HomeMy WebLinkAbout2020.01.31_CCO.p12_ResponsestoCFRWCommentsSupplementalReport 2501 Blue Ridge Road, Suite 430 Raleigh, NC 27607 PH 919.870.0576 FAX 919.870.0578 www.geosyntec.com
Responses to CFRW P12 Supplemental Report-final
Memorandum
Date: 31 January 2020
To: The Chemours Company FC, LLC
From: Geosyntec Consultants of NC, P.C.
Subject: Response to Cape Fear River Watch Comments Dated December 19,
2019
Geosyntec Consultants of NC, P.C. (Geosyntec) has prepared this memorandum for The Chemours
Company FC, LLC (Chemours) in response to a letter from the Southern Environmental Law
Center (SELC) on December 19, 2019 (SELC, 2019). The letter contained questions and
comments from Cape Fear River Watch (CFRW) on the Cape Fear River PFAS Loading
Reduction Plan – Supplemental Information Report (the Supplemental Information Report;
Geosyntec 2019a) regarding proposed actions to be completed by Chemours at the Chemours
Fayetteville Works site (the Site). The Supplemental Information Report was submitted to the
North Carolina Department of Environmental Quality (NCDEQ) and CFRW by Chemours on
November 4, 2019 in response to requests from NCDEQ and CFRW for additional information
regarding the Cape Fear River PFAS Loading Reduction Plan (the Reduction Plan; Geosyntec
2019b). The Reduction Plan was submitted by Chemours on August 26, 2019 pursuant to
paragraph 12 of the Consent Order amongst Chemours, NCDEQ and CFRW.
The objective of this memorandum is to provide CFRW with responses and explanations to their
questions and comments. The letter transmitted from SELC includes topical questions and
comments which are repeated in a few places. To provide the responses to both the topical and
specific comments, this memorandum is organized into the following sections:
• Summary of In-Progress and Proposed Corrective Actions (Section 1);
• Seep Remedy Responses and Explanations (Section 2);
• Old Outfall 002 Responses and Explanations (Section 3);
Response to Cape Fear River Watch Comments 31 January 2020
Page 2
Responses to CFRW P12 Supplemental Report-final
• Outfall 002 Responses and Explanations (Section 4);
• Groundwater Extraction (Section 5);
• Clarification Regarding Feasibility (Section 6); and
• Responses to Other Comments or Questions (Section 7).
1. SUMMARY OF IN-PROGRESS AND PROPOSED CORRECTIVE ACTIONS
Chemours has committed to perform eleven actions over the next five years to reduce remaining
PFAS loadings to the Cape Fear River. These actions are anticipated to reduce loadings to the Cape
Fear River by at least 75% consistent with paragraph 16 of the Consent Order. These actions, their
associated timelines and anticipated loading reductions are presented in Table 1. These actions
have been previously described in the following reports:
• Cape Fear River PFAS Loading Reduction Plan (the Reduction Plan; Geosyntec 2019b)
submitted by Chemours on August 26, 2019 pursuant to paragraph 12 of the Consent Order.
• Cape Rear River PFAS Loading Reduction Plan – Supplemental Information Report (the
Supplemental Information Report; Geosyntec 2019a) submitted by Chemours on
November 4, 2019 pursuant to requests for additional information by DEQ and CFRW.
• Corrective Action Plan (the CAP; Geosyntec 2019c) submitted by Chemours on December
31, 2019 pursuant to paragraph 16 of the Consent Order.
Of these eleven actions, two have been implemented (sediment removal from the cooling water
channel and installation of air abatement controls including commissioning of the thermal
oxidizer), two are in-progress interim actions to support rapid reductions, and the remaining seven
are in-progress actions. PFAS loading reductions from the Site to the Cape Fear River are proposed
to be evaluated as described in the CAP (Geosyntec, 2019c). Additional details about the
calculation of baseline river mass loads are provided in Attachment A – River Baseline Calculation
Methodology.
Response to Cape Fear River Watch Comments 31 January 2020
Page 3
Responses to CFRW P12 Supplemental Report-final
Table 1: Overall Estimated Reductions Plan Schedule and Estimated Reductions to Cape Fear River Total Table 3+ PFAS Loadings
Response to Cape Fear River Watch Comments 31 January 2020
Page 4
Responses to CFRW P12 Supplemental Report-final
2. SEEP REMEDY RESPONSES AND EXPLANATIONS
Chemours has proposed implementing interim seep remedies by pilot testing both a flow through
cell at Seep A where treatment occurs in situ and a French drain with ex situ treatment at Seep D.
After optimizing and evaluating the performance of these two interim remedies, and assuming
equivalent mass removal performance, Chemours would proceed implementing the flow through
cells at Seeps B and C. Flow through cells are the preferred seep remedy since among other
potential advantages they:
• are passive remediation systems;
• are less disruptive to local ecological habitats;
• have a higher likelihood of gaining the United States Army Corps of Engineers (USACE)
approval;
• have lower costs; and
• they can likely be made operational more quickly.
While flow through cells are preferred to French drains as a seep remedy, both are expected to
perform better than groundwater extraction near the headwaters of the seeps. Groundwater flow in
the perched zone and the surficial aquifer ultimately flows toward the Cape Fear River and is
expressed as seeps along the bluff. Smaller seeps toward the top of the bluff coalesce into larger
flows as water moves downhill. This natural seep system is significantly more amenable to control
at the seep than by extracting groundwater via wells. The water balance indicates that this flow
represents the vast majority of flow transported toward the east beneath the facility. No
configuration of pumping wells could capture as much of this flow as is already expressed at the
capture location design of the seeps.
CFRW comments that flow through cells (or French drains) should be implemented at all seeps
simultaneously. It is our professional judgment that given the technical challenges of the
contaminants and the proximity of the river at the likely seep treatment locations, pilot testing is
required to effectively design a resilient, effective, and implementable remedy; hence the pilot test
approach at Seeps A and D. After the pilot test period (proposed to be six months) and collection
of operational data, performance monitoring will demonstrate whether flow through cells are the
suitable long-term remedy. While a six-month pilot period is proposed, the results of the pilot may
indicate the viability of the flow through cell on a shorter timeframe, potentially as soon as 4
months after pilot system startup. Consequently, flow through cells could be installed at the
remaining onsite groundwater seeps, without the need for further pilot testing at those other seeps.
The findings from constructing and operating the pilot at Seep A will be valuable to implementing
effective flow through cells at the remaining seeps.
Response to Cape Fear River Watch Comments 31 January 2020
Page 5
Responses to CFRW P12 Supplemental Report-final
We anticipate granular activated carbon (GAC), or potentially another material evaluated in bench
scale testing, to be effective in flow through cells at reducing PFAS concentrations. The design of
the flow through cells will incorporate pretreatment and filtration to optimize, to the extent
practical, contact efficiency between adsorption media and the Table 3+ PFAS. Note that
pretreatment and filtration will be a key engineering design element for the French drains as well.
During the pilot test phase, Chemours will prepare preliminary design drawings and engineering
packages for implementation of French drains at Seeps A-C should assessment of pilot testing data
result in French drains being selected as the long-term remedy. These drawings and engineering
packages would be in addition to the design drawings and details being prepared for the Seep D
pilot French drain or possible future flow through cells. This package would then be finalized as a
detailed design package using the findings from the pilot tests.
Seep Remedy Performance
During normal operating conditions, to achieve a 95% total Table 3+ PFAS loading reduction from
the seeps, the seep remedies will be designed to capture the maximum flow possible from the seeps
and to treat such flow at a greater than 95% removal efficiency of total Table 3+ PFAS. The
attainable removal efficacy of the seep remedies will be developed from the bench and pilot tests.
Normal operating conditions are defined as the time when river levels are below the elevation of
the seep remedy. Periodically, river levels may become elevated to levels above the seep remedies
due to weather conditions such as flooding caused by hurricanes or heavy rain events. An extreme
weather preparedness plan will be prepared to recommend measures to safeguard seep remedy
infrastructure during these events.
The seep remedies will be designed to capture the maximum surface water based upon the possible
placement location at the seep. Chemours recently received lidar topographic survey data of the
Site adjacent to the Cape Fear River. This and other data will be used to target the most effective
placement locations for the flow through cells. Selection factors include (a) locations where
multiple seep flows have come together and (b) locations where natural topography is conducive
to construction designs supporting mass loading reductions.
An essential requirement for a seep remedy that fulfills a 95% PFAS mass loading reduction is
securing any necessary Clean Water Act (CWA) 401 permit from the NCDEQ Division of Water
Resources (DWR) and a CWA 404 permit from the USACE. Potential seep remedy designs may
exist in either or both Waters of the United States (WOTUS) or wetland areas. Chemours is
actively engaging both DWR and USACE, including proposing Site visits to view the seeps, to
discuss PFAS loading reduction objectives and potential seep remedy designs including
advantages and disadvantages regarding both mass loading reductions and permitting needs.
Response to Cape Fear River Watch Comments 31 January 2020
Page 6
Responses to CFRW P12 Supplemental Report-final
Seep Remedy Performance Monitoring
At this time, seep remedy performance monitoring is proposed to be accomplished using the sum
of the twenty (20) Total Table 3+ PFAS. Seep remedy mass removal rates, which will provide an
indication of overall seep remedy performance, will be calculated using Equation 1 below where
the influent and effluent concentrations are used to calculate percentage mass removals. As the
design of the seep remedies are finalized, Chemours will develop a similar mass loading reduction
equation consistent with the seep remedy designs. The final designs will identify the potential
monitoring opportunities and constraints.
Equation 1 – Seep Remedy Mass Removal Rate 𝑺𝑺𝑺𝑺𝑺𝑺= 𝒄𝒄𝒊𝒊− 𝒄𝒄𝒆𝒆𝒄𝒄𝒊𝒊× 𝟏𝟏𝟏𝟏𝟏𝟏%
Where:
SMR = seep remedy mass removal rate calculated as a percentage for a set of paired influent
and effluent samples representing equivalent volumes of water flowing through the seep
remedy treatment system; 𝑐𝑐𝑖𝑖 = the total Table 3+ PFAS concentration of the seep influent into the treatment system; and 𝑐𝑐𝑒𝑒 = the total Table 3+ PFAS concentration of the seep effluent after leaving the treatment
system.
3. OLD OUTFALL 002 RESPONSES AND EXPLANATIONS
The Consent Order states in paragraph 12(e)(i) that the Old Outfall 002 treatment system, “shall
… capture the dry weather flow” and, “shall meet such discharge standards as shall be set by DEQ,
and shall, in addition and at a minimum, be at least 99% effective in controlling indicator
parameters, GenX [HFPO-DA] and PFMOAA”.
Chemours is on track to meet these requirements of the Consent Order. First, the treatment system
is being constructed to treat up to 750 gallons per minute. Second, treatability testing performed
by Chemours has demonstrated that the treatment system will be at least 99% effective in
controlling indicator parameters HFPO-DA and PFMOAA. CFRW’s comments about
groundwater extraction and the Old Outfall are discussed later in Section 5.
4. OUTFALL 002 RESPONSES AND EXPLANATIONS
Chemours proposed five actions focused on reducing Outfall 002 PFAS concentrations including:
Response to Cape Fear River Watch Comments 31 January 2020
Page 7
Responses to CFRW P12 Supplemental Report-final
• Removal of Sediment from Conveyance Network (completed in 2019);
• Replacement of Terracotta Pipe (scheduled for 2021);
• Developing a Stormwater Pollution Prevention Plan (in progress);
• Assessment of Means to Mitigate Groundwater Intrusion (in progress); and
• Implementing Targeted Stormwater Control (in progress).
These five actions, in addition to the installation of air abatement controls, will reduce Outfall 002
PFAS loading to the Cape Fear River.
This section provides responses and explanations to CFRW comments and questions related to
Outfall 002 including stormwater (targeted and Site-wide); process water and Outfall 001; and the
Outfall 002 80% reduction target specified in paragraph 12 of the Consent Order. A response to
CFRW’s comment about groundwater extraction related to potential groundwater intrusion into
Outfall 002 is provided later in the Groundwater Extraction section.
Stormwater
Targeted Stormwater
Building on 2019 data and analyses, Chemours is undertaking a set of detailed stormwater control
assessments and investigations in 2020 to develop and implement a targeted stormwater control
program. This includes performing a stormwater PFAS treatability evaluation, which will
investigate effective treatment (and pretreatment) methods for treating PFAS in stormwater.
Targeted stormwater sampling will also be conducted to sample numerous sources of stormwater
runoff to Outfall 002 in order to determine how stormwater concentrations vary by source and
spatially. A Stormwater Action Plan will then be developed to summarize findings from the
treatability evaluation and stormwater sampling (site-wide and targeted) and outline actions to
address source control and/or treatment of stormwater.
Standalone Site-Wide Stormwater Treatment System
The costs presented in the Supplemental Information Report (Geosyntec 2019a) for site-wide
stormwater treatment include a standalone treatment system because of the nature of stormwater
flows. Rainfall and consequently stormwater runoff are not both evenly distributed in time. Storm
events vary widely, in both duration and intensity, and peak runoff can be very high. Consequently,
site-wide stormwater treatment requires a combination of large equalization tank(s) and a
treatment system that is much larger than the Old Outfall 002 system, hence necessitating a
separate stand-alone system. As described in the Supplemental Information Report, the Site area
draining to Outfall 002 was modeled using the hydrologic model and historical rainfall from 2006
through 2018. A range of storage volume sizes was also modeled, and the cost-effective storage
size was determined based on the plot of storage volume size versus percent capture of runoff
Response to Cape Fear River Watch Comments 31 January 2020
Page 8
Responses to CFRW P12 Supplemental Report-final
volume. The size used in the evaluation resulted in 85% average annual percent capture of runoff
volume. Increasing the size greater than the storage volume used in the evaluation would add
significant cost but would only result in minimal increases in the amount of runoff volume captured
and treated. The required storage tank for this scenario was estimated to be 5.5 million gallons,
and the treatment flowrate was approximately 3,800 gallons per minute. This is at least five times
the Old Outfall 002 treatment system flow rate, a significantly larger flow rate. Therefore, the
original costing presented in the Supplemental Information Report is appropriate to use in
evaluating the economic feasibility of implementing a Site-wide stormwater remedy.
Additionally, the estimated Site-wide stormwater treatment system flow rate of 3,800 gallons per
minute represents the peak flowrate to the treatment system (from the stormwater storage tank).
This peak flow rate cannot be used to estimate yearly flows (these flows would result in incorrect
estimates of 5,472,000 gallons per day or 2,000,000,000 gallons per year). Due to rain events and
subsequent stormwater runoff rates being high in intensity at times, the design treatment flowrate
will be used during these events but will not be utilized at a constant rate for the entire year. The
annual treatment volume of 120 million gallons was estimated based on hydrologic modeling using
long-term rainfall data, so that volume accounts for the expected fluctuations in stormwater runoff
throughout an average year.
Stormwater Runoff Flows
On page 6 of the letter, CFRW expressed confusion regarding values in the Supplemental Report
and the NPDES Application. It appears CFRW may have mistakenly read the value of stormwater
runoff discharged from Outfall 002 in the NPDES renewal application as units of gallons per year
instead of gallons per day. If the correct units, as presented in Attachment B.1.1 of the NPDES
renewal application, are used (resulting in a value of 355,308 gallons per day of non-process
stormwater), there is no conflict.
Outfall 001 Flows and Process Water
CFRW’s comments mention process water but are not specific to which process waters are being
referred to. Based on context, for the purposes of this response, we assume CFRW is referring to
process water from Kuraray and DuPont, which presently is sent to the WWTP. Chemours process
wastewater is presently sent for offsite disposal.
At the Site, the Wastewater Treatment Plant (WWTP) discharges to the open channel to Outfall
002. Prior to November 29, 2017, the WWTP received Chemours process water flows from the
Monomers IXM area, which contained Table 3+ PFAS compounds from fluoroproduct
manufacturing. At present, the WWTP receives water from: process water from Site tenants
Kuraray and DuPont, stormwater, and sanitary water.
Response to Cape Fear River Watch Comments 31 January 2020
Page 9
Responses to CFRW P12 Supplemental Report-final
The processes at Kuraray and DuPont are not known to produce Table 3+ PFAS. In the paragraph
11(b) characterization sampling program results (Geosyntec, 2019d), process water sampling from
both Kuraray and DuPont generally indicate total Table 3+ PFAS concentrations similar to river
intake water at the Site (Location 1). Stormwater will have a component of PFAS. Stormwater is
being assessed in 2020 as part of a focused stormwater management program.
Historically, the WWTP received process water containing Table 3+ PFAS via the terracotta pipe.
While the section of this pipe from the Monomers IXM area has been disconnected and grouted,
the remaining length of the terracotta pipe may still be contributing small releases of PFAS to the
WWTP as past sedimentation in the pipe which may have contained PFAS from process water
might be periodically re-mobilized. In the paragraph 11(b) characterization sampling program,
Location 23A is located where the terracotta pipe is connected to the Monomers IXM area. The
samples collected from this location after the grouting occurred indicate that water at this location
continues to contribute total Table 3+ PFAS to the WWTP.
By the Fall of 2021, Chemours and Kuraray will replace the remaining in use portions of the
terracotta pipe. As described in the Reductions Plan, Chemours will “remov[e] the connection of
the terracotta pipe to the Wastewater Treatment Plant. Flows of water to the Wastewater Treatment
Plant from the terracotta pipe will be transmitted through newly constructed above ground piping.”
This action is expected to further reduce the loading of total Table 3+ PFAS mass to the WWTP.
Therefore, designing and implementing a treatment system for either flows of process water into
the WWTP or for flow from the effluent the WWTP are not merited at present based on the
upcoming planned terracotta pipe replacement.
Outfall 002 and Paragraph 12 Reduction Targets
Paragraph 12 of the Consent Order states that Chemours must demonstrate that the concentrations
of GenX [HFPO-DA] and PFMOAA detected in Outfall 002 cannot be reduced by at least 80%.
The Outfall 002 Assessment (Attachment 3 to the Reduction Plan submitted on August 26, 2019)
presented one potential control approach that could potentially achieve an 80% reduction at Outfall
002: treating all flows (i.e., stormwater and dry weather flows) to Outfall 002 end of pipe. The
Supplemental Information Report showed that this option was economically infeasible.
Treating site-wide stormwater (at 85% average annual percent capture) was presented as a
potential control approach in The Outfall 002 Assessment. However, this action was estimated to
only result in a potential reduction to Outfall 002 of 40% (compared to the 2018 calendar year)
and so would need to be paired with other actions to achieve an 80% reduction. The Supplemental
Information Report showed that treating site-wide stormwater was economically infeasible.
Therefore, together both the Reduction Plan and the Supplemental Information Report provided
information to show that the 80% reduction of HFPO-DA and PFMOAA in Outfall 002 was
economically infeasible.
Response to Cape Fear River Watch Comments 31 January 2020
Page 10
Responses to CFRW P12 Supplemental Report-final
5. GROUNDWATER EXTRACTION
Chemours’s proposed remedial alternatives will treat PFAS in groundwater that have or are
reaching Willis Creek, the Old Outfall 002, Seeps A-D, and the Cape Fear River. CFRW suggests
Chemours perform significant additional extraction of groundwater at the Site. This groundwater
extraction is unwarranted and also in cases infeasible since much of the groundwater extraction
suggested by CFRW would:
• extract groundwater which would have been intercepted by other remedies; and / or
• compromise the schedule for implementing long-term remedies; and / or
• be economically infeasible.
This section describes why specific groundwater extraction recommendations by CFRW are
unwarranted or infeasible.
Extracting groundwater from all three aquifers is not necessary
On page 8 of the letter, CFRW suggests that groundwater from all three aquifers be extracted to
reduce PFAS loading to Willis Creek. Extracting groundwater from all three aquifers is not
warranted. An effective hydraulic control remedy is one that will extract groundwater where it
provides the most value. All surface water bodies at the Site are in contact with at least one
geological formation at any given transect, therefore usually the most efficient place to capture
this groundwater is before discharge to the adjacent surface water body. This approach makes
groundwater extraction more targeted.
For instance, the Perched Zone is not in contact with the Cape Fear River. Groundwater from the
Perched Zone must travel downwards and eastwards before being discharged at either a seep or
the Cape Fear River via the Black Creek Aquifer. The seep remedies proposed in the Reduction
Plan will treat this Perched Zone groundwater. For discharge to the Cape Fear River, the long-term
groundwater remedy will capture and treat this water. Groundwater capture and treatment can be
targeted and extracting groundwater from all three aquifers is unwarranted to attain PFAS loading
reductions to surface water.
Extracting groundwater reaching Seeps A to D and Old Outfall 002 is unwarranted
Extracting groundwater that eventually reaches the seeps and Old Outfall 002 is unwarranted for
two reasons. First, this water can be effectively treated by the seep and Old Outfall 002 remedies.
Second, extracting this groundwater is unlikely to sufficiently stop the flow of groundwater to the
seeps or Old Outfall 002 (i.e., dry up the streambeds) and hence would then require the seep and
Old Outfall 002 remedies still be installed.
Response to Cape Fear River Watch Comments 31 January 2020
Page 11
Responses to CFRW P12 Supplemental Report-final
Extracting all groundwater reaching the seeps or Old Outfall 002 is likely not possible using either
wells or extraction trenches. First, groundwater wells alone are unlikely to capture all flows. All
geological formations are heterogenous. While the extraction wells may capture a large portion of
flow, there can exist highly transmissive zones between wells where groundwater is not captured
and still is expressed at the seeps or Old Outfall 002. Additionally, as groundwater expresses itself
at the bluff in an unconfined aquifer environment, the groundwater layer becomes very thin,
meaning that the radius of hydraulic influence of each well becomes much smaller, enabling
greater opportunities for flow bypass.
Second, extraction trenches are unlikely to capture enough of the total groundwater flow.
Extraction trenches would need to be built close to the point of discharge on the bluff to capture
flows reaching the seeps and Old Outfall 002. Setting the trenches at the plant is technically
feasible for construction but would allow for additional infiltration and seep and Old Outfall 002
discharge to occur. On the other hand, it is infeasible to effectively construct the extraction trenches
on the steeply sloping terrain of the bluff. Therefore, extraction trenches would not completely
capture the water reaching the seeps and Old Outfall 002.
In a remedy feasibility evaluation process, if two or more proposed remedies achieve the same
desired results, but one at a lower cost, the lesser cost solution can be chosen based on qualified
engineering judgement. Because of the need for many extraction wells or a large capture trench,
both of the remedies described above will have a higher construction cost than the proposed flow
through cells or French drains for the seeps or the Old Outfall 002 capture and treat system.
Therefore, extracting groundwater before it reaches Seeps A – D or Old Outfall 002 is unwarranted
since equally effective proposed seep and Old Outfall 002 remedies can be implemented.
Additional Interim Groundwater Extraction Wells
Additional interim groundwater extraction wells will compromise the ability to expeditiously
implement the long-term groundwater remedy and provide minimal additional benefit. The “Install
new Black Creek Extraction Wells (Interim)” alternative on p. 60 of the Supplemental Information
Report (Geosyntec, 2019a) described installing seven additional Black Creek Aquifer wells on an
interim basis in and near the plant area at the Site to provide an estimated 70 gallons per minute of
groundwater extraction. This extraction rate will not meaningfully reduce loadings to the Cape
Fear River. The results of a modeling simulation provided as Appendix H of the CAP (Geosyntec,
2019c) showed that if extraction wells were installed at the plant along with a barrier wall by the
river, upwards of 30 wells would be required. These wells would reduce the flow of upwelling
groundwater to the Cape Fear River by about 1,000 gallons per minute, approximately 65% of the
volume of water reaching the river. By contrast, seven interim wells withdrawing a total of 70
gallons per minute of groundwater and lacking a barrier wall would achieve much less reductions
to river loadings.
Response to Cape Fear River Watch Comments 31 January 2020
Page 12
Responses to CFRW P12 Supplemental Report-final
For interim extraction wells to meaningfully reduce groundwater loadings they would need to be
placed in greater numbers and positioned at the base of the bluff adjacent to the Cape Fear River.
This increase in numbers and placement position would compromise the ability to expeditiously
implement the long-term groundwater remedy. These interim wells and their associated piping and
power needs would create obstructions and logistical challenges for construction.
Extracting additional groundwater reaching Willis Creek is infeasible
Willis Creek PFAS loadings will be reduced by the long-term groundwater remedy and other
actions being taken under the proposed corrective actions. Installing interim wells adjacent to
Willis Creek is unwarranted and extending the potential length of the long-term remedy is
economically infeasible.
Willis Creek runs adjacent to the Site for approximately 1.5 miles from North Carolina Highway
87 to where the creek empties into the Cape Fear River. Willis Creek gains approximately 14% of
its total Table 3+ PFAS mass loading in the first mile adjacent to the Site starting from the highway
and going towards the river. Willis Creek then gains approximately 70% of its total Table 3+ PFAS
mass loadings for the last half mile before the creek empties into the Cape Fear River1. The
groundwater remedy described in the CAP, a barrier wall with groundwater extraction, is estimated
to potentially reduce the estimated 70% of loadings reaching Willis Creek.
Extending a groundwater hydraulic containment remedy to reach NC Highway 87 is economically
infeasible. The additional benefit of extending the remedy would be at most a 14% reduction of
loadings to Willis Creek. Willis Creek total Table 3+ PFAS loadings have been estimated to range
between 3% to 10% of the loads in the Cape Fear River. This means that extending the Willis
Creek remedy would contribute between 0.42% and 1.4% additional loading reductions to the
Cape Fear River. Meanwhile the cost of extending the groundwater remedy an additional mile to
encompass the distance from sampling point WC2 to Highway 87 is estimated to be $30,400,000
(with +50% / -30% ranges of $45,600,00 and $21,300,000). A cost of $30,400,000 divided by a
Cape Fear River loading reduction of between 0.4% and 1.4% produces a cost of $22 million to
$76 million per percentage river reduction. This cost is economically infeasible for the reduction
achieved. Supporting costs for this are provided in Attachment B.
1 Data collected from five sampling locations in Willis Creek in February 2019 were used to calculate these loading values (see Seeps and Creeks Investigation Report (Geosyntec, 2019f)). Samples started at the creek mouth, Location
WC1, and ended at Location WC5 near NC Highway 87. The value of 14% total Table 3+ PFAS loadings coming from the mile of the creek adjacent to the site from NC Highway 87 towards the river was calculated as the
concentration at location WC2 (680 ng/L) minus the concentration at WC5 (370 ng/L) all divided by the concentration at WC1 (2,220 ng/L). The value of 70% of total Table 3+ PFAS loading coming from the half mile just before the river was calculated as the concentration at location WC1 (2,220 ng/L) minus the concentration at WC2 (680 ng/L), all divided by the concentration at WC1 (2,220 ng/L).
Response to Cape Fear River Watch Comments 31 January 2020
Page 13
Responses to CFRW P12 Supplemental Report-final
Last, adding interim wells adjacent to Willis Creek is not recommended. As described previously,
interim wells, their piping and power supply will interfere with the expeditious implementation of
the long-term groundwater remedy, which will achieve meaningful mass loading reductions.
Meanwhile, interim extraction wells will be far less effective and hamper the implementation of
the long-term remedy. Therefore, interim groundwater extraction wells for Willis Creek are
considered to be unwarranted.
Extracting groundwater from the Site reaching Georgia Branch Creek is infeasible
Georgia Branch Creek is entirely offsite and is groundwater fed. Concentrations are relatively
uniform along the creek, therefore loadings are also assumed to be relatively uniform across the
creek. Assuming relatively uniform loadings is also supported by the air deposition signature of
PFAS in Georgia Branch Creek. Air deposition PFAS are not spatially clustered and concentrated
like process water PFAS release signatures but are relatively evenly distributed in concentration
on and offsite (Geosyntec, 2019e).
Georgia Branch Creek runs adjacent to the Site within 100 to 700 feet for approximately 2 miles
between well SMW-01 where the Site has an intersection with NC Highway 87 to where the
Southern Boundary of the Site intersects Glengerry Road. This 2-mile reach of Georgia Branch
Creek represents approximately 25% of the length of Georgia Branch Creek and its tributaries. A
groundwater remedy implemented here would limit discharge from only one side of the creek, and
therefore would reduce loadings by 13%.
Georgia Branch Creek total Table 3+ PFAS loadings have been estimated to range between 2% to
4% of the loads in the Cape Fear River. This means that extracting groundwater from the Site
reaching Georgia Branch Creek between well SMW-01 and Glengerry Road would contribute
between 0.26% and 0.52% additional loading reductions to the Cape Fear River. Meanwhile the
cost of extending this groundwater extraction remedy is estimated to be $43,300,000 (with +50%
/ -30% ranges of $65,000,00 and $30,300,000). A cost of $43,300,000 divided by a Cape Fear
River loading reduction of between 0.26% and 0.52% produces a cost of $83 million to $166
million per percentage river reduction. This cost is economically infeasible for the reduction
achieved. Supporting costs for this are provided in Attachment B.
6. CLARIFICATION REGARDING FEASIBILITY
CFRW’s comments incorrectly state that the supplemental report, “[assumes] that less than $10
million per percentage reduction of loading to the Cape Fear is economically feasible”. The remedy
selection process outlined in the supplemental report identifies that in Step 1 of the process, initial
screening, remedies with a score of 5 (i.e., greater than $10 million per percentage loading of total
Table 3+ reduction to the Cape Fear River) were removed from the selection process. However,
Response to Cape Fear River Watch Comments 31 January 2020
Page 14
Responses to CFRW P12 Supplemental Report-final
remedies can still be determined to be economically infeasible if they would cost less than $10
million per percentage loading reduction in this process. Beyond that, as shown above, the options
not recommended consistently have costs per percentage reduction substantially in excess of $10
million.
CFRW stated that feasibility should not be assessed on a per-pathway basis. Because Geosyntec
has identified potential treatment options on a per-pathway basis, it has also assessed the feasibility
of those options on a per-pathway basis, while also looking holistically to meet overall loading
reduction objectives specified in the Consent Order.
7. RESPONSES TO OTHER COMMENTS OR QUESTIONS
CFRW requested information about the timespan for the thermal oxidizer and other air abatement
controls to produce reductions in PFAS in surface waters. The air abatement controls are expected
to result in a 99% reduction of PFAS emissions to air. Over a multi-year timeframe, these air
reductions will result in lower groundwater and surface water concentrations.
CFRW requested a copy of the groundwater model. Geosyntec will provide the model by March
30,2020. A functional description of the model will be developed to be provided with the model
files. Since completing the CAP, the modeling team is in the process of updating the model to
perform detailed remedy design simulations using transient groundwater solutions.
CFRW requested additional details on the ratings assigned to each remedy. These descriptions are
provided in Attachment C.
CFRW requested that Cost-Benefit Analysis figures (Figures 21 and 22) of the Supplemental
Information Report show values for all alternatives considered. Plotting all alternatives considered
would not be appropriate since reductions from certain pathways would be double- counted since
the reductions plotted on the y-axis are a cumulative sum. In other words, plotting all alternatives
together on this graph would produce estimated river reductions greater than 100%. Instead, the
most feasible alternatives to reduce loadings per pathway were plotted. Additionally, CFRW
expressed confusion about which remedies were proposed for the Site. The CAP submitted to DEQ
describes the set of remedies considered for the Site.
CFRW requested clarification on what reductions can be achieved, for targeted stormwater control
and groundwater intrusion mitigation. The Mass Loading Model (Attachment 1 to the Reduction
Plan) estimated total Table 3+ mass loading contributions to the Cape Fear River from each
potential transport pathway. Outfall 002 was estimated to contribute 3.6% and 7.2% of the total
loading to the river, based on data from the May 2019 and June 2019 sampling events, respectively
(these values were rounded to 4% and 7% for presentation in the table). The average between the
two events was calculated to be 5.5%. The estimate that targeted stormwater control would achieve
Response to Cape Fear River Watch Comments 31 January 2020
Page 15
Responses to CFRW P12 Supplemental Report-final
a 1.7% reduction to the river (stated on page 63) used the averaged Outfall 002 loading to the Cape
Fear River estimate of 5.5%. The 1.3% reduction estimate (stated on page 77) used an incorrect
value for the Outfall 002 loading to the Cape Fear River.
The discrepancy in reduction estimates for groundwater intrusion mitigation resulted from using
rounded numbers. Using the estimates of Outfall 002 loading to the Cape Fear River of 3.6% and
7.2% (based on the May and June 2019 sampling events, respectively), groundwater intrusion
mitigation is expected to achieve between 0.5% and 0.9% loading reductions to the river.
ATTACHMENTS
Attachment A: River Baseline Calculation Methodology
Attachment B: Remedy Costing
Attachment C: Remedy Scoring Table Narrative
REFERENCES
Geosyntec, 2019a. Cape Fear River PFAS Loading Reduction Plan – Supplemental Information
Report. Chemours Fayetteville Works. 4 November 2019.
Geosyntec, 2019b. Cape Fear River PFAS Loading Reduction Plan. Chemours Fayetteville Works.
26 August 2019.
Geosyntec, 2019c. Corrective Action Plan. Chemours Fayetteville Works. 31 December 2019.
Geosyntec, 2019d. Characterization of PFAS in Process and Non-Process Wastewater and
Stormwater; Quarterly Report #3. Chemours Fayetteville Works. 31 January 2019.
Geosyntec, 2019e. On and Offsite Assessment (Version 2). October 31, 2019.
Geosyntec, 2019f. Seeps and Creeks Investigation Report. Chemours Fayetteville Works. 26
August 2019.
NCDEQ, 2019. Letter to Brian Long, Chemours. Re: Cape Fear River PFAS Loading Reduction
Plan - Supplemental Information Report. 19 December 2019.
Southern Environmental Law Center, 2019. Letter to Joel Gross, Arnold & Porter. Re: Cape Fear
River Watch Comments and Questions on Chemours Cape Fear River PFAS Loading
Reduction Plan – Supplemental Information Report. December 19, 2019.
*****
Responses to CFRW P12 Supplemental Report
ATTACHMENT A
River Baseline Calculation Methodology
Geosyntec Consultants of NC P.C.
Attachment A River Baseline Calculation Methodology
Attachment A – River Baseline Calculation Methodology
Chemours Fayetteville Works
Recommended Mass Loading Baseline Calculation Formula
Geosyntec proposes that the mass load of total Table 3+ compounds in the Cape Fear River be
calculated using Equation 1 shown below:
Equation 1 – Total Table 3+ Baseline Mass Loading
𝑀𝑇𝑇3ிோ ൌ 𝑚ிோ െ𝑚ோௗ௦
𝑀𝑇𝑇3ிோ ൌ 𝑐ிோ,,𝑄ிோ,
ୀଶ
ୀଵ
െ𝑚ோௗ௦
Where
𝑀𝑇𝑇3ிோ = is the total baseline mass load of the twenty Table 3+ PFAS compounds either in
the Cape Fear River, or diverted from the Cape Fear River by applied remedies;
𝑚ிோ = is the total Table 3+ PFAS mass load measured from samples taken in the Cape Fear
River downstream of the Site where the river is well mixed;
𝑚ோௗ௦ = is the total Table 3+ PFAS mass load prevented from reaching the Cape Fear
River by remedies implemented by Chemours;
n = is the number of Cape Fear River samples collected in a monitoring period (e.g. annual) to
calculate mass loading in the Cape Fear River, e.g., given no complications during sample
collection, then total samples in an annual period would be, n = 365/3.5 = 105;
j = is the number of Table 3+ PFAS compounds (twenty) being summed to determine the total
Table 3+ PFAS concentration in the sample;
𝑐ிோ,, = is the concentration of Table 3+ PFAS in a composite water sample collected from
the Cape Fear River; and
𝑄ிோ, = is the volume of Cape Fear River water that flowed past the sampling point while the
composite sample was being collected.
Responses to CFRW P12 Supplemental Report
ATTACHMENT B
Remedy Costing
Rough Order of Magnitude Cost Estimate for Groundwater Capture Impacting Willis Creek
Chemours Fayetteville Works, North Carolina
Basis of Cost Estimate (Scope and Assumptions) for Willis Creek (WC) Groundwater Remedy:
Hydraulic containment along 5,280 linear feet of WC reach that is impacted by aerial deposition signature PFAS.
The portion of the Black Creek aquifer groundwater (process water signature) that is discharging to WC is covered in other cost estimates.
The discharging aquifer is the surficial aquifer in this area (in contrast with process water signature onsite groundwater).
This remedy scenario assumes groundwater capture only.
It is assumed that extraction wells will be spaced 100 feet apart and pumping rates will on average be 10 gpm.
A total of 54 wells and 540 gpm (0.8 MGD) would be required for hydraulic containment.
It would not be practical to convey this much flow to the OOF2 system location. A new standalone system would be required.
The average PMPA and PFMOAA concentration of the extracted groundwater is estimated to be 1,100 and 550 ng/L, respectively.
Wells will convey groundwater under pressure to the system, with basic heat tracing (no prefabricated building).
Piping will be HDPE and trenches will be approximately 3 feet deep, and reuse of excavated soils as backfill will be permitted.
HDPE pipe sizes range from 2 to 18 inch diameter SDR 11.
Treated groundwater will be discharged to the WC.
Includes a 20‐year net present value cost with a 3.5% discount factor applied.
Item Qty Unit Unit Cost Total Notes
Construction Costs
Drilling Costs
Driller mobilization 1LS 10,000$ 10,000$ Engineer's Estimate
Extraction Wells drilling and well installation (no appurtenances)1,620 LF 225$ 364,500$ Engineer's Estimate
Aquifer pump testing on 25% of extraction wells 14 EA 15,000$ 202,500$ Engineer's Estimate
Monitoring Wells drilling and installation 540 LF 75$ 40,500$ Engineer's Estimate
IDW 2,160 LF 10$ 21,600$ Engineer's Estimate
Drilling Subtotal 639,100$
Site Work Costs
HDPE SDR 11 ‐ 2"180 LF 1.35$ 243$ Engineer's Estimate
HDPE SDR 11 ‐ 3"250 LF 2.35$ 588$ Engineer's Estimate
HDPE SDR 11 ‐ 4"500 LF 3.90$ 1,949$ Engineer's Estimate
HDPE SDR 11 ‐ 6"500 LF 8.43$ 4,213$ Engineer's Estimate
HDPE SDR 11 ‐ 8"600 LF 14.28$ 8,568$ Engineer's Estimate
HDPE SDR 11 ‐ 10"600 LF 22.18$ 13,307$ Engineer's Estimate
HDPE SDR 11 ‐ 12"750 LF 31.20$ 23,400$ Engineer's Estimate
HDPE SDR 11 ‐ 14"900 LF 37.61$ 33,853$ Engineer's Estimate
HDPE SDR 11 ‐ 16"600 LF 49.07$ 29,445$ Engineer's Estimate
HDPE SDR 11 ‐ 18"400 LF 62.17$ 24,870$ Engineer's Estimate
HDPE fusing and fittings 1LS 2,500.00$ 2,500$ Engineer's Estimate
3'x3'x3' Well Vault + H20‐Rated Lid (4.5x4.5x4.5)54 ea 12,993.00$ 701,622$ Engineer's Estimate
Flow Meters, Level and Pressure Transmitters 54 ea 1,603.00$ 86,562$ Engineer's Estimate
Grundfos 3" 15SQ05‐110‐240V Submersible Pump, fittings, appurtenances 54 ea 2,190.58$ 118,292$ Engineer's Estimate
Power poles, hardware, guy wires, excavation, wiring, transformers 5ea 30,639.71$ 153,199$ Engineer's Estimate
Local control panels 54 ea 5,000.00$ 270,000$ Engineer's Estimate
Utility Connection to System 1ea 100,000.00$ 100,000$ Engineer's Estimate
Subcontractor Installation Costs‐Piping 2"‐6"1,430 LF 75.00$ 107,250$ Engineer's Estimate
Subcontractor Installation Costs‐Piping 8"‐14"2,850 LF 100.00$ 285,000$ Engineer's Estimate
Subcontractor Installation Costs‐Piping 16"‐18"1,000 LF 125.00$ 125,000$ Engineer's Estimate
Subcontractor Installation Costs‐Well Vault 54 ea 5,000.00$ 270,000$ Engineer's Estimate
Subcontractor Installation Costs‐Electrical 1LS 240,000.00$ 240,000$ Engineer's Estimate
Subcontractor mobilization 5%of 2,599,859$ 129,993$ Engineer's Estimate
Site Work Subtotal 2,729,852$
Page 1 of 2 January 2020
Rough Order of Magnitude Cost Estimate for Groundwater Capture Impacting Willis Creek
Chemours Fayetteville Works, North Carolina
540 GPM (0.8 MGD) Treatment Plant Cost
Land clearing and site prep for new system 500,000$ 500,000$ Parsons
Influent & Effluent Handling, includes lift stations, EQ tanks, feed forward
pumps, discharge pumps 147,600$ 147,600$ Parsons
Multi Media Filtration, includes skids and backwash pumps 238,320$ 238,320$ Parsons
Granular Activated Carbon, includes skid, water suppy tank, backwash
waste tank, backwash pumps 892,080$ 892,080$ Parsons
Solids Handling and Chemical Precipitation, includes feed pumps, clarifiers,
sludge pumps, filter press, chemicals 773,280$ 773,280$ Parsons
Enclosures and Heat Tracing 309,600$ 309,600$ Parsons
Installation Cost (Construction, Site Preparation, Civil, Structural)70% of 2,051,280$ 1,500,000$ Parsons
Anciliary Cost (I&C, Piping‐Mechanical & Electrical)30% of $ 3,860,880 1,158,264$ Parsons
0.8 MGD Treatment Plant Subtotal 5,519,144$
Total Construction Costs 8,888,096$
Professional Services Costs
Modeling, Design, Work Planning, and Permitting 10%of 8,888,096$ 888,810$ adapted from EPA Guidance
Construction Oversight 10%of 8,888,096$ 888,810$ adapted from EPA Guidance
Project Management 8%of 8,888,096$ 711,048$ adapted from EPA Guidance
Professional Services Subtotal 2,488,667$
Contingency 30%of 11,376,762$ 3,413,029$
Construction Cost 14,800,000$
+50%22,200,000$
‐30%10,360,000$
Annual Operations & Maintenance Costs
Electricity ‐ Field Equipment 1LS 40,000$ 40,000$ Engineer's Estimate
Electricity ‐ Treatment Systems 1LS 16,704$ 16,704$ Parsons
GAC Usage & Replacement 1LS 432,000$ 432,000$ Parsons
Chemicals for treatment (Acid, Caustic, Ferric, Polymer)1LS 19,440$ 19,440$ Parsons
Solids Disposal 1LS 18,000$ 18,000$ Parsons
Sampling & Analytical 1LS 38,160$ 38,160$ Parsons
Operational Labor 1LS 324,000$ 324,000$ Parsons
Equipment Maintenance 1LS 170,640$ 170,640$ Parsons
Annual O&M Subtotal 1,058,944$
Annual Cost 1,100,000$
+50%1,588,416$
‐30%741,261$
Years 20
Discount Rate 3.5%
Net Present Value (NPV) of Annual Costs over 20 Years 15,600,000$
+50%23,400,000$
‐30%10,920,000$
Total Cost ‐ Construction and Annual O&M
Total: Construction + NPV of Annual Costs over 20 Years 30,400,000$
+50%45,600,000$
‐30%21,280,000$
Costs are rough order of magnitude estimates, and assumed to represent the actual installed cost within a range of ‐30%/ +50% of the value
indicated above. The estimates have been prepared for guidance in project evaluation and implementation from the information available at the
time of the estimate. The final costs of the project will depend on final approved design, actual labor and material costs, and competitive variable
factors. These estimates are not intended for budgetary or future planning purposes; they have been prepared to facilitate an inter‐remedial
alternative comparison.
Process Package
Process Package
Process Package
Process Package
Process Package
Process Package
Page 2 of 2 January 2020
Rough Order of Magnitude Cost Estimate for Groundwater Capture Impacting Georgia Branch Creek
Chemours Fayetteville Works, North Carolina
Basis of Cost Estimate (Scope and Assumptions) for Georgia Branch Creek (GBC) Groundwater Remedy:
Hydraulic containment along 10,850 linear feet of GBC reach that is impacted by aerial deposition signature PFAS.
The discharging aquifer is the surficial aquifer in this area (in contrast with process water signature onsite groundwater).
This remedy scenario assumes groundwater capture only.
It is assumed that extraction wells will be spaced 200 feet apart and pumping rates will on average be 15 gpm.
A total of 54 wells and 810 gpm (1.2 MGD) would be required for hydraulic containment.
It would not be practical to convey this much flow to the OOF2 system location. A new standalone system would be required.
The average PMPA and PFMOAA concentration of the extracted groundwater is estimated to be 1,450 and 310 ng/L, respectively.
Wells will convey groundwater under pressure to the system, with basic heat tracing (no prefabricated building).
Piping will be HDPE and trenches will be approximately 3 feet deep, and reuse of excavated soils as backfill will be permitted. HDPE
pipe sizes range from 2 to 18 inch diameter SDR 11.
Treated groundwater will be discharged to the GBC.
Includes a 20‐year net present value cost with a 3.5% discount factor applied.
Item Qty Unit Unit Cost Total Notes
Construction Costs
Drilling Costs
Driller mobilization 1LS 10,000$ 10,000$ Engineer's Estimate
Extraction Wells drilling and well installation (no appurtenances)1,620 LF 225$ 364,500$ Engineer's Estimate
Aquifer pump testing on 25% of extraction wells 14 EA 15,000$ 202,500$ Engineer's Estimate
Monitoring Wells drilling and installation 540 LF 75$ 40,500$ Engineer's Estimate
IDW 2,160 LF 10$ 21,600$ Engineer's Estimate
Drilling Subtotal 639,100$
Site Work Costs
HDPE SDR 11 ‐ 2"500 LF 1.35$ 674$ Engineer's Estimate
HDPE SDR 11 ‐ 3"600 LF 2.35$ 1,410$ Engineer's Estimate
HDPE SDR 11 ‐ 4"750 LF 3.90$ 2,924$ Engineer's Estimate
HDPE SDR 11 ‐ 6"800 LF 8.43$ 6,741$ Engineer's Estimate
HDPE SDR 11 ‐ 8"1,000 LF 14.28$ 14,280$ Engineer's Estimate
HDPE SDR 11 ‐ 10"1,000 LF 22.18$ 22,178$ Engineer's Estimate
HDPE SDR 11 ‐ 12"1,000 LF 31.20$ 31,200$ Engineer's Estimate
HDPE SDR 11 ‐ 14"2,000 LF 37.61$ 75,230$ Engineer's Estimate
HDPE SDR 11 ‐ 16"1,700 LF 49.07$ 83,427$ Engineer's Estimate
HDPE SDR 11 ‐ 18"1,500 LF 62.17$ 93,262$ Engineer's Estimate
HDPE fusing and fittings 1LS 2,500.00$ 2,500$ Engineer's Estimate
3'x3'x3' Well Vault + H20‐Rated Lid (4.5x4.5x4.5)54 ea 12,993.00$ 701,622$ Engineer's Estimate
Flow Meters, Level and Pressure Transmitters 54 ea 1,603.00$ 86,562$ Engineer's Estimate
Grundfos 3" 15SQ05‐110‐240V Submersible Pump, fittings, appurtenances 54 ea 2,190.58$ 118,292$ Engineer's Estimate
Power poles, hardware, guy wires, excavation, wiring, transformers 10 ea 30,639.71$ 306,397$ Engineer's Estimate
Local control panels 54 ea 5,000.00$ 270,000$ Engineer's Estimate
Utility Connection to System 1ea 120,000.00$ 120,000$ Engineer's Estimate
Subcontractor Installation Costs‐Piping 2"‐6"2,650 LF 75.00$ 198,750$ Engineer's Estimate
Subcontractor Installation Costs‐Piping 8"‐14"5,000 LF 100.00$ 500,000$ Engineer's Estimate
Subcontractor Installation Costs‐Piping 16"‐18"3,200 LF 125.00$ 400,000$ Engineer's Estimate
Subcontractor Installation Costs‐Well Vault 54 ea 5,000.00$ 270,000$ Engineer's Estimate
Subcontractor Installation Costs‐Electrical 1LS 270,000.00$ 270,000$ Engineer's Estimate
Subcontractor mobilization 5%of 3,575,447$ 178,772$ Engineer's Estimate
Site Work Subtotal 3,754,219$
Page 1 of 2 January 2020
Rough Order of Magnitude Cost Estimate for Groundwater Capture Impacting Georgia Branch Creek
Chemours Fayetteville Works, North Carolina
810 GPM (1.2 MGD) Treatment Plant Cost
Land clearing and site prep for new system 500,000$ 500,000$ Parsons
Influent & Effluent Handling, includes lift stations, EQ tanks, feed forward
pumps, discharge pumps 221,400$ 221,400$ Parsons
Multi Media Filtration, includes skids and backwash pumps 357,480$ 357,480$ Parsons
Granular Activated Carbon, includes skid, water suppy tank, backwash
waste tank, backwash pumps 1,338,120$ 1,338,120$ Parsons
Solids Handling and Chemical Precipitation, includes feed pumps, clarifiers,
sludge pumps, filter press, chemicals 1,159,920$ 1,159,920$ Parsons
Enclosures and Heat Tracing 464,400$ 464,400$ Parsons
Installation Cost (Construction, Site Preparation, Civil, Structural)70% of 3,076,920$ 2,200,000$ Parsons
Anciliary Cost (I&C, Piping‐Mechanical & Electrical)30% of $ 5,741,320 1,722,396$ Parsons
1.2 MGD Treatment Plant Subtotal 7,963,716$
Total Construction Costs 12,357,035$
Professional Services Costs
Modeling, Design, Work Planning, and Permitting 10%of 12,357,035$ 1,235,704$ adapted from EPA Guidance
Construction Oversight 10%of 12,357,035$ 1,235,704$ adapted from EPA Guidance
Project Management 8%of 12,357,035$ 988,563$ adapted from EPA Guidance
Professional Services Subtotal 3,459,970$
Contingency 30%of 15,817,005$ 4,745,101$
Construction Cost 20,600,000$
+50%30,900,000$
‐30%14,420,000$
Annual Operations & Maintenance Costs
Electricity ‐ Field Equipment 1LS 56,000$ 56,000$ Engineer's Estimate
Electricity ‐ Treatment Systems 1LS 25,056$ 25,056$ Parsons
GAC Usage & Replacement 1LS 648,000$ 648,000$ Parsons
Chemicals for treatment (Acid, Caustic, Ferric, Polymer)1LS 29,160$ 29,160$ Parsons
Solids Disposal 1LS 27,000$ 27,000$ Parsons
Sampling & Analytical 1LS 57,240$ 57,240$ Parsons
Operational Labor 1LS 486,000$ 486,000$ Parsons
Equipment Maintenance 1LS 255,960$ 255,960$ Parsons
Annual O&M Subtotal 1,584,416$
Annual Cost 1,600,000$
+50%2,376,624$
‐30%1,109,091$
Years 20
Discount Rate 3.5%
Net Present Value (NPV) of Annual Costs over 20 Years 22,700,000$
+50%34,050,000$
‐30%15,890,000$
Total Cost ‐ Construction and Annual O&M
Total: Construction + NPV of Annual Costs over 20 Years 43,300,000$
+50%64,950,000$
‐30%30,310,000$
Process Package
Costs are rough order of magnitude estimates, and assumed to represent the actual installed cost within a range of ‐30%/ +50% of the value
indicated above. The estimates have been prepared for guidance in project evaluation and implementation from the information available at the
time of the estimate. The final costs of the project will depend on final approved design, actual labor and material costs, and competitive variable
factors. These estimates are not intended for budgetary or future planning purposes; they have been prepared to facilitate an inter‐remedial
alternative comparison.
Process Package
Process Package
Process Package
Process Package
Process Package
Page 2 of 2 January 2020
Responses to CFRW P12 Supplemental Report
ATTACHMENT C
Remedy Scoring Table Narrative
Geosyntec Consultants of NC P.C.
Response to CFRW Supplemental Information Report Comments 1
Attachment C – Remedy Scoring Table Narratives Chemours Fayetteville Works
The Supplemental Information Report (Geosyntec 2019) contained details on the ranking of
alternatives. This section is presented below. Following this a remedy scoring table summary is
provided.
2.3 Compare Remedial Alternatives
Remedies can be assessed and scored for the following criteria:
i. Environmental Protection (i.e. reduction of PFAS Mass Loading);
ii. Adverse Environmental Effects;
iii. Technical Feasibility;
iv. Timing (i.e., 2 years or 5 years); and
v. Economic Feasibility (i.e., reduction achieved per relative cost expended).
These criteria recognize the adverse impacts may result during remediation and that selected
alternatives must be both technologically and economically feasible. The following sub-sections
describe each assessment criteria and how it was scored on a scale of 1 to 5 where 1 was the most
favorable score and 5 the least favorable score.
2.4 Assessment Criteria 1 – Environmental Protection
Remedial alternatives were assessed to establish the expected degree of loading reduction they
would provide to the Cape Fear River, Willis Creek, Georgia Branch Creek, and Outfall 002. For
each waterbody based on professional engineering and scientific judgement and analyses of the
alternatives presented in this Supplemental Report, the alternatives were assigned scores as
follows:
Total Table 3+ PFAS Mass Loading Reductions to Surface Water Body
Scoring
>20% 1
>10 - 20% 2
>5 - 10% 3
>2 - 5% 4
0 - 2% 5
Geosyntec Consultants of NC P.C.
Response to CFRW Supplemental Information Report Comments 2
2.5 Assessment Criteria 2 – Adverse Environmental Effects
Remedial alternatives were assessed to establish the potential degree of adverse environmental
effects they might cause (e.g. habitat destruction). Based on professional engineering and scientific
judgement and analyses of the alternatives presented in this Supplemental Report were assigned
scores as follows:
Adverse Environmental Effect Scoring
No anticipated local effect 1
Some destruction of local habitat 2
Some alteration to local waterbody 3
Habitat destruction or
alteration over a large extent 4
Extensive destruction of habitat type or waterbody 5
2.6 Assessment Criteria 3 – Technical Feasibility
Remedial alternatives were assessed to establish their potential technical feasibility. Based on
professional engineering and scientific judgement and analyses of the alternatives presented in this
Supplemental Report were assigned scores as follows:
Technical Feasibility Criteria Scoring
Simple to Implement 1
Some Challenges, Success Fairly Certain 2
Complex or Large, Some Uncertainty about Degree of Success 3
Complex, Large, Access Issues,
Success Potentially Possible 4
Complex, Large, Access Issues, Success Unlikely 5
Geosyntec Consultants of NC P.C.
Response to CFRW Supplemental Information Report Comments 3
2.7 Assessment Criteria 4 – Timeframe
Remedial alternatives were assessed to establish the timeframes in which they could be
implemented. Based on professional engineering and scientific judgement and analyses of the
alternatives presented in this Supplemental Report were assigned scores as follows:
Time To Implement Scoring
Up to 1 year 1
From 1 to 2 years 2
>2 - 3 years 3
>3 - 5 years 4
> 5 years 5
2.8 Assessment Criteria 5 – Economic Feasibility
Remedial alternatives were assessed to establish their economic feasibility, where feasibility was
established using the metric of cost in millions of dollars per reduction of one percent of Total
Table 3+ PFAS Loading to the Cape Fear River. Based on the reductions to the Cape Fear River
for each alternative and the estimated costs of each were assigned scores as follows:
Cost (Millions of Dollars) to achieve a 1% Reduction in Cape Fear River Total Table 3+ PFAS Loading
Scoring
$0 - $1M 1
>$1M - $2.5M 2
>$2.5M - $5M 3
>$5M - $10M 4
>$10M 5
2.9 Selection Process
Chemours is committed to taking actions to achieve expedited loading reduction for groundwater
seeps and onsite groundwater, and the feasibility of each is evaluated in this Supplemental Report.
The remedial alternatives for these pathways are still undergoing a final remedy selection process,
as the technical evaluation of these options is in progress as described in Sections 5 and 6 (see
Supplemental Information Report, Geosyntec 2019).
For remedies considered as part of the Reduction Plan (Geosyntec 2019a), selection is advanced
herein as follows:
Geosyntec Consultants of NC P.C.
Response to CFRW Supplemental Information Report Comments 4
• Step 1: Initial screening
• Step 2: Selection of several viable remedial alternatives per pathway
In Step 1, alternatives with scores of 5, the least favorable score, for criteria 2, 3 and 5 (adverse
impacts, technical feasibility and economic feasibility) were removed from the selection process.
Criteria Action
1 – Achieves Reductions All remedies regardless of scores are advanced
2 – Adverse Impacts Remedies with a score of 5 are removed from selection process
3 – Technical Feasibility Remedies with a score of 5 are removed from selection process
4 – Implementation Timing All remedies regardless of scores are advanced
5 – Economic Feasibility Remedies with a score of 5 are removed from selection process
If a proposed remedial alternative would cause severe adverse environmental impacts, it was not
advanced as the purpose of remediation is to protect human health and improve environmental
quality. If a remedy was infeasible, in other words if it was scored as 5, it was not advanced as it
would not be implementable. If two proposed alternatives effectively achieved the same goals, the
lower cost remedy was advanced. If a remedy was economically infeasible, i.e. it did not provide
benefit that was commensurate with the cost to implement the remedy, it was not advanced for
consideration. In Step 2, remedies were selected for further evaluation after balancing perspectives
from all criteria presented here, comparison against remedial objectives and using professional
engineering and scientific judgement.
Ultimately, those remedial options selected to advance will require further evaluation in the
context of how the remedy integrates into the longer-term remedial approach. The additional
evaluation includes groundwater flow modeling and the empirical studies currently underway.
Geosyntec Consultants of NC P.C. Remedy Scoring Table Summary
Chemours Fayetteville Works
Response to CFRW Supplemental Information Report Comments 5
Pathway Remedial Alternative Reductions to the Cape Fear River Rank Adverse Environmental Effects Technology Feasibility Time Cost per Loading Removal Direct Aerial Deposition Air Abatement
Controls
Air abatement consists of less than 2% of loadings to the Cape
Fear River.
5
Air abatement controls are all
being constructed in the built area of the facility causing limited local impacts. Additional emissions of
greenhouse gases from
granular activated carbon (GAC) and natural gas usage are not considered in this scoring.
1
The air abatement controls, particularly the Thermal Oxidizer,
are large capital projects executed
on an extremely rapid timeline.
3
The Thermal Oxidizer and other air abatement controls have been
implemented between 2018 and 2019.
1
Cost per loading removal was not scored because air abatement controls were not considered or installed
to reduce total Table 3+ PFAS loading to the Cape Fear River.
Old Outfall 002 Capture and Treat Old Outfall 002
The Old Outfall 002 has been estimated to contribute between 23% and 29% of total Table 3+ PFAS loading to the Cape Fear
River.
1
Capturing and treating the
Old Outfall 002 requires cutting down acres of forested area, placing a structure in a stream, and
dramatically reducing flow in
a portion of the stream.
3
Using GAC to treat PFAS is an established method, but the system must be installed in a flowing stream.
3
The Old Outfall system will be operational by September 2020 pending necessary
permits/approvals.
2 The estimated price per percentage loading reduction was $1,700,000. 2 Seeps Flow Through Cells
-
CFR Seeps A, B, C & D - Interim
Remedy reduction scores were not assigned for interim remedies
at the time of remedy
development in the Supplemental Information Report.
NA
Installing the flow through cells and French drains would require installing
infrastructure in the seep
streams and also require access roads through the forested area.
2
Long term operation of the flow through cells will require
implementing a relatively long-
lived treatment media and dealing with sedimentation.
3 Remedy is expected to
take 2 years to implement. 2
Percentage loading reductions not estimated
where reductions could not be estimated.
Flow Through Cells -
CFR Seeps A, B, C
& D – Long-Term
Remedy expected to reduce approximately 27% of total Table
3+ PFAS loading to the Cape
Fear River.
1
Installing the flow through cells and French drains would require installing infrastructure in the seep
streams and also require
access roads through the forested area.
2
GAC is a potential material that has been proven to sorb PFAS. Flow through cells will have to manage
GAC contact time, sedimentation
issues and extreme weather events.
2 Remedy is expected to take 2 years to implement. 2 The estimated price per percentage loading
reduction was $450,000.
1 Seeps Flow Through Cells - WC Seeps – Long-
Term
Remedy expected to reduce approximately 0.1% of total Table 3+ PFAS loading to the
Cape Fear River.
5
Installing the flow through cells and French drains would require installing infrastructure in the seep streams and also require
access roads through the forested area.
2
GAC is a potential material that has been proven to sorb PFAS. Flow through cells will have to manage GAC contact time, sedimentation
issues and extreme weather events.
2 Remedy is expected to take 2 years to implement. 2 The estimated price per percentage loading reduction was $1,500,000. 5
Geosyntec Consultants of NC P.C. Remedy Scoring Table Summary
Chemours Fayetteville Works
Response to CFRW Supplemental Information Report Comments 6
Pathway Remedial Alternative Reductions to the Cape Fear River Rank Adverse Environmental Effects Technology Feasibility Time Cost per Loading Removal
Ex Situ Capture and
Treatment - CFR
Seeps A, B, C & D – Interim
Remedy reduction scores were not assigned for interim remedies
since interim remedies
performance is not expected to be as certain as fully designed and piloted long-term remedies.
NA
Installing the flow through cells and French drains would require installing
infrastructure in the seep
streams and also require access roads through the forested area.
2
French drains will have to manage
sedimentation issues and extreme
weather events.
2 Remedy is expected to
take 3 years to implement. 3
Percentage loading reductions not estimated
where reductions could not be estimated.
Ex Situ Capture and Treatment - CFR
Seeps A, B, C & D –
Long-Term
Remedy expected to reduce approximately 27% of total Table
3+ PFAS loading to the Cape
Fear River.
1
Installing the flow through cells and French drains would require installing infrastructure in the seep
streams and also require access roads through the forested area.
1 French drains will have to manage sedimentation issues and extreme
weather events.
2 Remedy is expected to
take 3 years to implement. 3 The estimated price per percentage loading
reduction was $940,000.
1
Plume Stop - CFR Seeps A and B –
Interim
Remedy reduction scores were not assigned for interim remedies since interim remedies performance is not expected to be
as certain as fully designed and piloted long-term remedies.
NA
PlumeStop would require the drilling of wells and then injecting PlumeStop into
wells, a relatively minor
disturbance.
1
Considerable volumes of PlumeStop material are required and PlumeStop is potentially
challenged as a long-lasting remedy
to maintain sequestration of PFAS.
4 Remedy is expected to take 1 year to implement. 1
Percentage loading
reductions not estimated
where reductions could not
be estimated.
Plume Stop - WC Seeps – Long-Term
Remedy expected to reduce
approximately 0.1% of total Table 3+ PFAS loading to the Cape Fear River.
5
PlumeStop would require the
drilling of wells and then injecting PlumeStop into wells, a relatively minor disturbance.
1
Considerable volumes of
PlumeStop material are required and PlumeStop is potentially challenged as a long-lasting remedy to maintain sequestration of PFAS.
3 Remedy is expected to take 1 year to implement. 1 The estimated price per percentage loading reduction was $39,100,000. 5 Onsite Groundwater Extract from Black Creek Monitoring Wells - Interim
Remedy reduction scores were
not assigned for interim remedies since interim remedies performance is not expected to be as certain as fully designed and
piloted long-term remedies.
NA Wells exist and are in the plant area of the Site. 1
The wells can be connected with
piping across the active manufacturing facility and pumped to the Old Outfall 002 treatment system.
2 Remedy is expected to take 1 year to implement. 1
Percentage loading reductions not estimated where reductions could not be estimated.
Install New Black
Creek Extraction Wells - Interim
Remedy reduction scores were not assigned for interim remedies
since interim remedies
performance is not expected to be as certain as fully designed and piloted long-term remedies.
NA Wells would be installed in
the plant area of the Site. 1
The wells can be connected with piping across the active
manufacturing facility and pumped to the Old Outfall 002 treatment system.
2 Remedy is expected to
take 2 years to implement. 2
Percentage loading
reductions not estimated
where reductions could not be estimated.
Groundwater Extraction Remedy expected to reduce approximately 23% of total Table 1 Wells would be installed with ideally minimal disturbance in the forested area adjacent 1 A large number of wells would need to be installed over a long length of river. 3 Remedy is expected to take 5 years to implement. 4 Remedy costs were not available at the time of the
Geosyntec Consultants of NC P.C. Remedy Scoring Table Summary
Chemours Fayetteville Works
Response to CFRW Supplemental Information Report Comments 7
Pathway Remedial Alternative Reductions to the Cape Fear River Rank Adverse Environmental Effects Technology Feasibility Time Cost per Loading Removal
3+ PFAS loading to the Cape Fear River. to the river along the existing access path. Supplemental Information Report preparation.
Groundwater Extraction with Barrier Wall
Remedy expected to reduce approximately 23% of total Table 3+ PFAS loading to the Cape Fear River.
1 The barrier wall would require removing acres of forested cover. 1
A large number of wells would need to be installed over a long length of river along with a barrier wall.
3 Remedy is expected to take 5 years to implement. 4
Remedy costs were not available at the time of the Supplemental Information Report preparation.
Outfall 002 Conveyance Network Sediment Removal
Reductions to the Cape Fear River could not be quantified with the data available in the Supplemental Information Report and the Reductions Plan.
NQ Sediment were removed from existing channels at Site. 1 Areas were easily accessible using common construction equipment. 1 Remedy is expected to take 1 year to implement. 1
Percentage loading reductions not estimated where reductions could not be estimated.
Stormwater
Pollution
Prevention Plan (SWPPP)
Reductions to the Cape Fear River could not be quantified
with the data available in the Supplemental Information Report and the Reductions Plan.
NQ
The plan will be prepared in
office environments and
implemented in the active plant areas at Site.
1
Plan is prepared in the office and likely implementable with common
construction equipment and practices; final assessment will depend on results of SWPPP
1 Remedy is expected to
take 2 years to implement. 2
Percentage loading
reductions not estimated
where reductions could not be estimated.
Targeted Stormwater Control
Remedy expected to reduce approximately 1.7% of total Table 3+ PFAS loading to the Cape Fear River.
5 Targeted stormwater will be implemented in active plant areas at the Site. 1 Targeted stormwater control may require infrastructure to be built in the active plant area. 2 Remedy is expected to take 4 years to implement. 4
Remedy costs were not available at the time of the Supplemental Information Report preparation.
Terracotta Pipe Decommissioning
Remedy expected to reduce approximately 0.1% of total Table 3+ PFAS loading to the
Cape Fear River.
5
Terracotta pipe decommissioning will be implemented in active plant
area at the Site.
1
Terracotta pipe decommissioning will require construction in the plant area to active water
transmission lines.
2 Remedy is expected to take 2 years to implement. 2
Remedy costs were not available at the time of the Supplemental Information
Report preparation.
Groundwater Intrusion Mitigation
Remedy expected to reduce
approximately 0.7% of total Table 3+ PFAS loading to the Cape Fear River.
5
Potentially required
groundwater intrusion
mitigation actions will be implemented in the active plant area at Site.
1
Groundwater intrusion mitigation
may require construction in the plant area to active water release and transmission lines.
2 Remedy is expected to take 3 years to implement. 3
The estimated price per
percentage loading reduction was $100,000. 1
Treat site-wide stormwater at
Outfall 002
Remedy expected to reduce approximately 2.2% of total Table 3+ PFAS loading to the
Cape Fear River.
4
Site-wide stormwater treatment would be implemented in the active
plant areas at Site.
1
Site-wide stormwater treatment would require considerable infrastructure construction, treatment plant construction and
modification to the actively used
conveyance network at Site.
4 Remedy is expected to take 5 years to implement. 4 The estimated price per percentage loading
reduction was $4,500,000.
5
Treat site-wide flows at Outfall 002
Remedy expected to reduce
approximately 4.4% of total Table 3+ PFAS loading to the Cape Fear River.
4
Site-wide Outfall 002 flows
treatment would be implemented in the active plant areas at Site.
1
Treating all site-wide flows at
Outfall 002 would require building a large treatment plant adjacent to the Outfall capable of handling the large volumes of flow.
2 Remedy is expected to take 5 years to implement. 4 The estimated price per percentage loading reduction was $3,900,000. 5
Geosyntec Consultants of NC P.C. Remedy Scoring Table Summary
Chemours Fayetteville Works
Response to CFRW Supplemental Information Report Comments 8
Pathway Remedial Alternative Reductions to the Cape Fear River Rank Adverse Environmental Effects Technology Feasibility Time Cost per Loading Removal Willis and Georgia Branch Creeks Treating all Flows at Willis Creek Mouth
Remedy expected to reduce approximately 7% of total Table 3+ PFAS loading to the Cape Fear River.
3
Requires damming up Willis Creek and capturing these flows, significant alternation to the local habitat.
3
The dam and water capture system
would be subject to extreme weather events; the treatment system would be large and potentially complicated to place at
the mouth were topography is quite
steeply sloped.
3 Remedy is expected to take 5 years to implement. 4 The estimated price per percentage loading reduction was $1,200,000. 5
Treating all Flows at Georgia Branch Creek Mouth
Remedy expected to reduce approximately 3% of total Table 3+ PFAS loading to the Cape Fear River.
4
Requires damming up
Georgia Branch Creek and capturing these flows, significant alternation to the local habitat.
3
The dam and water capture system
would be subject to extreme
weather events; the treatment system would be large and potentially complicated to place at the mouth were topography is quite
steeply sloped.
3 Remedy is expected to take 5 years to implement. 4 The estimated price per percentage loading reduction was $2,400,000. 5
PlumeStop™ along full Willis Creek Length
Remedy expected to reduce approximately 6% of total Table 3+ PFAS loading to the Cape
Fear River.
3
Requires many wells to be installed adjacent to the creek causing periodic disruption for miles along the creek’s
length.
2
Numerous access agreements would need to be arranged, certain
areas would require the construction of access roads, the application of PlumeStop may be heterogeneous in areas, and the PlumeStop remedy would have to
be re-applied periodically as PlumeStop will not permanently degrade, sorb or remove the Table 3+ PFAS reaching the Creek.
5 Remedy is expected to take 9 years to implement. 5 The estimated price per percentage loading reduction was $24,000,000. 5
PlumeStop™ along full Georgia Branch Creek Length
Remedy expected to reduce approximately 3% of total Table 3+ PFAS loading to the Cape Fear River.
4
Requires many wells to be installed adjacent to the creek causing periodic disruption for miles along the creek’s length.
2
Numerous access agreements would need to be arranged, certain
areas would require the
construction of access roads, the application of PlumeStop may be heterogeneous in areas, and the PlumeStop remedy would have to be re-applied periodically as
PlumeStop will not permanently degrade, sorb or remove the Table 3+ PFAS reaching the Creek.
5 Remedy is expected to take 9 years to implement. 5 The estimated price per percentage loading reduction was $31,000,000. 5
Geosyntec Consultants of NC P.C. Remedy Scoring Table Summary
Chemours Fayetteville Works
Response to CFRW Supplemental Information Report Comments 9
Pathway Remedial Alternative Reductions to the Cape Fear River Rank Adverse Environmental Effects Technology Feasibility Time Cost per Loading Removal Offsite Groundwater Offsite Groundwater Extraction with
Barrier Wall
Remedy expected to reduce approximately 11.5% of total Table 3+ PFAS loading to the
Cape Fear River.
2
Requires significant
disruption to miles of shoreline on both sides of the Cape Fear River to install the barrier wall and groundwater
wells. Continual operation of
the extraction system may also continually interfere with local wildlife habitats.
4
The length of the barrier is extreme
in length and will potentially be considerably challenging in areas. Also, there are many private lands where access would need to be
negotiated to create a continuous
barrier. Last the amount of pipe and the size of the needed treatment system is significant
5 Remedy is expected to take 10 years to
implement.
5 The estimated price per percentage loading
reduction was $19,000,000.
5
Notes: See Tables in introduction for information on the rankings.