Francisco; Abraczinskas, Michael; Scott, Michael; Culpepper, Linda; Long,
Brian D; Shelton, Dave; jfsavarese@wlrk.com; kemp@cfrw.us; kemp@cfrw.org; Joel M.; Holman,
Sheila; Kelly Moser; Jean Zhuang
Subject: [External] RE: Chemours - Sampling Plan - dated 12-28-2018 CO 11(b)
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to report.spam@nc.gov
Christel,I submit the following comments and questions on behalf of Cape Fear River Watch.
Figures 1 and 2 only show the “known drains and ditches.” Chemours should analyze the site
for other areas that receive process and non-process wastewater flow and stormwater flow
during rain events. Only then can Chemours adequately characterize all process and non-process wastewater and stormwater streams from each of the facility’s manufacturing areas.
On page 5 of the plan, it states that “Locations 4, 7, 10, 12, 13, and 15 are a combination of
stormwater and treated process and non-process water.” However, we were informed duringthe site visit that not all of the locations contain all three types of water (combination, process,and non-process water). Looking at the sampling locations, it appears that locations 4, 7, 10,and possibly 13 and 15, should not contain process wastewater. Please clarify exactly what
types of water are at each location.
At the very least, Chemours should sample at the intake and discharge for each of the
manufacturing areas at the facility. It is not entirely clear that is being done within thissampling plan.
The sampling plan should also include a sampling location at Chemours’ intake location for
the Cape Fear River. Sample location 1 is not representative of actual backgroundconcentrations in the Cape Fear River.
The sampling plan should include more sampling locations along the cooling water channel,
particularly the areas that historically carried process wastewater in order for the sampling tobe representative of potential contamination throughout that channel.
Slide 31 of Chemours’ January 31, 2019 Conceptual Site Model Updates and Old Outfall 002
Presentation demonstrated that there are extremely high levels of contamination in the
southeast corner of the DuPont manufacturing area. The sampling plan should include moresampling points in that area of the facility to determine the source of that contamination.
The sampling plan does not include a sampling point in the open channel to Outfall 002
anywhere from location 7 to location 20. There should be more sampling points along thischannel (i.e., after it receives discharges from the WWTP, from the cooling water channel, andfrom DuPont’s ditches).
Flow should be analyzed as well to determine mass loading of PFAS from each stream.
How does DuPont’s process wastewater reach the wastewater treatment plant?
How does Kuraray’s process wastewater reach the wastewater treatment plant? Through the
wood-lined channel?
Why is there non-process wastewater at location 4? Is there non-process wastewater in areas
of the site outside of the cooling water channel as depicted in Figure 2?Thank you,Geoff
Geoffrey R. GislerSenior AttorneySouthern Environmental Law Center601 W. Rosemary St., Suite 220Chapel Hill, NC 27516P: (919) 967-1450F: (919) 929-9421www.SouthernEnvironment.org
This electronic message and any attached files are confidential and are intended solely for theuse of the addressee(s) named above. This communication may contain material protected byattorney-client, work product or other privileges. If you are not the intended recipient orperson responsible for delivering this confidential communication to the intended recipient(s),and/or you have received this communication in error, then any review, use, dissemination,forwarding, printing, copying or other distribution of this email message and any attachedfiles is strictly prohibited. If you have received this confidential communication in error,please notify the sender immediately by reply email message and permanently delete theoriginal message.
From: Compton, Christel E [mailto:CHRISTEL.E.COMPTON@chemours.com] Sent: Tuesday, March 19, 2019 5:41 PMTo: Grzyb, JulieCc: Lane, Bill F; Benzoni, Francisco; Abraczinskas, Michael; Scott, Michael; Culpepper, Linda; Long, BrianD; Shelton, Dave; jfsavarese@wlrk.com; kemp@cfrw.us; Geoff Gisler; kemp@cfrw.org; Joel M.; Holman,SheilaSubject: RE: Chemours - Sampling Plan - dated 12-28-2018 CO 11(b)
Thank you, Julie –
I am in receipt of your comments and will ensure they are addressed in the plan.
Thank you –
Christel
Christel ComptonProgram ManagerThe Chemours Company – Fayetteville Works(o) 910-678-1213(m) 910-975-3386
The Chemours Company FC, LLC
22828 NC Highway 87 W
Fayetteville, NC 28306-7332
From: Grzyb, Julie [mailto:julie.grzyb@ncdenr.gov]
Sent: Tuesday, March 19, 2019 5:38 PM
To: Compton, Christel E <CHRISTEL.E.COMPTON@chemours.com>
Cc: Lane, Bill F <Bill.Lane@ncdenr.gov>; Benzoni, Francisco <fbenzoni@ncdoj.gov>;
Abraczinskas, Michael <michael.abraczinskas@ncdenr.gov>; Scott, Michael
<michael.scott@ncdenr.gov>; Culpepper, Linda <linda.culpepper@ncdenr.gov>; Long, Brian D
<Brian.D.Long@chemours.com>; Shelton, Dave <DAVID.C.SHELTON@chemours.com>;
jfsavarese@wlrk.com; kemp@cfrw.us; ggisler@selcnc.org; kemp@cfrw.org; Joel M.
<Joel.Gross@arnoldporter.com>; Holman, Sheila <sheila.holman@ncdenr.gov>
Subject: Chemours - Sampling Plan - dated 12-28-2018 CO 11(b)
External email. Confirm links and attachments before opening.
To: Christel Compton, Program Manager, The Chemours Company- Fayetteville Works
From : Julie Grzyb, Supervisor, NPDES Complex Permitting
Subject: Chemours’ Sampling Plan submitted per Consent Order Requirement 11(b)
Date: 3/19/2019
The Division of Water Resources, NPDES Complex Permitting has reviewed the sampling
plan submitted by Chemours on Dec. 31, 2018 as part of the CO and we have the following
comments:
1) The influent to the Wastewater Treatment Plant should be included as one of the
sampling locations.
2) The effluent from whichever sedimentation basin is discharging (only one basin is in
use at a time) should be included as one of the sampling locations.
3) Page 6 : Process Wastewater
Process wastewater samples will be collected as grab samples from the Chemours
Monomers IXM Area, Chemours PPA Area, Kuraray and DuPont (Locations 16 to 19). The
project team is working with Chemours, Kuraray and DuPont facility staff to identify
and access the appropriate sampling points for the combined process wastewater from
each of these areas.
Discrete process wastewater samples should be collected from Kuraray and DuPont.
4) All PFAS reported as a result of the 537.1 test method shall be reported in the
results including PFOS and PFOA (i.e. Table 1 seems incomplete only one compound
is listed for Method 537).
5) Page 8: Equipment, Trip and Field Blanks.
Equipment blanks will be collected at a frequency of one per day during the Initial
Characterization, then their frequency and the need for other blanks will be re-evaluated
for Ongoing Sampling.
Because contamination can be random as well as systemic, analysis of all three types
of blanks, not just if there is a value above the PQL for Equipment Blank should be
required.
6) On the first page,
a. it should say “requirements specified in Paragraph 11(b)” (rather than
“Paragraph 11” since there are additional requirements and plans due under
Paragraph 11);
b. off-site disposal is for all Chemours process wastewater (not just process
wastewater containing GenX);
c. Chemours uses “emissions” to refer to both air and water; should it be
“discharges” for water?
NPDES recommends that Chemours proceed with the Sampling Plan provided sampling
points identified in comments number 1, 2, and 3 are added and all PFAS compounds
analyzed using the modified 537.1 test method are reported including PFOS and PFOA.
Item number 5 should be addressed as standard QA QC procedures.
The Division has a site visit planned on March 29th and reserves final approval of the
sampling plan until comments that may result from that visit can be stated and addressed.
Items listed in number 6 can be addressed with any additional comments and revisions
resulting from the site visit.
Please let me know if you would like to discuss any of these items in more detail.
Julie A Grzyb
Supervisor
NPDES Complex Permitting
NC DEQ / Division of Water Resources / Water Quality Permitting
919 707 3605 office
919 707 9000 main office
julie.grzyb@ncdenr.gov
Physical Address: 512 North Salisbury St., Raleigh, NC, 27604
Mailing Address: 1617 Mail Service Center, Raleigh, NC, 27699-1617
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
This communication is for use by the intended recipient and contains information that may beprivileged, confidential or copyrighted under applicable law. If you are not the intendedrecipient, you are hereby formally notified that any use, copying or distribution of this e-mail,in whole or in part, is strictly prohibited. Please notify the sender by return e-mail and deletethis e-mail from your system. Unless explicitly and conspicuously designated as "E-ContractIntended”, this e-mail does not constitute a contract offer, a contract amendment, or anacceptance of a contract offer. This e-mail does not constitute a consent to the use of sender'scontact information for direct marketing purposes or for transfers of data to third parties.