HomeMy WebLinkAbout20180630 Ver 1_More Info Received_20180618Goss, Stephanie
,From: Goss, Stephanie'
.Sent: Friday, June 15, 2018 1:57 PM
To: 'Eric Kulz'
Subject: Crabtree Creek Interceptor
Eric;
Ca'n,you please provide the -following information for the above referenced project:
® The buffer -and stream impacts requested in this application need to be clearly shown and enumerated
on the site plan. These impacts need to correspond to the impacts requested in the application. The
labels on the site ,plan must match the impacts listed in the application. As the application and impact
map currently stands; it isnot possible to match up what is listed the application with the site
plan. [15A NCAC 0214.0502(g)]
Thanks!
Stephanie Z. Goss ,
Environmental Senior. Specialist
Division of Water, Resources
Raleigh Regional Office
3800 Barrett Drive
Raleigh, NC 27609
919-791-4256
E-mail'correspondence to and from this address may be subject to the
North Carolina Public Records Law- and may be disclosed to third parties
1
TOE OF,
2' HORIZONTAL 1 } \ EMBANKMENT'
s - RIPRAP APRON
f
=, II
r CLASS 'B* RIPRAP 1 1
t:•- (MIN 18" THICK)
S co
N
/ GRAPH C CALE /
CUT BACK BANK AT 6:1 SLOPE TO 20 / 0 0 z0 / / 40
PROVIDE SLOPING POINT BAR
1 inch = 20 Ft 1
GRADE BACK CHANNEL BANKS AT
MIN 2:1 SLOPES
r �
2q1-
1 Rte 00
C-9 I �^
l i Li .
EXISTING GRADE
2:1 SLOPE
CLASS '8' RIP ----FILTER FABRIC
X=MANTPJN EXISTING
CHANNEL INVERT
TYPICAL CHANNEL RIPRAP PLACEMENT PROFILE
CLASS
NOT TO SCALE
CHANNEL POINT BAR RIPRAP PLACEMENT PROFILE
NOT TO SCALE
IFCRABTREE CREEK I— 90 DEGREE BEND ARMORING III ;�WithersRavenet JI
GREENWAY Engineers I Planners I Surveyors
... _ 115 MacKenan Drive I Cary. NC 27511) c 919.469.3340 I I'Kense 8:6-0832 I w .vdthersravenelxom