May 17, 2019
LETTER OF APPROVAL WITH MODIFICATIONS
Piedmont Natural Gas
Attn: Tom Morris, Project Manager
4720 Piedmont Row Dr.
Charlotte,NC 27210
RE: Project Name: Piedmont Natural Gas Line 448 Project
Acres Approved: 254
Project ID: SAMPS-2019-010
County: Sampson, City: Clinton Address: Stanley Hall Rd.
River Basin: Cape Fear
Stream Classification: Other
Submitted By: Mott MacDonald
Date Received by LQS: April 18, 2019
Plan Type: New
Dear Mr. Morris:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan
to be acceptable with modifications and hereby issue this Letter ofApproval with Modifications.
The Modifications Required for Approval are listed on the attached page. The enclosed
Certificate of Approval must be posted at the job site. This plan approval shall expire three (3)
years following the date of approval, if no land-disturbing activity has been undertaken, as is
required by Title 15A NCAC 413 .0129.
As of April 1,2019, all new construction activities are required to complete and submit an electronic
Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the NCGO10000
Construction Stormwater General Permit. This form MUST be submitted prior to the
commencement of any land disturbing activity on the above named project. The NOI form may be
accessed at deq.nc.govINCG01. Please direct questions about the NOI form to Annette Lucas at
Annette.lucas@ncdenr.gov or Paul Clark at Paul.clark@ncdenr.gov. After you submit a complete
and correct NOI Form, a COC will be emailed to you within three business days. Initially,DEMLR
will not charge a fee for coverage under the NCGO1 permit. However, on or after June 1, 2019, a
$100 fee will be charged annually. This fee is to be sent to the DEMLR Stormwater Central Office
staff in Raleigh.
1,E North Carolina Department of Environmental Quality I Division of Energy,Mineral and Land Resources
Fayetteville Regional Office I225 Green Street.Suite 714 I Fayetteville,North Carolina 28301 910.433.3300
ESN CPROIJNA
a pf axnt a F EnH rwmmt+!4u.Rh
Letter of Approval
Piedmont Natural Gas
May 17, 2019
Page 2 of 3
'F
r
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be 4
kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO 1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
F
North Carolina's Sedimentation Pollution Control Act is performance-oriented, requiring
protection of existing natural resources and adjoining properties. If,following the commencement
of this project, the erosion and sedimentation control plan is inadequate to meet the requirements
of the Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51
through 66), this office may require revisions to the plan and implementation of the revisions to
insure compliance with theAct.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State
water quality laws, regulations, and rules. In addition, local city or county ordinances or rules may
also apply to this land-disturbing activity. This approval does not supersede any other permit or
approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. This permit allows for a land-disturbance,as
called for on the application plan, not to exceed the approved acres. Exceeding the acreage will be
a violation of this permit and would require a revised plan and additional application fee. Any
addition in impervious surface, over that already noted on the approved plan, would also require a
revised plan to verify the appropriateness of the erosion control measures and the stormwater
retention measures. (GS I I3A-54.1(b)). You are requested to file an amended form if there is any
change in the information included on the form. In addition, it would be helpful if you notify this
office of the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Your cooperation is appreciated.
3.
Sincerely,
Jodi Pace,EI
Regional Engineering Associate
DEMLR
Enclosures: Certificate of Approval
cc: Justin Miner, Mott MacDonald(electronic copy)
Myron Cashwell, Building Inspector (electronic copy)
DEMLR- Fayetteville Regional Office File
i
Letter of Approval
Piedmont Natural Gas
May 17, 2019
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Quail Glen- Phase 4B
Project ID: HARNE-2019-081
County: Harnett
No silt fence is to be installed in the wetlands, wattles are to be used instead. Per G.S. 113A-57(3)
Provide a detail, construction specifications and maintenance requirements for the construction
Entrance. Per G.S. 113A-57(3),
Provide a copy of the 401 permit from the Army Corps of Engineers before any work is done
in the wetlands.
Provide PDF copies of each revised plan sheets, showing all the Modifications required for
approval, prior to beginning any land-disturbing activity.
Per G.S. 113A-57(4), 15A NCAC 04B.0118 & G.S. 113A-54(d)(4)