HomeMy WebLinkAbout20090705 Ver 1_Approval Letter_20090625A -X_ VA
NCDENR
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Beverly Eaves Perdue Coleen H. Sullins Dee Freeman
Governor Director Secretary
June 25, 2009
Mr. Gregory Bean, Directorate of Public Works
Fort Bragg
IMSE-BRG-PW, 2175 Reilly Road Stop A
Fort Bragg, NC 28310-5000
DWQ Project # 09-0705
Cumberland County
Subject Property: Fort Bragg - Perimeter Road Improvements 108`h ADA
Ut to Bones Creek [030615, 18-31-24-2, C]
Approval of 401 Water Quality Certification with Additional Conditions
Dear Mr. Bean:
You have our approval, in accordance with the attached conditions and those listed below, to place fill
within or otherwise impact 0.22 acres of 404/wetland, and 87 linear feet of perennial stream, as described
within your application dated June 4, 2009, and received by the N.C. Division of Water Quality (DWQ)
on June 17, 2009, to construct the proposed improvements to Perimeter Road at the site. After reviewing
your application, we have decided that the impacts are covered by General Water Quality Certification
Number(s) 3704 (GC3704). The Certification(s) allows you to use Nationwide Permit(s) NW14 when
issued by the US Army Corps of Engineers (USAGE). In addition, you should obtain or otherwise
comply with any other required federal, state or local permits before you go ahead with your project
including (but not limited to) Erosion and Sediment Control, Non-discharge, and other regulations. Also,
this approval to proceed with your proposed impacts or to conduct impacts to waters as depicted in
your application shall expire upon expiration of the 404 or CAIVIA Permit.
This approval is for the purpose and design that you described in your application. If you change your
project, you must notify us and you may be required to send us a new application. If the property is sold,
the new owner must be given a copy of this Certification and approval letter and is thereby responsible for
complying with all conditions. If total fills for this project (now or in the future) exceed one acre of
wetland or 150 linear feet of stream, compensatory mitigation may be required as described in 15A
NCAC 2H.0506 (h). This approval requires you to follow the conditions listed in the attached
certification and any additional conditions listed below.
The Additional Conditions of the Certification are:
Conditions of Certification:
1. Impacts Approved
The following impacts are hereby approved as long as all of the other specific and general
conditions of this Certification (or Isolated Wetland Permit) are met. No other impacts are
approved including incidental impacts:
401 Oversight/Express Review Permitting Unit
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
Location: 2321 Crabtree Blvd., Raleigh, North Carolina 27604
Phone: 919-733-17861 FAX: 919-733-6893
Internet: http://h2o.enr.state.nc.us/ncwetlands/
NorthCarohna
Naturally
An Equal Opportunity 1 Affirmative Action Employer
Fort Bragg
Page 2 of 4
June 25, 2009
Type of Impact Amount Approved nits Plan Location or Reference
404/Wetland 0.22 (acres) PCN page 4 of 10
Stream - perennial 87 (linear feet) PCN page 4 of 10
Sediment and Erosion Control:
2. Erosion and sediment control practices must be in full compliance with all specifications governing
the proper design, installation and operation and maintenance of such Best Management Practices in
order to protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed, installed,
operated, and maintained in accordance with the most recent version of the North Carolina
Sediment and Erosion Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control
measures must be such that they equal, or exceed, the requirements specified in the most
recent version of the North Carolina Sediment and Erosion Control Manual. The devices
shall be maintained on all construction sites, borrow sites, and waste pile (spoil) projects,
including contractor-owned or leased borrow pits associated with the project.
c. Sufficient materials required for stabilization and/or repair of erosion control measures and
stormwater routing and treatment shall be on site at all times.
3. No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas beyond the
footprint of the impacts depicted in the 404/401 Permit Application. All construction activities,
including the design, installation, operation, and maintenance of sediment and erosion control Best
Management Practices, shall be performed so that no violations of state water quality standards,
statutes, or rules occur;
Sediment and erosion control measures shall not be placed in wetlands or waters without prior approval
from the Division. If placement of sediment and erosion control devices in wetlands and waters is
unavoidable, design and placement of temporary erosion control measures shall not be conducted in a
manner that may result in dis-equilibrium of wetlands or stream beds or banks, adjacent to or upstream
and down stream of the above structures. All sediment and erosion control devices shall be removed
and the natural grade restored within two (2) months of the date that the Division of Land Resources or
locally delegated program has released the project;
5. Protective Fencing - The outside buffer, wetland or water boundary and along the construction corridor
within these boundaries approved under this authorization shall be clearly marked with orange warning
fencing (or similar high visibility material) for the areas that have been approved to infringe within the
buffer, wetland or water prior to any land disturbing activities to ensure compliance with 15 NCAC 2H,
Section .0500;
6. Culvert Installation
All work in or adjacent to stream waters shall be conducted in a dry work area. Approved BMP
measures from the most current version of NCDOT Construction and Maintenance Activities manual
(http://www.ncdot.org/doh/operations/BMP manual/download/BMP Manual.pdf)
such as sandbags, rock berms, cofferdams and other diversion structures shall be used to prevent
excavation in flowing water.
Culverts required for this project shall be installed in such a manner that the original stream profiles
are not altered. Existing stream dimensions (including the cross section dimensions, pattern, and
longitudinal profile) must be maintained above and below locations of each culvert. Culverts shall
Fort Bragg
Page 3 of 4
June 25, 2009
be designed and installed to allow for aquatic life movement as well as to prevent head cutting of
the streams. If any of the existing pipes are or become perched, the appropriate stream grade shall
be re-established or, if the pipes installed in a perched manner, the pipes shall be removed and re-
installed correctly.
Culvert(s) shall not be installed in such a manner that will cause aggradation or erosion of the
stream up or down stream of the culvert(s). Existing stream dimensions (including the cross section
dimensions, pattern and longitudinal profile) shall be maintained above and below locations of each
culvert.
Placement of culverts and other structures in waters, streams, and wetlands must be placed below
the elevation of the streambed by one foot for all culverts with a diameter greater than 48 inches,
and 20 percent of the culvert diameter for culverts having a diameter less than 48 inches, to allow
low flow passage of water and aquatic life. Design and placement of culverts and other structures
including temporary erosion control measures shall not be conducted in a manner that may result in
dis-equilibrium of wetlands or streambeds or banks, adjacent to or upstream and down stream of the
above structures. The applicant is required to provide evidence that the equilibrium shall be
maintained if requested in writing by DWQ.
The establishment of native, woody vegetation and other soft stream bank stabilization techniques
must be used where practicable instead of rip rap or other bank hardening methods. If rip-rap is
necessary, it shall not be placed in the stream bed, unless specifically approved by the Division of
Water Quality.
Installation of culverts in wetlands must ensure continuity of water movement and be designed
to adequately accommodate high water or flood conditions.
Upon completion of the project, the Applicant shall complete and return the enclosed "Certificate of
Completion" form to notify NCDWQ when all work included in the 401 Certification has been
completed. The responsible party shall complete the attached form and return it to the
401/Wetlands Unit of the NC Division of Water Quality upon completion of the project. Please
send photographs upstream and downstream of each culvert site to document correct installation
along with the Certificate of Completion form.
Certificate of Completion:
7. Upon completion of all work approved within the 401 Water Quality Certification or applicable
Buffer Rules, and any subsequent modifications, the applicant is required to return the attached
certificate of completion to the 401/Wetlands Unit, North Carolina Division of Water Quality,
1650 Mail Service Center, Raleigh, NC, 27699-1650.
Also, this approval to proceed with your proposed impacts or to conduct impacts to waters as
depicted in your application shall expire upon expiration of the 404 or CAMA Permit.
Violations of any condition herein set forth may result in revocation of this Certification and may result in
criminal and/or civil penalties. The authorization to proceed with your proposed impacts or to conduct
impacts to waters as depicted in your application and as authorized by this Certification shall expire upon
expiration of the 404 or CAMA Permit.
If you do not accept any of the conditions of this Certification (associated with the approved wetland or
stream impacts), you may ask for an adjudicatory hearing. You must act within 60 days of the date that
you receive this letter. To ask for a hearing, send a written petition, which conforms to Chapter 150B of
Fort Bragg
Page 4 of 4
June 25, 2009
the North Carolina General Statutes to the Office of Administrative Hearings, 6714 Mail Service Center,
Raleigh, N.C. 27699-6714. This certification and its conditions are final and binding unless you ask for a
hearing.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water
Act. If you have any questions, please telephone Cyndi Karoly or Ian McMillan in the Central Of ice in
Raleigh at 919-733-1786 or Lauren Witherspoon in the DWQ Raleigh Regional Office at 9194200.
CHS/gym
Enclosures: GC3704
Certificate of Completion
Sincerely,
9L?? Teen H. Sullins
cc: Ken Averitte, DWQ Fayetteville Regional Office
USACE Wilmington Regulatory Field Office
DLR Fayetteville Regional Office
File Copy
Michael O'Rouke, The Louis Berger Group, 101 Wade Avenue, Suite 400, Raleigh, NC 27605
Filename: 090243FortBraggPerimeterRdlmprovements l O8thADA(Cumberland)401