HomeMy WebLinkAbout20061312 Ver 1_Application_20060811DR. J.H. CARTER III & ASSOCIATES, INC.
Environmental Consultants
P O Box 891 • Southern Pines, N C 28388
(910) 695-1043 • Fax (910) 695-3317
9 August 2006
Mr William Wescott
U S Army Corps of Engineers
Washington Regulatory Field Office
P O Box 1000
Washington, NC 27889-1000
061312
Dear Mr Wescott
Enclosed is a permit application for the proposed temporary relocation of an overhead
electric transmission line south of Washington in Beaufort County The proposed relocation is
necessary in order to allow for construction of the US Highway 17 Bypass (R-2510B) The
temporary relocation will require clearing 1 64 acres of forested wetland (mechanized clearing
will not be used, root mats and stumps will be left intact and pre-construction contours will be
maintained) Approximately 1 acre of this clearing will be located within areas proposed for
clearing for the US Highway 17 Bypass right-of-way The project will also require the
temporary installation of 9 transmission poles within wetland areas Vibratory foundations
(maximum of 4 feet in diameter) will be installed for the poles Matting will be used in wetland
areas to support equipment during construction but a temporary access road may need to be
constructed if matting fails to work The temporary road and/or matting will be removed once
construction is complete Once highway construction is complete, all temporary structures will
be removed and 5 existing transmission poles within the existing cleared transmission line right-
of-way will be permanently replaced with larger poles to allow for highway clearance
Please review the attached permit application and let us know if you need additional
information or need to make a site visit in order to issue the permit Thank you for your time
Sincerely,
n
aU P?_
Tracy R sh
Senior Biologi tR@20wop
CC- Mr Brian Wrenn -NC Division of Water Quality AUG 1 1 2006
Mr Steve Sollod - NC Division of Coastal Management
D9NR - WATER alJAL17Y
Mr Keith Hardt, PE - City of Washington Nr ILANO$MO3XI." d?ATERV NCH
Endangered Species Surveys 9 Environmental Assessments 9 Land Management • Wetlands Mapping and Permitting
Office Use Only: Form Version March 05
USACE Action ID No. DWQ No. 2 0 0 6 1 3 1 2
(If any particular item is not applicable to this protect, please enter "Not Applicable" or "N/A" )
1. Processing
1. Check all of the approval(s) requested for this project-
0 Section 404 Permit ? Riparian or Watershed Buffer Rules
? Section 10 Permit ? Isolated Wetland Permit from DWQ
N 401 Water Quality Certification ? Express 401 Water Quality Certification
2. Nationwide, Regional or General Permit Number(s) Requested NWP 12
3 If this notification is solely a courtesy copy because written approval for the 401 Certification
is not required, check here ?
4 If payment into the North Carolina Ecosystem Enhancement Program (NCEEP) is proposed
for mitigation of impacts, attach the acceptance letter from NCEEP, complete section VIII,
and check here ?
5 If your project is located in any of North Carolina's twenty coastal counties (listed on page
4), and the project is within a North Carolina Division of Coast of
Environmental Concern (see the top of page 2 for further details), 9="
II. Applicant Information AUG 1 1 1006
1 Owner/Applicant Information ftl o Aryp Tl ATkS OK 10
Name City of Washington - Mr Keith A Hardt PE, Electric Utilities Director
Mailing Address- P O Box 1988
Washington, NC 27889-1988
Telephone Number: (252) 975-9300 Fax Number (252) 946-1965
E-mail Address
2 Agent/Consultant Information (A signed and dated copy of the Agent Authorization letter
must be attached if the Agent has signatory authority for the owner/applicant )
Name Tracy E. Rush
Company Affiliation Dr J H Carter III & Associates, Inc
Mailing Address 515F Midland Road
Southern Pines NC 28387
Telephone Number 910-695-1043 Fax Number 910-695-3317
E-mail Address trush@jhcartennc corn
Updated 11/1/2005
Page 5 of 13
III. Project Information
Attach a vicinity map clearly showing the location of the property with respect to local
landmarks such as towns, rivers, and roads Also provide a detailed site plan showing property
boundaries and development plans in relation to surrounding properties Both the vicinity map
and site plan must include a scale and north arrow. The specific footprints of all buildings,
impervious surfaces, or other facilities must be included If possible, the maps and plans should
include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property
boundaries outlined. Plan drawings, or other maps may be included at the applicant's discretion,
so long as the property is clearly defined For administrative and distribution purposes, the
USACE requires information to be submitted on sheets no larger than 11 by 17-inch format,
however, DWQ may accept paperwork of any size DWQ prefers full-size construction
drawings rather than a sequential sheet version of the full-size plans If full-size plans are
reduced to a small scale such that the final version is illegible, the applicant will be informed that
the project has been placed on hold until decipherable maps are provided
1 Name of project City of Washington 230 kV Transmission Line Temporary Relocation
2 TIP Project Number or State Project Number (NCDOT Only). R-2510B
3 Property Identification Number (Tax PIN) 12026056
4 Location
County Beaufort Nearest Town Washington
Subdivision name (include phase/lot number) N/A
Directions to site (include road numbers/names, landmarks, etc) Site is located west of US
Hi wa7pproximately 12 miles north of the intersection of NC Highway 33 and US
Highway 17 south of the City of Washington in Beaufort County
5 Site coordinates (For linear projects, such as a road or utility line, attach a sheet that
separately lists the coordinates for each crossing of a distinct waterbody )
Decimal Degrees (6 digits minimum) 35 5253692 ON 77 0851932 °W
6. Property size (acres): 3000 feet of transmission line w/ 40 foot right-of-way (2 75 acres)
(approximately 1300 feet 0 2 acres) of this will be located within existing right-of-way}
7 Name of nearest receiving body of water- Crawford Creek
8 River Basin Tar-Pamlico River Basin
(Note - this must be one of North Carolina's seventeen designated mayor river basins The
River Basin map is available at hU //h2o enr state nc us/admin/maps/.)
9 Describe the existing conditions on the site and general land use in the vicinity of the project
at the time of this application- The proposed project corridor consists of forested
swampland railroad corridor transmission line corridor and proposed highway corridor_
Updated 11/1/2005
Page 6 of 13
General land use includes forestland, agricultural, residential, small commercial and hi hwaY
corridor
10 Describe the overall protect in detail, including the type of equipment to be used
A transmission line must be temporanly relocated in order to construct the US Highway 17
Bypass south of Washington The proposed temporary transmission linen nght-of-wgy will
require clearing forested wetland areas - mechanized clearing will not be used, root mats and
stumps will be left intact and pre-construction contours will be maintained Vibratory
foundations will be used for the poles Matting will be used in wetland areas to support
equipment during construction A temporary road may need to be constructed for equipment
if matting does not work Once hi way construction is complete, 5 existing transmission
poles within the existing cleared ri t-of-way will be permanently replaced with larger poles
to allow for hi way clearance
11 Explain the purpose of the proposed work A transmission line must be temporarily
relocated in order to construct the US Highway 17 Bypass south of Washington Once
highway construction is complete the transmission line will be returned to its original
corridor
IV. Prior Project History
If jurisdictional determinations and/or permits have been requested and/or obtained for this
protect (including all prior phases of the same subdivision) in the past, please explain Include
the USACE Action ID Number, DWQ Project Number, application date, and date permits and
certifications were issued or withdrawn Provide photocopies of previously issued permits,
certifications or other useful information Describe previously approved wetland, stream and
buffer impacts, along with associated mitigation (where applicable) If this is a NCDOT project,
list and describe permits issued for prior segments of the same T I P project, along with
construction schedules None
V. Future Project Plans
Are any future permit requests anticipated for this project? If so, describe the anticipated work,
and provide justification for the exclusion of this work from the current application.
None
VI. Proposed Impacts to Waters of the United States/Waters of the State
It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to
wetlands, open water, and stream channels associated with the project Each impact must be
listed separately in the tables below (e g, culvert installation should be listed separately from
nprap dissipater pads) Be sure to indicate if an impact is temporary All proposed impacts,
permanent and temporary, must be listed, and must be labeled and clearly identifiable on an
accompanying site plan All wetlands and waters, and all streams (intermittent and perennial)
should be shown on a delineation map, whether or not impacts are proposed to these systems
Wetland and stream evaluation and delineation forms should be included as appropriate.
Updated 11/1/2005
Page 7 of 13
Photographs may be included at the applicant's discretion If this proposed impact is strictly for
wetland or stream mitigation, list and describe the impact in Section VIII below If additional
space is needed for listing or description, please attach a separate sheet
1 Provide a written description of the proposed impacts- The proposed temporary
transmission line will require non-mechanized clearing of 16 acres of forested wetland
Approximately 1 acre of this clearing will be located within areas proposed for clearing for
the proposed US Highway 17 Bypass right-of-way The project will also require the
temporary installation of 9 transmission poles within wetland areas and the permanent
replacement of 5 existing transmission poles Vibratory foundations (maximum of 4 feet in
diameter) will be installed for the poles A temporary access road (20 feet wide) may need to
be constructed if equipment matting does not work The temporary road and matting will be
removed once construction is complete
2 Individually list wetland impacts. Types of impacts include, but are not limited to
mechanized clearing, grading, fill, excavation, flooding, ditching/drainage, etc For dams,
separately list impacts due to both structure and flooding
Wetland Impact Type of Wetland Located within Distance to Area of
Site Number Type of Impact (e g , forested, marsh, 100-year
Floodplain Nearest
Stream Impact
(acres)
(indicate on map) herbaceous, bog, etc) (yes/no) linear feet
1 Temporary (9) Forested Wetland Yes >800 feet 0 003 ac
Vibratory Foundations
I Permanent (5) Mowed herbaceous Yes >800 feet 0 001 ac
Vibratory Foundations Wetland (existing ROW)
I Clearing Forested Wetland Yes >800 feet 16 ac
I Temporary Fill Forested Wetland Yes >800 feet 0 8 ac
For Access Road
Total Wetland Impact (acres) 2 4 ac
3 List the total acreage (estimated) of all existing wetlands on the property all wetland
4. Individually list all intermittent and perennial stream impacts Be sure to identify temporary
impacts Stream impacts include, but are not limited to placement of fill or culverts, dam
construction, flooding, relocation, stabilization activities (e g, cement walls, rip-rap, crib
walls, gabions, etc.), excavation, ditching/straightening, etc If stream relocation is proposed,
plans and profiles showing the linear footprint for both the original and relocated streams
must be included To calculate acreage, multi 1 len h X width, then divide b 43,560
Stream Impact
Number
indicate on ma
Stream Name
Type of Impact Perennial or
Intermittent9 Average
Stream Width
Before Impact Impact
Length
linear feet Area of
Impact
(acres)
N/A
Total Stream Impact (by length and acreage) 0
Updated 11/1/2005
Page 8 of 13
5 Individually list all open water impacts (including lakes, ponds, estuaries, sounds, Atlantic
Ocean and any other water of the U S ) Open water impacts include, but are not limited to
fill, excavation, dredging, floodin , drainage, bulkheads, etc
Open Water Impact Name Waterbody Type of Waterbody Area of
Site Number applicable) e)
(if ap Type of Impact (lake, pond, estuary, sound, bay, Impact
indicate on ma ocean, etc acres
N/A
Total Open Water Impact (acres) 0
6 List the cumulative impact to all Waters of the U S resulting from the protect
Stream Impact (acres) 0
Wetland Impact (acres) TEMPORARY 2 4 ac
Open Water Impact (acres) 0
Total Impact to Waters of the U S (acres) TEMPORARY 2 4 ac
Total Stream Impact (linear feet) 0
7 Isolated Waters
Do any isolated waters exist on the property9 ? Yes ® No
Describe all impacts to isolated waters, and include the type of water (wetland or stream) and
the size of the proposed impact (acres or linear feet) Please note that this section only
applies to waters that have specifically been determined to be isolated by the USACE
8 Pond Creation
If construction of a pond is proposed, associated wetland and stream impacts should be
included above in the wetland and stream impact sections Also, the proposed pond should
be described here and illustrated on any maps included with this application
Pond to be created in (check all that apply) ? uplands ? stream ? wetlands
Describe the method of construction (e g, dam/embankment, excavation, installation of
draw-down valve or spillway, etc) N/A
Proposed use or purpose of pond (e g, livestock watering, irrigation, aesthetic, trout pond,
local stormwater requirement, etc ) N/A
Current land use in the vicinity of the pond N/A
Size of watershed draining to pond N/A Expected pond surface area
VII. Impact Justification (Avoidance and Minimization)
Specifically describe measures taken to avoid the proposed impacts. It may be useful to provide
information related to site constraints such as topography, building ordinances, accessibility, and
financial viability of the project The applicant may attach drawings of alternative, lower-impact
site layouts, and explain why these design options were not feasible Also discuss how impacts
Updated 11/1/2005
Page 9 of 13
were minimized once the desired site plan was developed If applicable, discuss construction
techniques to be followed during construction to reduce impacts The transmission line must be
temporarily relocated in order to construct the US Highway 17 Bypass south of Washin on
Once highway construction is complete the transmission line will be returned to its original
corridor TMporary foundations will be removed and any temporary roads will be removed.
VIII. Mitigation
DWQ - In accordance with 15A NCAC 2H 0500, mitigation may be required by the NC
Division of Water Quality for projects involving greater than or equal to one acre of impacts to
freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial
streams
USACE - In accordance with the Final Notice of Issuance and Modification of Nationwide
Permits, published in the Federal Register on January 15, 2002, mitigation will be required when
necessary to ensure that adverse effects to the aquatic environment are minimal Factors
including size and type of proposed impact and function and relative value of the impacted
aquatic resource will be considered in determining acceptability of appropriate and practicable
mitigation as proposed Examples of mitigation that may be appropriate and practicable include,
but are not limited to reducing the size of the project, establishing and maintaining wetland
and/or upland vegetated buffers to protect open waters such as streams, and replacing losses of
aquatic resource functions and values by creating, restoring, enhancing, or preserving similar
functions and values, preferable in the same watershed
If mitigation is required for this project, a copy of the mitigation plan must be attached in order
for USACE or DWQ to consider the application complete for processing Any application
lacking a required mitigation plan or NCEEP concurrence shall be placed on hold as incomplete
An applicant may also choose to review the current guidelines for stream restoration in DWQ's
Draft Technical Guide for Stream Work in North Carolina, available at
hqp //h2o enr.state nc us/ncwetlands/stnngide html
Provide a brief description of the proposed mitigation plan The description should provide
as much information as possible, including, but not limited to site location (attach directions
and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet)
of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view,
preservation mechanism (e.g, deed restrictions, conservation easement, etc ), and a
description of the current site conditions and proposed method of construction Please attach
a separate sheet if more space is needed
Once highway construction is complete and the transmission line is located back to its
original corridor, temporarily cleared areas not within the highway right-of-way will be
allowed to naturally re-vegetate If these areas fail to re-vegetate cypress seedlings will be
planted at a density equal to 435 trees/acre
2 Mitigation may also be made by payment into the North Carolina Ecosystem Enhancement
Program (NCEEP) Please note it is the applicant's responsibility to contact the NCEEP at
Updated 11/1/2005
Page 10 of 13
(919) 715-0476 to determine availability, and written approval from the NCEEP indicating
that they are will to accept payment for the mitigation must be attached to this form For
additional information regarding the application process for the NCEEP, check the NCEEP
website at http //h2o enr state nc us/wrp/index htm If use of the NCEEP is proposed, please
check the appropriate box on page five and provide the following information
Amount of stream mitigation requested (linear feet) N/A
Amount of buffer mitigation requested (square feet) N/A
Amount of Riparian wetland mitigation requested (acres) N/A
Amount of Non-riparian wetland mitigation requested (acres) N/A
Amount of Coastal wetland mitigation requested (acres) N/A
IX. Environmental Documentation (required by DWQ)
Does the project involve an expenditure of public (federal/state/local) funds or the use of
public (federal/state) land9 Yes E] No
2 If yes, does the project require preparation of an environmental document pursuant to the
requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)?
Note If you are not sure whether a NEPA/SEPA document is required, call the SEPA
coordinator at (919) 733-5083 to review current thresholds for environmental documentation
Yes ? No ?
3 If yes, has the document review been finalized by the State Clearinghouse? If so, please
attach a copy of the NEPA or SEPA final approval letter Yes ? No ?
X. Proposed Impacts on Riparian and Watershed Buffers (required by DWQ)
It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to
required state and local buffers associated with the project The applicant must also provide
justification for these impacts in Section VII above All proposed impacts must be listed herein,
and must be clearly identifiable on the accompanying site plan All buffers must be shown on a
map, whether or not impacts are proposed to the buffers Correspondence from the DWQ
Regional Office may be included as appropriate. Photographs may also be included at the
applicant's discretion
Will the project impact protected riparian buffers identified within 15A NCAC 2B 0233
(Meuse), 15A NCAC 2B 0259 (Tar-Pamlico), 15A NCAC 02B 0243 (Catawba) 15A NCAC
2B 0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please
identify. V Yes ? No
2 If "yes", identify the square feet and acreage of impact to each zone of the riparian buffers
If buffer mitigation is required calculate the required amount of mitigation by applying the
buf
Updated 11/1/2005
.er multipliers
Zone* Impact Multiplier Required
(square feet) Mitigation
Page 11 of 13
3 (2 for Catawba)
15
Total
* Zone I extends out 30 feet perpendicular from the top of the near bank of channel, Zone 2 extends an
additional 20 feet from the edge of Zone 1
If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e.,
Donation of Property, Riparian Buffer Restoration / Enhancement, or Payment into the
Riparian Buffer Restoration Fund) Please attach all appropriate information as identified
within 15A NCAC 2B 0242 or 0244, or 0260 N/A
XI. Stormwater (required by DWQ)
Describe impervious acreage (existing and proposed) versus total acreage on the site Discuss
stormwater controls proposed in order to protect surface waters and wetlands downstream from
the property If percent impervious surface exceeds 20%, please provide calculations
demonstrating total proposed impervious level There is no existing impervious acreage
Proposed impervious acreage is 0 003 acres from the temporary pole foundations - which will be
removed once hi way construction is complete
XII. Sewage Disposal (required by DWQ)
Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of
wastewater generated from the proposed project, or available capacity of the subject facility
No wastewater will be generated by the proposed project
XIII. Violations (required by DWQ)
Is this site in violation of DWQ Wetland Rules (15A NCAC 2H 0500) or any Buffer Rules?
Yes ? No
Is this an after-the-fact permit application Yes E] No
XIV. Cumulative Impacts (required by DWQ)
Will this project (based on past and reasonably anticipated future impacts) result in additional
development, which could impact nearby downstream water quality9 Yes ? No
If yes, please submit a qualitative or quantitative cumulative impact analysis in accordance with
the most recent North Carolina Division of Water Quality policy posted on our website at
http•//h2o enr state nc us/ncwetlands. If no, please provide a short narrative description
Impacts will be temporary so there will be no cumulative impacts
Updated 11/1/2005
Page 12 of 13
XV. Other Circumstances (Optional):
It is the applicant's responsibility to submit the application sufficiently in advance of desired
construction dates to allow processing time for these permits However, an applicant may
choose to list constraints associated with construction or sequencing that may impose limits on
work schedules (e g, draw-down schedules for lakes, dates associated with Endangered and
Threatened Species, accessibility problems, or other issues outside of the applicant's control)
n
Applicot/Agent's Signature bath
(Agent's signature is valid only if an authorization letter from the applicant is provided )
Updated 11/1/2005
Page 13 of 13
08/03/2006 1:50
3 August 2006
252-974-6461
CITY HALL
City of Washington
PAGE 02/02
R O. Box 1983, Washington, ETC 27889-1988
To Whom It May Concern:
Dr. J.H. Carter III & Associates, Inc. is authorized to prepare and submit the necessary
permits for the temporary relocal ion of a 230 kV transmission line for the City of
Washington, Beaufort County, North Carolina. Additionally, this letter grants pernussion
to fedend and state regulatory authorities to visit the project site in order to evaluate
projcct impacts.
Sincerely,
1?
- / -
rMq'
Mr. Keith Hardt PE
Electric Utilities Director
City of Washington
P.O. Box 1988
Washington, NC 27889-1988
(252) 975-9300
!mss!
102 E. Second Sr. • Telephone 2 52.975-9300 TDD 1-800.735-2962 • Fax 252.94&1965
10•
"Cor \ t ^, r •' ,'r rt
- ? C^- • ` t .bt•_nt --- ?_ `? (, .{a: t•erri Zll/ -Y? ??.,'r `.?.. ••.? • 1 t Y 1t? !' ?' y ? .? ?yy`. .
? ? _. /.., -• i i o J•rif71H?CJ'1 ? ?`? G`Yanx? .-. ?;': ,`?• ? .i .,.,?r,; '.
- (`- ??•.?_ - '--? ?. t .- ? ? fl ! ?'• ll l?. '... .. /1 '- .. , j•. L?f?C'w:r'Jq•??, ? ? A ?•? ., - `
Glei :r.
Alls-4w 'C' Z,
42
• ii
ON
? ?t um
z
Y a.*
_.... - _ ?•. ` _ w _ _ _ ?. - art FA- ,t. - - A r • \?
' .r is ._ _ _«.. 1165,.. e?•. A•i 1 ?,,a. # ;.•. - ..? - - -. i The Castle
-? a - r -
o Rae., Tc„rr:
«
•
_ i
F Existing Transmission LuCorridor
.cam - - ..?. . -. - .".... ?- _ -' ? - 'sip -??-
f. ? •
Porter E Temoroary f2eeoe ri of '2* kV Transmission Line
Junction r , :-
- roposad US Highway 17,Bypass? .? , • . .
s
fc,
Station ^ •) \ } s- t °
^ Ti. pty\'•• t 9 7 25 \\ t C 4 _.. ?'b UH/f ?" r -
focou inity C.: " O lord " r
Tra ler
Pa.rB ?T t ant k Raa
?• .+'i•/ 38 -?` ? ;:nding (Ci Cr "? if
/17 .41'
IT S
T `c5-? ? ? i;a ? > 33
10°W
Name: WASHINGTON Location: 035.5285489° N 077.0801438° W
Date: 8/3/2006 Caption: Proposed temporary location of 230 kV tranmission line for
Scale: 1 inch equals 2000 feet construction of US Highway 17 Bypass, Beaufort County, NC.
Copyright (C) 1998,INaptech,Inc.
y
?'•Yr.: 1 AaA
r3 J
K}, y '44
ppU
- ?_ _TAR RiVRR
-a B Do
To La y
Sb
,y At At Me
StA /pro
AbA d 4
AaA At
StA 761,
Ur AaA
AaA
i Me
Pm
StA StA
Do
?Do
AbA
Ur
Ur Ur
AbA
b
paw
P?
Se C-1
4
Do Q7 -
Cu
Do The castle
O
. TaB OFIF00
j Do N
Sb Cu
' Ta
y
® TaB Q
( w
Do l
w w \
?t0 Me Fu ECT Sb Ds Cu
GoA
Wt
Sb
TaB
U't,400 Ds Sb Aa Rodman
Le
Le CO9
CrA SO Cn8 At
CnS
LY :
Do GOA
Tab StA
T e
/ ;f
, de CnB
s
Td6
B
CrB k
/ Sb
AaA At o
LY r6
. "
StA Me
CnB DS TaB
CrA
La
Le Me
j s
w
Cn6 BOB
( Cu
Cu , Tab
TaB
? I
CrA / CsC2
q C
w Me w
e Le CrA
CrB \4
`
Marsden CrA CrB CrB o? c? Do
`Station
Chotowinity
y
^° Cu
y
?' Cr
Ra
a
CsC2
Cu e
CreE f e1r
r•- Le
CrB
GOA CIA
Cr6
WtD
\ -- CrB
b
Ta
CrB BoB Pm GOA Cu
e
,- CrA Creek, Cu
CrA
SC BOB a
V Sidney Do
? \
Le CrA y GOA
33
Cu GOA WtD
C r8 ita ?'
?. ?
-
} ?
. k i ?.?? ?
-mod .
F
*
.: f
• .
o ?
`
? ? Y
1
jj , y ¢
im ;1 n,
l
.SSj
$.Yd?
r
p.
r
' , a
?' ?
•
'y
? `?' ? try +
, Aa. ? !?
" ?fii ? -
..
?
` ,
? ,. a, a
r
41
• r
?
t
1
t
t? .
R
o
r r 7
i 'r
' q4'?
l ? ?
a ! " T •( C
F ?f
Y1 hr :.
?
? -R
,
"?!?
114.
??
r'
Y
i•
?I
Y?
?
?
(
.._,
y
_
- !. T try Y .?' ?y-?Y i-. ?; 'e!, L
'9
.?+'? F? . g
??
L' 1.1 JpY? k ? ?
?,
L •
a
• T'
?
_
?_;_:?, ? ? _
?? tom.,-
Ye.
z
`
?t ?
J }
T y
? " ? • ?
? ',? ?
? !`
-
} s.,
_ - _ i?`
_?
Wr ' ,.. •?
.43
... r it ,
- ?'
?'
y /,`fir-;
p
. T
• f j?,
?4
?
? -ki ?-11 V 7w f ?r
U
z
{O
ir
W
C?
/.!U
w
cz
C?
V---l}}
O
C
O
.J
O
U
3«
O
cn
cS
M
N
O
c
O
ct
U
O
O
R.
a?
O
O
a
ff ?
b
k
ko
\\ ? I q y, 21
I
I
k Box
I? -
Z
/ OI a
i
? z.
I. I
i I
1
eft ? I I I
? ? I I.t I
I ?? I
L
I jg
I
'I
Its / ? ;
10
» 30
a /
ziz 1z iz % k
/ ?Y16- i pw 11+00.N i ft
- CONSTRUCTION _LIMIT
------- --- -------------
12'1 tY12 .. _. --- - --- /-%' ?
0
C? 0 let
?t2
{rye/ ?
- ? Y ?/ .cs o-'nw
? I? A ??• ••.gp'0"AMI / li
H 0-.Am
RIO
/ _V-
l< /
Atif ?
i
y;
i ?
l< K
2'12 12'12
-5-
K 5.
K K
eI? o I
I,
R R
R
Z
as
?41t+? 21
l< l<
1-( H
1-( 14
N
O ?
G ?
A
9z
D? pD
RV
i?
z >
A
A
k
k
o?
B; V
a?
? g