Gene Renegar Conversation 2/2/2018
• Work will be done by land
• Construction access will minimize disturbance to vegetation and will not involve building a
temporary access road to the shoreline. Equipment will be driven around trees to avoid
damaging vegetation. A temporary access road will be required at shoreline.
• Shoreline will be graded back to re -slope the existing 4-6 foot overhanging bank. Trees and
vegetation will be removed 12' upslope from shoreline to do this work.
• Disturbed areas will be applied with weed mat, mulched, and replanted