RE: Ash Basin Closure Plans — Revision
Allen Steam Station
Belews Creek Steam Station
Cliffside Steam Station/Rogers Energy Complex
Marshall Steam Station
Mayo Power Station
Roxboro Power Station
Dear Ms. Holman:
George T. Hamrick
Senior Vice President
Coal Combustion Products
400 South Tryon Street ST06A
Charlotte, NC 28202
Phone., 980-373-8113
Email. george.hamrick@duke-energy.com
In accordance with the requirements of North Carolina General Statues § 130A-309. 214(a)(4),
Closure of Coal Combustion Residuals Surface Impoundments, and the requirements of the
Settlement Agreement, Duke Energy provides revisions to the Basin Closure Plans submitted
on December 31, 2019 and January 30, 2020 for the subject stations. This revision consists of
an updated Appendix D, Closure Plan Drawings, for the Cliff side Steam Station and the
Roxboro Power Station and an updated Table 10-1, Regulatory Permits, Approvals, or
Requirements for Basin Closure by Excavation, for each of the subject closure plans.
Duke Energy remains committed to safely and permanently closing basins in ways that continue
to protect people and the environment and welcomes the opportunity to work constructively with
NCDEQ to move forward.
Respectfully submitted,
Georg . Hamrick
Senior Vice President
NCDEQ cc: damsafety@ncdenr.gov, deq.coalash@ncdenr.gov, Ed Mussler, Steven
Lanter, Toby Vinson
Duke Energy cc: Jessica Bednarcik, Dave Renner, Dan Mc Rainey, Jim Wells, Ed Sullivan,
Michael Kafka, Randy Hart
AECOM
February 3, 2020
Table 10-1: Marshall Steam Station Regulatory Permits, Approvals,
or Requirements for Ash Basin Closure by Excavation
Existing
Permit/Approval
Regulating
General Permit Name or Subject
Permit No.
Type of Regulatory Approval
Comments
Agency
(if applicable)
Mechanism or Not Required
Permit modification likely needed due to the increased
Permit Modification Likely
Air Quality
NCDEQ
heavy equipment vehicle traffic and potential dust
Required
generated during closure activities
Catawba
A local building permit is required for installation of
Building Permit
New Permit
County
construction trailers
Modification or abandonment of CAMA program
CAMA Monitoring Plan
NCDEQ
Written NCDEQ DWR approval
monitoring wells require the approval of the Division of
Water Resources (DWR)
CCR Impoundment Closure
US EPACCR
Self Regulating
Rule
CCR Impoundment Monitoring
US EPA
Maintain CCR GW monitoring network and
Self Regulating
Network
CCR Rule
requirements as stated in 257.90 - 257.98
It is anticipated that an individual permit will be
Clean Water Act 401
USACOE
Individual Permit
required due to jurisdictional area impacts associated
NCDEQ
with Ash Basin Closure
It is anticipated that an individual permit will be
Clean Water Act 404
USACOE
Individual Permit
required due to jurisdictional area impacts associated
NCDEQ
with Ash Basin Closure
Closure Plan
NCDEQ
Approval by Letter
See permitting for sedimentation/erosion control,
USACOE
Applicable and to be covered
Threatened or Endangered Species, and Wetlands. Tree
Cutting Trees
NCDEQ
as part of other permits
cutting could be covered under some or all of these
permits.
Permitting is required to modify or abandon wells and
Certificate of Approval to
instrumentation on regulatory dams through the
Dam Safety
NCDEQ
CATAW-054
Modify
Division of Energy, Mineral, and Land Resources
(DEMLR)
1of4
AECOM
February 3, 2020
Final approval after abandoning wells and
Certificate of Final Approval
instrumentation on regulatory dams through the
Dam Safety
NCDEQ
CATAW-054
(COFA)
Division of Energy, Mineral, and Land Resources
(DEMLR) in accordance with the Dam Safety Law of
19671 15A WAS 02K.0220.
Ash Basin Dam - Permitting is required to modify the
Certificate of Approval to
dam in accordance with the Dam Safety Law of 1967,
Dam Safety
NCDEQ
CATAW-054
15A NCAS 02K.0201 (b)(2); an application must be filed
Modify
with the Division of Energy, Mineral, and Land Resources
(DEMLR)
Final approval after modifying the Ash Basin Dam
Dam Safety
NCDEQ
CATAW-054
Certificate of Final Approval
through the Division of Energy, Mineral, and Land
(COFA)
Resources (DEMLR) in accordance with the Dam Safety
Law of 1967, 15A WAS 02K.0220.
Utilization of or modification to state or federal
DOT - General
Not anticipated at this time
highways to transport CCR will require consultation or
notification to relevant DOT agency (if off -site removal is
required)
Driveway Permit
NCDOT
New Permit possible
Temporary access or driveway permits as needed
Land disturbance activities outside of the ash basin will
exceed one acre, therefore in conformance with 15A
Erosion and Sediment Control (E&SC)
NCDEQ
New Permit
NCAC 04, an E&SC Permit is required from Land Quality
prior to commencement of construction in those areas.
Note that land disturbance includes tree clearing and
grubbing and vehicular wheel or tracking as disturbance.
Requirements set forth in the Duke Energy Catawba-
Wateree Shoreline Management Plan will be met. As
FERC (Federal Energy Regulatory
required by the FERC Catawba-Wateree Project License
Commission)
FERC
Approval by Letter
P-2232, issued November 25, 2015, approval for any
placement of fill into Lake Norman will be obtained by
FERC prior to commencing closure construction
activities.
2 of 4
AECOM
February 3, 2020
Removal from or import of material could be restricted
Fire Ants
Restriction not likely
dependent on the potential for fire ants and geographic
regions involved
Section 44-429 of the Catawba County Code of
Catawba
Ordinances, requires a Floodplain Development Permit
Floodplain Development
New Permit
prior to any development activities within FEMA
County
mapped Special Flood Hazard Areas for the Flood
Insurance Rate Maps
MT-2 Form 1, Form 2, Form 3, and associated
documentation for the request of a Conditional Letter of
Map Revision (C-LOMR) will be completed and
submitted to the Department of Homeland Security
Floodplain Development
DHS FEMA
Floodplain Map Revision
Federal Emergency Management Agency (DHS FEMA)
prior to closure activities. Upon completion of Ash Basin
closure activities, a Letter of Map Revision (LOMR) will
be requested from DHS FEMA through submittal of the
aforementioned forms and a copy of the as -built plans.
Permits are required to construct any water supply well
Large Capacity Water Supply Well
NCDEQ
New Permit possible
or water well system with a design capacity equal to or
greater than 100,00 gallons per day - for dewatering
outside of the ash basin
Multi -State Agreement
Not required
If movement of CCR will cross state lines, multi -state
regulations might apply
NPDES (National Pollution Discharge
NCDEQ
NC0004987
Permit modification likely
Modification of NPDES may be necessary if new source
Elimination System) Wastewater
or outfall is created.
NPDES (National Pollution Discharge
Revision to existing sitewide permit or new permit may
Elimination System) Industrial
NCDEQ
NCS000548
Permit modification likely
be required for access roads, staging areas, etc.
Stormwater
NPDES (National Pollution Discharge
Permit required for temporary and permanent
Elimination System) Stormwater
NCDEQ
New Permit possible
stormwater rerouting.
3 of 4
AECOM
February 3, 2020
Removal from or import of vegetated material could be
Noxious Weeds
Not anticipated at this time
restricted dependent on the vegetation and geographic
regions involved
Railroad Easement, Access, or Crossing
Construction activities adjacent to tracks/ballast or a
Permit
Not anticipated at this time
new railroad crossing require an agreement or permit
SPCC (Spill Prevention Control and
In accordance with the Federal Water
Countermeasure) Plan
US EPA
Modification of existing plan
Pollution Control Act (Clean Water Act) of 1974, Title 40,
Code of Federal Regulations, Part 112.
Threatened or Endangered Species:
Federal and/or state regulations may apply including
Candidate Conservation Agreement
agency consultation and performing site -specific surveys
Avian Protection Plan(s)
US EPA
Completed as part of 401/404
within the proper survey period (e.g., flowering period
Bird and Bat Conservation Strategies
NCDEQ
process
for listed plant) to determine if Threatened or
Eagle Conservation Plan
Endangered Species or their habitat exist within the
Eagle Take Permit
limits of disturbance
According to 15A NCAC 13B .1625, disturbance of any
closed landfill or permitted beneficial use facility will be
Solid Waste
NCDEQ
CCB0030
Approval by Letter
subject to approval by the Division of Waste
Management (DWM). Required for the excavation of
the Structural Fill Access Road.
4 of 4