April 3, 2019
LETTER OF APPROVAL
Fort Bragg Federal Credit Union
Jennifer King, Director Cons Svs
4172 Hefner Drive
Fort Bragg, NC 28310
RE: Project Name: Fort Bragg Federal Credit Union
Acres Approved: 2A
Project ID: CUMBE-2019-106
County: Cumberland, City: Fayetteville
Address: Skibo Road
River Basin: Cape Fear
Stream Classification: Other
Submitted by: Del Crawford
Date Received by LQS: February 20, 2019
Plan Type: Commercial
Dear Mrs. King:
This office has reviewed the subject erosion and sedimentation control plan. We find
the plan to be acceptable with modifications and hereby issue this Letter of Approval.
The enclosed Certificate of Approval must be posted at the job site. This plan approval
shall expire three (3) years following the date of approval, if no land -disturbing
activity has been undertaken, as is required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and
submit an electronic Notice of Intent (NOI) form requesting a Certificate of Coverage
(COC) under the NCGO10000 Construction Stormwater General Permit. This form
MUST be submitted prior to the commencement of any land disturbing activity on the
above named project. The NOI form may be accessed at deq.nc.gov/NCG01. Please
direct questions about the NOI form to Annette Lucas at Annette.lucas@ncdenr.gov
or Paul Clark at Paul,clark@ncdenr.gov. After you submit a complete and correct NOI
Form, a COC will be emailed to you within three business days. Initially, DEMLR will
not charge a fee for coverage under the NCG01 permit. However, on or after May 1,
2019, a $100 fee will be charged annually. This fee is to be sent to the DEMLR
Stormwater Central Office staff in Raleigh.
North Carolina Department of Environnientdl Quality I Division of Energy, Mineral and Land Resources
Fayetteville Regional Office 1 225 Green Street. Suite'714 i Fayetteville. North Carolina 28301
Be42; 910433.:3300 -
Title 15A NCAC 4B .0118(a) and the NCG01 permit require that the following
documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
North Carolina's Sedimentation Pollution Control Act is performance -oriented,
requiring protection of existing natural resources and adjoining properties. If,
following the commencement of this project, the erosion and sedimentation control
plan is inadequate to meet the requirements of the Sedimentation Pollution Control
Act of 1973 (North Carolina General Statute 113A-51 through 66), this office may
require revisions to the plan and implementation of the revisions to insure
compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with
Federal and State water quality laws, regulations, and rules. In addition, local city or
county ordinances or rules may also apply to this land -disturbing activity. This
approval does not supersede any other permit or. approval.
Please note that this approval is based in part on the accuracy of the information
provided in the Financial Responsibility Form, which you provided. You are
requested to file an amended form if there is any change in the information included
on the form. In addition, it would be helpful if you notify this office of the proposed
starting date for this project. Please notify us if you plan to have a preconstruction
conference.
Your cooperation is appreciated.
Sincerely,
Chris Baker
Assistant Regional Engineer
DEMLR - Fayetteville Regional Office
Enclosures: Certificate of Approval
cc: Del Crawford, Crawford Design Company - electronic copy
David Steinmetz, City of Fayetteville Permits - electronic copy
David Winstead, City of Fayetteville Permits -- electronic copy
i Fayetteville Regional Office ,'