April 2, 2009
CERTIFIED MAIL:
#7007 3020 0001 8861 9152
Inner Banks Development, LLC.
Attn: Zane Buckman
206 Crescent Drive
Windsor, NC 27983
DWQ Project # 08-1775 vs 2
Beaufort County
Subject Property: Shady Shores
UT to Pamlico River, Tar-Pamlico Basin, 030407, SC, NSW
REQUEST FOR MORE INFORMATION
Dear Mr. Buckman:
On March 17, 2009, the Division of Water Quality (DWQ) received your application
dated March 2, 2009 to impact 1.03 acres of waters, 0.092 acres of wetlands, 3011.02
square feet (ft) of Zone 1 protected riparian buffers and 2040.39 square feet (ft) of Zone
2 protected riparian buffers for the purpose of developing a 27 lot subdivision on the
subject property. The DWQ has determined that your application was incomplete and/or
provided inaccurate information as discussed below. Therefore, unless we receive the
additional information requested below, we will have to move toward denial of your
application as required by 15A NCAC 2H .0506 and 15A NCAC 2B .0259 (8) and will
place this project on hold as incomplete until we receive this additional information.
Please provide the following information so that we may continue to review your project.
Additional Information Requested:
1. Wetland Connectivity
Within your application you indicate that 1823.93 square feet of wetland fill will
be required to access lot 22. There is no indication of culvert placement to
North Carolina Division of Water Quality Internet: www.ncwaterquality.org
943 Washington Square Mall Phone: 252-946-6481
Washington, NC 27889 FAX 252-946-9215
An Equal Opportunity/Affirmative Action Employer - 50% Recycledl10% Post Consumer Paper
NorthCarohna
Naturally
Page 2 of 2
maintain wetland connectivity. Please provide information indicating an
appropriately sized culvert and engineered plans showing culvert placement.
2. Docking Facility
Within your application and project narrative a docking facility is indicated but no
facility is indicated on the associated project plan. Please provide information
indicating whether or not you intend to build such a facility or provide dockage on
the subject property.
Please respond in writing to the DWQ within four weeks of the date of this letter with the
requested information. If we do not hear from you within four weeks, we will assume that
you no longer want to pursue this project and we will consider the project as withdrawn.
This letter only addresses the application review and does not authorize any impacts to
wetlands, waters or protected buffers. Please be aware that any impacts requested within
your application are not authorized (at this time) by the DWQ. Please call Kyle Barnes
of the Washington Regional Office at 252-948-3917or Ian McMillan of the DWQ Central
Office at 919-733-1786 if you have any questions regarding or would like to set up a
meeting to discuss this matter.
Sincerely,
Coleen H. Sullins
cc: 401 Oversight/Express Permitting Unit
USACE Washington Regulatory Field Office
File Copy
CAMA: Doug Hugget/Morehead
CAMA, WaRO
Warren Eadus, Quible & Associatess, P.C.
PO Drawer 870, Kitty Hawk, NC 27949
Filename: 08-1775 vs2