HomeMy WebLinkAbout7607-GreatOakMSWLF_CQArpt_Vol1_Cell3B4&5_FID1416698_20200623June 22, 2020 Waste Management of Carolinas, Inc. 1047 Highway Church Road Elgin, South Carolina 29045 Attention: Ms. Susan Harrison, P.E. Market Area Engineering Manager Subject: Construction Quality Assurance Report Construction of Cells 3B, 4, and 5 Volume 1 of 3 Structural Fill and Subgrade Preparation Great Oak Landfill Facility Permit No. 7607-MSWLF-2015 Randolph County, North Carolina BLE Project Number J20-13334-02 Dear Ms. Harrison: This Volume 1 of 3 of the Construction Quality Assurance (CQA) Report summarizes our observations and construction quality assurance test results, from the start of Cells No. 3B, 4, and 5 construction on March 16, 2020 through completion of the subgrade on June 5, 2020, at Great Oak Landfill. Bunnell-Lammons Engineering, Inc. (BLE) has monitored and documented the Cells No. 3B, 4, and 5 construction tasks listed below to determine if the construction was performed in accordance with the project drawings, specifications, and conditions, as approved by the North Carolina Department of Environmental Quality (NC DEQ), Division of Waste Management. The report will be presented in three volumes as outlined below. Volume 1 •Structural fill and subgrade preparation Volume 2 •Secondary 60-mil HDPE Geomembrane (Flexible Membrane Liner, FML), •Leachate Detection System (LDS) Geocomposite, •Reinforced Geosynthetic Clay Liner (GCL), •Primary 60-mil HDPE Geomembrane (Flexible Membrane Liner, FML), and •Leachate Collection System (LCS) Geocomposite Volume 3 •Protective cover layer, and •Leachate collection system. i TABLE OF CONTENTS VOLUME 1 PAGE 1.0 PROJECT DESCRIPTION 1-1 2.0 SUMMARY OF QUALITY CONTROL/QUALITY ASSURANCE PARTIES 1-2 2.1 WASTE MANAGEMENT OF CAROLINAS, INC. 1-2 2.2 PROMUS ENGINEERING, LLC 1-2 2.3 EARNHARDT GRADING, INC. 1-2 2.4 ENVIRONMENTAL SPECIALTIES INTERNATIONAL, INC. 1-2 2.5 SURVEY CAROLINA PLLC 1-2 2.6 BUNNELL-LAMMONS ENGINEERING, INC. 1-2 3.0 CONSTRUCTION OBSERVATION AND TESTING 1-2 3.1 CELLS 3B, 4, and 5 1-3 3.1.1 Site Preparation 1-3 3.1.2 Subgrade Preparation 1-3 VOLUME 2 3.2.1 Secondary 60-mil HDPE Geomembrane (FML) 2-1 3.2.2 Leak Detection System (LDS) Geocomposite 2-1 3.2.3 Reinforced Geosynthetic Clay Liner (GCL) 2-1 3.2.4 Primary 60-mil HDPE Geomembrane (FML) 2-1 3.2.5 Leachate Collection System (LCS) Geocomposite 2-1 VOLUME 3 3.3.1 Protective Cover and Leachate Collection System Description 3-1 ii APPENDICES VOLUME 1 A FIGURES: Site Location Map, Field Sketch – Cells 3B, 4, and 5, and Base Grade As- Built Survey B RECORDS OF DAILY OBSERVATIONS & PROJECT MEETINGS: Structural Fill and Subgrade C PHOTOGRAPHS: Structural Fill and Subgrade D REPORT OF GEOLOGIC OBSERVATIONS E LABORATORY TEST RESULTS: Structural Fill and Subgrade F FIELD TEST RESULTS: Structural Fill and Subgrade G MATERIAL SUBMITTALS VOLUME 2 H RECORDS OF DAILY OBSERVATIONS & PROJECT MEETINGS: Geosynthetics Installation I PHOTOGRAPHS: Geosynthetics Installation J REINFORCED GEOSYNTHETIC CLAY LINER (GCL) CQA & MQC Conformance Documentation iii APPENDICES (continued) K REINFORCED GEOSYNTHETIC CLAY LINER (GCL) CQA Construction Documentation L PRIMARY & SECONDARY HDPE GEOMEMBRANE (FML): CQA & MQC Conformance Documentation M PRIMARY & SECONDARY HDPE GEOMEMBRANE (FML): CQA Construction Documentation and FML As-Built Drawing N INTERFACE FRICTION TEST RESULTS O LDS GEOCOMPOSITE DRAINAGE MEDIA (GDM) CQA & MQC Conformance Documentation P LCS GEOCOMPOSITE DRAINAGE MEDIA (GDM) CQA & MQC Conformance Documentation VOLUME 3 Q RECORDS OF DAILY OBSERVATIONS & PROJECT MEETINGS: Leachate Collection System R PHOTOGRAPHS: Leachate Collection System S LABORATORY & FIELD TEST RESULTS: Leachate Collection System T PROTECTIVE COVER AS-BUILT SURVEY U MATERIAL SUBMITTALS Leachate Collection System Construction of Cells 3B, 4, and 5 June 22, 2020 Great Oak Landfill BLE Project No. J20-13334-02 Randolph County, North Carolina 1-1 1.0 PROJECT DESCRIPTION Great Oak Landfill is located in Randolph County, North Carolina (Figure 1). The landfill is owned by Waste Management of Carolinas, Inc. Cells 3B, 4, and 5 occupy approximately 12.7 acres (553,214 sq. ft.) north of the existing Cells 1B and 2 at the landfill. The majority of the earthwork performed to reach the design subgrade elevations in the cells consisted of mass excavation. Mass excavation included the removal of partially weathered rock and blasting of non-rippable rock. Structural fill was placed to bring the cell floor to the design grades after the blasting was completed. The Cells 3B, 4, & 5 base liner will consist of a subgrade (base grade), overlain by the secondary textured 60-mil geomembrane. The secondary geomembrane will be overlain by a leak detection system (LDS), composed of an LDS geocomposite having a minimum transmissivity (Θ) of 5.1 x 10-9 m2/s, and approximately 1,970 lf of perforated 8-inch diameter, SDR 11 HDPE pipe, surrounded by ASTM No. 57 stone. Approximately 160 lf of solid wall 8-inch diameter, SDR 11 HDPE pipes serve as the clean-out accesses for the LDS perforated pipes. The clean-outs are located on the south and east sides of the cells. The leak detection system will be overlain by a geosynthetic clay liner (GCL). The GCL will be overlain by the primary textured 60-mil HDPE geomembrane. The primary geomembrane will be overlain by a leachate collection system (LCS), composed of an LCS geocomposite having a minimum transmissivity (Θ) of 4.2 x 10-4 m2/s and approximately 1,970 lf of perforated 8-inch diameter, SDR 9, HDPE pipe, surrounded by ASTM No. 57 stone. It also includes approximately 400 lf of solid wall 8-inch diameter, SDR 11, HDPE pipes which serve as the clean-out accesses for the perforated pipes. The clean-outs are located on the north and west sides of the cells. The protective cover consists of a minimum 2-foot thick layer of screened material with a maximum particle size less than 3-inches (approximately 41,830 cy). The protective cover material was obtained during mass excavation in the proposed cell footprint. The ASTM No. 57 stone was obtained from an off-site quarry. The leachate system drains by gravity to the northeast end of the cells, where it ties into the existing Cell 3A leachate collection system. The purpose of this document is to report construction observations and testing by BLE and provide the CQA report required by Title 15A, NCAC 13B, Section .1624 of the North Carolina Department of Environmental Management (NCDEQ) and as outlined in the project contract documents and the CQA Plan. Volume 1 of 3 of this report documents the following construction of Cells 3B, 4, and 5: • Structural fill and subgrade preparation. Volumes 2 and 3 will document the following construction tasks of Cells 3B, 4, and 5: • Secondary 60-mil HDPE Geomembrane (Flexible Membrane Liner, FML) • Leachate Detection System (LDS) Geocomposite • Reinforced Geosynthetic Clay Liner (GCL) • Primary 60-mil HDPE Geomembrane (Flexible Membrane Liner, FML) • Leachate Collection System (LCS) Geocomposite Construction of Cells 3B, 4, and 5 June 22, 2020 Great Oak Landfill BLE Project No. J20-13334-02 Randolph County, North Carolina 1-2 • Protective cover layer, and • Leachate collection system. 2.0 SUMMARY OF QUALITY CONTROL/QUALITY ASSURANCE PARTIES The following parties were responsible for various aspects of quality control/quality assurance during the construction of this project. 2.1 WASTE MANAGEMENT OF CAROLINAS, INC. Waste Management of Carolinas, Inc. (Waste Management) is the owner and operator of the Great Oak Landfill. 2.2 PROMUS ENGINEERING, LLC Promus Engineering, LLC (Promus) of Chattanooga, Tennessee, is the Design Engineer for the Great Oak Landfill. Promus prepared the project construction plans and a portion of the specifications. S&ME of Raleigh, NC prepared the original permitted technical specifications and CQA Plan. SCS Engineers of Charlotte, NC revised the technical specifications and CQA Plan in 2017. 2.3 EARNHARDT GRADING, INC. Earnhardt Grading, Inc. (Earnhardt) of Stanley, North Carolina, was the general contractor for the construction of Cells No. 3B, 4, and 5. Earnhardt Grading will also install the protective cover and leachate collection system. 2.4 ENVIRONMENTAL SPECIALTIES INTERNATIONAL, INC. Environmental Specialties International, Inc. (ESI) was contracted by Waste Management to complete the geosynthetic installations of the 60-mil minimum textured HDPE geomembrane, the LDS and LCS geocomposite, and the geosynthetic clay liner (GCL) for Cells No. 3B, 4, and 5. The geomembrane was manufactured by Agru America, Inc. of Georgetown, South Carolina. The the LDS and LCS geocomposite was manufactured by SKAPS Industries of Commerce, Georgia. The geosynthetic clay liner was manufactured by Solmax of Houston, Texas. 2.5 SURVEY CAROLINA PLLC Survey Carolina PLLC (Survey Carolina) were retained by Earnhardt to serve as the surveyor of record. Survey Carolina performed the as-built surveys to document the rock blasting, subgrade and the top of the protective cover and the leachate collection system. 2.6 BUNNELL-LAMMONS ENGINEERING, INC. Bunnell-Lammons Engineering, Inc. (BLE) was retained by of Waste Management to serve as the independent third-party Construction Quality Assurance (CQA) firm. BLE has observed, tested, and documented the procedures, processes, results, and related work, used to install, or construct the various landfill components. BLE has specifically provided quality assurance field and laboratory testing during the construction. The fieldwork has been performed under the direction of the CQA engineers, Mr. Jonathan Usher, P.E., and Mr. Bjorn Sundquist, P.E. 3.0 CONSTRUCTION OBSERVATION AND TESTING Construction observations are contained in the daily reports, which are presented in Appendix B, and a series of color photographs of major project features is included in Appendix C. The general construction Construction of Cells 3B, 4, and 5 June 22, 2020 Great Oak Landfill BLE Project No. J20-13334-02 Randolph County, North Carolina 1-3 procedures observed by BLE and the testing performed during landfill construction are summarized in the following report sections. 3.1 CELLS 3B, 4, and 5 3.1.1 Site Preparation Prior to construction, site vegetation and topsoil were cleared and grubbed to allow for the removal of overburden soils and rock. Site grading to achieve the design subgrade elevations required mass excavation and placement of structural fill. The excavation was performed by dozers and track excavators loading articulated off-road trucks. Overburden soils and partially weathered rock above the design subgrade elevations were ripped and removed from the Cells 3B, 4, and 5 area. Earnhardt used blasting to remove rock that could not be excavated using conventional construction equipment to a minimum of 4 feet of separation between the top of the subgrade and the top of bedrock. The soils and blasted rock excavated during Cells 3B, 4, and 5 mass excavation were stockpiled in the on-site borrow area to the west of Cells 3B, 4, and 5 for potential use as structural fill or protective cover. The stockpiled soils were screened through a 3-inch mechanical screen for use as structural fill and protective cover. 3.1.2 Subgrade Preparation During the Cells 3B, 4, and 5 construction, earthwork grading to obtain the design subgrade elevations within the cells required earthwork cuts in a majority of the cell to have a minimum 4-foot buffer between rock and the subgrade. Based on the survey data provided by Survey Carolina, PLLC and our site observations, the minimum 4-foot buffer was verified by a BLE Professional Geologist, and these reports are presented in Appendix D. Areas where structural fill was placed were successfully proofrolled using a loaded off-road haul truck. The proofrolling was monitored by the CQA engineering technician under the direction of the CQA engineer. Structural fill soils were placed in maximum 8-inch thick loose lifts to reach the design subgrade elevations. The structural fill soils placed in the cell consisted primarily of sandy silt and sandy clay borrowed from earthwork cut areas within the cell limits. The surface of the soil subgrade was compacted, and in-place density tests performed to confirm that compaction requirements were achieved. The Cells 3B, 4, and 5 Base Grade As-Built Survey, prepared by the project surveyor (Survey Carolina) is presented in Appendix A of this report volume. The CQA technician performed field (in-place) density tests on the compacted structural fill and subgrade in Cells 3B, 4, and 5, using the nuclear gauge method (ASTM D6938). The field sketch used for referencing density test locations is provided in Appendix A (Figure 2). The test locations are referenced to a series of grids with an area less than or equal to 10,000 sf to assist in achieving the specified in-place density test coverage. The in-place density tests were compared to laboratory standard Proctor compaction tests (ASTM D 698) of the site soils. Standard Proctor compaction test results representative of the structural fill soils are presented in Appendix E. The results of the field density tests are presented in Appendix F, and document that the structural fill was placed in accordance with the project Contract Documents and CQA Plan. In conclusion, it is our professional opinion the structural fill and subgrade for Cells 3B, 4, and 5 have been constructed in accordance with the following: • The Construction Plans and Contract Documents, • The CQA Plan, Construction of Cells 3B, 4, and 5 June 22, 2020 Great Oak Landfill BLE Project No. J20-13334-02 Randolph County, North Carolina 1-4 • The requirements of the NCDEQ Solid Waste Disposal Permit, • Acceptable Engineering Practices, and the soil subgrade is acceptable for placement of the project geosynthetics. This statement is based on the observation, field testing, and laboratory testing by CQA testing personnel under the direction of CQA Engineer for Bunnell-Lammons Engineering, Inc. and the provided as-built survey information by Survey Carolina. Prior to deployment of the geosynthetics, each section of the soil subgrade will be approved by the CQA technician based on guidance for acceptable surface preparation provided by the CQA engineer. FIGURE 1: FIGURE 2: SUBGRADE AS-BUILT SURVEY FIELD SKETCH – CQA CELLS NO. 3B, 4, & 5 SITE LOCATION MAP FIGURES APPENDIX A FIGURE 1: SITE LOCATION MAP 1 SITE FIGURE 2: FIELD SKETCH – CELLS NO. 3B, 4, & 5 200100200400 SUBGRADE AS-BUILT SURVEY EXISTING CELL 1B 7.3 ACRES EXISTING CELL 3A8.2 ACRESFUTURE CELLS 6 &79.8 ACRES LegendCell Limits Plan Contours Base Grade SEALL-4787 IIRENNATWNAD ROYEVRUSDNALPROFESSION A LNO R T H CAROLINA I, Dan W Tanner II, Professional Land Surveyor, certify: The Horizontal Tolerance for all points are 0.2' and Vertical Tolerance for allpoints are 0.08'.Horizontal Datum: NAD83 (2011)Vertical Datum: NAVD88 _______________________________________________Date L-4787 Ex. Geo BG Point on top of Existing Geosynthetics Job #: 11737 Base Grade As-Built SurveyCell 3B, 4 And 5 ConstructionGreat Oak LandfillNCDEQ Permit 7607-MSWLF-20153597 Old Cedar Falls Road Randleman, NC 27317 Asheboro Township Randolph CountyNorth Carolina June 6, 2020Scale: 1" = 50 US Survey Feet SURVEY CAROLINA, PLLC Firm #: P-1110Dan W Tanner II L-4787© 2020 Survey Carolina, Pllc 154 S. Fayetteville St, Suite B, Asheboro, NC 27203Phone Number:336 625-8000Email:mail@surveycarolina.com 0 50 100 150 Dan W Tanner II Digitally signed by Dan W Tanner II Date: 2020.06.22 13:49:48 -04'00' APPENDIX B RECORDS OF DAILY OBSERVATIONS AND PROJECT MEETINGS RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 03/16/2020 7:30 17:30 10 1 03/16/2020 Tommy Anderson 48 54 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Contractor started drilling in Cell 3B, 4 & 5, using a Sandik Ranger DX800. 55 locations drilled today. N/A Observed and documented the elevation, depth to rock, and the termination depth of the boreholes. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 03/17/2020 7:30 17:30 10 2 03/16/2020 Tommy Anderson 48 54 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Contractor continued drilling in Cell 3B, 4 & 5, using a Sandik Ranger DX800. 93 locations drilled today. N/A Observed and documented the elevation, depth to rock, and the termination depth of the boreholes. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 03/18/2020 7:30 13:30 10 3 03/16/2020 Tommy Anderson 51 62 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Contractor continued drilling in cell 3B, 4 & 5, using a Sandik Ranger DX800. 30 locations drilled today. N/A Observed and documented the elevation, depth to rock, and the termination depth of the boreholes. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/02/2020 11:00 15:00 11.0 18 03/16/2020 Ben Nisbeth 4 50 60 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER 1. Contractor moved structural fill materials from overburden located near the middle of the proposed cell, using a track-hoe to load four off road dump trucks, to the area of structural fill placement in the north-center area of the proposed cell. 2. Material was spread out, using a CAT D8 bulldozer, in loose lifts not exceeding 12 inches. The material was compacted, using a CAT 815 compactor. 3. Contractor was also observed to be drilling, and preparing to blast rock, located near the south portion of the proposed cell. N/A 1. Observed contractor activities within the proposed cell. 2. Conducted soil density tests at three locations on the structural fill being placed near the north-central section of the proposed cell. The three tests met the required 95% minimum compaction. 3. Observed that the material being used as structural fill appeared to not contain any material larger than 4 inches in diameter. Rev. 2.10 Jonathan P. Usher, P.E. 200100200400Density test locations RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/06/2020 07:30 16:30 9 22 03/16/2020 Tommy Anderson 4 4 56 79 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER Earnhardt Grading 1). Excavating soils to be placed as structural fill in the cell, and to be stockpiled. 2). Placing and compacting fill in the cell. 1) Density test on fill placed in the cell. 2) Sampling Jonathan P. Usher, P.E. Rev. 2.10 20010020040004/06/2020Approximate area of excavationApproximate area of fill placement RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/14/2020 10:00 13:15 3.25 30 03/16/2020 TJ DANIEL 4 68 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER N/A N/A -BLE Geologist T.J. Daniel observed the geologic subgrade in the southern corner of cells 3B, 4, and 5. -Soil observed to be a brown, fine to medium sandy, SILT. -Rock from approximately 100-300' north of cell 1B tie in in portion of blasting area observed to be a greyish green, massive, quartzite. -No obvious quartz veins within the quartzite were visible but several boulders of white quartz ranging from 6" to 2' in diameter were visible in left over shot rock. -Two joint features measured within quartzite with S1 strike = S80E and dip = 88 SW while S2 strike = N25W and dip = 76 NE. One apparent fracture was denoted in an in situ boulder with strike = S48W and dip = 49 NW. (continued on next page) Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQA TECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017304/14/2020 TJ DANIEL -Rock from approximately 0-100' north of cell 1B tie in in portion of blasting area varies from a tan slate to a tan phyllite. The foliation of this formation has a strike = S25W and dip = 52 NE. -Rock was blasted deeper than necessary for 4' vertical separation from top of structural fill in several areas. -Observed blast area was approximately 300x200' in size with approximately 30% covered in >4" diameter shot rock of various geology. -TJD collected various rock samples to be brought back to BLE office for additional evaluation. Photos of geologic observations can be found on the solid waste server at: "\\BLEGVLSVR1\SolidWasteProjects\Great Oak Landfill\13334-02A Cells 3B, 4, and 5 Rock Blasting\Photos" and all photos at original resolution with geotags can be found at https://photos.app.goo.gl/nM85QrugxNa5yHP66. A more formal report will be prepared and submitted with BLE’s rock blasting certification letter, once all blasting activities have been completed. Jonathan P. Usher, P.E. 200100200400Approximate area withextensive >4" bouldersPhoto is facingsoutheast towardsactive face RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/15/2020 0700 1430 7.5 31 03/16/2020 James Fortson 4 40 58 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER Earnhardt Grading 1. Contractor continued mass excavation of soil from the proposed cell footprint, using (1) CAT 349E excavator, (1) D6N dozer, and (4) CAT 745 off-road dump trucks. All soil was transported to the stockpile located North of the proposed cell, for screening and future use as fill. 2. Rock drill contractor continued rock drilling and preparing for blasting to remove rock. 3. Contractor continued to compact previously placed structural fill, using (1) CAT 815B compactor. N/A 1. Observed contractors activities. 2. Obtained 6 stockpile structural fill samples, and 4 protective cover stockpile samples. 3. Performed 12 nuclear density density tests. All tests passed the minimum project specification of 95% compaction. Jonathan P. Usher, P.E. Rev. 2.10 20010020040004/15/2020Compacted placed structural fillMass excavated and transported to stockpile for screening RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/22/2020 10:15am 38 03/16/2020 Benjamin Nisbeth, P.G. 4 52 64 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 Geologic Observation Contractor was observed moving shot rock from the north end of the cell, to a stockpile located north of the cell. Contractor was also observed moving screened structural fill material from the structural fill stockpile to the fill area located near grids 32-33, 42-43, and 52-53. Materials were observed to be spread out with a CAT D6 bulldozer, and then compacted with a CT 815B sheepsfoot roller. Contractor performed proofroll in grids 3-4 adn 12-13. Rutting and pumping due to wet soils. Contractor was observed removing wet soils located near grids 3-4, and 12-13. N/A Upon arrival, rep conducted a geologic observation of the exposed shot rock located near grids 12-13. Area of shot rock observed was measured to be approximately 120 feet long (North-South axis), by approximately 45 feet wide (East-West axis). Area was observed to be covered in shot rock, ranging in size from less than an inch in diameter, up to approximately 2.5 feet in diameter. The shot rock was observed to consist mostly of partially weathered quartzite, with some light brown slate (meta-mudstone) mixed in along the south end. Quartz veins were not observed, however, small pieces of quartz were observed sporadically throughout the shot rock (2-5 inches in diameter). One Joint set was observed within the exposed quartzite, with the measured strike and dip as follows: Strike = N 28 W, Dip = 83 E; Strike = N 39 W, Dip = 84 E. Data collected today from the geologic observation will be reviewed and presented in a later report. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQA TECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017304/22/2020 Benjamin Nisbeth, P.G. BLE rep also observed a proofroll of the subgrade located near grids 3-4 and 12-13. Area was observed to have not proofrolled successfully, with pumping and rutting of the soils observed. It was recommended that 8-12 inches of material be removed and replaced with the screened structural fill. Recommendations were communicated to Marc with Earnhardt Grading. It should be noted that the contractor began removing the wet soils prior to BLE rep departing the job site today. Rep also conducted soil density tests on the structural fill material that was being placed today near grids 32-33, 42-43, and 52-53. A total of five tests were conducted today. All five tests conformed with the required compaction. Rep also collected soil samples from the screened structural fill stockpile (total of six 5-gallon buckets), and transported them back to the lab for shipment to other labs and for in-house analysis. Rep also observed the geomembrane that had been delivered to the job site prior to today. Rep also observed that the rolls delivered (87 rolls) matched with the numbers on the packing slips. Jonathan P. Usher, P.E. 20010020040004/22/2020Geologic observation and proofroll areaStructural fill placement and density testing area RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/24/2020 1245 1545 3 40 03/16/2020 James Fortson 4 59 77 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER Earnhardt Grading 1. Contractor continued to excavate soil out of the proposed cell footprint, using 1 CAT 349E excavator, 1 D6N dozer, and 4 CAT 745 off-road dump trucks. All soil was transported to the stockpile located North of the proposed cell for screening to be used as fill. N/A 1. Observed contractors activities 2. Inventoried all geomembrane that had been previously delivered. All geomembrane rolls delivered were on the approved delivery list. 3. Inventoried and measured all 8" HDPE pipe. All pipe delivered appeared to be consistent with the project drawings with proper hole size, spacing, and offsets. Jonathan P. Usher, P.E. Rev. 2.10 20010020040004/24/2020Continued excavating soil to achieve subgrade elevation. RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/04/2020 11:30 14:30 10.0 50 03/16/2020 Benjamin Nisbeth, P.G. 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 Geologic Observation Contractor was observed to be removing soils and blast from from the northeast area of the cell today. Material was loaded onto three CAT 745 Off-Road dump trucks and hauled to the stockpile located north of the cell. Rep also observed contractor blasting rock near Grid 21. Prior to departing the job site, rep observed contractor beginning to haul structural fill from the structural fill stockpile to the cell near the northwest corner (Grids 47 and 37). N/A Upon arrival, rep observed a proofroll of the subgrade prior to placement of structural fill, located in Grids 16-20, 26-30, 36-40, and 46-50. Area was observed to have proofrolled successfully with a loaded Off-road dump truck (CAT 745). Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQA TECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017305/04/2020 Benjamin Nisbeth, P.G. Rep conducted a geologic observation of the exposed rock and weathered rock after blasting in Grids 47-49, 55, and 56. Area observed was measured to be approximately 300 feet long, by 35 feet wide, from the northwest corner of the cell headed southeast along the west edge of the cell. Rep observed loose boulders approximately 4 inches in diameter, up to approximately 2.5 feet in diameter. Rep observed weathered and partially weathered light brown to white phylite in the south 150 feet, with gray quartzite in the middle section (approximately 85 feet in length), and weathered phylite with pieces of quartzite in the north 65 feet. Rep did not observe any exposed quartz veins today. Additionally, suitable planar features (joint sets, foliations, fracture planes) were not exposed today, so no strike and dip measurements could be obtained. Jonathan P. Usher, P.E. 20010020040005/04/2020Proofroll areaProofroll areaGeologic observation area RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/07/2020 11:45 13:45 9.0 53 03/16/2020 Benjamin Nisbeth, P.G. 4 41 60 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 Geologic Observation Contractor was observed to be removing landfill waste from the existing landfill cell, located west of the cell under construction, in order to expose the landfill liner to tie into it. Material was loaded onto three CAT 745 off-road dump trucks, and hauled to the active face of the landfill. N/A Upon arrival, BLE representative observed a proofroll of the cell subgrade prior to placement of structural fill near Grids 1, 7-9, 16-19, and 26-29. Area was proofrolled with a loaded CAT 745 off-road dumptruck. Area was observed to have proofrolled successfully with very little to no movement of the subgrade observed. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQA TECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 Benjamin Nisbeth, P.G. BLE Representative also conducted a geologic observation of the exposed shot-rock located near Grids 1, 7, 8, 18, and 28. Rep observed that these areas were comprised mainly of boulders of gray to green quartzite, ranging in size from approximately 3 inches in diameter to approximately 2 feet in diameter. Quartz veins were not observed today in the exposed shot-rock. Additionally, planer features (joint sets, foliations, fractures, etc.) were not observed in any exposed, undisturbed bedrock, so strike and dip measurements were not collected today. Jonathan P. Usher, P.E. 05/07/2020 20010020040005/07/2020Geologic observationProofroll area RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/14/2020 12:45 14:30 8.75 60 03/16/2020 Benjamin Nisbeth 4 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 Geologic Observation Contractor was observed staging soils near Grids 24 and 34 for fine grading activities. N/A Upon arrival, BLE rep observed a proofroll of the subgrade prior to placement of structural fill near Grids 49, 50, 51, and 56. Area was proofrolled with a loaded CAT 740 off-road dump truck. Area was observed to have proofrolled successfully with little to no deflection or rutting of the soils observed. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQA TECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017305/14/2020 Benjamin Nisbeth Rep also attempted to conduct a geologic observation of the same area near grids 49, 50, 51, and 56. Rep observed several pockets of shot-rock consisting of weathered quartzite and weathered phylite, with boulders observed ranging in size from approximately 2 inches in diameter up to approximately 18 inches in diameter. The pockets of the weathered quartzite and phylite ranged in size from approximately 3 feet in diameter up to approximately 25 feet in diameter, spread sporadically throughout the 4 grids observed today. Residual soils had been graded across the area, so planer features (foliations, joint sets, fracture sets, etc.) were not observed during today’s visit. Subsequently, strike and dip measurements were not collected today. Jonathan P. Usher, P.E. 20010020040005/14/2020Approximate location of BLE proofroll observation RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/18/2020 13:30 16:30 11.0 64 03/16/2020 Jimmy Bartlett 4 N/A 88 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER N/A N/A Performed 18 density tests on structural fill. Did required safety training before going on site. Jonathan P. Usher, P.E. Rev. 2.10 200100200400 RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/26/2020 11:45 16:45 5.0 72 03/16/2020 James Fortson 4 65 74 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER Earnhardt Grading Inc. 1. Contractor continued placing structural fill along the southern tie-in in the southern corner of the cell, using 4 CAT 740 off-road dump trucks, 1 CAT D6N dozer, 1 CAT D8 dozer, 1 CAT 815 compactor, and 1 CAT smooth drum compactor. 2. Contractor continued cleaning off southern tie-in, using 1 CAT 303 excavator. 3. Contractor unloaded, stored, and covered rolls of GCL on-site. 4. Contractor continued screening structural fill material outside of cell limits for future fill, using 1 CAT 349 excavator, 1 CAT D8 dozer, and 1 screen. N/A 1. Observed placement of structural fill along the southern tie-in. 2. Observed cleaning off southern tie-in for future geosynthetics tie-in. 3. Performed 23 nuclear density tests structural fill. All tests exceeded 95% compaction by standard proctor. 4. Observed unloading rolls of GCL. 5. Observed screening of structural fill outside of cell limits. Jonathan P. Usher, P.E. Rev. 2.10 20010020040005/26/2020Placed structural fill along tie-inCleaned off tie-in for future connection RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/27/2020 07:00 17:00 10.0 73 03/16/2020 James Fortson Mauricio Moreno Jonathan Usher 4 4 65 72 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER Earnhardt Grading, Inc. 1. Contractor continued placing structural fill along the southern tie-in in the southwestern corner of the cell, using 4 CAT 740 off-road dump trucks, 1 CAT D6N dozer, 1 CAT D8 dozer, 1 CAT 815 compactor, and 1 CAT smooth drum compactor. 2. Contractor unloaded, stored, and covered rolls of GCL shipped to the site. 3. Contractor continued screening operations outside of cell footprint, using 1 CAT 349 excavator, 1 CAT D8 dozer, and 1 screen. N/A 1. Observed placement of structural fill along the southern tie-in. 2. Observed unloading of GCL that was shipped to site. 3. Attended the predeployment meeting held with landfill personnel, BLE personnel, Earnhardt personnel, and ESI personnel. 4. Inventoried on-site LCS and LDS GDM to ensure all delivered materials was on the approved roll list. Jonathan P. Usher, P.E. Rev. 2.10 20010020040005/27/2020Placed structural fill along tie-in RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/28/2020 07:00 18:00 11.0 74 03/16/2020 James Fortson Mauricio Moreno 4 4 66 82 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Earnhardt Grading, Inc. 1. Contractor began excavating leachate collection corridor trench in the eastern half of the cell, using 4 laborers, 1 CAT D6N dozer, and 1 CAT 336 excavator 2. Contractor continued screening structural fill material for future placement in the cell footprint, using 1 CAT 349 excavator, 1 CAT D8 dozer, and 1 screen. 3. Contractor performed general site cleanup and bladed access roads after previous rain event. N/A 1. Observed excavation of the leachate collection corridor trench along the eastern half of the cell. 2. Observed screening operations outside of cell limits. 3. Observed general site cleanup and access road repair. 4. Began inventorying on-site GCL to ensure all delivered materials was on the approved roll list. Jonathan P. Usher, P.E. Rev. 2.10 20010020040005/28/2020Began excavating and shaping leachate collection corridor trench RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/29/2020 07:00 17:30 5 75 03/16/2020 James Fortson Mauricio Moreno 4 4 68 76 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Earnhardt Grading, Inc. 1. Contractor cleaned off tie-in along the Cell 3A using 8 laborers with flat-tipped shovels. N/A 1. Observed cleaning the Cell 3A tie-in off using flat-tipped shovels. Jonathan P. Usher, P.E. Rev. 2.10 20010020040005/29/2020Contractor cleaned washed silt off the tie-in using flat tipped shovels RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 06/01/2020 07:00 19:00 11.50 78 03/16/2020 James Fortson Mauricio Moreno 4 56 73 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Earnhardt Grading, Inc. 1. Contractor cleaned off tie-in and shaped the soil along the Cell 3A tie-in, using 8 laborers with flat-tipped shovels, 1 CAT D6N dozer, and 1 CAT smooth drum roller. 2. Contractor filled in rills and ruts from the previous rain events along the eastern half of the cell, using 2 CAT 740 off-road dump trucks, 2 CAT D6N dozers, and 1 CAT smooth drum compactor. 3. Contractor began excavating northern anchor trench along the northern perimeter berm, using 1 CAT 336 excavator and 1 laborer. 4. Contractor continued to clean off the southern tie-in along the western half of the cell, using 1 CAT 336 and 4 laborers with shovels. N/A 1. Observed cleaning and shaping soil against the Cell 3A tie-in. 2. Observed filling in of ruts and rills cause by previous rain event. 3. Observed excavation of anchor trench along the northern perimeter berm. 4. Observed cleaning off southern tie-in for future connection. Jonathan P. Usher, P.E. Rev. 2.10 20010020040006/01/2020Contractor cleaned washed-in silt off the tie-in, using flat tipped shovels, and shaped the soil interface to allow ESI to have a smooth transitionFilled in ruts and rills from the previous rain eventExcavated northern perimeter berm anchor trenchCleaned washed-in silt off the tie-in RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 06/02/2020 07:00 19:00 11.50 79 03/16/2020 James Fortson Mauricio Moreno 4 56 73 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Earnhardt Grading, Inc. 1. Contractor pulled back existing material, to allow for more room to tie-in along the southern tie-in, using 1 CAT 336 excavator, 2 CAT 740 off-road dump trucks, and 4 laborers with shovels. 2. Contractor continued placing structural fill along the western half of the proposed cell, using 2 CAT D6N dozers, 2 CAT 740 off-road dump trucks, and 1 CAT 815 compactor. N/A 1. Observed pulling back waste along southern tie-in. 2. Observed placement of structural fill in the western half of the proposed cell. Jonathan P. Usher, P.E. Rev. 2.10 20010020040006/02/2020Pulled back material to allow for more room to tie-in.Graded, placed, and compacted structural fill RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 06/03/2020 07:00 18:30 11.00 80 03/16/2020 James Fortson Mauricio Moreno 4 67 88 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Earnhardt Grading, Inc. 1. Contractor continued placing structural fill along the western half of the proposed cell, using 2 CAT D6N dozers, 2 CAT 740 off-road dump trucks, and 1 CAT 815 compactor. 2. Contractor re-graded and re-rolled the leachate corridor in the eastern half of the cell, using 1 CAT D6N and 1 CAT smooth drum compactor. 3. FML was being deployed in the easter hafl of the cell. Contractor continued to apply water and smooth drum roll all surfaces ahead of deployment, using 1 CAT smooth drum compactor and 1 off-road water truck. N/A 1. Observed placement of structural fill in the western half of the proposed cell. 2. Observed re-grading and re-rolling the eastern leachate collection corridor. 3. Observed contractor applying water and re-rolling subgrade surface along the eastern half of the cell. 4. Performed 6 nuclear density tests along top of subgrade. All tests passed 95% compaction by standard proctor. Jonathan P. Usher, P.E. Rev. 2.10 20010020040006/03/2020Graded, placed, and compacted structural fill Regraded and rerolled leachate collection corridorAdded moisture and re-rolled surface prior to FML deployment RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 06/04/2020 0700 1830 11.00 81 03/16/2020 James Fortson Mauricio Moreno 4 72 89 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Earnhardt Grading, Inc. 1. Contractor continued placing structural fill along the western half of the proposed cell, using 2 CAT D6N dozers, 2 CAT 740 off-road dump trucks, and 1 CAT 815 compactor. 2. Contractor continued to apply water and smooth drum all surfaces in the eastern half of the cell, where FML was being deployed, using 1 CAT smoothdrum compactor and 1 off-road water truck. N/A 1. Observed placement of structural fill in the western half of the proposed cell. 2. Observed applying water and re-rolling subgrade surface along the eastern half of the cell. 3. Performed 15 Nuclear Density tests along top of subgrade. All tests passed 95% compaction by standard proctor. Jonathan P. Usher, P.E. Rev. 2.10 20010020040006/04/2020Graded, placed, and compacted structural fill Added moisture and rerolll surface prior to FML deployment RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 06/05/2020 0700 1830 11.00 82 03/16/2020 James Fortson Mauricio Moreno 4 70 86 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 OTHER Earnhardt Grading, Inc. 1. Contractor continued placing structural fill along the western half of the proposed cell using 2 CAT D6N dozers, 2 CAT 740 off-road dump trucks, and 1 CAT 815 compactor. 2. Contractor continued to apply water and smooth drum all surfaces in the eastern half of the cell FML was being deployed on using 1 CAT smoothdrum compactor and 1 off-road water truck. N/A 1. Observed placement of structural fill in the western half of the proposed cell. 2. Observed applying water and rerolling subgrade surface along the eastern half of the cell. 3. Performed 7 Nuclear Density tests along top of subgrade. All tests passed 95% compaction by standard proctor. Jonathan P. Usher, P.E. Rev. 2.10 20010020040006/05/2020Graded, placed, and compacted structural fill Added moisture and rerolll surface prior to FML deployment APPENDIX C PHOTOGRAPHS CQA Report Photographs BLE Project No. J20-13334-02 Great Oak Landfill – Cells No. 3B, 4, & 5 Volume 1 of 3 Randolph County, North Carolina Photograph No. 1: Clearing and excavating overburden soils from Cells No. 3B, 4, & 5. Photograph No. 2: Drilling holes for blasting rock in Cells No. 3B, 4, & 5. CQA Report Photographs BLE Project No. J20-13334-02 Great Oak Landfill – Cells No. 3B, 4, & 5 Volume 1 of 3 Randolph County, North Carolina Photograph No. 3: Blasted rock in Cells No. 3B, 4, & 5. Photograph No. 4: Screening excavated soils for Cells No. 3B, 4, & 5. CQA Report Photographs BLE Project No. J20-13334-02 Great Oak Landfill – Cells No. 3B, 4, & 5 Volume 1 of 3 Randolph County, North Carolina Photograph No. 5: Exposing the existing geomembrane tie-in along the Cells No. 3B, 4, & 5 boundary. Photograph No. 6: Placing fill in Cells No. 3B, 4, & 5. CQA Report Photographs BLE Project No. J20-13334-02 Great Oak Landfill – Cells No. 3B, 4, & 5 Volume 1 of 3 Randolph County, North Carolina Photograph No. 7: Excavation of leachate collection channel in Cells No. 3B, 4, & 5. Photograph No. 8: Proof rolling the subgrade surface in Cells No. 3B, 4, & 5 using a loaded off-road truck. CQA Report Photographs BLE Project No. J20-13334-02 Great Oak Landfill – Cells No. 3B, 4, & 5 Volume 1 of 3 Randolph County, North Carolina Photograph No. 9: Finishing subgrade surface in Cells No. 3B, 4, & 5 prior to liner installation. Photograph No. 10: Finished subgrade surface in Cells No. 3B, 4, & 5 prior to liner installation. APPENDIX D REPORT OF GEOLOGIC OBSERVATIONS GEOLOGIC OBSERVATION REPORT: EASTERN PORTION OF CELLS 3B, 4, AND 5 GREAT OAK MSW LANDFILL RANDOLPH COUNTY, NORTH CAROLINA SOLID WASTE PERMIT NO. 7607-MSWLF-2015 Prepared For: Waste Management of South Carolina, Inc. 1047 Highway Church Road Elgin, South Carolina 29045 BLE Project Number J20-13334-02 BLE North Carolina Business License C-1538 May 28, 2020 May 28, 2020 North Carolina Department of Environmental Quality Division of Waste Management 1646 Mail Service Center Raleigh, NC 27699-1601 Attention: Ms. Christine Ritter, Hydrogeologist Subject: Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 Great Oak Landfill Randolph County, North Carolina Solid Waste Permit Number 7607-MSWLF-2015 BLE North Carolina Business License C-1538 BLE Project Number J20-13334-02 Dear Ms. Harrison: As authorized, Bunnell-Lammons Engineering, Inc. (BLE) has assembled this report of Geologic Observations carried out by North Carolina licensed geologists as related to cell subgrade preparation in the eastern portion of Cells 3B, 4, and 5, which are currently under construction. A separate report including the western portion of Cells 3B, 4, and 5 will be submitted at a later date. This project was required by the North Carolina Department of Environmental Quality (NCDEQ) and is to be submitted by BLE on behalf of Waste Management, Inc. for approval prior to deployment of the landfill liner system, as outlined in the Solid Waste Permit No. 7607-MSWLF-2015 issued for the landfill. The enclosed report describes the work performed and presents the results obtained. We appreciate the opportunity to serve as your geological and geotechnical consultant on this project and look forward to working with you in the future. If you have any questions, please contact us at (864) 288- 1265. Sincerely, BUNNELL LAMMONS ENGINEERING INC. T.J. Daniel, P.G. Mark Preddy, P.G. Staff Geologist Senior Geologist Licensed, North Carolina No. 2653 Licensed, North Carolina No. 1043 cc: Susan Harrison, P.E. – Waste Management Jonathan Usher, P.E. – Bunnell Lammons Engineering Bjorn Sundquist, P.E. – Bunnell Lammons Engineering Rob Witcher, P.E. – Promus Engineering Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 i of i TABLE OF CONTENTS 1.0 PROJECT INFORMATION ........................................................................................................ 1 2.0 GEOLOGIC OBSERVATIONS ................................................................................................... 2 3.0 VERTICAL SEPARATION CERTIFICATION ........................................................................ 3 4.0 CONCLUSION .............................................................................................................................. 4 TABLES Table 1 Top of Rock Vertical Separation FIGURES Figure 1 Site Location Map Figure 2 Top of Rock Vertical Separation Survey APPENDICES Appendix A Rock Blasting Plan Appendix B Daily Reports and Field Sketches Appendix C Photographs Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 1 of 4 1.0 PROJECT INFORMATION The existing Great Oak Municipal Solid Waste (MSW) Landfill is located on Old Cedar Falls Road approximately four (4) miles northeast of Asheboro, North Carolina (Figure 1). The landfill is owned and operated by Waste Management (WM). The landfill development is being implemented in phases as new solid waste cells are needed. To date, Cell Nos. 1A, 1B, 2, and 3A have been constructed. Cell No’s. 3B, 4 and 5 are currently under construction and are nearing completion. Subgrade preparation activities have been completed in the eastern portion of Cells 3B, 4, and 5 and liner installation is ready to proceed at the approval of this geologic observation report. Rock blasting was performed along the southern, west-central, and northern portions of the cell construction area. The approximate blast area occupies <20% of the 12.7-acre Cells 3B, 4, and 5 footprint. A North Carolina licensed BLE geologist (either Mr. Benjamin Nisbeth or Mr. T.J. Daniel) was on call to be on site within 48 hours post-blasting event to inspect the geologic subgrade. Three (3) geologic observations were performed in the eastern portion of Cells 3B, 4, and 5 on April 14, April 22, and May 14, 2020. Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 2 of 4 2.0 GEOLOGIC OBSERVATIONS Pursuant to the facilities Permit to Construct issued January 19, 2016 and in accordance with the facilities blasting plan for Cells 3B, 4, and 5 approved on March 23, 2020 (Appendix A) a brief summary of the geologic conditions encountered in the eastern portion of Cells 3B, 4, and 5 are as follows: • Contractor excavation exposed “unrippable” rock above the proposed subgrade elevation and resulted in the blasting and over excavation of rock from <20% of the 12.7-acre cell area. • In areas where rock had not been exposed, soil was observed as a brown, fine to medium sandy, SILT and is consistent with regolith derives from the Uwharrie Formation and Carolina Slate Belt. • The bedrock encountered within the cell area predominately consisted of a grey-green quartzite ranging in size from three (3) inches to twenty-five (25) feet in diameter. The quartzite was overlain in areas by a tan to white slate (meta-mudstone) and phyllite ranging in size from three (3) inches to two and a half (2.5) feet in diameter. No in situ quartz veins were observed within the exposed rock; however, there were several boulders ranging from three (3) inches to two (2) feet in diameter amongst the shot rock, indicating isolated intrusive quartz veins were present. • Strike and dip values were taken when encountered on exposed in situ bedrock (see Appendix B) and were consistent with the range of values denoted in the Site Hydrogeologic Report (SHR) prepared by Golder Associates and dated December, 2014. A more detailed summary of geologic observations and field sketches for this subgrade inspection of the eastern portion of Cells 3B, 4, and 5 is included in Appendix B of this report. In areas where a greater than four (4) foot separation between the top of rock and proposed landfill subgrade was achieved, as much shot rock as feasible was removed by the contractor. In the event that any shot rock was left behind structural fill was placed above and around these areas and proof rolled with a loaded CAT 740 dump truck to ensure that proper stability was achieved. Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 3 of 4 3.0 VERTICAL SEPARATION CERTIFICATION Pursuant to rule 15A NCAC 13B.1624(b)(4), for municipal solid waste landfills, and the facilities approved Permit to Construct, the top of the landfill subgrade and subsequent bottom of the liner system must maintain a minimum four (4) foot vertical separation from the top of bedrock. Prior to blasting within the cell footprint, Survey Carolina, PLLC., was contracted to survey the initial elevations of bedrock. These same northings and easting were surveyed again after blasting was complete and the appropriate amount of shot rock was removed. Table 1 shows the total separation between top of rock and top of subgrade in the eastern portion of Cells 3B, 4, and 5 to ensure that a minimum of four (4) feet of separation was achieved. A plot of the bedrock survey locations in the eastern cell area can be found on Figure 2. Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 4 of 4 4.0 CONCLUSION Bedrock that was exposed in <20% of the 12.7 acre Cells 3B, 4, and 5 footprint was exposed, blasted, and removed to create a four (4) foot vertical separation from top of bedrock to the top of subgrade. A North Carolina licensed geologist was mobilized to the site three (3) times in order to observe the exposed geologic subgrade in the eastern portion of Cells 3B, 4, and 5 and to ensure that no impacts to the integrity of the environmental monitoring system had occurred. All surveyed locations were shown to have a minimum of at least four (4.0) feet of separation between the top of bedrock and the top of subgrade. A separate report will be prepared and submitted for the western portion of Cells 3B, 4, and 5 at a later date. TABLES Point NumberNorthing (ft)Easting (ft)Base Elevation (ft)Subgrade Below Liner (ft)Difference Between Base Elevation and Subgrade (ft)Top of Rock (ft)Depth to Rock Below Liner (ft)1102728005.771777102.89633.19633.230.05628.744.501103727975.091777060.57634.00634.030.03629.574.461105727933.181777115.24632.00632.040.04627.844.201112727699.211776755.64647.99648.040.05643.774.271113727714.091776692.29650.00650.050.05645.854.201114727700.371776654.25650.68650.710.03646.644.071115727801.841776690.16652.19652.200.01647.734.471116727732.711776665.70651.16651.210.05647.074.141117727765.271776743.72649.14649.160.02645.054.111121727682.471776677.54652.00652.000.00647.684.321125727634.121776784.78660.00660.030.03655.264.761126727657.581776838.23660.00660.030.03655.264.771127727684.701776775.60650.00650.010.01645.694.321128727701.161776813.13650.00650.060.06645.834.231138727566.331776817.80662.26662.330.07657.814.521139727538.771776800.02672.00672.060.06667.384.691163727490.451776874.88672.01672.070.07667.924.151167727977.791777141.22631.80631.810.01627.064.751168727992.681777149.89638.00638.010.01632.045.971169728001.241777154.88638.05638.090.04632.985.111178727963.961777200.62634.00634.040.04629.134.921179727960.081777197.47634.00634.000.00629.844.161180727940.111777203.57629.63629.690.06625.404.291181727910.361777188.16629.72629.780.07625.694.09Survey provided by Survey Carolina, PLLC., on May 26, 2020.RANDOLPH COUNTY, NORTH CAROLINAGEOLOGIC OBSERVATION REPORT - EASTERN PORTION OF CELLS 3B, 4, & 5Bunnell-Lammons Engineering, Inc. Project No. J20-13334-02Table 1TOP OF ROCK VERTICAL SEPARATIONGREAT OAK LANDFILL FIGURES SITE 200100200400 APPENDIX A Rock Blasting Plan / DE d W/ W , d , ,dy Edhd Et d / d s d d yd W s W / D s DE :d E, E E :dKKWD t, W D, K,,DD, d tE E :d t, W: W: E,D, DD,,D d t DE E :d t, WD DD, ,D,D :, D E E :d t, D:D WEDE E,D ,D D E E :dWD t, D , APPENDIX B Daily Reports and Field Sketches RECORD OF DAILY OBSERVATIONS CLIENT:DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME:WORK HOURS:NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/14/2020 10:00 13:15 3.25 30 03/16/2020 TJ DANIEL 68 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM OTHER N/A N/A -BLE Geologist T.J. Daniel observed the geologic subgrade in the southern corner of cells 3B, 4, and 5. -Soil observed to be a brown, fine to medium sandy, SILT. -Rock from approximately 100-300' north of cell 1B tie in in portion of blasting area observed to be a greyish green, massive, quartzite. -No obvious quartz veins within the quartzite were visible but several boulders of white quartz ranging from 6" to 2' in diameter were visible in left over shot rock. -Two joint features measured within quartzite with S1 strike = S80E and dip = 88 SW while S2 strike = N25W and dip = 76 NE. One apparent fracture was denoted in an in situ boulder with strike = S48W and dip = 49 NW. (continued on next page) Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQATECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017304/14/2020 TJ DANIEL -Rock from approximately 0-100' north of cell 1B tie in in portion of blasting area varies from a tan slate to a tan phyllite. The foliation of this formation has a strike = S25W and dip = 52 NE. -Rock was blasted deeper than necessary for 4' vertical separation from top of structural fill in several areas. -Observed blast area was approximately 300x200' in size with approximately 30% covered in >4" diameter shot rock of various geology. -TJD collected various rock samples to be brought back to BLE office for additional evaluation. Photos of geologic observations can be found on the solid waste server at: "\\BLEGVLSVR1\SolidWasteProjects\Great Oak Landfill\13334-02A Cells 3B, 4, and 5 Rock Blasting\Photos" and all photos at original resolution with geotags can be found at https://photos.app.goo.gl/nM85QrugxNa5yHP66. A more formal report will be prepared and submitted with BLE’s rock blasting certification letter, once all blasting activities have been completed. Jonathan P. Usher, P.E. 200100200400Approximate area withextensive >4" bouldersPhoto is facingsoutheast towardsactive face RECORD OF DAILY OBSERVATIONS CLIENT:DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME:WORK HOURS:NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 04/22/2020 10:15am 38 03/16/2020 Benjamin Nisbeth, P.G. 52 64 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM Geologic Observation Contractor was observed moving shot rock from the north end of the cell, to a stockpile located north of the cell. Contractor was also observed moving screened structural fill material from the structural fill stockpile to the fill area located near grids 32-33, 42-43, and 52-53. Materials were observed to be spread out with a CAT D6 bulldozer, and then compacted with a CT 815B sheepsfoot roller. Contractor performed proofroll in grids 3-4 adn 12-13. Rutting and pumping due to wet soils. Contractor was observed removing wet soils located near grids 3-4, and 12-13. N/A Upon arrival, rep conducted a geologic observation of the exposed shot rock located near grids 12-13. Area of shot rock observed was measured to be approximately 120 feet long (North-South axis), by approximately 45 feet wide (East-West axis). Area was observed to be covered in shot rock, ranging in size from less than an inch in diameter, up to approximately 2.5 feet in diameter. The shot rock was observed to consist mostly of partially weathered quartzite, with some light brown slate (meta-mudstone) mixed in along the south end. Quartz veins were not observed, however, small pieces of quartz were observed sporadically throughout the shot rock (2-5 inches in diameter). One Joint set was observed within the exposed quartzite, with the measured strike and dip as follows: Strike = N 28 W, Dip = 83 E; Strike = N 39 W, Dip = 84 E. Data collected today from the geologic observation will be reviewed and presented in a later report. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQATECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017304/22/2020 Benjamin Nisbeth, P.G. BLE rep also observed a proofroll of the subgrade located near grids 3-4 and 12-13. Area was observed to have not proofrolled successfully, with pumping and rutting of the soils observed. It was recommended that 8-12 inches of material be removed and replaced with the screened structural fill. Recommendations were communicated to Marc with Earnhardt Grading. It should be noted that the contractor began removing the wet soils prior to BLE rep departing the job site today. Rep also conducted soil density tests on the structural fill material that was being placed today near grids 32-33, 42-43, and 52-53. A total of five tests were conducted today. All five tests conformed with the required compaction. Rep also collected soil samples from the screened structural fill stockpile (total of six 5-gallon buckets), and transported them back to the lab for shipment to other labs and for in-house analysis. Rep also observed the geomembrane that had been delivered to the job site prior to today. Rep also observed that the rolls delivered (87 rolls) matched with the numbers on the packing slips. Jonathan P. Usher, P.E. 20010020040004/22/2020Geologic observation and proofroll areaStructural fill placement and density testing area RECORD OF DAILY OBSERVATIONS CLIENT:DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME:WORK HOURS:NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/14/2020 12:45 14:30 8.75 60 03/16/2020 Benjamin Nisbeth STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM Geologic Observation Contractor was observed staging soils near Grids 24 and 34 for fine grading activities. N/A Upon arrival, BLE rep observed a proofroll of the subgrade prior to placement of structural fill near Grids 49, 50, 51, and 56. Area was proofrolled with a loaded CAT 740 off-road dump truck. Area was observed to have proofrolled successfully with little to no deflection or rutting of the soils observed. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQATECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017305/14/2020 Benjamin Nisbeth Rep also attempted to conduct a geologic observation of the same area near grids 49, 50, 51, and 56. Rep observed several pockets of shot-rock consisting of weathered quartzite and weathered phylite, with boulders observed ranging in size from approximately 2 inches in diameter up to approximately 18 inches in diameter. The pockets of the weathered quartzite and phylite ranged in size from approximately 3 feet in diameter up to approximately 25 feet in diameter, spread sporadically throughout the 4 grids observed today. Residual soils had been graded across the area, so planer features (foliations, joint sets, fracture sets, etc.) were not observed during today’s visit. Subsequently, strike and dip measurements were not collected today. Jonathan P. Usher, P.E. 20010020040005/14/2020Approximate location of BLE proofroll observation APPENDIX C Photographs Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 Photograph #1: 4-foot excavation of blasted rock in the south-central portion of the blast area near existing Cell 1B taken on 4-14-20. Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 Photograph #2: Representative shot rock size and distribution in the northeastern corner of the blast area, taken 5-7-20. Geologic Observation Report: Eastern Portion of Cells 3B, 4, and 5 May 28, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 Photograph #3: A loaded CAT 740 off-road truck proof rolling a section of blasted and over excavated rock prior to the placement of structural fill, taken 5-14-20. GEOLOGIC OBSERVATION REPORT: WESTERN PORTION OF CELLS 3B, 4, AND 5 GREAT OAK MSW LANDFILL RANDOLPH COUNTY, NORTH CAROLINA SOLID WASTE PERMIT NO. 7607-MSWLF-2015 Prepared For: Waste Management of South Carolina, Inc. 1047 Highway Church Road Elgin, South Carolina 29045 BLE Project Number J20-13334-02 BLE North Carolina Business License C-1538 June 8, 2020 June 8, 2020 North Carolina Department of Environmental Quality Division of Waste Management 1646 Mail Service Center Raleigh, NC 27699-1601 Attention: Ms. Christine Ritter, Hydrogeologist Subject: Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 Great Oak Landfill Randolph County, North Carolina Solid Waste Permit Number 7607-MSWLF-2015 BLE North Carolina Business License C-1538 BLE Project Number J20-13334-02 Dear Ms. Harrison: As authorized, Bunnell-Lammons Engineering, Inc. (BLE) has assembled this report of Geologic Observations carried out by North Carolina licensed geologists as related to cell subgrade preparation in the western portion of Cells 3B, 4, and 5, which are currently under construction. A separate report including the eastern portion of Cells 3B, 4, and 5 was approved by the state on May 29, 2020. This project was required by the North Carolina Department of Environmental Quality (NCDEQ) and is to be submitted by BLE on behalf of Waste Management, Inc. for approval prior to deployment of the landfill liner system, as outlined in the Solid Waste Permit No. 7607-MSWLF-2015 issued for the landfill. The enclosed report describes the work performed and presents the results obtained. We appreciate the opportunity to serve as your geological and geotechnical consultant on this project and look forward to working with you in the future. If you have any questions, please contact us at (864) 288- 1265. Sincerely, BUNNELL LAMMONS ENGINEERING INC. T.J. Daniel, P.G. Bjorn Sundquist, P.E. Staff Geologist Senior Engineer Licensed, North Carolina No. 2653 Licensed, North Carolina No. 42473 cc: Susan Harrison, P.E. – Waste Management Jonathan Usher, P.E. – Bunnell Lammons Engineering Mark Preddy, P.G. – Bunnell Lammons Engineering Rob Witcher, P.E. – Promus Engineering Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 i of i TABLE OF CONTENTS 1.0 PROJECT INFORMATION ........................................................................................................ 1 2.0 GEOLOGIC OBSERVATIONS ................................................................................................... 2 3.0 VERTICAL SEPARATION CERTIFICATION ........................................................................ 3 4.0 CONCLUSION .............................................................................................................................. 4 TABLES Table 1 Top of Rock Vertical Separation FIGURES Figure 1 Site Location Map Figure 2 Top of Rock Vertical Separation Survey APPENDICES Appendix A Rock Blasting Plan Appendix B Daily Reports and Field Sketches Appendix C Photographs Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 1 of 4 1.0 PROJECT INFORMATION The existing Great Oak Municipal Solid Waste (MSW) Landfill is located on Old Cedar Falls Road approximately four (4) miles northeast of Asheboro, North Carolina (Figure 1). The landfill is owned and operated by Waste Management (WM). The landfill development is being implemented in phases as new solid waste cells are needed. To date, Cell Nos. 1A, 1B, 2, and 3A have been constructed. Cell No’s. 3B, 4 and 5 are currently under construction and are nearing completion. Subgrade preparation activities have been completed in the western portion of Cells 3B, 4, and 5 and liner installation is ready to proceed at the approval of this geologic observation report. Rock blasting was performed along the southwestern, west-central, and northwestern portions of the cell construction area. The approximate blast area occupies <20% of the 12.7-acre Cells 3B, 4, and 5 footprint. A North Carolina licensed BLE geologist (Mr. Benjamin Nisbeth) was on call to be on site within 48 hours post-blasting event to inspect the geologic subgrade. Two (2) geologic observations were performed in the western portion of Cells 3B, 4, and 5 on May 4, 2020 and May 7, 2020. Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 2 of 4 2.0 GEOLOGIC OBSERVATIONS Pursuant to the facilities Permit to Construct issued January 19, 2016 and in accordance with the facilities blasting plan for Cells 3B, 4, and 5 approved on March 23, 2020 (Appendix A) a brief summary of the geologic conditions encountered in the western portion of Cells 3B, 4, and 5 are as follows: • Contractor excavation exposed “unrippable” rock above the proposed subgrade elevation and resulted in the blasting and over excavation of rock from <20% of the 12.7-acre cell area. • In areas where rock had not been exposed, soil was observed as a brown, fine to medium sandy, SILT and is consistent with regolith derives from the Uwharrie Formation and Carolina Slate Belt. • The bedrock encountered within the cell area predominately consisted of a grey-green quartzite ranging in size from three (3) inches to two and a half (2.5) feet in diameter. The quartzite was overlain in areas by a tan to white slate (meta-mudstone) and phyllite ranging in size from three (3) inches to two and a half (2.5) feet in diameter. No in situ quartz veins were observed within the exposed rock; however, there were several boulders ranging from three (3) inches to two (2) feet in diameter amongst the shot rock, indicating isolated intrusive quartz veins were present. • No planar features were visible and as such no strike and dip values were taken within the western portion of Cells 3B, 4, and 5. A more detailed summary of geologic observations and field sketches for this subgrade inspection of the western portion of Cells 3B, 4, and 5 is included in Appendix B of this report. In areas where a greater than four (4) foot separation between the top of rock and proposed landfill subgrade was achieved, as much shot rock as feasible was removed by the contractor. In the event that any shot rock was left behind structural fill was placed above and around these areas and proof rolled with a loaded CAT 745 dump truck to ensure that proper stability was achieved. Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 3 of 4 3.0 VERTICAL SEPARATION CERTIFICATION Pursuant to rule 15A NCAC 13B.1624(b)(4), for municipal solid waste landfills, and the facilities approved Permit to Construct, the top of the landfill subgrade and subsequent bottom of the liner system must maintain a minimum four (4) foot vertical separation from the top of bedrock. Prior to blasting within the cell footprint, Survey Carolina, PLLC., was contracted to survey the initial elevations of bedrock. These same northings and easting were surveyed again after blasting was complete and the appropriate amount of shot rock was removed. Table 1 shows the total separation between top of rock and top of subgrade in the western portion of Cells 3B, 4, and 5 to ensure that a minimum of four (4) feet of separation was achieved. A plot of the bedrock survey locations in the western cell area can be found on Figure 2. Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 4 of 4 4.0 CONCLUSION Bedrock that was exposed in <20% of the 12.7 acre Cells 3B, 4, and 5 footprint was exposed, blasted, and removed to create a four (4) foot vertical separation from top of bedrock to the top of subgrade. A North Carolina licensed geologist was mobilized to the site three (3) times in order to observe the exposed geologic subgrade in the western portion of Cells 3B, 4, and 5 and to ensure that no impacts to the integrity of the environmental monitoring system had occurred. All surveyed locations were shown to have a minimum of at least four (4.0) feet of separation between the top of bedrock and the top of subgrade. A separate report was submitted for the eastern portion of Cells 3B, 4, and 5 and approved by the NCDEQ on May 29, 2020. TABLES Point Number Northing (ft) Easting (ft) Base Elevation (ft) Subgrade Below Liner (ft) Difference Between Base Elevation and Subgrade (ft) Top of Rock (ft) Depth to Rock Below Liner (ft) 1000 728316.14 1776474.34 710.19 710.26 0.07 705.80 4.46 1001 728225.38 1776432.36 708.69 708.76 0.07 704.61 4.15 1002 728134.61 1776390.39 707.69 707.74 0.05 703.57 4.17 1003 728043.85 1776348.42 707.10 707.17 0.07 702.75 4.42 1004 727951.89 1776309.12 707.99 708.05 0.06 703.96 4.09 1005 727872.72 1776277.67 709.84 709.87 0.03 705.41 4.46 1007 728313.18 1776481.36 710.20 710.20 0.00 705.50 4.70 1008 728308.30 1776478.97 710.12 710.14 0.02 705.65 4.49 1009 728222.24 1776439.15 708.69 708.70 0.01 704.23 4.47 1010 728131.48 1776397.17 707.68 707.68 0.00 703.12 4.56 1011 728040.71 1776355.20 707.09 707.13 0.04 702.98 4.15 1012 727948.75 1776315.91 708.00 708.02 0.02 703.74 4.28 1013 727869.38 1776284.38 709.86 709.90 0.04 704.98 4.92 1015 728283.06 1776552.61 687.99 688.04 0.05 683.54 4.50 1016 728278.46 1776550.66 687.99 688.04 0.05 683.46 4.58 1017 728267.43 1776546.00 684.00 684.07 0.07 679.71 4.36 1018 728214.83 1776519.91 683.64 683.70 0.06 679.30 4.40 1019 728162.24 1776493.82 683.27 683.29 0.02 679.22 4.07 1020 728094.58 1776429.33 692.67 692.71 0.04 687.42 5.29 1021 728026.47 1776365.30 702.00 702.00 0.00 697.28 4.72 1022 727993.80 1776346.91 702.78 702.84 0.06 698.51 4.33 1023 727943.09 1776328.15 703.53 703.60 0.07 699.25 4.35 1028 727929.23 1776358.13 702.00 702.06 0.06 697.70 4.36 1029 728092.38 1776552.26 673.04 673.06 0.02 668.90 4.16 1037 727795.49 1776423.32 683.00 683.03 0.03 679.00 4.03 1039 727752.81 1776467.14 672.00 672.01 0.01 667.67 4.34 1040 727763.08 1776476.70 667.40 667.47 0.07 663.36 4.11 1041 727866.89 1776454.59 686.15 686.20 0.05 681.11 5.09 1042 727896.14 1776530.02 674.29 674.31 0.02 670.15 4.16 1044 727858.25 1776554.53 664.00 664.00 0.00 659.67 4.33 1045 727810.67 1776515.62 665.70 665.75 0.05 661.57 4.18 1046 727838.78 1776485.10 675.92 675.92 0.00 671.35 4.57 1047 727898.06 1776406.36 694.07 694.11 0.04 689.81 4.30 1048 727983.03 1776420.20 692.68 692.71 0.03 688.19 4.52 1049 727939.58 1776475.11 683.37 683.42 0.05 678.90 4.52 1050 728038.18 1776488.04 682.58 682.61 0.03 677.78 4.83 1051 727981.78 1776546.74 672.48 672.49 0.01 667.71 4.78 1052 728160.09 1776595.04 672.57 672.57 0.00 667.71 4.86 1053 728227.80 1776637.82 672.09 672.12 0.03 667.84 4.28 1054 728239.52 1776642.77 676.34 676.38 0.04 671.82 4.56 1055 728244.13 1776644.72 676.34 676.34 0.00 671.93 4.41 1056 728214.19 1776715.55 667.17 667.22 0.05 663.13 4.09 1057 728209.58 1776713.61 667.17 667.23 0.06 662.97 4.26 1058 728197.86 1776708.65 662.93 662.93 0.00 658.87 4.06 1059 728110.19 1776659.67 662.87 662.88 0.01 658.79 4.09 1080 727719.33 1776520.26 669.92 669.94 0.02 665.47 4.47 1081 727730.47 1776527.42 665.48 665.53 0.05 661.33 4.20 1082 727778.63 1776580.74 662.80 662.81 0.01 658.52 4.29 1083 727878.79 1776604.64 660.91 660.93 0.02 656.64 4.29 1086 727844.31 1776641.55 658.86 658.89 0.03 654.56 4.33 1087 727809.82 1776678.47 656.81 656.81 0.00 652.28 4.53 1088 727746.60 1776645.86 659.06 659.06 0.00 654.67 4.39 1089 727684.83 1776610.53 662.00 662.01 0.01 657.73 4.28 1090 727697.87 1776578.15 663.56 663.61 0.05 659.27 4.34 1091 727686.64 1776570.91 668.00 668.04 0.04 663.57 4.47 1120 727632.79 1776654.35 669.51 669.57 0.06 665.13 4.44 1123 727587.09 1776725.15 670.80 670.86 0.06 666.45 4.41 1124 727616.21 1776743.94 660.00 660.07 0.07 655.49 4.58 Survey provided by Survey Carolina, PLLC., on June 8, 2020. RANDOLPH COUNTY, NORTH CAROLINA GEOLOGIC OBSERVATION REPORT - WESTERN PORTION OF CELLS 3B, 4, & 5 Bunnell-Lammons Engineering, Inc. Project No. J20-13334-02 Table 1 TOP OF ROCK VERTICAL SEPARATION GREAT OAK LANDFILL FIGURES 1 SITE 200100200400 APPENDIX A Rock Blasting Plan Carolina Drilling, Inc. 326 Railroad St. Mocksville, NC 27028 Jason Tutterow 336-607-4478 reesecrushing@yahoo.com -Blasting Plan Information for the Randleman Landfill 3597 Old Cedar Falls Rd. Procedures 1. Holes will be laid on a 6’x6’ box pattern to an 8’x8’ box pattern depending on rock density and depth. The average and most used pattern will be the 7’x7’ box pattern. 2. Holes will be drilled 3.5” inches in diameter maximum with an average depth of 15’ deep. So far, the cuts have ranged from 4.5’ to 18’ deep. 3. Holes will be drilled with Tamrock Ranger 800’ or a Sandvik DX800’ (same machine different name depending on year model). Each one of the machines has digital level on it for straight hole setup. 4. All explosives will be brought in daily and no explosives will be stored onsite overnight. Either Elite Blasting or Carolina Drilling will haul all explosives in accordance with the NCDOT and USDOT. 5. Dry holes will be loaded with a 1 ¼”x8” stick of Riodin dynamite and ANFO. Wet holes will be loaded with a booster and Riohit emulsion sticks. All holes will have a minimum stemming 5.5’. 6. Only non-electric blasting caps will be used 25/500ms factory delayed. 7. SDS sheet will be attached. 8. All holes will be loaded with non-sparking tools (depth gauges and loading poles). 9. The rock in this area is of medium thickness and will only take 3’ to 11’ of the boreholes to loaded with explosives. In this case our average stemming (78m) will be held at 5.5’ to 9’. 10. All holes will be wired with a minimum of 8ms of delay between them giving us 1 hole per delay. 11. The holes then will be walked over to make sure all connections are clean. 12. Vibratech will have all seismographs in place before any blasting is done. 13. Once the area is cleared by Earnhardt Grading and Carolina Drilling a series of horns will be sound. -Three short blast for a 5 minute warning -Two long blast for a 1 minute warning -One long blast for an all clear, back to work after the shot has been inspected to assure all holes have fired. Drilling Equipment -A Sandvik DX800 or Tamrock Ranger 800 will be used, this machine has a digital level on the boom that reads in the cab. Seismology and Preblast Surveys Vibratech is handling the preblast surveys and seismology on this project. All machines shall be calibrated within 6 months of the blast. Post Blast Report or Shot Report A shot report used by Carolina Drilling blaster will be attached to this plane. It will show the following as required. 1. Material data information on products used. 2. Drawing of shot, with hole diameter, depth, voids, etc. 3. Loading diagram with weights of explosives used 4. Amount and type of explosives 5. Delay and initiation method 6. Results and yardages 7. Vibratech will furnished readings 8. A blast damage report if necessary. Carolina Drilling 326 Railroad St. Mocksville, NC 27028 336-607-4478 Resumes -Jason Tutterow 546 N. Hiddenbrooke Dr. Advance, NC 27006 Date of Birth: 3/13/76 NCDL: 8735947 Job Title: Owner, Operator, Blaster, Blast Consultant, Project Manager Work History: Part time at Carolina Drilling (1990-1997) blasters helper Full time at Carolina Drilling (1997 until present) blaster, blast consultant, MSHA trained, OSHA 10 certified, Haz Mat training every 2 years, MSHA trained 2004 to 2018, Licensed blaster in the State of Tennessee -Randy Key 3660 Cash Dr. Winston-Salem, NC 27107 Date of Birth: 1/26/72 NCDL: 8005777 Job Title: Blaster Work History: Piedmont Explosives (July 1991-2006) blasters helper, driver, then blaster Austin Powder (Jan 2006-2017) blaster for quarries and construction Carolina Drilling (Nov 2017 until present) blaster, Haz Mat licensed driver, Haz Mat training every two years, MSHA trained 1991-2018, CDL Haz Mat -David Tanner 166 Westview Ave. Mocksville, NC 27028 Date of Birth: August 2, 1981 NCDL: 24434333 Job Title: Blaster Work History: Austin Powder (December 2005-May 2014) blasters assistant, driver Carolina Drilling (May 2014 until present) blaster, driver, MSHA trained since 2005 to 2018, Haz Mat training every two years, CDL Haz Mat -Jerry Hebert 110 Shady Meadow Circle Cary, NC 27513 Date of Birth: 9/23/81 NCDL: 33759347 Job Title: Blaster Work History: McDowell’s Auto Body (June 1999-March 2010) Park Construction of NC (March 2010-November 2016) Carolina Drilling (Nov 2016 until present) blaster, driver, Haz Mat trained every two years, CDL Haz Mat, tunnel blast daily (1 to 4 times per day) -Keith Dunlap 236 L. Moore Rd. Seagrove, NC 23741 Date of Birth: 9/13/57 NCDL: 2661159 Job Title: Blaster/Project Manager Work History: Mid South Drilling (2000-2013) Carolina (2014 until present) Hazmat trained every 2 years, head blaster of Carolina Drilling APPENDIX B Daily Reports and Field Sketches RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/04/2020 11:30 14:30 10.0 50 03/16/2020 Benjamin Nisbeth, P.G. 4 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 Geologic Observation Contractor was observed to be removing soils and blast from from the northeast area of the cell today. Material was loaded onto three CAT 745 Off-Road dump trucks and hauled to the stockpile located north of the cell. Rep also observed contractor blasting rock near Grid 21. Prior to departing the job site, rep observed contractor beginning to haul structural fill from the structural fill stockpile to the cell near the northwest corner (Grids 47 and 37). N/A Upon arrival, rep observed a proofroll of the subgrade prior to placement of structural fill, located in Grids 16-20, 26-30, 36-40, and 46-50. Area was observed to have proofrolled successfully with a loaded Off-road dump truck (CAT 745). Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQA TECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 19017305/04/2020 Benjamin Nisbeth, P.G. Rep conducted a geologic observation of the exposed rock and weathered rock after blasting in Grids 47-49, 55, and 56. Area observed was measured to be approximately 300 feet long, by 35 feet wide, from the northwest corner of the cell headed southeast along the west edge of the cell. Rep observed loose boulders approximately 4 inches in diameter, up to approximately 2.5 feet in diameter. Rep observed weathered and partially weathered light brown to white phylite in the south 150 feet, with gray quartzite in the middle section (approximately 85 feet in length), and weathered phylite with pieces of quartzite in the north 65 feet. Rep did not observe any exposed quartz veins today. Additionally, suitable planar features (joint sets, foliations, fracture planes) were not exposed today, so no strike and dip measurements could be obtained. Jonathan P. Usher, P.E. 20010020040005/04/2020Proofroll areaProofroll areaGeologic observation area RECORD OF DAILY OBSERVATIONS CLIENT: DATE:Project Day Number ARRIVAL TIME:Notice to Proceed Date: DEPARTURE TIME: WORK HOURS: NAME ONSITE BLE PERSONNEL: WEATHER: °F TEMPERATURE MORNING LOW: DAYTIME HIGH:°F SITE ACTIVITIES CONTRACTOR ACTIVITIES: TECHNICIAN ACTIVITIES: RECORD REVIEWED & APPROVED BY: Signature REPRESENTING CONSTRUCTION ISSUES: VISITORS: RAIN WINDY SUNNY PTLY CLOUDY CLOUDY BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 WASTE MANAGEMENT 05/07/2020 11:45 13:45 9.0 53 03/16/2020 Benjamin Nisbeth, P.G. 4 41 60 STRUCTURAL FILL PLACEMENT GEOMEMBRANE PROTECTIVE COVER LEACHATE COLLECTION SYSTEM 4 Geologic Observation Contractor was observed to be removing landfill waste from the existing landfill cell, located west of the cell under construction, in order to expose the landfill liner to tie into it. Material was loaded onto three CAT 745 off-road dump trucks, and hauled to the active face of the landfill. N/A Upon arrival, BLE representative observed a proofroll of the cell subgrade prior to placement of structural fill near Grids 1, 7-9, 16-19, and 26-29. Area was proofrolled with a loaded CAT 745 off-road dumptruck. Area was observed to have proofrolled successfully with very little to no movement of the subgrade observed. Jonathan P. Usher, P.E. Rev. 2.10 RECORD OF DAILY OBSERVATIONS DATE: BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. CQA TECHNICIAN: RECORD REVIEWED & APPROVED BY: Signature GREAT OAK LANDFILL CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4 AND 5 RANDOLPH COUNTY, NORTH CAROLINA J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 Benjamin Nisbeth, P.G. BLE Representative also conducted a geologic observation of the exposed shot-rock located near Grids 1, 7, 8, 18, and 28. Rep observed that these areas were comprised mainly of boulders of gray to green quartzite, ranging in size from approximately 3 inches in diameter to approximately 2 feet in diameter. Quartz veins were not observed today in the exposed shot-rock. Additionally, planer features (joint sets, foliations, fractures, etc.) were not observed in any exposed, undisturbed bedrock, so strike and dip measurements were not collected today. Jonathan P. Usher, P.E. 05/07/2020 20010020040005/07/2020Geologic observationProofroll area APPENDIX C Photographs Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 Photograph #1: Representative size of blast rock in southwestern corner of the western portion of Cells 3B, 4, and 5 looking southeast taken 5-4-20. Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 Photograph #2: Representative shot rock size and distribution in the northwestern corner of the blast area, taken 5-7-20. Geologic Observation Report: Western Portion of Cells 3B, 4, and 5 June 8, 2020 Great Oak MSW Landfill – Randolph Co., North Carolina BLE Project No. J20-13334-02 Photograph #3: A loaded CAT 745 off-road truck proof rolling a section of blasted and over excavated rock prior to the placement of structural fill, taken 5-7-20. GRAIN SIZE DISTRIBUTION TEST RESULTS ATTERBERG LIMIT TEST RESULTS STANDARD PROCTOR TEST RESULTS STRUCTURAL FILL FILL, SUBGRADE STRUCTURAL SUMMARY OF LABORATORY TEST RESULTS: CONFORMANCE TESTS SUMMARY OF D&O PLAN: STRUCTURAL FILL TABLE OF CONTENTS: LABORATORY TEST RESULTS: APPENDIX E SUMMARY OF D&O PLAN: STRUCTURAL FILL REQUIRED NUMBER REQUIRED NUMBER OF OF TESTS TEST METHOD FREQUENCY TESTS PERFORMED* FIELD TEST DENSITY (Structural Fill) ASTM D 6938 or D 2937 1 / 1,500 cy 39 96 DENSITY (Subgrade) 1 / 10,000 sf 56 65 LABORATORY TEST MOISTURE-DENSITY (PROCTOR) ASTM D 698 1 / 10,000 cy 7 7 GRAIN SIZE ASTM D 422 1 / 10,000 cy 7 7 ATTERBERG LIMITS ASTM D 4318 1 / 10,000 cy 7 7 * The number of tests shown represent "passing" tests. BORROW & STOCKPILE SAMPLES (BEFORE PLACEMENT): SUMMARY OF CQA CONFORMANCE TESTING REQUIREMENTS CONSTRUCTION OF CELLS 3B, 4, & 5 Cells 3B, 4, & 5 = 552,736 sq ft (12.7 Acres) STRUCTURAL FILL & SUBGRADE GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA DESIGN & OPERATION PLAN BLE Project No. J19-13334-02 PROMUS Engineering Project No. 190173 ASTM D 6938 or D 2937 SUMMARY OF LABORATORY TEST RESULTS: STRUCTURAL FILL AND SUBGRADE MATERIAL DESCRIPTION MAXIMUM OPTIMUM GRAVEL SAND SILT & CLAY LIQUID PLASTICITY DRY MOISTURE CONTENT CONTENT CONTENT LIMIT INDEX DENSITY CONTENT (USCS) % % % % % pcf % Light brown fi.-co. sandy SILT (ML) 6.0 21.0 73.0 40 13 103.5 17.7 Light brown fi.-co. sandy CLAY (CL) 8.2 19.2 72.6 38 13 105.9 17.0 Light brown fi.-co. sandy CLAY (CL) 5.1 22.1 72.8 40 15 104.3 18.8 Light brown fi.-co. sandy CLAY (CL) 5.9 24.4 69.7 37 12 108.0 17.3 Light brown fi.-co. sandy CLAY (CL) 9.0 24.0 67.0 38 13 108.7 16.5 Light brown fi.-co. sandy CLAY (CL) 11.4 16.2 72.4 40 16 107.0 16.1 Light brown fi.-co. sandy CLAY (CL) 9.9 11.9 78.2 38 13 107.3 16.4 BUNNELL-LAMMONS ENGINEERING INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NO. 190173 NUMBER PROCTOR PARAMETERS Cells 3B, 4, & 5 = 552,736 sq ft (12.7 Acres) SUMMARY OF LABORATORY TEST RESULTS - STRUCTURAL FILL AND SUBGRADE SOILS CONSTRUCTION OF CELLS 3B, 4, & 5 CONSTRUCTION QUALITY ASSURANCE GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA SFSP-6 SFSP-7 SFSP-2 SIEVE ANALYSIS ATTERBERG LIMITSSAMPLE SFSP-1 SFSP-4 SFSP-5 SFSP-3 LABORATORY TEST SUMMARY STANDARD PROCTOR TEST RESULTS MOISTURE DENSITY RELATIONSHIP Dry density, pcf95 100 105 110 115 120 Water content, % 0 5 10 15 20 25 30 ZAV for Sp.G. = 2.70 Test specification:ASTM D 698-12 Method A Standard ML A-6(9)40 13 6.0 73.0 Light brown fi.-co. sandy SILT 13334-02 Waste Management Elev/Classification Nat.Sp.G.LL PI % >% < Depth USCS AASHTO Moist.#4 No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Source of Sample: Prot. Cover Sample Number: SFSP-1 Bunnell Lammons Engineering, Inc. Greenville, SC Figure Maximum dry density = 103.5 pcf Optimum moisture = 17.7 % Great Oak Landfill Cells 3B, 4 & 5 MOISTURE DENSITY RELATIONSHIP Dry density, pcf95 100 105 110 115 120 Water content, % 0 5 10 15 20 25 30 ZAV for Sp.G. = 2.70 Test specification:ASTM D 698-12 Method A Standard CL A-6(9)38 13 8.2 72.6 Light brown fi.-co. sandy CLAY 13334-02 Waste Management Elev/Classification Nat.Sp.G.LL PI % >% < Depth USCS AASHTO Moist.#4 No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Source of Sample: Prot. Cover Sample Number: SFSP-2 Bunnell Lammons Engineering, Inc. Greenville, SC Figure Maximum dry density = 105.9 pcf Optimum moisture = 17.0 % Great Oak Landfill Cells 3B, 4 & 5 MOISTURE DENSITY RELATIONSHIP Dry density, pcf95 100 105 110 115 120 Water content, % 0 5 10 15 20 25 30 ZAV for Sp.G. = 2.70 Test specification:ASTM D 698-12 Method A Standard CL A-6(10)40 15 5.1 72.8 Light brown fi.-co. sandy CLAY 13334-02 Waste Management Elev/Classification Nat.Sp.G.LL PI % >% < Depth USCS AASHTO Moist.#4 No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Source of Sample: Prot. Cover Sample Number: SFSP-3 Bunnell Lammons Engineering, Inc. Greenville, SC Figure Maximum dry density = 104.3 pcf Optimum moisture = 18.8 % Great Oak Landfill Cells 3B, 4 & 5 MOISTURE DENSITY RELATIONSHIP Dry density, pcf95 100 105 110 115 120 Water content, % 0 5 10 15 20 25 30 ZAV for Sp.G. = 2.70 Test specification:ASTM D 698-12 Method A Standard CL A-6(8)37 12 5.9 69.7 Light brown fi.-co. sandy CLAY 13334-02 Waste Management Elev/Classification Nat.Sp.G.LL PI % >% < Depth USCS AASHTO Moist.#4 No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Source of Sample: Prot. Cover Sample Number: SFSP-4 Bunnell Lammons Engineering, Inc. Greenville, SC Figure Maximum dry density = 108.0 pcf Optimum moisture = 17.3 % Great Oak Landfill Cells 3B, 4 & 5 MOISTURE DENSITY RELATIONSHIP Dry density, pcf95 100 105 110 115 120 Water content, % 0 5 10 15 20 25 30 ZAV for Sp.G. = 2.70 Test specification:ASTM D 698-12 Method A Standard CL A-6(8)38 13 9.0 67.0 Light brown fi.-co. sandy CLAY 13334-02 Waste Management Elev/Classification Nat.Sp.G.LL PI % >% < Depth USCS AASHTO Moist.#4 No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Source of Sample: Prot. Cover Sample Number: SFSP-5 Bunnell Lammons Engineering, Inc. Greenville, SC Figure Maximum dry density = 108.7 pcf Optimum moisture = 16.5 % Great Oak Landfill Cells 3B, 4 & 5 MOISTURE DENSITY RELATIONSHIP Dry density, pcf95 100 105 110 115 120 Water content, % 0 5 10 15 20 25 30 ZAV for Sp.G. = 2.70 Test specification:ASTM D 698-12 Method A Standard CL A-6(11)40 16 11.4 72.4 Light brown fi.-co. sandy CLAY 13334-02 Waste Management Elev/Classification Nat.Sp.G.LL PI % >% < Depth USCS AASHTO Moist.#4 No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Source of Sample: Prot. Cover Sample Number: SFSP-6 Bunnell Lammons Engineering, Inc. Greenville, SC Figure Maximum dry density = 107.0 pcf Optimum moisture = 16.1 % Great Oak Landfill Cells 3B, 4 & 5 MOISTURE DENSITY RELATIONSHIP Dry density, pcf95 100 105 110 115 120 Water content, % 0 5 10 15 20 25 30 ZAV for Sp.G. = 2.70 Test specification:ASTM D 698-12 Method A Standard CL A-6(10)38 13 9.9 78.2 Light brown fi.-co. sandy CLAY 13334-02 Waste Management Elev/Classification Nat.Sp.G.LL PI % >% < Depth USCS AASHTO Moist.#4 No.200 TEST RESULTS MATERIAL DESCRIPTION Project No.Client:Remarks: Project: Source of Sample: Prot. Cover Sample Number: SFSP-7 Bunnell Lammons Engineering, Inc. Greenville, SC Figure Maximum dry density = 107.3 pcf Optimum moisture = 16.4 % Great Oak Landfill Cells 3B, 4 & 5 ATTERBERG LIMIT TEST RESULTS LIQUID AND PLASTIC LIMITS TEST REPORT PLASTICITY INDEX0 10 20 30 40 50 60 LIQUID LIMIT 0 10 20 30 40 50 60 70 80 90 100 110 CL-ML CL or OL CH or O H ML or OL MH or OH Dashed line indicates the approximate upper limit boundary for natural soils 47 SOIL DATA SYMBOL SOURCE NATURAL USCSSAMPLEDEPTHWATERPLASTICLIQUIDPLASTICITY NO.CONTENT LIMIT LIMIT INDEX (%)(%)(%)(%) Bunnell Lammons Engineering, Inc. Greenville, SC Client: Project: Project No.:Figure Waste Management Great Oak Landfill Cells 3B, 4 & 5 13334-02 Prot. Cover SFSP-1 27 40 13 ML Prot. Cover SFSP-2 25 38 13 CL Prot. Cover SFSP-3 25 40 15 CL Prot. Cover SFSP-4 25 37 12 CL Prot. Cover SFSP-5 25 38 13 CL LIQUID AND PLASTIC LIMITS TEST REPORT PLASTICITY INDEX0 10 20 30 40 50 60 LIQUID LIMIT 0 10 20 30 40 50 60 70 80 90 100 110 CL-ML CL or OL CH or O H ML or OL MH or OH Dashed line indicates the approximate upper limit boundary for natural soils 47 SOIL DATA SYMBOL SOURCE NATURAL USCSSAMPLEDEPTHWATERPLASTICLIQUIDPLASTICITY NO.CONTENT LIMIT LIMIT INDEX (%)(%)(%)(%) Bunnell Lammons Engineering, Inc. Greenville, SC Client: Project: Project No.:Figure Waste Management Great Oak Landfill Cells 3B, 4 & 5 13334-02 Prot. Cover SFSP-6 24 40 16 CL Prot. Cover SFSP-7 25 38 13 CL GRAIN SIZE DISTRUBTION TEST RESULTS Bunnell Lammons Engineering, Inc. Greenville, SC Client: Project: Project No.:Figure Waste Management Great Oak Landfill Cells 3B, 4 & 5 13334-02 SYMBOL SOURCE SAMPLE DEPTH Material Description USCSNO.(ft.) SOIL DATAPERCENT FINER0 10 20 30 40 50 60 70 80 90 100 GRAIN SIZE -mm 0.0010.010.1110100 % +3"Coarse % Gravel Fine Coarse Medium % Sand Fine Silt % Fines Clay 0.0 0.0 6.0 4.8 6.1 10.1 73.0 0.0 0.0 8.2 3.8 6.0 9.4 72.6 0.0 0.0 5.1 7.2 6.4 8.5 72.8 0.0 0.0 5.9 6.2 8.1 10.1 69.7 0.0 0.0 9.0 6.4 7.5 10.1 67.06 in.3 in.2 in.1½ in.1 in.¾ in.½ in.3/8 in.#4#10#20#30#40#60#100#140#200Particle Size Distribution Report Prot. Cover SFSP-1 Light brown fi.-co. sandy SILT ML Prot. Cover SFSP-2 Light brown fi.-co. sandy CLAY CL Prot. Cover SFSP-3 Light brown fi.-co. sandy CLAY CL Prot. Cover SFSP-4 Light brown fi.-co. sandy CLAY CL Prot. Cover SFSP-5 Light brown fi.-co. sandy CLAY CL Bunnell Lammons Engineering, Inc. Greenville, SC Client: Project: Project No.:Figure Waste Management Great Oak Landfill Cells 3B, 4 & 5 13334-02 SYMBOL SOURCE SAMPLE DEPTH Material Description USCSNO.(ft.) SOIL DATAPERCENT FINER0 10 20 30 40 50 60 70 80 90 100 GRAIN SIZE -mm 0.0010.010.1110100 % +3"Coarse % Gravel Fine Coarse Medium % Sand Fine Silt % Fines Clay 0.0 0.0 11.4 3.9 4.4 7.9 72.4 0.0 0.0 9.9 1.8 3.0 7.1 78.26 in.3 in.2 in.1½ in.1 in.¾ in.½ in.3/8 in.#4#10#20#30#40#60#100#140#200Particle Size Distribution Report Prot. Cover SFSP-6 Light brown fi.-co. sandy CLAY CL Prot. Cover SFSP-7 Light brown fi.-co. sandy CLAY CL APPENDIX F FIELD TEST RESULTS: STRUCTURAL FILL & SUBGRADE FIELD DENSITY TEST GRIDMAP CHECKLIST FIELD DENSITY TEST RESULTS SUBGRADE FIELD DENSITY TEST GRIDMAP CHECKLIST Cells 3B, 4 & 5 = 552,736 SF (12.7 AC) MAP GRID MAP GRID MAP GRID MAP GRID NUMBER NUMBER NUMBER NUMBER 1 SFD-61 15 SFD-70 29 SFD-82 43 SFD-84 2 SFD-60 16 SFD-90 30 SFD-81 44 SFD-42, SFD-55 3 SFD-59 17 SFD-27 31 SFD-80 45 SFD-46 4 SFD-58 18 SFD-28 32 SFD-25 46 SFD-35 5 SFD-71 19 SFD-39, SFD-63 33 SFD-79 47 SFD-33, SFD-64 6 SFD-72 20 SFD-40, SFD-62 34 SFD-41, SFD-74 48 SFD-34, SFD-65 7 SFD-68 21 SFD-83 35 SFD-47 49 SFD-36 8 SFD-85 22 SFD-37 36 SFD-92 50 SFD-93 9 SFD-86 23 SFD-38, SFD-56 37 SFD-31 51 SFD-94 10 SFD-87 24 SFD-73 38 SFD-32 52 SFD-95 11 SFD-88 25 SFD-48 39 SFD-76 53 SFD-96 12 SFD-89 26 SFD-91 40 SFD-77 54 SFD-45 13 SFD-57 27 SFD-29 41 SFD-78 55 SFD-43, SFD-67 14 SFD-69 28 SFD-30 42 SFD-26 56 SFD-44, SFD-66 PROMUS ENGINEERING PROJECT NO. 190173 FIELD DENSITY TEST NO. FIELD DENSITY TEST NO.FIELD DENSITY TEST NO. FIELD DENSITY TEST NO. FIELD DENSITY GRID MAP CHECKLIST CONSTRUCTION QUALITY ASSURANCE - CELLS 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 Cell 3B, 4 & 5 Gridmap Checklist STRUCTURAL FILL AND SUBGRADE FIELD DENSITY TEST RESULTS Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILL FIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-1 6 SF-6 H 117.2 22.4 0.1 95.7 98.2 95 Pass 10 SFD-2 6 SF-6 H 116.2 21.2 -1.1 95.9 98.4 95 Pass 10 SFD-3 6 SF-6 H 117.5 21.8 -0.5 96.5 99 95 Pass 10 1 SF-1 H 118.8 12.0 2 SF-2 H 113.0 13.9 3 SF-3 H 112.0 13.5 4 SF-4 H 112.6 14.2 5 SF-5 H 112.3 15.6 6 SF-6 H 97.5 22.3 7 SF-7 H 121.3 13.3 8 SF-8 H 99.7 18.9 9 SF-9 H 98.7 17.3 10 SF-10 103.6 18.2 Ben Nisbeth 04/02/0020 Jonathan P. Usher, P.E. NOTE: N/A 39 30 29 Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-4 10 SF-10 115.0 16.9 -1.3 98.9 95.5 95 Pass 16 SFD-5 10 SF-10 119.5 15.8 -2.4 101.9 98.4 95 Pass 36 SFD-6 10 SF-10 118.6 15.7 -2.5 104.3 100.7 95 Pass 28 SFD-7 10 SF-10 106.6 20.3 2.1 98.7 95.3 95 Pass 8 SFD-8 10 SF-10 105.8 16.2 -2.0 98.5 95.1 95 Pass 21 SFD-9 10 SF-10 116.0 15.2 -3.0 101.6 98.1 95 Pass 41 1 SF-1 H 118.8 12.0 2 SF-2 H 113.0 13.9 3 SF-3 H 112.0 13.5 4 SF-4 H 112.6 14.2 5 SF-5 H 112.3 15.6 6 SF-6 H 97.5 22.3 7 SF-7 H 121.3 13.3 8 SF-8 H 99.7 18.9 9 SF-9 H 98.7 17.3 10 SF-10 103.6 18.2 Tommy Anderson 04/06/2020 Jonathan P. Usher, P.E. 5701 1076 836 NOTE: N/A 4 4 4 4 4 4 Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-10 6 SF-6 H 116.7 23.7 1.4 94.3 96.7 95 Pass 53 SFD-11 6 SF-6 H 115.1 22.8 0.5 93.7 96.1 95 Pass 52 SFD-12 6 SF-6 H 112.8 21.5 -0.8 92.9 95.3 95 Pass 51 SFD-13 6 SF-6 H 116.5 20.8 -1.5 96.4 98.9 95 Pass 41 SFD-14 6 SF-6 H 117.8 22.8 0.5 95.9 98.4 95 Pass 42 SFD-15 6 SF-6 H 119.1 22.7 0.4 97.1 99.6 95 Pass 0.5 26 SFD-16 6 SF-6 H 116.9 20.5 -1.8 97.0 99.5 95 Pass 43 SFD-17 6 SF-6 H 115.8 20.3 -2.0 96.3 98.8 95 Pass 49 SFD-18 6 SF-6 H 117.0 24.0 1.7 94.3 96.7 95 Pass 50 SFD-19 6 SF-6 H 115.8 21.8 -0.5 95.1 97.5 95 Pass 40 1 SF-1 H 118.8 12.0 2 SF-2 H 113.0 13.9 3 SF-3 H 112.0 13.5 4 SF-4 H 112.6 14.2 5 SF-5 H 112.3 15.6 6 SF-6 H 97.5 22.3 7 SF-7 H 121.3 13.3 8 SF-8 H 99.7 18.9 9 SF-9 H 98.7 17.3 10 SF-10 103.6 18.2 James Fortson 04/15/2020 Jonathan P. Usher, P.E. 1881 654 NOTE: N/A 3 3 3 3 3 3 3 3 3 Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-20 6 SF-6 H 117.5 21.8 -0.5 96.5 99.0 95 Pass 32 SFD-21 6 SF-6 H 115.8 20.5 -1.8 96.1 98.6 95 Pass 31 1 SF-1 H 118.8 12.0 2 SF-2 H 113.0 13.9 3 SF-3 H 112.0 13.5 4 SF-4 H 112.6 14.2 5 SF-5 H 112.3 15.6 6 SF-6 H 97.5 22.3 7 SF-7 H 121.3 13.3 8 SF-8 H 99.7 18.9 9 SF-9 H 98.7 17.3 10 SF-10 103.6 18.2 James Fortson 04/15/2020 Jonathan P. Usher, P.E. 1881 654 NOTE: N/A 3 3 Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-22 5 SF-5 H 129.5 15.2 -0.4 112.4 100.1 95 Pass 3 52 SFD-23 5 SF-5 H 124.6 15.4 -0.2 108.0 96.2 95 Pass 2 43 SFD-24 5 SF-5 H 126.8 16.8 1.2 108.6 96.7 95 Pass 2 33 SFD-25 5 SF-5 H 129.1 16.8 1.2 110.5 98.4 95 Pass SG 32 SFD-26 5 SF-5 H 129.9 16.6 1 111.4 99.2 95 Pass SG 42 Ben Nisbeth 1 SF-1 H 118.8 12.0 04/22/2020 2 SF-2 H 113.0 13.9 Jonathan P. Usher, P.E.3 SF-3 H 112.0 13.5 4 SF-4 H 112.6 14.2 5 SF-5 H 112.3 15.6 6 SF-6 H 97.5 22.3 7 SF-7 H 121.3 13.3 8 9 10 SF-9 H SF-8 H SF-10 99.7 98.7 103.6 17.3 18.9 18.2 NOTE: N/A Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID 5 SFSP-5 122.8 13.9 -2.6 107.8 99.2 95 Pass SG 17 5 SFSP-5 122.3 13.6 -2.9 108.2 99.5 95 Pass SG 18 5 SFSP-5 122.8 14.1 -2.4 107.6 99.0 95 Pass SG 27 5 SFSP-5 123.6 14.2 -2.3 108.2 99.5 95 Pass SG 28 5 SFSP-5 125.4 14.3 -2.2 109.4 100.6 95 Pass SG 37 5 SFSP-5 123.6 13.7 -2.8 108.7 100.0 95 Pass SG 38 5 SFSP-5 125.2 13.6 -2.9 110.2 101.4 95 Pass SG 47 5 SFSP-5 124.6 13.7 -2.8 109.6 100.8 95 Pass SG 48 5 SFSP-5 123.8 13.6 -2.9 108.9 100.2 95 Pass SG 46 5 SFSP-5 124.6 14.1 -2.4 109.2 100.5 95 Pass SG 49 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 JIMMY BARTLETT 05/18/2020 Jonathan P. Usher, P.E.31423 NOTE: N/A SFD-36 SFD-35 SFD-34 SFD-33 SFD-32 SFD-31 SFD-30 SFD-29 SFD-28 SFD-27 Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID 5 SFSP-5 125.5 14.1 -2.4 110.0 101.2 95 Pass SG 22 5 SFSP-5 125.2 14.4 -2.1 109.4 100.6 95 Pass SG 23 5 SFSP-5 125.8 13.9 -2.6 110.4 101.6 95 Pass SG 19 5 SFSP-5 124.8 13.8 -2.7 109.6 100.8 95 Pass SG 20 5 SFSP-5 125.8 15.9 -0.6 108.5 99.8 95 Pass SG 34 5 SFSP-5 126.4 16.1 -0.4 108.8 100.1 95 Pass SG 44 5 SFSP-5 127.4 16.6 0.1 109.2 100.5 95 Pass SG 55 5 SFSP-5 127.2 16.7 0.2 109.0 100.3 95 Pass SG 56 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 JIMMY BARTLETT 05/18/2020 Jonathan P. Usher, P.E.31423 NOTE: N/A SFD-37 SFD-38 SFD-39 SFD-40 SFD-41 SFD-42 SFD-43 SFD-44 Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-45 3 SFSP-3 123.9 21.2 2.4 102.2 98.0 95 Pass SG 54 SFD-46 3 SFSP-3 124.1 21.4 2.6 102.3 98.1 95 Pass SG 45 SFD-47 3 SFSP-3 124.3 20.8 2.0 102.9 98.7 95 Pass SG 35 SFD-48 3 SFSP-3 124.4 20.0 1.2 103.7 99.4 95 Pass SG 25 SFD-49 3 SFSP-3 120.8 21.3 2.5 99.6 95.5 95 Pass 1 15 SFD-50 3 SFSP-3 123.6 21.4 2.6 101.8 97.6 95 Pass 1 6 SFD-51 3 SFSP-3 120.4 20.7 1.9 99.8 95.7 95 Pass 1.5 5 SFD-52 3 SFSP-3 124.1 21.2 2.4 102.4 98.2 95 Pass 1 14 SFD-53 3 SFSP-3 125.7 19.8 1.0 104.6 100.3 95 Pass 1 24 SFD-54 3 SFSP-3 121.8 21.6 2.8 100.2 96.1 95 Pass 1 34 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 James Fortson 05/26/2020 Jonathan P. Usher, P.E.836 NOTE: N/A Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-55 3 SFSP-3 118.4 18.1 -0.7 100.2 96.1 95 Pass SG 44 SFD-56 3 SFSP-3 118.4 19.0 0.2 99.5 95.4 95 Pass SG 23 SFD-57 3 SFSP-3 121.3 21.6 2.8 99.8 95.7 95 Pass 13 SFD-58 3 SFSP-3 123.7 19.2 0.4 103.8 99.5 95 Pass SG 4 SFD-59 3 SFSP-3 124.1 18.4 -0.4 104.8 100.5 95 Pass SG 3 SFD-60 3 SFSP-3 122.3 21.3 2.5 100.8 96.6 95 Pass SG 2 SFD-61 3 SFSP-3 120.3 20.9 2.1 99.5 95.4 95 Pass SG 1 SFD-62 3 SFSP-3 118.7 19.5 0.7 99.3 95.2 95 Pass SG 20 SFD-63 3 SFSP-3 120.5 21.2 2.4 99.4 95.3 95 Pass SG 19 SFD-64 3 SFSP-3 122.5 21.6 2.8 100.7 96.5 95 Pass SG 47 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 James Fortson 05/26/2020 Jonathan P. Usher, P.E.836 NOTE: N/A SG Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-65 3 SFSP-3 120.0 20.9 2.1 99.3 95.2 95 Pass SG 48 SFD-66 3 SFSP-3 124.2 21.0 2.2 102.6 98.4 95 Pass SG 56 SFD-67 3 SFSP-3 123.0 20.3 1.5 102.2 98.0 95 Pass SG 55 SFD-68 3 SFSP-3 121.4 21.6 2.8 99.8 95.7 95 Pass SG 7 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 James Fortson 05/26/2020 Jonathan P. Usher, P.E.836 NOTE: N/A Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-69 4 SFSP-4 130.6 17.0 -0.3 111.7 103.4 95 Pass SG 14 SFD-70 4 SFSP-4 131.4 19.2 1.9 110.2 102.0 95 Pass SG 15 SFD-71 4 SFSP-4 122.9 18.0 0.7 104.2 96.5 95 Pass SG 5 SFD-72 4 SFSP-4 123.6 16.2 -1.1 106.3 98.4 95 Pass SG 6 SFD-73 4 SFSP-4 127.9 19.4 2.1 107.1 99.2 95 Pass SG 24 SFD-74 4 SFSP-4 120.0 16.4 -0.9 103.1 95.5 95 Pass SG 34 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 James Fortson 06/03/2020 Jonathan P. Usher, P.E.836 NOTE: N/A Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-75 4 SFSP-4 123.9 17.4 0.1 105.6 97.8 95 Pass 2' below 39 SFD-76 4 SFSP-4 119.8 14.4 -2.9 104.7 96.9 95 Pass SG 39 SFD-77 4 SFSP-4 120.8 17.4 0.1 102.9 95.3 95 Pass SG 40 SFD-78 4 SFSP-4 126.4 20.3 3.0 105.1 97.3 95 Pass SG 41 SFD-79 4 SFSP-4 125.6 16.2 -1.1 108.1 100.1 95 Pass SG 33 SFD-80 4 SFSP-4 128.5 16.1 -1.2 110.7 102.5 95 Pass SG 31 SFD-81 4 SFSP-4 122.7 19.3 2.0 102.8 95.2 95 Pass SG 30 SFD-82 4 SFSP-4 120.3 16.5 -0.8 103.3 95.6 95 Pass SG 29 SFD-83 4 SFSP-4 122.1 17.3 0.0 104.1 96.4 95 Pass SG 21 SFD-84 4 SFSP-4 126.9 18.5 1.2 107.1 99.2 95 Pass SG 43 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 James Fortson 06/04/2020 Jonathan P. Usher, P.E.836 NOTE: N/A Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-85 4 SFSP-4 124.3 17.2 -0.1 106.1 98.2 95 Pass SG 8 SFD-86 4 SFSP-4 119.0 14.3 -3.0 104.1 96.4 95 Pass SG 9 SFD-87 4 SFSP-4 122.2 16.4 -0.9 105.0 97.2 95 Pass SG 10 SFD-88 4 SFSP-4 120.3 15.7 -1.6 104.0 96.3 95 Pass SG 11 SFD-89 4 SFSP-4 126.4 17.1 -0.2 108.0 100.0 95 Pass SG 12 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 James Fortson 06/04/2020 Jonathan P. Usher, P.E.836 NOTE: N/A Technician Date S/N:Reviewed By COUNTS Std. Count M: READINGS WET DENSITY (PCF) MOISTURE CONTENT (%) PERCENT MOISTURE OVER OMC (%) DRY DENSITY (PCF) MOISTURE COUNT DENSITY COUNT % COMP (%) REQ COMP (%)P/F FIELD DENSITY TEST NO.PROCTOR NUMBER Std. Count D:Proctor No.OMC(%) Maximum Dry Density(PCF) STRUCTURAL FILLFIELD DENSITY TEST RESULTS FOR NUCLEAR GAUGE (ASTM D 6938) CONSTRUCTION OF CELL NO. 3B, 4, & 5 GREAT OAK LANDFILL RANDOLPH COUNTY, NORTH CAROLINA BUNNELL-LAMMONS ENGINEERING, INC. PROJECT NO. J20-13334-02 PROMUS ENGINEERING PROJECT NUMBER: 190173 DEPTH BELOW SG (FT) GRID SFD-90 4 SFSP-4 124.3 19.9 2.6 103.7 96.0 95 Pass SG 16 SFD-91 4 SFSP-4 123.5 19.5 2.2 103.3 95.6 95 Pass SG 26 SFD-92 4 SFSP-4 127.2 19.4 2.1 106.5 98.6 95 Pass SG 36 SFD-93 4 SFSP-4 127.1 19.7 2.4 106.4 98.5 95 Pass SG 50 SFD-94 4 SFSP-4 127.9 19.4 2.1 107.1 99.2 95 Pass SG 51 SFD-95 4 SFSP-4 125.4 20.0 2.7 104.5 96.8 95 Pass SG 52 SFD-96 4 SFSP-4 121.7 18.2 0.9 103.0 95.4 95 Pass SG 53 1 SFSP-1 103.5 17.7 2 SFSP-2 105.9 17.0 3 SFSP-3 104.3 18.8 4 SFSP-4 108.0 17.3 5 SFSP-5 108.7 16.5 6 SFSP-6 107.0 16.1 7 SFSP-7 107.3 16.4 8 9 10 James Fortson 06/05/2020 Jonathan P. Usher, P.E.836 NOTE: N/A APPENDIX G Material Submittals Plant 44315-Asheboro Basic Quality Statistical Summary Report Sieve/Test SpecificationAverageSt DevTests Product 0585-Pegson Portable ABC Target Specification NCDOT ABC Period 01/01/2020 - 03/13/2020 1 1/2" (37.5mm)100.0 0.00 100-100272 1" (25mm)93.9 1.47 75-97272 1/2" (12.5mm)71.4 3.00 55-80272 #4 (4.75mm)52.9 2.99 35-55272 #10 (2mm)32.6 3.11 25-45272 #40 (0.425mm)15.8 1.02 14-3081 #200 (75µm)9.12 0.855 4-1281 Pan 0.00 0.000271 1Page:of 2Martin Marietta, Inc.StonemontQC 03/13/2020 Plant 44315-Asheboro Basic Quality Statistical Summary Report Sieve/Test SpecificationAverageSt DevTests Product 0570-Pegson Portable #57 Target Specification NCDOT 57 Period 01/01/2020 - 03/13/2020 1 1/2" (37.5mm)100.0 0.00 100-10021 1" (25mm)98.6 0.68 95-10021 3/4" (19mm)87.9 4.2921 1/2" (12.5mm)41.0 8.75 25-6021 3/8" (9.5mm)18.4 7.0521 #4 (4.75mm)2.6 0.68 0-1021 #8 (2.36mm)1.8 0.40 0-521 Pan 0.00 0.00021 Query Query Selections Date Created 03/13/2020 Date Range 01/01/2020 - 03/13/2020 Plant Asheboro 2Page:of 2Martin Marietta, Inc.StonemontQC 03/13/2020 Plant 44307-Jamestown Basic Quality Statistical Summary Report Sieve/Test SpecificationAverageSt DevTests Product 0400-#4 Target Specification NCDOT 4 Period 01/01/2020 - 03/13/2020 2" (50mm)100.0 100-1001 1 1/2" (37.5mm)98.8 90-1001 1" (25mm)47.6 20-551 3/4" (19mm)8.8 0-151 1/2" (12.5mm)3.31 3/8" (9.5mm)2.7 0-51 Pan 0.001 Query Query Selections Date Created 03/13/2020Date Range 01/01/2020 - 03/13/2020 Plant Jamestown 1Page:of 1Martin Marietta, Inc.StonemontQC 03/13/2020 85"12" 31" 6" 6"24" 56" Side View Top View Notes: Date: 4/11/14 x All concrete used to be a min of 4000 psi @ 28 days. x Reinforcement steel shall meet ASTM-A615 Grade 60 with 2" minimum clearance. x Headwall to conform with NCDOT Std. 838.80 50" Opening for 24" pipe 137"12" 43" 6" 12"39" 66" Side View Top View Notes: Date: 10/29/14 x All concrete used to be a min of 4000 psi @ 28 days. x Reinforcement steel shall meet ASTM-A615 Grade 60 with 2" minimum clearance. x Headwall to conform with NCDOT Std. 838.80 x Drawing n.t.s. 65" Opening for 36" pipe TEGA IPS SERIES SDR11 ELECTROFUSION COUPLER, DUAL RATED WATER/NATURAL GAS Water ‐ 200‐240 PSI at 73 Deg F Sustainable Maximum Operating Pressure Gas ‐ 150 PSI at 73 Deg F Sustainable Maximum Operating Pressure Suitable for Water,Fluids &Slurry'sSuitable for Water, Fluids & Slurry s Engineered for PE3408, PE4710 & PE100 HDPE Pipe Systems Manufactured in accordance with ASTM F‐714, ASTM F‐1055, ASTM D‐2513 ASTM D‐3035, ASTM D‐3261, ASTM D‐3350, AWWA C‐901, AWWA C‐906 DIN16963, EN1555, EN12201, ISO‐9001/2000 Also suitable for use on IPS SDR13.5, SDR15.5, SDR17 Series HDPE pipe Style "A" Style "A" Style "B" Style "B" Nominal  Pipe Size "d & d/2" "D" "L" Unit Weight Style Item Code NotePipe Size d & d/2 D L Unit Weight Style Item Code Note 1/2" 0.840" 1.610" 2.800" 0.060 lbs A 30.MA1.11.11.0021 3/4" 1.050" 1.610" 2.800" 0.110 lbs A 30.MA1.11.11.0026 1" 1.315" 1.890" 3.230" 0.160 lbs A 30.MA1.11.11.0033 1 1/4" 1.660" 2.170" 3.390" 0.180 lbs A 30.MA1.11.11.0042 1 1/2" 1.900" 2.640" 3.860" 0.350 lbs A 30.MA1.11.11.0048 2" 2.375" 3.150" 4.210" 0.490 lbs A 30.MA1.11.11.0060 2 1/2""2 875"3 820"4 645"0 770 lb A 30 MA1 11 11 00732 1/2"" 2.875" 3.820" 4.645" 0.770 lbs A 30.MA1.11.11.0073 3" 3.500" 4.530" 5.910" 1.330 lbs A 30.MA1.11.11.0088 4" 4.500" 5.590" 6.690" 1.860 lbs A 30.MA1.11.11.0114 5" 5.563" 7.090" 6.730" 3.530 lbs A 30.MA1.11.11.0141 6" 6.675" 8.070" 7.280" 5.510 lbs A 30.MA1.11.11.0169 7" 7.125" 9.060" 7.560" 5.650 lbs A 30.MA1.11.11.0180 8" 8.625" 10.830" 8.030" 8.990 lbs A 30.MA1.11.11.0219 * 10"10 750"13 580"8 660"14 990 lbs B 30 MA1 11 11 027310"10.750"13.580"8.660"14.990 lbs B 30.MA1.11.11.0273 12" 12.750" 15.550" 9.060" 19.530 lbs B 30.MA1.11.11.0323 * 14" 14.000" 17.520" 10.000" 29.130 lbs B 30.MA1.11.11.0355 16" 16.000" 19.490" 11.810" 39.810 lbs B 30.MA1.11.11.0406 * 18" 18.000" 21.810" 12.600" 52.040 lbs B 30.MA1.11.11.0457 * 20" 20.000" 24.210" 14.410" 73.070 lbs B 30.MA1.11.11.0508 * 22" 22.000" 27.170" 15.750" 108.880 lbs B 30.MA1.11.11.0558 * 24" 24.000" 29.720" 15.750" 131.860 lbs B 30.MA1.11.11.0609 26" 26.000" 32.280" 17.320" 132.720 lbs B 30.MA1.11.11.0660 ** 28" 28.000" 34.650" 17.520" 198.580 lbs B 30.MA1.11.11.0711 ** 30" 30.000" 37.010" 17.520" 223.980 lbs B 30.MA1.11.11.0762 * 32" 32.000" 39.170" 18.500" 257.200 lbs B 30.MA1.11.11.0812 * 34" 34.000" 42.130" 19.690" 318.260 lbs B 30.MA1.11.11.0863 36"36 000"44 090"19 690"310 570 lbs B 30 MA1 11 11 0914 *36"36.000"44.090"19.690"310.570 lbsB30.MA1.11.11.0914 * 42" 42.000" 51.180" 19.690" 456.000 lbs B 30.MA1.11.11.1066 * These couplers can be fused to SDR9 pipe by using Special Bar Code. Contact Strongbridge before fusing  to SDR9 pipe Reducing Couplers In This Series Available Under Special Request * 200 psi (240 psi under special order) ** 220 psi (240 psi under special order) Phone (416) 795‐8962 STRONGBRIDGE INTERNATIONAL (CANADA) INC. 200 North Service Road West, Unit 1 Suite 381 Oakville, Ontario L6M 2Y1 ELECTROFUSION FITTINGS MUST BE INSTALLED BY QUALIFIED INDIVIDUALS TRAINED AND CERTIFIED IN ELECTROFUSION INSTALLATION PROCEDURES. Copyright 2009 Strongbridge International Inc. All rights reserved. Information subject to change without notice. E. & O.E. () STRONGBRIDGE INTERNATIONAL INC. PO Box 58177, Jacksonville FL 32241 Phone: (904) 607‐6384 Fax:(904) 565‐2776 www.strongbridge.us www.strongbridgecanada.com 09/09 Subject to Strongbridge International Inc. Limited Warranty, available at www.strongbridge.us