Loading...
HomeMy WebLinkAbout4117_A1SandrockCDLF_MSEwall_App_Incompleteness_DIN28647_201711281 Chao, Ming-tai From:Chao, Ming-tai Sent:Tuesday, November 28, 2017 1:46 PM To:'Garrett, David' Cc:Mussler, Ed Subject:RE: [External] A-1 Sandrock MSE wall Attachments:Draft_4117_A1SandrockCDLF_MSEwall_App_Incompleteness_DIN28647_2017##.docx Hi David: As promised, attached please find the draft letter pertaining concerns from our end about the proposed MSE wall construction at A-1 Sandrock C&DLF. The draft letter is serving as a tool for both sides to discuss in the upcoming meeting and to reach some degree of consensuses about the wall construction and long-term operations. Please contact me if you have any question of the draft comments. Have a wonderful day. Ming Chao Ming-Tai Chao, P.E. Environmental Engineer Permitting Branch, Solid Waste Section NCDEQ, Division of Waste Management (Mailing Address) 1646 Mail Service Center Raleigh, NC 27699-1646 (Street Address) Green Square, 217 West Jones Street Raleigh, NC 27603 Tel. 919-707-8251 ming.chao@ncdenr.gov http://portal.ncdenr.org/web/wm/sw E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties.     From: Chao, Ming‐tai   Sent: Tuesday, November 28, 2017 11:08 AM  To: 'Garrett, David' <david.garrett2@woodplc.com>  Cc: Mussler, Ed <ed.mussler@ncdenr.gov>  Subject: RE: [External] A‐1 Sandrock MSE wall    HI David: The meeting is set on schedule. Ed is reviewing the “comment” letter right now. After the letter is approved, I will email it to you as discussion topics/agenda for the upcoming meeting so your side can respond, rebut, rebuke, or discuss the solutions for the concerns. 2   Ming Chao Ming-Tai Chao, P.E. Environmental Engineer Permitting Branch, Solid Waste Section NCDEQ, Division of Waste Management (Mailing Address) 1646 Mail Service Center Raleigh, NC 27699-1646 (Street Address) Green Square, 217 West Jones Street Raleigh, NC 27603 Tel. 919-707-8251 ming.chao@ncdenr.gov http://portal.ncdenr.org/web/wm/sw E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties.       From: Garrett, David [mailto:david.garrett2@woodplc.com]   Sent: Tuesday, November 28, 2017 9:58 AM  To: Chao, Ming‐tai <ming.chao@ncdenr.gov>; Mussler, Ed <ed.mussler@ncdenr.gov>  Subject: [External] A‐1 Sandrock MSE wall    CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to  report.spam@nc.gov.    Checking to verify we’re still on schedule for a meeting on December 6 at 9 o’clock, your offices.          David Garrett, PG, PE Senior Engineer Direct: 919-765-0070 Mobile: 919-418-4375 www.woodplc.com All engineering and land surveying services, in North Carolina, are offered/performed by Amec Foster Wheeler Environment & Infrastructure, Inc. (License #F-1253), a wholly owned subsidiary of John Wood Group, plc.        3   This message is the property of John Wood Group PLC and/or its subsidiaries and/or affiliates and is intended only for the named recipient(s). Its contents (including any attachments) may be confidential, legally privileged or otherwise protected from disclosure by law. Unauthorised use, copying, distribution or disclosure of any of it may be unlawful and is strictly prohibited. We assume no responsibility to persons other than the intended named recipient(s) and do not accept liability for any errors or omissions which are a result of email transmission. If you have received this message in error, please notify us immediately by reply email to the sender and confirm that the original message and any attachments and copies have been destroyed and deleted from your system. If you do not wish to receive future unsolicited commercial electronic messages from us, please forward this email to: unsubscribe@woodplc.com and include “Unsubscribe” in the subject line. If applicable, you will continue to receive invoices, project communications and similar factual, non-commercial electronic communications. Please click http://www.woodplc.com/email-disclaimer for notices and company information in relation to emails originating in the UK, Italy or France.    ROY COOPER Governor MICHAEL S. REGAN Secretary MICHAEL SCOTT Director Solid Waste Section ##, 2017 Mr. Ronnie E. Petty III A-1 Sandrock, Inc 2901 Bishop Road Greensboro, NC 27406 Subject: (DRAFT) Determination of Completeness for a Permit Application A-1 Sandrock Construction and Demolition Debris Landfill (C&DLF) Guilford County, North Carolina, Permit No. 4117-CDLF-2008, Document ID No. (DIN) 28647 Dear Mr. Petty: On September 29, 2017, the Solid Waste Section (SWS), Division of Waste Management (DWM) received a permit application titled as “MSE Wall Permit to Construction and Facility Plan for A-1 Sandrock C&D Landfill (4117-CDLF-2008) Phase 2B (the Application) dated September 14, 2017. The Application is on behalf of A-1 Sandrock, Inc. prepared by AMEC Foster Wheeler Environmental & Infrastructure, Inc. (AMEC Foster Wheeler). Fitzpatrick Engineering Associates (FEA), contracting A-1 Sandrock, Inc. designs the mechanically stabilized earth wall (MSE wall). Pursuant to North Carolina General Statute (N.C.G.S.) 130A-295.8(e), the SWS conducted a review of the Application and determines: A. The Application is a new facility application, and the permit fee is required. It is evident that the increment of the final gross capacity of the C&DLF, upon completing all four stage walls around the landfill unit as described in the Facility Plan, will be ten percent (10%) more than the originally approved one (2,240,000 cubic yards). This results in a substantial amendment to the existing permit per N.C.G.S. 130A 294(b1), and the landfill facility is considered a “New Facility” as defined in N.C.G.S. 130A-295.8(b)(1a). Therefore, A-1 Sandrock, Inc. must pay the fee of $550 dollars, which is 10% of the annual permit fee according to N.C.G.S. 150A 295.8(d2). The fee of $550 dollars was received on October 16, 2017, and the SWS thanks A-1 Sandrock, Inc. for promptly sending the fee. B. The Application states that the MSE wall design is according to the National Concrete Masonry Association and the Federal Highway Administration (FHWA) methodology. But the field inspection and performance monitoring, portions of the guidance documents published by above-mentioned agency or trade organization are neither not referenced Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 2 of 18 nor appending to the Application. Without adequately and sufficiently conducting the field inspection and performance monitoring is conclusively determined as the culprits of the wall failure either partially or totally in the past. Please provide a state-of-art the field inspection and performance monitoring plan for the wall construction and post- construction performance monitoring in the revised Application. C. The Application is incomplete. The Application requests an approval of new facility plan of the landfill without changing the approved landfill gross capacity of 2,240, 000 cubic yards (CY); gross capacity is defined in North Carolina Solid Waste Management Rule (Rule) 15A NCAC 13B .0537(e)(2)(B). However, the Application only provides the first stage MSE wall to enhance landfill operations and fails providing the comprehensive landfill development which comprises four-stage walls. The Application fails to define the comprehensive development of the C&DLF unit in the Facility Plan and to provide completed plans associated with landfill engineering design, construction, operations, and closure and post closure cares for each of the proposed MSE Wall, which are provided in the comments below. Because the Application doesn’t include all required components required by the Rules 15A NCAC 13B .0531et seq., the SWS determines that the Application is incomplete. Pursuant to N.C.G.S. 130A-295.8(e), the SWS notifies A-1 Sandrock, Inc. that the following components stated below are required to complete the application. Please be advised that a determination of completeness means that the application includes all required components but does not mean that the required components provide all the information that is required for the DWM to make a permit decision on the application. Facility Plan 1. The update Facility Plan must be prepared according to Rule 15A NCAC 13B .0537. The submitted plan should be expanded to define the comprehensive development of the landfill unit after each of the proposed stages of MSE walls are completed. If the content in the previously approved plan is not changed, the minimum components of the updated plan include the operation capacity and the estimate operating life at each stage of Stage 1 through 4, total gross capacity of the landfill, the active life of the landfill unit, soil sources and quantity for covers (weekly cover and final cover system) and the wall construction at each stage. The Facility Plan drawing(s) should pertain and present the update facility plan information of the comprehensive landfill development for each of the proposed stages of MSE walls are completely constructed. 2. Local government approval. i. The increment of the proposed gross capacity of the C&DLF after four-stage walls are completely constructed will be ten percent (10%) more than the originally approved one. This increment will trigger the Substantial Amendment Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 3 of 18 to the Permit as defined in N.C.G.S. 130A 294(b1)(1)a.2; therefore, A-1 Sandrock, Inc. must complete a local governmental approval processes according to 130A 294(b1)(4) and Rule 15A NCAC 13B .0536(c)(11). ii. Additionally, the ten-year-term Franchise Agreement between A-1 Sandrock, Inc. and Guilford County, North Carolina will expire on October 03, 2023, but the service life expectance of the C&DLF will substantially last for decades after the franchise term expires if the MSE walls are constructed. Pursuant to N.C.G.S. 130A 294(a2) & (a3) [Session Law 2017-211 Senate Bill 16], A-1Sandrock may want to request Guilford County an approval of a new or extension of the existing Franchise Agreement to preserve the proposed long-term landfill capacity. iii. The landfill facility is in the Deep River Reservoir watershed (Section 5.1.2). The proposed MSE wall is designed to permanently retain C&D wastes, and the proposed Stage 1 wall alignment will be located approximately several hundred feet away from Hickory Creek, a tributary of the Deep River Reservoir watershed. The waste volume will increase significantly than the originally approved one due to the wall height of about 40 feet above the existing grade. Should the wall fail, the wastes likely roll into the immediately adjacent Sediment Basin # 1 and Hickory Creek. Therefore, A-1 Sandrock, Inc. shall officially contact Guilford County Department Planning and Development, Watershed Protection and Stormwater Management or a government agency (such as Land Quality Section, Dam Safety) which has the jurisdiction over the creek and watershed to determine if an environmental impact study or remedial/response plan are required due to the high wall retaining solid wastes. The approved document(s) must be a portion of the Application. 3. (Section 1.2) Please address the following concerns: i. In comparison with the approved waste footprint on the Facility Plan drawings of the approved permit application, the waste foot print of the C&DLF shown on Drawings E3 & E4 expands southwestward and encroaches/includes the areas on the south side of the Sediment Basin # 1. The new encompassed area is not approved waste footprint. If the change of waste footprint is approved by the local government, A-1 Sandrock can submit the revised Facility Plan and new waste disposal boundary for an approval; otherwise, revise the Drawings E-3 & E-4 accordingly. ii. The construction of Stage 1 MSE wall may impact/disturb the area on the west side of the existing haul road. The Erosion and Sediment Control Permit issued by the NC Land Quality Section may be subjected to modification. If the permit Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 4 of 18 modification deems required, the modified Erosion and Sediment Control Plan should be appended to the Application. 4. (Section 1.2.2) Please address the following concerns: i. This subsection states that “It is NOT anticipated that each wall increment beyond the first lift (assumed 12 feet according to the narrative in this subsection) will requires individual permitting by the SWS.” This statement or proposal violates the Rules 15A NCAC 13B .0541 and .0201(d)(2). The Permit Approval To Operate will be issued only if the rule-required CQA Report for that lift wall section is reviewed and approved by the SWS. Please revise the statement according to the rule requirements. ii. A-1 Sandrock, Inc. intends to vegetative the exterior side the MSE wall (vegetative facing) as described in this subsection. a. What kind/type of vegetation is to be used for the wall facing unit? Should the Technical Specification include the installation, establishment, replacement, and long-tern cares of the vegetative facing unit of the wall? b. Should the maintenance and care of the vegetation be a portion of the Operations Plan and Post-Closure Care Plan? 5. (Section 1.3.3 or Section 2) Please provide the following supplemental documents to the summary of subgrade soil stratifications and related strengths. i. The drawing(s) to show locations of soil borings (with identifications) relative the alignment of Stage 1 wall. The data (boring logs) of these selected soil borings used for the MSE wall design must be appended to the Application. ii. The drawing(s)/profiles to summarize a. Soil and rock stratification, b. Engineering character and strength, c. Groundwater levels based on the results of subsurface investigation of the selected soil borings for wall design and historical groundwater well information. iii. The reference(s)/document(s) used to generate the summary of subsurface investigation. 6. (Section 1.3.4) For long-term and comprehensive landfill planning, the soil volume analysis should estimate the quantity of soil to be used for landfill operations (rule- required covers) and for wall construction at all four stages (must be met the Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 5 of 18 requirements in Appendix 3 of the Engineering Plan). Please address the concerns below: i. The detail calculations of the soil volume for constructing each of the four-stage wall. The required soil quantity should be consistent to the operational sequence stated in Section 1.2.2. ii. The soil borrow location (on-site or off-site) and the AutoCAD calculations of borrow volumes. If the Phase 3 (as described in Section 1.2.2) the landfill base grade of the proposed Phase 3 of the C&DLF unit shall be submitted to the SWS for a review and approval. Engineering Plan 7. To integrate the proposed MSE wall into the landfill as a unit, it is imperative to design leachate and stormwater separation devise/structure and/or a leachate collection/removal system in the life cycle of the landfill for the following condition as mentioned in Appendix 3 of the Application. The narratives of the storm water and leachate separation and disposal approaches in accompany with detail drawings must be provide in the Engineering Plan. i. Stormwater separation devise/structure. This design and construction of this structure must consider the approaches to prevent building up hydrostatic pressure behind the wall (the wall area intimately contacts the waste) or “back drainage zone design” and to facilitate internally drainage of any surface water and the percolation through the wall material (the long-term permeability evaluation of earthen material in the soil-reinforce zone) as recommended by FEA in Appendix 3. The design must conclude the following parameters which must be incorporated into the CQA Plan and Technical Specification of the Application. The minimum parameters are factor of safety, flow rate, thickness and hydraulic conductivity or transmissivity for the proposed drainage material/medium, piping size and material (if applicable), the outlet/exit design including energy dissipater(s). a. While the Stage 1 wall is constructing and the landfill (Phase 1 is inactive and Phase 2 active) is operating. b. After wall is completed but not reaching the final height and the first waste load is placed to the landfill cell. The disposal sequence must also be illustrated in the Engineering or Operation Plan drawings. c. After the wall is reached final height and waste is placed above the height of the perimeter drainage ditches. Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 6 of 18 ii. If the installed stormwater and surface water measures can’t properly separate from the waste disposal activities which generates leachate as defined in NCGS 130A-290.a(16a), the leachate collection and removal system and storage unit must be properly designed and operated. The details of the design, construction, operations, and closure and post-closure cares of the leachate collection and removal system must be adequately and sufficiently addressed in the Application. 8. Building Code Requirements. A-1 Sandrock must contact the City of Greensboro (the City) and/or Guilford County (the County) to request if the proposed wall design and construction are required a local building permit. The written request and responses from the local governments must be appended to the Application. Any building permit requirements must be appended to the Application as well. 9. The Engineering Plan must provide or establish the criteria of acceptable displacement or deformation of the constructed MSE wall [the lateral movements (direction along the wall alignment – left to right and direction perpendicular to the wall - front to back) and vertical movement – up (heave) or down (settlement) directions]. The instrumentation(s) for the specified monitoring elements and triggering must be specified. The criteria as the trigging of the emergency response plan shall be incorporated into the routine inspection and monitoring activities (Comment Nos. B & 12, 34, 40, & 53) throughout the landfill life (both active and post-closure periods). 10. The Engineering Plan should include a cost estimate to construct the MSE wall; the breakdown cost, total cost, and unit cost per wall facing unit ($ per square feet) should be available, which will be used as the basis to establish Financial Responsibility (Comment No. 54) including both Financial Qualification and Financial Assurance of the landfill (N.C.G.S. 130A-295.2). 11. The MSE wall design (in Appendix 3) is based on the data in Appendix 2 generated by A-1 Sandrock, Inc. However, the data in Appendix 2 is collected for the landfill design and not directly from the sub-surface investigations along the proposed wall alignment. The geotechnical testing on soil samples (or confirmation testing results) from borings along the proposed Stage 1 wall alignment should be conducted prior to wall construction; the testing results must be used to compare the ones used in design in Appendix 3. Adjustment or redesign a portion of or the entire walls may be warranted by a professional engineer if the design parameters based on the confirmation soil testing results vary significantly (as requested by FEA – Sections 2.1, 3.0 & 6.0, Appendix 3 of the Engineering Plan). Therefore, A-1 Sandrock, Inc. should prepare a subsurface investigation plan and soil testing program (the program), which should be appended to the Engineering Plan. Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 7 of 18 i. The program must be prepared according to building codes or the FHWA guidance for subsurface investigations for design/construction of a retaining wall or a MSE wall. The program must be prepared by a Professional Engineer registered in the State of North Carolina and reviewed and approved by the SWS. ii. The program must be executed with ample time prior to the wall construction. iii. The collected info and produced results (including conclusions and/or design modification, as needed) from the program must be submitted to the SWS for a review and approval and to the consultants contracted to A-1 Sandrock, Inc. for modify the wall design as necessary. 12. The Engineering Plan shall include the technical specifications pertaining to the design and performance of the landfill containment and environmental control systems including the proposed MSE wall components and drainage networks [Rule 15A NCAC 13B .0539]. Above mentioned tasks are excluded from the FEA’s scope of work for the MSE wall design (Section 1.3, Appendix 3 of the Engineering Plan); therefore, A-1 Sandrock must provide detail of surface water and seepage designs. 13. (Section 2.1) Per FHWA specification, the MSE wall backfill shall be compacted to a specified compaction effort based on the distance from the wall facing. The second paragraph proposes the “…compacted soil with a target maximum dry density of 90 percent…” shall be revised according to the FHWA specification. Additionally, the specification of compaction effort in this Section is contradicting those in Sections 2.2 and 4.2.1.1. 14. (Section 2.1.1) The FHWA design and construction guidelines (Publication No. FHWA- NHI-00-043) is used as one of the reference to design the MSE wall; The guidelines are based on allowable stress design (ASD) procedures to conduct MSE wall design; however, the design approaches in Appendix 2 and Appendix 3 of the Application are based on load and resistance factor design (LRFD) procedures. Please clarify. 15. Please provide a summary of the testing requirements of the MSE walls as described in the subsection 2.1.1. The referenced testing summary isn’t available in the Section 7 of the Application. 16. Throughout the entire application document please use the consistent engineering parameters for all calculations and analyses (settlement, slope stability, bearing capacity, etc.) in Appendices 2 & 3. There is no reason that same material has different engineering parameters. If A-1 Sandrock, Inc. insists this approach, the SWS demands Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 8 of 18 A-1 Sandrock, Inc. conduct a sensitive analysis by using lower and upper bound data on each task conducted in Appendices 2 & 3. 17. (Section 2.1.1) The required minimum factor of safety for minimum reinforcement length/wall height is 0.8 as described in Section 2.1.1, but the factor of 0.7 is used in Appendix C1. Please clarify. 18. (Section 2.2) Please address the following concerns: i. The on-site soil material classified as SM-ML and CL per Unified Soil Classifications are nor suitable to use as fill material in the reinforcing zone of the MSW wall according to Section 1.4 in Appendix 3. Please make clarification in this Section how to use the earthen material in Phases 2B & 3 for selected fill material for constructing the wall. ii. Should this section add more info/specification related to the MSE wall construction? For example, geosynthetic material, weld metal mesh, vegetative supporting material, etc. iii. Please provide the procedures/ sequences of the wall construction (referring Drawing E5 & RW1 through RW-4). iv. Any off-site borrow is required? How much the selected backfill must be obtained from off-site borrow. How the borrow material can be confirmed to be suitable for fill material inside the reinforced zone? v. Will the 10% organic debris/material in the selected backfill material for the wall construction meet the specification in Appendix 3? Why is the compaction effort stated in this section different from that in Section 2.1? 19. (Section 2.4) The wall construction drawings must be part of the Application. The Drawing E4 shows the wall width is variable and station is different from that in Drawing E5. Please provide details of wall widths along the station. 20. (Section 2.5.1 Settlement, Page 16) Please provide the source of the referenced waste density of 0.6 ton per cubic yard. Is the waste density compatible with that in the facility annual report? Is the loading based on the final, not interim, in-place waste (show the elevations of the bottom of the waste and of the top of the final cover)? Appendix 2 Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 9 of 18 21. (Appendix 2, Sections 3 & 4.2 & Appendix 2-A) The MSE wall will be seated on the top of in-placed waste or embankment of the haul road, or haul road as shown on Drawing E4. The haul road and embankment were not constructed by partial weather rock (PWR) but compacted on-site soil as described in Section 2.2 of the Engineering Plan. Throughout the entire application document, A-1 Sandrock must use the consistent engineering parameters for all calculations and analyses (settlement, slope stability, bearing capacity, sliding & overturning in Appendix 2 and MSE wall internal and compound stability analysis in Appendix 3). It is not professional practice of using different engineering parameters for the same selected materials or foundation strata to fit in the pre-determined outcome. If A-1 Sandrock, Inc. intends to use this approach, the SWS demands that A-1 Sandrock, Inc. conducts a sensitivity analysis on each task in Appendix 2 and Appendix 3 by using all available lower- and upper-bound engineering parameters – density/unit weight, shear strength, internal friction angles. 22. (Appendix 2, Section 4.2) Please provide the copy of the referenced AASHTO tables. 23. (Appendix 2, Section 5.1 & Facility Plan) According to the Facility Plan, the MSE wall will be constructed by four (4) stages, but the information provided in Appendix 2-A shows three (3) wall alignments/stages (?) (with three options of wall heights). Is there contradicting info described in Facility Plan & Engineering Plan. Please explain. 24. (Appendix 2-B, Global Slope Stability Analyses) i. Please provide the input data sheet for each round of analysis. The layout drawing to show the critical slope (cross-sections) locations must be provide in the Appendix 2-B. ii. According the historical soil boring logs in Appendix 2-D, there are layers of sandy silt, silty clay overlain the PWR as described in the Section 2.5.2.1 of the Engineering Plan. a. Why those layers inside the landfill waste footprint are eliminated from the slope stability analysis? b. Why groundwater table is not considered in the analysis? c. The deep seated global stability analysis shall be conducted below the MSE wall; although for the sake of simplicity, the wall unit is a block but the foundation soil that supporting the wall is not PWR. 25. (Appendix 2-B Settlement Calculations) Please address the following concerns: i. The soil boring log B-10 is not included in Appendix D. ii. The consolidation test results are not available in Appendix 2-B. Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 10 of 18 iii. Provide Hough’s method equations for sand and the selection processes of the SPT values used in Hough’s method. iv. Section 2.5.1 & Appendix 2-B of the Engineering Plan concluded that estimated settlement of the foundation soil underneath the MSE wall of 0.51 feet (5/100) is acceptable. But the Section 2.1 of Appendix 3 specified the settlement of the soil underneath the wall shall not exceed 1/100. Please explain the discrepancy and which one shall be used for the wall project. 26. (Appendix C1, LRFD External Forces Analysis) The external loading arrangement used in Appendix C1 is different from the loading arrangement as shown on Drawing E5 and Appendix 3, which shows that: i. There is no surcharge on the MSE wall except the traffic load (uniform loading) of 250 pounds per square feet as described in Section 2.0 of the Engineering Plan. ii. The interim or final soil cover - back slope [3 (horizontal) to 1 (vertical)] of the C&DLF is located on the backside of the wall, not over the entire wall width of 25 feet. iii. The retained backfill shall include C&D waste (the solely purpose to build the wall), not backfill material alone. iv. The distance of water table, 5 feet, below the bottom of the wall is used, please provide the reference. Is the data from a nearby monitoring water well? Will the water level be impacted by the water levels in the Sediment Basin # 1, and nearby Hickory Creek? v. Soil parameters for the foundation soil are those for PWR; but the MSE wall will be seated on the top of in-placed waste or embankment of the haul road, or haul road as shown on Drawing E4. The haul road and embankment were not constructed by PWR but compacted on-site soil as described in Section 2.2 of the Engineering Plan. The input data are irrelevant and inconsistent to the site conditions. Based on the findings, the SWS does not think the results from the calculations for each design wall heights -30, 50, and 60 feet in submitted Appendix C1 and Appendix 3 truly reflects the real field loading conditions that the proposed wall will be encountered. Appendix 3 Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 11 of 18 27. (Appendix 3 MSE Wall Design Report) According to Section 4.2 in Appendix 2, the retained backfill/C&D waste is a non-cohesive material (e.g. c’ = 0 psf). Additionally, referring the Comment No. 20 that foundation soil for the wall including sandy/silty soil, C&D wastes overlying the PWR. Therefore, the entire wall design is based on the questionable geological and geotechnical information. The modification of the wall design is possibly warranted. 28. (Section 2.2) Please provide a copy of the material data sheet/specification of the selected geogrid, FortractTM made by Huesker. 29. (Section 2.4) Please address the following concerns: i. The seasonal high ground water table for both C&DLF - Phases 1 & 2 areas are previously confirmed by the 2002 Site Suitability Study Report and the Design Hydrological Reports as stated in Section 2.5 of the Engineering Plan. The semi- annual groundwater monitoring reports must be used for the water tale degermation as well. A-1 Sandrock, Inc. must use the site-specific data to determine if the groundwater level is greater than 0.66H. If not, the modification of the wall design is warranted. ii. The portion of the wall (Stage 1) is very closed to the existing Sediment Basin #1. The highest water level in the basin must be considered for the wall design. Especially, when the nearby creek is flooded, and water in the basin may not be able to drain into the creek for several days which results in infiltration of surface water/flood water into MSE wall reinforced fill zone (Section 2.4, Appendix 3 of the Engineering Plan & refer Drawing No. 5, wall is embedded unknown depth below the existing grade). The wall must design the worst scenario. iii. (Section 2.4) The wall design should be revised by considering the seepage generated from landfill leachate that is retained by the wall. Construction Quality Assurance (CQA) Plan 30. In addition to the landfill construction, the CQA Plan and technical specifications that are the same documents submitted previously should include construction quality assurance and control and specifications associated with material and construction of the proposed MSE wall including reinforcement, graduation & compaction requirements for the selected fill material, and drainage media, etc. 31. Referring Comment No. 8, if the construction of the MSE wall requires to satisfy local building codes, the CQA Plan and Technical Specifications must incorporate the code requirements. Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 12 of 18 32. (Section 4.1.2) What is the role and responsibilities of Fitzpatrick Engineering Associates, PC in the MSE wall project? 33. (Section 4.2.1.3) The listed soil types which are generated from on-site borrows are not entirely satisfactory use for the selected fill material (excluding fine-grained soils such as SC, ML, CL, MH, & CH) inside the MSE wall reinforcing zone as described in Appendix E, Appendix 3 of the Engineering Plan. A-1 Sandrock must produce a CQA Plan for the material used in the MSE wall construction. 34. (Section 4.1.2.4) The MSE wall has geosynthetic component (geogrid) specified as reinforcement; therefore, CQA Testing Firm should be both certified soil laboratory and geosynthetic laboratory. And some tests on geosynthetic material are abiding by the standardized method by other organization such as GRI. The testing methods and frequencies are required in the CQA Plan and Technical Specifications. Please make the necessary revision. 35. (Section 4.2) The CQA Plan, in a minimum, should address the inspection and oversight of the MSE wall construction (referring Sections 1.2 & 3.0, Appendix 3 of the Engineering Plan). i. Who is responsible the inspection & oversight of the MSE wall construction? ii. The inspection item/checklist & frequency, inspector qualification & authority, inspection report and submittal 36. (Section 4.3) Please refer the pre-construction requirements stated in Section 3.0, Appendix 3 of the Engineering Plan. 37. (Section 4.3) This section, in a minimum, should include the requirements for wall foundation preparation & proof-rolling final grade with specified precision and survey control, soil classification for fill material, compaction test, wall foundation approval processes prior to proceeding next task of erecting a layer of wall, and approaches to handle if a non-conformance foundation soil encounters. 38. Plesae provide the material and construction specification of the material to be used in the “back drainage” design . Operations Plan 39. (Section 5.2) The DWM Winston-Salem Regional office contact info has changed, the correct info is shown below: 450 West Hanes Mill Road, Suite 300, Winston-Salem, NC 27105 Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 13 of 18 Phone: 336-776-9800 Fax: 336-776-9797 40. (Section 5.3) The section may require some revisions to meet the current regulation change such as a life-of-site permit and past ten years operation experiences. 41. (Section 5.7) Please provide additional info of inspection & monitoring associated with MSE wall. i. The constructed MSE wall including both structure components and stormwater draining system shall be part of routine inspection and maintenance (I&M) tasks, which shall be conducted by independent third-party according to the requested I&M Plan for the constructed wall (referring Comment No. 9). ii. The inspection, monitoring, and maintenance records/reports certified by a Professional Engineer registered in the State of North Carolina shall be placed in the operating record in Section 5.12. 42. (Section 5.11) Please describe if the C&DLF is subject to EPA Green House Reporting requirements and status in the future landfill operation after each stage of wall is completely constructed. 43. (Section 5.13) The Division Water Quality merged into the Division Water Resource. Please make necessary correction. 44. (Section 5.14) The Contingency Plan should include the response action plan to handle the following conditions if failure of the wall segment(s) occurs; in a minimum, the plan should include, but not limited to the person(s) responsibility for cleanup and site restoration, verbal and written notifications and timing to submit an incident report and follow-up action plan to regulatory agencies, and coordination (including firm schedule of each activity) of restoration of the wall segment(s), removal waste rolled out of waste footprint, impacted area investigation and remediation, and routine waste disposal activities if A-I Sandrock is allowed to assume the waste disposal activities. 45. (Sections 6.3 & 7.2) Please provide the correct references in the Application. i. The reference (in Sections 6.3 and 7.2) for the hazardous waste definition is incorrect. ii. The Tables 6.1 and 7.1 are not available in the Application. 46. (Section 6.4.2) Please use the correct acronym of the NC DEQ instead of the NC DENR. Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 14 of 18 47. (Table 6A) The wastewater treatment sludge shall be prohibited for treating or processing at the Processing Facility. 48. (Section 7.3.2) There is no “on-site” waste transfer station in the landfill facility. Please correct the typo. 49. (Table 7A) The exception for an industrial solid waste as referenced in Rule 15A NCAC 13B .0503(2)(d)(ii)(A) is irrelevant. An industrial solid waste shall not be disposed in a C&DLF. Closure and Post-Closure Plans 50. (Section 8.1) The referenced drawings in this subsection are nor consistent to the ones in the Application. Drawing E-3 is likely show the interim cover of the landfill while Stage 1 wall is constructed. 51. (Section 8.2.2) The permit (DIN 284550) dated October 02, 2017 allows A-1 Sandrock, Inc. to operate both Phases 1 & 2 of the C&DLF. The Phases1 & 2 encompasses 16-acre waste boundary and have an approved operating capacity of 1,078,524 cubic yards. Please update the data in this subsection. 52. (Section 8.3) Please provide additional information to the Post-Closure Plan: i. The Plan should state how to routinely conduct the maintenance and care of the vegetation established in the final cover system and facing unit of the wall. ii. The Plan should detail the monitoring, inspection, repair of the wall during the post-closure period. The SWS strongly recommend that A-1 Sandrock adopt the guidance documents published by Federal Highway Administration (FHWA) or State Department of Transportation (NCDOT) and the White Paper #19 issued by Geosynthetic Institute (GRI) dated April 19, 2011. iii. The costs related to each above-mentioned care activities that shall be conducted by a independent third party must be added to the post closure cost estimate. 53. (Table 8A) Please explain why the unit cost for the following item is less than previously approved cost estimate for site closure, the credible documents for supporting the cost reduction must be provide in the Application: i. VSL; ii. CSB, iii. Establish Vegetation. 54. (Section 8.3) Please address the following concerns: Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 15 of 18 i. The Post Closure Plan must address the routine inspection, repair, maintenance the constructed MSE walls. The emergency response plan for management wastes and restoration the wall must be appended to the Post Closure Plan. ii. (Section 8.3.1.3) The drawing MP-1 is likely a typo of Drawing M1/Sheet 11. iii. The facing unit of the MSE wall is vegetation, please provide a care and maintenance plan for the vegetative facing unit. The related cost must be added to the post-closure cost estimate (Table 8C). iv. (Table 8C) The number of ground water monitoring well is six (6), not five (5). 55. Financial Responsibility [NCGS 130A-295.2] According to Section 2 – Engineering Plan, the design of MSE wall is based on the FHWA methodology and guidance documents which state the service life for a long-term permanent retaining wall is routinely about 75 years. Therefore, in addition to providing a financial assurance mechanism(s) to cover costs of landfill unit closure, post-closure cares, groundwater corrective action as needed, and potential assurance and corrective action for the C&DLF facility, A-1 Sandrock, Inc. must provide: i. Financial qualification to pay the costs of proper design, construction, operation, and maintenance of the MSE wall. ii. Financially responsible for a. Repairing or replacing the entire walls – Stage 1 through Stage 4 around the landfill. The costs should include waste removal and replacement while repairing or replacing the entire walls when the 70-year service life of the wall expires or the function of the wall is questionable or unsafe to a human life or adversely damaging environment]), whichever comes first. The latter is concluded and judged by a profession engineer registered in the State of North Carolina throughout the routine inspection of the MSE wall [see Comment No. 9]. The costs for this part should be the same costs for construction of the wall plus additional costs for removing and replacing wastes and restore the final cover system. b. Remediation and cleanup the wastes (including wall materials) and restoration of the wall in the event of a wall failure. According to GRI Report No. 40, Dr. Robert Koerner reports “the cost of the remediation varied from 1.05 times the original cost to 3.50 times. The rebuild case history was 4.66 times the original cost.” The average costs for this part is about twice the initial cost of wall construction. Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 16 of 18 c. All above-mentioned costs shall be annually adjusted for inflation according to NCGS 130A-295.2. Drawings 56. Drawing Sheet 12- MSW Wall Monitoring Locations is not included in the Application. 57. Provide a drawing or drawings of final/interim cover layout which has referenced the locations of the typical details of erosion and sediment control measures on Drawing EC1 through EC-3. 58. (Drawing E-5, MSE Wall Details) The details of cross-section at Station 26+00 must include, but not limited to the following items as described in Appendix 2, Section 2.1.1 (on page 12): i. Drainage systems/networks for surface water, leachate, seepage flow behind the wall, toe drain (surface water) including various size piping and drainage media. The hydraulic design of the drainage system must be appended to the Engineering Plan. The material and construction specifications must be added to the CQA Plan and the Technical Specification which must meet the requirements stated in Section 4.0, Appendix 3 of the Engineering Plan. ii. What is the toe slope of the foundation soil affront of the wall? iii. The tensile strength of reinforcement is color-coded. For each color zone, please tabulate the data of the reinforcement strength & length & vertical spacing, thickness of the layer (by elevations amsl). iv. The facing of the wall should be constructed with a 6-inch set back/stagger per course (Section 1.2, Facility Plan). Please show the described setbacks on the drawing. v. The back-side of the wall, an earthen material will be backfilled and compacted between C&D waste and reinforced zone of the wall. a. Will this non-reinforced zone of the wall be built vertically? Please described the construction procedures for construction of a 60-feet-tall non-reinforced earthen wall in the Engineering Plan (same comment applicable to Sheet No. RW-5 in Appendix 3). b. Provide the dimensions of the non-reinforced zone of the wall – slopes, base width, top width, in any (same comment applicable to Sheet No. RW-5 in Appendix 3). Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 17 of 18 c. According to the Facility Plan, the wall will be built vertically by 10 to 12 feet life/layer per time (1.5-feet per course). In addition to providing the detail of final cover system of the C&DLF related to the full-height wall, please provide a typical detail/cross-section of each interim wall height (30 feet and 50 feet) with landfill operating grades. vi. The details of wall connection details. vii. What is the embedment depth of the MSE wall (same comment applicable to Sheet No. RW-5 in Appendix 3)? viii. The Profile of Stage 1 MSE wall is confusion. What the color code area means? ix. The profile should be simplified by providing elevations of the existing grade, the finish grade of foundation layer, the first 10-feet layer, second 10-feet layer, and so on to the final layer of the Stage 1 wall (approximately 800 feet amsl). x. A-1 Sandrock may want to verify and confirm if the guardrails installed on the edge of the top of the wall are required to protect worker driving hauling trucks. Equipment and/or machinery from fatal accident? xi. The typical wall section adjacent to the Sediment Basin # 1 (including basin grade and water level elevation) should be present on this drawing. 59. (Drawing EC-2, Landfill Gas Vent Detail) i. Should there a layer of geotextile (density of x oz./square yard) to separate the NC DOT # 57 washed stone from the compacted soil liner at the gas vent trench? ii. What is the side slope of the gas trench? iii. Gas pipe material specification is missing. PVC or HDPE, thickness, perforation size and spacing, etc. 60. The layout, cross-sections, and detail drawings of the comprehensive landfill development are required; the minimum info should include the landfill base grades (relative to the rock stratum or seasonal high ground water table), the existing waste fill grades, component of a MSE wall unit, leachate and stormwater separation devices, interim grades of different phased landfill development in coordination with wall erection at four different stages, and final grades of the landfill. Mr. Ronnie Petty III ##, 2017 DIN 28647 Page 18 of 18 Please submit a revised Application including a hard copy with a set of full-size drawings and an electronic copy (in pdf format) of the Application. The SWS will conduct the second-round review when the revised Application which incorporates all proper responses to the above- mention comments. Thank you for your cooperation in this matter. If you have any questions of the requested application components, please contact myself at 919-707-8251 ming.chao@ncdenr.gov. Sincerely, Ming-Tai Chao, P.E. Division of Waste Management, NCDEQ cc: David Garrett, P.G. P.E., AMEC Foster Wheeler Ed Mussler, Permitting Branch Supervisor Christin Ritter, DWM Susan Heim, DWM Deb Aja, DWM Central Files