June b, 2019
LETTER OF APPROVAL WITH MODIFICATIONS
Anson County
Attn: Baron Monroe, Manager
101 S. Green St.
Wadesboro, NC 28170
RE: Project Name: Anson County - Perimeter and Wildlife Fence
Acres Approved: 7
Project ID: ANSON-2019-006
County. Anson, City: Wadesboro Address: Airport Rd.
River Basin: Yadkin
Stream Classification: Other
Submitted By: Michael Baker Engineering Inc.
Date Received by LQS: May 7, 2019
Plan Type: New
Dear Mr. Monroe:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be
acceptable with modifications and hereby issue this Letter of Approval. The enclosed Certificate of
Approval must be posted at the job site. This plan approval shall expire three (3) years following
the date of approval, if no land -disturbing activity has been undertaken, as is required by Title I5A
NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the NCG010000
Construction Stormwater General Permit. This form MUST be submitted prior to the commencement
of any land disturbing activity on the above named project. The NOI form may be accessed at
deq.nc.govINCGOI. Please direct questions about the NOI form to Annette Lucas at
Annette.lucas@ncdenr.gov or Paul Clark at Paul.clark@ncdenr.gov. After you submit a complete
and correct NOI Form, a COC will be emailed to you within three business days. Initially, DEMLR
will not charge a fee for coverage under the NCGO1 permit. However, on or after June 1, 2019, a
$100 fee will be charged annually. This fee is to be sent to the DEMLR Stormwater Central Office
staff in Raleigh.
^E� North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
DFayetteville Regional Office 1225 Green street. Suite 714 I Fayetteville, North Carolina 28301 91,0.433.3300
Letter of Approval
Anson County
June 6, 2019
Page 2 of 3
Title 15A NCAC 4B .0118(a) and the NCGO I permit require that the following documentation be kept
on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous twelve (12) months..
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the commencement
of this project, the erosion and sedimentation control plan is inadequate to meet the requirements
of the Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51
through 66), this office may require revisions to the plan and implementation of the revisions to
insure compliance with theAct.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State
water quality laws, regulations, and rules. In addition, local city or county ordinances or rules may
also apply to this land -disturbing activity. This approval does not supersede any other permit or
approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. This permit allows for a land -disturbance, as
called for on the application plan, not to exceed the approved acres. Exceeding the acreage will be
a violation of this permit and would require a revised plan and additional application fee. Any
addition in impervious surface, over that already noted on the approved plan, would also require a
revised plan to verify the appropriateness of the erosion control measures and the stormwater
retention measures. (GS 113A-54.l(b)). You are requested to file an amended form if there is any
change in the information included on the form. In addition, it would be helpful if you notify this
office of the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Your cooperation is appreciated.
Si?Jo
rely,
Pace, EI
Regional Engineering Associate
DEMLR
Enclosures: Certificate of Approval
cc: Jared Penny, Michael Baker Engineering Inc. (electronic copy)
Keith Gaskins, Chief Inspector (electronic copy)
DEMLR - Fayetteville Regional Office File
Letter of Approval
Anson County
June 6, 2019
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: ANSON COUNTY - PERIMETER AND WILDLIFE FENCE
Project ID: ANSON-2019-006
County: Anson
The Construction Entrance must be included within. the Limits of Disturbance.
Per G.S. 113A-57(4),
Provide Approval to this office from NC Div. Water Resources and US Army Corps of Engineers
for the stream disturbances before doing any work in the streams or wetlands.
Per G.S. 113A-54.1 (a)
Provide two fail size copies each of revised plan sheets, showing all the Modifications required
for approval, prior to beginning any land -disturbing activity.
Per G.S. 113A-57(4), 15A NCAC 04B.0118 & G.S. 113A-54(d)(4)