July 26, 2018
Contract:
WBS No.:
Tip Number.
FA Project No.
Counry:
Route:
Description:
T.A. Loving Company
Attn: Clay Wisniewski
P.O. Drawer919
Goldsboro, NC 27534
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
DB00408
385593.1
B-4789
BRZ-1424 (7)
Pitt
SRI424 Allpine-Taylor Road
Replace Bridge # 164 over Grindle Creek
JAMES H. 71tOGDON, III
SECRETARY
A pre-construction meeting was held Thursday, ]uly 26, 2018 for the above referenced project. The following
individuals were in attendance:
Name
Sazah Lentine
Jason Beasley
Beverly Daniels
Andy Blankenship
Justin Davis
Jeffrey Dunning
Gary McSweeney
Clay Wisniewski
A.K. Reeves
Gazcy Wazd
David Peasley
Companv/Aeencv
NCDOT — Resident Engineer
NCDOT — Senior Asst. Resident Engineer
NCDOT—Administrative Specialist
NCDOT — Roadside Env'vonmenta]
NCDOT — Roadside Environmental
NCDOT — Traffic Services
NCDOT — Bridge Maintenance
T.A. Loving Co. — Project Manager
T.A. L,oving Co. — Superintendent
NCDWR—Environmental Sc Specialist (Permitting & Compliance)
RK&K — CEI Project Inspector for NCDOT
Mrs. Lentine opened the meeting announcing recording of today's minutes and verbal introduction were given by each
attendee.
Proiect Schedule
Date of Availability: August 6, 2018
Estimated Start Date: August 13, 2018 as stated by Mr. Wisniewski.
Completion Date: February 2, 2019 (includes vegetation)
Liquidated Damages: $200.00 per calendar day
Intermediate Contract Time Number t:
Date of Availability: August 6, 2018
Mailing Address: Telephone: (252) 830-3495
NC DEPARTMENT OF TRANSPoRTATION F'as: (252) 830-8556
GREENVILLERESIDENTENGINEERSOFFICE CusromerService: 1-877-368-4968
P.O. BOX 1587
GREENVILLE, NC 2783 5-1 5 87 Websile: www.ncdoLgov
Loca(ion:
1710 N. MEMORIAL DRIVE
GREENVILLE,NC 27834
DB00408
Page 2 of 4
July 26, 2018
Completion Date (other than vegetation): November 4, 2018
Liquidated Damages: $600.00 per calendaz day
Contract Review
• Major Contract Items: Line Item No. 80 Prestressed Concrete Cored Slabs
• Specialty Items: Line Item Nos.: 30-34 Guardrail; 38-62 Erosion Control and 63 Reforestation
• Fuel Price Adjustment: Base index price for Diesel #2 Fuel is $2.0070 per gallon
• The DBE Goal was met at 7% with Florence Concrete Products.
• Cooperation Behveen Contractors: NCDOT Traffic Services will supply signs and barricades. A one-week
notice to Traffic Services is required per Mrs. Lentine.
• Certified Erosion Control/Stormwater Officer documentation was submitted by Mr. Wisniewski as well as all
other DOT required submittals. Mc Beasley verified receipt of alI documents.
• Mrs. Lentine advised no borrow pits aze listed on the contract but should it be needed advanced notice is
required and must come from a commercial pit.
• Lump Sum Grading is required with this conffact per Mrs. Lentine.
• Contract Addendum 2 decreased the base price for asphalt binder for plant mix from $430.45 per ton to
$429.00 perton.
• Relocation of Existing Gate in accordance with plans was discussed by Mrs. Lentine and verification of that
plan was given by Mr. Reeves.
• Safety Fence and Jurisdictional flagging is required due to the wetlands per Mrs. Lentine.
• Native Grass Seeding and Mulching shall be performed on the disturbed areas of wetlands per Mrs. Lentine.
Mr. Blankenship added native seed mix is mainly used in wetlands. Mowing and maintenance areas use
permanent.
• Mrs. Lentine quoted Buffer and Stream Impacts in the Tar-Pamlico River Basin. Mr. Ward reviewed specific
conditions of certification.
No. 3: A dry work area shall be maintained to prevent direct contact with stream water during
construction if concrete is used.
No. 4: Highly visible fencing is required before any land disturbance at the outside buffer, wetland or
water boundary.
No. 5: No staging of equipment is permitted in the water or buffers during consWction.
No. 6: Contamination prevention is required by regulazly inspecting mechanized equipment to avoid
fluid spills when operating near surface water.
No. 9: Erosion and sediment control practices must be in compliance per Mr. Ward.
No. 11: Nylon Mesh Matting must not be used within 25 feet from top of stream bank for erosion
control.
No. 12: All erosion control devices mus[ be removed within two months of DLR area release.
No. 17: The bridge demolition must be accomplished in strict compliance with the most recent version
ofNCDOT's Best Management Practices for Construction and Maintenance Activities.
No. 23: Drilling or driving within the srream channel, stream bank or within 5 feet of the top of bank
requires a turbidity curtain. Mr. Reeves stated there is one interior bent.
No. 28: Riparian azeas within the construction limits requires aative vegetation by the end of the
growing season following completion of construction.
No. 29: Dischazging Hydroseed mixtures adjacent to surface waters is strictly prohibited.
No. 30: All activities must comply with the State water quality standards of the Clean Water Act or
the NCDWR may reevaluate and modify the certification.
DB00408
Page 3 of 4
July 26, 2018
No. 31: Any violation should be reported to the Division of Water Resources within 24 hours of
discovery.
No. 32: Upon project completion, the NCDOT Division Engineer shall completed and retum the
"Certification of Completion Form" to notify NCDWR.
No. 33: A copy of Water Quality Certification should be maintained on the construction site at all
times.
Mr. Ward stated stormwater pertnit compliance is required which would include weekly monitor forms, inspection
forms, temporary stabilization requirements and covering of stockpiled materials. Mc Reeves stated mailboxes and
rain gauges will be on-site.
General Discussion
Mr. Reeves reassured Mc Blankenship no gravel would be used in driveways. Mr. Blankenship stated no gravel can be
used within the buffer zone.
Mrs. Lentine questioned what would be used for the laydown area. Mr. Reeves responded, laydown area would be the
road iuelf behind the crane.
Per Mr. Blankenship, the contractor was advised not to go beyond the hatched area or permitted buffer. The safety
fence needs to be brought to the access drive.
Mr. Reeves requested that dirt removed during bridge construction be taken to the local DOT yard for storage. Mrs.
Lentine requested Pitt Co. Maintenance be notified for approval. Mr. Beasley agreed to check with maintenance about
storing excavated material.
M& J Seeding will be responsible for erosion control and seeding per Mr. Reeves.
Mrs. Lentine stated this project is federally funded with a special provision for the Davis-Bacon Act. However,
certified payroll is not required because of project being on local roads. Minimum wage rates do apply per Mrs.
Lentine.
Mr. Wisniewski estimated a construction time of 12 %, - 13 weeks for compietion.
Mr. Wisniewski requested Mr. Blankenship, Mr. Reeves and Mr. Peasley meet on Monday, August 13'h for stakeout.
There being no further business, the meeting was adjoumed.
These minutes are prepazed as they aze dowmented. Any discrepancies with the content of these minutes should be
submitted in writing to this office within 7 days of receipt. Failure to do so will be an indication of agreement.
MINUTES PREPARED BY:
j� G��%�
�" L�
Beverly Daniels, Administrative Specialist I
DB00408
Page 4 of 4
July 26, 20t8
MINUTES SUBMITTED BY:
o��� �r
��
&17672857F8[Y152...
Coaus�Ma uy:
ador.� �apr��,
87F75258T1534D7...
Sarah Lentine, Resident Engineer
MINi1TE5 APPROVED BY:
DocuSigned by:
923D84A7CB054A5...
T.A. Loving Company
Attachment: (At#endance Roster}
EC: Cadmus Capehart, PE
Jason Beasley, Sr. Asst. Res/ Engineer
Meeti�g Attendees (wlAttachments)
Shareplus {w/Attachments)