FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
UNIT TYPE:
Lined
LCID
X
YW
Transfer
Compost
SLAS
COUNTY: Nash
MSWLF
PERMIT NO.: 6403-LCID-2020
Closed
HHW
White
Incin
T&P
FIRM
MSWLF
goods
FILE TYPE: COMPLIANCE
CDLF
TireT&P/
Tire
Industrial
DEMO
SDTF
Collection
Monofill
Landfill
Date of Site Inspection: March 24, 2021 Date of Last Inspection: N/A
FACILITY NAME AND ADDRESS:
Nash County LCID Landfill
SR 1425
3057 Duke Rd.
Nashville, NC 27856
GPS COORDINATES: N: 36.052542° E:-78.001889'
FACILITY CONTACT NAME AND PHONE NUMBER:
Name: Ben Barnes and Matthew Richardson
Telephone: 252-459-9823, 252-459-9899 (Barnes cell 252-904-3396)
Email address: solidwastegnashcoun , nc..ov; Matthew.Richardson&nashcogn , nc..ov
FACILITY CONTACT ADDRESS:
Nash County Solid Waste
P.O. Box 849
Nashville, NC 27856
PARTICIPANTS:
Amanda Thompson, NCDEQ Solid Waste
Drew Hammonds, NCDEQ Solid Waste
Ben Barnes, Nash County Solid Waste
Steve Nichting, Garett & Moore
Craig Fortner, Garett & Moore
STATUS OF PERMIT:
6403-LCID-2020: Permit to Construct and Permit to Operate was issued July 13, 2020, and the Permit to Operate will expire
on July 13, 2025.
PURPOSE OF SITE VISIT:
Pre -operation Inspection.
STATUS OF PAST VIOLATIONS
None.
OBSERVED VIOLATIONS
None.
Page 1 of 4
NORTH CAR()LINAD_E Q��
OepaNnent of Envieonmenbl W.I�
FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
The item(s) listed above were observed by Section staff and require action on behalf of the facility in order to come into or maintain compliance
with the Statutes, Rules, and/or other regulatory requirements applicable to this facility. Be advised that pursuant to N.C.G.S. 130A-22, an
administrative penalty of up to $15,000 per day may be assessed for each violation of the Solid Waste Laws, Regulations, Conditions of a Permit,
or Order under Article 9 of Chapter 130A of the N.C. General Statutes. Further, the facility and/or all responsible parties may also be subject to
enforcement actions including penalties, injunction from operation of a solid waste management facility or a solid waste collection service and any
such further relief as may be necessary to achieve compliance with the North Carolina Solid Waste Management Act and Rules.
ADDITIONAL COMMENTS:
The purpose of this inspection was to complete the required pre -operation inspection, prior to accepting waste at the newly
constructed LCID. Upon arrival, the Section was informed that the facility had received approximately 1.5 inches of rain
that morning.
1. The sediment basin to the northeast of Phase I of the LCID has been constructed. Three porous fabric baffles run
the length of the sediment basin. The sediment basin also consists of a skimmer, concrete riser, and an emergency
spillway. The side slopes of the sediment basin have been seeded and lined with fabric to help prevent erosion and
facilitate the growth of permanent vegetation.
2. Riprap has been placed on the downstream side of the outfall. During this inspection, the water exiting the outfall
was extremely turbid and flowing into the forested area adjacent to Pig Basket Creek. Mr. Fortner stated that the
water was still very turbid after running through a filter. The turbidity of the outfall needs to be monitored, so that
the excess sediment does not inundate the forested area. DEMLR staff have been notified and will visit site.
3. The drainage ditch along the southern and eastern edges of Phase I of the LCID has been constructed. The drainage
ditch has been seeded and lined with fabric to facilitate the establishment of permanent vegetation. The grasses are
expected to ensure erosion control. Any repairs to the ditch and/or established vegetation need to be completed
immediately.
4. One area of riprap was identified within the ditch, at the sediment basin inlet pipe. Monitor the drainage ditch to
determine if additional riprap areas are needed to prevent erosion in the drainage ditch.
5. Vegetation was still located within the Phase I LCID cell. Mr. Nichting and Mr. Fortner stated that since there was
no excavation required for the LCID, the vegetation would be scraped off and the cell would be ready to receive
waste. If there is no issue here with separation from the seasonal water table, it may be possible to remove any trees
and bush hog the remaining area to assist in stabilization of this area.
6. The roadway to the Phase I LCID cell was not complete at the time of this inspection. Mr. Fortner stated that the
roadway would continue to the southern tree line and terminate in a cul-de-sac. This would allow for vehicles to
turn around and dump their LCID waste. Another option is to continue the roadway around the entire Phase I and
II LCID cells. This would help with the flow of traffic.
7. Once the LCID is operational, an operator shall be on duty at all times while the LCIDLF is open for public
use to direct patrons, monitor and remove unacceptable waste, and compact/cover the waste (15A NCAC
13B .0566 (6)).
8. The site must be completed before operations begin. Please notify Section Staff for follow up site visit.
9. Digital photographs were taken during the inspection.
Page 2 of 4
FACILITY COMPLIANCE INSPECTION REPORT
D_E Q�� Division of Waste Management
NORTH CAROLINA
OepnNnent of Envieonmenlnl Welily
Solid Waste Section
Please contact me if you have any questions or concerns regarding this inspection report.
Amanda
Thompson
Digitally signed by
Amanda Thompson
Date: 2021.03.30
15:30:42-04'00'
Amanda Thompson
Environmental Senior Specialist
Regional Representative
Phone: (910) 433-3353
Sent on: March 30, 2021 X Email Hand delivery US Mail Certified No.
Copies: Andrew Hammonds, Eastern District Supervisor — Solid Waste Section
Donna Wilson, Engineer — Solid Waste Section
Photographs taken by Amanda Thompson on March 24, 2021.
View of the LCID, from the NW corner. Facing SE.
View of the sediment basin. Facing SE.
L
View of the LCID, from the northern boundary. Facing S.
View of the sediment basin and drainage ditch. Facing S.
Page 3 of 4
NOR;T CA�INA
OepaNmen� of Environmental0uali�
FACILITY COMPLIANCE INSPECTION REPORT
Division of Waste Management
Solid Waste Section
View of the turbid water exiting the sediment basin.
View of the turbid water flowing through the forested
area.
Page 4 of 4