Loading...
HomeMy WebLinkAbout20151209 Ver 2_Haywood 273 Percussive activity_20180221Haywood 273 Percussive Activities Some hoe-ram hammering of bedrock is anticipated to complete phase 2 of the culvert. There is shallow bedrock apparent in the vicinity of the phase 2 portion of the culvert. It is anticipated that this percussive activity will occur intermittently on 2-3 work days over a couple of weeks. But, this is difficult to estimate with any certainty due to variations in rock density and depth of bedrock. Pile driving is not expected.