McMahan Hydroelectric, LLC
Attn: Mr. Andrew (McMahan
105 Durham Eubanks Road
Pittsboro, NC 27312
Subject: REQUEST FOR ADDITIONAL INFORMATION
Bynum Hydro Project (FERC # 4093)
Dear Mr. McMahan:
On March, 3, 2017, the Division of Water Resources (Division) received your application dated
February 16, 2017, requesting a 401 Water Quality Certification from the Division for the subject
project. The Division has determined that your application is incomplete and cannot be
processed. The application is on -hold until all of the following information is received:
1. A water quality monitoring plan, as outlined in our comments on the Draft License
Application on February 2, 2015, is required for processing the 401 Water Quality
Certification. [15A NCAC 02H .0506(b)(2 &3)]
a. Plan should include specific time periods for each specific monitoring frequency
proposed (e.g. weekly between June 1st and August 31st).
b. Assuming that continuous 02 monitoring in the river and tailrace will be
accomplished with deployed units, what type of units will be used to collect the data.
Low -profile units are desirable due to reduced risk of vandalism.
c. Plan should include an inspection and calibration schedule for, 02 units to prevent
membrane fouling.
d. Units in river and tailrace should be situated such that they are under water at all
flows. Plan should provide the specific depth of deployment for each unit.
e. It would be most informative to sample reservoir on river -left (powerhouse side) at
deepest point, at every foot increment in the water column to determine epi-, meta -
and hypolimnion.
State of North Carolina [ Environmental Quality [ WaterResources
617 Mail Service Center S Raleigh, Norfli Carolina 27699-1617
919 807 6300
McMahan Hydroelectric, LLC
Request for Additional Information
DDR Project # 15-0124
Page 2 of 2
f. Plan should include collection of current conditions at time of sampling (e.g., time,
ambient temperature, wind, last rain event, cloud cover, gage reading, and pond level
at dam crest).
g. Plan should stipulate that latitude/longitude coordinates, of all sample sites will be
collected and total depth of sample sites in river at both time of deployment and any
return visits to harvest data or for r -maintenance will also be collected', -
2. Title 15A NCAC OIC .0107 (a) stipulates that no Department of Environmental Quality
agency shall issue a permit approval while work on an environmental document is in
progress. Please provide one paper copy of the Federal Energy Regulatory Commission
Draft Environmental Assessment to the 401 & Buffer Permitting Branch,
Pursuant to Title 15A NCAC 02H .0502(e), the, applicant shall furnish all of the above requested
information for the proper consideration of the application. If all of the requested information is
not received in writing within 30 calendar days of receipt of this letter, the Division will be unable
to approve the application and it will be returned. The return of this project will necessitate
reapplication to the Division for approval, including a complete application package and the
appropriate fee.
Please respond in writing within 30 calendar days of receipt of this letter by sending three copies
of all of the above requested information to the 401 & Buffer Permitting Branch, 1617 Mail
Service Center, Raleigh, NC 27699-1617.
Please be, aware that you have no authorization under the Section 401 of the Clean Water Act
for this activity and any work done within waters of the state may be a violation of North
Carolina General Statutes and Administrative Code,
Please contact Jennifer Buirdette at 919-807-6364 or jenriifer.burdette@ncdenf.gov if you have
any questions or concerns.
Sincerely,
�ftw
Karen Higgins, Supervisor
401 & Buffer Permitting Branch
CC' Robert Rose, PK Ventures, P 0 Box 35236, Sarasota:, FIL 34242