HomeMy WebLinkAbout20140277_SAW-2013-01544 Rogers Road Sidewalk NWP 14 Verification_20170912U.S. ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Action Id. SAW-2013-01544 County: Orange U.S.G.S. Quad: NGChapel Hill
GENERAL PERMIT (REGIONAL AND NATIONWIDE) VERIFICATION
Applicant: Town of Carrboro
Mr. Nate Broman-Fulks
Address: 301 West Main Street
Carrboro, North Carolina 27510
Authorized Agent:
Address:
Size (acres)
Nearest Waterway
USGS HUC
Axiom Environmental, Inc.
Mr. Scott Davis
218 Snow Avenue
RaleiEh, North Carolina 27603
6_5
Bolin Creek
03030002
Nearest Town Carrboro
River Basin Haw: CaAe Fear River
Coordinates Latitude:35.957725
Longitude: -79.084886
Description of the project location: The proiect area is identified as an approximate 1.1 mile corridor, on the west side of Rogers
Road, between Homestead Road and Meadow Run Court, in Carrboro, Orange Countv, North Carolina. Work in waters of
the United States would occur in streams and wetlands within the Bolin Creek watershed, an indirect tributary of the Haw
River. The U.S. Army Corps of Engineers (Corps) has analyzed the Aroposed linear transportation proiect to determine if the
proposed discharges of fill material into waters of the United States are single and complete. The Corps has made the
determination that the overall linear sidewalk proiect involves two (2) single and complete Aroiect areas.
Description of projects area and activity: The applicant, Town of Carrboro, has requested a Department of the Armv
authorization to discharge fill material into waters of the United States in coniunction with the construction of the Rogers
Road Sidewalk Project.
On April 15, 2014 the Rogers Road Sidewalk Proiect was authorized under a Nationwide Permit 14, for the construction of a
5-foot wide, 1.1 mile long, concrete pedestrian sidewalk along Rogers Road, between Homestead Road and Meadow Run
Court. The permit verification authorized the discharge fill material into 171inear feet of stream channel and 0.01 acres of
wetland. The Ro�ers Road Sidewalk Proiect was not constructed and the permit verification expired on March 18, 2017.
Proiect activitv associated with the revised Rogers Road Sidewalk Proiect will involve the extension of two (2) existin� 48-inch
CMPs in order to facilitate the installation of the 5-foot wide, 1.1 mile long, concrete pedestrian sidewalk. Implementation of
the proposed proiect will result in the temporarv discharge of fill material into 241inear feet of stream channel and the
permanent discharge of till material into 181inear feet of stream channel and 0.002 acres of wetland at two (2) single and
complete proiect areas, as outlined in Table 1. Compensatory mitigation is NOT required in conjunction with the
aforementioned activities.
Applicable Law: � Section 404 (Clean Water Act, 33 USC 1344)
❑ Section 10 (Rivers and Harbors Act, 33 USC 403)
Authorization: Regional General Permit Number or Nationwide Permit Number: NWP 14 — Linear Transportation Proiects
SEE ATTACHED RGP or NWP GENERAL, REGIONAL AND SPECIAL CONDITIONS
Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the attached
conditions and your submitted application and attached information dated August 4, 2017. Any violation of the attached
conditions or deviation from your submitted plans may subject the permittee to a stop work order, a restoration order, a Class
I administrative penalty, and/or appropriate legal action.
This verification will remain valid until the expiration date identified below unless the nationwide authorization is modified,
suspended or revoked. If, prior to the expiration date identified below, the nationwide permit authorization is reissued and/or
modified, this verification will remain valid until the expiration date identified below, provided it complies with all requirements of
the modified nationwide permit. If the nationwide permit authorization expires or is suspended, revoked, or is modified, such that the
activity would no longer comply with the terms and conditions of the nationwide permit, activities which have commenced (i.e., are
under construction) or are under contract to commence in reliance upon the nationwide permit, will remain authorized provided the
activity is completed within twelve months of the date of the nationwide permit's expiration, modification or revocation, unless
discretionary authority has been exercised on a case-by-case basis to modify, suspend or revoke the authorization.
Activities subject to Section 404 (as indicated above) may also require an individual Section 401 Water Quality Certification. You
should contact the NC Division of Water Quality (telephone 919-807-6300) to determine Section 401 requirements.
For activities occurring within the twenty coastal counties subject to regulation under the Coastal Area Management Act (CAMA),
prior to beginning work you must contact the N.C. Division of Coastal Management in Morehead City, NC, at (252) 808-2808.
This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federal,
State or local approvals/permits.
If there are any questions regarding this verification, any of the conditions of the Permit, or the Corps of Engineers regulatory
program, please contact Samantha Dailev at 919-554-4884 x22 or Samantha.J.DailevC�a,usace.armv.mil.
DAILEY.SAMANT DAILEYSAMAN HA.J.1387567948
DN: c=US, o=U.S. Government, ou=DoD, ou=PKl,
HA J 13 8 7 5 6 7 948 Date: 2017.09.12I 12 09AMA04'00' ,� 387567948
Corps Regulatory Official: ' '
Date: September 12, 2017
Expiration Date of Verification: March 18, 2022
Table 1. Authorized discharge of fill material into waters of the United States in association with the
Rogers Road Sidewalk Project (SAW-2013-01544).
Flow Fill Fill Area of Duration
Aquatic Regime or Length of Regulated Discharge of Fill
Wetland of Fill
Resource ID Cowardin Stream (ac) Material Material Activity
Class (lf�
Crossin� 1 Installation of one (1) 48-inch CMP and
S1 & W1 PER/PFO 9 0.001 Permanent associated grading for roadway slope
Crossin� 1 Dewatering to facilitate the installation of
S2 PER 13 N/A Temporary one (1) 48-inch CMP
Crossin� 2 Installation of two (2) 54-inch CSPs and
S3 & W2 PER/PFO 9 0.001 Permanent associated grading for roadway slope
Crossin� 2 Dewatering to facilitate the installation of
S4 PER 11 N/A Temporary two (2) 54-inch CSPs
Action ID Number: SAW-2013-01544
Permittee: Town of Carrboro
Mr. Nate Broman-Fulks
Project Name: Rogers Road Sidewalk Proiect
Date Verification Issued: Seqtember 12, 2017
Project Manager: Samantha Dailev
County: Orange
Upon completion of the activity authorized by this permit and any mitigation required by the permit,
sign this certification and return it to the following address:
US ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Raleigh Regulatory Field Office
Attn: Samantha Dailey
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27857
Please note that your permitted activity is subject to a compliance inspection by a U. S. Army Corps of
Engineers representative. Failure to comply with any terms or conditions of this authorization may
result in the Corps suspending, modifying or revoking the authorization and/or issuing a Class I
administrative penalty, or initiating other appropriate legal action.
I hereby certify that the work authorized by the above referenced permit has been completed in
accordance with the terms and condition of the said permit, and required mitigation was completed in
accordance with the permit conditions.
Signature of Permittee Date