HomeMy WebLinkAbout20140341 Ver 1_Email_20140311Wainwright, David
From:
Sent:
To:
Cc:
Subject:
David,
DeCola, Richard <Richard.DeCola@rsandh.com>
Tuesday, March 11, 2014 1:34 PM
Wainwright, David; King, Art C; Sarah.E.Hair@usace.army.mil
Bollinger, Richard; 'Chris Powers'
RE: Emailing: 17BP.8.R.57 Bridge 750029
Please see below for responses to your questions. If you have any particular concern or want to discuss this mat[er any further,
please feel free to contact me.
Thanks,
Rick DeCola
Rick DeCola, PE
Roadway Engineer
8601 Six Forks Rd, Suite 260
Raleigh, NC 27615
Phone: 919-926�104
mailto:Directorv. Sender.mail
Visit our website at httF
Connect with RS&H on
-----Original Message-----
From: King, Art C [mailto:ackinR@ncdot.Qov]
Sent: Thursday, March 06, 2014 3:16 PM
To: DeCola, Richard
Subjed: FW: Emailing:l7BP.8.R.57 Bridge 750029
FYI
-----Original Message----
From: Wainwright, David
Sent: Thursday, March 06, 2014 2:53 PM
To: King, Art C; Hair, Sareh E SAW (Sarah.E.HairCdusace.armv.mil)
Subject: RE: Emailing:l7BP.8.R.57 Bridge 750029
Art,
httos://twitter.com/wearersand h
I have looked over the plans and information you sent for this projec[. I have a few questions:
- How long will the causeway need to be in place?
• The ICT for this project is 180 days and the causeway will be in place for the majority of this time, approximately 5
months. This is due to the need for the causeway in removal of exis[ing bents, drilling and construction of the proposed
bent and setting of the box beams.
7he causeway appears to be blocking the whole river, correct?
This is correct. Due to the steep river banks, using this causeway is the only way to access [he south side for
construction. While we acknowledge that placing [he causeway throughout the entire width of the river is not optimal, this
was the only solution in order to replace the deficient structure. During the design process, there were discussions at
length with Division 8 without a viable alternative to this causeway.
- How confident are you that 4@48" will be ample to handle higher flows in the river?
• The scenario shown on the permit drawings was modeled in HEC-RAS under the normal high water condition. The spillway
area was provided to assist with higher flows.
- I notice there is a spillway incorporeted into the causeway, which dips about 2.5' below the aMual work pad. Is the purpose of the
spillway to allow water to flow over it when the water level rises7 If so, will this not potentially trep equipment on the work pad?
As stated above, the purpose of the spillway is to assist with higher flows. The contractor is aware of the risk in using a
causeway for construction, and will remove equipment from the causeway as it becomes necessary.
- How will the rock placed for the causeway be kept from being carried away during higher flow events? How would this be cleaned
up if rock does move from the causeway and off the fabric?
• There is no guarantee tha[ rock will not be carried away during higher flow events, as that is an inherent risk with using
causeways. The contractor will make every effort to dean up any rock that is displaced. It should be noted that this
channel is currently full of rock and there are several rock dams just downstream of the bridge site.
- - -- - - -- - • �- • =- ' --= _- .. . . -- -
-- - - •- -- �--- - -- - -•�� -•� � •-
Thanks,
David
-----Original Message-----
From: King, Art C
Sent: Tuesday, March 04, 2014 9:08 AM
To: Hair, Sareh E SAW (Sareh.E.HairCqlusace.armv.mil�; Wainwright, David
Subject: FW: Emailing: 176P.8.R.57 Bridge 750029 Permit Review 02-24-2014.zip, DWQ contacts _310612.pdf
Importance: High
Liz, David,
The attached zip file contains information related to project 17BP.8.R.57 , Bridge ri29 in Randolph County.
This is a discussion I had started with Ronnie Smith severel months ago about the need to install a large causeway on this project to
gain access to one side of the stream. Liz; Ronnie should have some information and pictures that I sent to him on file.
7here is a high, sheer rock face at the south end bent that makes accessed from that side by equipment nearly impossible, without a
drastic removal of the rock, which would no doubt include extensive blasting. Due to the structure and size of the existing bridge it is
necessary to use heavy equipment to both remove the existing bents, and to drill and install the end bent and center bent for the
new bridge. Ronnie had tentatively agreed to this approach but was waiting to see the structure design, the causeway design, and
Hec-Ras data that is included in the zip file.
: ��
This causeway is needed in order for us to replace the existing structure, and to bring the bridge up to current safety standards. The
material used to construct the causeway will be placed on fabric and removed completely at the end of the project. We would like
to construct this bridge replacement under NWP#3.
Please let me know if you have difficulty with the zip file.
Thanks,
Art King
Subject: Emailing: 176P.8.R.57 Bridge 750029 Permit Review 02-24-2014.zip, DWQ contacts _110612.pdf
17BP.8.R.57 Bridge 750029 Permit Review 02-24-2014.zip DWQ contacts _110612.pdf
Note: To protect against computer viruses, e-mail programs may prevent sending or receiving certain types of file
attachments. Check your e-mail security settings to determine how attachments are handled.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.