HomeMy WebLinkAboutNCC190525_ESC Approval Submitted_20190606 L
ROY COOPER �E
Governor
MICHAEL S.REGAN ^'^�
Secretary
S.DANIEL SMITH NORTH CARouNA
Interim Director Environmental Quality
May 13, 2019
LETTER OF APPROVAL
r
Express Option
H & H Constructors of Fayetteville, LLC
Attn: Brian Walker,Agent
2919 Breezewood Ave
Fayetteville,NC 28301
RE: Project Name: Juniper Ridge - Phase Three (Lots 55)
Acres Approved: 0.47
Project ID: MOORE-2019-059
County: Moore, City: Mineral Springs Township Address: Mountain Run Dr.
River Basin: Cape Fear r
Stream Classification: Other
Submitted By: Moorman,Kizer&Reitzel, Inc.
Date Received by LQS: May 13, 2019
Plan Type: Express
Dear Mr. Walker:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to
be acceptable and hereby issue this Letter of Approval. The enclosed Certificate of Approval must
be posted at the job site. This plan approval shall expire three (3) years following the date of
approval, if no land-disturbing activity has been undertaken, as is required by Title 15A NCAC
4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the
NCGO10000 Construction Stormwater General Permit. This form MUST be submitted prior to the
commencement of any land disturbing activity on the above named project. The NOI form may be
accessed at deq.nc.govINCGO1. Please direct questions about the NOI form to Annette Lucas at
Annette.lucas@edenr.gov or Paul Clark at Paul.clark@nedenr.gov. After you submit a complete
and correct NOI Form, a COC will be emailed to you within three business days. Initially,
DEMLR will not charge a fee for coverage under the NCGO1 permit. However, on or after June 1,
2019,a$100 fee will be charged annually. This fee is to be sent to the DEMLR Stormwater Central
Office staff in Raleigh.
D E A North Carolina Department of Environmental Quality I Division of Energy,Mineral and Land Resources
Fayetteville Regional Office f 225 Green Street,Suite 714 1 Fayetteville,North Carolina 28301
Ncr�ni cnneu� +
OeOa BMA EtanmmlaFO�1"y /"`� 910.433.3300
i
Letter of Approval
H & H Constructors of Fayetteville, LLC
May 13, 20t9
Page 2 of 2
i
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be !
kept on file at the job site:
i
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
North Carolina's Sedimentation Pollution Control Act is performance-oriented, requiring
protection of existing natural resources and adjoining properties. If,following the commencement
of this project, the erosion and sedimentation control plan is inadequate to meet the requirements
of the Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51
through 66), this office may require revisions to the plan and implementation of the revisions to
insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State
water quality laws,regulations, and rules. In addition, local city or county ordinances or rules may
also apply to this land-disturbing activity. This approval does not supersede any other permit or
approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form,which you provided. This permit allows for a land-disturbance, as
called for on the application plan, not to exceed the approved acres. Exceeding the acreage will '
be a violation of this permit and would require a revised plan and additional application fee. Any
addition in impervious surface, over that already noted on the approved plan, would also require a
revised plan to verify the appropriateness of the erosion control measures and the stormwater
retention measures. (GS 113A-54.I(b)). You are requested to file an amended form if there is any
change in the information included on the form. In addition, it would be helpful if you notify this
office of the proposed starting date for this project. Please notify us if you plan to have a
preconstruction conference.
Your cooperation is appreciated.
Sincerel ,
Jodi Pace, EI
Regional Engineering Associate
DEN LR
Enclosures: Certificate of Approval
NPDES Permit
cc: Dennis Gilbert, Moorman, Kizer & Reitzel, Inc. (electronic copy)
Debra Ensminger, Moore County Planning (electronic copy)
DEMLR- Fayetteville Regional Office File