Loading...
HomeMy WebLinkAbout22007 EMP Rev.1_South Tryon Commercial (BPN 22007-18-060)_20190327Environmental Management Plan South Tryon Commercial Charlotte, North Carolina Brownfields Project No. 22007-18-060 Revised March 26, 2019 H&H Job No. RMR-006 #C-1269 Engineering #C-245 Geology CONTENTS Completed EMP Template Form Tables Table 1 Summary of Soil Analytical Data Table 2 Summary of Groundwater Analytical Data Table 3 Summary of Soil Vapor Analytical Data Figures Figure 1 Site Location Map Figure 2 Site and Surrounding Area Map Figure 3 Sample Location Map Appendices Appendix A Current Redevelopment Site Plan Appendix B Grading Plan and Cut-Fill Analysis Appendix C Construction Schedule     1  EMP Version 2, June 2018    NORTH CAROLINA BROWNFIELDS PROGRAM  ENVIRONMENTAL MANAGEMENT PLAN    This form is to be used to prepare an Environmental Management Plan (EMP) for projects in  the North Carolina Brownfields Program at the direction of a Brownfields project manager.    The EMP is a typical requirement of a Brownfields Agreement (BFA).  Its purpose is to clarify  actions to be taken during the demolition and construction at Brownfields properties in an  effort to avoid delays in the event of the discovery of new contamination sources or other  environmental conditions.  The EMP provides a means to document redevelopment plans and  environmental data for each applicable environmental medium to inform regulatory‐compliant  decision‐making at the site.  As much detail as possible should be included in the EMP,  including contingency planning for unknowns.  Consult your project manager if you have  questions.    Prospective Developers and/or their consultants must complete and submit this form and all  pertinent attachments, see checklist below, to their Brownfields project manager prior to any  earthmoving or other development‐related activities that have the potential to disturb soil at  the Brownfields Property, including demolition.  For the resultant EMP to be valid for use, it  must be completed, reviewed by the program, signed by all parties working on the project,  and approved by the Brownfields project manager.  Failure to comply with the requirements of  the EMP could jeopardize project eligibility, or in the event of a completed agreement, be  cause for a reopener      So that the EMP provides value in protecting brownfields eligibility and public health, the  preparer shall ensure that the following steps have been completed prior to submitting the  EMP for review.  Any EMP prepared without completing these steps is premature.      ☒ Site sampling and assessment that meets Brownfields’ objectives is complete and has  been reviewed and approved by the Brownfields Project Manager.  ☒ Specific redevelopment plans, even if conceptual, have been developed for the project,  submitted and reviewed by the Brownfields Project Manager.                          2  EMP Version 2, June 2018    Please submit, along with the completed EMP form, the following attachments, as relevant  and applicable to the proposed redevelopment:            ☒ A set of redevelopment plans, including architectural/engineering plans, if available; if  not conceptual plans may suffice if updated when detailed plans are drafted.    ☒ A figure overlaying redevelopment plans on a map of the extent of contamination for  each media.    ☒ Site grading plans that include a cut and fill analysis.    ☒ A figure showing the proposed location and depth of impacted soil that would remain  on site after construction grading.    ☐ Any necessary permits for redevelopment (i.e. demolition, etc.).    ☒ A detailed construction schedule that includes timing and phases of construction.    ☒ Tabulated data summaries for each impacted media (i.e. soil, groundwater, soil gas,  etc.) applicable to the proposed redevelopment.    ☒ Figures with the sampling locations and contamination extents for each impacted media  applicable to the proposed redevelopment.    ☐ A full final grade sampling and analysis plan, if the redevelopment plan is final.    ☐ If known, information about each proposed potential borrow soil source, such as aerial  photos, historic site maps, historic Sanborn maps, a site history, necessary for  brownfields approval.    ☐ Information and, analytical data if required, for quarries, or other borrow sources,  detailing the type of material proposed for importation to the Brownfields Property.    ☐ A work plan for the sampling and analysis of soil to be brought onto the Brownfields  Property.  Refer to Issue Resolution 15 in Brownfields Program Guidelines.    ☐ A map of the Brownfields Property showing the location of soils proposed for export  and sampling data from those areas.    ☒ If a Vapor Mitigation System is required by the Brownfields Program, the Vapor  Intrusion Mitigation System (VIMS) plan will be signed and sealed by a NC Professional  Engineer.  The VIMS Plan may also be submitted under separate cover.        3  EMP Version 2, June 2018    GENERAL INFORMATION      Date: 2/27/2019 Revision Date (if applicable): 3/26/2019    Brownfields Assigned Project Name: South Tryon Commercial    Brownfields Project Number: 22007‐18‐060    Brownfields Property Address: 340 W. Tremont Street, Charlotte    Brownfields Property Area (acres): approximately 2.4 acres   Is Brownfields Property Subject to RCRA Permit?.......................☐ Yes   ☒ No  If yes enter Permit No.: Click or tap here to enter text.  Is Brownfields Property Subject to a Solid Waste Permit….……..☐ Yes   ☒ No  If yes, enter Permit No.: Click or tap here to enter text.      COMMUNICATIONS    A copy of this EMP shall be distributed to all the parties below as well as any contractors or site workers  that may be exposed to site vapors, soil, groundwater, and/or surface water.  Additionally, a copy of the  EMP shall be maintained at the Brownfields Property during redevelopment activities.  NOTE, THE EMP  DOES NOT TAKE THE PLACE OF A SITE‐SPECIFIC HEALTH AND SAFETY PLAN.    Prospective Developer (PD): RRPV South Tryon Charlotte, LP    Contact Person: Mr. Ashley Saulpaugh   Phone Numbers:   Office: 704‐377‐6730 Mobile: Click or tap here to enter text.    Email: asaulpaugh@ramrealestate.com      Contractor for PD: Choate Construction    Contact Person: David Behr  Phone Numbers:   Office: 704‐602‐7255 Mobile: Click or tap here to enter text.    Email: dbehr@choateco.com       Environmental Consultant: Hart & Hickman, PC     Contact Person: Ralph McGee  Phone Numbers:   Office: 704‐887‐4621 Mobile: Click or tap here to enter text.    Email: rmcgee@harthickman.com     Brownfields Program Project Manager:  Bill Schmithorst  Phone Numbers:   Office: 919‐707‐8159 Mobile: Click or tap here to enter text.    Email: william.schmithorst@ncdenr.gov      Other DEQ Program Contacts (if applicable, i.e., UST Section, Inactive Hazardous Site Branch,      4  EMP Version 2, June 2018    Hazardous Waste, Solid Waste):   Click or tap here to enter text.    NOTIFICATIONS TO THE BROWNFIELDS PROGRAM      Written advance Notification Times to Brownfields Project Manager: Check each box to accept  minimum advance notice periods (in calendar days) for each type of onsite task:    On‐site assessment or remedial activities:……………………………………….…… 10 days Prior        ☒    Construction or grading start:……………………………………….………………………. 10 days Prior       ☒    Discovery of stained soil, odors, USTs, buried drums or waste, landfill, or other signs of previously  unknown contamination: ……………………………….……………………………………. Within 48 hours   ☒   Implementation of emergency actions (e.g. dewatering, flood or soil erosion control measures in  area of contamination, ventilation of work zones):…………….……….……… Within 48 hours  ☒    Installation of mitigation systems:………………………….………………….……….. 10 days Prior         ☐   Other notifications as required by local, state or federal agencies to implement redevelopment  activities: (as applicable): ……………………….…………………………………………..… Within 30 days     ☒  REDEVELOPMENT PLANS    1) Type of Redevelopment (check all that apply):  ☐Residential  ☐Recreational  ☐Institutional  ☒Commercial  ☒Office  ☒Retail  ☐Industrial  ☒Other specify:  Open space and parking    2) Check the following activities that will be conducted prior to commencing earth‐moving activities  at the site:  ☒ Review of historic maps (Sanborn Maps, facility maps)  ☐ Conducting geophysical surveys to evaluate the location of suspect UST, fuel lines, utility  lines, etc.  ☐ Interviews with employees/former employees/facility managers/neighbors    3) Summary of Redevelopment Plans (MANDATORY: attach detailed plans or conceptual plans, if  detailed plans are not available. EMP review without such information would be premature):    Provide brief summary of redevelopment plans, including demolition, removal of building  slabs/pavement, grading plans and planned construction of new structures:   A Site location map is provided as Figure 1 and the Site and surrounding area are shown in Figure      5  EMP Version 2, June 2018    2.  Redevelopment plans include construction of one approximate 17,400 square foot (sq ft)  single story building (Building AB), and one approximate 43,700 sq ft 3‐story building (Building C;  approximately 14,600 sq ft footprint) and associated parking areas and open spaces.  The  intended future uses of the proposed buildings include commercial businesses, retail businesses,  and offices with associated parking areas and common areas.  A copy of the current  redevelopment plan is included in Appendix A.  A copy of the proposed grading plan with cut‐fill  analysis is provided as Appendix B.     4) Do plans include demolition of structure(s)?:     ☐ Yes  ☒ No ☐ Unknown   ☐ If yes, please check here to confirm that demolition will be conducted in accordance with  applicable legal requirements, including without limitation those related to lead and asbestos  abatement that are administered by the Health Hazards Control Unit within the Division of Public  Health of the North Carolina Department of Health and Human Services.  If available, please  provide a copy of your demolition permit.     5) Are sediment and erosion control measures required by federal, state, or local regulations?    ☒ Yes    ☐ No    ☐ Unknown   ☒  If yes, please check here to confirm that demolition will be conducted in accordance with  applicable legal requirements.  If soil disturbance is necessary to install sediment and erosion  control measures, they may not begin until this EMP is approved.     6) Which category of risk‐based screening level is used or is anticipated to be specified in the  Brownfields Agreement?  Note: If children frequent the property, residential screening levels shall  be cited in the Brownfields Agreement for comparison purposes.  ☐ Residential   ☒ Non‐Residential or Industrial/Commercial    7) Schedule for Redevelopment (attach construction schedule):  a) Construction start date: 4/2/2019     b) Anticipated duration (specify activities during each phase):   Approximately 7 months  A detailed construction schedule is provided as Appendix C.    c) Additional phases planned? ☐ Yes  ☐ No      If yes, specify the start date and/or activities if known:   Start Date:  Click or tap to enter a date.      Planned Activity:  Click or tap here to enter text.  Start Date:  Click or tap to enter a date.      Planned Activity:  Click or tap here to enter text.          6  EMP Version 2, June 2018    Start Date: Click or tap to enter a date.      Planned Activity:  Click or tap here to enter text.  d) Provide the planned date of occupancy for new buildings: 11/1/2019     CONTAMINATED MEDIA    1) Contaminated Media on the Brownfields Property  Part 1. Soil:……………………………………….……………. ☐  Yes   ☒ No   ☐ Suspected    Part 2. Groundwater:.……………………….……..……. ☒  Yes   ☐ No   ☐ Suspected    Part 3. Surface Water:.……………...……..…………… ☐  Yes   ☒ No   ☐ Suspected    Part 4. Sediment:.……………...……..…………………… ☐  Yes   ☒ No   ☐ Suspected    Part 5. Soil Vapor:…..…………...……..…………………. ☐  Yes   ☒ No   ☐ Suspected    Part 6. Sub‐Slab Soil Vapor:……...……..…………….. ☐  Yes   ☐ No   ☐ Suspected  Part 7. Indoor Air:...……..…………………………………. ☐  Yes   ☐ No   ☐ Suspected    2) For the Area of Proposed Redevelopment on the Brownfields Property, attach tabulated data  summaries for each impacted media and figure(s) with sample locations.       PART 1. Soil – Please fill out the information below, using detailed site plans, if available, or estimate  using known areas of contaminated soil and a conceptual redevelopment plan.  Provide a figure  overlaying new construction onto figure showing contaminated soil and groundwater locations.    1) Known or suspected contaminants in soil (list general groups of contaminants):  Multiple soil sampling events have been completed at the Brownfields property.  A tabular  summary of available soil analytical data from each sampling event in comparison to the  February 2018 North Carolina Department of Environmental Quality (DEQ) Inactive Hazardous  Sites Branch (IHSB) Preliminary Soil Remediation Goals (PSRGs) is included as Table 1.  Soil  sample locations are shown in Figure 3.  A brief summary of the results is provided below.       Volatile Organic Compounds (VOCs)   Assessment activities conducted on the Brownfields property have identified low levels of VOCs  at concentrations below DEQ IHSB Industrial/Commercial PSRGs.     Semi‐Volatile Organic Compounds (SVOCs)  Assessment activities conducted on the Brownfields property have identified low levels of SVOCs  at concentrations below DEQ IHSB Industrial/Commercial PSRGs.           7  EMP Version 2, June 2018    Polychlorinated Biphenyls (PCBs)  Assessment activities conducted on the Brownfields property did not identify PCBs at  concentrations above laboratory method detection limits.    Metals   Assessment activities conducted on the Brownfields property have identified low levels of metals  at concentrations below DEQ IHSB Industrial/Commercial PSRGs.  In addition, the metals  concentrations are within the expected range for naturally occurring levels and are therefore  considered background.      Organochlorine Pesticides (OCPs)  Assessment activities conducted on the Brownfields property did not identify OCPs at  concentrations above laboratory method detection limits.      2) Depth of known or suspected contaminants (feet):  Not applicable    3) Area of soil disturbed by redevelopment (square feet):  Up to 104,000 sq ft (i.e., entire site will be graded for leveling prior to construction)    4) Depths of soil to be excavated (feet):  Proposed grading activities are expected to include excavations of up to approximately 6 ft  below ground surface (bgs) in various portions of the Brownfields property to reach final  proposed grade elevations.  Construction of building footers, foundations and utility installations  may require additional excavations of up to 3 to 5 ft bgs.  A grading plan and cut/fill analysis for  the proposed redevelopment is provided as Appendix C.      5) Estimated volume of soil (cubic yards) to be excavated (attach grading plan):  Up to approximately 1,800 cubic yards of soil are planned to be excavated and re‐used on‐Site as  beneficial fill during grading activities.      6) Estimated volume of excavated soil (cubic yards) anticipated to be impacted by contaminants:              None anticipated at this time    7) Estimated volume of contaminated soil expected to be disposed of offsite, if applicable:    None anticipated at this time.      Part 1.A. MANAGING ONSITE SOIL  If soil is anticipated to be excavated from the Brownfield Property, relocated on the Brownfields  Property, or otherwise disturbed during site grading or other redevelopment activities, please  provide a grading plan that clearly illustrates areas of cut and fill (approximate areas & volumes are      8  EMP Version 2, June 2018    acceptable, if only preliminary data available).      1) HAZARDOUS WASTE DETERMINATION:   a) Does the soil contain a LISTED WASTE as defined in the North Carolina Hazardous  Waste Section under 40 CFR Part 261.31‐261.35?....................................... ☐Yes   ☒No  ☐ If yes, explain why below, including the level of knowledge regarding processes  generating the waste (include pertinent analytical results as needed).  Click or tap here to enter text.    ☐ If yes, do the soils exceed the “Contained‐Out” levels in Attachment 1 of the  North Carolina Contained‐In Policy?................................................. ☐ Yes   ☐ No    b) NOTE: IF SOIL MEETS THE DEFINITION OF A LISTED HAZARDOUS WASTE AND EXCEEDS  THE CONTAINED‐OUT LEVELS IN ATTACHMENT 1 TO THE NORTH CAROLINA  CONTAINED‐IN POLICY THE SOIL MAY NOT BE RE‐USED ON SITE AND MUST BE  DISPOSED OF IN ACCORDANCE WITH DEQ HAZARDOUS WASTE SECTION RULES AND  REGULATIONS.      c)  Does the soil contain a CHARACTERISTIC WASTE?.................................... ☐ Yes   ☒ No  ☐ If yes, mark reason(s) why below (and include pertinent analytical results).  ☐ Ignitability  Click or tap here to enter text.                ☐ Corrosivity Click or tap here to enter text.  ☐ Reactivity Click or tap here to enter text.  ☐ Toxicity Click or tap here to enter text.  ☐ TCLP results Click or tap here to enter text.  ☐ Rule of 20 results (20 times total analytical results for an individual  hazardous constituent on TCLP list cannot, by test method, exceed regulatory  TCLP standard)    Click or tap here to enter text.    ☒ If no, explain rationale:   Soil analytical data does not indicate detections capable of exceeding toxicity  characteristic leaching procedure (TCLP) criteria using the Rule of 20.    d) NOTE: IF SOIL MEETS THE DEFINITION OF A CHARACTERISTIC HAZARDOUS WASTE, THE  SOIL MAY NOT BE RE‐USED ON SITE AND MUST BE DISPOSED OF IN ACCORDANCE  WITH DEQ HAZARDOUS WASTE SECTION RULES AND REGULATIONS.    2) Screening criteria by which soil disposition decisions will be made (e.g., left in place, capped in  place with low permeability barrier, removed to onsite location and capped, removed offsite):        ☐ Preliminary Health‐Based Residential SRGs       9  EMP Version 2, June 2018          ☒ Preliminary Health‐Based Industrial/Commercial SRGs              ☒ Division of Waste Management Risk Calculator (For Brownfields Properties Only)      ☐ Site‐specific risk‐based cleanup level. Please provide details of methods used for  determination/explanation.   Click or tap here to enter text.    Additional comments:   Click or tap here to enter text.    3) If known impacted soil is proposed to be reused within the Brownfields Property Boundary,  please check the measures that will be utilized to ensure safe placement and documentation of  same.   Please attach a proposed location diagram/site map.         ☒ Provide documentation of analytical report(s) to Brownfields Project Manager  ☒ Provide documentation of final location, thickness and depth of relocated soil on site map  to Brownfields Project Manager once known  ☐ Geotextile to mark depth of fill material.   Provide description of material:   Click or tap here to enter text.    ☒ Manage soil under impervious cap ☒  or clean fill ☒   ☒ Describe cap or fill:   Should potentially impacted soil be encountered during redevelopment, the potentially  impacted soil will be placed in areas that will be beneath impervious surfaces (asphalt  pavement, sidewalks, access roads, buildings, etc.) or a minimum of 2 ft of clean fill upon  completion of redevelopment activities.     ☒ Confer with NC BF Project Manager if Brownfield Plat must be revised (or re‐recorded if  actions are Post‐Recordation).          ☒ GPS the location and provide site map with final location.  ☐ Other. Please provide a description of the measure:        4) Please describe the following action(s) to be taken during and following excavation and  management of site soils:  Management of fugitive dust from site  ☒ Yes, describe the method will include:  Significant areas of contaminated soil are not expected to be encountered during Site  redevelopment activities based upon soil sampling data and the grading plan. The grading  contractor will take into account conditions such as wind speed, wind direction, and  moisture content of soil during soil grading and stockpiling activities to minimize dust  generation.  Particular attention will be paid by contractors to implement dust control  Click or tap here to enter text.      10  EMP Version 2, June 2018    measures as needed based on Site and atmospheric conditions (i.e., by controlled water  application, hydro‐seeding, and/or mulch, stone, or plastic cover).  Potentially impacted soil  will be managed as described below      ☐ No, explain rationale:  Click or tap here to enter text.     Field Screening of site soil  ☒ Yes, describe the field screening method, frequency of field screening, person conducting  field screening:   During soil disturbance at the Site, the workers or contractors will observe soils for  evidence of potential significantly impacted soil.  Evidence of potential significantly  impacted soil includes a distinct unnatural color, strong odor, or filled or previously  disposed materials of concerns (i.e., chemicals, tanks, drums, etc.).  Should the above be  noted during Site work, the contractor will contact the project environmental engineer to  observe the suspect condition.  If the project environmental engineer confirms that the  material may be impacted, then the procedures below will be implemented. In addition,  the environmental engineer will contact the DEQ Brownfields project manager within two  business days to advise that person of the condition    ☐ No, explain rationale:     Click or tap here to enter text.    Soil Sample Collection  ☐ Yes, describe the sampling method (e.g., in‐situ grab, composite, stockpile, etc.):   Click or tap here to enter text.    ☒ No, explain rationale:   Collection of additional soil samples is not anticipated based on results of previous Site  assessment activities.  If significant soil impact is encountered during grading and/or  installation or removal of utilities, excavation will proceed only as far as needed to allow  grading and/or construction of the utility to continue and/or only as far as needed to  allow alternate corrective measures described below.  Suspect significantly impacted soil  excavated during grading and/or utility line installation or removal may be stockpiled and  covered in a secure area to allow construction to progress.  Suspect impacted soil will be  underlain by and covered with minimum 10‐mil plastic sheeting.  At least one  representative sample of the soil will be collected for analysis of total VOCs, SVOCs, and  RCRA metals.  If the results of analysis of the sample indicate that the soil could  potentially exceed toxicity characteristic hazardous waste criteria, then the soil will also  be analyzed by TCLP for those compounds that could exceed the toxicity characteristic  hazardous waste criteria.  *Please note that total chromium concentrations detected at  the Site will be considered trivalent chromium as hexavalent chromium detections in Site  soil appear to be consistent with background levels.  If concentrations of total chromium      11  EMP Version 2, June 2018    are detected in a soil sample at concentrations greater than an order of magnitude above  the highest detected historical concentration (100 mg/kg), that soil sample will be  submitted for hexavalent chromium analysis.                                                                                   Impacted soil will be handled in the manner described below based upon the laboratory  analyses:                                                                                                                                                    i.       If no organic compounds are detected in a sample (other than which are  attributable to sampling or laboratory artifacts) and metals are below the lowest  applicable PSRG or are consistent with Site‐specific background levels, then the soil will be  deemed suitable for use as on‐Site fill or as off‐Site fill.  The proposed location(s) for off‐ Site placement of soil (other than a permitted facility) along with the receiving facility’s  written approval for acceptance of the soil will be provided to DEQ for approval prior to  taking the soil off‐Site.                                                                                                                            ii.       If detectable levels of compounds are found which do not exceed the DEQ IHSB  Industrial/Commercial PSRGs (other than which are attributable to sampling or laboratory  artifacts or which are consistent with Site‐specific background levels for metals) and the  TCLP concentrations are below hazardous waste criteria, then the soil may be used on‐ Site as fill without conditions.                                                                                                               iii.     If detectable levels of compounds are found which exceed the DEQ IHSB  Industrial/Commercial PSRGs (other than which are attributable to sampling or laboratory  artifacts or which are consistent with background levels for metals) and the TCLP  concentrations are below hazardous waste criteria, then the soil, with DEQ written  approval, may be used on‐Site as fill below an impervious surface, or at least 2 ft of  compacted clean soil.  If the impacted soil with concentrations above  Industrial/Commercial PSRGs is moved to an on‐Site location, its location and depth will  be documented, and its location will be provided to DEQ.                                                              iv.     Impacted soil may be transported to a permitted facility such as a landfill provided  that the soil is accepted at the disposal facility.  If soil is transported to a permitted  facility, the permitted facility’s written approval or approved waste characterization  profile to dispose of soil from the Site will be included with the final EMP report.  In the  unlikely event that the sample data indicates concentrations above TCLP hazardous waste  criteria, then the soil must be transported off‐site to a permitted disposal facility that can  accept or treat hazardous waste.                                                                                             *Please note that should the PD elect to transport export soil to a permitted facility or to  a DEQ Brownfields pre‐approved receiving facility, soil will be direct loaded onto trucks  for transport off‐Site.     If soil samples are collected for analysis, please check the applicable chemical analytes:  ☒ Volatile organic compounds (VOCs) by EPA Method 8260  ☒ Semi‐volatile organic compounds (SVOCs) by EPA Method 8270  ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium  and silver): Specify Analytical Method Number(s):      12  EMP Version 2, June 2018    EPA Methods 6020/7471   ☐ Pesticides: Specify Analytical Method Number(s):   Click or tap here to enter text.   ☐ PCBs: Specify Analytical Method Number(s):   Click or tap here to enter text.   ☐ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent Chromium,  Herbicides, etc.): Specify Analytical Method Number(s):        ☒ Check to confirm that stockpiling of known or suspected impacted soils will be conducted  in accordance with Figure 1 of this EMP.  Stockpile methodology should provide erosion  control, prohibiting contact between surface water/precipitation and contaminated soil,  and preventing contaminated runoff.  Explain any variances or provide additional details as  needed:      ☒ Final grade sampling of exposed native soil (i.e., soil that will not be under buildings or  permanent hardscape). Select chemical analyses for final grade samples with check boxes  below (Check all that apply):  ☒ Volatile organic compounds (VOCs) by EPA Method 8260  ☒ Semi‐volatile organic compounds (SVOCs) by EPA Method 8270  ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead,  selenium and silver): Specify Analytical Method Number(s):  EPA Method 6020 and 7471   ☒ Pesticides: Specify Analytical Method Number(s):     EPA Method 8081   ☐ PCBs: Specify Analytical Method Number(s):   Click or tap here to enter text.   ☐ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent  Chromium, Herbicides, etc.):         Please provide a scope of work for final grade sampling, including a diagram of soil  sampling locations, number of samples to be collected, and brief sampling methodology.   Samples should be collected from 0‐2 ft below ground surface, with the exception of VOCs  which should be taken from 1‐2 ft below ground surface.  Alternatively, a work plan for  final grade sampling may be submitted under separate cover.         Click or tap here to enter text.      13  EMP Version 2, June 2018    ☒ If final grade sampling was NOT selected please explain rationale:  Following completion of soil disturbance for future Site development (i.e., after grading  and utility construction), an environmental professional will be contracted to assess the  Site for areas that are not covered with clean fill soil, building foundations, sidewalks, or  asphalt or concrete parking areas and driveways, or other similar impervious areas.  If such  areas exist, a plan will be prepared for final grade sampling for DEQ Brownfields review  and approval.  If no such areas exist, documentation will be provided to the DEQ  Brownfields project manager.      Part 1.B. IMPORTED FILL SOIL    NO SOIL MAY BE BROUGHT ONTO THE BROWNFIELDS PROPERTY WITHOUT PRIOR APPROVAL  FROM THE BROWNFIELDS PROGRAM.  According to the Brownfields IR 15, “Documenting  imported soil (by sampling, analysis, and reporting in accordance with review and written  approval in advance by the Brownfields Program), will safeguard the liability protections provided  by the brownfields agreement and is in the best interest of the prospective developer/property  owner.”    Requirements for importing fill:    1) Will fill soil be imported to the site?................................................ ☒ Yes  ☐ No  ☐ Unknown    2) If yes, what is the estimated volume of fill soil to be imported?   According to the grading plan and cut‐fill analysis, up to approximately 1,202 cubic yards of  import soil may be needed to balance the Site.  The PD also plans to import limited amounts of  organic rich topsoil from a reputable landscape material vendor for use in proposed landscaped  areas..    3) If yes, what is the anticipated depth that fill soil will be placed at the property? (If a range  of depths, please list the range.)  Select areas at the Site will require up to approximately 6 ft of fill.  Soil from areas of cut will be  used in planned areas of fill to balance the Site.  The estimated approximately 1,202 cubic yards of  fill will be placed at the Site for leveling once on‐Site soil has been used.  Therefore, the  anticipated depth for placement of import fill is unknown at this time.       4) Provide the source of fill, including: location, site history, nearby environmental concerns,  etc. Attach aerial photos, maps, historic Sanborn maps and a borrow source site history:  The source of potential import fill that may be needed is unknown at this time.  DEQ will be  notified and the procedures outlined below will be implemented prior to transporting soil to the  Site for use as fill.    5) PRIOR TO ITS PLACEMENT AT THE BROWNFIELDS PROPERTY, provide a plan to analyze fill  soil to demonstrate that it meets acceptable standards applicable to the site and can be  approved for use at the Brownfields property.      14  EMP Version 2, June 2018    The PD plans to import limited amounts of organic rich topsoil from a commercial landscape  material vendor for use in proposed landscaped areas.  The PD does not plan to collect samples  of landscaping materials prior to placement at the Site.  DEQ Brownfields will be notified of the  volume of landscaping material needed and the proposed source of the material prior to  placement in proposed landscaping areas.  A limited volume of import fill for grading and  construction purposes may be needed during redevelopment.  Please refer to No. 7 below for  details outlining the proposed plan to demonstrate import soil meets acceptable standards  applicable to the Site.     6) Please check the applicable chemical analytes for fill soil samples.  (Check all that apply):  ☒ Volatile organic compounds (VOCs) by EPA Method 8260  ☒ Semi‐volatile organic compounds (SVOCs) by EPA Method 8270  ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead,  selenium and silver): Specify Analytical Method Number(s):  EPA Method 6020 and EPA Method 7471   ☐ Pesticides: Specify Analytical Method Number(s):     Click or tap here to enter text.   ☐ PCBs: Specify Analytical Method Number(s):   Click or tap here to enter text.   ☒ Other Constituents & Respective Analytical Method(s) (i.e. Hexavalent  Chromium, Herbicides, etc.):   Hexavalent Chromium by EPA Method 7199   7) The scope of work for import fill sampling may be provided below or in a Work Plan  submitted separately for DEQ review and approval.  Attach specific location maps for in‐situ  borrow sites.  If using a quarry, provide information on the type of material to be brought  onto the Brownfields Property.  The PD will follow the procedures outlined below to demonstrate import soil meets acceptable  standards applicable to the Site.                                                                                                                         If the PD plans to import fill material from Vulcan Materials Company quarry located near  Pineville, NC or from the Martin Marietta quarry located on Beatties Ford Road in Charlotte, NC,  and the material from these facilities is virgin material, no samples of the import material will be  collected as adequate analytical data is available in the DEQ Brownfields database to demonstrate  virgin material from these facilities is suitable for use as structural fill at a Brownfields property.       If fill soil is obtained from an off‐Site property that is not a known permitted quarry, a sampling  plan will be developed and submitted for DEQ review.  DEQ approval of the sampling plan and  analytical results will be obtained prior to transporting import soil to the Site. The specific  sampling rate will be outlined in the aforementioned sampling plan.  However, if the proposed  borrow source has not been previously developed (i.e., virgin land), soil samples will be collected  for laboratory analyses indicated above at a general rate of one per 1,000 cubic yards.  If the  borrow source property has been previously developed, soil samples will be collected for      15  EMP Version 2, June 2018    laboratory analyses indicated above at a general rate of approximately one per 500 cubic yards.   Fill soil will be considered suitable for use at the Site if it does not contain compound  concentrations above DEQ IHSB Industrial/Commercial PSRGs or typical metals concentrations  which are consistent with background levels identified at the Site.         Part 1.C. EXPORTED SOIL    NO SOIL MAY LEAVE THE BROWNFIELDS PROPERTY WITHOUT APPROVAL FROM THE  BROWNFIELDS PROGRAM.  FAILURE TO OBTAIN APPROVAL MAY VIOLATE A BROWNFIELDS  AGREEMENT CAUSING A REOPENER OR JEOPARDIZING ELIGIBILITY IN THE PROGRAM,  ENDANGERING LIABILITY PROTECTIONS AND MAKING SAID ACTION POSSIBLY SUBJECT TO  ENFORCEMENT.  JUSTIFICATIONS PROVIDED BELOW MUST BE APPROVED BY THE PROGRAM IN  WRITING PRIOR TO COMPLETING TRANSPORT ACTIVITIES.  Please refer to Brownfields IR 15 for  additional details.     1) If export from a Brownfields Property is anticipated, please provide details regarding the  proposed export actions.  Volume of exported soil, depths, location from which soil will  be excavated on site, related sampling results, etc. Provide a site map with locations of  export and sampling results included.  Export soil is not anticipated at this time.  Should soil need to be exported from the Brownfields  property during redevelopment, a sampling plan will be developed and submitted to DEQ  Brownfields for review and approval once the volume of soil for export is known.  Generally, soil  samples will be collected from export soil at a rate of 1 sample per every 500 cubic yards of  export.    DEQ approval of the sampling plan and analytical results will be obtained prior to transporting  export soil from the Site.  Based on analytical results of soil samples collected from the export  soil, the soil will be transported off‐Site to a suitable location.  The PD will notify DEQ  Brownfields of the location receiving the export soil and DEQ Brownfields approval and written  approval from the receiving facility will be obtained prior to transporting the soil off‐Site.    2) To what type of facility will the export Brownfields soil be sent?   ☒ Subtitle D/Municipal Solid Waste Landfill (analytical program to be determined by  landfill)  ☒ Permitted but Unlined Landfill (i.e. LCID, C&D, etc.) Analytical program to be  determined by the accepting Landfill;   ☒ Landfarm or other treatment facility   ☒ Use as fill at another suitable Brownfields Property – determination that a  site is suitable will require, at a minimum, that similar concentrations of the same or  similar contaminants already exist at both sites, use of impacted soil will not increase  the potential for risk to human health and the environment at the receiving Brownfields  property, and that a record of the acceptance of such soil from the property owner of  the receiving site is provided to Brownfields.  Please provide additional details below.       16  EMP Version 2, June 2018    ☒ Use as Beneficial Fill off‐site at a non‐Brownfields Property ‐ Please provide  documentation of approval from the property owner for receipt of fill material.  This will  also require approval by the DEQ Solid Waste Section.  Additional information is  provided in IR 15.  Please provide additional details below.     3) Additional Details: (if transfer of soil to another property is requested above, please provide  details related to the proposed plans).  The environmental engineer will contact DEQ Brownfields to obtain DEQ Brownfields and DEQ  Solid Waste approval prior to exporting soil to a non‐Brownfields property or non‐permitted  disposal facility.       Part 1.D. MANAGEMENT OF UTILITY TRENCHES    ☐ Install liner between native impacted soils and base of utility trench before filling with clean fill  (Preferred)    ☒ Last out, first in principle for impacted soils (if soil can safely be reused onsite and is not a  hazardous waste), i.e., impacted soils are placed back at approximately the depths they  were removed from such that impacted soil is not placed at a greater depth than the original  depth from which it was excavated.    ☐ Evaluate whether necessary to install barriers in conduits to prevent soil vapor transport,  and/or degradation of conduit materials due to direct impact with contaminants?  ☐ If yes, provide specifications on barrier materials:  Click or tap here to enter text.    ☒ If no, include rationale here:  Results of assessment activities completed at the Site indicate that no soil vapor concentrations  exceeding risk thresholds for a worker have been identified at the Site.    Other comments regarding managing impacted soil in utility trenches:   Although not anticipated, in the event contaminated soil and/or vapors are encountered in utility  trenches during redevelopment activities, the trench will be evacuated and appropriate safety  screening of the vapors will be performed to protect workers.  If results indicate further action is  warranted in response to vapors to protect workers, appropriate engineering controls (such as use of  industrial fans) will be implemented.      The contractor and workers will observe soil for potential impacts during utility installation activities.  Evidence of potential significant impacted soil includes a distinct unnatural color, strong odor, or filled  or previously disposed materials of concerns (i.e. chemicals, tanks, drums, etc.).  Should the above be  noted during utility work, the contractor will contact the project environmental engineer to observe  the suspect condition.  If the project environmental engineer confirms that the material may be  impacted, then the procedures outlined Managing On‐Site Soil above will be implemented.  In      17  EMP Version 2, June 2018    addition, the environmental engineer will contact the DEQ Brownfields project manager within two  business days to advise that person of the condition.      PART 2. GROUNDWATER – Please fill out the information below.    1) What is the depth to groundwater at the Brownfields Property?  Based on available information, depth to groundwater appears to be approximately 20 to 30 ft  bgs at the Brownfields property.        2) Is groundwater known to be contaminated by ☐onsite  ☐offsite   ☐both or ☒unknown  sources?  Describe source(s):   Multiple groundwater sampling events have been completed at the Brownfields property.  A  tabular summary of available groundwater analytical data from each sampling event in  comparison to the North Carolina Administrative Code (NCAC) 2L Groundwater Standards (2L  Standards) is included as Table 2 and groundwater sample locations are shown in Figure 3.      Results of groundwater assessment indicated low levels of VOCs tetrachloroethene (PCE),  trichloroethene (TCE), and OCPs aldrin and dieldrin have been detected in groundwater at  concentrations above 2L Standards at the Brownfields property.    3) What is the direction of groundwater flow at the Brownfields Property?   Based on available information, direction of groundwater flow appears to be to the north‐ northwest.      4) Will groundwater likely be encountered during planned redevelopment activities?     ☐Yes    ☒No   If yes, describe these activities:  Click or tap here to enter text.    Regardless of the answer; in the event that contaminated groundwater is encountered  during redevelopment activities (even if no is checked above), list activities for contingent  management of groundwater (e.g., dewatering of groundwater from excavations or  foundations, containerizing, offsite disposal, discharge to sanitary sewer, NPDES permit, or  sampling procedures).   Although not anticipated at this time, appropriate worker safety measures will be undertaken if  groundwater gathers in an open excavation within an area determined to be impacted during  construction activities. The accumulated water will be allowed to evaporate/infiltrate to the  extent time for dissipation does not disrupt the construction schedule.  Should the time needed  for natural dissipation of accumulated water be deemed inadequate, the water will be tested  and disposed off‐Site (if impacted), or tested and discharged to the storm sewer (if not  impacted above DEQ surface water standards) in accordance with applicable municipal and  State regulations for erosion control and construction stormwater control.    5) Are monitoring wells currently present on the Brownfields Property?.................☐Yes   ☒No     If yes, are any monitoring wells routinely monitored through DEQ or other      18  EMP Version 2, June 2018    agencies?..................................................................................................................☐Yes   ☒No     6) Please check methods to be utilized in the management of known and previously  unidentified wells.    ☐ Abandonment of site monitoring wells in accordance with all applicable regulations.  It  is the Brownfields Program’s intent to allow proper abandonment of well(s) as  specified in the Brownfields Agreement, except if required for active monitoring  through another section of DEQ or the EPA.    ☐ Location of existing monitoring wells marked  ☐ Existing monitoring wells protected from disturbance   ☒ Newly identified monitoring wells will be marked and protected from further  disturbance until notification to DEQ Brownfields can be made and approval for  abandonment is given.    7) Please provide additional details as needed:        Please note, disturbance of existing site monitoring wells without approval by DEQ is not  permissible.  If monitoring wells are damaged and/or destroyed, DEQ may require that the PD  be responsible for replacement of the well.          PART 3. SURFACE WATER ‐Please fill out the information below.  1) Is surface water present at the property?  ☐ Yes ☒ No  2) Attach a map showing the location of surface water at the Brownfields Property.  3) Is surface water at the property known to be contaminated? ☐ Yes  ☒ No  4) Will workers or the public be in contact with surface water during planned redevelopment  activities?    ☐ Yes  ☒ No  5) In the event that contaminated surface water is encountered during redevelopment  activities, or clean surface water enters open excavations, list activities for management of  such events (e.g. flooding, contaminated surface water run‐off, stormwater impacts):  If surface water run‐off gathers in an open excavation within an area determined to be impacted  during construction activities, appropriate worker safety measures will be undertaken.  The  accumulated water will be allowed to evaporate/infiltrate to the extent time for dissipation does  not disrupt the construction schedule.  Should the time needed for natural dissipation of  accumulated water be deemed inadequate, the water will be tested and disposed off‐Site (if  impacted), or tested and discharged to the storm sewer (if not impacted above DEQ surface  water standards) in accordance with applicable municipal and State regulations for erosion  control and construction stormwater control.      Click or tap here to enter text.      19  EMP Version 2, June 2018      PART 4. SEDIMENT – Please fill out the information below.    1) Are sediment sources present on the property?  ☐ Yes  ☒ No    2) If yes, is sediment at the property known to be contaminated: ☐ Yes  ☒ No    3) Will workers or the public be in contact with sediment during planned redevelopment  activities?   ☐ Yes ☒ No    4) Attach a map showing location of known contaminated sediment at the property.    5) In the event that contaminated sediment is encountered during redevelopment activities, list  activities for management of such events (stream bed disturbance):  Not Applicable        PART 5.  SOIL VAPOR – Please fill out the information below.    1) Do concentrations of volatile organic compounds at the Brownfields property exceed the  following vapor intrusion screening levels (current version) in the following media:  IHSB Residential Screening Levels:  Soil Vapor:………..☒ Yes ☐ No  ☐ Unknown  Groundwater:.….☒ Yes ☐ No ☐ Unknown  IHSB Industrial/Commercial Screening Levels:  Soil Vapor:………..☐ Yes ☒ No ☐ Unknown  Groundwater:…..☒ Yes ☐ No ☐ Unknown  2) Attach a map showing the locations of soil vapor contaminants that exceed site  screening levels.   3) If applicable, at what depth(s) is soil vapor known to be contaminated?   Soil vapor assessment activities were completed on the Brownfields property within the approximate  footprint of the proposed commercial buildings.  The results of the assessment identified low levels of  VOCs at concentrations below DEQ Division of Waste Management (DWM) Vapor Intrusion Non‐ Residential Sub‐Slab and Exterior Soil Gas Screening Levels (SGSLs).  Additionally, results of risk  evaluation using the February 2018 DEQ Risk Calculator indicate that vapor intrusion is not a  significant risk for a non‐residential worker.  A tabular summary of soil vapor analytical data in  comparison to the February 2018 DEQ Vapor Intrusion Non‐Residential SGSLs is included as Table 3  and soil vapor sample locations are shown in Figure 3.    At the request of DEQ Brownfields, soil gas vertical profile assessment activities will be completed at  the Site prior to construction of the proposed Site buildings to further evaluate the potential for      20  EMP Version 2, June 2018         4) Will workers encounter contaminated soil vapor during planned redevelopment activities?    ☐ Yes  ☒ No ☐ Unknown  5) In the event that contaminated soil vapor is encountered during redevelopment activities  (trenches, manways, basements or other subsurface work,) list activities for management  of such contact:   In the unlikely event contaminated soil vapors are encountered during future redevelopment  activities, the area will be evacuated and appropriate safety screening of the vapors will be  performed.  If results indicate further actions are warranted, appropriate engineering controls  (such as use of industrial fans) will be implemented.        PART 6.  SUB‐SLAB SOIL VAPOR – Please fill out the information below if existing buildings or  foundations will be retained in the redevelopment.  1) Are sub‐slab soil vapor data available for the Brownfields Property? ☐ Yes   ☒ No   ☐ Unknown  2) If data indicate that sub‐slab soil vapor concentrations exceed screening levels, attach a map  showing the location of these exceedances.  3) At what depth(s) is sub‐slab soil vapor known to be contaminated? ☐0‐6 inches ☐Other, please  describe:             4) Will workers encounter contaminated sub‐slab soil vapor during planned redevelopment  activities? ☐ Yes   ☒ No   ☐ Unknown  5) In the event that contaminated soil vapor is encountered during redevelopment activities, list  activities for management of such contact  In the unlikely event impacted soil vapors are encountered during future redevelopment  activities, worker breathing zone will be monitored using a calibrated photoionization detector.   If results indicate further action is warranted, appropriate engineering controls (such as use of  industrial fans) will be implemented.          PART 7. INDOOR AIR – Please fill out the information below.    1) Are indoor air data available for the Brownfields Property? ☐ Yes   ☒ No   ☐ Unknown  2) Attach a map showing the location(s) where indoor air contaminants exceed site screening levels.  3) If the structures where indoor air has been documented to exceed risk‐based screening levels will  not be demolished as part of redevelopment activities, will workers encounter contaminated  indoor air during planned redevelopment activities? ☐ Yes   ☐ No   ☐ Unknown  structural vapor intrusion risks associated with redevelopment at the Site.      21  EMP Version 2, June 2018    4) In the event that contaminated indoor air is encountered during redevelopment activities, list  activities for management of such contact:            VAPOR INTRUSION MITIGATION SYSTEM – Please fill out the information below.  Is a vapor intrusion mitigation system (VIMS) proposed for this Brownfields Property?  ☒ Yes   ☐ No   ☐ Unknown  If yes, ☐ VIMS Plan Attached or ☒ VIMS Plan to be submitted separately    If submitted separately provide date:   4/15/2019    VIMS Plan shall be signed and sealed by a NC Professional Engineer    If no, please provide a brief rationale as to why no vapor mitigation plan is warranted:                 CONTINGENCY PLAN – encountering unknown tanks, drums, or other waste materials    In this section please provide actions that will be taken to identify or manage unknown  potential new sources of contamination.   During redevelopment activities, it is not uncommon  that unknown tanks, drums, fuel lines, landfills, or other waste materials are encountered.   Notification to DEQ Brownfields Project Manager, UST Section, Fire Department, and/or other  officials, as necessary and appropriate, is required when new potential source(s) of  contamination are discovered.  These Notification Requirements were outlined on Page 1 of this  EMP.      Should potentially impacted materials be identified that are inconsistent with known site  impacts, the DEQ Brownfields Project Manager will be notified and a sampling plan will be  prepared based on the EMP requirements and site‐specific factors.  Samples will generally be  collected to document the location of the potential impacts.      Check the following chemical analysis that are to be conducted on newly identified releases:  ☒ Volatile organic compounds (VOCs) by EPA Method 8260  There are no current structures located on the Brownfields property.  In the unlikely event there is  evidence of potential indoor air issues (i.e., unusual odors) during future redevelopment activities, the  area will be evacuated and appropriate safety screening of the indoor air will be performed.  If  warranted, safety screening procedures will include periodically screening indoor air for volatile  organic vapors with a calibrated photoionization detector.  If results indicate further action is  warranted, appropriate engineering controls (such as use of industrial fans) will be implemented.       22  EMP Version 2, June 2018    ☒ Semi‐volatile organic compounds (SVOCs) by EPA Method 8270  ☒ Metals RCRA List (8) (arsenic, barium, cadmium, chromium, mercury, lead, selenium and  silver)  EPA Method 6020/7471    ☐ Pesticides: Specify Analytical Method Number(s):   Click or tap here to enter text.    ☐ PCBs: Specify Analytical Method Number(s):   Click or tap here to enter text.    ☒ Other Constituents & Analytical Method(s) (i.e. Hexavalent Chromium, Herbicides, etc.)  Please note, if field observations indicate the need for additional analyses, they should  be conducted, even if not listed here.   Hexavalent Chromium by EPA Method 7199  Please provide details on the proposed methods of managing the following commonly  encountered issues during redevelopment of Brownfields Properties.  During construction activities, contractors may encounter unknown sub‐surface environmental  conditions (i.e. tanks, drums, or waste materials) that if encountered, will require proper  management.  Prior to beginning Site work, the environmental engineer will attend a pre‐ construction kick‐off meeting with the PD and the redevelopment contractors to discuss the DEQ  approved EMP and various scenarios when it would be appropriate and necessary to notify the  environmental engineer of the discovery of unknown subsurface features or potentially impacted  media at the Site.    In the event that such conditions are encountered during site development activities, the  environmental actions noted below will be used to direct environmental actions to be taken during  these activities and sampling data for potentially impacted soil and the disposition of impacted soil  will be provided to DEQ when the data becomes available.    Underground Storage Tanks:   In the event a UST or impacts associated with a UST release are discovered at the Site during  redevelopment activities, the UST and/or UST related impacts will be addressed through the  Brownfields Program.  DEQ Brownfields will be notified within 48‐hours of discovery of the UST.    If a UST is encountered, the UST will be removed, if possible and the UST will be transported off‐Site  for disposal at a suitable facility. If the UST contains residual fluids, the fluids will be sampled for  VOCs, SVOCs, and RCRA metals, and transported off‐Site for disposal at a suitable facility based on  the laboratory analytical results prior to removing the UST from the ground.  If a UST is encountered  that cannot be removed or does not require removal for geotechnical or construction purposes, it  may be abandoned in‐place with prior DEQ approval and construction will proceed.  Where  appropriate, the bottom may be penetrated before abandonment to prevent fluid accumulation.   Impacted soil in the vicinity of the UST will be managed in accordance with the Managing On‐Site      23  EMP Version 2, June 2018    Soil section outlined above in the EMP.      Sub‐Grade Feature/Pit:  If a sub‐grade feature or pit is encountered and does not require removal for geotechnical or  construction purposes, it will be filled with soil or suitable fill and construction will proceed.  Where  appropriate, the bottom may be penetrated before back filling to prevent fluid accumulation.  If the  pit has waste in it, the waste may be set aside in a secure area and will be sampled for waste  disposal purposes for TCLP VOCs, TCLP SVOCs, and TCLP metals and disposed off‐Site at a permitted  facility or the waste will be managed in accordance with the Managing On‐Site Soil section outlined  above in the EMP, whichever is most applicable based on the type of waste present.  If the pit must  be removed and the observed waste characteristics indicate the concrete may potentially be  contaminated to a significant degree, the concrete will be sampled and analyzed by methods  specified by the disposal facility..    Buried Waste Material:  If excavation into buried wastes or significantly impacted soils occurs, the contractor is instructed to  stop work in that location and notify the environmental consultant.  The environmental consultant  will observe the materials and collect samples for laboratory analysis, if warranted.  In this event,  confirmation sampling will be conducted at representative locations in the base and the sidewalls of  the excavation after the waste or significantly impacted soil is removed.  The confirmation samples  will be analyzed for VOCs, SVOCs, and the RCRA metals.  Areas of suspected contaminated soil that  remain at the Site after excavation is complete above the DEQ Industrial/Commercial PSRGs will be  managed pursuant to this plan.    Re‐Use of Impacted Soils On‐Site:  Please refer to description outlined in the Managing On‐Site Soil section of the EMP above.    If unknown, impacted soil is identified on‐site, management on‐site can be considered after the  project team provides the necessary information, outlined in Part 1.A. Item 11, for Brownfields  Project Manager approval prior to final placement on‐site.     If other potential contingency plans are pertinent, please provide other details or scenarios as  needed below:  Click or tap here to enter text.         POST‐REDEVELOPMENT REPORTING    ☒  Check this box to acknowledge that a Redevelopment Summary Report will be required for the  project.  If the project duration is longer than one year, an annual update is required and will be  due by January 31 of each year, or 30 days after each one‐year anniversary of the effective date of      24  EMP Version 2, June 2018    this EMP (as agreed upon with the Project Manager).  These reports will be required for as long as  physical redevelopment of the Brownfields Property continues, except that the final  Redevelopment Summary Report will be submitted within 90 days after completion of  redevelopment.  Based on the estimated construction schedule, the first Redevelopment Summary  Report is anticipated to be submitted on Click or tap to enter a date.     The Redevelopment Summary Report shall include environment‐related activities since the last  report, with a summary and drawings, that describes:   1. actions taken on the Brownfields Property;    2. soil grading and cut and fill actions;   3. methodology(ies) employed for field screening, sampling and laboratory analysis of  environmental media;   4. stockpiling, containerizing, decontaminating, treating, handling, laboratory analysis and  ultimate disposition of any soil, groundwater or other materials suspected or confirmed  to be contaminated with regulated substances; and   5. removal of any contaminated soil, water or other contaminated materials (for example,  concrete, demolition debris) from the Brownfields Property (copies of all legally required  manifests shall be included).    ☒ Check box to acknowledge consent to provide a NC licensed P.G. or P.E. sealed, Redevelopment  Summary Report in compliance with the site’s Brownfields Agreement.         26  EMP Version 2, June 2018          Table 1 Summary of Soil Analytical Data South Tryon CommercialCharlotte, North Carolina Brownfields Project No. 22007-18-060H&H Job No. RMR-006 Sample Location Former UST Dispenser Former UST Northeast Property Corner Sample ID DPT-1 DPT-2 DPT-8 SB-1 SB-2 SB-3 SB-4 SB-5 BKG-01 BKG-02 Depth (ft bgs)1-2 8-10 1-2 1-2 0-1 2-3 0-2 0-2 0.5-1.5 0.5-1.5 Sample Date 7/19/2007 7/19/2007 7/19/2007 5/17/2018 5/17/2018 5/17/2018 5/18/2018 5/18/2018 5/17/2018 5/17/2018 Range Mean Units VOCs (8260) Acetone <0.020 <0.031 0.056 0.040 J 0.11 J <0.023 0.054 J 0.076 J 0.062 J 0.051 J NA NA 140,000 ---- Toluene BRL BRL BRL <0.0009 <0.0011 <0.0008 <0.0008 0.0021 J <0.0009 <0.0009 NA NA 9,700 o-Xylene BRL BRL BRL <0.00081 <0.00098 <0.00070 <0.00071 0.00088 J <0.00076 <0.00078 NA NA 5,900 ---- SVOCs (8270) Benzo[a]anthracene NA NA NA <0.061 <0.058 <0.054 0.056 J 0.064 J 0.083 J 0.12 J NA NA 21 ---- Benzo[a]pyrene NA NA NA <0.072 <0.068 <0.063 <0.059 0.068 J 0.082 J 0.17 J NA NA 2.1 ---- Benzo[b]fluoranthene NA NA NA <0.065 <0.062 <0.057 0.074 J 0.090 J 0.11 J 0.21 NA NA 21 ---- Benzo[g,h,i]perylene NA NA NA <0.100 <0.097 <0.089 <0.084 <0.092 <0.088 0.12 J NA NA NE ---- Benzo[k]fluoranthene NA NA NA <0.072 <0.068 <0.063 <0.059 <0.065 <0.062 0.077 J NA NA 210 ---- Butylbenzylphthalate NA NA NA <0.110 <0.100 <0.097 0.18 J <0.099 <0.095 <0.092 NA NA 1,200 Chrysene NA NA NA <0.072 <0.068 <0.063 <0.059 0.065 J 0.085 J 0.15 J NA NA 2,100 ---- Fluoranthene NA NA NA <0.076 <0.072 <0.067 0.11 J 0.11 J 0.14 J 0.23 NA NA 6,000 ---- Phenanthrene NA NA NA <0.12 <0.11 <0.10 <0.10 <0.11 <0.10 0.13 J NA NA NE ---- Pyrene NA NA NA <0.076 <0.072 <0.067 0.11 J 0.11 J 0.14 J 0.24 NA NA 4,500 ---- PCBs (8082) NA NA NA ALL BRL ALL BRL ALL BRL NA NA NA NA NA NA ------ RCRA Metals (6010/7471/7196) Arsenic NA NA NA 1.0 MS-07 1.4 1.1 1.0 2.0 1.4 1.6 0.28 2.6 3.0 0.28 - 2.6 1.43 Barium NA NA NA 13 23 14 52 65 41 56 63 100 47,000 63 - 100 81.5 Cadmium NA NA NA <0.015 <0.014 <0.013 <0.012 0.025 J <0.013 <0.012 <0.013 0.120 J 200 <0.013 - 0.12 0.07 Chromium (Total)NA NA NA 100 99 24 47 53 33 34 3.1 J 34 NE 3.1 - 34 18.6 Chromium (hexavalent)NA NA NA <0.27 DL-03 0.43 J, DL-03 <0.24 DL-03 <0.23 DL-03 0.39 J, DL-03 <0.23 DL-03 0.38 J, DL-03 <0.24 DL-03 0.63 J, DL-03 6.5 <0.24- 0.63 0.44 Chromium (trivalent)NA NA NA 100 98.57 24 47 52.76 33 33.62 0.7 33.37 350,000 0.7-33 26.9 Lead NA NA NA 10 12 7.5 17 32 15 13 5.7 28 800 5.7 - 28 16.9 Mercury NA NA NA 0.064 0.042 0.028 0.032 0.042 0.029 0.025 J 0.009 J 0.033 9.7 0.009 - 0.033 0.021 Selenium NA NA NA <0.065 MS-07 <0.062 0.12 J <0.053 <0.058 <0.056 <0.055 <0.056 <0.051 1,200 ALL BRL -- Silver NA NA NA 0.057 J 0.069 J 0.027 J 0.043 J 0.058 J 0.050 J 0.068 J 0.061 J 0.070 J 1,200 0.061 - 0.070 0.066 OCPs (8081) NA NA ALL BRL NA NA NA NA NA NA NA NA NA ------ Notes:1) North Carolina Department of Environmental Quality (DEQ) Inactive Hazardous Sites Branch (IHSB) Preliminary Soil Remediation Goals (PSRGs) (February 2018).Only compounds detected in at least one sample are shown.Soil concentrations are reported in milligrams per kilogram (mg/kg).Laboratory analytical methods are shown in parentheses. Compound concentrations reported to laboratory method detection limits. VOCs = volatile organic compounds; SVOCs = semi-volatile organic compounds; PCBs = polychlorinated biphenyls; RCRA = Resource Conservation and Recovery Act; OCPs = Organochlorine PesticidesNA = Not Analyzed; NE = Not Established; BRL = Below Reporting Limit; ft bgs = feet below the ground surface; -- = Not ApplicableJ = Analyte detected at a level less than the laboratory reporting limit and greater than or equal to the laboratory method detection limit resulting in an laboratory estimated concentration DL-03 = Elevated reporting limit due to matrix; MS-07= Matrix spike recovery is outside of control limits. Analysis is in control based on laboratory fortified blank recovery. Possibility of sample matrix effects that lead to low bias for reported result or non-homogeneous sample aliquot cannot be eliminated. 0-2 5/18/2018 mg/kg Former Electrical Supply Warehouse Former Motor Freight Station Background Screening CriteriaSB-6/Duplicate Industrial / Commercial PSRGs(1) Site-Specific Background Metals in Soil S:\AAA-Master Projects\Ram Realty - RMR\RMR-006 Tryon & Tremont Brownfields Assistance\EMP\Data Tables\EMP Combined Tables (RMR-006) 9/19/2018 Table 1 (Page 1 of 1)Hart & Hickman, PC Table 2Summary of 2007 Groundwater Analytical DataS. Tryon CommercialCharlotte, North CarolinaH&H Job No. RMR-006 Sample IDDPT-8DPT-9MW-3 Sample Date7/23/2007 7/24/20078/9/2007 UnitsVOCs (8260B)Acetone16<10 <106,000 4,500,000 19,000,000Chloroform<1.03.22.6708.1361,1-Dichloroethene2.5<1.0<1.035039160Tetrachloroethene<1.0<1.01.60.701248Trichloroethene 2.514113.01.04.4OCPs (8081)Aldrin0.63<0.050 <0.0500.002 *3.2 14Dieldrin0.75 0.15<0.0500.002-- --Endrin Aldehyde 0.32<0.050 <0.050NE-- --RCRA Metals (6010B/7470A)UnfilteredFilteredArsenic<10 <10 NA NA NA10-- --Barium 35 26NA NA NA700-- --Cadmium<1.0 <1.0 NA NA NA2.0-- --Chromium (total)<5.0 <5.0 NA NA NA10-- --Lead<5.0 <5.0 NA NA NA15-- --Mercury <0.20 <0.20 NA NA NA1.0-- --Selenium30 33NA NA NA20-- --Silver<5.0 <5.0 NA NA NA20-- --Notes:1) North Carolina Department of Environmental Quality (DEQ) Title 15A NCAC 02L. 0202 Groundwater Quality Standard (April 2013)* DEQ Title 15A NCAC 02L. 0202 Appendix I Interim Maximum Allowable Concentration (April 2018) is used for screening2) DEQ Division of Waste Management (DWM) Vapor Intrusion Groundwater Screening Levels (GWSLs) (February 2018)Bold indicates an exceedance of the Groundwater Standard.Underline indicates an exceedance of the Residential Vapor Intrusion GWSL.Highlight indicates an exceedance of the Non-Residential Vapor Intrusion GWSL.With the exception of metals, only compounds detected in at least one sample are shown.Concentrations are reported in micrograms per liter (µg/L).Laboratory analytical methods are shown in parentheses.Compound concentrations are reported to laboratory reporting limits.VOCs = volatile organic compounds; OCPs = Organochlorine Pesticides; RCRA = Resource Conservation and Recovery ActNA = Not Analyzed; NE = Not Established; -- = Not ApplicableNon-Residential GWSLs25.720NANANAGroundwater Standard(1)<1.0<1.0DPT-27/20/2007<10µg/LResidential GWSLs2S:\AAA-Master Projects\Ram Realty - RMR\RMR-006 Tryon & Tremont Brownfields Assistance\2007 Groundwater Sampling Report\Tables\GW tables11/15/2018Table 2 (Page 1 of 1) Hart & Hickman, PC Table 3 Summary of Soil Vapor Analytical Data South Tryon CommercialCharlotte, North Carolina Brownfields Project No. 22007-18-060 H&H Job No. RMR-006Sample LocationSample IDVMP-1 VMP-2VMP-4 VMP-5 VMP-6 VMP-7Sample Depth (ft bgs)9.5-10 9.5-109.5-10 9.5-10 9.5-10 9.5-10Sampling Date 05/18/18 05/18/1805/18/18 05/18/18 05/18/18 05/18/18UnitsVOCs (TO-15)Acetone13 J 14 J 11 J 9.9 J 25<6.635 9.2 J220,0002,700,000Benzene8.72130313661775.4 120 1,6002-Butanone (Methyl Ethyl Ketone)1.3 J 1.6 J 1.6 J 1.4 J<0.441.5 J 1.8 J 1.3 J35,000440,000Carbon Disulfide5.9 J 121716327182 3.0 J4,90061,000Carbon Tetrachloride<0.372.44.14.3<0.37 <0.37 <0.371.31602,000Chloroform726928275446290 36041530Cyclohexane<0.49 <0.49 <0.49 <0.49 <0.496.98.5<0.4942,000530,0001,3-Dichlorobenzene2524171525283126NENEDichlorodifluoromethane (Freon 12)3.2 L-05 2.8 3.4 L-05 2.9<0.433.0 3.8 L-05 2.87008,8001,1-Dichloroethylene<0.31 <0.31<0.31 <0.31 <0.311.6<0.31 <0.311,4007,700Ethanol<6.77.1 J<6.7 <6.7 <6.7 <6.7 <6.7 <6.7NENEEthylbenzene7890110 12091160 170223704,9004-Ethyltoluene<0.604038402036508.4NENEHeptane133531345890110 7.82,80035,000Hexane3.2 J 16 J 10 J 11 J396888 5.7 J4,90061,000Isopropanol0.99 J 3.9 J 1.2 J<0.60 <0.60 <0.60 <0.60 <0.601,40018,000Propene (Propylene)2.3 J<0.34 <0.34 <0.34 <0.3412 J48<0.3421,000260,000Tetrachloroethene6.23.71213843.71.9<0.752803,500Toluene280 380 580 590 580 970 1,100 11035,000440,000Trichloroethene664252536.4708.06.114180Trichlorofluoromethane (Freon 11)3.2 J 2.2 J 6.25.2 2.2 J 2.9 J 4.2 J 2.2 JNENE1,2,4-Trimethylbenzene120 120 100 1004590120254205,3001,3,5-Trimethylbenzene282620201119266.54205,300Vinyl Acetate1.4 J 3.2 J<0.34 <0.34 <0.349.8 J 12 J 1.8 J1,40018,000m&p-Xylene300 320 410 420 320 550 640847008,800o-Xylene96110 140 14094160 190257008,800Notes:1) North Carolina Department of Environmental Quality (DEQ) Division of Waste Management (DWM) Residential Sub-slab and Exterior Soil Gas Screening Levels (SGSLs) (February 2018).2) North Carolina DEQ DWM Non-Residential SGSLs (February 2018).Bold indicates concentration exceeds DEQ Residential SGSLs (February 2018).Only compounds detected in at least one sample are shown.Compound concentrations reported to laboratory method detection limits.Analytical method is indicated in parentheses.J = Detected concentration is above the laboratory method detection limit, but below the laboratory reporting limit, resulting in a laboratory estimated concentration.L-05 = Laboratory fortified blank/laboratory control sample recovery is outside of control limits and is biased on the high side.µg/m3 = micrograms per cubic meter; ft bgs = feet below ground surface; NE = Not EstablishedBuilding Labels correspond to locations shown on Figure 4.µg/m3Residential Soil-Gas Screening Level (1)Non-Residential Soil-Gas Screening Level (2)Building CBuilding BBuilding AVMP-3/DUPLICATE9.5-1005/18/18S:\AAA‐Master Projects\Ram Realty ‐ RMR\RMR‐006 Tryon & Tremont Brownfields Assistance\Report\Tables\Table 2 South Tryon Commercial SV Table6/27/2018Table 3 (Page 1 of 1) Hart & Hickman, PC TITLE PROJECT SITE LOCATION MAP SOUTH TRYON COMMERICAL CHARLOTTE, NORTH CAROLINA DATE: JOB NO: REVISION NO: FIGURE: 06-04-2018 0 1RMR-006 SITE 0 2000 4000 APPROXIMATE SCALE IN FEET N U.S.G.S. QUADRANGLE MAP QUADRANGLE 7.5 MINUTE SERIES (TOPOGRAPHIC) CHARLOTTE EAST, NORTH CAROLINA, 1991 REVISION NO. 0 JOB NO. RMR-006 DATE: 7-2-18 FIGURE NO. 2 SOUTH TRYON COMMERCIAL CHARLOTTE, NORTH CAROLINA SITE AND SURROUNDING AREA MAP LEGEND SITE PROPERTY BOUNDARY LIMITS OF WEST TREMONT BROWNFIELDS AGREEMENT FORMER BUILDING FOOTPRINT APPROXIMATE LOCATION OF FORMER GASOLINE UNDERGROUND STORAGE TANK 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology MOTOR FRE I G H T S T A T I O N (1950-1950) S. TR Y O N S T R E E T FORMER B&B CONTRACTING COMPANY W. TREMON T A V E N U E DO GG E T T S TR E E T NOTES: 1.AERIAL IMAGERY OBTAINED FROM MECKLENBURG COUNTY GIS (2017). 2.HISTORICAL BUILDING FOOTPRINTS & HISTORICAL USES OBTAINED FROM AVAILABLE RESOURCES INCLUDING SANBORN FIRE INSURANCE MAPS, AERIAL PHOTOGRAPHY, & CITY DIRECTORY. 3.UST = UNDERGROUND STORAGE TANK FORMER RESTAURANT (1949-1959) FORMER FARM MACHINERY SALES & SERVICE (1959-1963) ELECTRICAL SUPPLY WAREHOUSE BUILDING C (1960-1990) FORMER B&B CONTRACTING COMPANY FORMER TERMINIX, INC. (1969-2014) EMCI LTD (2101 S. TRYON STREET) MULTI-TENANT COMMERCIAL (307-349 W. TREMONT AVENUE) GAS FIRED PRODUCTS (305 DOGGETT STREET) MULTI-TENANT COMMERCIAL (1926-2030 S. TRYON STREET) MULTI-TENANT COMMERCIAL (1927 S. TRYON STREET) FORMER AUTO REPAIR SHOP (1950-1963) APPROXIMATE LOCATION FORMER UST DISPENSER S:\AAA-Master Projects\Ram Realty - RMR\RMR-006 Tryon & Tremont Brownfields Assistance\Figures\Figures060418.dwg, FIG 2, 2/27/2019 3:01:03 PM,SVincent SB-2 SB-1 SB-3 VMP-3 VMP-2 VMP-1 SB-4 VMP-4 VMP-5 VMP-6 VMP-7 SB-5 SB-6 REVISION NO. 0 JOB NO. RMR-006 DATE: 2-11-19 FIGURE NO. 3 SOUTH TRYON COMMERCIAL CHARLOTTE, NORTH CAROLINA SAMPLE LOCATION MAP LEGEND SITE PROPERTY BOUNDARY LIMITS OF BROWNFIELDS AGREEMENT FORMER BUILDING FOOTPRINT PROPOSED BUILDING FOOTPRINT PROPOSED PARKING/ PLAZA AREA APPROXIMATE LOCATION OF FORMER GASOLINE UNDERGROUND STORAGE TANK SOIL BORING LOCATION SOIL VAPOR SAMPLE LOCATION MONITORING WELL LOCATION TEMPORARY MONITORING WELL LOCATION TEMPORARY MONITORING WELL/ SOIL BORING LOCATION 2923 South Tryon Street-Suite 100 Charlotte, North Carolina 28203 704-586-0007(p) 704-586-0373(f) License # C-1269 / #C-245 Geology MOTOR FRE I G H T S T A T I O N (1950-1950) S. TR Y O N S T R E E T FORMER B&B CONTRACTING COMPANY W.TREMONT A V E N U E DO GG E T T S TR E E T NOTES: 1. AERIAL IMAGERY OBTAINED FROM MECHLENBURG COUNTY GIS (2017). 2. SOIL SAMPLES COLLECTED ON 5/17/18 AND 5/18/18. 3. SOIL VAPOR SAMPLES COLLECTED ON 5/18/18. 4. TCE = TRICHLOROETHYLENE BZP = BENZO(A)PYRENE CF = CHLOROFORM PCE = TETRACHLOROETHYLENE μg/L = MICROGRAMS PER LITER μg/m³ = MICROGRAMS PER CUBIC METER mg/kg = MILLIGRAMS PER KILOGRAM NA = NOT ANALYZED 5. J FLAG INDICATES AN ESTIMATED CONCENTRATION BETWEEN THE LABORATORY REPORTING LIMIT AND THE METHOD DETECTION LIMIT. 6. NO COMPOUNDS DETECTED ABOVE SCREENING LEVELS IN SOIL SAMPLES SB-1, SB-2, SB-3, SB-4 AND SB-5. 7. HISTORICAL GROUNDWATER DATA ARE IDENTIFIED IN PURPLE. FORMER RESTAURANT (1949-1959) FORMER B&B CONTRACTING COMPANY FORMER TERMINIX, INC. (1969-2014) FORMER AUTO REPAIR SHOP (1950-1963) FORMER UST DISPENSER SOIL VAPOR VMP-2 TCE 42 μg/m³ CF 69 μg/m³ FORMER FARM MACHINERY SALES & SERVICE (1959-1963) ELECTRICAL SUPPLY WAREHOUSE BUILDING C (1960-1990) SAMPLE ID CONCENTRATIONSCONSTITUENTS SOIL VAPOR VMP-2 TCE 42 μg/m³ CF 69 μg/m³ SOIL VAPOR VMP-1 TCE 66 μg/m³ CF 72 μg/m³ SOIL VAPOR VMP-3 / DUPLICATE TCE 52/53 μg/m³ CF 28/27 μg/m³ SOIL VAPOR VMP-4 TCE 6.4 μg/m³ CF 54 μg/m³ SOIL VAPOR VMP-5 TCE 70 μg/m³ CF 46 μg/m³ SOIL VAPOR VMP-6 TCE 8.0 μg/m³ CF 290 μg/m³ SOIL VAPOR VMP-7 TCE 6.1 μg/m³ CF 360 μg/m³ SOIL SB-6 BZP 0.17J mg/kg GROUNDWATER DPT-08 (7/23/07) PCE <1.0 μg/L TCE 2.5 μg/L DIELDRIN 0.75 μg/LGROUNDWATER DPT-09 (7/24/07) PCE <1.0 μg/L TCE 14 μg/L DIELDRIN 0.15 μg/LGROUNDWATER MW-3 (8/9/07) PCE 1.6 μg/L TCE 11 μg/L DIELDRIN <0.050 μg/L GROUNDWATER DPT-02 (7/20/07) PCE <1.0 μg/L TCE 5.7 μg/L DIELDRIN NA GROUNDWATER DPT-07 (7/20/07) PCE <1.0 μg/L TCE <2.0 μg/L DIELDRIN NA GROUNDWATER MW-2 (8/9/07) PCE <1.0 μg/L TCE 3.0 μg/L DIELDRIN <0.050 BUILDING AB BUILDING C S:\AAA-Master Projects\Ram Realty - RMR\RMR-006 Tryon & Tremont Brownfields Assistance\Figures\Figures060418.dwg, FIG 3 ALT, 2/27/2019 3:00:42 PM,SVincent Appendix A Current Redevelopment Site Plan WE S T T R EM O N T A V E N U E SOUTH T R Y O N S T R E E T LODLODLODLODLODLODLODLODLODLODLODLODLODL O D LOD L O D LODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLOD LODLODLODLODLODLODLODLODLOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LO D LOD LODLODLODF IR E L A N E - NO PAR KING PROP. PATIO ± 1,000 SF T T10 5 8 24 7 4 5 7 PROP. PATIO ± 1,000 SF PROP. OUTDOOR AMENITY AREA ± 1,800 SF PROP. PARKING STRIPING PROP. 16' SETBACK FROM EX. B.O.C.LOADI N G Z ONE PROP. PARKING STRIPING (TYP) PROP. PARKING STRIPING (TYP)PROP. 45° PAVEMENT MARKINGS (TYP.)6'R7'R 1'R7'R2'R 4.5'R4.5'R4.5'R2'R 1'R 4.5'R4.5'R 4.5'R4.5'R 4. 5 ' R 5. 9 ' R 12'R 3 . 8 'R 5'R 5'R50'R 4. 5 ' R 9 8 9 PROP. RETAINING WALL W/ SAFETY RAIL LIMITS OF NEW CURB LIMITS OF NEW CURB PROP. 30" C&G CONTRACTOR TO SAWCUT EDGE OF EX. PAVEMENT FOR SMOOTH TRANSITION LIMITS OF NEW CURB PROP. 3 CY RECYCLE PROP. MARATHON RJ-250SC 30 CY TRASH COMPACTOR LIMITS OF NEW CURB LIMITS OF NEW CURB LIMITS OF NEW CURB PROP. BOLLARD MOUNTED ACCESSIBLE PARKING SIGN (TYP.) PROP. STOP SIGN & STOP BAR (TYP.) PROP. BOLLARD MOUNTED ACCESSIBLE PARKING SIGN (TYP.) PROP. BOLLARD MOUNTED ACCESSIBLE PARKING SIGN (TYP.) PROP. INVERTED U BIKE RACK (2). REFER TO DETAIL PROP. CURB TO MATCH EX. AT DRIVEWAY LOCATION (TYP.) PROP. INVERTED U BIKE RACK (2). REFER TO DETAIL LIMITS OF NEW CURB PROP. SAWCUT LINE (TYP.) PROP. SAWCUT LINE (TYP.) PROP. SAWCUT LINE (TYP.) PROP. SAWCUT LINE (TYP.)BUILDING A/B 17,375 SF GROSS (1 STORY) FFE1= 731.63 PROP. RETAINING WALL W/ SAFETY RAIL BUILDING C 14,605 SF GROSS /FLOOR (3 STORY) FFE = 730.4 3 1'R PROP. PLAZA AREA HARDSCAPE TO BE SPECIFIED AT A LATER DATE PROP. 9' CURB TRANSITION TO FLUSH PROP. 9' CURB TRANSITION TO FLUSH PROP. INVERTED U BIKE RACK (2). REFER TO DETAIL PROP. STEPS PROP. ADA RAMP (TYP.) PROP. BOARD ON BOARD FENCE TO SCREEN TRASH/RECYCLE PROP. FIRST FLOOR COVERED PATIO. REF. ARCH.PROP. 16' SETBACK FROM EX. B.O.C. P R O P . 1 6 ' S E T B A C K F R O M F U T U R E B. O . C . P E R R E Z O N I N G P L A N 2 0 0 7 - 1 2 4 PROP. FUTURE BACK OF CURB LINE PER REZONING PLAN 16'PROP. 8' SW EASEMENT PROP. 16' SETBACK FROM EX. B. O . C . PROP. INVERTED U BIKE RACK (2). REFER TO DETAIL PROP. BENCH REFER TO NCDOT TRAFFIC CONTROL PLANS FOR WORK IN NCDOT ROW PROP. BUILDING MOUNTED FDC PROP. BUILDING MOUNTED FDC PROP. BUILDING MOUNTED FDC 17 '24'17'24'9' 8' 9' 17 '9'17'8'8' 9'6.3'10'10 '25'9'9' 9' 1 6 ' 8. 5 '8.5'8.5'8.5' PROP. PLANTING STRIP8.3'10'8.5'6'5.2'9'3.5'9' 5. 5 ' 5' 5. 4 ' 8'9.8'18.5'18.5'24 '17'8' 8'8'8'5' 8' WIDT H V ARI ES 8' PROP. SW5.3'6'2' FFE2 = 734.30OHOHOHOHOHOHOHOHOHOH T 50' X 50' SIGHT DISTANCE TRIANGLE 50' X 50' SIGHT DISTANCE TRIANGLE 10'X10' CITY OF CHARLOTTE PEDESTRIAN SIGHT TRIANGLE 10'X10' CITY OF CHARLOTTE PEDESTRIAN SIGHT TRIANGLE OBJ REVISIONS REV DATE COMMENT BY LOCATION OF SITE FOR PROJECT No.: DRAWN BY: CHECKED BY: DATE: SCALE: CAD I.D.: SHEET NUMBER: SHEET TITLE: PROJECT: H:\2017\NCC172144\DRAWINGS\PLAN SETS\CONSTRUCTION DOCUMENTS\NCC172144SS0.DWG PRINTED BY: DRENCKENS 2.18.19 @ 4:43 PM LAST SAVED BY: DRENCKENS NCC172144 DR/RB RH 02/18/2019 CONSTRUCTION DOCUMENTS 335 TREMONT MIXED USE BUILDING A/B: 340 W TREMONT AVE. BUILDING C: 330 W TREMONT AVE. PID: 121-033-02 KNOW WHAT'S BELOW ALWAYS CALL 811 BEFORE YOU DIG It's fast. It's free. It's the law. TM 1927 S. TRYON STREET, SUITE 310 CHARLOTTE, NC 28203 Phone:(980) 272-3400 Fax:(980) 272-3401 NC@BohlerEng.com NCBELS P-1132TM THE INFORMATION, DESIGN AND CONTENT OF THIS PLAN ARE PROPRIETARY AND SHALL NOT BE COPIED OR USED FOR ANY PURPOSE WITHOUT PRIOR WRITTEN AUTHORIZATIONFROM BOHLER ENGINEERING. ONLY APPROVED, SIGNED AND SEALED PLANS SHALL BE UTILIZED FOR CONSTRUCTION PURPOSES©NEW ENGLANDUPSTATE NEW YORKNEW YORK, NYPHILADELPHIA, PALEHIGH VALLEY, PABALTIMORE, MDREHOBOTH BEACH, DEWASHINGTON, DCNORTHERN VIRGINIARALEIGH, NCCENTRAL VIRGINIASOUTHERN MARYLANDNORTHERN NEW JERSEYSOUTHEASTERN, PACHARLOTTE, NCBOSTON, MASOUTHERN NEW JERSEYNEW YORK METROTAMPA, FLSOUTH FLORIDADALLAS, TXATLANTA, GAPITTSBURGH, PATMSUSTAINABLE DESIGNLANDSCAPE ARCHITECTURESITE CIVIL AND CONSULTING ENGINEERINGLAND SURVEYINGPROGRAM MANAGEMENTPERMITTING SERVICESTRANSPORTATION SERVICES2017 BOHLER ENGINEERING039258 RA D D. H U D S O NSEAL ENGI NE E RPROFESSIO N ALNO R T H CAROLI NA02/18/19 1"=20' 0 2051020 5.ZONING ORDINANCE PROVISIONS REQUIRED PROPOSED A.)SETBACKS/BUFFERS/STRIP:BUILDING BUFFER BUILDING BUFFER FRONT (TRYON) -16 FT FROM BOC N/A 16 FT N/A SIDE (W TREMONT) - 16 FT (SEE N/A 16 FT N/A APPROVED REZONING DOCUMENTS) REQUIRED/ALLOWED PROPOSED B.)MAXIMUM BUILDING HEIGHT: 40 FT W/ INCREASED 1' PER 10' SETBACK C.)PARKING REQUIRED: 70 SPACES15,000 GROSS SF OF EATING, DRINKING, AND +30 SPACES SHARED BETWEEN ENTERTAINMENT ESTABLISHMENT ADJACENT MULTIFAMILY (EXTRA SPACES AVAILABLE) 1 SPACE / 150 S.F. * 15,000 SF = 100 SPACES TOTAL: 100 SPACES 29,210 GROSS SF OF OFFICE SPACE 0 SPACES MAX 1 SPACE / 300 SF, MINIMUM = 0 ADJACENT SITE PARKING INFORMATION: 164 UNITS 268 SPACES MINIMUM = 0, MAXIMUM = 1.6/UNIT = 263 SURFACE PARK = 80 SPACES, GARAGE = 188 SPACES D.)BIKE PARKING REQUIRED: LONG TERM: 1/10,000 SF, MIN OF 2 4 SPACES (LOCATED IN THREE30FIVE PARKING DECK) 31250/10,000 = 4 SPACESSHORT TERM: 5% OF AUTO PARKING 12 SPACES (LOCATED IN THREE30FIVE PARKING DECK) 209 SPACES X 5% = 11 SPACES HANDICAP PARKING REQUIRED: HANDICAP - 76-100 SPACES 4 TOTAL SPACES 5 SPACES VAN ACCESSIBLE 1 SPACE 2 SPACES STANDARD DIMENSION 8.5 FT x 18.5 FT 24 SPACESSTANDARD DIMENSION 9.0 FT x 17.0 FT 40 SPACES ACCESSIBLE DIMENSION 8.0 FT x 17.0 FT 6 SPACES SHARED PARKING VARIES 30 SPACES E.)OPEN SPACE: : PUBLIC OPEN SPACE= 1SF/100 GFA OR 104,238 GFA / 100 SF = 1043 SF 1SF/200 SF LOT AREA, WHICHEVER IS GREATER 3,076 SF PROVIDED 6.FLOOR AREA (F.A.R.) REQUIREMENT BUILDING A:8,168 S.F.0.50 MINIMUM BUILDING B: 8,514 S.F. BUILDING C:43,698 S.F. TOTAL SITE AREA:104,238 S.F TOTAL F.A.R.:±0.58 GENERAL NOTES 1. DEVELOPER/APPLICANT: RAM REALTY ADVISORS CONTACT: ASHLEY SAULPAUGHEMAIL:ASAULPAUGH@RAMREALESTATE.COM PHONE:(704) 377-6730 2. THIS PLAN IS BASED UPON THE FOLLOWING: THE JOHN R. MCADAMS COMPANY, INC. "2001 SOUTH TRYON" PROJECT #: SURS-16203 DATED:04/15/2016 3. EX. SITE INFORMATION OWNER:2001 SOUTH TRYON LLC ADDRESS:2035 SOUTH TRYON STREET CHARLOTTE, NC 28203 PARCEL NUMBER:121103302 AND 12103301 D.B. 27409 P.N. 714 GROSS AREA: ±2.39 ACRES ZONING: TOD-M 4.EXISTING USE: VACANT PROPOSED USE: MIXED USE PERMITTED LAND USE: YES 1" = 20' SS0 C-302 SITE PLAN 1.NON-STANDARD ITEMS(IE: PAVERS,IRRIGATION SYSTEMS,ETC.) IN THE RIGHT-OF-WAY REQUIRE A RIGHT-OF-WAY ENCROACHMENT AGREEMENT WITH THE CHARLOTTE DEPARTMENT OF TRANSPORTATION/ NORTH CAROLINA DEPARTMENT OF TRANSPORTATION BEFORE INSTALLATION. FOR CITY OF CHARLOTTE MAINTAINED STREETS, CONTACT CDOT AT (704)336-3888. 2.ANY WORK WITHIN THE CITY'S R/W THAT REQUIRES CLOSURE OF A SIDEWALK OR TRAVEL LANE MUST BE APPROVED BY CDOT AND WILL REQUIRE A R/W USE PERMIT OR R/W LEASE DEPENDING UPON THE PROPOSED DURATION OF CLOSURE. THESE APPROVALS ARE IN ADDITION TO SITE APPROVALS AND SHOULD BE COORDINATED WITH CDOT PRIOR TO CONSTRUCTION. CONTRACTOR SHALL CONTACT CDOT AT (704) 432-1562 AT LEAST 5 BUSINESS DAYS PRIOR TO BEGINNING WORK FOR IMPACTS LESS THAT 30 DAYS. CONTRACTOR SHALL CONTACT CDOT AT (704) 336-8648 AS SOON AS POSSIBLE FOR IMPACTS GREATER THEN 30 DAYS. EVERY EFFORT SHALL BE MADE TO CONSTRUCT IMPROVEMENTS WITH MINIMAL IMPACT TO DRIVERS AND PEDESTRIANS. CITY OF CHARLOTTE NOTES: Appendix B Grading Plan and Cut-Fill Analysis SSSSSSSSS S SSSSSSSSSSSSSSSLSLSSSSSS S S S S S S S S SSWE S T T R EM O N T A V E N U E SOUTH T R Y O N S T R E E T LODLODLODLODLODLODLODLODLODLODLODLODLODL O D LOD L O D LODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLOD LODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLODLOD LODLODLODLODLODLODLODLODLOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LO D LOD LODLODLODRIDGET TW W WWW W WWWWWWWWWW W W W W W W W W W FFFFFFFFFPROP. SAWCUT LINE (TYP.) PROP. SAWCUT LINE (TYP.) PROP. SAWCUT LINE (TYP.) PROP. SAWCUT LINE (TYP.)BUILDING A/B 17,375 SF GROSS (1 STORY) FFE1= 731.63 BUILDING C 14,605 SF GROSS /FLOOR (3 STORY) FFE = 730.4 PROP. EXPOSED FOUNDATION PROP. BURIED FOUNDATION PROP. EXPOSED FOUNDATION PROP. EXPOSED FOUNDATION W PROP. EXPOSED FOUNDATION PROP. 8' SW EASEMENT TRANSITION FROM EXPOSED TO BURIED FOUNDATION FFE2 = 734.30 PROP. INTERNAL BUILDING STEPPROP. BURIED FOUNDATION T 727 73 0 73373072973173273573173273373472 8 729730 730727 728 729729 729730 730 731 732 733 73 4 7 3 1 7 3 2 7 3 5 733734730 729 STM B6 STM B1STM B2 STM B3 STM B4 STM A4 STM A2 STM A3 STM B5 STM C4 7 3 1 728729 730 729728727726 72 7 729 728RD1 RD3RD5 RD6 RD4 BLD-B CO1 CO2 BLD-A CO4 BLD-C 730STM C1 725724726729G 731.57 G 733.85 FF= 731.63 G 727.55 G 730.03 BW 732.84 TW 731.16 BW 729.84 TW 730.58 BW 726.77 FF= 730.40 FF= 731.63 G 735.31 FF= 730.40 TW 730.40 TW=BW 726.91 BW 727.39 TW 730.25 FF= 734.30 FF= 734.30 BW 728.10 TW 731.52 TW=BW 723.88 TW 726.91 BW 724.15 TW 729.90 BW 727.33 TW 729.90 G 723.97 FF= 730.40 TC 732.53 TC 731.94 TC 731.28 TC 731.43 TC 734.16 G 733.76 TC 733.60 TC 733.28 TC 731.01 TC 730.35 G 730.2+/- MATCH EX. TC 732.31 TC 732.69 TC 732.80 TC 732.20 TC 730.72 TC 730.30 TC 730.07 LP - RIM 729.01 TC 730.30 TC 730.30 HP - TC 730.62 TC 730.34 TC 730.05 TC 730.30 TC 729.85 TC 729.66 TC 729.62 TC 729.47 LP - RIM 727.91 TC 728.84 TC 728.86 LP - RIM 728.20 TC 730.40 TC 730.12 TC 730.09 TC 730.62 TC 730.00 TC 730.35 TC 729.89 TC 730.05 TC 729.95 TC 732.95 TC 732.96 TC 731.99 TC 731.98 TC 729.61 TC 727.00 TC 726.51 G 725.0+/- MATCH EX. G 727.0+/- MATCH EX. G 728.51 G 728.65G 728.80 G 729.09 G 729.09 G 729.09 G 733.91 G 728.49 G 728.39 G 729.35 G 729.35 G 734.16 TC 729.07 TC 728.97 G 729.13 G 728.86 TC 729.17 TC 729.85 TC 728.78 G 729.85 G 729.85 G 727.34 G 727.37G 729.96 G 730.14 G 726.99 G 730.24 G 730.24 TC 723.15 TC 724.09 TC 725.45 TC 726.06G 725.89 G 726.15 FF= 730.40 G 729.89 G 729.67 G 729.24 G 732.27 G 732.65 G 735.08 G 727.98 G 730.22 G 730.14 G 725.79 G 725.67 G 724.3+/- MATCH EX. G 724.64 G 724.6+/- MATCH EX. TC 726.2+/- MATCH EX. G 724.1+/- MATCH EX. TC 731.17 G 735.0+/- MATCH EX. G 730.25 TC 731.30 TC 725.65 TC 723.85 G 731.48 G 729.59 G 729.22 G 727.39 G 733.73 G 733.56 G 735.21 G 735.8+/- MATCH EX. G 735.6+/- MATCH EX. G 734.20 G 734.16 TC 734.23 FF= 730.40 G 727.42 G 726.82 FF= 731.63 FF= 731.63 G 733.88 G 731.57 FF= 731.63 FF= 731.63 FF= 731.63 FF= 731.63 BW 724.49 G 726.54 FF= 734.30 FF= 734.30 FF= 734.30 TC 734.16 FF= 734.30 G 735.10 FF= 730.40 FF= 730.40 FF= 730.40 TW 726.61 FF= 730.40G 731.53 G 731.53 TW 730.16 TW 730.19 BW 728.96 TW=BW 729.07 G 729.41 G 728.05 G 727.8+/- MATCH EX. G 726.7+/- MATCH EX. TW 726.15 TC 729.85 TC 730.22 BW 725.16 G 723.41 G 723.25 G 722.98 G 722.87 TC 723.31 TC 723.54 G 724.88 G 724.59 G 725.2+/- MATCH EX. G 725.3+/- MATCH EX. G 726.13 FF= 734.30 BW 727.39 BW 724.01 TW 727.39 G 723.55 TW 730.25BW 723.59 TW 727.39 G 734.21 FF= 734.30 G 728.49 G 726.88 G 727.26 G 727.14 G 726.92 G 726.89 G 726.60 G 726.68 G 726.85 G 724.84 TW=BW 729.71 FF= 730.40 G 728.18 FF= 730.40 G 729.42 G 726.69 G 726.93 G 727.06 G 727.08 G 727.23 G 726.6+/- MATCH EX. G 726.4+/- MATCH EX. G 726.2+/- MATCH EX. G 726.3+/- MATCH EX. FF= 734.30 TW 734.24 BW 734.09 G 724.79 G 724.65 TW 730.25 BW 723.59 BW 723.61 BW 723.78 TW 727.39 TC 727.01 G 725.41 G 725.41 G 725.90 G 725.86 G 729.42 G 729.52 G 729.52 G 726.40 G 731.51 G 730.51 TC 729.40 G 730.32 G 729.56 G 729.08 TW 729.98 TW 730.33 TW 729.98 BW 727.51 BW 728.21 BW 728.21 G 728.18 FF= 730.40 G 730.34 TW 730.34 BW 726.69 BW 726.06 G 726.08 G 726.64 TW=BW 730.33 TW=BW 729.98 TW=BW 728.15 G 730.15 G 731.00 G 729.87 G 727.84G 727.51 G 727.60 TC 731.08 TC 730.28 TC 730.39 TC 728.13 TC 732.00 TC 733.06 TC 734.13 G 727.95 G 728.08 G 731.51 G 731.57 G 731.53 FF= 734.30 FF= 734.30 FF= 734.30 FF= 734.30 FF= 731.63 G 729.23 G 729.01 G 731.32 G 734.21 FF= 734.30 FF= 731.63 TW 734.00 BW 732.72 G 731.31 G 730.38 G 730.85 BW 726.96 TW 729.90 TW 729.98 BW 727.03 FF= 730.40 FF= 730.40 G 730.18 G 730.20 G 728.96 G 728.03 G 728.16 FF= 730.40FF= 730.40FF= 730.40FF= 730.40 FF= 730.40 FF= 730.40 G 727.21 G 726.84 G 726.19 G 726.92 G 726.31 G 723.9+/- MATCH EX. G 724.77 G 724.35 G 724.33 G 724.9+/- MATCH EX. REVISIONS REV DATE COMMENT BY LOCATION OF SITE FOR PROJECT No.: DRAWN BY: CHECKED BY: DATE: SCALE: CAD I.D.: SHEET NUMBER: SHEET TITLE: PROJECT: H:\2017\NCC172144\DRAWINGS\PLAN SETS\CONSTRUCTION DOCUMENTS\NCC172144SS0.DWG PRINTED BY: DRENCKENS 2.18.19 @ 4:44 PM LAST SAVED BY: DRENCKENS NCC172144 DR/RB RH 02/18/2019 CONSTRUCTION DOCUMENTS 335 TREMONT MIXED USE BUILDING A/B: 340 W TREMONT AVE. BUILDING C: 330 W TREMONT AVE. PID: 121-033-02 KNOW WHAT'S BELOW ALWAYS CALL 811 BEFORE YOU DIG It's fast. It's free. It's the law. TM 1927 S. TRYON STREET, SUITE 310 CHARLOTTE, NC 28203 Phone:(980) 272-3400 Fax:(980) 272-3401 NC@BohlerEng.com NCBELS P-1132TM THE INFORMATION, DESIGN AND CONTENT OF THIS PLAN ARE PROPRIETARY AND SHALL NOT BE COPIED OR USED FOR ANY PURPOSE WITHOUT PRIOR WRITTEN AUTHORIZATIONFROM BOHLER ENGINEERING. ONLY APPROVED, SIGNED AND SEALED PLANS SHALL BE UTILIZED FOR CONSTRUCTION PURPOSES©NEW ENGLANDUPSTATE NEW YORKNEW YORK, NYPHILADELPHIA, PALEHIGH VALLEY, PABALTIMORE, MDREHOBOTH BEACH, DEWASHINGTON, DCNORTHERN VIRGINIARALEIGH, NCCENTRAL VIRGINIASOUTHERN MARYLANDNORTHERN NEW JERSEYSOUTHEASTERN, PACHARLOTTE, NCBOSTON, MASOUTHERN NEW JERSEYNEW YORK METROTAMPA, FLSOUTH FLORIDADALLAS, TXATLANTA, GAPITTSBURGH, PATMSUSTAINABLE DESIGNLANDSCAPE ARCHITECTURESITE CIVIL AND CONSULTING ENGINEERINGLAND SURVEYINGPROGRAM MANAGEMENTPERMITTING SERVICESTRANSPORTATION SERVICES2017 BOHLER ENGINEERING039258 RA D D. H U D S O NSEAL ENGI NE E RPROFESSIO N ALNO R T H CAROLI NA02/18/19 1" = 20' SS0 C-401 GRADING PLAN 1"=20' 0 2051020 GRADING NOTES: 1.CONTRACTOR IS RESPONSIBLE FOR DEMOLITION OF EXISTING STRUCTURES INCLUDING REMOVAL OF ANY EXISTING UTILITIES. UTILITIES ARE TO BE REMOVED TO THE RIGHT-OF-WAY. 2.THE CONTRACTOR IS SPECIFICALLY CAUTIONED THAT THE LOCATION AND/OR ELEVATION OF EXISTING UTILITIES AS SHOWN ON THESE PLANS IS BASED ON RECORDS OF THE VARIOUS UTILITY COMPANIES, AND WHERE POSSIBLE, MEASUREMENTS TAKEN IN THE FIELD. THE INFORMATION IS NOT TO BE RELIED ON AS BEING EXACT OR COMPLETE. THE CONTRACTOR MUST CALL THE APPROPRIATE UTILITY COMPANIES AT LEAST 72 HOURS BEFORE ANY EXCAVATION TO REQUEST EXACT FIELD LOCATION OF UTILITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO RELOCATE ALL EXISTING UTILITIES WHICH CONFLICT WITH THE PROPOSED IMPROVEMENTS SHOWN ON THE PLANS. 3. ALL CUT OR FILL SLOPES SHALL BE 3:1 OR FLATTER UNLESS OTHERWISE NOTED. 4.PRECAST STRUCTURES MAY BE USED AT CONTRACTORS OPTION. 5.CLASS III RCP (ASTM C76) SHALL BE CONSTRUCTED WITH RUBBER O-RING GASKETS. 6.EXISTING PIPES TO BE CLEANED OUT TO REMOVE ALL SILT AND DEBRIS. 7.EXISTING GRADE CONTOUR INTERVALS SHOWN AT 1'. 8.PROPOSED GRADE CONTOUR INTERVALS SHOWN AT 1' INTERVALS. 9. IF ANY EXISTING STRUCTURES TO REMAIN ARE DAMAGED DURING CONSTRUCTION IT SHALL BE THE CONTRACTORS RESPONSIBILITY TO REPAIR AND/OR REPLACE THE EXISTING STRUCTURE AS NECESSARY TO RETURN IT TO EXISTING CONDITIONS OR BETTER. 10.ALL STORM PIPE ENTERING STRUCTURES SHALL BE GROUTED TO ASSURE CONNECTION AT STRUCTURE IS WATERTIGHT. 11. ALL STORM SEWER MANHOLES IN PAVED AREAS SHALL BE FLUSH WITH PAVEMENT, AND SHALL HAVE TRAFFIC BEARING RING & COVERS. MANHOLES IN UNPAVED AREAS SHALL BE 6" ABOVE FINISH GRADE. LIDS SHALL BE LABELED "STORM SEWER". 12.THE CONTRACTOR SHALL ADHERE TO ALL TERMS & CONDITIONS AS OUTLINED IN THE EPA OR APPLICABLE STATE GENERAL N.P.D.E.S. PERMIT FOR STORM WATER DISCHARGE ASSOCIATED WITH CONSTRUCTION ACTIVITIES AND THE SPECIAL CONDITIONS, SECTION 8, ENVIRONMENTAL COMPLIANCE AND STORM WATER POLLUTION PREVENTION. 13. CONTRACTOR SHALL ADJUST AND/OR CUT EXISTING PAVEMENT AS NECESSARY TO ASSURE A SMOOTH FIT AND CONTINUOUS GRADE. 14.CONTRACTOR SHALL ASSURE POSITIVE DRAINAGE AWAY FROM BUILDINGS FOR ALL NATURAL AND PAVED AREAS. 15.TOPOGRAPHIC INFORMATION IS TAKEN FROM A TOPOGRAPHIC SURVEY BY LAND SURVEYORS. IF THE CONTRACTOR DOES NOT ACCEPT EXISTING TOPOGRAPHY AS SHOWN ON THE PLANS, WITHOUT EXCEPTION, THEN THE CONTRACTOR SHALL SUPPLY, AT THEIR EXPENSE, A TOPOGRAPHIC SURVEY BY A REGISTERED LAND SURVEYOR TO THE OWNER FOR REVIEW. 16.ALL UNSURFACED AREAS DISTURBED BY GRADING OPERATION SHALL RECEIVE 4 INCHES OF TOPSOIL. CONTRACTOR SHALL APPLY STABILIZATION FABRIC TO ALL SLOPES 3H:1V OR STEEPER. CONTRACTOR SHALL STABILIZE DISTURBED AREAS IN ACCORDANCE WITH GOVERNING SPECIFICATIONS UNTIL A HEALTHY STAND OF VEGETATION IS OBTAINED. 17.CONSTRUCTION SHALL COMPLY WITH ALL APPLICABLE GOVERNING CODE AND BE CONSTRUCTED TO SAME. 18.ALL STORM STRUCTURES SHALL HAVE A SMOOTH UNIFORM POURED MORTAR INVERT FROM INVERT IN TO INVERT OUT. 19. CONTRACTOR TO ADJUST ANY EXISTING STRUCTURES TO PROPOSED GRADE IN ANY AREA OF PROPOSED GRADING. 20.ALL REINFORCED CONCRETE PIPES ARE TO BE CLASS III UNLESS INDICATED OTHERWISE. 21.ALL ROOF DRAINAGE SHALL BE TIED TO UNDERGROUND PIPING. REFER TO ARCH. PLANS FOR ADDITIONAL INVERT INFORMATION. 22.FOR CROSSING INFORMATION, SEE UTILITY PLAN. 23.ALL NEW CURB SHALL BE INSTALLED WITH A SLOPE TO MATCH ADJACENT PAVEMENT GRADE.LP - RIM XX TC - XX.XX WALL ELEVATION LEGEND GRADE RETAINING WALL. SEE DESIGN BY OTHERS FOR TOP OF WALL AND FOOTING ELEVATIONS GRADE NOTES: 1.THE GRADES SHOWN ON GRADING PLAN REFER TO FINISHED GROUND GRADES AT THE TOP AND BOTTOM OF WALL. 2.GC IS TO REVIEW RETAINING WALL PLANS VS CIVIL GRADING PLAN AND NOTIFY THE ENGINEER OF RECORD IF THERE ARE ANY QUESTIONS PRIOR TO CONSTRUCTING THE WALL AND PERFORMING EARTHWORK OPERATIONS. TW - XX.XX BW - XX.XX CURB ELEVATION LEGEND Job: Updated 2-18-19 Units: Ft-CY Mon Feb 18, 2019 18:07:50 Page 1 Volume Report Subgrade vs. Stripped Area Volume Comp/Ratio Compact Export Change Total Cut Fill OnGrade Cut Fill Cut Fill Cut Fill -Import Per .1 Ft Landscape 16,625 1,154 14,783 688 57 522 1.00 1.15 57 600 -543 71 LD Asphalt 22,491 16,579 5,150 762 676 145 1.00 1.15 676 167 509 96 LD Asphalt 439 264 6 169 2 0 1.00 1.15 2 0 2 2 LD Sub: 22,930 16,843 5,156 931 678 145 678 167 511 98 Pad AB 17,336 1,001 15,414 921 14 782 1.00 1.15 14 899 -885 74 Pad C 13,774 9,633 3,784 357 568 322 1.00 1.15 568 370 198 59 Pad Sub: 31,110 10,634 19,198 1,278 582 1,104 582 1,269 -687 133 Patio 1,165 13 1,150 2 0 166 1.00 1.15 0 191 -191 5 Paving Islands 284 0 279 5 0 6 1.00 1.15 0 7 -7 1 Paving Islands 362 362 0 0 6 0 1.00 1.15 6 0 6 2 Paving Islands 402 402 0 0 32 0 1.00 1.15 32 0 32 2 Paving Islands 107 65 38 4 2 3 1.00 1.15 2 3 -1 0 Paving Sub: 1,155 829 317 9 40 9 40 10 30 5 Sidewalks 14,529 9,385 3,301 1,843 462 115 1.00 1.15 462 132 330 62 Sidewalks 12,154 31 11,883 240 0 567 1.00 1.15 0 652 -652 52 Sidewalks Sub: 26,683 9,416 15,184 2,083 462 682 462 784 -322 114 Regions Total 99,668 38,889 55,788 4,991 1,819 2,628 1,819 3,021 -1,202 426 Plane Slope Stripping Qtys Area Area Depth Volume Topsoil 99,668 100,056 0.500 1,853 Plane Slope Sectional Qtys Area Area Depth Volume LD Asphalt 22,491 22,520 0.670 559 LD Asphalt 439 440 0.670 11 LD Sub: 22,930 22,960 570 Pad AB 17,336 17,344 0.840 540 Pad C 13,774 13,776 0.840 429 Pad Sub: 31,110 31,120 969 Patio 1,165 1,176 0.330 14 Paving Islands 402 430 0.000 0 Paving Islands 107 112 0.000 0 Paving Islands 284 284 0.000 0 Paving Islands 362 362 0.000 0 Paving Sub: 1,155 1,188 0 Sidewalks 14,529 14,598 0.330 178 Sidewalks 12,154 12,206 0.330 149 Sidewalks Sub: 26,683 26,804 327 Sectional Total 83,043 83,248 1,880 SUMMARY: Disturbed Area = 2.29 AC Topsoil @ 6" = 1,853 CY Cut/Fill = 1,819 CY Import = 1,202 CY 0 17.5 35Tremont Mixed UseCut/Fill Map Appendix C Construction Schedule ID Task NameDuration Start Finish Resource Names% Complete1PRECONSTRUCTION125 daysTue 11/13/18Mon 5/6/1924%2Design Kickoff74 daysTue 11/13/18Fri 2/22/199%3Design Kickoff Meeting1 dayTue 11/13/18Tue 11/13/18RAM100%4Internal Design Charrette for Envelope Development1 dayTue 12/4/18Tue 12/4/18BB&M100%5Preliminary Review with Mecklenburg County31 daysFri 1/11/19Fri 2/22/19BB&M3%6Schematic Design42 daysFri 11/16/18Mon 1/14/19100%7Begin SD 1 dayFri 11/16/18Fri 11/16/18BB&M100%8SD Complete0 daysThu 12/20/18Thu 12/20/18BB&M100%9SD Pricing 17 daysFri 12/21/18Mon 1/14/19Choate100%10SD Budget Update to RAM0 daysMon 1/14/19Mon 1/14/19Choate100%25Design Development 63 daysFri 12/21/18Tue 3/19/1951%26Begin DD1 dayFri 12/21/18Fri 12/21/18BB&M100%27DD Check Set1 dayFri 1/11/19Fri 1/11/19BB&M100%28Return DD Check Set w/ Comments1 dayFri 1/18/19Fri 1/18/19Choate100%29DD Complete5 daysMon 2/4/19Fri 2/8/19BB&M100%30Update Pricing for DD Dwgs15 daysMon 2/11/19Fri 3/1/19Choate80%32Upload Dwgs and Fees Paid for Express Review1 dayMon 2/18/19Mon 2/18/19BB&M100%33Express Review for Footings/Foundations/Frame Permit0 daysWed 2/20/19Wed 2/20/19BB&M100%34Footing/Foundation/Frame Permit Review3 daysWed 2/20/19Fri 2/22/19Meck Cty100%36Combine Parcels - PLAT Recorded15 daysMon 2/25/19Fri 3/15/19Bohler5%31DD Budget Update to RAM (Incl. Final Pricing for FF & Frame)0 daysFri 3/1/19Fri 3/1/19Choate0%35Footing/Foundation/Frame Pricing Review5 daysMon 3/4/19Fri 3/8/19RAM0%38Notice to Proceed - Ftg/Fnd/Frame Package0 daysFri 3/8/19Fri 3/8/19RAM0%37Footing/Foundation/Frame Permit Processing and Issuance2 daysMon 3/18/19Tue 3/19/19Meck Cty0%39Construction Drawings Design58 daysMon 2/11/19Wed 5/1/1916%40CD's Begin20 daysMon 2/11/19Fri 3/8/19BB&M60%41CD Check Set1 dayMon 3/11/19Mon 3/11/19BB&M0%42Return CD Check Set w/ Comments1 dayMon 3/18/19Mon 3/18/19Choate0%43100% CD/Full Bldg Permit Construction Set Due9 daysTue 3/19/19Fri 3/29/19BB&M0%44Update Pricing for CD Dwgs15 daysMon 4/1/19Fri 4/19/19Choate0%45Upload Dwgs for Full Bldg Permit0 daysMon 4/1/19Mon 4/1/19BB&M0%46Permit Review and Approval22 daysTue 4/2/19Wed 5/1/19Meck Cty0%47CD/GMP Final Pricing to RAM0 daysFri 4/19/19Fri 4/19/19Choate0%48GMP Pricing Approval5 daysMon 4/22/19Fri 4/26/19RAM0%49Notice to Proceed - Full GMP0 daysFri 4/26/19Fri 4/26/19RAM0%11Site/Civil Design21 daysFri 2/15/19Fri 3/15/1932%13Site Plan Pricing10 daysFri 2/15/19Thu 2/28/19Choate100%12Original Site Plan Approval0 daysFri 2/22/19Fri 2/22/19Bohler100%17Updated Brownfield Agreement Based on New Site Plan15 daysMon 2/25/19Fri 3/15/190%14Sitework Pricing to RAM1 dayFri 3/1/19Fri 3/1/19Choate0%15Sitework Pricing Approval5 daysMon 3/4/19Fri 3/8/19RAM0%16Notice to Proceed - Sitework Scope0 daysFri 3/8/19Fri 3/8/19RAM0%18Subcontractor Awards/Submittals/Procurement41 daysMon 3/11/19Mon 5/6/190%19Sitework Award1 dayMon 3/11/19Mon 3/11/190%21Steel Contractor Award1 dayMon 3/11/19Mon 3/11/190%23Concrete/Masonry Award1 dayMon 3/11/19Mon 3/11/190%20Site Submittals and Approval9 daysTue 3/12/19Fri 3/22/190%PRECONSTRUCTIONDesign KickoffInternal Design Charrette for Envelope DevelopmentPreliminary Review with Mecklenburg CountyDesign Development Return DD Check Set w/ CommentsDD CompleteUpdate Pricing for DD DwgsUpload Dwgs and Fees Paid for Express Review2/20Footing/Foundation/Frame Permit ReviewCombine Parcels - PLAT Recorded3/13/4Footing/Foundation/Frame Pricing Review3/83/18Footing/Foundation/Frame Permit Processing and IssuanceConstruction Drawings DesignCD's Begin3/11CD Check Set3/18Return CD Check Set w/ Comments3/19100% CD/Full Bldg Permit Construction Set Due4/1Update Pricing for CD Dwgs4/14/2Permit Review and Approval4/194/22GMP Pricing Approval4/26Site/Civil DesignSite Plan Pricing2/22Updated Brownfield Agreement Based on New Site Plan3/1Sitework Pricing to RAM3/4Sitework Pricing Approval3/83/11Subcontractor Awards/Submittals/Procurement3/11Sitework Award3/11Steel Contractor Award3/11Concrete/Masonry Award3/12Site Submittals and Approval2/243/33/103/173/243/314/74/144/214/285/55/125/195/266/26/96/166/236/307/77/147/217/288/48/118/188/259/19/89/159/229/2910/610/1310/2010/2711/311/1011/1711/24March 2019April 2019May 2019June 2019July 2019August 2019September 2019October 2019November 2019TREMONT MIXED-USE CONSTRUCTION PROJECT SCHEDULEPage 1Wed 2/27/19 ID Task NameDuration Start Finish Resource Names% Complete22Steel Submittals and Procurement40 daysTue 3/12/19Mon 5/6/190%24Concrete & Masonry Rebar Submittals and Procurement30 daysTue 3/12/19Mon 4/22/190%50CONSTRUCTION181 daysMon 3/25/19Mon 12/2/190%51SITEWORK181 daysMon 3/25/19Mon 12/2/190%52Erosion Control Precon Site Meeting1 dayMon 3/25/19Mon 3/25/190%53Erosion Control 5 daysTue 3/26/19Mon 4/1/190%54Mass Grading/Storm77 daysTue 4/2/19Wed 7/17/190%55Staking/Layout1 dayTue 4/2/19Tue 4/2/190%56Remove Existing Storm Drain (Bldg C Area)4 daysWed 4/3/19Mon 4/8/190%57Strip Topsoil and Haul Off3 daysTue 4/9/19Thu 4/11/190%58Mass Grading / Cut/Fill/Import10 daysFri 4/12/19Thu 4/25/190%59Fine Grading3 daysFri 4/26/19Tue 4/30/190%60Pad Ready Bldg C0 daysWed 5/1/19Wed 5/1/190%63Storm Drainage20 daysThu 5/2/19Wed 5/29/190%61Pad Ready Bldg A/B0 daysFri 5/3/19Fri 5/3/190%62Retaining Walls20 daysThu 6/20/19Wed 7/17/190%64Utilities 97 daysFri 4/26/19Mon 9/9/190%65Sanitary Sewer to MH 2 4 daysFri 4/26/19Wed 5/1/190%66Sanitary Sewer / Water15 daysThu 5/30/19Wed 6/19/190%67Gas / Power40 daysTue 7/16/19Mon 9/9/190%69Curb & Gutter / Asphalt / Site Concrete40 daysTue 10/8/19Mon 12/2/190%70Curb10 daysTue 10/8/19Mon 10/21/190%71Stone Base12 daysTue 10/15/19Wed 10/30/190%73Site Concrete15 daysTue 10/22/19Mon 11/11/190%72Binder5 daysMon 10/28/19Fri 11/1/190%74Final Asphalt Coat / Striping / HC Signage5 daysTue 11/26/19Mon 12/2/190%68Landscaping/ Irrigation15 daysTue 11/5/19Mon 11/25/190%75BUILDING C CONSTRUCTION138 daysWed 5/1/19Mon 11/11/190%76BUILDING C STRUCTURE126 daysWed 5/1/19Thu 10/24/190%77Concrete - Foundations16 daysWed 5/1/19Thu 5/23/190%78Pad Ready0 daysWed 5/1/19Wed 5/1/190%79Layout/Control2 daysThu 5/2/19Fri 5/3/190%80Foundations10 daysFri 5/3/19Thu 5/16/190%81CMU Foundation Walls5 daysFri 5/17/19Thu 5/23/190%82Sub Slab Plumbing/ Electrical7 daysFri 5/24/19Mon 6/3/190%83Sub Slab Plumbing Waste/ S.D.7 daysFri 5/24/19Mon 6/3/190%84Sub Slab Electrical5 daysFri 5/24/19Thu 5/30/190%85CMU15 daysFri 5/24/19Thu 6/13/190%86CMU Stairwells/Elevator Shaft15 daysFri 5/24/19Thu 6/13/190%87Concrete - Slabs36 daysTue 6/4/19Tue 7/23/190%88Ribbon Slab6 daysTue 6/4/19Tue 6/11/190%89Prep5 daysTue 6/4/19Mon 6/10/190%90Pour1 dayTue 6/11/19Tue 6/11/190%91SOD 2nd Floor6 daysMon 7/8/19Mon 7/15/190%92Prep - WWF & MEP Slab Rough5 daysMon 7/8/19Fri 7/12/190%93Pour1 dayMon 7/15/19Mon 7/15/190%94SOD 3rd Floor6 daysTue 7/16/19Tue 7/23/190%3/12Steel Submittals and Procurement3/12Concrete & Masonry Rebar Submittals and Procurement3/253/253/25Erosion Control Precon Site Meeting3/26Erosion Control 4/2Mass Grading/Storm4/2Staking/Layout4/3Remove Existing Storm Drain (Bldg C Area)4/9Strip Topsoil and Haul Off4/12Mass Grading / Cut/Fill/Import4/26Fine Grading5/15/2Storm Drainage5/36/20Retaining Walls4/26Utilities 4/26Sanitary Sewer to MH 2 5/30Sanitary Sewer / Water7/16Gas / Power10/810/8Curb10/15Stone Base10/22Site Concrete10/28Binder11/2611/5Landscaping/ Irrigation5/1BUILDING C CONSTRUCTION5/1BUILDING C STRUCTURE5/1Concrete - Foundations5/15/2Layout/Control5/3Foundations5/17CMU Foundation Walls5/24Sub Slab Plumbing/ Electrical5/24Sub Slab Plumbing Waste/ S.D.5/24Sub Slab Electrical5/24CMU5/24CMU Stairwells/Elevator Shaft6/4Concrete - Slabs6/4Ribbon Slab6/4Prep6/11Pour7/8SOD 2nd Floor7/8Prep - WWF & MEP Slab Rough7/15Pour7/16SOD 3rd Floor2/243/33/103/173/243/314/74/144/214/285/55/125/195/266/26/96/166/236/307/77/147/217/288/48/118/188/259/19/89/159/229/2910/610/1310/2010/2711/311/1011/1711/24March 2019April 2019May 2019June 2019July 2019August 2019September 2019October 2019November 2019TREMONT MIXED-USE CONSTRUCTION PROJECT SCHEDULEPage 2Wed 2/27/19 ID Task NameDuration Start Finish Resource Names% Complete95Prep - WWF & MEP Slab Rough5 daysTue 7/16/19Mon 7/22/190%96Pour1 dayTue 7/23/19Tue 7/23/190%97Structural Steel20 daysTue 6/18/19Mon 7/15/190%98Structural Steel / Decking - 1st Floor7 daysTue 6/18/19Wed 6/26/190%99Structural Steel / Decking - 2nd Floor7 daysThu 6/27/19Fri 7/5/190%100Structural Steel / Decking - 3rd Floor / Roof6 daysMon 7/8/19Mon 7/15/190%101Elevator15 daysThu 9/5/19Wed 9/25/190%102Elevator15 daysThu 9/5/19Wed 9/25/190%103Canopies10 daysFri 10/11/19Thu 10/24/190%104Canopies10 daysFri 10/11/19Thu 10/24/190%118BUILDING C - M/P/E/FP78 daysTue 7/9/19Thu 10/24/190%119Mechanical47 daysTue 7/9/19Wed 9/11/190%120Roof Top Equip. 34 daysTue 7/9/19Fri 8/23/190%121Roof Curbs5 daysTue 7/9/19Mon 7/15/190%122Set RTU's2 daysThu 8/22/19Fri 8/23/190%123Overhead Water / Sanitary Waste & Vent25 daysThu 8/8/19Wed 9/11/190%124Unit Heaters15 daysThu 8/8/19Wed 8/28/190%125Electrical56 daysThu 8/8/19Thu 10/24/190%126Power Distribution - Unit Heaters, RTU's, Convenience Receptacles20 daysThu 8/8/19Wed 9/4/190%127Lighting15 daysFri 10/4/19Thu 10/24/190%105BUILDING C ENVELOPE75 daysTue 7/16/19Mon 10/28/190%106Building Envelope75 daysTue 7/16/19Mon 10/28/190%107Metal Stud Framing / Sheathing / Weather Barrier25 daysTue 7/16/19Mon 8/19/190%108Metal Stud Framing / Sheathing / Weather Barrier25 daysTue 7/16/19Mon 8/19/190%112Brick Veneer / EIFS55 daysTue 7/23/19Mon 10/7/190%113Brick Veneer30 daysTue 7/23/19Mon 9/2/190%114EIFS25 daysTue 9/3/19Mon 10/7/190%109Roofing63 daysThu 8/1/19Mon 10/28/190%110TPO Roofing 5 daysThu 8/1/19Wed 8/7/190%111Gutter/DS5 daysTue 10/22/19Mon 10/28/190%115Storefront25 daysTue 9/17/19Mon 10/21/190%116Storefront Framing20 daysTue 9/17/19Mon 10/14/190%117Storefront Glass20 daysTue 9/24/19Mon 10/21/190%128BUILDING C COMPLETION SCHEDULE10 daysTue 10/29/19Mon 11/11/190%129TCO Inspections5 daysTue 10/29/19Mon 11/4/190%130Core/Shell TCO Inspections5 daysTue 10/29/19Mon 11/4/190%131Punchlist10 daysTue 10/29/19Mon 11/11/190%132Architect/Engineer to Provide to Choate5 daysTue 10/29/19Mon 11/4/190%133Choate/Subcontractors to Complete5 daysTue 11/5/19Mon 11/11/190%134Final Inspections5 daysTue 11/5/19Mon 11/11/190%135Core/Shell Final Inspections5 daysTue 11/5/19Mon 11/11/190%136BUILDING A CONSTRUCTION115 daysFri 5/3/19Fri 10/11/190%137BUILDING A STRUCTURE105 daysFri 5/3/19Fri 9/27/190%138Concrete - Foundations28 daysFri 5/3/19Wed 6/12/190%139Pad Ready0 daysFri 5/3/19Fri 5/3/190%140Layout/Control2 daysFri 5/17/19Mon 5/20/190%7/16Prep - WWF & MEP Slab Rough7/23Pour6/18Structural Steel6/18Structural Steel / Decking - 1st Floor6/27Structural Steel / Decking - 2nd Floor7/8Structural Steel / Decking - 3rd Floor / Roof9/5Elevator9/5Elevator10/11Canopies10/11Canopies7/9BUILDING C - M/P/E/FP7/9Mechanical7/9Roof Top Equip. 7/9Roof Curbs8/22Set RTU's8/8Overhead Water / Sanitary Waste & Vent8/8Unit Heaters8/8Electrical8/8Power Distribution - Unit Heaters, RTU's, Convenience Receptacles10/4Lighting7/16BUILDING C ENVELOPE7/16Building Envelope7/16Metal Stud Framing / Sheathing / Weather Barrier7/16Metal Stud Framing / Sheathing / Weather Barrier7/23Brick Veneer / EIFS7/23Brick Veneer9/3EIFS8/1Roofing8/1TPO Roofing 10/22Gutter/DS9/17Storefront9/17Storefront Framing9/24Storefront Glass10/29BUILDING C COMPLETION SCHEDULE10/29TCO Inspections10/29Core/Shell TCO Inspections10/29Punchlist10/29Architect/Engineer to Provide to Choate11/5Choate/Subcontractors to Complete11/5Final Inspections11/5Core/Shell Final Inspections5/3BUILDING A CONSTRUCTION5/3BUILDING A STRUCTURE5/3Concrete - Foundations5/35/17Layout/Control2/243/33/103/173/243/314/74/144/214/285/55/125/195/266/26/96/166/236/307/77/147/217/288/48/118/188/259/19/89/159/229/2910/610/1310/2010/2711/311/1011/1711/24March 2019April 2019May 2019June 2019July 2019August 2019September 2019October 2019November 2019TREMONT MIXED-USE CONSTRUCTION PROJECT SCHEDULEPage 3Wed 2/27/19 ID Task NameDuration Start Finish Resource Names% Complete141Foundations12 daysMon 5/20/19Tue 6/4/190%142CMU Foundation Walls6 daysWed 6/5/19Wed 6/12/190%143Sub Slab Plumbing/ Electrical7 daysWed 6/5/19Thu 6/13/190%144Sub Slab Plumbing Waste/ S.D.7 daysWed 6/5/19Thu 6/13/190%145Sub Slab Electrical5 daysWed 6/5/19Tue 6/11/190%146Concrete - Slabs8 daysFri 6/14/19Tue 6/25/190%147Ribbon Slab8 daysFri 6/14/19Tue 6/25/190%148Prep6 daysFri 6/14/19Fri 6/21/190%149Pour2 daysMon 6/24/19Tue 6/25/190%150Structural Steel11 daysTue 7/16/19Tue 7/30/190%151Structural Steel Erection 8 daysTue 7/16/19Thu 7/25/190%152Roof Decking 5 daysWed 7/24/19Tue 7/30/190%153Canopies8 daysWed 9/18/19Fri 9/27/190%154Canopies8 daysWed 9/18/19Fri 9/27/190%167BUILDING A - M/P/E/FP43 daysWed 7/24/19Fri 9/20/190%168Mechanical30 daysWed 7/24/19Tue 9/3/190%169Roof Top Equip. 30 daysWed 7/24/19Tue 9/3/190%170Roof Curbs5 daysWed 7/24/19Tue 7/30/190%171Set RTU's2 daysMon 9/2/19Tue 9/3/190%172Overhead Water6 daysMon 8/19/19Mon 8/26/190%173Unit Heaters4 daysMon 8/19/19Thu 8/22/190%174Electrical25 daysMon 8/19/19Fri 9/20/190%175Power Distribution - Unit Heaters, RTU's, Convenience Receptacles10 daysMon 8/19/19Fri 8/30/190%176Lighting10 daysMon 9/9/19Fri 9/20/190%155BUILDING A ENVELOPE38 daysWed 7/31/19Fri 9/20/190%156Building Envelope38 daysWed 7/31/19Fri 9/20/190%157Metal Stud Framing / Sheathing / Weather Barrier20 daysWed 7/31/19Tue 8/27/190%158Metal Stud Framing / Sheathing / Weather Barrier20 daysWed 7/31/19Tue 8/27/190%159Roofing30 daysMon 8/12/19Fri 9/20/190%160TPO Roofing 5 daysMon 8/12/19Fri 8/16/190%161Gutter/DS3 daysWed 9/18/19Fri 9/20/190%162Brick Veneer15 daysWed 8/28/19Tue 9/17/190%163Brick Veneer15 daysWed 8/28/19Tue 9/17/190%164Storefront15 daysWed 8/28/19Tue 9/17/190%165Storefront Framing12 daysWed 8/28/19Thu 9/12/190%166Storefront Glass10 daysWed 9/4/19Tue 9/17/190%177BUILDING A COMPLETION SCHEDULE10 daysMon 9/30/19Fri 10/11/190%178TCO Inspections5 daysMon 9/30/19Fri 10/4/190%179Core/Shell TCO Inspections5 daysMon 9/30/19Fri 10/4/190%180Punchlist10 daysMon 9/30/19Fri 10/11/190%181Architect/Engineer to Provide to Choate5 daysMon 9/30/19Fri 10/4/190%182Choate/Subcontractors to Complete5 daysMon 10/7/19Fri 10/11/190%183Final Inspections5 daysMon 10/7/19Fri 10/11/190%184Core/Shell Final Inspections5 daysMon 10/7/19Fri 10/11/190%5/20Foundations6/5CMU Foundation Walls6/5Sub Slab Plumbing/ Electrical6/5Sub Slab Plumbing Waste/ S.D.6/5Sub Slab Electrical6/14Concrete - Slabs6/14Ribbon Slab6/14Prep6/24Pour7/16Structural Steel7/16Structural Steel Erection 7/24Roof Decking 9/18Canopies9/18Canopies7/24BUILDING A - M/P/E/FP7/24Mechanical7/24Roof Top Equip. 7/24Roof Curbs9/2Set RTU's8/19Overhead Water8/19Unit Heaters8/19Electrical8/19Power Distribution - Unit Heaters, RTU's, Convenience Receptacles9/9Lighting7/31BUILDING A ENVELOPE7/31Building Envelope7/31Metal Stud Framing / Sheathing / Weather Barrier7/31Metal Stud Framing / Sheathing / Weather Barrier8/12Roofing8/12TPO Roofing 9/18Gutter/DS8/28Brick Veneer8/28Brick Veneer8/28Storefront8/28Storefront Framing9/4Storefront Glass9/30BUILDING A COMPLETION SCHEDULE9/30TCO Inspections9/30Core/Shell TCO Inspections9/30Punchlist9/30Architect/Engineer to Provide to Choate10/7Choate/Subcontractors to Complete10/7Final Inspections10/7Core/Shell Final Inspections2/243/33/103/173/243/314/74/144/214/285/55/125/195/266/26/96/166/236/307/77/147/217/288/48/118/188/259/19/89/159/229/2910/610/1310/2010/2711/311/1011/1711/24March 2019April 2019May 2019June 2019July 2019August 2019September 2019October 2019November 2019TREMONT MIXED-USE CONSTRUCTION PROJECT SCHEDULEPage 4Wed 2/27/19