May 17, 2019
BP Black Mountain 1, LLC
Attn: Todd Chambers
POBox 3180
Asheville, NC 28802
Mr. Chambers,
This office has reviewed the Erosion and Sedimentation Conh•ol Plan submitted for the project listed below. We find the
plan to be acceptable with the attached rnod fications nisi!/or performance reservations and hereby issue this Letter of
Approval. Please be advised that Section 26-228 requires that a copy of the approved Soil Erosion Control Plan be on file
at the job site.
•The Buncombe County Soil Erosion and Sedimentation Control Ordinance is a performance oriented program requh•irig
protection of the natural resources and adjoining properties. If, following commencement ofthis project it is determined
that the plan is inadequate, this office may require revisions to the plan and its implementation. The approval for this
project is good for the time frame stated on the original land disturbing permit. This permit shall become null and
void ifyou have not made progress to begin construction activities on the site within six months after the date of
approval. Renewal of the land disturbing permit will require a new plait revie►v submittal with associated fees.
The approval of an erosion plan is conditioned on the applicant's compliance with federal and state water quality laws,
regulations, and rules. A copy of the erosion conhol plan for any land dishu•bing activity that involves the utilization of
ditches for the purpose of de -watering or lowering the water table must be forwarded to the dnector of water quality.
*As ofAprill, 2019, all new construction activities are regttired to complete nrtdsubrttit all electronic Notice ofLtfertl
(NOI) for regttesting a Certificate of Coverage (COC) tntder• the NCG01000 Consbnetion Storrnwnter General
Permit. This form MUST be submitted prior to the commencement of any land disturbing activity on Ilse below
nansedprojecf.TheNOlforniinaybeaccessedatdealnc.gov/NCG01. Please direct all questions about theNOlform
or the process to Amieffe Lttcas at Annette.lucas( nedenrl ov or Paul Clark at Paul. clark(k)ncdenr.t;ov. Initially,
DEMLR will not charge a fee for coverage under the NCG01 permit. However, on or after May 1, 2019, a $100 fee
will be charged annually. This fee is to be sent to the DEMLR Storrtnvater Central Office staff In Raleigh and is not
collected by this local progrant. Once the NCG01 permit has been completed and approved by DEMLR, a project
permit number will be given for this project that mast be written ors the Buncombe County Land Disturbing Permit,
Witch must be on site throughout llte construction phase of file project.
When the project is complete, the financially responsible party or their representative will contactBuncontbe County
Erosion oil dSedimentation Control Office to close out file Erosion and Sedimentation Control Plan. A Certificate of
Compliance will be issued for the project once Cite site meets the regairentent as stated in llte original Letter of
Approval and standards stated in the Buncombe County Soil Erosion and Sedimentation Control Ordinance. The
responsible party will then be instructed to visit dea.nc.,eoy11VCG01 to submit an e NOT (electronic Notice of
Termination) form for closing out the NCG01 permit. Please refer to the attached NCG01 Fact Si►eet.
Page 2
A Combined Self -Monitoring and Self -Inspection Form for the NCG01 is enclosed, Please review all pertinent
documents prior to starting construction. We look forward to working with you on this project,
Sincerely,
Doug Sharp
Erosion Control Officer
cc:
Project name: Padgettown Road Subdivision
Location: 542 Padgettown Road
Date received: May 1, 2019
Date approved: May 17, 2019
Permitted Disturbance: 8 Acres
Person financially responsible: BP Black Mountain 1, LLC / Todd Chambers
MODIFICATIONS AND/OR PERFORMANCE RESERVATIONS FOR
No work can begin on site until the NCGO1 State permit is submitted to this office.
No work in the areas covered under the ACOE permit, until permit is submitted to this office.
No work on site until all permits from the Town of Black Mountain are in place.
Make sure the contractor has the latest set of plans, dated May 13, 2019.
Read and understand page 3.7, typical lot erosion control and 3.5 Pump around for the culvert install.
Contractor or owner must contact Buncombe County Erosion Control Office to schedule an on -site
pre -construction meeting prior to beginning any grading activity,
Contractor must have a copy of the latest set of plans marked "Construction Documents" and
showing any revisions and/or details, Approved plans must be available at the construction site at
all times for inspection by inspectors and any other governing regulatory agent.
A copy of the Erosion Control Permit, a copy of the Letter of Approval with Modification and/or
Performance Reservations, and a copy of the Combined Self -Monitoring and Self -Inspection Form
must be available on -site in a job box or contractor's trailer at all times. These documents must be
reviewed and understood by all parties involved prior to any land disturbing activities. A worldng
n•ain gauge must also be present and installed at the site for monitoring.
Contractor to insure that any import or export material be from a permitted site.
Erosion control measures must be installed in accordance with the approved engineering plans and
maintained at all times. Alternate measures must first be approved with the engineer of record and
regulatory site inspector prior to installation.
Areas of constructions left bare for more than 21 days without temporary ground cover could delay
building construction inspections and cause possible delays in issuance of building occupancy
letters.
Notification must be given to this office for• inspection at the completion of site stabilization of the
project prior to the removal of any perimeter/pertinent erosion control measures at the site,
Clearing limits for grading must be clearly delineated in the field as shown on the approved
engineering plans. Any additional clearing or land disturbing activity that disturbs the ground
surface outside of those limits will constitute a violation of the County's Ordinance and will be
subject to penalties,
Additional erosion control measures and MvIr devices will be required if approved measures are
not sufficient to contain and control sediment and runoff on the project site, Additional measures to
help control and reduce on -site runoff during construction will be discussed at pre -construction
meeting,
Page 3
Erosion control measures must be inspected and repaired if needed on a regular basis and
maintained at all times, Failure to maintain erosion control measures can result in delayed building
inspections, revocation of permits or possible civil penalties.
Approval of this projecl is in accordance with the requirements set forth by the Buncombe County Soil Erosion and
Sedimentation Control Ordinance and information provided in the approved construction plans, construction
sequence, construction details, and documentation. Any modification of this approval in regards to soil erosion and
sedimentation conh•01 must be made aware to the Buncombe County Erosion Control Office prior to any changes.
�RcLot, 0doa 3
County of
PLANNING AND DEVELOPMENT
Nate Pennington 46 Valley Street Telephone 828-2504830
Planning Director Asheville, NC 28801 Fax 82&250-6086
LETTER OF APPROVAL
June 28, 2019
BP Black Mountain 1, LLC
Attn: Todd Chambers
P O Box 3180
Asheville, NC 28802
Mr. Chambers,
Erosion and Sedimentation Conri•ol
Telephone: (828)-250=4848
This office has reviewed the Revised Erosion and Sedimentation Conriol Plan submitted for the project listed below. We
find the plan to be acceptable and hereby issue this Letter of Approval. Please be advised that Section [26-228] requites
that a copy of the approved Soil Erosion Control Plan be on file at the job site.
The approval of an erosion plan is conditioned on the applicant's compliance with federal and state water quality laws,
regulations, and rules. A copy of the erosion control plan for any land disturbing activity that involves the utilization of
Af
ditches for the purpose of de -watering or lowering the water table must be forwarded to the director of the division of
water quality. 96
The Buncombe County Soil Erosion and Sedimentation Conri•ol Ordinance is a performance oriented program requiring
protection of the natural resources and adjouiing properties, If, following commencement of this project, it is
determined that the plan is inadequate, this office may require revisions to the plan and its implementation,
Please inform this office of the construction start date.
We look forward to working with you on this project.
Sinc I 1 ,
Do Sharp
T
Erosion Control Officer
Project name: Padgettown Road Subdivision
Location: 542 Padgettown Road
Date received : June 28, 2019
Date approved : June 28, 2019
Person financially responsible: BP Black Mountain 1, LLC / Todd Chambers