HomeMy WebLinkAbout20080867 Ver 2_Approval Letter_20090430I; IVA
A NCDEX_ WA
NR
North Carolina Department of Environment and Natural Resources
Division of Water Quality
Beverly Eaves Perdue Coleen H. Sullins Dee Freeman
Governor Director Secretary
April 30,2009
DWQ Project # 08-0867, Ver. 2
Johnston County
Mr. Michael Coates
Mr. Daniel Coates
Crossroads Development Company
12400 NC Highway 50 North
Willow Spring, NC 27592
Subject Property: Millstone Ridge Subdivision
Ut to Hooks Branch - Black Creek [030404, 27-45-4, C, NSW]
Approval of 401 Water Quality Certification and Authorization Certificate per the Neuse River Buffer
Protection Rules (15A NCAC 2B.0233) with Additional Conditions
Gentlemen:
You have our approval, in accordance with the attached conditions and those listed below, to place fill within or
otherwise impact 0.222 acres of 404/wetland, 107 linear feet of perennial stream, and 5,750 square feet of Zone
1 Neuse River basin protected riparian buffers and 2,446 square feet of Zone 2 Neuse River basin protected
riparian buffers, as described in your application dated May 20, 2008, and received by the Division of Water
Quality (DWQ) on November 25, 2008, with additional information received from you on February 12, 2009,
and April 24, 2009, to construct the proposed residential development at the site. After reviewing your
application, we have decided that the impacts are covered by General Water Quality Certification Number(s)
3705 (GC3705). The Certification(s) allows you to use Nationwide Permit(s) NW29 when issued by the US
Army Corps of Engineers (USACE). In addition, you should obtain or otherwise comply with any other
required federal, state or local permits before you go ahead with your project including (but not limited to)
Erosion and Sediment Control, and Non-discharge regulations. Also, this approval to proceed with your
proposed impacts or to conduct impacts to waters as depicted in your application shall expire upon
expiration of the 404 or CAMA Permit.
This approval is for the purpose and design that you described in your application. If you change your project,
you must notify us and you may be required to send us a new application. If the property is sold, the new owner
must be given a copy of this Certification and approval letter and is thereby responsible for complying with all
conditions. If total fills for this project (now or in the future) exceed one acre of wetland or 150 linear feet of
stream, compensatory mitigation may be required as described in 15A NCAC 2H.0506 (h). This approval
requires you to follow the conditions listed in the attached certification and any additional conditions
listed below.
The Additional Conditions of the Certification are:
1. Impacts Approved
401 Oversight/Express Review Permitting Unit
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
Location: 2321 Crabtree Blvd., Raleigh, North Carolina 27604
Phone: 919-733-17861 FAX: 919-733-6893
Internet: http://h2o.enr.state.nc.us/ncwetlands/
NorthCarolina
Awmallty
An Equal Opportunity l Affirmative Action Employer
Crossroads Development Company
Page 2 of 5
April 30, 2009
The following impacts are hereby approved as long as all of the other specific and general conditions of
this Certification (or Isolated Wetland Permit) are met. No other impacts are approved including
incidental impacts:
Type of Impact Amount Approved nits Plan Location or Reference
404/Wetland 0.222 (acres) PCN page 9 of 15
Stream - perennial 107 linear feet) PCN pages 10 of 15
Buffers Zone 1 5,750 (square ft. PCN page 13 of 15
Buffers Zone 2 2,446 (square ft.) PCN page 13 of 15
2. No Waste, Spoil, Solids, or Fill of Any Kind
No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas beyond the
footprint of the impacts depicted in the Pre-Construction Notification. All construction activities,
including the design, installation, operation, and maintenance of sediment and erosion control Best
Management Practices, shall be performed so that no violations of state water quality standards, statutes,
or rules occur.
3. Erosion and sediment control practices must be in full compliance with all specifications governing the
proper design, installation and operation and maintenance of such Best Management Practices in order to
protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed, installed, operated,
and maintained in accordance with the most recent version of the North Carolina Sediment and
Erosion Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures
must be such that they equal, or exceed, the requirements specified in the most recent version of
the North Carolina Sediment and Erosion Control Manual. The devices shall be maintained on all
construction sites, borrow sites, and waste pile (spoil) projects, including contractor-owned or
leased borrow pits associated with the project.
c. Sufficient materials required for stabilization and/or repair of erosion control measures and
stormwater routing and treatment shall be on site at all times.
4. Sediment and Erosion Control Measures
Sediment and erosion control measures shall not be placed in wetlands or waters without prior approval
from the Division. If placement of sediment and erosion control devices in wetlands and waters is
unavoidable, design and placement of temporary erosion control measures shall not be conducted in a
manner that may result in dis-equilibrium of wetlands or stream beds or banks, adjacent to or upstream
and down stream of the above structures. All sediment and erosion control devices shall be removed and
the natural grade restored within two (2) months of the date that the Division of Land Resources or locally
delegated program has released the project;
5. Culvert Installation
All work in or adjacent to stream waters shall be conducted in a dry work area. Approved BMP measures
from the most current version of NCDOT Construction and Maintenance Activities manual
(http://www.nedot.org,/doh/operations/BMP manual/downloadBMP Manual.pdf)
such as sandbags, rock berms, cofferdams and other diversion structures shall be used to prevent excavation
in flowing water.
Crossroads Development Company
Page 3 of 5
April 30, 2009
Culverts required for this project shall be installed in such a manner that the original stream profiles are
not altered. Existing stream dimensions (including the cross section dimensions, pattern, and
longitudinal profile) must be maintained above and below locations of each culvert. Culverts shall be
designed and installed to allow for aquatic life movement as well as to prevent head cutting of the
streams. If any of the existing pipes are or become perched, the appropriate stream grade shall be re-
established or, if the pipes installed in a perched manner, the pipes shall be removed and re-installed
correctly.
Culvert(s) shall not be installed in such a manner that will cause aggradation or erosion of the stream up
or down stream of the culvert(s). Existing stream dimensions (including the cross section dimensions,
pattern and longitudinal profile) shall be maintained above and below locations of each culvert.
Placement of culverts and other structures in waters, streams, and wetlands must be placed below the
elevation of the streambed by one foot for all culverts with a diameter greater than 48 inches, and 20
percent of the culvert diameter for culverts having a diameter less than 48 inches, to allow low flow
passage of water and aquatic life. Design and placement of culverts and other structures including
temporary erosion control measures shall not be conducted in a manner that may result in dis-
equilibrium of wetlands or streambeds or banks, adjacent to or upstream and down stream of the above
structures. The applicant is required to provide evidence that the equilibrium shall be maintained if
requested in writing by DWQ.
The establishment of native, woody vegetation and other soft stream bank stabilization techniques must
be used where practicable instead of rip rap or other bank hardening methods. If rip-rap is necessary, it
shall not be placed in the stream bed, unless specifically approved by the Division of Water Quality.
Installation of culverts in wetlands must ensure continuity of water movement and be designed to
adequately accommodate high water or flood conditions.
Upon completion of the project, the Applicant shall complete and return the enclosed "Certificate of
Completion" form to notify NCDWQ when all work included in the §401 Certification has been
completed. The responsible party shall complete the attached form and return it to the 401/Wetlands
Unit of the NC Division of Water Quality upon completion of the project. Please send photographs
upstream and downstream of each culvert site to document correct installation along with the
Certificate of Completion form.
6. Diffuse Flow (DWQ Reviewed Plans)
All stormwater shall be directed as diffuse flow at non-erosive velocities through the protected stream
buffers and will not re-concentrate before discharging into the stream as identified within 15A NCAC
2B .0233 (5)
In an effort to comply with the diffuse flow provision of the Buffer Rule (15A NCAC 02B .0233(5)),
you have provided the DWQ with level spreader designs received by the DWQ on April 24, 2009. The
DWQ believes that if implemented, as per these plans, diffuse flow will be achieved. However, if
diffuse flow as per 15A NCAC 02B .0233(5) is not achieved, then the DWQ shall be notified and
corrective actions to restore diffuse flow shall be taken if necessary to impede the formation of erosion
gullies. At no time shall stormwater from the proposed development be piped directly through the
buffer without prior DWQ written authorization.
The structural stormwater practices as approved by this Office as well as drainage patterns must be
maintained in perpetuity. No changes to the structural stormwater practices shall be made without
written authorization from the Division of Water Quality. Stormwater easements shall be recorded for a
distance of at least 10 feet on each side of all stormwater conveyances on all lots containing these
Crossroads Development Company
Page 4 of 5
April 30, 2009
structures including future access for maintenance. The stormwater easements shall allow for the
ability to maintain the structures, perform corrective actions as described above and shall provide
protection of the structures from potential alternations by future property owners.
An Operation & Maintenance (O&M) agreement signed by the current landowner must be approved by
the DWQ. This O&M agreement must transfer with the sale of the land or transfer of responsibility for
the stormwater facilities and the DWQ must be notified of every transfer.
7. Protective Fencing
The outside buffer, wetland or water boundary and along the construction corridor within these
boundaries approved under this authorization shall be clearly marked with orange warning fencing (or
similar high visibility material) for the areas that have been approved to infringe within the buffer,
wetland or water prior to any land disturbing activities;
8. Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer
Rules, and any subsequent modifications, the applicant is required to return the attached certificate of
completion to the 401 Oversight/Express Review Permitting Unit, North Carolina Division of Water
Quality, 1650 Mail Service Center, Raleigh, NC, 27699-1650.
Violations of any condition herein set forth may result in revocation of this Certification and may result in
criminal and/or civil penalties. The authorization to proceed with your proposed impacts or to conduct impacts
to waters as depicted in your application and as authorized by this Certification, shall expire upon expiration of
the 404 or CAMA Permit.
If you do not accept any of the conditions of this Certification (associated with the approved wetland or stream
impacts), you may ask for an adjudicatory hearing. You must act within 60 days of the date that you receive
this letter. To ask for a hearing, send a written petition, which conforms to Chapter 150B of the North Carolina
General Statutes to the Office of Administrative Hearings, 6714 Mail Service Center, Raleigh, N.C. 27699-
6714. This certification and its conditions are final and binding unless you ask for a hearing.
Any disputes over determinations regarding this Authorization Certificate (associated with the approved buffer
impacts) shall be referred in writing to the Director for a decision. The Director's decision is subject to review
as provided in Articles 3 and 4 of G.S. 150B.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water Act and
the Neuse riparian buffer protection rule as described within 15A NCAC 213 .0233. If you have any questions,
please telephone Cyndi Karoly or Ian McMillan at 919-733-1786. A ??
Since ,
G
Coleen H. Sullins
CHS/gym
Enclosures: GC3705
Certificate of Completion
Crossroads Development Company
Page 5 of 5
April 30, 2009
cc: USACE Raleigh Regulatory Field Office
Lauren Witherspoon, DWQ Raleigh Regional Office
DLR Raleigh Regional Office
File Copy
Daniel J. Bliley, Daniel J. Bliley Soil & Land Use Consultant, Inc., 614 South Second Street, Smithfield,
NC 27577
Filename: 080867 Ver2MillstoneRidgeSD(Johnston)401 _NBR