HomeMy WebLinkAboutDEQ-CFW_00067538ea-
PAT MCCRORY
Governor
i.a
Air Quality
ENVIRONMENTAL QUALITY
January 19, 2016
Mr. Ellis McGaughy, Plant Manager
Chemours Company - Fayetteville Works
22828 NC Highway 87 West
Fayetteville, NC 28306
SUBJECT: 'Title V Annual Compliance Certification
Chemours Company - Fayetteville Works
Fayetteville, Bladen County
Facility ID: 0900009; Permit No. 03735T41
Dear Mr. McGaughy:
DONALD R. VAN DER VAART
Secretary
SHEILA C. HOLMAN
Director
Our records indicate that Chemours Company - Fayetteville Works, Fayetteville, Bladen County, has been
issued a Title V Permit, which requires the submittal of an annual compliance certification (ACC) each year by the
date specified in General Condition 3.P. of your Title V Permit. The ACC must be signed by a responsible
official (as defined under 40 CFR 70.2), and signed copies must be submitted to the following:
a. Two copies to the Fayetteville Regional Office of the Division of Air Quality (DAQ) at:
Systel Building, 225 Green Street, Suite 714, Fayetteville, North Carolina 28301-5094
b. One copy to the EPA at:
Air and EPCRA Enforcement Branch, EPA, Region 4, 61 Forsyth Street SW, Atlanta, GA 30303
We recommend that, as a minimum, you send the ACC to the EPA via certified mail.
The DAQ has developed forms that meet the requirements for the ACC. The DAQ forms are available for
download on the DAQ web site (http-.Hwww.ncair.org/enf/certification/). Instructions and examples to assist you in
properly completing the DAQ forms are included within the compliance certification forms themselves. You may opt
to use the DAQ forms or you may supply the information required for compliance certification in your own format. If
you choose to use the DAQ forms, please note that these forms have been modified slightly from versions you have
used in previous years. The current version is Revision 3.0, as noted in the bottom right hand corner of the forms.
If you choose to use your own format, the compliance certification must include all the required information to
be considered complete. The required information is specified in the instruction section of the DAQ forms and is
also specified in General Condition 3.P. of your Title V Permit. Finally, please remember to include in your
ACC all deviations cited in any Notices of Violation or Notices of Deficiency issued to your company during
calendar year 2015.
If you have any questions with regard to the annual compliance certification, please do not hesitate to contact
Heather Carter at 910-433-3363.
Sincerely,
Steven E Vozzo, Regional Supervisor
Division of Air Quality, NCDEQ
cc: Fayetteville Regional Office Files
State of North Carolina I Environmental Quality I Air Quality
Fayetteville Regional Office I Systel Building, 225 Green Street, Suite 714 1 Fayetteville, NC 28301-5094
910 433 3300 T 1910 485 7467 F
DEQ-CFW 00067538
Mr. Ellis McGaughy
January 19, 2016
Page 2
P.S.- Permitting Procedures
DAQ has established two new procedures that allow Title V permit holders to expedite implementing changes
at their facilities. Both procedures, authorized under the Clean Air Act, allow changes to be made prior to
revising the Title V permit.
Minor Permit Modifications - Changes that qualify as "minor" still require a permit application,
however the change can be made immediately after the NCDAQ determines that your application
describing the change is complete. See 15A NCAC 2Q .0515 and
[http://daq.state.nc.us/permits/TV_minor_mod.shtml] for more information about what changes
qualify as "minor."
Off Permit 502(b)(10) Changes - Changes that qualify as "502(b)(10)" can be made seven (7) days
after notification (no application needed) to the NCDAQ and the federal EPA. See 15A NCAC 2Q
.0523 and fhttp://daq.state.nc.us/permits/502b10.shtmll for more information about what changes
qualify as "502(b)(10)" and for the 502(b)(10) Notification Form.
DEQ-CFW 00067539