HomeMy WebLinkAbout7305_DukeMayo_ LeachateHaulingPlan_2018-04-02Mayo Electric Steam Plant
Monofill Permit No. 7305-INDUS
Leachate Transportation Plan
10660 Boston Road, Roxboro North Carolina
Person County
Created by: CCP Operations & Maintenance Carolina East
April 2, 2018 – Revision 0
Duke Energy Mayo Monofill Leachate Transportation Plan - Rev 0
Page 2 of 5
1.0 Mayo Monofill Leachate Hauling Plan
The scope of work in this leachate transportation plan (Plan) outlines information for the
support of transportation activities from the Mayo Electric Steam Plant Monofill (Permit No 7305-INDUS) (monofill) leachate tanks to the FGD Pond network.
Current operational conditions of the leachate collection system (LCS) force main have
resulted in a temporary inability to convey leachate from the monofill storage tanks to
the FGD pond via force main piping. Leachate will temporarily be conveyed from the monofill storage tanks to the FGD pond via water tight trucks. While the current force
main outage is anticipated to last 6 to 8 weeks, this Plan is intended to be entered into
the operating record as a permanent contingency plan for conveying leachate, should it
be needed in the future.
Leachate hauling via truck will typically be conducted during daylight hours. The haul
route is similar to the CCR disposal haul route (Figure 1) with the exception of
proceeding on an existing road parallel to the rail line, onsite, to the FGD pond area. No
deviations from the haul route shown below are anticipated. Should deviations occur,
the alternate route will be internally reviewed to ensure the alternate route is safe for transport. The Division will be contacted if any portion of the offsite route requires an
alteration. A speed limit of 15 mph will be maintained by the leachate haul trucks. At the
railroad and Hwy 501crossings, drivers are required to stop and verify it is safe to
proceed.
Figure 1 – Mayo Leachate Haul Road Plan
MAYO
MONOFILL
TANK AREA
FGD
Pond
RAILROAD
CROSSING HWY
501
Duke Energy Mayo Monofill Leachate Transportation Plan - Rev 0
Page 3 of 5
2.0 Leachate Loading and Unloading Operations
Loading at the monofill storage tanks
A water truck loading system is already in place at the monofill. This is a contained area that drains to a collection sump. Should there be any spill of leachate during loading, the sump pumps the leachate back to the LCS. Leachate will be loaded into a
water water tight truck intended to transport liquid. The operator will inspect the truck
during loading operations for leaks, prior to leaving the loadout pad, including
verification that the truck tank is not overfilled. Unloading at the FGD pond area
Unloading will occur at the FGD pond area which consists of a decommissioned bio-
reactor building, FGD flush pond, and FGD settling pond. Leachate will be unloaded
into the drainage system in the decommissioned bioreactor building which gravity drains to the FGD pond system (Figure 2).
Figure 2 – Mayo Unloading at The FGD Pond Area
The water truck will back into the decommissioned bio-reactor building so that it is completely in containment. A hose will route the leachate to the internal drainage ditch
(Figure 3) allowing the leachate to safely flow into the drainage system. Any potential
spills will be captured in the building drainage system that flows to the FGD pond
system.
BIO-REACTOR
BUILDING FGD FLUSH
POND
FGD
SETTLING
POND
Duke Energy Mayo Monofill Leachate Transportation Plan - Rev 0
Page 4 of 5
Figure 3 – Decommissioned Bio-Reactor Building Drain
3.0 Safety
Work will occur with strict conformance to Duke Energy safe work practices including
but not limited to:
• Before all work is started, workers will complete the CCP Operations and Maintenance (O&M) work start checklist and pre-job briefs will be conducted in the
morning and mid-day, after lunch. Workers will review this work plan every morning.
• A spotter will be used, as needed, to ensure trucks traverse safely around obstacles.
• All workers will utilize standard PPE.
• At the railroad crossing and Hwy 501, a stop will occur and the driver will look for
oncoming train or vehicular traffic before proceeding. 4.0 Risk Mitigation
Vehicle Accident Causing Injury and Spill:
Mitigation: A spotter will be used when backing up near FGD ponds, Bioreactor building, and congested areas; the driver will follow posted speed limits. All personnel will be trained on this work plan.
Spill to waters of the state:
Mitigation: The driver will inspect equipment prior to use; ensure no path besides approved route is used without approval from O&M representative; if a leak is observed during transit, a spill kit will be available to contain the leak. All leachate
loading and unloading operations will be conducted in a contained area as described
above.
Struck-by heavy equipment:
Duke Energy Mayo Monofill Leachate Transportation Plan - Rev 0
Page 5 of 5
Mitigation: Workers will utilize radios for spotters. Ensure personnel have been trained on this work plan.
5.0 Environmental Controls
• Routine inspections of the haul route will occur during hours of operation to identify
spills or areas of potential spills.
• All leachate loading and unloading operations will be conducted in a contained area as described above.
• The leachate hauling trucks will be equipped with a spill kit in case of leachate or
other fluid release to the environment
• If a spill occurs, notifications will be made according to the site emergency response plan which is summarized in the call tree (Figure 4). If a spill occurs at Hwy 501 the
Person County Emergency Management will be notified in addition to the Division.
Figure 4 – Mayo Leachate Hauling Emergency Response Call Tree
Charah Site Superintendent
Duke Energy Site Environmental Coordinator
Duke Energy Waste Subject Matter Expert
NCDEQ DWM
Duke Energy Water Subject Mater Expert
NCDEQ DWR
Offsite Spill Person County Emergency Management
Duke Energy Site System Owner Duke Energy Site Safety Officer