July 11, 2019
LETTER OF APPROVAL WITH MODIFICATIONS
Duke Energy Progress, LLC
ATTN: Buddy Murray, Site Services
5421 Shearon Harris Road
New Hill, NC 27562
RE: Project Name: Shearon Harris Nuclear Plant -- Access Road
Project 1D: WAKE-2019-105
Acres Approved: 1.9
County: WAKE, City: New Hill, Address: Shearon Harris Road
River Basin: Cape Fear, Stream Classification: Other
Submitted By: McKim & Creed
Date Received by LQS: June 11, 2019
Plan Type: New
Dear Mr. Murray:
This office has reviewed the subject erosion and sedimentation control plan. We Find the plan to be
acceptable and hereby issue this Letter of Approval with Modifications. The enclosed Certificate of
Approval must be posted at the job site. This plan approval shall expire three (3) years following the
date of approval, if no land -disturbing activity has been undertaken, as is required by Title 15A NCAC
4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the NCGO1000O
Construction Stormwater General Permit. This form MUST be submitted prior to the commencement
of any land disturbing activity on the above named project. The N01 form may be accessed at
deq.nc.gov/NCGO1. Please direct questions about the N01 form to Annette Lucas at
Annette.lucas@ncdenr.gov or Paul Clark at Paul.clark@ncdenr.gov. After you submit a complete and
correct N01 form, a CPOC will be emailed to you within three business days. Initially, DEMLR will
not charge a fee for the coverage under the NCGO1 permit. However, on or after June 1, 2019, a $100
fee will be charged annually. This fee is to be sent to the DEMLR Stormwater Central Office staff in
Raleigh.
North Carolina Department of Environmental Quality I Division or Energy. Mineral and Land Resources
Raleigh Regional Office 11628 Mall Service Center 3800 Barrett Drive I Raleigh. North Carolina 27609
919.791.4200
Letter of Approval with Modifications
Duke Energy Progress, LLC
July 11, 2019
Page 2 of 3
Title 15A NCAC 413.0118(a) and the NCGO1 permit require that the following documentation be kept
on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspection made during the previous 30 days.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, the
erosion and sedimentation control plan is inadequate to meet the requirements of the Sedimentation
Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this office may require
revisions to the plan and implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form if
there is any change in the information included on the form. In addition, it would be helpful if you
notify this office of the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Your cooperation is appreciated.
Sincerely,
Sally Cast e, El
Regional Engineering Associate
DEMLR
Enclosures: Certificate of Approval
NCGO1 Fact Sheet
cc: Gareth Avant, PE (gavant@mckimcreed.com)- Electronic Copy
DEMLR - Raleigh Regional Office File
Letter of Approval with Modifications
Duke Energy Progress, LLC
July 11, 2019
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Shearon Harris Nuclear Plant — Access Road
Project ID: WAKE-2019-I05
County: WAKE
Approval of this erosion and sedimentation control plan does not authorize impacts to
wetlands, coastal marsh, streams or other waters of the State or United States or supersede
any other permitting requirement of any Federal, State or Local agency. Provide a copy of
the USACE 404 permit for the office file. Submit documentation with maps showing
location and extent of impacts to streams and wetlands with any special conditions
pertaining to erosion and sediment control and restoration of affected areas. Identify the
streams and wetlands on the plan sheets. Include any additional measures, construction
specifications, maintenance requirements and construction sequencing as required by the
404 permit on the plan sheets. if this project is exempt from 404 permitting, provide
supporting documentation from the USACE. (GS I I3A-54.I(c))
2. Provide two copies of the plan set (one full-size and one half-size), showing the
modifications required for approval prior to initiating Iand-disturbing activity. To
facilitate DEMLR review, bubble, highlight, or otherwise identify the changes to your
resubmittal. Provide one copy of additional items (such as design calculations). Provide
a cover letter referencing the project name, project 1D, and purpose for submittal. (G.S.
1 l 3A-57(4))