HomeMy WebLinkAbout2019.03_CCO.p8.A_Inventory of Emissions of GenX CompoundsChemours Company - Fayetteville Works Mar-19
Air Permit No. 03735T44
Month Notes Status
GenX Compound
Emissions
(lbs)
October 6-31, 2018 1 Actual 0.1
November 2018 Actual 57.9
December 2018 2 Actual 68.9
January 2019 Actual 11.2
February 2019 Estimated 31.4
March 2019 Projected 55.3
April 2019 Projected 12.1
May 2019 Projected 13.8
June 2019 Projected 11.7
July 2019 Projected 5.0
August 2019 Projected 7.0
September 2019 Projected 3.0
October 1-5, 2019 3 Projected 0.2
277.5
2,302.7
87.95%
Notes:
1) Contains emissions from October 6, 2018 - October 31, 2018
2) Contains summation of emissions from December 1 - 30, 2018 and December 31, 2018
3) Contains emissions from October 1, 2019 - October 5, 2019
Assumptions:
1) Reconfigurations to VE-North would decrease future stack emissions by 99%.
2) Assume 2019 PPVE campaign runs through Tuesday 3/26/19 (52.4% operating
time ABR is on, 2.7% burnout, and 44.9% ABR is off). ABR operating time for Dec
20-30, 2018 PPVE campaign was as follows: 38.2% operating time ABR is on,
2.1% burnout, and 59.7% ABR is off.
3) Carbon bed, with 99% efficiency, to be installed on VE-South process and
equipment emissions by end of June 2019.
2017 Baseline Emissions
Percent Reduction
Table 1
Inventory of Emissions of GenX Compounds
(Per Consent Order, Paragraph 8a)
March-19
Total GenX Compound Emissions
(12-Month Period from October 6, 2018
through October 5, 2019)
Chemours Company - Fayetteville Works Mar-19
Air Permit No. 03735T44
Month Notes Status
GenX Compound
Emissions
(lbs)
December 31, 2018 1 Actual 0.3
January 2019 Actual 11.2
February 2019 Estimated 31.4
March 2019 Projected 55.3
April 2019 Projected 12.1
May 2019 Projected 13.8
June 2019 Projected 11.7
July 2019 Projected 5.0
August 2019 Projected 7.0
September 2019 Projected 3.0
October 2019 Projected 0.8
November 2019 Projected 5.8
December 1-30, 2019 2 Projected 3.9
161.2
2,302.7
93.00%
Notes:
1) Contains emissions from December 31, 2018 only
2) Contains emissions from December 1, 2019 - December 30, 2019
Assumptions:
2) Assume 2019 PPVE campaign runs through Tuesday 3/26/19 (52.4% operating time
ABR is on, 2.7% burnout, and 44.9% ABR is off). ABR operating time for Dec 20-30,
2018 PPVE campaign was as follows: 38.2% operating time ABR is on, 2.1% burnout,
and 59.7% ABR is off.
3) Carbon bed, with 99% efficiency, to be installed on VE-South process and equipment
emissions by end of June 2019.
Total GenX Compound Emissions
(12-Month Period from December 31, 2018
through December 30, 2019)
2017 Baseline Emissions
Percent Reduction
Table 2
Inventory of Emissions of GenX Compounds
(Per Consent Order, Paragraph 8b)
March-19
1) Reconfigurations to VE-North would decrease future stack emissions by 99%.