HomeMy WebLinkAbout20140957 Ver 2_NC Contractor Yards_Fayetteville_ESCP_Compiled_20171208ATLANTIC COAST PIPELINE PROJECT CONTRACTOR YARDS - FAYETTEVILLE REGION CUMBERLAND COUNTY, NORTH CAROLINA EROSION & SEDIMENT CONTROL PLAN PROJECT CONTACTS 00" , i Dominion Energy CR) OWNER/APPLICANT DOMINION ENERGY TRANSMISSION, INC. 5000 DOMINION BOULEVARD GLEN ALLEN, VA 23060 PHONE: 804-335-4923 ERM NC, INC. CONSULTANT ERM NC, INC. LICENSE #F-1223 15720 BRIZHAM HILL AVENUE, SUITE 120 CHARLOTTE, NORTH CAROLINA 28277 SCOTT ROBINSON, PE 704-541-8345 scott.robinson@erm.com EXISTING INFORMATION SOURCES CONTOURS AND BASE MAP PROVIDED BY 13 CONSULTING, LLC WITH ADDITIONAL CONTOURS OBTAINED FROM THE USGS NATIONAL ELEVATION DATASET. PLAN REPRODUCTION WARNING THE PLANS HAVE BEEN CREATED ON 2411X361' SHEETS FOR REDUCTIONS, REFER TO GRAPHIC SCALE. THE PLANS HAVE BEEN CREATED FOR FULL COLOR PLOTTING, AND SET OF THE PLANS THAT IS NOT PLOTTED IN FULL COLOR SHALL NOT BE CONSIDERED ADEQUATE FOR CONSTRUCTION PURPOSES. ***WARNING"** INFORMATION MAY BE LOST IN COPYING AND/OR GRAY SCALE PLOTTING. NORTH CAROLINA SHEET INDEX LOCATION MAP • f •" 4 1 _ t4�•�__ f f �'� _ S"� se :}��. °C iS ' rr .4 ` I{I - W • r i • r • « - � T ,_ ; -• Yt, r rr �- • �-.r ' � - rM +2 � •�• •� i p �a ,.. �t � ± I1 { � � # � � r1� •�+; . y Fr.r• rye` .i .war.. rr i r .... �� � • s r S}• fM�• ' f ♦ x�+.{ y + i +..*����'♦r� it ! �! - �� yti M • h',•,r�ar i� f'R' —1 ��� f •� S • !r i• �T VVV w r � � _� _ . � 't i " ,A4 Its' ' ' 1� F Q a _ 4�,? iyr r . • i .—ALI •fir «r � r. :. r •'�.+rb � ' + r•j ' d +moi # jsr • `" $r I SHEETS oil " � �, �+• •5 ti• � �.�-~�- !��'--'moi• �y ''�'�• -+�' � ,•i }p r{ y? - - , - " !( r • t1. r�r„r' '+`?' rte• \ ` * iw : •+ ^''♦ate," y - "�''' -►� ,ti Lr. a _. -' % - •�.. TV 31 qf 00 `� it �I tiI s'`'••- �• a r �� � • .� 1 i •; � � r �r r fir• ..rte+ .. - . r •^- ;+*�,' ate!' :. + •`' zo di ' rt� - + ,� � � � .� • fir' r3�� : � S � • ti • �� + *R� -' !. _ t IL �. -• - i*sicrdf�ury � � . .�.c `T -a,` - "� •� 4 4w pp i + Ldll{!' —� ' { ��71M ■+;moi' i■ c x 1a -3 _- A- . �!i�' y :� • +. 'fir ;�'-- of i..ii.7" •••TSSSYYY# ; � f M . . � a � � / `'1�iT1T�'9�[�t� � • t • -rte �� �} - .� r *•q6' !{ kcirt.. Locki Creek ` I♦ -0�• Ci1 •f�t L • ��lrf' 4- . �. 77f - T -+►. \ ' - 11` +'fin• . J ` / _Qyl �qp • * - = fir- •� k . = 1; = 2,000 FEET 1NHEN PRINTED FULL SIZE 1 08/04/2017 SHEET 1 - COVER SHEET 1* 1 08/04/2017 SHEET 2 - FAYETTEVILLE (SP10_CY SPR10-A) AERIAL OVERVIEW 0 1 08/04/2017 SHEET 3 - FAYETTEVILLE (SP10_CY SPR10-A) ESCP *1 1 08/04/2017 SHEET 4 - ESCP NOTES 0 1 08/04/2017 SHEET 5 - ESCP DETAILS *1 1 08/04/2017 SHEET 6 - ESCP DETAILS 1* 1 08/04/2017 SHEET 7 - ESCP DETAILS DRAWING INDEX LEGEND F FILLED CIRCLE INDICATES DRAWING INCLUDED WITHIN THIS ISSUE MOST RECENT REVISION NUMBER F MOST RECENT ISSUE OR REVISION DATE 6 - X/XX/201X SHEET X - SHEET TITLE LOCATION MAP • f •" 4 1 _ t4�•�__ f f �'� _ S"� se :}��. °C iS ' rr .4 ` I{I - W • r i • r • « - � T ,_ ; -• Yt, r rr �- • �-.r ' � - rM +2 � •�• •� i p �a ,.. �t � ± I1 { � � # � � r1� •�+; . y Fr.r• rye` .i .war.. rr i r .... �� � • s r S}• fM�• ' f ♦ x�+.{ y + i +..*����'♦r� it ! �! - �� yti M • h',•,r�ar i� f'R' —1 ��� f •� S • !r i• �T VVV w r � � _� _ . � 't i " ,A4 Its' ' ' 1� F Q a _ 4�,? iyr r . • i .—ALI •fir «r � r. :. r •'�.+rb � ' + r•j ' d +moi # jsr • `" $r I SHEETS oil " � �, �+• •5 ti• � �.�-~�- !��'--'moi• �y ''�'�• -+�' � ,•i }p r{ y? - - , - " !( r • t1. r�r„r' '+`?' rte• \ ` * iw : •+ ^''♦ate," y - "�''' -►� ,ti Lr. a _. -' % - •�.. TV 31 qf 00 `� it �I tiI s'`'••- �• a r �� � • .� 1 i •; � � r �r r fir• ..rte+ .. - . r •^- ;+*�,' ate!' :. + •`' zo di ' rt� - + ,� � � � .� • fir' r3�� : � S � • ti • �� + *R� -' !. _ t IL �. -• - i*sicrdf�ury � � . .�.c `T -a,` - "� •� 4 4w pp i + Ldll{!' —� ' { ��71M ■+;moi' i■ c x 1a -3 _- A- . �!i�' y :� • +. 'fir ;�'-- of i..ii.7" •••TSSSYYY# ; � f M . . � a � � / `'1�iT1T�'9�[�t� � • t • -rte �� �} - .� r *•q6' !{ kcirt.. Locki Creek ` I♦ -0�• Ci1 •f�t L • ��lrf' 4- . �. 77f - T -+►. \ ' - 11` +'fin• . J ` / _Qyl �qp • * - = fir- •� k . = 1; = 2,000 FEET 1NHEN PRINTED FULL SIZE w— -4 I f JL AL � s " I . # .I k% t-40 46 ■ Ir - 1 — • 410045701 GA \ G. OSTS \\ TRAILERS 1 1 1 • 1 1 11 VA E POSTS 5t0 \ .LAT :35.02'37' L 8 2ON'.78-49'20 1 ZONE X 000".; r � } loopIS A �- .� f t L 'o / 1 E Q U I P M E N T \\\/ / 1 lel , \I / TI I ' GENERAL NOTES AND COMMENTS: SYM. DATE BY 1. CONTOURS AND BASE MAP PROVIDED BY 13 ENGINEERING AND CONSULTING, LLC WITH ADDITIONAL CONTOURS OBTAINED FROM THE USGS NATIONAL ELEVATION DATASET. THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING ITS ACCURACY. Ao 03/10/17 NJB 2. DISCREPANCIES FOUND IN THE PROJECT EXISTING CONDITIONS MUST BE REPORTED TO THE PROJECT ENGINEER/OWNER. A 08/04/17 WTS 3. NO GUARANTEE OR ASSURANCE IS GIVEN BY THE OWNER OR ENGINEER AS TO THE ACCURACY, COMPLETENESS, OR VALIDITY OF THE EXISTING UTILITIES. CONTRACTOR TO PERFORM "CALL BEFORE YOU DIG" TO COORDINATE WITH UTILITY COMPANIES, AND LOCATE AND IDENTIFY ALL UTILITIES PRIOR TO CONSTRUCTION. 4. DOMINION RESERVES THE RIGHT TO USE EITHER, OR BOTH, 12" COMPOST FILTER SOCK OR STANDARD SILT FENCE, FOR ANY APPLICATION IN WHICH EITHER OF THESE TWO CONTROL MEASURES ARE SPECIFIED i lb REVISION INFORMATION ISSUED FOR REVIEW ISSUED FOR REVIEW .0 VZI PROJECT/TASK APP. \ �CAROr1,'',' 17 TRUE NORTH 200 0 100 200 IIII1IIII L E G E N D $ LIMITS OF CONSTRUCTION C _ _ _ _ _ _ LIMITS OF DISTURBANCE 0 G CONTRACTOR YARD LIMITS E OVERHEAD ELECTRIC LINE 0 LM UNDERGROUND GAS LINE 0 FENCE TS DITCH STREAM -----1000------ CONTOUR Ew.. 0 11e WETLAND ® FUEL TANK AREA (25'x 250') TRAILER (24'x 60') ® STORAGE UNITS TOP SOIL SEGREGATION AREA GRAVEL AREA. $ UTILITY POLE GA E GUY ANCHOR 0 G GUY POLE ® UTILITY VALVE 0 LM LINE MARKER 0 POST TS TEST STAND -TBM TEMPORARY BENCH MARK FLOW ARROW ERM NC, INC. Atlantic Coast Pipeline LLC License #F-1223 15720 Brixham Hill Ave, Suite 120 ERM Charlotte, NC 28277 (704) 541-8345 925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000 RAwN: NJB 08/04/17 CHECKED: _ _ TITLE: ATLANTIC COAST PIPELINE APP. FORBID: FAYETTEVILLE CONTRACTOR YARD AERIAL OVERVIEW APP. FOR CONST.: DISTRICT. - COUNTY: CUMBERLAND STATE: NC GROUP DWG. NO. REV. SCALE: AS NOTED DIWFILE: ACP\North Carolina\ - 2 OF 7 1 EX. 18" CULVERT CQ SUPER SILT FENCE OR STACKED 18 -INCH CFS GA (REF. SHEET 7) NC ST ATE $I GltWA Y 24 TS TOPSOIL SEGREGATION GA (1.6 ACRES)/\\ \ j �\\\/ C � _ ' \X TRAILERS ROCK CONSTRUCTION ENTRANCE (REF. SHEET 5) e DIVERSION SWALE (REF. SHEET 6) y y GRAVEL PARKING LOT (11.3 ACRES) DIVERSION SWALE (REF. SHEET 6) Is \�V>GX ATE POSTS LAT:35°02'38.27" LON:78°49'20.7146" DIVERSION SWALE ! (REF. SHEET 6) / GRAVEL PARKING LOT ' (6.7 ACRES) y F' PROP. (2) 18" CULVE & OUTLET PROTECTI c 000 (REF. SHEET 6) E Q U I P M E N T 90 �I I wcuc 051e I y I ' I � 'I I I H TRAILERS ✓C'/i' /// //tel �� 1 OUTLET PROTECTION (REF. SHEET 6) e / \ \/ TOPSOIL SEGREGATION \\jam (2.0 ACRES) SUPER SILT FENCE OR STACKED 18 -INCH CFS (REF. SHEET 7) UNNAMED TRIBUTARY EK LOCKS CRE T y SUPER SILT FENCE OR STACKED 18 -INCH CFS (REF. SHEET 7) y y y TRUE NORTH 100 0 50 100 iIIIIIIII L EG E N D LIMITS OF CONSTRUCTION (40.8 ACRES) $ UTILITY POLE C------ LIMITS OF DISTURBANCE GAE GUY ANCHOR (39.4 ACRES) - - - - CONTRACTOR YARD LIMITS GP 0 GUY POLE E OVERHEAD ELECTRIC LINE ® UTILITY VALVE UNDERGROUND GAS LINE • LM LINE MARKER FENCE o POST TS DITCH TEST STAND -TBM TEMPORARY BENCH MARK STREAM -__--1000------ CONTOUR FLOW ARROW wcuc 051e WETLAND ROCK CONSTRUCTION ENTRANCE (OR APPROVED ALT.) ® FUEL TANK AREA (25'x 250') OUTLET PROTECTION TRAILER (24'x 60') I PROPOSED DIVERSION SWALE ® JI TOP SOIL SEGREGATION AREA ��•Q�T� GRAVEL AREA. PROPOSED COMPOST FILTER SOCK OR SILT FENCE SUPER SILT FENCE OR STACKED 18 -INCH CFS GA (REF. SHEET 7) NC ST ATE $I GltWA Y 24 TS TOPSOIL SEGREGATION GA (1.6 ACRES)/\\ \ j �\\\/ C � _ ' \X TRAILERS ROCK CONSTRUCTION ENTRANCE (REF. SHEET 5) e DIVERSION SWALE (REF. SHEET 6) y y GRAVEL PARKING LOT (11.3 ACRES) DIVERSION SWALE (REF. SHEET 6) Is \�V>GX ATE POSTS LAT:35°02'38.27" LON:78°49'20.7146" DIVERSION SWALE ! (REF. SHEET 6) / GRAVEL PARKING LOT ' (6.7 ACRES) y F' PROP. (2) 18" CULVE & OUTLET PROTECTI c 000 (REF. SHEET 6) E Q U I P M E N T 90 �I I wcuc 051e I y I ' I � 'I I I H TRAILERS ✓C'/i' /// //tel �� 1 OUTLET PROTECTION (REF. SHEET 6) e / \ \/ TOPSOIL SEGREGATION \\jam (2.0 ACRES) SUPER SILT FENCE OR STACKED 18 -INCH CFS (REF. SHEET 7) UNNAMED TRIBUTARY EK LOCKS CRE T y SUPER SILT FENCE OR STACKED 18 -INCH CFS (REF. SHEET 7) y y y TRUE NORTH 100 0 50 100 iIIIIIIII L EG E N D GENERAL NOTES AND COMMENTS: SYM. DATE BY REVISION INFORMATION PROJECT/TASK APP. * ��t� ; "S faE 11 i�r , 1. CONTOURS AND BASE MAP PROVIDED BY 13 ENGINEERING AND CONSULTING, LLC WITH ADDITIONAL CONTOURS OBTAINED FROM THE USGS NATIONAL ELEVATION DATASET. �� \A CARO ' r ERM NC, INC. Atlantic Coast Pipeline, LLC THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING ITS ACCURACY. �0 03/10/17 NJB ISSUED FOR REVIEW �ti .''' r License #F-1223 15720 Brixham Hill Ave, Suite 120 2. DISCREPANCIES FOUND IN THE PROJECT EXISTING CONDITIONS MUST BE REPORTED TO THE PROJECT ENGINEER/OWNER. A 08/04/17 WTS ISSUED FOR REVIEW Vit. ' = ERM Charlotte, NC 28277 (704) 541-8345 925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000 3. NO GUARANTEE OR ASSURANCE IS GIVEN BY THE OWNER OR ENGINEER AS TO THE ACCURACY, COMPLETENESS, OR VALIDITY OF THE EXISTING UTILITIES. CONTRACTOR TO f RAWN: NJB 08/04/17 PERFORM "CALL BEFORE YOU DIG" TO COORDINATE WITH UTILITY COMPANIES, AND LOCATE AND IDENTIFY ALL UTILITIES PRIOR TO CONSTRUCTION. - 4. DOMINION RESERVES THE RIGHT TO USE EITHER, OR BOTH, 12" COMPOST FILTER SOCK OR STANDARD SILT FENCE, FOR ANY APPLICATION IN WHICH EITHER OF THESE TWO Q w CHECKED: _ _ TITLE: ATLANTIC COAST PIPELINE CONTROL MEASURES ARE SPECIFIED. �',, 1 7'.` APP. FORBID: FAYETTEVILLE CONTRACTOR YARD ESCP C ` CUMBERLAND NC GROUP DWG. NO. REV. APP. FOR CONST.: DISTRICT: - COUNTY: STATE: SCALE:AS NOTED DIR/FILE: ACP\NOrth Carolina\ - 3 O F 7 LIMITS OF CONSTRUCTION (40.8 ACRES) $ UTILITY POLE C------ LIMITS OF DISTURBANCE GAE GUY ANCHOR (39.4 ACRES) - - - - CONTRACTOR YARD LIMITS GP 0 GUY POLE E OVERHEAD ELECTRIC LINE ® UTILITY VALVE UNDERGROUND GAS LINE • LM LINE MARKER FENCE o POST TS DITCH TEST STAND -TBM TEMPORARY BENCH MARK STREAM -__--1000------ CONTOUR FLOW ARROW wcuc 051e WETLAND ROCK CONSTRUCTION ENTRANCE (OR APPROVED ALT.) ® FUEL TANK AREA (25'x 250') OUTLET PROTECTION TRAILER (24'x 60') PROPOSED CULVERT PROPOSED DIVERSION SWALE ® STORAGE UNITS TOP SOIL SEGREGATION AREA ��•Q�T� GRAVEL AREA. PROPOSED COMPOST FILTER SOCK OR SILT FENCE GENERAL NOTES AND COMMENTS: SYM. DATE BY REVISION INFORMATION PROJECT/TASK APP. * ��t� ; "S faE 11 i�r , 1. CONTOURS AND BASE MAP PROVIDED BY 13 ENGINEERING AND CONSULTING, LLC WITH ADDITIONAL CONTOURS OBTAINED FROM THE USGS NATIONAL ELEVATION DATASET. �� \A CARO ' r ERM NC, INC. Atlantic Coast Pipeline, LLC THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING ITS ACCURACY. �0 03/10/17 NJB ISSUED FOR REVIEW �ti .''' r License #F-1223 15720 Brixham Hill Ave, Suite 120 2. DISCREPANCIES FOUND IN THE PROJECT EXISTING CONDITIONS MUST BE REPORTED TO THE PROJECT ENGINEER/OWNER. A 08/04/17 WTS ISSUED FOR REVIEW Vit. ' = ERM Charlotte, NC 28277 (704) 541-8345 925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000 3. NO GUARANTEE OR ASSURANCE IS GIVEN BY THE OWNER OR ENGINEER AS TO THE ACCURACY, COMPLETENESS, OR VALIDITY OF THE EXISTING UTILITIES. CONTRACTOR TO f RAWN: NJB 08/04/17 PERFORM "CALL BEFORE YOU DIG" TO COORDINATE WITH UTILITY COMPANIES, AND LOCATE AND IDENTIFY ALL UTILITIES PRIOR TO CONSTRUCTION. - 4. DOMINION RESERVES THE RIGHT TO USE EITHER, OR BOTH, 12" COMPOST FILTER SOCK OR STANDARD SILT FENCE, FOR ANY APPLICATION IN WHICH EITHER OF THESE TWO Q w CHECKED: _ _ TITLE: ATLANTIC COAST PIPELINE CONTROL MEASURES ARE SPECIFIED. �',, 1 7'.` APP. FORBID: FAYETTEVILLE CONTRACTOR YARD ESCP C ` CUMBERLAND NC GROUP DWG. NO. REV. APP. FOR CONST.: DISTRICT: - COUNTY: STATE: SCALE:AS NOTED DIR/FILE: ACP\NOrth Carolina\ - 3 O F 7 EROSION AND SEDIMENT CONTROL PLAN NARRATIVE THE EROSION AND SEDIMENT (E&S) CONTROL MEASURES FOR THE PIPELINE CONSTRUCTION ACTIVITIES PRIMARILY CONSIST OF BUT ARE NOT LIMITED TO COMPOST FILTER SOCK, BELTED SILT RETENTION FENCE, SUPER SILT FENCE, SLOPE BREAKERS, AND TEMPORARY AND PERMANENT SEEDING AND MULCHING. BEST MANAGEMENT PRACTICES (BMP) SPECIFICATIONS FOR THE E&S CONTROL PLAN (E&SCP) ARE TO BE UTILIZED BY THE CONSTRUCTION CONTRACTOR ACCORDING TO THE PROVIDED PLAN. GENERAL CONSTRUCTION NOTES: 1. DISCHARGING SEDIMENT LADEN WATER WHICH WILL CAUSE OR CONTRIBUTE TO THE DEGRADATION OF A BENEFICIAL USE OF A WATER OF THE STATE FROM THE CONSTRUCTION SITE, A DEWATERING SITE, OR SEDIMENT BASINTRAP INTO ANY SURFACE WATER WITHOUT FILTRATION OR EQUIVALENT TREATMENT IS PROHIBITED. 2. THE DISCHARGER SHALL AMEND THE EROSION & SEDIMENT CONTROL PLAN WHENEVER THERE IS A CHANGE IN THE CONSTRUCTION OR OPERATIONS, WHICH MAY EFFECT THE DISCHARGE OF POLLUTANTS TO SURFACE WATERS OR GROUNDWATER. 3. DISCHARGES ORIGINATING FROM OFF-SITE SOURCES, WHICH FLOW THROUGH OR ACROSS THE AREAS DISTURBED BY CONSTRUCTION, MAY BE DIVERTED AROUND THE ACTIVE CONSTRUCTION AREA WHENEVER POSSIBLE. 4. PERFORM PERMANENT OR TEMPORARY SOIL STABILIZATION WITHIN 7 DAYS WHEN SITE IS AT FINAL GRADE AND ON SITES THAT ARE NOT AT FINAL GRADE, BUT WILL REMAIN DORMANT FOR MORE THAN 14 DAYS. 5. DUE TO VARYING SITE CONDITIONS, ADDITIONAL SEDIMENT CONTROL BMPS MAY BE NECESSARY BEYOND THE MEASURES SHOWN ON THE E&S CONTROL PLAN. 6. STAGING AREAS, ASSEMBLY AREAS, TEMPORARY EQUIPMENT AND NON -HAZARDOUS MATERIAL STORAGE AREAS SHALL BE LOCATED OUTSIDE 100 -YR FLOOD ZONES. HAZARDOUS MATERIAL STORAGE AREAS SHALL BE LOCATED AT LEAST 100 FEET BACK FROM SURFACE WATER BODIES. 7. EQUIPMENT STORAGE IN CONSTRUCTION STAGING AREAS SHALL BE LOCATED A MINIMUM OF 100 FEET AWAY FROM WETLAND EDGE. 8. AT MINIMUM, ALL BMPS ARE TO BE INSPECTED ONCE EVERY SEVEN CALENDAR DAYS AND WITHIN 24 HOURS AFTER ANY STORM EVENT GREATER THAN 0.5 -INCH PER 24-HOUR PERIOD DURING THE ENTIRE PROJECT. A WRITTEN REPORT MUST ALSO BE COMPLETED, DOCUMENTING EACH INSPECTION AND, IF NECESSARY, ANY REPAIR, REPLACEMENT OR MAINTENANCE ACTIVITY. 9. THE CONTRACTOR SHALL TAKE PRECAUTIONARY MEASURES TO PROTECT ANY EXISTING FACILITY SHOWN ON THE DRAWINGS, AND ANY OTHER WHICH IS NOT ON RECORD OR NOT SHOWN ON THE DRAWINGS. THE CONTRACTOR SHALL POTHOLE EXISTING UTILITIES AT THE POINTS OF CONNECTION AND ALL UTILITY CROSSINGS TO DETERMINE EXACT LOCATIONS PRIOR TO THE START OF WORK. ANY DISCREPANCIES BETWEEN THESE DRAWINGS AND EXISTING CONDITIONS SHALL BE REPORTED TO THE ENGINEER OF RECORD IMMEDIATELY. 10. ALL WORK WITHIN A PUBLIC RIGHT-OF-WAY SHALL BE COORDINATED WITH THE AGENCY HAVING JURISDICTION. 11. ALL REQUIRED PERMITS MUST BE OBTAINED PRIOR TO STARTING WORK. 12. DURING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR CONSTRUCTION, STABILIZATION AND MAINTENANCE OF ALL EXISTING AND PROPOSED SITE EROSION & SEDIMENTATION CONTROL DEVICES AND FACILITIES. 13. THE CONTRACTOR AGREES THAT IN ACCORDANCE WITH GENERALLY ACCEPTED CONSTRUCTION PRACTICES, THE CONTRACTOR WILL BE REQUIRED TO ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION OF THE PROJECT, INCLUDING EROSION & SEDIMENTATION DEVICES AND SAFETY OF ALL PERSONS AND PROPERTY; THAT THIS REQUIREMENT SHALL BE MADE TO APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS, AND CONSTRUCTION CONTRACTOR FURTHER AGREES TO DEFEND, INDEMNIFY AND HOLD THE ENGINEER OF RECORD HARMLESS OF ANY AND ALL LIABILITY, REAL OR ALLEGED, IN CONNECTION WITH THE PERFORMANCE OF WORK ON THIS PROJECT, EXCEPTING LIABILITY ARISING FROM THE SOLE NEGLIGENCE OF ENGINEER OF RECORD. 14. AS SITE SPECIFIC CONDITIONS MAY WARRANT, THE E&SC PLAN MAY REQUIRE MINOR MODIFICATIONS TO ENSURE PROPER PROTECTION OF RECEIVING WATERS. THE RESPECTIVE PROJECT ENVIRONMENTAL INSPECTOR (EI) WILL IDENTIFY SITE SPECIFIC AREAS WHERE A CERTAIN BMP MODIFICATION(S) IS NECESSARY TO EITHER OMIT OR ENHANCE BMPS IN SUCH AREAS. THIS PROCESS ENTAILS THE EI TO IDENTIFY LOCATIONS WHERE BMPS WILL NEED TO BE ALTERED, SUBSTITUTED OR OMITTED AND CONTACT THE DOMINION GAS COMPLIANCE SPECIALIST TO REVIEW PROPOSED CHANGES. UPON REVIEW AND APPROVAL BY THE DOMINION COMPLIANCE SPECIALIST, THE EI WILL REDLINE, DATE, AND SIGN THE E&SCP DRAWING(S) DEPICTING THE REDLINE CHANGE(S). ONCE THIS PROCESS IS COMPLETED, THE EI WILL NOTIFY NCDEQ OF SUCH MINOR MODIFICATION REDLINE AMENDMENTS AS REQUIRED BY THE GENERAL PERMIT. BMP INSTALLATION AND REMOVAL SEQUENCE SEQUENCE OF CONSTRUCTION EROSION AND SEDIMENTATION. THE CONTRACTOR MAY DEVIATE SLIGHTLY FROM THE STAGING OF PERMANENT SITE STABILIZATION TIMEFRAMES 1. A PRE -CONSTRUCTION MEETING SHOULD TAKE PLACE PRIOR TO START OF CONSTRUCTION ACTIVITIES. PERIMETER DIKES, SWALES, DITCHES, SLOPES 7 DAYS 2. BEGIN CLEARING AND GRUBBING SITE. CLEAR AND GRUB ONLY THOSE AREAS NECESSARY FOR INSTALLATION OF THE HIGH QUALITY WATER (HQW) ZONES 7 DAYS EROSION CONTROL MEASURES. SLOPES STEEPER THAN 3:1 7 DAYS 3. INSTALL SILT FENCE AS SHOWN ON THE PLANS. SLOPES 3:1 OR FLATTER 14 DAYS 4. ONCE EROSION CONTROL MEASURES HAVE BEEN INSTALLED AND PRIOR TO SEDIMENT REMOVAL ACTIVITIES, THE SITE IS TO ALL OTHER AREAS (SLOPES FLATTER THAN 4:1) 14 DAYS BE INSPECTED BY NCDENR - LAND QUALITY. ACTIVITIES HAVE TEMPORARILY OR PERMANENTLY CEASED, BUT IN NO CASE MORE THAN 21 DAYS AFTER THE CONSTRUCTION 5. GRADE SITE ACCORDING TO CONTRACT DOCUMENTS. MAINTAIN EROSION CONTROL DEVICES AS NEEDED. ACTIVITY IN THAT PORTION OF THE SITE HAS PERMANENTLY CEASED. 6. INSTALL STORM DRAINAGE AS INDICATED ON PLANS. 4. WHERE THE INITIATION OF STABILIZATION MEASURES WITHIN 7 DAYS AFTER CONSTRUCTION ACTIVITY TEMPORARILY OR 7. GRASS OR OTHERWISE STABILIZE ALL AREAS AS THEY ARE BROUGHT TO FINAL GRADES. PERMANENTLY CEASES IS PRECLUDED BY SNOW COVER, STABILIZATION MEASURES SHALL BE INITIATED AS SOON AS 8. THE CONTRACTOR SHALL DILIGENTLY AND CONTINUOUSLY MAINTAIN ALL EROSION CONTROL DEVICES AND STRUCTURES TO CONDITIONS ALLOW. MINIMIZE EROSION. INSPECT AND REPAIR MEASURES AFTER EACH RAINFALL AND AS NEEDED THROUGHOUT THE PROJECT. 5. WHERE CONSTRUCTION ACTIVITY WILL RESUME ON A PORTION OF THE SITE WITHIN 21 DAYS FROM WHEN ACTIVITIES CEASED 9. CONTRACTOR TO LEAVE ALL EROSION CONTROL DEVICES IN PLACE AT THE CONCLUSION OF THIS CONTRACT. CONTRACTOR IS (E.G., THE TOTAL TIME PERIOD THAT CONSTRUCTION ACTIVITY IS TEMPORARILY HALTED IS LESS THAN 21 DAYS), THEN TO CLEAN-OUT, REPAIR AND GRASS STABILIZE ALL DENUDED AREAS. ALL AREAS WILL BE RETURNED TO THE STATE OF STABILIZATION MEASURES DO NOT HAVE TO BE INITIATED ON THAT PORTION OF THE SITE BY THE SEVENTH DAY AFTER EXISTING CONDITIONS PRIOR TO CONTRACT AS A MINIMUM. CONSTRUCTION ACTIVITIES HAVE TEMPORARILY CEASED. 10. IT IS THE CONTRACTOR'S RESPONSIBILITY TO CONTAIN SEDIMENT ONSITE. ADDITIONAL EROSION CONTROL MEASURES MAY BE 6. AREAS WHERE THE SEED HAS FAILED TO GERMINATE ADEQUATELY (UNIFORM PERENNIAL VEGETATIVE COVER WITH A DENSITY REQUIRED BY THE ENGINEER. OF 70%) WITHIN 30 DAYS, SEEDING AND MULCHING MUST BE RE -SEEDED IMMEDIATELY, OR AS SOON AS WEATHER PERMITS. 11. ALL EROSION CONTROL MEASURES TO BE IN ACCORDANCE WITH THE NORTH CAROLINA EROSION AND SEDIMENT CONTROL PLANNING AND DESIGN REQUIREMENTS AND LAND DEVELOPMENT STANDARDS. POLLUTANT CONTROLS MAINTENANCE SCHEDULE AFTER FULL REVEGETATION HAS BEEN ACHIEVED, ALL BMPS WILL BE REMOVED AND ANY LAND DISTURBED BY REMOVAL WILL BE PERMANENTLY STABILIZED. UNLESS OTHERWISE SPECIFIED, ALL MAINTENANCE MUST BE COMPLETED IMMEDIATELY AFTER AN INSPECTION IDENTIFIES THAT A BMP IS NOT FUNCTIONING AS REQUIRED. THE ROW AND ESC DEVICES WILL BE INSPECTED DAILY AT THE ACTIVE CONSTRUCTION SITE AND AT LEAST ONCE EVERY SEVEN CALENDAR DAYS FOR ACTIVELY DISTURBED AREAS, 14 CALENDAR DAYS FOR RESTORED AREAS, AND WITHIN 24 HOURS AFTER ANY STORM EVENT GREATER THAN ONE -HALF-INCH PER 24-HOUR PERIOD. SEDIMENT MUST BE REMOVED WHERE ACCUMULATION REACHES ONE-HALF THE ABOVE GROUND HEIGHT OF THE CONTROL MEASURE. EROSION CONTROL MEASURES, WHICH HAVE BEEN UNDERMINED OR TOPPED, SHALL BE REPAIRED IMMEDIATELY. • OTHER REQUIRED REPAIRS OR MAINTENANCE SHALL BE MADE IMMEDIATELY. TEMPORARY AND PERMANENT E&S CONTROL BMPS SHALL BE MAINTAINED AND REPAIRED AS NEEDED TO ASSURE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION. MATERIAL WASTE HANDLING AND RECYCLING 1. SOLID WASTE DISPOSAL SHALL BE HANDLED THROUGH ONE OF THE LOCAL LICENSED WASTE MANAGEMENT PROVIDERS AND PERMITTED DISPOSAL FACILITIES. THE CONTRACTOR WILL PROVIDE MOBILE AND COVERED WASTE RECEPTACLES AS NEEDED ALONG THE PROJECT LIMITS. CONTRACTOR SHALL ALSO PROVIDE A COVERED DUMPSTER FOR CONSOLIDATION OF WASTE FOR PICK UP AND DISPOSAL FOR THE DURATION OF THE PROJECT. ALL SOLID WASTE SHALL BE DISPOSED OF AT A LICENSED PERMITTED MUNICIPAL LANDFILL. 2. THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY PERMITS AN DOR DISPOSAL FEES. THE CONTRACTOR SHALL BE SOLELY RESPONSIBLE TO ASSURE THAT ALL MATERIALS AREA HANDLED AND DISPOSED OF IN ACCORDANCE WITH APPLICABLE LAWS, RULES, AND REGULATIONS, INCLUDING BUT NOT LIMITED TO THOSE ISSUED BY THE ENVIRONMENTAL PROTECTION AGENCY, NCDEQ, AND OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION. 3. CONTRACTOR SHALL PRACTICE GOOD HOUSEKEEPING FOR THE DURATION OF THE PROJECT INCLUDING THE ROUTINE REMOVAL AND DISPOSAL OF SOLID WASTE. 4. CONTRACTOR SHALL KEEP RECORDS OF PROPER SOLID WASTE DISPOSAL AND PROVIDE COPIES TO THE EI. SEEDING AND MULCHING CONSTRUCTION MUST BE IN ACCORDANCE WITH THE FOLLOWING SEQUENCE. THIS SEQUENCE IS DESIGNED TO MINIMIZE SOIL EROSION AND SEDIMENTATION. THE CONTRACTOR MAY DEVIATE SLIGHTLY FROM THE STAGING OF PERMANENT SITE SEE SEED MIXES, SOIL AMENDMENTS, AND MULCH SPECIFICATIONS SPECIFIED IN THE ACP RESTORATION AND REHABILITATION IMPROVEMENTS, BUT NO DEVIATION FROM THE RELATIVE ORDER OF EROSION AND SEDIMENTATION CONTROL MEASURES WILL BE PLAN. ALLOWED. 1. SEEDBED PREPARATION: AREAS TO BE SEEDED SHALL BE DISKED TO A DEPTH OF 4 -IN TO 6 -IN WHENEVER FEASIBLE, AND SMOOTHLY GRADED. THE STAGING OF EARTHMOVING ACTIVITIES FOR THIS PROJECT IS A GENERAL DESCRIPTION OF THE WORK REQUIRED. ALL WORK 2. IN TOPSOILED AREAS, SOIL TO BE REDISTRIBUTED EVENLY AND STABILIZED PRIOR TO SEEDING. SHALL BE COMPLETED IN ACCORDANCE WITH COMPANY STANDARDS, THE NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL 3. STABILIZATION MEASURES SHALL BE INITIATED AS SOON AS PRACTICABLE IN PORTIONS OF THE SITE WHERE CONSTRUCTION QUALITY REGULATIONS AND ALL OTHER APPLICABLE FEDERAL, STATE OR LOCAL REQUIREMENTS. ACTIVITIES HAVE TEMPORARILY OR PERMANENTLY CEASED, BUT IN NO CASE MORE THAN 21 DAYS AFTER THE CONSTRUCTION ACTIVITY IN THAT PORTION OF THE SITE HAS PERMANENTLY CEASED. THE APPROVED EROSION AND SEDIMENTATION CONTROL PLAN INCLUDING THE SOIL EROSION CONTROL DRAWINGS AND NARRATIVE 4. WHERE THE INITIATION OF STABILIZATION MEASURES WITHIN 7 DAYS AFTER CONSTRUCTION ACTIVITY TEMPORARILY OR SHALL BE AVAILABLE ON SITE AT ALL TIMES DURING EARTH DISTURBANCE. PERMANENTLY CEASES IS PRECLUDED BY SNOW COVER, STABILIZATION MEASURES SHALL BE INITIATED AS SOON AS CONDITIONS ALLOW. 1. STAKE AND/OR FLAG ALL LIMITS OF DISTURBANCE FOR CONSTRUCTION ACTIVITIES, CLEARLY IDENTIFYING WETLAND AND 5. WHERE CONSTRUCTION ACTIVITY WILL RESUME ON A PORTION OF THE SITE WITHIN 21 DAYS FROM WHEN ACTIVITIES CEASED STREAM EDGES. INSTALL SIGNS TO DESIGNATE THE AREA TO IDENTIFY IMPORTANT PROJECT ATTRIBUTES SUCH AS (E.G., THE TOTAL TIME PERIOD THAT CONSTRUCTION ACTIVITY IS TEMPORARILY HALTED IS LESS THAN 21 DAYS), THEN WETLANDSTREAM BOUNDS, EXCLUSION AREAS ETC. STABILIZATION MEASURES DO NOT HAVE TO BE INITIATED ON THAT PORTION OF THE SITE BY THE SEVENTH DAY AFTER 2. INSTALL ROCK CONSTRUCTION ENTRANCES IMMEDIATELY BEFORE INITIAL DISTURBANCES. THE ROCK CONSTRUCTION CONSTRUCTION ACTIVITIES HAVE TEMPORARILY CEASED. ENTRANCES TO BE UNDERLAIN BY FILTER FABRIC. ALL CONSTRUCTION TRAFFIC SHOULD USE ONLY ROCK CONSTRUCTION 6. AREAS WHERE THE SEED HAS FAILED TO GERMINATE ADEQUATELY (UNIFORM PERENNIAL VEGETATIVE COVER WITH A DENSITY ENTRANCE FOR INGRESS AND EGRESS. ALL MUD OR SEDIMENT TRACKED ONTO THE EXISTING ROADWAY SHALL BE REMOVED OF 70%) WITHIN 30 DAYS, SEEDING AND MULCHING MUST BE RE -SEEDED IMMEDIATELY, OR AS SOON AS WEATHER PERMITS. BY THE CONTRACTOR AS NECESSARY. 3. INSTALL SILT FENCE AND COMPOST FILTER SOCKS AS NECESSARY ALONG THE ACCESS ROADS TO PREVENT SEDIMENT LADEN POLLUTANT CONTROLS RUNOFF FROM ENTERING DOWNSTREAM WATER BODIES. MAINTAIN THE ACCESS ROADS AS REQUIRED, ASSOCIATED DITCHES, AND NECESSARY OUTLET PROTECTION. REPORTABLE SPILLS OCCURRING DURING CONSTRUCTION, OPERATION AND MAINTENANCE ARE TO BE REPORTED 4. PRIOR TO AND SIMULTANEOUS WITH GRADING AND EXCAVATION, INSTALL REMAINING EROSION CONTROL DEVICES (ECD) IMMEDIATELY TO THE MONITORING CENTER IN ACCORDANCE WITH DOMINION POLICIES, PLANS AND PROCEDURES. SHOWN ON THE PLANS. DOMINION'S ENVIRONMENTAL HEALTH AND SAFETY DEPARTMENT WILL BE RESPONSIBLE FOR CONTACTING THE APPROPRIATE 5. COMMENCE GRADING AND ASSOCIATED CUT AND FILL SLOPES. THE EARTH MOVING ACTIVITY SHALL BEGIN IN AREA OF CUT SO AGENCIES, EXCEPT AS PROVIDED FOR BELOW. THAT THE CUTS CAN BE PLACED IN AREAS OF FILL. REMOVE TOPSOIL FROM AREAS TO RECEIVE FILL PRIOR TO FILLING. ANY FACILITY OWNER/OPERATOR WHO IS SUBJECT TO THE SPCC RULE MUST COMPLY WITH THE REPORTING REQUIREMENTS 6. FINALIZE UTILITY INSTALLATION AND ROADWAY GRADES AND PLACE TOPSOIL ON THE CUT AND FILL AREAS. STABILIZE CUT AND FOUND IN 40 CFR 112.4. A DISCHARGE MUST BE REPORTED TO THE EPA REGIONAL ADMINISTRATOR (RA) WHEN THERE IS A FILL SLOPES, AFTER PLACEMENT OF STOCKPILED TOPSOIL ON EXCAVATED SLOPES, AND AS DIRECTED. DISCHARGE OF: 7. RE -DISTRIBUTION OF WET SEDIMENT FROM DEVICES AND FACILITIES SHALL ONLY BE PERMITTED UPHILL OF AN EFFECTIVE •• MORE THAN 1,000 GALLONS OF OIL IN A SINGLE DISCHARGE TO NAVIGABLE WATERS OR ADJOINING SHORELINES, SEDIMENT CONTROL DEVICE OR FACILITY. SEDIMENT LADEN RUNOFF SHALL NOT BE ALLOWED TO FLOW DIRECTLY INTO •• MORE THAN 42 GALLONS OF OIL IN EACH OF TWO DISCHARGES TO NAVIGABLE WATERS OR ADJOINING SHORELINES WATER BODIES. OCCURRING WITHIN ANY TWELVE-MONTH PERIOD. 8. ANY EXPOSED TOPSOIL PILES SHOULD BE STABILIZED & SEEDED PER THE PERMIT REGULATIONS, AND BY TABLES SHOWN ON IF A DOMINION REPRESENTATIVE CANNOT BE PROMPTLY CONTACTED AND THE SPILL HAS IMPACTED WATER, THE PERSON THE APPROVED EROSION CONTROL PLANS AND MULCHED WITH STRAW AS SPECIFIED BY THE PROJECT OWNER. DISCOVERING THE SPILL OR RELEASE WILL CONTACT THE NATIONAL RESPONSE CENTER AT 1-800-424-8802 AND REPORT THE 9. UPON MINIMUM 70% UNIFORM PERENNIAL VEGETATIVE GROWTH, REMOVE TEMPORARY SEDIMENT CONTROLS. REMOVE RELEASE. THAT PERSON WILL CONTINUE CALLING DOMINION UNTIL A REPRESENTATIVE IS REACHED. ACCUMULATED SEDIMENTS WITHIN THE TRAPS, RE -GRADE TRAPS TO FINAL CONTOURS. STABILIZE SITE PER THE PLANS. GENERAL NOTES AND COMMENTS: SYM. DATE BY REVISION INFORMATION PROJECT/TASK APP. 1 ��L {0Ar��O ��r ; ��j, C�.f� ; ,�, �_ C� ♦ '(� ERM NC, INC. License #F-1223 Atlantic Coast Pipeline, LLC 0 o 03/10/17 NJB ISSUED FOR REVIEW �.' {f • 15720 Brixham Hill Ave, Suite 120 08/04/17 WTS ISSUED FOR REVIEW O = F, R Nf Charlotte, NC 28277 (704) 541-8345 925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000 DRAWN: NJB 08/04/17 - -•� o TITLE: ATLANTIC COAST PIPELINE CHECKED: _ _ �/-! EROSION AND SEDIMENT CONTROL PLAN NOTES APP. FOR BID: ♦ 'G� G GROUP DWG. NO. REV. f�Q ? 0�*y � )% APP. FOR CONST.: DISTRICT. - COUNTY. - STATE: NC 'rA Fk0 r/+,I�i1,ti DIRiFILE: ACP\North Carolina\ - 4 OF 7 1 SCALE: AS NOTED 100' MIN. PUBLIC STREET Op p O 00 o OOro U 00000 pp a 6" MIN. THICKNESS FILTER FABRIC UNDER STONE EXISTING GROUND 100' MIN. GENERAL NOTES: 1. A STABILIZED PAD OF WASHED STONE SHALL BE LOCATED WHERE TRAFFIC WILL BE ENTERING OR LEAVING A CONSTRUCTION SITE TO OR FROM A PUBLIC STREET. 2. STONE TO BE SURGE STONE OR 2"-3" RAILROAD BALLAST 3. THE ENTRANCE SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING OR FLOWING OF SEDIMENT ONTO PUBLIC STREETS OR EXISTING PAVEMENT. THIS MAY REQUIRE PERIODIC TOP DRESSING WITH ADDITIONAL STONE AS CONDITIONS DEMAND AND REPAIR AND/OR CLEANOUT OF ANY MEASURES USED TO TRAP SEDIMENT. 4. ALL SEDIMENT SPILLED, DROPPED, WASHED OR TRACKED ONTO PUBLIC STREETS MUST BE REMOVED IMMEDIATELY. 5. WHEN NECESSARY, WHEELS MUST BE CLEANED TO REMOVE SEDIMENT PRIOR TO ENTERING A PUBLIC STREET. WHEN WASHING IS REQUIRED, IT SHALL BE DONE ON AN AREA STABILIZED WITH CRUSHED STONE WHICH DRAINS INTO AN APPROVED SEDIMENT BASIN. 6. FILTER FABRIC SHALL BE MIRAFI 500 OR EQUIVALENT. (N. C. STD. N0. 6.06 TEMPORARY CONSTRUCTION ENTRANCE DETAIL 0 A � SANDBAGS, JERSEY BARRIERS, ROAD PLATES, SAMOI BAGS ETC. DIRT Pm c r , K I EXCAVATED TRENCH r B EROSION COW17ROL ._MEASURES TO BE 1 "KATED BELOW APPROACH AREAS PLAN VIE W �I SANDBAGS A CREEK BANK AIDMOATE OR SANDBAGS 1' FLUME PW CREEK MOTTO Y ~ QCiYAflD TQM PROPOSED PIPELM SECTION d'A -A" DIRT PLUG ` EXCAVATED TRENCH _n e ' _ 1 I ' PROPOSED UTIL17Y r r '.l_. I.1. 1._1.1 .l ■1 . _ EROSION CON"M MEASURES TO K __ LOCATED BELOW APPROACH AREAS AC4114fOATE OR CREE-K BANK SANDBAGS FLUME PIPE PROPOSED PIPEUNE SECTIO.N" "B-- B" NOT TO SCALE NOTES: 1. GRUBBING SHALL NOT TAKE PLACE WITHIN 50 FT OF TOP OF BANK UNTIL ALL MATERIALS REQUIRED TO COMPLETE THE CROSSINGS ARE ON SITE AND PIPE IS READY FOR INSTALLATION. 2. PIPE CULVERT FOR FLUME AND ACCESS ROAD MAY BE ONE CONTINUOUS PIPE. 3. WATER ACCUMULATING WITHIN THE WORK AREA SHALL BE PUMPED TO A PUMPED WATER FILTER BAG PRIOR TO DISCHARGING INTO SURFACE WATER. 4. ALL EXCESS MATERIAL SHALL BE IMMEDIATELY REMOVED FROM THE STREAM CROSSING AREA. 5. ALL DISTURBED AREAS WITHIN 50 FEET OF TOP OF BANK SHALL BE BLANKETED OR MATTED WITHIN 24 HOURS OF INITIAL DISTURBANCE FOR MINOR STREAMS OR 48 HOURS OF INITIAL DISTURBANCE FOR MAJOR STREAMS, UNLESS OTHERWISE AUTHORIZED. STREAM CROSSING RESTORATION: 1. ONCE THE SOIL EROSION AND SEDIMENT CONTROL MEASURES AND THE REQUIRED WATER FLOW CONTROL MEASURES ARE IN PLACE, CONTRACTOR CAN PROCEED WITH TRENCH EXCAVATION. 2. ALL EXCAVATED MATERIALS THAT WILL BE USED AS BACKFILL SHALL BE PLACED IN A TEMPORARY STOCKPILE LOCATED OUTSIDE THE CHANNEL. CHANNEL BED MATERIAL SHALL BE SEGREGATED FOR LATER USE. A SEDIMENT BARRIER SHALL BE INSTALLED BETWEEN THE STOCKPILE AND STREAM CHANNEL. 3. COMPLETE TRENCH EXCAVATION FOR PIPELINE CONSTRUCTION, PLACE PIPELINE AND BACKFILL. 4. STREAM BANKS SHALL BE RESTORED TO PRE -CONSTRUCTION CONFIGURATIONS, AS MUCH AS POSSIBLE, AND STABILIZED. 5. RE -SEED RESTORED STREAM BANKS USING SEED MIXTURES AS SPECIFIED HEREIN. 6. RESTORED STREAM BANKS AND ADJACENT DISTURBED AREAS TO BE STABILIZED WITH APPROVED EROSION CONTROL BLANKET USING MANUFACTURER RECOMMENDED STAPLES AND PATTERNS. 7. PLACE SALVAGED BED MATERIAL ON THE CHANNEL BED IN THE DISTURBED AREA. DRY DITCH CROSSING 1: FLUME CROSSING DETAIL NOT TO SCALE 24" DEPTH OF TRENCH SECTION VIEW ti TRENCH PLUG SPACING jl I STACKED CLAY, BENTONITE OR CONCRETE -FILLED SACKS PIPE BEDDING ELEVATION PIPE INVERT CONSTRUCTION NOTES: 1. TRENCH PLUGS ARE REQUIRED AT ALL STREAM, RIVER, WETLAND, OR OTHER WATER BODY CROSSINGS REGARDLESS OF TRENCH SLOPE. 2. TOPSOIL MAY NOT BE USED TO FILL SACKS. 3. TRENCH PLUG LOCATION AND SPACING SHALL BE IN ACCORDANCE WITH CONSTRUCTION ALIGNMENT SHEETS, OR AS OTHERWISE DIRECTED BY THE EI. TRENCH PLUG DETAIL NOT TO SCALE TRENCH S�Oey WELL VEGETATED AREA SPACING OF WATERBARS (IN ACCORDANCE WITH CONSTRUCTION ALIGNMENT SHEETS) PIPELINE TRENCH \ TRENCH SPOILS (TYP.) `SLOPE BREAKER (TYP.) A A' SOIL DIVERSION BERM OR COMPOST FILTER SOCK FOR TEMPORARY WATERBAR (SEE SOIL 18" MIN. AFTER DIVERSION BERM AND COMPOST FILTER SOCK COMPACTIO DETAILS, THIS SHEET), SOIL DIVERSION BERM FOR PERMANENT WATERBAR. U MIN. AFTER COMPACTION FINAL GRADE SECTION A - A' TYPICAL LOCATION OF SEDIMENT PROPOSED BARRIER (IF REQUIRED, SEE NOTE 5) R.O.W. NOTES: 1. TEMPORARY SLOPE BREAKERS SHALL BE INSTALLED UPON INITIAL DISTRUBANCE OF THE SOIL. PERMANENT WATERBARS SHALL BE INSTALLED AFTER THE TRENCH HAS BEEN BACKFILLED. 2. WATERBARS SHALL NOT DISCHARGE TO THE OPEN TRENCH AND SHOULD BE ALIGNED SO THAT DISCHARGES DO NOT FLOW BACK ONTO THE RIGHT-OF-WAY. RUNOFF SHALL BE DIRECTED TO THE DOWNSLOPE SIDE OF THE DISTURBED AREA. 3. SLOPES GREATER THAN 30% MAY REQUIRE THE INSTALLATION OF A PARALLEL COLLECTION DITCH AND SEDIMENT TRAP AT THE BOTTOM OF THE SLOPE IN PLACE OF WATERBARS. 4. WATERBARS MUST BE INSTALLED AT ALL PUBLIC ROADWAY AND RAILROAD CUT SLOPES. 5. IF A SUITABLE VEGETATIVE FILTER STRIP DOES NOT EXIST AT THE POINT OF DISCHARGE FOR ANY WATERBAR, A SEDIMENT BARRIER SHALL BE PROVIDED (E.G., FILTER SOCK, SILT FENCE, OR SOIL DIVERSION BERM, SEE DETAILS, THIS SHEET) MAINTENANCE NOTES: 1. PERIODICALLY INSPECT RIGHT-OF-WAY DIVERSIONS FOR WEAR AND AFTER EVERY HEAVY RAINFALL FOR EROSION DAMAGE. IMMEDIATELY REMOVE SEDIMENT FROM THE FLOW AREA, AND REPAIR THE DIKE. CHECK OUTLET AREAS AND MAKE TIMELY REPAIRS AS NEEDED. WHEN PERMANENT ROAD DRAINAGE IS ESTABLISHED AND THE AREA ABOVE THE TEMPORARY RIGHT-OF-WAY DIVERSIONS IS PERMANENTLY STABILIZED, REMOVE THE DIKE, FILL THE CHANNEL TO BLEND WITH THE NATURAL GROUND, AND APPROPRIATELY STABILIZE THE DISTURBED AREA. TYPCIAL WATERBAR AND TEMPORARY SLOPE BREAKER DETAIL TRENCH PLUG AND FILTER SOCK TOP SPOIL PILE SOIL § BELTED SILT RETENTION 0 FENCE (TYP.) TOPSOIL \ \ 0 I w BUFFER ZONE IS NOT TO HAVE 0 VEGETATION REMOVED (EXCEPT CL O TRENCH LINE). TREES ARE TO BE CUT STANDBY PUMP \\\\ Iz z \ \\ j�\\ FLUSH TO GRADE. REMOVE STUMPS U) \/\\/ ONLY IF SAFETY BECOMES A FACTO[ PUMP AND FUEL CAN PLACED FS 50' 5 � 50 _/ (BOTH SIDES OF STREAM) IN FLUID CONTAINMENT BOX Ui 0 F BACKHOE�� o 25' MIN. TIMBERMAT TOP OF BANK tuu_j HOSE UU STREAM FLOW TRENCHENERGY DISSIPATOR SCREENED INLET PLU1-1 G 7 (E.G., FILTER BAG) TOP OF BANK BACKHOE / 0 25' MIN. DOWNSTREAM SANDBAG UPSTREAM SANDBAG / COFFERDAM COFFERDAM \ F-� 50, LU / J 0LU LU Q TOP TOP SOIL SOIL SPOIL PILE PIPE WELDED, CONIC. COATED OR WEIGHTED TRENCH PLUG AND BELTED SILT RETENTION FENCE NOTES: 1. USE DAM AND PUMP METHOD ON NARROW WATERCOURSES WITH LIMITED STREAM FLOW TO PREVENT SEDIMENTATION AND INTERRUPTION OF STREAM FLOW DURING CROSSING CONSTRUCTION. IF FISH PASSAGE IS A CONCERN THIS METHOD IS NOT APPROPRIATE. 2. SCHEDULE CONSTRUCTION DURING PERIOD OF LOW STREAM FLOW. 3. SET UP PUMP AND HOSE AS SHOWN, OR USE OTHER PRACTICAL ALTERNATIVES. PUMP SHOULD HAVE TWICE THE PUMPING CAPACITY OF ANTICIPATED FLOW. HAVE STANDBY PUMP ON SITE. 4. INSTALL UPSTREAM DAM COMPOSED OF SANDBAGS OR CLEAN GRAVEL WITH PLASTIC UNDERLINING. INSTALL DOWNSTREAM DAM IF REQUIRED TO KEEP STREAMBED DRY. 5. EXCAVATE TRENCH AND INSTALL PIPE BY LOWERING IN UNDER HOSE. MOVE HOSE AS REQUIRED OR DISCONNECT IF TEMPORARY FLOW BLOCKAGE IS ACCEPTABLE. BACKFILL TRENCH. 6. DISMANTLE DOWNSTREAM DAM, THEN UPSTREAM DAM. KEEP PUMP RUNNING TO MAINTAIN FLOW. 7. MONITOR DAM AND PUMP FOR PROPER OPERATION THROUGHOUT THE CROSSING INSTALLATION. 8. IN HIGH QUALITY (HQ) OR EXCEPTIONAL VALUE (EV) STREAMS, USE 12" FILTER SOCK IN PLACE OF SILT FENCE. 9. ENSURE DISTURBED AREAS ARE SEEDED AND MULCHED USING SEED MIXTURES AS SPECIFIED IN THE INCLUDED TABLE. STREAM CROSSING RESTORATION: 1. ONCE THE SOIL EROSION AND SEDIMENT CONTROL MEASURES AND THE REQUIRED WATER FLOW CONTROL MEASURES ARE IN PLACE, CONTRACTOR CAN PROCEED WITH TRENCH EXCAVATION. 2. ALL EXCAVATED MATERIALS THAT WILL BE USED AS BACKFILL SHALL BE PLACED IN A TEMPORARY STOCKPILE LOCATED OUTSIDE THE CHANNEL. CHANNEL BED MATERIAL SHALL BE SEGREGATED FOR LATER USE. A SEDIMENT BARRIER SHALL BE INSTALLED BETWEEN THE STOCKPILE AND STREAM CHANNEL. 3. COMPLETE TRENCH EXCAVATION FOR PIPELINE CONSTRUCTION, PLACE PIPELINE AND BACKFILL. 4. STREAM BANKS SHALL BE RESTORED TO PRE -CONSTRUCTION CONFIGURATIONS, AS MUCH AS POSSIBLE, AND STABILIZED. 5. RE -SEED RESTORED STREAM BANKS AT THE RATE OF 15 LBS./ACRE WITH 'RIPARIAN BUFFER MIX' BY ERNST CONSERVATION SEEDS (MIX ERNMIX-178) OR APPROVED EQUAL. 6. RESTORED STREAM BANKS AND ADJACENT DISTURBED AREAS TO BE STABILIZED WITH APPROVED EROSION CONTROL BLANKET USING MANUFACTURER RECOMMENDED STAPLES AND PATTERNS. 7. PLACE SALVAGED BED MATERIAL ON THE CHANNEL BED IN THE DISTURBED AREA. DRY DITCH CROSSING 2: DAM AND PUMP DETAIL NOT TO SCALE TOP OF SILT MUST BE AT ABOVE THE l THE WASHED NOTES. I. REMOVE SEDIMENT *HEN HALF OF STONE OJTLET IS COVERED. 2. REPLACE STONE AS NEEDED TO ENSJW DENATERING_ NOT TO SCALE MAINTENANCE NOTES: 1. INSPECT SILT FENCE OUTLETS AT LEAST ONCE PER WEEK AND AFTER EACH SIGNIFICANT (0.5 -INCH OR MORE) RAINFALL EVENT. MAKE REPAIRS IMMEDIATELY. 2. REMOVE SEDIMENT DEPOSITS AS NECESSARY TO PROVIDE ADEQUATE STORAGE VOLUME FOR NEXT RAIN EVENT AND RELIEVE PRESSURE ON SILT FENCE. TAKE CARE NOT TO UNDERMINE FENCING DURING CLEANING. 3. REMOVE ALL SILT FENCE OUTLET MATERIALS AND UNSTABLE SEDIMENTS AND BRING THE AREA TO SURROUNDING GRADE AND STABILIZE ONCE UPSTREAM AREAS HAVE BEEN PROPERLY STABILIZED. STEEL POST WOVEN WIRE FABRIC HARDWARE CLOTH -- FILTER OF •57 WASHED STONE 2�l ?'INTO SOLA CRDU�O SECTION VIEW lo'IAI 3' FILTER FABRIC APRON ON GROUND 6'-- I I a RYPP R 6 U E E7^ZE OF II BURY WIRE FENCE GNC �A FILTER FABRIC AKRON IN TRENCH HARDWARE CLOTH II U SILT FENCE OUTLET DETAIL NOT TO SCALE WELL VEGETATED, GRASSY AREA MAP FILTER BAG PLAN VIEW FILTER BAG WELL VEGETATED, GRASSY AREA ELEVATION VIEW DISCHARGE HOSE -- PUMP INTAKE HOSE CLAMPS DISCHARGE HOSE PUMP CLAMPS INTAKE HOSE CONSTRUCTION NOTES: 1. FILTER BAGS MAY BE USED TO FILTER WATER PUMPED FROM DISTURBED AREAS PRIOR TO DISCHARGING TO WATERS OF THE COMMONWEALTH. THEY MAY ALSO BE USED TO FILTER WATER PUMPED FROM THE SEDIMENT STORAGE AREAS OF SEDIMENT BASINS. 2. THE PUMPING RATE SHOULD BE DETERMINED BY THE CONTRACTOR BASED UPON THE ACTUAL AMOUNT OF GROUNDWATER ENCOUNTERED DURING CONSTRUCTION. PUMPING RATES WILL VARY DEPENDING ON THE SIZE OF THE FILTER BAG AND THE TYPE AND AMOUNT OF SEDIMENT DISCHARGED TO THE BAG. 3. FILTER BAGS SHALL BE MADE FROM NON -WOVEN GEOTEXTILE MATERIAL SEWN WITH HIGH STRENGTH, DOUBLE STITCHED "J" TYPE SEAMS. THEY SHALL BE CAPABLE OF TRAPPING PARTICLES LARGER THAN 150 MICRONS. 4. A SUITABLE MEANS OF ACCESSING THE BAG WITH MACHINERY REQUIRED FOR DISPOSAL PURPOSES MUST BE PROVIDED. FILTER BAGS SHALL BE REPLACED WHEN THEY BECOME 1/2 FULL. SPARE BAGS SHALL BE KEPT AVAILABLE FOR REPLACEMENT OF THOSE THAT HAVE FAILED OR ARE FILLED. 5. BAGS SHALL BE LOCATED IN WELL -VEGETATED (GRASSY) AREAS AND DISCHARGE ONTO STABLE, EROSION RESISTANT AREAS. WHERE THIS IS NOT POSSIBLE, A GEOTEXTILE FLOW PATH SHALL BE PROVIDED. BAGS SHALL NOT BE PLACED ON SLOPES GREATER THAN 5%. 6. THE PUMP DISCHARGE HOSE SHALL BE INSERTED INTO THE BAGS IN THE MANNER SPECIFIED BY THE MANUFACTURER AND SECURELY CLAMPED. 7. THE PUMPING RATE SHALL BE NO GREATER THAN 750 GPM OR 1/2 THE MAXIMUM SPECIFIED BY THE MANUFACTURER, WHICHEVER IS LESS. PUMP INTAKES SHOULD BE FLOATING AND SCREENED. FILTER BAGS DETAIL NOT TO SCALE 8 X 8 X18 ROUGH OAK TIMBER TYPICAL 4' STEEL CABLE WETLAND TIMBER MATTING DETAIL NOT TO SCALE DIVERSION 4 - RIDGE 6" - COMPACTED EARTH OR STONE ENTRANCE PADS TO BE MADE OF COURSE AGGREGATE (AASHTO NO. 1) OR TIMBER SLAB WOOD (TYP.). TIMBERMATS 4' DIVERSION RIDGE 611 / / COMPACTED EARTH OR STONE APPLY ONE LAYER (TWO LAYERS IN WET J AREAS) GEATEXTILE UNDER ENTRANCE PADS (TYP.). NOTES: 1. ONLY CLEARING Q NECESSARY FOR INSTALLATION OF EQUIPMENT AND EQUIPMENT E EQUIPMENT BRIDGES MAY CROSS WATER BODIES PRIOR Q Q TO BRIDGE INSTALLATION. LIMIT THE CROSSING OF EACH WATERBODY TO ONE PIECE OF CLEARING EQUIPMENT. 2. INSTALL BELTED SILT RETENTION FENCE ACROSS THE DISTURBED AREA OF THE RIGHT OF WAY. 3. APPLY GEOTEXTILE UNDER ENTRANCE PADS. 4. EXCESS MUD IS TO BE REMOVED FROM THE ENTRANCE PADS AND MATS DURING CONSTRUCTION. 5. DURING FINAL CLEAN UP WHEN MATS, CULVERTS, CLEAN ROCK FILL, ETC. ARE REMOVED, INSTALL BELTED SILT RETENTION FENCE ACROSS THE ENTIRE RIGHT OF WAY ON BOTH SIDES OF STREAM. TEMPORARY BRIDGE CROSSING NOT TO SCALE GENERAL NOTES AND COMMENTS: SYM. DATE BY REVISION INFORMATION PROJECT/TASK APP. y 1s,{t till ;�R$�aDA�� , ; N ` \ C 1 ���,�0 `7 � � � , . • " � • �� � � ,Z ' 7 r � (• � ;�, �_ P]�1 �`� o - .� � t1 f ) ��''',, t���{���,,'���� � f�0�.� Y �� �� ����ti 1 �'rAl,� � I �� ���� ERM NC, INC. License #F-1223 15720 Brixham Hill Ave, Suite 120 ERM Charlotte, NC 28277 (704) 541-8345 Atlantic Coast P1 eline LLC �0 03/10/17 08/04/17 NJB WTS ISSUED FOR REVIEW ISSUED FOR REVIEW - - L� 925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000 DRAwN: NJB 08/04/17 T'T`E: ATLANTIC COAST PIPELINE EROSION AND SEDIMENT CONTROL PLAN DETAILS �HE�KED: - - APP. FORBID: APP. FOR CONST.: DISTRICT: - COUNTY: - STATE: jsJ C D►R�FaE: ACP\North Carolina\ GROUP - DWG. NO. 5 O F 7 REV. 1 scALE: AS NOTED ANCHOR POSTS MIN. 2" STEEL "U" (`LJ ANI A I CI C' III I CKI(`TLJ ATTACHED TO POST IN 3 MIN. 18" INTO NOTES: 1. PROTECTION BARRIER SHALL BE 4' HIGH, CONSTRUCTED OF DURABLE AND HIGHLY VISIBLE MATERIAL (PLASTIC ORANGE CONSTRUCTION FENCE AND SNOW FENCE MAY BE USED). 2. PROTECTION BARRIERS SHALL BE MAINTAINED THROUGHOUT THE DURATION OF THE WORK AT THE SITE. 3. ADDITIONAL WARNING SIGNS SHOULD ALSO BE PLACED ON THE FENCING AND IN APPROPRIATE AREAS NEAR THE WORK ZONE. CONSTRUCTION FENCE DETAIL Pipe Outlet to Flat Area— No Well-defined Channel 3do A deo --- Pipe Outlet to Well-defined Channel Filter blanket MAINTENANCE NOTES: 1. INSPECT RIPRAP OUTLET STRUCTURES WEEKLY AND AFTER SIGNIFICANT (j INCH OR GREATER) RAINFALL EVENTS TO SEE IF ANY EROSION AROUND OR BELOW THE RIPRAP HAS TAKEN PLACE, OR IF STONES HAVE BEEN DISLODGED. IMMEDIATELY MAKE ALL NEEDED REPAIRS TO PREVENT FURTHER DAMAGE. OUTLET PROTECTION DETAIL NOT TO SCALE NOT TO SCALE PEPS'PECTI VE 17I E W INTRODUCTION 1. PROTECTIVE FENCING SHOULD BE INSTALLED TO PREVENT ACCESS TO POTENTIALLY HAZARDOUS AREAS OF A CONSTRUCTION SITE. CONDITIONS WHERE PRACTICE APPLIES 1. APPLICABLE TO ANY CONTROL MEASURE OR SERIES OF MEASURES, WHICH CAN BE CONSIDERED UNSAFE BY VIRTUE OF POTENTIAL FOR ACCESS BY THE PUBLIC. THE DESIGNER, DEVELOPER, AND CONTRACTOR SHOULD ALWAYS BE SURE THAT THE MOST APPROPRIATE TYPE OF FENCE IS UTILIZED FOR A PARTICULAR NEED. CONSTRUCTION SPECIFICATIONS 1. SAFETY FENCES SHOULD BE LOCATED SO AS TO CREATE A FORMIDABLE BARRIER TO UNDESIRED ACCESS, WHILE ALLOWING FOR THE CONTINUATION OF NECESSARY CONSTRUCTION OPERATIONS. 2. SAFETY FENCES ARE MOST APPLICABLE TO THE CONSTRUCTION OF TRAPS AND DAMS. IN USE WITH THOSE STRUCTURES, SAFETY FENCES SHOULD BE LOCATED FAR ENOUGH BEYOND THE OUTER TOE OF THE EMBANKMENT TO ALLOW FOR THE PASSAGE OF MAINTENANCE VEHICLES. FENCES SHOULD NOT BE INSTALLED ACROSS THE SLOPE OF A DAM OR DIKE. 3. SIGNS NOTING POTENTIAL HAZARDS SUCH AS 'HANGER" OR 'HAZARDOUS AREA - KEEP OUT" SHOULD BE POSTED AND EASILY SEEN BY ANYONE APPROACHING THE PROTECTED AREA. 4. PLASTIC (POLYETHYLENE) FENCE MAY BE USED AS SAFETY FENCING, PRIMARILY IN SITUATIONS WHERE THE NEED IS FOR A TEMPORARY BARRIER. THE FENCE SHOULD MEET THE PHYSICAL REQUIREMENTS NOTED IN TABLE 3.04.1. 5. SAFETY FENCES SHOULD BE INSTALLED PRIOR TO THE SEDIMENT CONTROL MEASURE BECOMING ACCESSIBLE. 6. APPLICABLE WARNING SIGNS NOTING HAZARDOUS CONDITIONS MUST BE INSTALLED IMMEDIATELY UPON INSTALLATION OF SAFETY FENCE. 7. CHAIN LINK FENCE SHOULD BE USED FOR PERMANENT STRUCTURES (GREATER THAN ONE YEAR). MAINTENANCE 1. SAFETY FENCE SHALL BE CHECKED REGULARLY FOR WEATHER-RELATED OR OTHER DAMAGE. ANY NECESSARY REPAIRS MUST BE MADE IMMEDIATELY. 2. CARE SHOULD BE TAKEN TO SECURE ALL ACCESS POINTS (GATES) AT THE END OF EACH WORKING DAY. ALL LOCKING DEVICES MUST BE REPAIRED OR REPLACED AS NECESSARY. SLOPE ROAD SURFACE TOWARDS DITCHUNE TABLE 3.04.1 PHYSICAL PROPERTIES OF PLASTIC SAFETY FENCE PHYSICAL PROPERTY TEST N/A REQUIREMENTS INTERNATIONAL ORANGE RECOMMENDED COLOR TENSILE YIELD ASTM D638 AVERAGE 2,000 Ibs. ULTIMATE TENSILE ASTM D638 AVERAGE 2,000 Ibs. STRENGTH 50 per 4FT. WIDTH ELONGATION AT ASTM D638 GREATER THAN 1000% BREAK(%) 100 30 CHEMICAL RESISTANCE N/A INERT TO MOST 60 500 CHEMICALS/ACIDS STABILIZE DITCH MRH APPROPRIATE LINING SUCH 1 AS RIPRAP. RECP, OR GRASS ROCK DITCH CHECKS MAX GRADE SAFETY FENCE SPECIFICATIONS GRAVEL SURFACE MIN. SPACING .- MAX. SPACING 300' OUTLET PROTECTION Y olo/ '11\ OUTLET P SILT FENCE GRAVEL ROADWAY SURFACE FLOW OF SUMP WATER DITCH CHECK SUMP DITCH LINE CROSS SECTIO.' CULVERT SIZING TABLE DRAINAGEAREA (AC) PIPEDIAMETER (IN) PIPECAPACITY (CFS) 10 15 5 20 18 9 30 21 12 50 24 18 80 27 24 100 30 29 300 36 60 500 42 85 SOURCE: WEST VIRGINIA EROSION AND SEDIMENT CONTROL FIELD MANUAL, MAY 2012 SEDIMENT AND EROSION CONTROL FOR ACCESS ROADS AND DRIVEWAYS NOT TO SCALE EROSION AND SEDIMENT CONTROL PRODUCTS i 0 Td TOE OF SLOPE FABRIC TOBE 24" ABOVE GROUND WITH 'J' IN IN TRENCH 26' 74' FLOW a' 22" fW 4. 4TOE IN AND COMPACT BACKFILL T SIDE VIEW Green Band 4' MAX O.C. FRONT ELEVATION BONDING STRIP I i' x t x 24") 4STAPLES 11" x 1"j GROUND LINE €� 1- BOTTOM OF j[u�pa TRENCH LINE POST OAK (14'x14"x48') (OR EQUAL DENSITY) REPAIR DETAIL ATTACHING TW0 SILT FENCES WHEN TRENCHING IS USED P'' ACE IHd ENL POST CF ONE FENOE INSxlC IIaE END POST OF THE OTHER FENCE ROTATE BOON POST AT LAST 1T' AJ A CLOCKYASE BIREF TMN �Qzl TD CRBATE R SEAL OATH THE FABRIC MATERIAL LYRECTM OF RUNCFF WATER MINE BOTH PQ$TS I I ABOUT 12 INCHES IISTO THE CTtCUHG FNG B�JRY THE FLAP IH A iREHCN PLAN VIEW NOTES: 1. PRIORITY 1 – GREEN BAND BELTED SILT RETENTION FENCE SHALL BE INSTALLED UPGRADIENT OF WATERBODIES, WETLANDS, AND OTHER SENSITIVE RESOURCES. 2. USE OF BSRF PRIORITY 1 AND 2 IN OTHER AREAS WILL BE AT THE DISCRETION OF THE OWNER. 3. IF BSRF DOES NOT PERFORM TO SPECIFICATIONS, THEN STANDARD SILT FENCE WILL BE USED. MAINTENANCE NOTES: 1. INSPECT SEDIMENT FENCES AT LEAST ONCE A WEEK AND AFTER EACH RAINFALL MAKE ANY REQUIRED REPAIRS IMMEDIATELY. 2. SHOULD THE FABRIC OF A SEDIMENT FENCE COLLAPSE, TEAR, DECOMPOSE OR BECOME INEFFECTIVE, REPLACE IT PROMPTLY. 3. REMOVE SEDIMENT DEPOSITS AS NECESSARY TO PROVIDE ADEQUATE STORAGE VOLUME FOR THE NEXT RAIL AND TO REDUCE PRESSURE ON THE FENCE. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEANOUT. BELTED SILT RETENTION FENCE (BSRF) PRIORITY 1 - GREEN BAND FIGURE 3.35.1 TYPES OF ROAD CROSS—SECTIONS I 4% 4% SYM. A 24' 36" SILTSAVER PRIORITY 11 9SRF FABRIC <5 acres FOR LOW GROUND USE TRENCH 4% 1 4% 6feet 4' LONG WOOD POST (DAIQ SPACED AT 4'-0" 1 foot FRONT ELEVATION BONDING STRIP I i' x t x 24") 4STAPLES 11" x 1"j GROUND LINE €� 1- BOTTOM OF j[u�pa TRENCH LINE POST OAK (14'x14"x48') (OR EQUAL DENSITY) REPAIR DETAIL ATTACHING TW0 SILT FENCES WHEN TRENCHING IS USED P'' ACE IHd ENL POST CF ONE FENOE INSxlC IIaE END POST OF THE OTHER FENCE ROTATE BOON POST AT LAST 1T' AJ A CLOCKYASE BIREF TMN �Qzl TD CRBATE R SEAL OATH THE FABRIC MATERIAL LYRECTM OF RUNCFF WATER MINE BOTH PQ$TS I I ABOUT 12 INCHES IISTO THE CTtCUHG FNG B�JRY THE FLAP IH A iREHCN PLAN VIEW NOTES: 1. PRIORITY 1 – GREEN BAND BELTED SILT RETENTION FENCE SHALL BE INSTALLED UPGRADIENT OF WATERBODIES, WETLANDS, AND OTHER SENSITIVE RESOURCES. 2. USE OF BSRF PRIORITY 1 AND 2 IN OTHER AREAS WILL BE AT THE DISCRETION OF THE OWNER. 3. IF BSRF DOES NOT PERFORM TO SPECIFICATIONS, THEN STANDARD SILT FENCE WILL BE USED. MAINTENANCE NOTES: 1. INSPECT SEDIMENT FENCES AT LEAST ONCE A WEEK AND AFTER EACH RAINFALL MAKE ANY REQUIRED REPAIRS IMMEDIATELY. 2. SHOULD THE FABRIC OF A SEDIMENT FENCE COLLAPSE, TEAR, DECOMPOSE OR BECOME INEFFECTIVE, REPLACE IT PROMPTLY. 3. REMOVE SEDIMENT DEPOSITS AS NECESSARY TO PROVIDE ADEQUATE STORAGE VOLUME FOR THE NEXT RAIL AND TO REDUCE PRESSURE ON THE FENCE. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEANOUT. BELTED SILT RETENTION FENCE (BSRF) PRIORITY 1 - GREEN BAND FIGURE 3.35.1 TYPES OF ROAD CROSS—SECTIONS I 4% 4% SYM. A 2.1 ---- - CROWNED FILL SECTION <5 acres FOR LOW GROUND USE Bottom width flow channel 4% 1 4% 6feet Depth of flow channel 1 foot CROWNED TURNPIKE SECTION Side slopes FOR LOW GROUND USE WHERE 2:1orflatter FILL IS UNAVAILABLE 0.5% minimum h ` ' - 4-6% - �% T'T`E: ATLANTIC COAST PIPELINE EROSION AND SEDIMENT CONTROL PLAN DETAILS OUTSLOPE SECTION ' FOR USE ON MODERATE SLOPE AND STABLE SOILS �HE�KED: - 4-6% INSLOPE WITH DITCH SECTION APP. FORBID: _ - - FOR USE ON STEEP SLOPE AND l AREAS WITH POOR SOILS THE CHOICE OF CROSS-SECTION DEPENDS / ON DRAINAGE NEEDS. SOIL STABILITY, SLOPE. APP. FOR CONST.: AND EXPECTED TRAFFIC VOLUMES. DISTRICT: - COUNTY: - STATE: Nf C D►R�FaE: ACP\North Carolina\ GROUP - DWG. NO. 6 O F 7 4x 14% ..F----- ------ 11111- ' CROWNED AND DITCHED SECTION scALE: AS NOTED FOR HIGHER VOLUME ROADS ON - - STEEP SLOPES FROM: US FOREST SERVICE AND MICHIGAN DNR TYPES OF ROAD CROSS-SECTIONS NOT TO SCALE FIGURE 3.28.1 NOT TO SCALE SUPER SILT FENCE N&M FENCE PWT SPACM SHALL NOT EXCEED 1Nf TO CENTER OROLNrD suAFACE FLDW TO' OVUM LIM "MCE Wffw 1 LAYER OF FLm CLOM 2 �' DIANE�ER GALVANIZED OR ALLACNW POST OR 4'x4' '04T 44r CHAIN LM FENCIgO 44F MYER C M- F1Aw Sr MINW1 P= HEIM Dl1R1f run CN mm 12" I MLIYWY N GROUND 3B' MIN RJUII WRIED Ll NOTE: WHERE SUPER SILT FENCE IS SHOWN ON THE ALIGNMENT SHEETS AN ACCEPTABLE SUBSTITUTE SHALL BE A PYRAMID STACK OF THREE 18 INCH DIAMETER COMPOST FILTER SOCKS, SUBJECT TO THE APPROVAL OF THE EI. SUPER SILT FENCE NOT TO SCALE r i EROSION AND SEDIMENT CONTROL PRODUCTS 10' To TOE OF SLOPE 7 FABRIC TO BE 24" ABOVE GROUND WITii "J" IN TRENCH 26' 24. FLOW e" J�T TOE IN AND COMPACT BACKFILL SIDE VIEW Black Band & MAX D.C. � { FRONT ELEVATION BONDING STRIP (i"x'x24'j 4 STAPLES (1' x 1�') GROUND LINE [� 8070M OF TRENCH LINE POST OAK (18° x 1 8° x 49') (OR EQUAL DENSITY) REPAIR DETAIL ATTACHING TWO SILT FENCES WHEN TRENCHING 0 USED PLACF THE EMTI POSE OF ONE FENCE IN567E PIiE END POSE OF THE QTHDt FtNCE POTClXiA E TH POST AT LEAST 160' IN A aoci<x1SE� aREcnaN TO CREATE A TIGHT SEAL OATH THE FABRIC MAIERIAL DIRFCIION OF R1INCFF WATER DRIVE BOT, PCSTS I T A97UT 12 INCHES INTI THE GRCUHO AND 6BRT TIS FLAP IN A En, RENCTI PLAN VIEW BELTED SILT RETENTION FENCE (BSRF) PRIORITY 2 - BLACK BAND 10% SETTLEMENT NOT TO SCALE PARABOLIC DIVERSION 10% SETTLEMENT ^ TRAPEZOIDAL DIVERSION 10% SETTLEMENT VEE—SHAPED DIVERSION Table3.15.1 CHANNEL CROSS SECTION REQUIREMENTS SYM. A B Drainage area <5 acres 5 -10 acres Bottom width flow channel 4feet 6feet Depth of flow channel 1 foot 1 foot Side slopes 2:1orflatter 2:1orflatter Grade 0.5% minimum 0.5% minimum DIVERSION DETAIL NOT TO SCALE GENERAL NOTES AND COMMENTS: SYM. DATE BY REVISION INFORMATION PROJECT/TASK APP. y 1s,{t till ;�R$�a���� , ; � ` \ C 1 ���,�0 `7 � • �� � � ,� ' 7 r � (• � ;�, �_ P]�1 �`� o - .� � t1 f ) ��''',, ���{/��,,,'��;� � f�0�.� Y �� �� ����ti 1 �'ril,� � I �� ���� ERM NC, INC. 15720 Brixham Hill Ave, Suite 120 ERM Charlotte, NC 28277 (704) 541-8345 Atlantic Coast P1 eline LLC % �0 03/10/17 08/04/17 NJB WTS ISSUED FOR REVIEW ISSUED FOR REVIEW - - 925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000 DRAwN: NJB 08/04/17 T'T`E: ATLANTIC COAST PIPELINE EROSION AND SEDIMENT CONTROL PLAN DETAILS �HE�KED: - - APP. FORBID: APP. FOR CONST.: DISTRICT: - COUNTY: - STATE: Nf C D►R�FaE: ACP\North Carolina\ GROUP - DWG. NO. 6 O F 7 REV. 1 scALE: AS NOTED COFFERDAMS 4 NIL. PU=C PUMP E%CESS WATER TO APPROVED GEWATERIKG DEVICE S,AHDBW DRY WORK AREA, JE R,S? E BA 4J 41,' 4 CO J<' L: RD 1i 6 MIL PLA!VX PUb&P EXCESS WATER TO APPROVED DEWATERING pEYLCE � SANDBAG L}RY WORT( MRSA COFFERDAMS NOT TO SCALE TYPE 1 5/8 IN. POLYPROPYLENE ROPE 1/4 IN. TIE ROPE A FOLDS FOR COMPACT STORAGE DEPTH ACCORDING TO NEED NYLON REINFORCED VINYL 18 (OR 22) OZ. VINYL COVERED NYLON PLAN VIEW SILT JERSEY AIRIER, AGGREGATE OR SANOBACS CREEK SANK S MIL. PLA"C PRY WORK ARE, SANDBAGS PROPOSED PIPUHE SECTION"A — " COFFERDAM CROSSING NOT TO SCALE TWKHM OF STONE i–} DMAiErM OYER PIPE, A MWETER COAM AOG1 OATS WACM OF NPE CULVERTS OF PIPE OR IY. E" DEFP SHOULD EQUAL BAHMLL FLAW WFIICJ•If'YER IS USE ONLY LARGE GREATER AMCULAR DURA6IE ii4OK �_=� f � � �•' ll�� II I IIII-li,11��. unix 11�illl I! IIII t� II rm cum —11111 I I I II I I I i I I�i III 1111111 III f I� I� l�I l I III�f I CIII� Y CLASS B EROSION STONE T111, Iimil I if lipIw I,1I;UILv4I 14 w ; fik'I ItPL,% -oiwI 4I;t.s-L r, 014 111 iBuI1ti41rI� 0��� , •� � 'L-4 '-1k- Mf1 1131 mumi I hlm1 - � NL31 0 {#'int,m -I IL, Or ER-11thtig nvg., l as 1w - 4' MAXyn STAKE 1'MIN. STREAM FLOW 1 —SEDIMENT LOG FLOATATION ANCHOR PT. 11 11 11 = II WOODEN STAKES PLACED 10' WOODEN STAKES PLACED 10' —.-� STAKE OR ANCHOR, 11 111 1 Ili 11 11 11 O.C. AND THROUGH MIDDLE OF ZO.C. AND THROUGH MIDDLE -_--_-----_ EVERY 100' (TYPICAL) Z FILTER SOCK OF FILTER SOCK I BLOWN/PLACED COMPOST FILTER SOCK BLOWN/PLACED COMPOST FILTER SOCK SHORELINE ®FILL AREA FILTER MEDIA, AS FILTER MEDIA, AS (MINIMUM 12 INCH DIAMETER) FLAT, LEVEL AREA AASHTO 957 NEEDED AREA TO BE PROTECTED NEEDED LIMITS OF ) ' P. FREE OF DEBRIS STONE AREA TO BE PROTECTED CONSTR. WORK AREA WORK AREA ECONOMY FABRICS AVAILABLE ------------- -- J4" SHORELINE FRONT VIEW 18 OZ. 300 LB/IN. STANDARD lx� TURBIDITY STAKE OR EQUIVALENT X1,2 NOM. 2 � //�//%%/��/��/��/�\ � '\N M\� ANCHOR PT. THIS DISTANCE IS VARIABLE �— i \� � CURTAIN ALL SEAMS HEAT SEALED 1/4 IN. CHAIN (BLOW—UP OF SHACKLE CONNECTION) 0 TYPE D GALVANIZED #24 SAFETY HOOK TIDAL WATERS AND/OR HEAVY WIND & WAVE ACTION FLOOD �— EBB oanpncrn rnp, SEDIMENT LOG - I, T. SHEET FLOW 2. COMPACTED BACKFILL MATERIAL UNDISTURBED FLAT, LEVEL AREA FREE OF DES GROUND BRI m ELEVATION VIEW 2'x2'x48'(t318')WOOD G•TA.IC ^AM 1-!1111%]AN Ci1T SECTION WOODEN STAKES PLACED 10' O.C. AND THROUGH MIDDLE OF FILTER SOCK (TYP.) am AREA TO BE PROTECTED WATER FLOW COMPOST y FILTER SOCK an WATER FLOW SECTION WOODEN STAKES PLACED 10' O.C. AND THROUGH MIDDLE OF FILTER SOCK (TYP.) AREA TO BE PROTECTED COMPOST FILTER SOCK :, CAUSEWAY Y � WORK FLOW FLOW 4 O SILT FiN Sart FENCE INC DOT #5 OR _ , .. a* �I #57 WASHED _x R 1ltf fill= _ I ft 111h LLIIIU11 L PLAN PLAN STONE ANCHOR & AASHTO #57 STONE NOTES: 100 FT. STANDARD LENGTH EXTEND �. ANCHOR BUOY Of 4 RUrralw3 PLAN VIEW NECESSARY UP—SLOPE OF FILTER SOCK, TO BE FILTREXX FILTERMEDIA OR APPROVED EQUAL. BARRIER MOVEMENT SHORELINE DUE TO TIDAL CHANGE ANCHOR PT. 2. SEDIMENT SHALL BE REMOVED WHEN ACCUMULATIONS REACH 1/2 THE ABOVE GROUND HEIGHT OF THE FILTER SOCK. f[ + • ill Jill hijilklItik if ANCH RIN T. 3. MINIMUM OF 12 INCHES DIAMETER. g 51411• vik'%k L+of IXFPk THIS DISTANCE IS VARIABLE ® FILL AREA 1. SEDIMENT FILTER LOGS SHALL BE INSPECTED WEEKLY AND AFTER EACH MAINTENANCE NOTES: f RUNOFF EVENT. SEDIMENT DEPOSITS SHALL BE CLEANED FROM THE LOG 1. INSPECT COMPOST SOCK WEEKLY AND AFTER EACH SIGNIFICANT RAINFALL EVENT (1/2 INCH OR GREATER). REMOVE TURBIDITY CURTAIN DETAIL WHEN IT REACHES HALF THE HEIGHT OF THE LOG. DAMAGED FILTER LOGS SHALL BE REPLACED WITHIN 24 HOURS OF INSPECTION. A ACCUMULATED SEDIMENT AND ANY DEBRIS. THE COMPOST SOCK MUST BE REPLACED IF CLOGGED OR TORN, IF r SUPPLY OF FILTER LOGS SHALL BE MAINTAINED ON SITE FOR THIS CLOGGING BECOMES EXCESSIVE, THE SOCK MAY NEED TO BE REPLACED WITH A LARGER DIAMETER OR A DIFFERENT STRESS BAND STRESS PLATE IN. CH IN NOT TO SCALE PURPOSE. MEASURE. THE COMPOST SOCK SHALL BE INSPECTED UNTIL LAND DISTURBANCE IS COMPLETED AND THE AREA BALLAST 2. COIR LOGS TO BE REMOVED FROM ALL WETLANDS AT THE COMPLETION ABOVE THE MEASURE HAS BEEN PERMANENTLY STABILIZED. u OF CONSTRUCTION ACTIVITIES. COMPOST FILTER SOCK TURBIDITY CURTAIN DETAIL 50 FEET MINIML144 4O FM w3mui1 NOT TO SCALE Fv1p111 k i+'titi NOT TO SCALE TOP OF STREAM CHANNEL TOP Of RANK IWMK STRUCTURAL STREAMBANK STABILIZATION DETAIL -- -- - SYM. DATE BY NOT TO SCALE CULVERT STREAM CROSSING APP. y 1s{t till L�R �aEI'.' , ;� ` \C1 " " `7� ERM NC, INC. License #F-1223,'15720 Atlantic Coast Pipeline, LLC NOT TO SCALE ISSUED FOR REVIEW 4' MAXyn STAKE 1'MIN. STREAM FLOW 1 —SEDIMENT LOG FLOATATION ANCHOR PT. 11 11 11 = II WOODEN STAKES PLACED 10' WOODEN STAKES PLACED 10' —.-� STAKE OR ANCHOR, 11 111 1 Ili 11 11 11 O.C. AND THROUGH MIDDLE OF ZO.C. AND THROUGH MIDDLE -_--_-----_ EVERY 100' (TYPICAL) Z FILTER SOCK OF FILTER SOCK I BLOWN/PLACED COMPOST FILTER SOCK BLOWN/PLACED COMPOST FILTER SOCK SHORELINE ®FILL AREA FILTER MEDIA, AS FILTER MEDIA, AS (MINIMUM 12 INCH DIAMETER) FLAT, LEVEL AREA AASHTO 957 NEEDED AREA TO BE PROTECTED NEEDED LIMITS OF ) ' P. FREE OF DEBRIS STONE AREA TO BE PROTECTED CONSTR. WORK AREA WORK AREA ECONOMY FABRICS AVAILABLE ------------- -- J4" SHORELINE FRONT VIEW 18 OZ. 300 LB/IN. STANDARD lx� TURBIDITY STAKE OR EQUIVALENT X1,2 NOM. 2 � //�//%%/��/��/��/�\ � '\N M\� ANCHOR PT. THIS DISTANCE IS VARIABLE �— i \� � CURTAIN ALL SEAMS HEAT SEALED 1/4 IN. CHAIN (BLOW—UP OF SHACKLE CONNECTION) 0 TYPE D GALVANIZED #24 SAFETY HOOK TIDAL WATERS AND/OR HEAVY WIND & WAVE ACTION FLOOD �— EBB oanpncrn rnp, SEDIMENT LOG - I, T. SHEET FLOW 2. COMPACTED BACKFILL MATERIAL UNDISTURBED FLAT, LEVEL AREA FREE OF DES GROUND BRI m ELEVATION VIEW 2'x2'x48'(t318')WOOD G•TA.IC ^AM 1-!1111%]AN Ci1T SECTION WOODEN STAKES PLACED 10' O.C. AND THROUGH MIDDLE OF FILTER SOCK (TYP.) am AREA TO BE PROTECTED WATER FLOW COMPOST y FILTER SOCK an WATER FLOW SECTION WOODEN STAKES PLACED 10' O.C. AND THROUGH MIDDLE OF FILTER SOCK (TYP.) AREA TO BE PROTECTED COMPOST FILTER SOCK :, CAUSEWAY Y � WORK AREA® WORK AREA O �-- p O O O 0 O X15• ' PLAN PLAN ANCHOR & AASHTO #57 STONE NOTES: 100 FT. STANDARD LENGTH FOLDS EVERY 6 FEET ANCHOR BUOY 1. FILTER SOCK TO BE FILTREXX SEDIMENT CONTROL SILTSOXX OR APPROVED EQUAL. FILTER MEDIA INSIDE AND, AS PLAN VIEW NECESSARY UP—SLOPE OF FILTER SOCK, TO BE FILTREXX FILTERMEDIA OR APPROVED EQUAL. BARRIER MOVEMENT SHORELINE DUE TO TIDAL CHANGE ANCHOR PT. 2. SEDIMENT SHALL BE REMOVED WHEN ACCUMULATIONS REACH 1/2 THE ABOVE GROUND HEIGHT OF THE FILTER SOCK. DEPTH ACCORDING TO NEED ANCH RIN T. 3. MINIMUM OF 12 INCHES DIAMETER. NOTES: THIS DISTANCE IS VARIABLE ® FILL AREA 1. SEDIMENT FILTER LOGS SHALL BE INSPECTED WEEKLY AND AFTER EACH MAINTENANCE NOTES: RUNOFF EVENT. SEDIMENT DEPOSITS SHALL BE CLEANED FROM THE LOG 1. INSPECT COMPOST SOCK WEEKLY AND AFTER EACH SIGNIFICANT RAINFALL EVENT (1/2 INCH OR GREATER). REMOVE TURBIDITY CURTAIN DETAIL WHEN IT REACHES HALF THE HEIGHT OF THE LOG. DAMAGED FILTER LOGS SHALL BE REPLACED WITHIN 24 HOURS OF INSPECTION. A ACCUMULATED SEDIMENT AND ANY DEBRIS. THE COMPOST SOCK MUST BE REPLACED IF CLOGGED OR TORN, IF SUPPLY OF FILTER LOGS SHALL BE MAINTAINED ON SITE FOR THIS CLOGGING BECOMES EXCESSIVE, THE SOCK MAY NEED TO BE REPLACED WITH A LARGER DIAMETER OR A DIFFERENT STRESS BAND STRESS PLATE IN. CH IN NOT TO SCALE PURPOSE. MEASURE. THE COMPOST SOCK SHALL BE INSPECTED UNTIL LAND DISTURBANCE IS COMPLETED AND THE AREA BALLAST 2. COIR LOGS TO BE REMOVED FROM ALL WETLANDS AT THE COMPLETION ABOVE THE MEASURE HAS BEEN PERMANENTLY STABILIZED. OF CONSTRUCTION ACTIVITIES. COMPOST FILTER SOCK TURBIDITY CURTAIN DETAIL COIR LOG DETAIL NOT TO SCALE NOT TO SCALE NOT TO SCALE GENERAL NOTES AND COMMENTS: SYM. DATE BY REVISION INFORMATION PROJECT/TASK APP. y 1s{t till L�R �aEI'.' , ;� ` \C1 " " `7� ERM NC, INC. License #F-1223,'15720 Atlantic Coast Pipeline, LLC �0 ISSUED FOR REVIEW 03/10/17 NJB ��,�0 A 08/04/17 WTS ISSUED FOR REVIEW (• ERM Brixham Hill Ave, Suite 120 Charlotte, NC 28277 (704) 541-8345 925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000 DRAWN: NJB 08/04/17 P]�1 o .� t1 f ) TITLE: ATLANTIC COAST PIPELINE CHECKED: - - /7,,,';� EROSION AND SEDIMENT CONTROL PLAN DETAILS APP. FOR BID: 1 GROUP DWG. NO. ��ti APP. FOR CONST.: DISTRICT: - COUNTY: - STATE: INC REV. SCALE: AS NOTED DIRiFI�E: ACP\North Carolina\ — 7 OF 7 1