HomeMy WebLinkAboutSW6190508_Response to Comments_20190708ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
S. ❑ANIEL SMITH
Interim Director
Robert L. Day, PE
810 South Cincinnati Ave. Suite 200
Tulsa, OK 74119
NORTH CAROLINA
Environmental Quality
June 14, 2019
Subject: Request for Additional Information
Stormwater Permit No. SW6190508
SOF Battalion Administration Facility PN 63850
Cumberland County
Dear Mr. Day:
The Division of Energy, Mineral and Land Resources (DEMLR), received a Stormwater
Management Permit Application for the subject project on May 17, 2019. A review of that
information has determined that the application is not complete. The following
information is needed to continue the stormwater review:
Please write the directions to the project site from the nearest intersection of two
major roads. Major roads are any 1, 2, or 3 digit NC, US, or Interstate highway.
(Section I, 3).
Response: Provided on Cover Sheet
2. Please list the date issued and type of permit issued for the previously acquired permit
(Section II, 4, b).
Response: Updated on Application
2. Please include the "Future Parking Access Drive" in the future impervious area section
of drainage area 1 or provide justification for its omission (Section IV, 10).
Response: Future access drive is for representation only and not part of this contract.
If awarded under separate contract a SCM will be provided then.
Please provide the original, signed copy of the application form (Section VI, 1).
Response: Provided
4. Please provide the original, signed copy of the supplemental form (Section VI, 3).
Response: Provided
D7> North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
EQ 512 North Salisbury Street 1 1612 Mail Service Center I Raleigh, North Carolina 27699-1612
rvaarH caw�uw �
919.747.9200
6. Please provide signed, sealed, and dated detailed design calculations (Section VI, 7).
Calculations should include, but are not limited to:
a. Calculations showing that the 10-year storm will be passed at a non -
erosive velocity (As per 15A NCAC 02H .1061(5).
Response: Provided
b. Calculations showing that the infiltration trench will be able to dewater within
the required 72 hours (Infiltration System, MDC 5).
Response: Infiltration trench has been removed from this project. Bio-
retention area 2 has been modified to accommodate the additional area.
7. Please provide the title sheet with project location map (Section VI, 8, c).
Response: Provided
8. Please dimension all proposed BUA on the plans (Section VI, 8, j).
Response: Provided
9. Please provide a note on the plans declaring that no wetlands are present on the site.
Please also provide documentation of qualification and identify the person who made
this determination (Section VI, 8, m).
Response: Note provided on the coversheet. See attached document for the
information requested.
10. No soil boring was performed within the footprint of the infiltration trench and it
is required (Infiltration System, MDC 1).
Response: Infiltration trench has been removed for this project.
11. The infiltration rate for the soils on -site are very low (0.001 — 0.003 inches per hour).
Please provide calculations showing that the infiltration trench will be able to
dewater within the required 72 hours (Infiltration System, MDC 5).
Response: Infiltration trench has been removed for this project.
12. Vegetated filter strips should be at least five feet wide and should not exceed 8% slope.
Please revise.
Response: Updated
13. There is a discrepancy between the bottom elevation of bioretention cell 1 as reported
in the supplemental form and the plans. Please revise for consistency.
Response: Updated
14. Bioretention cell 1 has an infiltration rate less than 2.0 inches per hour and
therefore requires IWS (Bioretention Cell, MDC 4). Please revise.
Response: Updated
15. Provide pdfs of all revisions, 2 hardcopies of revised plan sheets, and 1 hardcopy of
other documents. Pdfs must be uploaded using the form at:
https://edocs.deq.nc.gov/Forms/SW_Project Submittal
Response: Will provide
While it is not required, it is recommended that rip -rap be shown on the plans and that the
bioretention cells be outfitted with some form of pretreatment. It is also recommended that
the top of the infiltration trench be placed at an elevation lower than the adjacent parking
area to minimize ponding on the road surface.
Please note that this request for additional information is in response to a preliminary review.
The requested information should be received by this Office prior to July 14, 2019, or
the application will be returned as incomplete. The return of a project will necessitate
resubmittal of all required items, including the application fee. Please reference the State
assigned project number SW6190508 on all correspondence.
If you need additional time to submit the information, please submit your request for a time
extension to the Division at the contact below. The request must indicate the date by which
you expect to submit the required information. The Division is allowed 90 days from the
receipt of a completed application to issue the permit.
The construction of any impervious surfaces, other than a construction entrance under an
approved Sedimentation Erosion Control Plan, is a violation of NCGS 143-215.1 and is
subject to enforcement action pursuant to NCGS 143-215.6A.
If you have any questions concerning this matter please feel free to contact me at
Jim.Farkasgncdenr.gov or (919) 707-3646.
Sincerely,
Jim Farkas
Environmental Engineer
Stormwater Program
cc: Fayetteville Regional Office
LEGEND:
DESIGNATION
PROPERTY
e WETLAND LINE
._ :: •.
MICINITY MAP
(NOT TO
offl9*611!
1000 500 0 1000
( IN FEET )
1 inch = 1000 ft.
NOTES:
1) WETLANDS DELINEATION DONE BY
DIAL CORDY & ASSOCIATES, INC.
IN NOVEMBER 2008
2) HORIZONTAL DATUM IS NAD 83
3) NO BOUNDARY SURVEY WAS DONE AS
PART OF THIS SURVEY. BOUNDARY
LINES SHOWN ARE FOR REFERENCE ONLY
4) WETLAND AREAS ARE CALCULATED TO THE
PROPERTY LINE OF SUBJECT TRACT WHERE
CROSSING PROPERTY LINE.
5) SEE SHEET 2 OF 22 FOR TABULATION OF
WETLAND AREAS AND LINEAR FEET OF
CHANNELS
t s • * R. • !
t
UMIT OF DEUNEATIO)
OMIT OF DEUNEATION-
(04
M O
ccs W
o �}
CO
,
00
,
-
-j
•
w �.,
" s
•
.6 -
•
In
•ui
i' ..
ri
•
i
0
LL
0
U
O Q1
t� III>
CID 0
CV E
Q
J E
0 3
3
cc C-1
Q
z !J
U) Z L
E:i K) M'
U) J _ U)
J O O
(3 W 0v%� 9)
o < < c
U:;Q6163-0I%CIN20Y ASS—TIIL, ,-BftAt3G Vv£RANQ516Q-0ravMgatAD40LD ASPWDA ODD ASP WETLAN65.dv i-1-11 I9A5 AM, 1:1
Stefan Tittjung
From: McMillan, Kenneth V CTR USARMY IMCOM ATLANTIC (USA) <kenneth.v.mcmiIlan.ctr@mail.miI>
Sent: Monday, July 08, 2019 7:57 AM
To: Stefan Tittjung
Subject: FW: [Non-DoD Source] PN 63850 SOF Battalion Administrative Facility request for additional information by NCDEQ (UNCLASSIFIED)
Attachments: Wetland Delineation ASP 2008.pdf
-----Original Message -----
From: Hoffman, Erich L CIV USARMY IMCOM (USA)
Sent: Friday, July 5, 2019 2:33 PM
To: Stefan Tittjung <stittjung@cyntergy.com>
Cc: Ward, Lee P CIV USARMY IMCOM ATLANTIC (USA) <lee.p.ward.civ@mail. mil>; McMillan, Kenneth V CTR USARMY IMCOM ATLANTIC (USA)
<kenneth.v.mcmillan.ctr@mail. mil>
Subject: RE: [Non-DoD Source] PN 63850 SOF Battalion Administrative Facility request for additional information by NCDEO (UNCLASSIFIED)
CLASSIFICATION: UNCLASSIFIED
Stefan,
The area where this project, PN 63850, is located has been officially surveyed for wetlands by a Contract in 2008-2009. The formal JD was completed for the entire Old
Ammo Supply Point, which was later named Patriot Point, then more recently changed to the Yarborough Complex. The wetland boundaries are in our ESRI Arc Map
GIS layer as a feature class. PN 63850 falls in the uplands and no wetlands are present on the site. See attachment. I assume the project site by definition means the
project limits of disturbance polygon? The first JD was done by Dial Cordy and Associates Inc, Environmental Consultants, the field ecologist was Mr. Ralph Engle. The
Land Survey company was McKim & Creed. The USACE Action ID was SAW-2008-00067 dated 3 Feb 2009. The Wilmington Regulatory Authority was Mr. Richard
Spencer. This formal JD was done for the future Patriot Point Infrastructure requirement.
A later formal JD was completed in 2011-2012 for the Patriot Point Master Plan by 3e EEE Consulting, Inc., the field biologist name was Mr. Ray Bode. Both of these
environmental companies have trained and qualified staff to conduct wetland delineations. Each formal JD was field verified with a site visit with USACE Wilmington
District, Ft. Bragg EMB, and the Contractor. Both formal JDs were authorized by Wilmington District. The Wilmington Regulatory Authority was Mr. Ronnie Smith.
FYI, I am the Senior Wildlife Biologist who was the CORTR for both wetland delineation contracts on Ft. Bragg. Both JD Determinations were validated by USACE
Wilmington District and given Notice of Jurisdictional Determination letters. Each contract deliverables was a signed wetland delineation plate by a State of NC Licensed
Land Surveyor and a digital GIS wetland layer shapefile was provided to us for incorporation into our ArcMap GIS geodatabase.
NOTE: The majority of the old ASP area now known as the Yarborough Complex Cantonment Area (CA) area is 98% uplands. Two major drainages lie on either side (east
and west) of the CA. Bones Creek watershed lies to the west and Stewarts Creek watershed lies to the east. Riparian wetlands are associated with both watersheds
along the 1st order tributaries and 2nd order streams. The Yarborough Complex CA only has two places where JD wetlands occur inside the Complex. There is a small
western tributary headwater that begins at the northeastern corner of African Lion and New Dawn roads. The drainage flows west across African Lion toward Bones
Creek. The other wetland/tributary stream is on the East side and begins at Tora Bora. Its situated between Eagle Talon and New Dawn and flows from Tora Bora Rd. in
the east direct to Stewarts Creek.
Project PN 63850 is located at the Northern portion of the Yarborough Complex CA north of Urban Freedom road. Again, there are no wetlands in this project area. The
nearest wetland is approximately 1,000+ feet to the west on the west side of African Lion road. Let me know if NCDEQ Stormwater Permit No. SW6190508 Question 9
has been answered to your satisfaction.
Respectfully,
Erich L. Hoffman
Senior Wildlife Biologist
DPW -Environmental Management Branch
Building 3-1137, Butner Rd., Fort Bragg, NC 28310-5000
O: (910) 432-4505
Email: erich.l.hoffman.civ@mail.mil
-----Original Message -----
From: Stefan Tittjung [mailto:stittjung@cyntergy.com]
Sent: Monday, July 1, 2019 6:00 PM
To: McMillan, Kenneth V CTR USARMY IMCOM ATLANTIC (USA)<kenneth.v.mcmillan.ctr@mail. mil>; Hoffman, Erich L CIV USARMY IMCOM (USA)
<erich.1.hoffman.civ@ mail. mil>
Cc: Troy Secord <tsecord@slatx.us>; Robert Day <rday@cyntergy.com>; Kent Bray <kbray@cyntergy.com>
Subject: RE: [Non-DoD Source] PN 63850 SOF Battalion Administrative Facility request for additional information by NCDEQ
All active links contained in this email were disabled. Please verify the identity of the sender, and confirm the authenticity of all links contained within the message prior
to copying and pasting the address to a Web browser.
Good afternoon Erich,