HomeMy WebLinkAbout3405_Forsyth_RJReynolds_RuralHall_Indus_ExcavationSummary_FID1453241_20200929ERM FRN Inc. FFa
hone: +1 704 541 8345
Summit Avenue +1 704 624 7928
NC 28203 erm.com
29 September 2020
North Carolina Department of Environmental Quality
Division of Waste Management
1646 Mail Service Center
Raleigh, North Carolina 27699-1646
Attention: Ms. Jaclynne Drummond
jaclynne.drummond@ncdenr.gov
Via Email
Reference: 0564782
Subject: Sediment Boil — Excavation Summary
Permit #34-05 - Edwards Road Landfill
Edwards Road
Rural Hall, Forsyth County, North Carolina
Dear Ms. Drummond:
On behalf of R.J. Reynolds Tobacco Company (RJRT), ERM NC, Inc. (ERM) is providing this
summary of excavation activities conducted 25 August 2020 in the area of a surface boil
encountered at the Edwards Road landfill in Rural Hall, NC.
The boil, located on the eastern slope of the landfill immediately west of sediment trap ST-1, was
discovered 10 February 2020 during a routine post -closure quarterly inspection. Initial field
investigation results were provided to the Division of Waste Management (DWM) in
correspondence dated 16 April 2020 (ERM). An Excavation Work Plan (ERM) for additional
assessment/ investigation activities was submitted to the DWM on 16 June 2020. Due to above
average wet conditions in the area, field investigation activities have been delayed until dryer
conditions are available to conduct field work.
Background and Existing Site Conditions
• Field investigation activities were conducted pursuant to ERM's Sediment Boil — Excavation
Plan dated June 16, 2020 and submitted to NCDEQ - Division of Waste Management.
• Field investigation activities were conducted by ERM on August 25, 2020 with labor and
equipment supplied by Piedmont Industrial Services, Inc. (subcontractor to ERM).
• Conditions on August 25, 2020 were clear and dry with temperatures ranging from mid-80s to
low 90s.
• Existing site conditions noted:
o Silt fence previously placed down gradient of surface boil location was in place and in good
condition.
o Surface boil was not observed to be active at time of field investigation. Discharge from the
surface boil was last observed on 24 May 2020.
o Empty 5-gallon buckets remain placed at the boil area in the event sediments require
removal.
o Surface sediments were not observed at the time of field investigations.
Page 1 of 8
I'MV111
29 September 2020
Reference: 0564782
Page 2 of 8
Existing site conditions of the morning of August 25, 2020 upon ERM's arrival on site
Excavation Activities — Surface Boil
• Using a "mini-trackhoe" with hand tools, excavation began at the location of the previously
located surface boil (also adjacent to temporary piezometer PZ-6 previously installed by ERM).
• Incremental excavation was performed removing approximately 1 foot of soil at a time followed
by inspection of soils, probing and attempts to identify dark gray sediments.
• Dark gray sediments were encountered approximately 3 feet below surface grade and observed
to be contained in a small discrete pocket (approximately 12-inch diameter). A piece of rip rap
stone was located in the center of the sediment pocket.
• Dark gray sediments were not observed during excavation activities above 3 feet below ground
surface.
Initial excavation activities in area of surface boil
T1M
29 September 2020
Reference: 0564782
Page 3 of 8
Discrete pocket of dark gray
sediments observed approximately 3
feet below existing ground surface
and extending to approx. 3.5 feet
below ground surface.
• Excavation continued in the area of the identified sediment pocket. Dark gray sediments were
not observed below approximately 3.5 feet below ground surface.
• Inspection and observation of the area did not identify a "pathway" of sediments entering the
discovered pocket (from beneath the pocket or from horizontally upgradient or side -gradient).
Final depth of excavation in area of surface boil
�i
Excavation Activities — Upgradient of Surface Boil
29 September 2020
Reference: 0564782
Page 4 of 8
• Without evidence of a preferred sediment migration "pathway", excavation continued from the
surface boil location upgradient towards the closed landfill liner anchor trench.
• Excavation continued in a manner as previously described using the mini-trackhoe and hand
tools removing approximately 1-foot increments of soil to allow for inspection and observations.
• The liner anchor trench was located and uncovered approximately 12 feet west (upgradient) of
the surface boil location.
• The anchor trench was completely uncovered and exposed to allow for visual inspection; no
indications of dark gray sediments or wet soils observed.
• Additional soils were excavated on the downgradient side of the anchor trench and along the
anchor trench to allow for inspection of a broader area; no indication of dark gray sediments or
wet soils observed.
• Cover soils immediately upgradient (west) of the anchor trench were removed to allow for
inspection of soil conditions above the composite liner; no indication of dark gray sediments or
wet soils observed.
Excavation continuing upgradient (west) of surface boil towards anchor trench
29 September 2020
Reference: 0564782
Page 5 of 8
Exposed liner anchor trench area
• Lacking evidence of dark gray sediments beyond the initially located discrete pocket,
excavation of this area did not continue.
• Due to the location of the sediment pocket near the crest of an exterior containment berm,
excavation did not extend deeper than approximately 4 feet below ground surface (no dark gray
sediments observed below 3.5 feet).
• The excavated area was backfilled and compacted using excavated soils. The area was
seeded with erosion mat installed with staples over the disturbed area.
• A PVC pipe was placed to mark the outer limits of the liner anchor trench for easy identification
in the field for future activities.
Excavation area backfilled and stabilized with PVC pipe locating outer anchor trench limits
Observations
• Only one discrete pocket of dark gray sediments was observed during field activities.
• A preferred pathway of dark gray sediment migration was not encountered.
• Excavated soils were dry upon inspection.
�i
29 September 2020
Reference: 0564782
Page 6 of 8
Majority of soils excavated were observed to be clayey silts or silty clays; soils have plasticity.
Rip rap was encountered and excavated in the immediate vicinity of the surface boil area.
No flow was observed from anchor trench drains or underdrain outlet.
Cross Section Development
Utilizing field observations and measurements, ERM developed the enclosed cross section of the
excavation area. Information from as -built drawings developed from liner cap installation were
utilized to assign elevations. From development of the cross section, the following is noted:
• Elevation of ground surface at the surface boil location is approx. 831.9.
• Elevation of dark gray sediment pocket observed is approx. 828.4.
• Elevation of bottom of anchor trench is approx. 831.9.
• The outer limit of liner anchor trench is approx. 12 feet upgradient of surface boil location.
• Based on as -built drawings and photos documenting the landfill closure project, a minimal
depth of ash (5 to 10 feet) was placed immediately upgradient of the liner anchor trench in the
area of the surface boil.
• Investigation of the boil area included excavation of soils below elevations of upgradient liner
anchor trench and ash placed immediately upgradient of the anchor trench.
• Underdrain installed in 2012 to drain an area of saturated ash encountered during closure is
located approx. 105 feet west (upgradient) of surface boil location at an elevation of
approximately 828.
Conclusions
• Based on Site observations, there is no apparent risk to human health or the environment
related to the sediment boil.
• The surface boil was not actively flowing at the time of field investigation activities and all
surrounding soils removed during excavation were observed as dry.
• Based on inspections by RJR following significant rainfall events in the region, the surface boil
has not been observed as active for over two months prior to these excavation activities. Since
the installation of the liner in 2012, no sediment boils have been observed at the Site prior to
the extreme wet conditions of 2020.
• Previous surface water sampling results indicate that no exceedances of NC Surface Water
Standards have occurred in the nearby Leak Creek.
• A preferred "pathway" of sediment migration could not be visually identified during these field
activities.
• Based on observations of the section of liner anchor trench that was exposed immediately
upgradient of the surface boil, there is no visual indication of wetness or gray sediment
migration associated with the liner trench.
• Based on the previously submitted Sediment Boil — Excavation Plan dated June 16, 2020
(ERM), with the lack of "pathway" identification, further assessment, monitoring and/or
investigation is warranted.
Next Steps
Based on field investigation activities and observations, a video camera inspection of the previously
installed underdrain system is planned to evaluate the structure for potential collapse or
obstructions. Following initial installation, continuous flow from the underdrain has not been
�i
29 September 2020
Reference: 0564782
Page 7 of 8
observed, including during periods of peak flow from the sediment boil. Elevations of the
underdrain and dark gray sediment pocket observed during field excavation activities are similar.
Additional investigation steps may be considered following the camera inspection.
The boil area and nearby soil saturation conditions will continue to be monitored following
significant rainfall events plus inspections and maintenance of the previously installed silt fence and
coir wattles will be conducted as necessary for protection of human health and the environment.
Ongoing monthly updates will be provided to NCDEQ as investigation and monitoring of the
sediment boil continue.
Please contact Mr. Max Hopkins of R.J. Reynolds Tobacco Company at 336-741-6932 or me if you
have any questions or comments.
Sincerely,
Dave Wasiela, P.E.
Project Engineer
Attachments:
Cross Section Figure
A�rti'n, P.G.
Project Manager
cc: Mr. Scott Snow — R.J. Reynolds Tobacco Company
Mr. Max Hopkins — R.J. Reynolds Tobacco Company
Mr. Tom Wilson — ERM
870
860
850
840
830
820
810
800
790
780
770
760
760
Y
1
X
CREEK
350 340 330 320 310 300 290 280 270 260 250 240 230 220 210 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20
N
SCALE IN FEET
0 6.25 12.5 25