Subject HI -SPOT ESTIMATE - BOILER #1
THIS ESTIMATE IS FOR THE CONSTRUCTION SUPPORT PORTION
OF THE UPCOMING NO. 1 BOILER TUBE REPLACEMENT.
SITE ENGINNERING
*SKETCH AND MTO AS NEEDED
LABOR & IFC: $ 2,410.00 ( 60 HRS)
MECHANICAL PORTION
*REMOVE AND REINSTALL SOOT BLOWERS AND BOILER BREECHING
*REMOVE AND REINSTALL PLATFORMS AND LADDERS
*REMOVE AND REINSTALL BOILER SKIN AND SUPPORT FRAME
(REPLACE DAMAGED PORTIONS AS NEEDED)
*REMOVE AND REINSTALL PIPING (REPLACE DAMAGED PIPING AS
NEEDED)
LABOR & IFC: $ 19,605.00 (610 HRS)
FIELD MAT'L: $ 5,000.00
TOTAL: $ 24,605.00
CIVIL PORTION
*BUILD AND REMOVE SCAFFOLDING AS NEEDED
*REMOVE AND REPLACE BATT INSULATION
*INSTALL REFRACTORY @ SOOT BLOWERS
*SANDBLAST AND PRIME OUTER SKIN AND FRAME
*MISC TOUCH-UP PAINTING AS NEEDED
*UNLOAD, COVER AND PROTECT NEW BOILER TUBES FROM DAMAGE
*CRANE / OPERATOR AS NEEDED
LABOR & IFC:
FIELD MAT'L:
TOTAL:
ELECTRICAL PORTION
$ 14,168.00 (440 HRS)
$ 4,000.00
$ 18,168.00
*PROVIDE T / C POWER AND LIGHTS
*DISCONNECT / RECONNECT POWER / SIGNAL WIRING AS NEEDED
_'17
.za �7,
LABOR & IFC: $ 2,876.00 (100 HRS)
FIELD MAT'L: $ 1,000.00 C `T
TOTAL: $ 3,876.00 �--
DEQ-CFW 00087449
ESTIMATE SUMMARY
LABOR & IFC: $ 39,059.00
FIELD MAT'L: $ 10,000.00
SUB -TOTAL: $ 49,059.00
PREMIUM TIME ALLOWANCE: $ 7,500.00
CONTINGENCY (10%): $ 5,000.00
TOTAL: $ 61,559.00
DEQ-CFW 00087450