September 13, 2019
LETTER OF APPROVAL
RE: Project Name: Southern Pines Warrior Woods Sewer Lift Station
Acres Approved: 1.24
Project ID: MOORE-2020-004
County: Moore, City: Southern Pines,
River Basin: Cape Fear
Stream Classification: Other
Submitted By: WithersRavenel, Inc.
Date Received by LQS: August 28, 2019
Plan Type: Revised
Dear Mr. Kennedy
Address: Central Drive Hwy 22
The subject erosion and sedimentation control plan has been approved by default. The Sedimentation Pollution
Control Act (hereinafter "Act") states that this plan must be filed a minimum of 30 days (15 days for revised plans)
prior to the activity and the approving authority must approve or disapprove the submitted plan within 30 days (15
days for revised plans) of receipt of G.S. 113A-54.1. The Act further states that if the approving authority fails to
approve or disapprove the submitted plan within the 30-day (15 days for revised plans) period, the plan will be
deemed approved. The enclosed Certificate of Approval must be posted at the job site. This plan approval shall expire
three (3) years following the date of approval, if no land -disturbing activity has been undertaken, as is required by
Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice of Intent
(NOI) form requesting a Certificate of Coverage (CDC) under the NCGO10000 Construction Stormwater General
Permit. This form MUST be submitted and CDC issued prior to the commencement of any land disturbing activity on
the above -named project. The NOI form may be accessed at deq.nc.gov/NCGO1. Please direct questions about the
NOI form to Annette Lucas at Annette.lucasOncdenr.gov or Paul Clark at Paul.clarkgncdenr.gov. After you submit a
complete and correct NOI Form, a CDC will be emailed to you within three business days. Initially, DEMLR will not
charge a fee for coverage under the NCGO1 permit. However, a $100 fee will soon be charged annually. This fee is to
be sent to the DEMLR Stormwater Central Office staff in Raleigh.
North Carolina Department of Environmental Quality I Division of Energy. Mineral and Land Resources
Fayetteville Regional Office 1 225 Green Street, Suite 714 1 Fayetteville, North Carolina 28301
om.mm.n umfl�mniawen 910.433.3300
Letter of Approval with Modifications
Town of Southern Pines
September 13, 2019
Page 2 of 2
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on file at the
job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S.113A-61.1(a) of our right of periodic inspection to insure compliance
with the approved plan.
Title 15A NCAC 413.0118(a) requires that a copy of the approved erosion control plan be on file at the job site. Also,
this letter gives the notice required by G.S.113A-61.1(a) of our right of periodic inspection to insure compliance with
the approved plan.
North Carolina's Sedimentation Pollution Control Program is performance -oriented, requiring protection of existing
natural resources and adjoining properties. If, following the commencement of this project, it is determined that the
erosion and sedimentation control plan is inadequate to meet the requirements of the Sedimentation Pollution
Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this office may require revisions to the
plan and implementation of the revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water quality laws,
regulations, and rules. In addition, local city or county ordinances or rules may also apply to this land -disturbing
activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. This permit allows for a land -disturbance, as called for on the application
plan, not to exceed the approved acres. Exceeding the acreage will be a violation of this permit and would require a
revised plan and additional application fee. You are requested to file an amended form if there is any change in the
information included on the form. In addition, it would be helpful if you notify this office of the proposed starting
date for this project. Please notify us if you plan to have a preconstruction conference.
Your cooperation is appreciated.
Sincerely,
Jodi Pace, EI
Regional Engineering Associate
Land Quality Section
Enclosures: Certificate of Approval
NPDES NCGO1 Fact Sheet
cc: David McClure, WithersRavenel, Inc. (Electronic Copy)
Fayetteville Regional Office file